CN102296962B - Adverse slope excavating construction method of large-section tunnel in water-rich tunnel section - Google Patents

Adverse slope excavating construction method of large-section tunnel in water-rich tunnel section Download PDF

Info

Publication number
CN102296962B
CN102296962B CN 201110162591 CN201110162591A CN102296962B CN 102296962 B CN102296962 B CN 102296962B CN 201110162591 CN201110162591 CN 201110162591 CN 201110162591 A CN201110162591 A CN 201110162591A CN 102296962 B CN102296962 B CN 102296962B
Authority
CN
China
Prior art keywords
tunnel
excavation
hole section
section
water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN 201110162591
Other languages
Chinese (zh)
Other versions
CN102296962A (en
Inventor
夏泽勇
李军
周垂一
侯靖
陈祥荣
杨萍
刘伯全
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hydrochina East China Engineering Corp
Original Assignee
Hydrochina East China Engineering Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hydrochina East China Engineering Corp filed Critical Hydrochina East China Engineering Corp
Priority to CN 201110162591 priority Critical patent/CN102296962B/en
Publication of CN102296962A publication Critical patent/CN102296962A/en
Application granted granted Critical
Publication of CN102296962B publication Critical patent/CN102296962B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention relates to an adverse slope excavating construction method of a large-section tunnel in a water-rich tunnel section, and aims at providing a construction method capable of orderly and automatically discharging underground gushing water. The technical scheme of the invention comprises the steps of: a, firstly, carrying out top step excavation to form a top step excavating hole section; b, carrying out low slope excavation to form a top step sloping hole section; c, setting a ponding bin; d, installing a water pump and a pumping pipe in the ponding bin; e, carrying out top step excavation on a water-rich hole section according to a temporary positive slope; and f, carrying out bottom step bottom excavation according to the reverse direction of a designed longitudinal slope of a tunnel after the top step excavation of the water-rich hole section is completed and a bottom excavated working face at the downstream side of the tunnel runs through. The invention is suitable for construction of underground projects such as water conservancy and hydropower projects, traffics, mines and the like in an underground gushing water-rich hole section.

