CN105239586A - 一种支护基坑的支撑结构及其支护基坑的方法 - Google Patents

一种支护基坑的支撑结构及其支护基坑的方法 Download PDF

Info

Publication number
CN105239586A
CN105239586A CN201510746005.3A CN201510746005A CN105239586A CN 105239586 A CN105239586 A CN 105239586A CN 201510746005 A CN201510746005 A CN 201510746005A CN 105239586 A CN105239586 A CN 105239586A
Authority
CN
China
Prior art keywords
steel pipe
foundation pit
waist rail
excavation
built
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510746005.3A
Other languages
English (en)
Other versions
CN105239586B (zh
Inventor
雷春燕
沈家文
王剑非
王晓燕
周麟
杨成
王建成
张恩超
魏聪明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
YUNNAN WATER CONSERVANCY & HYPOWER ENGINEERING Co.,Ltd.
Original Assignee
YUNNAN CONSTRUCTION ENGINEERING GROUP Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by YUNNAN CONSTRUCTION ENGINEERING GROUP Co Ltd filed Critical YUNNAN CONSTRUCTION ENGINEERING GROUP Co Ltd
Priority to CN201510746005.3A priority Critical patent/CN105239586B/zh
Publication of CN105239586A publication Critical patent/CN105239586A/zh
Application granted granted Critical
Publication of CN105239586B publication Critical patent/CN105239586B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Foundations (AREA)

Abstract

一种支护基坑的支撑结构及其支护基坑的方法,支撑结构包括灌注桩(2)、分别浇筑于灌注桩顶部和中部的冠梁(3)和腰梁(4)、预埋于腰梁上的钢板(5)、预埋于基坑底混凝土垫层(9)中的预埋件(8)、两端分别焊接于钢板和预埋件上的斜置的钢管(6)、开设于钢管上部的注浆孔(10)以及注入钢管内的浆液(7)。本发明利用灌注桩、冠梁、腰梁和钢管形成受力转换体系,并充分利用浆液或混凝土或碎石等的抗压性和自重,使得受力体系稳定,安全可靠,可确保施工人员的安全。本发明施工难度小,施工效率高,材料成本低。

Description

一种支护基坑的支撑结构及其支护基坑的方法
技术领域
本发明涉及建筑施工中的基坑支护技术领域。
背景技术
随着现在城市人口的增加,越来越多的人开始注重开发地下空间,但是地下工程地质条件复杂,尤其开挖后形成新的开挖断面,破坏了岩体原有结构的稳定性,在施工中容易发生滑坡、坍塌等安全事故,为了防止发生上述安全事故,需要对基坑进行支护,对于设计标高在15米以内的基坑,目前大多数支护方式都是用桩锚进行支护,在灌注桩的腰梁上每隔一定距离必须用锚索或锚杆进行支护,使用的锚索(锚杆)量大,成本高,施工速度慢,效率低,人工费高。
发明内容
本发明的目的是为了解决现有技术存在的不足,提供一种材料成本低、施工难度小、支护结构稳定、安全可靠的支护基坑的支撑结构,本发明还提供采用这种支撑结构支护基坑的方法。
本发明的目的通过如下技术方案实现:
一种支护基坑的支撑结构,包括灌注桩、分别浇筑于灌注桩顶部和中部的冠梁和腰梁、预埋于腰梁上的钢板、预埋于基坑底混凝土垫层中的预埋件、两端分别焊接于钢板和预埋件上的斜置的钢管、开设于钢管上部的注浆孔以及注入钢管内的浆液。
本发明所述注浆孔的直径不得大于钢管直径的1/3。钢管与基坑底面之间的夹角为45°-60°。
采用本发明所述支撑结构支护基坑的方法如下:
a)采用桩机在地面打孔后,浇注灌注桩;
b)开挖基坑,当基坑开挖至冠梁设计深度位置时,在灌注桩顶部浇筑冠梁,
c)冠梁施工完毕后,继续向下开挖基坑,当施工至腰梁设计深度位置时,浇筑腰梁,同时在腰梁上预埋钢板;
d)腰梁施工完成后,采用分仓开挖或跳仓开挖的方式继续开挖,开挖至设计标高后,在基坑底部设计位置浇筑混凝土垫层,并埋设预埋件;
e)将钢管斜置于钢板和预埋件之间,并将钢管的两端分别与钢板和预埋件焊接;在钢管上预先开设注浆孔或者两端焊接好后再开设注浆孔;
f)从注浆孔注入浆液,至浆液凝固,形成支护基坑的受力系统。
本发明利用灌注桩、冠梁、腰梁和钢管形成受力转换体系,并充分利用浆液的抗压性和自重,使得受力体系稳定,安全可靠,可确保施工人员的安全。本发明施工难度小,施工效率高,材料成本低。
附图说明
图1是采用本发明支撑结构支护基坑的示意图。
具体实施方式
如图1所示,本发明所述支护基坑的支撑结构,包括灌注桩2、分别浇筑于灌注桩顶部和中部的冠梁3和腰梁4、预埋于腰梁上的钢板5、预埋于基坑底混凝土垫层9中的预埋件9、两端分别焊接于钢板和预埋件上的斜置的钢管6、开设于钢管上部的注浆孔10以及注入钢管内的浆液7。所述注浆孔10的直径不得大于钢管6直径的1/3,既便于灌注浆液,又使钢管保持足够的强度。钢管6与基坑底面之间的夹角α为45°-60°。
采用本发明所述支撑结构支护基坑的方法如下:
a)采用桩机在地面1打孔后,浇注灌注桩2,灌注桩主要起到围护基坑和止水作用。灌注桩可采用混凝土灌注,也可采用其他材料如水泥、水泥粉煤灰碎石等材料灌注;
b)开挖基坑,当基坑开挖至设计深度即冠梁高度位置时,在灌注桩顶部采用混凝土浇筑冠梁3;冠梁的高度、宽度、保护层厚度根据现场环境和设计确定;
c)冠梁施工完毕后,继续向下开挖基坑,当施工至腰梁设计深度位置时,采用混凝土浇筑腰梁4,同时在腰梁上预埋钢板5,钢板的长度和厚度根据施工现场确定;
d)腰梁施工完成后,采用分仓开挖的方法继续向下开挖基坑,开挖至设计标高后,在基坑底部设计位置(距离灌注桩一段距离)浇筑混凝土垫层9,并埋设预埋件8,混凝土垫层9的浇筑厚度不得小于20cm;
e)将钢管6斜置于钢板和预埋件之间,并将钢管的两端分别与钢板和预埋件焊接;在钢管上预先开设注浆孔10或者两端焊接好后再开设注浆孔;注浆孔可开设在钢管任何一端距离端口2-3cm处;
f)从注浆孔注入浆液7,至浆液凝固,形成支护基坑的受力系统。
本发明尤其适用于设计标高在15米以内的基坑。

