CN102518045A - 拱肋预埋段安装定位支架及其调整定位方法 - Google Patents

拱肋预埋段安装定位支架及其调整定位方法 Download PDF

Info

Publication number
CN102518045A
CN102518045A CN201110445270XA CN201110445270A CN102518045A CN 102518045 A CN102518045 A CN 102518045A CN 201110445270X A CN201110445270X A CN 201110445270XA CN 201110445270 A CN201110445270 A CN 201110445270A CN 102518045 A CN102518045 A CN 102518045A
Authority
CN
China
Prior art keywords
arch rib
distribution beam
buried section
back timber
vertical
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201110445270XA
Other languages
English (en)
Other versions
CN102518045B (zh
Inventor
汪芳进
张静
王令侠
许佳平
李军堂
涂满明
王东辉
张爱花
傅战工
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Major Bridge Engineering Group Co Ltd MBEC
Original Assignee
China Railway Major Bridge Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Major Bridge Engineering Co Ltd filed Critical China Railway Major Bridge Engineering Co Ltd
Priority to CN201110445270.XA priority Critical patent/CN102518045B/zh
Publication of CN102518045A publication Critical patent/CN102518045A/zh
Application granted granted Critical
Publication of CN102518045B publication Critical patent/CN102518045B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

本发明公开了一种拱肋预埋段的安装定位支架及其调整定位方法,安装定位支架包括支架主体、四个支座以及四个竖向、水平千斤顶,支架主体顶端分别放置有左、右分配梁,左、右分配梁下方固定设有左、右起顶梁,左、右起顶梁上分别滑动设置有前、后滑块;与拱肋预埋段空间几何关系相匹配的四个支座分别放置在左、右分配梁上;四个竖向千斤顶分别固定在前、后滑块上,且伸出端分别与其上方的分配梁固定;四个水平千斤顶分别固定在左、右起顶梁上,且伸出端分别与前、后滑块固定。本发明,采用与拱肋预埋段空间几何关系相匹配的支座,避免了在现场进行拱肋预埋段的横向倾角、竖向倾角和水平偏角调整,简化了操作程序,提高了调整定位精度。

Description

拱肋预埋段安装定位支架及其调整定位方法
技术领域
本发明涉及拱桥施工领域,具体涉及拱肋预埋段安装定位支架及其调整定位方法。
背景技术
众所周知,在钢箱拱桥施工过程中,拱肋的线形控制极其重要,其中,拱肋预埋段安装的精度将直接影响全桥的线形。
然而,对于空间关系复杂的拱肋预埋段,其安装定位通常需要调整横向倾角、竖向倾角、水平偏角、平面位置以及竖向位置等多个参数,尤其是横向倾角、竖向倾角和水平偏角的调整非常困难、精度不易控制,且操作不方便。
因此,目前急需一种钢箱拱肋预埋段安装定位及调整方法,以提高拱肋预埋段安装的精度,从而精确地控制拱肋的线形。
发明内容
本发明所要解决的技术问题是钢箱拱桥拱肋预埋段安装精度不易控制、操作不便的问题。
为了解决上述技术问题,本发明所采用的技术方案是提供一种拱肋预埋段的安装定位支架,包括支架主体、四个支座以及四个竖向千斤顶、四个水平千斤顶,所述支架主体由左、右立柱固定在地面上组成,所述左、右立柱的顶端分别放置有水平设置的左、右分配梁,所述左、右分配梁的下方分别固定设有与其平行的左、右起顶梁,所述左、右起顶梁前、后部的顶面上分别滑动设置有前、后滑块;所述四个支座分别放置在所述左、右分配梁的顶面上,每个所述支座的顶面分别与拱肋预埋段四条侧边棱的相应支撑部相适配,且四个所述支座的底面均位于水平面内;所述四个竖向千斤顶分别沿竖直方向固定在所述左、右起顶梁上的前、后滑块上,且伸出端分别与其上方的相应分配梁固定;所述四个水平千斤顶分别沿水平方向固定在所述左、右起顶梁上,且伸出端分别与相应的所述前、后滑块固定。
在上述安装定位支架中,设置在同一根起顶梁上的两个所述水平千斤顶位于相应的所述前、后滑块之间,且沿该起顶梁的纵轴线对称。
在上述安装定位支架中,所述左、右立柱的左、右侧面上分别固定设有安装平台,所述左、右起顶梁的前、后端部分别设有与所述左、右立柱外形相适配的开口,所述左、右起顶梁的两端分别插装在所述左、右立柱上,且通过螺栓固定在所述安装平台上。
本发明还提供了一种使用上述安装定位支架进行拱肋预埋段安装定位的方法,包括以下步骤:
A10、根据拱肋预埋段的外形,制造出与四条侧边棱相应支撑部相适配的四个支座,四个支座底面水平且当拱肋预埋段通过支座水平放置时,其横向倾角、竖向倾角和水平偏角自动满足设计要求;
A20、将四个支座分别焊接在拱肋预埋段的相应侧边棱上,然后吊放在左、右分配梁上,通过测量获得拱肋预埋段相应的竖向和水平调整量,并通过竖向千斤顶和水平千斤顶调整到位;
A30、分别将四个支座与相应的左、右分配梁焊接固定、分别将左、右分配梁与左、右立柱焊接固定,完成拱肋预埋段的安装定位。
在上述方法中,在进行竖向调整时,首先使用竖向千斤顶顶起左、右分配梁,然后在左、右分配梁与左、右立柱之间通过增加或减少相应厚度的垫块调整拱肋预埋段的竖向位置;在进行水平调整时,首先使用竖向千斤顶顶起左、右分配梁,然后使用水平千斤顶使前、后滑块移动相应的距离,再通过竖向千斤顶将左、右分配梁放下。
在上述方法中,拱肋预埋段位置调整完成后,将左、右起顶梁拆除。
本发明,采用与拱肋预埋段空间几何关系相匹配的特制支座,避免了在现场进行拱肋预埋段的横向倾角、竖向倾角和水平偏角调整,简化了现场操作程序,提高了调整定位精度。
附图说明
图1为本发明提供的拱肋预埋段的安装定位支架结构示意图;
图2为图1中的A-A剖面示意图;
图3为图1中的B-B剖面示意图。
具体实施方式
下面结合附图对本发明作出详细的说明。
如图1、图2、图3所示,本发明提供的拱肋预埋段的安装定位支架包括支架主体、四个支座5、四个竖向千斤顶8和四个水平千斤顶9。
支架主体2是由左、右立柱21、22固定在地面上组成的稳定结构,左、右立柱21、22均为框架结构。左、右立柱21、22的顶端分别放置有左、右分配梁41、42,左、右分配梁41、42沿水平方向布置,左、右分配梁41、42的下方分别固定设有左、右起顶梁31、32,左、右起顶梁31、32分别与左、右分配梁41、42平行,左、右起顶梁31、32的前、后部的顶面上滑动设置有前、后滑块71、72,前、后滑块71、72与左、右起顶梁顶面之间设四氟板滑动面。
四个支座5分别放置在左、右分配梁41、42的顶面上,每个支座5的顶面分别与拱肋预埋段1的相应侧边棱的支撑部相适配。
四个竖向千斤顶8均沿竖直方向设置,其中两个固定在左起顶梁31上的前、后滑块71、72上,另外两个固定在右起顶梁32上的前、后滑块71、72上,四个竖向千斤顶8的伸出端分别与其上方的分配梁固定。
四个水平千斤顶9均沿水平方向设置,其中两个固定在左起顶梁31上,另外两个固定在右起顶梁32上,且四个水平千斤顶9的伸出端分别与相应的前、后滑块71、72固定。
本发明提供的利用上述安装定位支架进行拱肋预埋段安装定位的方法,具体步骤如下(同样参见图1、图2和图3):
A10、根据拱肋预埋段1的三维形状,制造出与拱肋预埋段1四个侧边棱上的支撑部位相适配的四个支座5,四个支座5底面水平,从而当拱预埋段1通过支座5水平放置时,其横向倾角、竖向倾角和水平偏角自动满足设计要求。
A20、将四个支座5分别焊接在拱肋预埋段1的相应支撑部位上,然后将拱肋预埋段1连同四个支座5一起吊放在左、右分配梁41、42上,由于支座5与拱肋预埋段1理论空间几何关系相匹配,故无需再调整拱肋预埋段1的横向倾角、竖向倾角和水平偏角。通过测量拱肋预埋段1控制点坐标获得相应的竖向和水平调整量,并通过竖向千斤顶8和水平千斤顶9进行调整。
在进行竖向调整时,首先使用竖向千斤顶8顶起左、右分配梁41、42,然后在左、右分配梁41、42与左、右立柱21、22之间通过增加或减少相应厚度的垫块6调整拱肋预埋段1的竖向位置;在进行水平调整时,首先使用竖向千斤顶8顶起左、右分配梁41、42,然后使用水平千斤顶9使前、后滑块71、72移动相应的距离调整拱肋预埋段1的水平位置,再通过竖向千斤顶8将左、右分配梁41、42放下。
A30、分别将四个支座5与相应的左、右分配梁41、42焊接固定、分别将左、右分配梁41、42与左、右支架21、22焊接固定,完成拱肋预埋段的安装定位。
调整定位完成后,可将左、右起顶梁拆除,减少埋入拱座混凝土中的钢材数量,节约成本。
本发明不局限于上述最佳实施方式,任何人应该得知在本发明的启示下作出的结构变化,凡是与本发明具有相同或相近的技术方案,均落入本发明的保护范围之内。

Claims (6)

1.拱肋预埋段安装定位支架,其特征在于,包括:
支架主体,由左、右立柱固定在地面上组成,所述左、右立柱的顶端分别放置有水平设置的左、右分配梁,所述左、右分配梁的下方分别固定设有与其平行的左、右起顶梁,所述左、右起顶梁前、后部的顶面上分别滑动设置有前、后滑块;
四个支座,分别放置在所述左、右分配梁的顶面上,每个所述支座的顶面分别与拱肋预埋段四条侧边棱的相应支撑部相适配,且四个所述支座的底面均位于水平面内;
四个竖向千斤顶,分别沿竖直方向固定在所述左、右起顶梁上的前、后滑块上,且伸出端分别与其上方的相应分配梁固定;
四个水平千斤顶,分别沿水平方向固定在所述左、右起顶梁上,且伸出端分别与相应的所述前、后滑块固定。
2.如权利要求1所述的拱肋预埋段安装定位支架,其特征在于,设置在同一根起顶梁上的两个所述水平千斤顶位于相应的所述前、后滑块之间,且沿该起顶梁的纵轴线对称。
3.如权利要求1所述的拱肋预埋段安装定位支架,其特征在于,所述左、右立柱的左、右侧面上分别固定设有安装平台,所述左、右起顶梁的前、后端部分别设有与所述左、右立柱外形相适配的开口,所述左、右起顶梁的两端分别插装在所述左、右立柱上,且通过螺栓固定在所述安装平台上。
4.使用如权利要求1所述的安装定位支架进行拱肋预埋段安装定位的方法,其特征在于,包括以下步骤:
A10、根据拱肋预埋段的外形,制造出与四条侧边棱相应支撑部相适配的四个支座,四个支座底面水平且当拱肋预埋段通过支座水平放置时,其横向倾角、竖向倾角和水平偏角自动满足设计要求;
A20、将四个支座分别焊接在拱肋预埋段的相应侧边棱上,然后吊放在左、右分配梁上,通过测量获得拱肋预埋段相应的竖向和水平调整量,并通过竖向千斤顶和水平千斤顶调整到位;
A30、分别将四个支座与相应的左、右分配梁焊接固定、分别将左、右分配梁与左、右立柱焊接固定,完成拱肋预埋段的安装定位。
5.如权利要求4所述的方法,其特征在于,在步骤A20中,在进行竖向调整时,首先使用竖向千斤顶顶起左、右分配梁,然后在左、右分配梁与左、右立柱之间通过增加或减少相应厚度的垫块调整拱肋预埋段的竖向位置;在进行水平调整时,首先使用竖向千斤顶顶起左、右分配梁,然后使用水平千斤顶使前、后滑块移动相应的距离,再通过竖向千斤顶将左、右分配梁放下。
6.如权利要求4所述的方法,其特征在于,在步骤A30中,拱肋预埋段位置调整完成后,将左、右起顶梁拆除。
CN201110445270.XA 2011-12-28 2011-12-28 拱肋预埋段安装定位支架及其调整定位方法 Active CN102518045B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201110445270.XA CN102518045B (zh) 2011-12-28 2011-12-28 拱肋预埋段安装定位支架及其调整定位方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201110445270.XA CN102518045B (zh) 2011-12-28 2011-12-28 拱肋预埋段安装定位支架及其调整定位方法

Publications (2)

Publication Number Publication Date
CN102518045A true CN102518045A (zh) 2012-06-27
CN102518045B CN102518045B (zh) 2014-08-27

Family

ID=46289089

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201110445270.XA Active CN102518045B (zh) 2011-12-28 2011-12-28 拱肋预埋段安装定位支架及其调整定位方法

Country Status (1)

Country Link
CN (1) CN102518045B (zh)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103669229A (zh) * 2014-01-04 2014-03-26 中铁二十五局集团第二工程有限公司 一种防止拱架在拖拉过程中侧翻的装置
CN104631331A (zh) * 2015-01-07 2015-05-20 中铁大桥局第七工程有限公司 一种钢拱空中安装方法
CN110747747A (zh) * 2019-10-29 2020-02-04 中铁大桥局第七工程有限公司 基于钢拱支架的钢拱节段安装调整装置、支架系统及方法
CN113699887A (zh) * 2021-08-19 2021-11-26 中交二公局第三工程有限公司 一种多边形钢拱肋拼装调位装置及其使用方法

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2171330C1 (ru) * 2000-07-04 2001-07-27 Закрытое акционерное общество "Мост-бизнес-консалтинг" Арочный мост с ездой поверху и способ его возведения
CN201746778U (zh) * 2010-07-27 2011-02-16 中铁大桥局集团第三工程有限公司 用于外倾式钢管拱桥拱肋架设的安装调节装置
CN101984189A (zh) * 2010-11-10 2011-03-09 中交第二航务工程局有限公司 大型钢混组合多棱台斜面拱座施工方法
CN102071644A (zh) * 2010-12-31 2011-05-25 中铁港航工程局有限公司 一种桥梁拱肋整体提升安装方法
CN102080355A (zh) * 2010-12-10 2011-06-01 中铁大桥局集团第三工程有限公司 钢管拱桥拱座的安装方法

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2171330C1 (ru) * 2000-07-04 2001-07-27 Закрытое акционерное общество "Мост-бизнес-консалтинг" Арочный мост с ездой поверху и способ его возведения
CN201746778U (zh) * 2010-07-27 2011-02-16 中铁大桥局集团第三工程有限公司 用于外倾式钢管拱桥拱肋架设的安装调节装置
CN101984189A (zh) * 2010-11-10 2011-03-09 中交第二航务工程局有限公司 大型钢混组合多棱台斜面拱座施工方法
CN102080355A (zh) * 2010-12-10 2011-06-01 中铁大桥局集团第三工程有限公司 钢管拱桥拱座的安装方法
CN102071644A (zh) * 2010-12-31 2011-05-25 中铁港航工程局有限公司 一种桥梁拱肋整体提升安装方法

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
倪建华等: "京杭运河大桥主拱肋预制拼装施工工艺", 《公路》 *
许佳平等: "贵广铁路广州东平水道钢桁拱桥安装施工技术", 《辽宁省交通高等专科学校学报》 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103669229A (zh) * 2014-01-04 2014-03-26 中铁二十五局集团第二工程有限公司 一种防止拱架在拖拉过程中侧翻的装置
CN103669229B (zh) * 2014-01-04 2015-11-18 中铁二十五局集团第二工程有限公司 一种防止拱架在拖拉过程中侧翻的装置
CN104631331A (zh) * 2015-01-07 2015-05-20 中铁大桥局第七工程有限公司 一种钢拱空中安装方法
CN110747747A (zh) * 2019-10-29 2020-02-04 中铁大桥局第七工程有限公司 基于钢拱支架的钢拱节段安装调整装置、支架系统及方法
CN113699887A (zh) * 2021-08-19 2021-11-26 中交二公局第三工程有限公司 一种多边形钢拱肋拼装调位装置及其使用方法

Also Published As

Publication number Publication date
CN102518045B (zh) 2014-08-27

Similar Documents

Publication Publication Date Title
CN205296874U (zh) 桩柱一体化信息化施工监测定位装置
CN102518045B (zh) 拱肋预埋段安装定位支架及其调整定位方法
CN105113410A (zh) 支撑胎架及利用支撑胎架搭设公路钢桥的线型成形方法
CN108894117A (zh) 预制立柱或盖梁拼装用的调节夹片及其拼装结构与方法
CN103758213B (zh) 一种装配式墙板与梁体精准定位安装连接结构
CN202559236U (zh) 一种拱肋限位固定钢支座
CN106602984A (zh) 光伏支架立柱或桩基础标高调节件及施工方法
CN105317052A (zh) 一种塔吊基础螺栓固定方法
CN103486853B (zh) 步进梁式加热炉步进装置的安装方法
CN110193671A (zh) 一种冷轧大型板带激光焊机底座的安装调整方法
CN102896283B (zh) 一种h型坯连铸机扇形段检修对弧装置
JP2015155821A (ja) 凹凸計測装置
CN203323740U (zh) 一种建筑物沉降无损测量水准尺支架
CN105421480A (zh) 输电塔的正方形基础分坑方法
CN203403366U (zh) 一种基座钢锚箱三向式定位装置
KR20120088974A (ko) 선로용 좌표측량 프리즘타켓
CN205185334U (zh) 激光快速成型机用可快速更换的树脂槽
CN203795598U (zh) 一种装配式墙板与梁体精准定位安装连接结构
CN103195012B (zh) 一种生态河道模型的地形制作台架
CN208748530U (zh) 预制立柱或盖梁拼装用的调节夹片及其拼装结构
CN207513198U (zh) 移动式钢管内隔板安装成套装置及其安装体系
CN208238798U (zh) 一种全站仪棱镜
CN202212724U (zh) 桥面块体模拟拼装胎架
CN104452800B (zh) 水泥磨基础悬挂式预留孔洞埋设方法
CN109736296A (zh) 预埋基准的安装方法及厂房基准的设置方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: GROUP CO., LTD., ZHONGTIE DAQIAO BUREAU

Free format text: FORMER OWNER: CHINA ZHONGTIE MAJOR BRIDGE ENGINEERING CO., LTD.

Effective date: 20150303

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 430074 WUHAN, HUBEI PROVINCE TO: 430050 WUHAN, HUBEI PROVINCE

TR01 Transfer of patent right

Effective date of registration: 20150303

Address after: 430050 Hanyang Road, Hanyang District, Hubei, No. 38, No.

Patentee after: Group Co., Ltd., Zhongtie Daqiao Bureau

Address before: 430074 Hubei province Wuhan Dongxin East Lake New Technology Development Zone Road SBI Venture Street No. 6 Building 12 layer

Patentee before: China Zhongtie Major Bridge Engineering Co., Ltd.