Description

A kind of big section tunnel is in rich water hole section excavation adverse grade job practices
Technical field
The present invention relates to a kind of big section tunnel in rich water hole section excavation adverse grade job practices, be applicable to that underground constructions such as water conservancy and hydropower, traffic, mine enrich the construction of hole section at underground water burst.
Background technology
Underground construction is at underground water water burst hole section adverse grade excavation construction, not only there are constructor, device security hidden danger, and because the excavation face is subjected to influence on groundwater, cause tunnel floor boring, powder charge, slag tap and blasting efficiency reduces significantly, thereby increased the excavation activity duration, execution conditions are also comparatively abominable simultaneously.
Summary of the invention
The technical problem to be solved in the present invention is: provide a kind of big section tunnel in rich water hole section excavation adverse grade job practices at the problems referred to above, this method is safe and reliable, can flow automatically in order and discharge underground water burst,, improve construction environment to improve adverse grade water burst hole section efficiency of construction.
The technical solution adopted in the present invention is: a kind of big section tunnel may further comprise the steps in rich water hole section excavation adverse grade job practices:
A, at first in the position that is higher than tunnel design floor elevation to the tunnel excavation of topping bar, forming tops bar excavates the hole section;
B, before excavated surface enters rich water hole section, with tunnel according to ratio of slope less than 10% longitudinal gradient descending excavation, form the descending grade hole section of topping bar, it is terminal to design floor elevation with tunnel and flushes;
C, the ponding storehouse is set, in the scope of ponding storehouse, tunnel is carried out full face excavation, form the full face excavation section, its rich water hole of terminal next-door neighbour section in end one side of the descending grade hole section of topping bar;
D, water pump and drinking-water pipe are installed in described ponding storehouse, the water side of drinking-water pipe causes outside the hole;
E, according to interim along the slope to the rich water hole section excavation of topping bar, in digging process, arrange along the tunnel sidewall interim along sloping gutter, this gutter and the connection of ponding storehouse; Form the execution conditions of conventional tunnel;
F, excavation is finished and after connecting with tunnel downstream end of a year or month excavation face, be reversed getting out of a predicament or an embarrassing situation end of a year or month excavation according to tunnel design longitudinal gradient to treat to top bar rich water hole section.
As preferably, in step e, described interim ratio of slope along the slope is 0.15%~0.2%, and the tunnel height of its peak is 5~6m.
The invention has the beneficial effects as follows: the present invention is when tunnel excavation, according to landform and geology characteristic, top bar excavation section, the descending grade hole section of topping bar, full face excavation hole section and rich water hole section of construction successively, at last tunnel is reversed end of a year or month excavation, in the hole, also is furnished with the draining and the facility that draws water simultaneously.This method sequence of construction is reasonable, the underground water burst that discloses can be discharged outside the hole easily and effectively, thereby improve big section tunnel adverse grade water burst hole section efficiency of construction greatly, has improved construction environment.
Description of drawings
Fig. 1 is the layout schematic diagram of the embodiment of the invention.
Fig. 2 is the longitudinal section sectional view one of the embodiment of the invention.(excavation of topping bar)
Fig. 3 is the longitudinal section sectional view two of the embodiment of the invention.(excavation of getting out of a predicament or an embarrassing situation)
The specific embodiment
Fig. 1~Fig. 3 has shown the embodiment of the big section tunnel of the present invention in rich water hole section excavation adverse grade job practices, and its concrete construction sequence is as follows:
A, at first in the position that is higher than tunnel design floor elevation 11 to the tunnel excavation of topping bar, forming tops bar excavates hole section 1.(this moment, the excavated surface of tunnel did not also enter rich water hole section 4)
B, before excavated surface enters rich water hole section 4, with tunnel according to ratio of slope less than 10% longitudinal gradient descending excavation, form the descending grade hole section 2 of topping bar, the end of the descending grade hole section 2 of topping bar designs floor elevation 11 with tunnel and flushes.The excavation hole section 1 of promptly topping bar designs floor elevation 11 by descending grade hole section 2 descending grades to the tunnel of topping bar.(this moment, the excavated surface of tunnel did not enter rich water hole section 4 yet)
C, in end one side of the descending grade hole section 2 of topping bar ponding storehouse 5 is set, in the scope of ponding storehouse, tunnel is carried out full face excavation, form full face excavation section 3, the end of full face excavation section is close to rich water hole section 4.
D, water pump 6 and drinking-water pipe 7 are installed in described ponding storehouse 5, the water side of drinking-water pipe 7 causes outside the hole.
E, treat that the facility that draws water in the steps d forms pumpage after, according to interim along sloping i FaceTo rich water hole section 4 excavation of topping bar, in digging process, arrange along the tunnel sidewall interim along sloping gutter 8, this gutter and 5 connections of ponding storehouse.(this moment, the excavated surface of tunnel entered rich water hole section 4 fully)
General interim along sloping i FaceRatio of slope be 0.15%~0.2%, for making things convenient for mechanization supporting operation, interim along sloping i FaceThe tunnel height of peak is advisable with 5~6m.
When top bar interim disclose underground water burst along slope excavation face 9 after, can drain into voluntarily in the ponding storehouse 5 along sloping gutter 8 along interim, again by water pump 6 along drinking-water pipe 7 pump drainages to the hole, the arrow among Fig. 1 is represented water (flow) direction.
F, as shown in Figure 3, excavation is finished and after tunnel connects, according to tunnel design longitudinal gradient i whole piece hole section (promptly top bar excavation hole section 1, the descending grade hole section 2 of topping bar and rich water hole section 4) is reversed getting out of a predicament or an embarrassing situation end of a year or month excavation to treat to top bar rich water hole section.Reference numeral 10 expressions among Fig. 3 are got out of a predicament or an embarrassing situation to feel at ease and are excavated face.

Claims (2)

1. one kind big section tunnel is characterized in that may further comprise the steps in rich water hole section excavation adverse grade job practices:
A, at first in the position that is higher than tunnel design floor elevation (11) to the tunnel excavation of topping bar, forming tops bar excavates hole section (1);
B, to enter rich water hole section (4) at excavated surface preceding, with tunnel according to ratio of slope less than 10% longitudinal gradient descending excavation, form the descending grade hole section (2) of topping bar, it is terminal to design floor elevation (11) with tunnel and flushes;
C, ponding storehouse (5) is set, in the scope of ponding storehouse, tunnel is carried out full face excavation, form full face excavation section (3), its terminal next-door neighbour's rich water hole section (4) in end one side of the descending grade hole section (2) of topping bar;
D, water pump (6) and drinking-water pipe (7) are installed in described ponding storehouse (5), the water side of drinking-water pipe (7) causes outside the hole;
E, according to interim along slope (i Face) to rich water hole section (4) excavation of topping bar, in digging process, arrange temporarily along sloping gutter (8) along the tunnel sidewall, this gutter and ponding storehouse (5) connection form the execution conditions of conventional tunnel;
F, excavation is finished and after connecting with tunnel downstream end of a year or month excavation face (10), be reversed getting out of a predicament or an embarrassing situation end of a year or month excavation according to tunnel design longitudinal gradient (i) to treat to top bar rich water hole section.
2. big section tunnel according to claim 1 is characterized in that in rich water hole section excavation adverse grade job practices: among the step e, described interim along slope (i Face) ratio of slope be 0.15%~0.2%, the tunnel height of its peak is 5~6m.
CN 201110162591 2011-06-14 2011-06-14 Adverse slope excavating construction method of large-section tunnel in water-rich tunnel section Active CN102296962B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201110162591 CN102296962B (en) 2011-06-14 2011-06-14 Adverse slope excavating construction method of large-section tunnel in water-rich tunnel section