Claims (4)

1.一种支护基坑的支撑结构,其特征在于,包括灌注桩(2)、分别浇筑于灌注桩顶部和中部的冠梁(3)和腰梁(4)、预埋于腰梁上的钢板(5)、预埋于基坑底混凝土垫层(9)中的预埋件(8)、两端分别焊接于钢板和预埋件上的斜置的钢管(6)、开设于钢管上部的注浆孔(10)以及注入钢管内的浆液(7)。
2.根据权利要求1所述的一种支护基坑的支撑结构,其特征在于,所述注浆孔(10)的直径不得大于钢管(6)直径的1/3。
3.根据权利要求1所述的一种支护基坑的支撑结构,其特征在于,钢管(6)与基坑底面之间的夹角(α)为45°-60°。
4.采用如权利要求1或2或3所述的支撑结构支护基坑的方法,其特征在于,方法如下:
a)采用桩机在地面(1)打孔后,浇注灌注桩(2);
b)开挖基坑,当基坑开挖至冠梁设计位置深度时,在灌注桩顶部浇筑冠梁(3),
c)冠梁施工完毕后,继续向下开挖基坑,当施工至腰梁设计位置深度时,浇筑腰梁(4),同时在腰梁上预埋钢板(5);
d)腰梁施工完成后,继续向下开挖基坑,采用分仓开挖或跳仓开挖的方式开挖至设计标高后,在基坑底部设计位置浇筑混凝土垫层(9),并埋设预埋件(8);
e)将钢管(6)斜置于钢板和预埋件之间,并将钢管的两端分别与钢板和预埋件焊接;在钢管上预先开设注浆孔(10)或者两端焊接好后再开设注浆孔;
f)从注浆孔注入浆液(可为浆液或混凝土或者碎石等)(7),至浆液凝固,形成支护基坑的受力系统。
CN201510746005.3A 2015-11-05 2015-11-05 一种采用支撑结构支护基坑的方法 Active CN105239586B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510746005.3A CN105239586B (zh) 2015-11-05 2015-11-05 一种采用支撑结构支护基坑的方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510746005.3A CN105239586B (zh) 2015-11-05 2015-11-05 一种采用支撑结构支护基坑的方法

Publications (2)

Publication Number Publication Date
CN105239586A true CN105239586A (zh) 2016-01-13
CN105239586B CN105239586B (zh) 2017-04-12

Family

ID=55037385

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510746005.3A Active CN105239586B (zh) 2015-11-05 2015-11-05 一种采用支撑结构支护基坑的方法

Country Status (1)

Country Link
CN (1) CN105239586B (zh)

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107313433A (zh) * 2017-08-15 2017-11-03 江西基业科技有限公司 一种深基坑地下空间结构及其施工方法
CN107313434A (zh) * 2017-08-15 2017-11-03 江西基业科技有限公司 一种深基坑地下油库及其施工方法
CN107326931A (zh) * 2017-08-15 2017-11-07 江西基业科技有限公司 一种深基坑地下粮库及其施工方法
CN107354948A (zh) * 2017-08-15 2017-11-17 江西基业科技有限公司 一种深基坑地下库房及其施工方法
CN107476312A (zh) * 2017-08-15 2017-12-15 江西基业科技有限公司 一种用于基坑支护的挡墙及其施工方法
CN107476311A (zh) * 2017-08-15 2017-12-15 江西基业科技有限公司 一种深基坑地下车库及其施工方法
CN107542095A (zh) * 2017-08-15 2018-01-05 江西基业科技有限公司 一种深基坑水库及其施工方法
CN109555129A (zh) * 2018-12-24 2019-04-02 上海建工二建集团有限公司 一种用于基坑抢险快速应急斜撑及施工方法
CN111501776A (zh) * 2020-04-16 2020-08-07 温州设计集团有限公司 一种应用于基坑斜抛撑支护的装置及其施工工法
CN111705809A (zh) * 2020-06-18 2020-09-25 深圳市蛇口招商港湾工程有限公司 一种深基坑施工结构及深基坑施工方法
CN112323729A (zh) * 2020-10-28 2021-02-05 安徽省交通建设股份有限公司 桩基承台临河深基坑支护体系及施工方法
CN112813984A (zh) * 2020-12-31 2021-05-18 攀钢集团工程技术有限公司 复杂地质条件下深基坑施工方法

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1375754A2 (en) * 2002-06-22 2004-01-02 Korea Land Corporation A packing apparatus and method for soil nailing
KR20060010319A (ko) * 2004-07-28 2006-02-02 하람건설(주) 콘크리트 흙막이벽 축조 공법
CN103114595A (zh) * 2013-01-06 2013-05-22 厦门源昌城建集团有限公司 支护桩预留核心土双支墩斜内撑基坑支护方法及装置
CN103669365A (zh) * 2012-08-29 2014-03-26 张绍球 一种外斜拉内斜撑人字型基坑支护桩及其施工方法
CN203977434U (zh) * 2014-07-29 2014-12-03 上海市建工设计研究院有限公司 深厚淤泥质软土地区的基坑围护结构
CN205088687U (zh) * 2015-11-05 2016-03-16 云南建工集团有限公司 一种支护基坑的支撑结构

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1375754A2 (en) * 2002-06-22 2004-01-02 Korea Land Corporation A packing apparatus and method for soil nailing
KR20060010319A (ko) * 2004-07-28 2006-02-02 하람건설(주) 콘크리트 흙막이벽 축조 공법
CN103669365A (zh) * 2012-08-29 2014-03-26 张绍球 一种外斜拉内斜撑人字型基坑支护桩及其施工方法
CN103114595A (zh) * 2013-01-06 2013-05-22 厦门源昌城建集团有限公司 支护桩预留核心土双支墩斜内撑基坑支护方法及装置
CN203977434U (zh) * 2014-07-29 2014-12-03 上海市建工设计研究院有限公司 深厚淤泥质软土地区的基坑围护结构
CN205088687U (zh) * 2015-11-05 2016-03-16 云南建工集团有限公司 一种支护基坑的支撑结构

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
邵一帆: "国道107宝安段兴围、黄田掉头匝道桥工程施工新技术", 《交通标准化》 *

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107313433A (zh) * 2017-08-15 2017-11-03 江西基业科技有限公司 一种深基坑地下空间结构及其施工方法
CN107313434A (zh) * 2017-08-15 2017-11-03 江西基业科技有限公司 一种深基坑地下油库及其施工方法
CN107326931A (zh) * 2017-08-15 2017-11-07 江西基业科技有限公司 一种深基坑地下粮库及其施工方法
CN107354948A (zh) * 2017-08-15 2017-11-17 江西基业科技有限公司 一种深基坑地下库房及其施工方法
CN107476312A (zh) * 2017-08-15 2017-12-15 江西基业科技有限公司 一种用于基坑支护的挡墙及其施工方法
CN107476311A (zh) * 2017-08-15 2017-12-15 江西基业科技有限公司 一种深基坑地下车库及其施工方法
CN107542095A (zh) * 2017-08-15 2018-01-05 江西基业科技有限公司 一种深基坑水库及其施工方法
CN109555129A (zh) * 2018-12-24 2019-04-02 上海建工二建集团有限公司 一种用于基坑抢险快速应急斜撑及施工方法
CN111501776A (zh) * 2020-04-16 2020-08-07 温州设计集团有限公司 一种应用于基坑斜抛撑支护的装置及其施工工法
CN111705809A (zh) * 2020-06-18 2020-09-25 深圳市蛇口招商港湾工程有限公司 一种深基坑施工结构及深基坑施工方法
CN112323729A (zh) * 2020-10-28 2021-02-05 安徽省交通建设股份有限公司 桩基承台临河深基坑支护体系及施工方法
CN112813984A (zh) * 2020-12-31 2021-05-18 攀钢集团工程技术有限公司 复杂地质条件下深基坑施工方法
CN112813984B (zh) * 2020-12-31 2022-07-29 攀钢集团工程技术有限公司 复杂地质条件下深基坑施工方法

Also Published As

Publication number Publication date
CN105239586B (zh) 2017-04-12

Similar Documents

Publication Publication Date Title
CN105239586B (zh) 一种采用支撑结构支护基坑的方法
CN103485363B (zh) 立体连续框架式钢筋混凝土结构挡土墙
US8898996B2 (en) Method for forming a retaining wall, and corresponding retaining wall
CN104532868B (zh) 高陡变形斜坡区桥梁锚拉式高承台群桩基础修建方法
Chen et al. Recent advances in high slope reinforcement in China: Case studies
CN101476466B (zh) 巨厚层滑坡预应力锚索抗滑隧道施工方法及防治新结构
CN103938634B (zh) 一种深基坑支护结构及施工方法
CN202323970U (zh) 边坡联合加固系统
CN207878473U (zh) 土岩结合地层深基坑吊脚桩支护结构
CN105155602A (zh) 一种多支点地基加固综合纠倾方法
CN101838957B (zh) 整体式t形外悬臂道路及其施工方法
CN103572680B (zh) 煤矿采空区的公路路基填筑施工方法
CN104863613B (zh) 岩质地层暗挖地下结构高边墙锚拉初支结构及施工方法
CN205088687U (zh) 一种支护基坑的支撑结构
CN203498863U (zh) 立体连续框架式钢筋混凝土结构挡土墙
CN205688448U (zh) 一种利用岩溶破碎岩体加固支座的基坑支护装置
Hui Effect on existing building by foundation pit excavation
Dellaria et al. Combining multiple techniques to complete an urban deep excavation
CN207878462U (zh) 一种浆砌片石组合锚杆支护体系
Simon et al. Restoring RW5 at Yeager Airport: Design and construction of a tall retaining wall on the side of a mountain
CN206571503U (zh) 既有线路防护结构
CN205822207U (zh) 一种防护边坡的钢管桩桁架
Liu et al. Stability Analysis and Reinforcement Treatment of Open Pit Slope
CN103821106A (zh) 小型渔港及河道护岸结构
CN108360585A (zh) 临近边坡高层建筑基础的托换加固方法及建筑物复合基础

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C41 Transfer of patent application or patent right or utility model
CB03 Change of inventor or designer information

Inventor after: Lei Chunyan

Inventor after: Wei Congming

Inventor after: Shen Jiawen

Inventor after: Jiang Zehou

Inventor after: Wang Jianfei

Inventor after: Wang Xiaoyan

Inventor after: Zhou Lin

Inventor after: Yang Cheng

Inventor after: Wang Jiancheng

Inventor after: Zhang Enchao

Inventor before: Lei Chunyan

Inventor before: Shen Jiawen

Inventor before: Wang Jianfei

Inventor before: Wang Xiaoyan

Inventor before: Zhou Lin

Inventor before: Yang Cheng

Inventor before: Wang Jiancheng

Inventor before: Zhang Enchao

Inventor before: Wei Congming

COR Change of bibliographic data
TA01 Transfer of patent application right

Effective date of registration: 20170103

Address after: 650501 Yunnan Province Economic Development Zone of Kunming city information industry base, Forest Creek Road No. 188

Applicant after: Yunnan Construction Investment Holding Group Co., Ltd.

Address before: 650501 Yunnan city in Kunming Province Economic Development Zone No. 188 forest road information industry base construction development building

Applicant before: Yunnan Construction Engineering Group Co., Ltd.

GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20220414

Address after: 650000 Chunxi building, 256 Linxi Road, information industry base, Kunming Economic and Technological Development Zone, Yunnan Province

Patentee after: YUNNAN WATER CONSERVANCY & HYPOWER ENGINEERING Co.,Ltd.

Address before: 650501 No. 188 Lin Xi Road, information industry base, Kunming City, Yunnan Province

Patentee before: Yunnan Construction Investment Holding Group Co., Ltd.