CN102368435B CN2011103538351A CN201110353835A CN102368435B CN 102368435 B CN102368435 B CN 102368435B CN 2011103538351 A CN2011103538351 A CN 2011103538351A CN 201110353835 A CN201110353835 A CN 201110353835A CN 102368435 B CN102368435 B CN 102368435B
Authority
CN
China
Prior art keywords
press
iron core
screw rod
pull bar
pull
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN2011103538351A
Other languages
English (en)
Other versions
CN102368435A (zh
Inventor
高扬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Baoding Tianwei Baobian Electric Co Ltd
Original Assignee
Baoding Tianwei Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Baoding Tianwei Group Co Ltd filed Critical Baoding Tianwei Group Co Ltd
Priority to CN2011103538351A priority Critical patent/CN102368435B/zh
Publication of CN102368435A publication Critical patent/CN102368435A/zh
Application granted granted Critical
Publication of CN102368435B publication Critical patent/CN102368435B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

本发明涉及一种并联电抗器器身压紧工装及压紧方法,属于变压器专用辅助工装技术领域。技术方案是包含压梁(1)、调节垫圈(2)、压装螺杆(3),压装螺杆穿过调节垫圈后穿过压梁,压梁由双层钢板(8、9)和钢管(10)构成,钢管设置在双层钢板之间。在双层钢板上设有加强铁(11),焊接在双层钢板上。本发明的积极效果:工装结构简单,拆装方便,便于操作,实用性及通用性强,大大降低了劳动强度,提高了劳动效率,确保了电抗器铁芯及线圈能够轴向压紧,有效降低了噪声与振动,提高了产品性能。

Description

并联电抗器器身压紧工装及压紧方法
技术领域
本发明涉及一种并联电抗器器身压紧工装及压紧方法,属于变压器专用辅助工装技术领域。
背景技术
电抗器的振动和噪音是电抗器关键性能指标,是影响产品长期运行主要因素,降低振动提高器身的抗震性,对噪音进行控制是很关键的,因此在电抗器制造过程中就要保证对电抗器的器身整体进行有效、可靠的压装。这也正是并联电抗器制造过程中的必须解决的一个难点和关键点。对采用拉杆式压装结构的并联电抗器,采用传统的压梁方式进行压紧,存在以下缺点:1)拉杆处的紧固力往往不易得到保证,且操作较复杂。2)费时费力,工装受电抗器外形尺寸的限制不且通用。
发明内容
本发明的目的是提供一种并联电抗器器身压紧工装及压紧方法,操作简便,压力调节准确,能可靠保证电抗器器身整体压装所需压紧力,解决背景技术存在的上述问题。
本发明的技术方案是:并联电抗器器身压紧工装,包含压梁、调节垫圈、压装螺杆,压装螺杆穿过调节垫圈后穿过压梁,压梁由双层钢板和钢管构成,钢管设置在双层钢板之间。
在双层钢板上设有加强铁,焊接在双层钢板上。
压梁的下面设有拉杆螺母与压装螺杆匹配。拉杆螺母下面设有垫板、铁芯拉杆,垫板通过铁芯拉杆固定,垫板与压梁之间设有油缸。
并联电抗器器身压紧方法,包含如下步骤:待并联电抗器器身需要进行压紧时,安装并联电抗器的上轭铁及电抗器自带的拉杆螺母,并将其进行紧固;分别安装压紧装置的压梁、调节垫圈及压装螺杆,将压装螺杆与铁芯拉杆紧固连接在一起,同时在垫板与压梁之间放入油缸,接好油压泵站管路,即可开始按要求进行压装;由于压装螺杆已和铁芯拉杆、拉杆螺母连接在一起,启动液压设备,这样在加压过程使油缸向上顶起的过程中,将通过反作用力使铁芯拉杆处得到压缩;逐渐加压,当达到所需压紧力时,将铁芯拉杆处的拉杆螺母拧紧,撤除压装螺杆及压梁,旋紧拉杆螺母即可。
本发明的积极效果:工装结构简单,拆装方便,便于操作,实用性及通用性强,大大降低了劳动强度,提高了劳动效率,确保了电抗器铁芯及线圈能够轴向压紧,有效降低了噪声与振动,提高了产品性能。
附图说明
图1是本发明实施例的结构示意图;
图2是本发明实施例的俯视示意图;
图3是本发明实施例压梁的结构示意图;
图中:压梁1、调节垫圈2、压装螺杆3、拉杆螺母4、垫板5、铁芯拉杆6、油缸7、双层钢板8和9、钢管10、加强铁11。
具体实施方式
下面结合附图,通过实施例对本发明做进一步说明。
并联电抗器器身压紧工装,包含压梁1、调节垫圈2、压装螺杆3,压装螺杆穿过调节垫圈后穿过压梁,压梁由双层钢板8、9和钢管10构成,钢管设置在双层钢板之间。在双层钢板上设有加强铁11,焊接在双层钢板上。
压梁的下面设有拉杆螺母4与压装螺杆匹配。拉杆螺母下面设有垫板5、铁芯拉杆6,垫板通过铁芯拉杆固定,垫板与压梁之间设有油缸7。
并联电抗器器身压紧方法,包含如下步骤:待并联电抗器器身需要进行压紧时,安装并联电抗器的上轭铁及电抗器自带的拉杆螺母,并将其进行紧固;分别安装压紧装置的压梁、调节垫圈及压装螺杆,将压装螺杆与铁芯拉杆紧固连接在一起,同时在垫板与压梁之间放入油缸,接好油压泵站管路,即可开始按要求进行压装;由于压装螺杆已和铁芯拉杆、拉杆螺母连接在一起,启动液压设备,这样在加压过程使油缸向上顶起的过程中,将通过反作用力使铁芯拉杆处得到压缩;逐渐加压,当达到所需压紧力时,将铁芯拉杆处的拉杆螺母拧紧,撤除压装螺杆及压梁,旋紧拉杆螺母即可。

Claims (1)

1.一种并联电抗器器身压紧方法,其特征在于包含如下步骤:待并联电抗器器身需要进行压紧时,安装并联电抗器的上轭铁及电抗器自带的拉杆螺母,并将其进行紧固;分别安装压紧装置的压梁、调节垫圈及压装螺杆,将压装螺杆与铁芯拉杆紧固连接在一起,同时在垫板与压梁之间放入油缸,接好油压泵站管路,即开始进行压装;由于压装螺杆已和铁芯拉杆、拉杆螺母连接在一起,启动液压设备,在加压使油缸向上顶起的过程中,通过反作用力使铁芯拉杆处得到压缩;逐渐加压,当达到所需压紧力时,将铁芯拉杆处的拉杆螺母拧紧,撤除压装螺杆及压梁,旋紧拉杆螺母。
CN2011103538351A 2011-11-10 2011-11-10 并联电抗器器身压紧工装及压紧方法 Active CN102368435B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011103538351A CN102368435B (zh) 2011-11-10 2011-11-10 并联电抗器器身压紧工装及压紧方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011103538351A CN102368435B (zh) 2011-11-10 2011-11-10 并联电抗器器身压紧工装及压紧方法

Publications (2)

Publication Number Publication Date
CN102368435A CN102368435A (zh) 2012-03-07
CN102368435B true CN102368435B (zh) 2012-11-14

Family

ID=45760994

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011103538351A Active CN102368435B (zh) 2011-11-10 2011-11-10 并联电抗器器身压紧工装及压紧方法

Country Status (1)

Country Link
CN (1) CN102368435B (zh)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103310961A (zh) * 2013-06-21 2013-09-18 保定天威保变电气股份有限公司 一种电抗器的器身压紧方法及装置

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2583777Y (zh) * 2002-10-27 2003-10-29 特变电工衡阳变压器有限公司 有磁心电抗器铁心压紧结构
CN2720587Y (zh) * 2004-07-27 2005-08-24 特变电工衡阳变压器有限公司 一种有磁心电抗器铁心压紧结构
CN2773873Y (zh) * 2005-03-22 2006-04-19 济南志友集团股份有限公司 线圈压紧装置
JP2010062486A (ja) * 2008-09-08 2010-03-18 Denso Corp 巻線装置
CN101477888B (zh) * 2008-09-16 2011-05-04 卧龙电气集团股份有限公司 变压器的器身压紧装置
CN101521090B (zh) * 2008-11-21 2011-01-19 中国西电电气股份有限公司 一种电抗器铁心压紧工艺及压紧装置

Also Published As

Publication number Publication date
CN102368435A (zh) 2012-03-07

Similar Documents

Publication Publication Date Title
CN201270188Y (zh) 一种干式铁芯电抗器
CN102368435B (zh) 并联电抗器器身压紧工装及压紧方法
CN202625726U (zh) 大吨位顶压型前卡千斤顶
CN202307473U (zh) 并联电抗器器身压紧工装
CN202207879U (zh) 一种套筒结合件焊接工装
CN201067889Y (zh) 液压预紧装置
CN102259272A (zh) 一种机床强力夹紧装置
CN201544013U (zh) 一种水电发电机转子磁极铁芯压装装置
CN101944427A (zh) 并联电抗器器身整体压装装置
CN201769035U (zh) 衬套组立设备
CN202996580U (zh) 通用绕线模具
CN102364834B (zh) 发电机定子端部拉紧楔块和碟形垫圈的装配装置和方法
CN102969142A (zh) 一种变压器带压插铁工艺
CN101937766B (zh) 电抗器中心压紧拉杆
CN201744873U (zh) 一种螺栓机床夹紧装置
CN202197183U (zh) 水轮发电机定子铁芯通用同步压装装置
CN215601175U (zh) 一种大型水轮发电机磁极调整垫片快速夹紧装置
CN205021503U (zh) 一种试块抗渗检测用装卸设备
CN201940791U (zh) 并联电抗器器身整体压装装置
CN203494950U (zh) 一种法兰端板对接机
CN203730918U (zh) 一种固定液下泵扬水管的结构
CN201765948U (zh) 扁导线及组合导线揻制小s弯工具
CN203045141U (zh) 包边机侧电极随动装置
CN202088510U (zh) 螺旋压力机拉紧螺栓液压预紧装置
CN201250968Y (zh) 承插法兰装置

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: BAODING TIANWEI BAOBIAN ELECTRIC CO., LTD.

Free format text: FORMER OWNER: BAODING TIANWEI GROUP CO., LTD.

Effective date: 20131120

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 071051 BAODING, HEBEI PROVINCE TO: 071056 BAODING, HEBEI PROVINCE

TR01 Transfer of patent right

Effective date of registration: 20131120

Address after: 071056 West Road, Hebei, Baoding, No. 2222, No.

Patentee after: Baoding Tianwei Baobian Electric Co., Ltd.

Address before: 071051, Hebei City, Baoding province ginkgo Road, No. 198 Jin Di garden complex

Patentee before: Baoding Tianwei Group Co., Ltd.