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201110162591 CN102296962B (en) 2011-06-14 2011-06-14 Adverse slope excavating construction method of large-section tunnel in water-rich tunnel section

Publications (2)

Publication Number Publication Date
CN102296962A CN102296962A (en) 2011-12-28
CN102296962B true CN102296962B (en) 2013-07-24

Family

ID=45357617

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201110162591 Active CN102296962B (en) 2011-06-14 2011-06-14 Adverse slope excavating construction method of large-section tunnel in water-rich tunnel section

Country Status (1)

Country Link
CN (1) CN102296962B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105064280A (en) * 2015-07-16 2015-11-18 中国水利水电第十四工程局有限公司 Tunnel underground river water burst blockage construction method
CN108643920A (en) * 2018-04-17 2018-10-12 贵州开磷集团股份有限公司 A kind of blast working structure and construction method for the interim ditch in tunnel
CN109555528B (en) * 2018-11-26 2019-10-11 中铁二十局集团有限公司 Pass through that high angle is inverse to rush rich water richness sand tomography tunnel excavation and method for protecting support
CN113216123B (en) * 2021-04-30 2024-03-22 中国葛洲坝集团第一工程有限公司 Gate chamber side wall karst water gushing treatment method

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2760476B2 (en) * 1994-05-19 1998-05-28 株式会社大林組 Rock tunnel excavation method
JPH08270374A (en) * 1995-03-31 1996-10-15 Hazama Gumi Ltd Blasting type tunnel construction method
CN1920254A (en) * 2006-07-27 2007-02-28 董淑练 Small pilot hole penetrated construction method when small pilot hole entering big pilot hole in two holes crossing in tunnel construction
CN100487224C (en) * 2006-10-27 2009-05-13 中铁四局集团有限公司 Rapid-construction method for rapid change of small-section into large-section tunnel

Also Published As

Publication number Publication date
CN102296962A (en) 2011-12-28

Similar Documents

Publication Publication Date Title
CN104480974B (en) Reverse seepage drain system suitable for upstream type tailings pond and upstream type tailings pond
CN104047623B (en) A kind of big across cavern excavation construction method
CN103256052B (en) Construction method for integral straight middle wall type double-arch tunnel
CN103939109B (en) The permanent shutoff inclined shaft structure of isolating with tunnel
CN106049532B (en) A kind of pipe gallery open-cut branch blocking means and its construction method
CN102979535B (en) Draining type section of jurisdiction is used in a kind of tunnel lining
CN102296962B (en) Adverse slope excavating construction method of large-section tunnel in water-rich tunnel section
CN102383437B (en) Well point positioned pumping tubular well and well point positioned pumping method
CN101949148A (en) Method for constructing artificial dug pile at reduced well point ground water level
CN104791007A (en) Water draining method for tunnel construction process of penetrating through water-rich fracture zone
CN206785398U (en) Slurry balance shield mud circulating system and slurry balance shield
CN204532364U (en) Tunneling boring rock tunnel development machine engineering method subway tunnel pressure release type liner structure
CN104389634B (en) A kind of mine vertical shaft sieve well shaft wall structure and controlled trapping method thereof
CN204551510U (en) A kind of filled-up ground catchments pressure reduction well drop and drainage structure
CN104131566A (en) Method for constructing basement foundation pit without horizontal braces
CN205591201U (en) Water treatment system is gushed to interior refuse dump
CN205954559U (en) A ditch water treatment structure that is used for large -scale sediment field of blocking
CN204370462U (en) Open-cut station water drainage of deep foundation pit system
CN105696543B (en) A kind of method that dam front row is seeped when red mud dump constructs sub- dam
CN218642794U (en) Ion adsorption type rare earth mine priming device
CN204676504U (en) The emptying maintenance structure of a kind of long tailwater tunnel group without gravity flow ejectment condition
CN104088664B (en) A kind of mine wastewater treatment method and system of upwards filling mining
CN203796274U (en) Permanent inclined shaft blocking structure isolated from tunnel
CN204899930U (en) Secretly dig leading dry out well in subway hole
CN102261082A (en) Method for controlling seepage by laying membrane for slag field in high water level area, membrane laying slag field and use method thereof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant