CN102425173A - 深基坑土方开挖方法 - Google Patents

深基坑土方开挖方法 Download PDF

Info

Publication number
CN102425173A
CN102425173A CN2011104032351A CN201110403235A CN102425173A CN 102425173 A CN102425173 A CN 102425173A CN 2011104032351 A CN2011104032351 A CN 2011104032351A CN 201110403235 A CN201110403235 A CN 201110403235A CN 102425173 A CN102425173 A CN 102425173A
Authority
CN
China
Prior art keywords
steel plate
horizontal support
deep foundation
support steel
earthwork
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2011104032351A
Other languages
English (en)
Other versions
CN102425173B (zh
Inventor
张生雨
蔚素荣
白汉民
刘延彬
白艳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC Tiangong Group Corp Ltd
Original Assignee
MCC Tiangong Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC Tiangong Group Corp Ltd filed Critical MCC Tiangong Group Corp Ltd
Priority to CN 201110403235 priority Critical patent/CN102425173B/zh
Publication of CN102425173A publication Critical patent/CN102425173A/zh
Application granted granted Critical
Publication of CN102425173B publication Critical patent/CN102425173B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

本发明涉及一种深基坑土方开挖方法,其步骤为:(1)深基坑放线测量完毕后,根据深基坑工程情况在深基坑内由上到下设计N层水平支撑钢板并采用岛式开挖法逐层开挖基坑土方,1≤N≤20;(2)沿深基坑壁向下打入外侧钢板桩;(3)开挖第一层水平支撑钢板以上的土方,将第一层水平支撑钢板一端与外侧钢板桩焊接,在第一层水平支撑钢板的另一端向下打入内侧钢板桩;以此类推施工第N层水平支撑钢板,修建坡道并开挖第N层水平支撑钢板以下的土方,然后退行开挖坡道,拔除内侧钢板桩,挖除余下的土方,深基坑土方开挖完毕。本发明施工方法简单易行,无需栈桥、有效加快施工工期,降低了深基坑土方开挖成本,是一种安全可靠的深基坑土方开挖方法。

Description

深基坑土方开挖方法
技术领域
本发明属于土方开挖领域,尤其是一种深基坑土方开挖方法。
背景技术
环境要求高的大型深基坑,特别是软土地基的深基坑,多采用基坑支护,而不是大开挖。为了土方开挖方便,多数设置基坑栈桥,以便挖机直接站在栈桥上快速挖土。有些工程出于各种原因不设置栈桥,而是在基坑内设置土坡道,该坡道从基坑外延上部延伸到基坑底部,挖机和土方车从坡道进入基坑内将土挖走。当根据基坑深度设置多层次水平支撑用于挖机和土方车挖土时,由于坡道的影响,必须将坡道土方清除,才能施工水平支撑,当施工完水平支撑后需要再恢复坡道。水平支撑设置的越多,则清除和恢复坡道的次数越多,造成工期延长,费用增加,施工难度加大。如果开挖范围内土质不好,如淤泥质土,则很难恢复,而且反复修建坡道的费用较高。
发明内容
本发明的目的在于克服现有技术的不足,提供一种深基坑土方开挖方法,该深基坑土方开挖方法工艺简单、无需栈桥、有效加快施工工期,降低了深基坑土方开挖成本。
本发明解决其技术问题是通过以下技术方案实现的:
一种深基坑土方开挖方法,其方法包括的步骤为:
(1)、深基坑放线测量完毕后,根据深基坑工程情况在深基坑内由上到下设计N层水平支撑钢板并采用岛式开挖法逐层开挖基坑土方,1≤N≤20;
(2)、沿深基坑壁向下打入外侧钢板桩;
(3)、开挖第一层水平支撑钢板以上的土方,达到第一层水平支撑钢板施工标高后,将第一层水平支撑钢板一端与外侧钢板桩焊接,在第一层水平支撑钢板的另一端向下打入内侧钢板桩,内侧钢板桩与第一层水平支撑钢板之间留50~300mm的空隙,该空隙用细石混凝土浇灌密实;
(4)、修建坡道并开挖第二层水平支撑钢板以上的土方,达到第二层水平支撑钢板施工标高后,将第二层水平支撑钢板一端与外侧钢板桩焊接,在第二层水平支撑钢板的另一端与内侧钢板桩之间留50~300mm的空隙,该空隙用细石混凝土浇灌密实;
(5)、修建坡道并开挖第N层水平支撑钢板以上的土方,达到第N层水平支撑钢板施工标高后,将第N层水平支撑钢板一端与外侧钢板桩焊接,在第N层水平支撑钢板的另一端与内侧钢板桩之间留50~300mm的空隙,该空隙用细石混凝土浇灌密实;
(6)、修建坡道并开挖第N层水平支撑钢板以下的土方,然后退行开挖坡道,拔除内侧钢板桩,挖除余下的土方,深基坑土方开挖完毕。
而且,所述的N层水平支撑钢板的每一层水平支撑钢板均沿深基坑壁外侧钢板桩向内间隔设置。
而且,所述的细石混凝土与内侧钢板桩之间用油毡纸隔离。
本发明的优点和有益效果为:
1、本深基坑土方开挖方法采用深基坑壁向下打入外侧钢板桩,在深基坑内由上到下设计N层水平支撑钢板并采用岛式开挖法逐层开挖基坑土方,1≤N≤20,并在水平支撑钢板内侧打入内侧钢板桩,该方法不需要设置栈桥,修好的坡道在挖土阶段可一直保留,避免反复挖填。与单一修建坡道挖土的方法相比,能够加快工期,降低工程成本,保证深基坑安全。
2、本发明施工方法简单易行,无需栈桥、有效加快施工工期,降低了深基坑土方开挖成本,是一种安全可靠的深基坑土方开挖方法。
附图说明
图1为本发明应用在深基坑土方开挖的示意图。
具体实施方式
下面通过具体实施例对本发明作进一步详述,以下实施例只是描述性的,不是限定性的,不能以此限定本发明的保护范围。
一种深基坑土方开挖方法,其方法包括的步骤为:
(1)、深基坑放线测量完毕后,根据深基坑工程情况在深基坑内由上到下设计N层水平支撑钢板并采用岛式开挖法逐层开挖基坑土方,1≤N≤20;
(2)、沿深基坑壁向下打入外侧钢板桩1;
(3)、开挖第一层水平支撑钢板3以上的土方,达到第一层水平支撑钢板施工标高后,将第一层水平支撑钢板一端与外侧钢板桩焊接,在第一层水平支撑钢板的另一端向下打入内侧钢板桩7,内侧钢板桩与第一层水平支撑钢板之间留50~300mm的空隙,该空隙用细石混凝土6浇灌密实;内侧钢板桩是一顺一丁的打入,为了挖土完毕拔桩方便,细石混凝土与内侧钢板桩之间用油毡纸隔离;内侧钢板桩以及外侧钢板桩的规格通过坡道、车辆等产生的侧压力等计算确定;
(4)、修建坡道2并开挖第二层水平支撑钢板4以上的土方,可以由小型挖机在钢板桩一侧掏挖,然后由普通挖机8接力装车运走;达到第二层水平支撑钢板施工标高后,将第二层水平支撑钢板一端与外侧钢板桩焊接,在第二层水平支撑钢板的另一端与内侧钢板桩之间留50~300mm的空隙,该空隙用细石混凝土浇灌密实;
(5)、修建坡道并开挖第N层水平支撑钢板5以上的土方,达到第N层水平支撑钢板施工标高后,将第N层水平支撑钢板一端与外侧钢板桩焊接,在第N层水平支撑钢板的另一端与内侧钢板桩之间留50~300mm的空隙,该空隙用细石混凝土浇灌密实;N层水平支撑钢板的每一层水平支撑钢板均沿深基坑壁外侧钢板桩向内间隔设置;
(6)、修建坡道并开挖第N层水平支撑钢板以下的土方,然后退行开挖坡道,当普通挖机无法挖走剩余土方时,由长臂挖机在第一层水平支撑钢板上,将剩余土方挖走,但保留一部分土方临时固定钢板桩根部,拔除内侧钢板桩,挖除余下的土方,深基坑土方开挖完毕。

Claims (3)

1.一种深基坑土方开挖方法,其特征在于:该方法包括的步骤为:
(1)、深基坑放线测量完毕后,根据深基坑工程情况在深基坑内由上到下设计N层水平支撑钢板并采用岛式开挖法逐层开挖基坑土方,1≤N≤20;
(2)、沿深基坑壁向下打入外侧钢板桩;
(3)、开挖第一层水平支撑钢板以上的土方,达到第一层水平支撑钢板施工标高后,将第一层水平支撑钢板一端与外侧钢板桩焊接,在第一层水平支撑钢板的另一端向下打入内侧钢板桩,内侧钢板桩与第一层水平支撑钢板之间留50~300mm的空隙,该空隙用细石混凝土浇灌密实;
(4)、修建坡道并开挖第二层水平支撑钢板以上的土方,达到第二层水平支撑钢板施工标高后,将第二层水平支撑钢板一端与外侧钢板桩焊接,在第二层水平支撑钢板的另一端与内侧钢板桩之间留50~300mm的空隙,该空隙用细石混凝土浇灌密实;
(5)、修建坡道并开挖第N层水平支撑钢板以上的土方,达到第N层水平支撑钢板施工标高后,将第N层水平支撑钢板一端与外侧钢板桩焊接,在第N层水平支撑钢板的另一端与内侧钢板桩之间留50~300mm的空隙,该空隙用细石混凝土浇灌密实;
(6)、修建坡道并开挖第N层水平支撑钢板以下的土方,然后退行开挖坡道,拔除内侧钢板桩,挖除余下的土方,深基坑土方开挖完毕。
2.根据权利要求1所述的深基坑土方开挖方法,其特征在于:所述的N层水平支撑钢板的每一层水平支撑钢板均沿深基坑壁外侧钢板桩向内间隔设置。
3.根据权利要求1所述的深基坑土方开挖方法,其特征在于:所述的细石混凝土与内侧钢板桩之间用油毡纸隔离。
CN 201110403235 2011-12-07 2011-12-07 深基坑土方开挖方法 Active CN102425173B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201110403235 CN102425173B (zh) 2011-12-07 2011-12-07 深基坑土方开挖方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201110403235 CN102425173B (zh) 2011-12-07 2011-12-07 深基坑土方开挖方法

Publications (2)

Publication Number Publication Date
CN102425173A true CN102425173A (zh) 2012-04-25
CN102425173B CN102425173B (zh) 2013-10-16

Family

ID=45959199

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201110403235 Active CN102425173B (zh) 2011-12-07 2011-12-07 深基坑土方开挖方法

Country Status (1)

Country Link
CN (1) CN102425173B (zh)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103243720A (zh) * 2013-05-20 2013-08-14 中冶天工集团有限公司 软土地基超深基坑支护方法
CN103290849A (zh) * 2013-06-20 2013-09-11 江苏城市职业学院 一种半逆作法坑中坑支护结构及其施工方法
CN103821149A (zh) * 2014-02-28 2014-05-28 中天建设集团有限公司 大型深基坑留坡挖土及坑中坑混凝土后浇施工工法
CN104532854A (zh) * 2014-12-26 2015-04-22 上海建工一建集团有限公司 周边地下结构作支护体系的深基坑施工方法
CN104563128A (zh) * 2014-12-22 2015-04-29 上海建工集团股份有限公司 软土地区非对称深大基坑同步开挖的支护体系及实施方法
CN104988929A (zh) * 2015-07-03 2015-10-21 中国十七冶集团有限公司 一种高层建筑深基坑淤泥质土方开挖疏干方法
CN106013165A (zh) * 2016-06-23 2016-10-12 程华清 一种集装箱组合式基坑出土方法
CN107023012A (zh) * 2017-03-28 2017-08-08 深圳市工勘岩土集团有限公司 多道环形砼支撑深基坑土方外运施工方法
CN107268633A (zh) * 2017-06-01 2017-10-20 浙江德润市政园林有限公司 基坑开挖施工方法
CN113279421A (zh) * 2021-06-28 2021-08-20 上海兴怡基础工程有限公司 一种深基坑真空降水的工艺

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000282469A (ja) * 1999-03-31 2000-10-10 Hazama Gumi Ltd 切梁式土留め支保工及び根切り工法
KR20020054135A (ko) * 2000-12-27 2002-07-06 이동원 배수성 무지보 구체식 연약지반 터파기공법
US20030005650A1 (en) * 1999-01-13 2003-01-09 Hong Won Kee Composite retaining wall and construction method for underground structure
CN101457526A (zh) * 2009-01-07 2009-06-17 中冶天工建设有限公司 圆形深基坑混凝土排桩支护及主体结构逆作施工方法
CN101555692A (zh) * 2008-04-09 2009-10-14 中交三航局第二工程有限公司 水上基坑降水取土施工方法
CN101718094A (zh) * 2009-11-10 2010-06-02 朱奎 一种带地下室建筑物的基坑支护施工方法
CN101824825A (zh) * 2010-05-28 2010-09-08 天津三建建筑工程有限公司 一种深基坑明挖施工方法

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20030005650A1 (en) * 1999-01-13 2003-01-09 Hong Won Kee Composite retaining wall and construction method for underground structure
JP2000282469A (ja) * 1999-03-31 2000-10-10 Hazama Gumi Ltd 切梁式土留め支保工及び根切り工法
KR20020054135A (ko) * 2000-12-27 2002-07-06 이동원 배수성 무지보 구체식 연약지반 터파기공법
CN101555692A (zh) * 2008-04-09 2009-10-14 中交三航局第二工程有限公司 水上基坑降水取土施工方法
CN101457526A (zh) * 2009-01-07 2009-06-17 中冶天工建设有限公司 圆形深基坑混凝土排桩支护及主体结构逆作施工方法
CN101718094A (zh) * 2009-11-10 2010-06-02 朱奎 一种带地下室建筑物的基坑支护施工方法
CN101824825A (zh) * 2010-05-28 2010-09-08 天津三建建筑工程有限公司 一种深基坑明挖施工方法

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
张巍: "某工程深基坑支护施工技术", 《中外建筑》, no. 06, 30 June 2011 (2011-06-30) *
王东晖等: "地下室半逆作法施工技术在深厚淤泥质土层中的应用", 《浙江建筑》, no. 04, 30 April 2011 (2011-04-30) *

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103243720A (zh) * 2013-05-20 2013-08-14 中冶天工集团有限公司 软土地基超深基坑支护方法
CN103290849A (zh) * 2013-06-20 2013-09-11 江苏城市职业学院 一种半逆作法坑中坑支护结构及其施工方法
CN103290849B (zh) * 2013-06-20 2015-03-04 江苏城市职业学院 一种半逆作法坑中坑支护结构及其施工方法
CN103821149A (zh) * 2014-02-28 2014-05-28 中天建设集团有限公司 大型深基坑留坡挖土及坑中坑混凝土后浇施工工法
CN104563128B (zh) * 2014-12-22 2016-10-05 上海建工集团股份有限公司 软土地区非对称深大基坑同步开挖的支护体系及实施方法
CN104563128A (zh) * 2014-12-22 2015-04-29 上海建工集团股份有限公司 软土地区非对称深大基坑同步开挖的支护体系及实施方法
CN104532854B (zh) * 2014-12-26 2017-07-14 上海建工一建集团有限公司 周边地下结构作支护体系的深基坑施工方法
CN104532854A (zh) * 2014-12-26 2015-04-22 上海建工一建集团有限公司 周边地下结构作支护体系的深基坑施工方法
CN104988929A (zh) * 2015-07-03 2015-10-21 中国十七冶集团有限公司 一种高层建筑深基坑淤泥质土方开挖疏干方法
CN106013165A (zh) * 2016-06-23 2016-10-12 程华清 一种集装箱组合式基坑出土方法
CN107023012A (zh) * 2017-03-28 2017-08-08 深圳市工勘岩土集团有限公司 多道环形砼支撑深基坑土方外运施工方法
CN107268633A (zh) * 2017-06-01 2017-10-20 浙江德润市政园林有限公司 基坑开挖施工方法
CN113279421A (zh) * 2021-06-28 2021-08-20 上海兴怡基础工程有限公司 一种深基坑真空降水的工艺

Also Published As

Publication number Publication date
CN102425173B (zh) 2013-10-16

Similar Documents

Publication Publication Date Title
CN102425173B (zh) 深基坑土方开挖方法
CN103696784B (zh) 一种浅埋大跨隧道下穿建构筑物的大直径长管幕施工方法
KR101205783B1 (ko) 지하구조물의 철거와 신축을 동시에 진행하는 복합 시공방법
CN104790410B (zh) 一种适用于浅水淤泥河道的基坑开挖支护方法
CN110258582B (zh) 基于钢管桩与拉森钢板的斜支撑基坑支护结构及施工方法
CN112064751A (zh) 一种排水管线的深沟槽施工方法
CN104929133A (zh) 一种深基坑拉森钢板桩桩底放坡支护的施工方法
CN106545019A (zh) 用于级差式地下结构施工的换撑体系及施工方法
JP5351125B2 (ja) オープンシールド工法のオープンシールド機発進方法
JP6194388B1 (ja) オープンシールド工法
JP5204063B2 (ja) オープンシールド工法における函体基礎の築造方法
CN103741690B (zh) 一种土塞补偿管桩拔出施工方法及其所用的土塞补偿管桩拔桩装置
CN102418348A (zh) 利用咬合桩形成地下连续墙的施工工艺
CN110984216A (zh) 水平t字形钢筋混凝土挡土墙及其施工方法
CN104878774B (zh) 移动式围堰明挖法
JP2006214109A (ja) 地下構造物の構築方法
KR20030097084A (ko) 앵커링을 이용한 보강토 옹벽 시공방법
JP3917146B2 (ja) オープンシールド工法における覆工板の布設方法および撤去方法
CN103195067A (zh) 一种深基坑淤泥质粉质粘土垫层施工方法
JP2010242373A (ja) オープンシールド工法における覆工板の設置方法
CN105735324B (zh) 钢板桩支护的平台拆卸法
JP5639213B2 (ja) オープンシールド工法
CN211621670U (zh) 水平t字形钢筋混凝土挡土墙
JP4279818B2 (ja) オープンシールド工法
JP5960786B2 (ja) オープンシールド工法におけるシールド機回収方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant