CN105064280A - Tunnel underground river water burst blockage construction method - Google Patents

Tunnel underground river water burst blockage construction method Download PDF

Info

Publication number
CN105064280A
CN105064280A CN201510417891.5A CN201510417891A CN105064280A CN 105064280 A CN105064280 A CN 105064280A CN 201510417891 A CN201510417891 A CN 201510417891A CN 105064280 A CN105064280 A CN 105064280A
Authority
CN
China
Prior art keywords
waterwall
water
underground river
conservancy diversion
tunnel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510417891.5A
Other languages
Chinese (zh)
Inventor
陈晓光
王来所
浦友繁
尹浩
谭剑
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinohydro Bureau 14 Co Ltd
Original Assignee
Sinohydro Bureau 14 Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinohydro Bureau 14 Co Ltd filed Critical Sinohydro Bureau 14 Co Ltd
Priority to CN201510417891.5A priority Critical patent/CN105064280A/en
Publication of CN105064280A publication Critical patent/CN105064280A/en
Pending legal-status Critical Current

Links

Landscapes

  • Revetment (AREA)

Abstract

The invention discloses a tunnel underground river water burst blockage construction method. The early drainage and the later closing are performed on the underground river water burst by using modes of a water retaining wall, mortar filling and a water closing gate sluice valve to realize the maximum control over the underground river water burst. The construction method overcomes the influence of the water burst on the concrete pouring construction to the greatest extent in the concrete construction process of tunnel with a lot of water burst, so that the concrete construction quality is improved, the construction period is guaranteed, and the water burst treatment construction cost is reduced.

Description

A kind of tunnel underground river water burst plugging construction method
Technical field
The invention belongs to tunnel engineering technical field, be specifically related to a kind of tunnel hydrous fluids underground river water burst plugging construction method.
Background technology
In the various built tunnel engineering of China, 80% harm meeting underground water in construction.Water burst is geological disaster the most common in construction of tunnel.In water burst geological disaster, especially serious with Karst water bursting.
Happen suddenly in tunnel construction a large amount of water burst, and harm is serious, not only causes equipment, personal injury, is even forced to stop work, affect the duration adversely, and difficult treatment, somewhat expensive.In increasing Inter-Basin Water Transfer Project, the buried Super-long tunnel of big cross section, hole line passes through various stratum.The seepage of construction period and water burst are great engineering geological problems.Success ground solves burst problem in construction, particularly not only water burst but also gush the problem of sand, is the key of the buried Ultra long tunnel project success or failure of big cross section.
Such as, come from cattle pen river-Dian Chi moisturizing Pumping Station water diversion engineering tunnel engineering, diversion tunnel full face excavation meets underground river, underground to during 2+483.5 pile No., and the constant water yield in underground river is more than 2m 3/ s.This is underground water rare both at home and abroad, and 2+483.5 ~ 2+018 hole, the diversion tunnel main hole section causing diversion 2# working tunnel and completed excavation construction is flooded.This plugging construction method is invented for realizing underground river water burst control.
Summary of the invention
The object of the invention is to control to realize tunnel underground river water burst, a kind of construction method being conducive to the water burst shutoff of tunnel underground river is provided.
Technical scheme of the present invention is: the mode utilizing waterwall+filled with mortar+close Water gate valve, underground river water burst is carried out drainage in early stage and the later stage is closed, and realizes the control to greatest extent to underground river water burst.
Concrete grammar is as follows:
The first step, digs mutually with one voice by underground river and diversion tunnel, meanwhile, arranges joint bar at underground river water surface curve above hole wall hoop, exposes part and welds with it after water conservancy diversion penstock installation completes, as water conservancy diversion steel pipe anchor point;
Second step, water conservancy diversion penstock installation: install gate valve at water conservancy diversion steel pipe water export, fill a pressure meter at gate valve upstream side, and connect by a fine steel tube and cause diversion tunnel;
3rd step, build waterwall by laying bricks or stones: after water conservancy diversion penstock installation completes, inside and outside water conservancy diversion steel pipe, termination, both sides builds two standard common brick waterwall respectively by laying bricks or stones, first in-built concrete woven bag is jettisoninged bottom underground river, water level is made to increase, until water conservancy diversion steel pipe 1/3 section overcurrent, stopping is jettisoninged, start to build waterwall by laying bricks or stones on volume bag, first inner side waterwall is built by laying bricks or stones, space between water conservancy diversion steel pipe and underground river solution cavity is filled up by inner side waterwall, after inner side waterwall has been built by laying bricks or stones, carry out outside waterwall to build by laying bricks or stones, method is identical with inner side waterwall, fill concrete delivery port and the backfill grouting mouth of pipe is reserved on waterwall top, after 24h built by laying bricks or stones by waterwall, concrete backfill is carried out to the space between twice waterwall, after concrete backfill completes 24h, carry out backfill grouting,
4th step, closes valve and closes water: valve is implemented by 1/3 stroke, 2/3 stroke, complete shut-down 3 steps, and after front stroke completes, interval 10min carries out next stroke, observed pressure meter reading simultaneously, after gate valve complete shut-down, pressure gauge reading is stabilized in 0.35MPa, is less than blocking concrete unstability water pressure;
Finally, structural concrete lining construction is carried out.
Described two standard common brick waterwalls are made up of two-layer common brick therebetween filled with mortar.
Construction method of the present invention, ensure that and exist in the tunnel concrete work progress of a large amount of water burst, overcome the impact of water burst on concrete pouring construction to greatest extent, improve concrete construction quality, ensure that the construction period, reduce Tunnel gushing treatment construction cost.
Accompanying drawing explanation
Fig. 1 is tunnel underground river of the present invention water burst plugging construction method floor map.
In figure: 1-diversion tunnel, 2-gate valve, 3-waterwall, 4-water conservancy diversion steel pipe, 5-joint bar, 6-fills mortar, and 7-digs, 8-fine steel tube.
Detailed description of the invention
The first step, with one voice digs 7 for 3.5m × 2m, so that mounted valve, does not does not occupy diversion tunnel concrete lining size after valve installation by underground river and diversion tunnel 1 phase.Meanwhile, arrange joint bar 5 at underground river water surface curve above hole wall hoop, joint bar is Φ 25mm, and slotting L=2m enters rock 1.7m, an array pitch 1.5m, exposes part and welds with it after water conservancy diversion penstock installation completes, as water conservancy diversion steel pipe anchor point.
Second step, water conservancy diversion penstock installation, water conservancy diversion steel pipe 4 adopts internal diameter 600mm, wall thickness 4mm steel pipe, and the long 7.5m of water conservancy diversion steel pipe is formed by connecting by the single-unit steel pipe flange of long 1.5m, installs gate valve 2 at water conservancy diversion steel pipe water export.Water conservancy diversion steel pipe distance from bottom underground river water surface curve 30cm, water conservancy diversion steel pipe merogenesis is transported to installation work face, docks after in place, reinforces.For monitoring underground river water pressure, install a pressure meter additional at gate valve upstream side, pressure gage measuring range is 0.6MPa, is connect and causes diversion tunnel, be convenient to observed reading by the fine steel tube 8 of a 10mm.
3rd step, builds waterwall 3 by laying bricks or stones, and after water conservancy diversion penstock installation completes, inside and outside water conservancy diversion steel pipe, termination, both sides builds two standard common brick waterwall respectively by laying bricks or stones.Waterwall is made up of the 24 common brick walls of twice interval 30cm, space between twice brick wall adopts M30 slurry placement 6, first concrete for in-built C30 woven bag is jettisoninged bottom underground river, water level is made to increase, until water conservancy diversion steel pipe 1/3 section overcurrent, stop jettisoninging, start to build waterwall by laying bricks or stones on volume bag, first build inner side waterwall by laying bricks or stones, the space between water conservancy diversion steel pipe and underground river solution cavity is filled up by inner side waterwall.After inner side waterwall has been built by laying bricks or stones, carry out outside waterwall and build by laying bricks or stones, method is identical with inner side waterwall.But fill concrete delivery port and the backfill grouting mouth of pipe is reserved on waterwall top.
After 24h built by laying bricks or stones by waterwall, concrete backfill is carried out in the space between starting twice waterwall, and fill concrete grade is C30/38, and concrete adopts pumping to put in storage.After concrete backfill completes 24h, carry out backfill grouting.
4th step, carries out pass valve and closes water, and valve is implemented by 1/3 stroke, 2/3 stroke, complete shut-down 3 steps.After front stroke completes, interval 10min carries out next stroke.Observed pressure meter reading simultaneously, after gate valve complete shut-down, pressure gauge reading is stabilized in 0.35MPa, is less than blocking concrete unstability water pressure.
Finally, structural concrete lining construction is carried out.

Claims (4)

1. a tunnel underground river water burst plugging construction method, is characterized in that carrying out according to the following steps:
The first step, digs mutually with one voice by underground river and diversion tunnel, meanwhile, arranges joint bar at underground river water surface curve above hole wall hoop, exposes part and welds with it after water conservancy diversion penstock installation completes, as water conservancy diversion steel pipe anchor point;
Second step, water conservancy diversion penstock installation: install gate valve at water conservancy diversion steel pipe water export, fill a pressure meter at gate valve upstream side, and connect by a fine steel tube and cause diversion tunnel;
3rd step, build waterwall by laying bricks or stones: after water conservancy diversion penstock installation completes, inside and outside water conservancy diversion steel pipe, termination, both sides builds two standard common brick waterwall respectively by laying bricks or stones, first in-built concrete woven bag is jettisoninged bottom underground river, water level is made to increase, until water conservancy diversion steel pipe 1/3 section overcurrent, stopping is jettisoninged, start to build waterwall by laying bricks or stones on volume bag, first inner side waterwall is built by laying bricks or stones, space between water conservancy diversion steel pipe and underground river solution cavity is filled up by inner side waterwall, after inner side waterwall has been built by laying bricks or stones, carry out outside waterwall to build by laying bricks or stones, method is identical with inner side waterwall, fill concrete delivery port and the backfill grouting mouth of pipe is reserved on waterwall top, after 24h built by laying bricks or stones by waterwall, concrete backfill is carried out to the space between twice waterwall, after concrete backfill completes 24h, carry out backfill grouting,
4th step, closes valve and closes water: valve is implemented by 1/3 stroke, 2/3 stroke, complete shut-down 3 steps, and after front stroke completes, interval 10min carries out next stroke, observed pressure meter reading simultaneously, after gate valve complete shut-down, pressure gauge reading is stabilized in 0.35MPa, is less than blocking concrete unstability water pressure;
Finally, structural concrete lining construction is carried out.
2. tunnel underground river according to claim 1 water burst plugging construction method, is characterized in that
Described two standard common brick waterwalls are made up of two-layer 24 common brick centre M30 filled with mortar, twice waterwall interval 30cm.
3. tunnel underground river according to claim 1 water burst plugging construction method, is characterized in that described joint bar is Φ 25mm, long 2m, inserts rock 1.7m, an array pitch 1.5m.
4. tunnel underground river according to claim 1 water burst plugging construction method, it is characterized in that water conservancy diversion steel pipe adopts internal diameter 600mm, wall thickness 4mm, long 7.5m, connected and composed by the single-unit steel pipe flange of long 1.5m.
CN201510417891.5A 2015-07-16 2015-07-16 Tunnel underground river water burst blockage construction method Pending CN105064280A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510417891.5A CN105064280A (en) 2015-07-16 2015-07-16 Tunnel underground river water burst blockage construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510417891.5A CN105064280A (en) 2015-07-16 2015-07-16 Tunnel underground river water burst blockage construction method

Publications (1)

Publication Number Publication Date
CN105064280A true CN105064280A (en) 2015-11-18

Family

ID=54493767

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510417891.5A Pending CN105064280A (en) 2015-07-16 2015-07-16 Tunnel underground river water burst blockage construction method

Country Status (1)

Country Link
CN (1) CN105064280A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105821894A (en) * 2016-01-22 2016-08-03 中国水电基础局有限公司 Processing method for large karst cave underground river with water gushing and structure thereof
CN109653171A (en) * 2018-12-17 2019-04-19 中冶沈勘秦皇岛工程设计研究总院有限公司 Tailings Dam water discharge tunnel band water seal blocking method
CN112031811A (en) * 2020-07-22 2020-12-04 济南力稳岩土工程有限公司 System and method for blocking cliff through water burst and grouting
CN112282784A (en) * 2020-10-15 2021-01-29 浙江省水利水电勘测设计院 Construction method for tunnel crossing underpass close to karst cave underground river
CN113279429A (en) * 2021-07-01 2021-08-20 中国葛洲坝集团生态环境工程有限公司 Plugging structure and plugging method for underground diversion operation
CN114483185A (en) * 2022-02-17 2022-05-13 中铁二院工程集团有限责任公司 Overflow-prevention structure for operating period of diffusion-accumulation inclined shaft and construction method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS61155507A (en) * 1984-12-26 1986-07-15 Hiroaki Kojima Water storage system
CN102174818A (en) * 2011-03-25 2011-09-07 湖南宏禹水利水电岩土工程有限公司 Controlled impermeable leaking stoppage grout-extruding water-stopping technology of strong water permeable stratum of quaternary system
CN102296962A (en) * 2011-06-14 2011-12-28 中国水电顾问集团华东勘测设计研究院 Adverse slope excavating construction method of large-section tunnel in water-rich tunnel section
CN103527202A (en) * 2012-07-27 2014-01-22 中国有色金属工业第六冶金建设有限公司 Method for constructing tunnel under complicated geological conditions
CN104612113A (en) * 2014-12-29 2015-05-13 中国电建集团贵阳勘测设计研究院有限公司 Karstic water treating method for diversion tunnel

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS61155507A (en) * 1984-12-26 1986-07-15 Hiroaki Kojima Water storage system
CN102174818A (en) * 2011-03-25 2011-09-07 湖南宏禹水利水电岩土工程有限公司 Controlled impermeable leaking stoppage grout-extruding water-stopping technology of strong water permeable stratum of quaternary system
CN102296962A (en) * 2011-06-14 2011-12-28 中国水电顾问集团华东勘测设计研究院 Adverse slope excavating construction method of large-section tunnel in water-rich tunnel section
CN103527202A (en) * 2012-07-27 2014-01-22 中国有色金属工业第六冶金建设有限公司 Method for constructing tunnel under complicated geological conditions
CN104612113A (en) * 2014-12-29 2015-05-13 中国电建集团贵阳勘测设计研究院有限公司 Karstic water treating method for diversion tunnel

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
张宝忠等: "干河泵站工程引水隧洞暗河处理", 《云南水力发电》 *

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105821894A (en) * 2016-01-22 2016-08-03 中国水电基础局有限公司 Processing method for large karst cave underground river with water gushing and structure thereof
CN109653171A (en) * 2018-12-17 2019-04-19 中冶沈勘秦皇岛工程设计研究总院有限公司 Tailings Dam water discharge tunnel band water seal blocking method
CN112031811A (en) * 2020-07-22 2020-12-04 济南力稳岩土工程有限公司 System and method for blocking cliff through water burst and grouting
CN112282784A (en) * 2020-10-15 2021-01-29 浙江省水利水电勘测设计院 Construction method for tunnel crossing underpass close to karst cave underground river
CN113279429A (en) * 2021-07-01 2021-08-20 中国葛洲坝集团生态环境工程有限公司 Plugging structure and plugging method for underground diversion operation
CN114483185A (en) * 2022-02-17 2022-05-13 中铁二院工程集团有限责任公司 Overflow-prevention structure for operating period of diffusion-accumulation inclined shaft and construction method
CN114483185B (en) * 2022-02-17 2022-09-13 中铁二院工程集团有限责任公司 Overflow-prevention structure for operating period of diffusion-accumulation inclined shaft and construction method

Similar Documents

Publication Publication Date Title
CN105064280A (en) Tunnel underground river water burst blockage construction method
CN105201448B (en) Block water slip casting method for blocking in a kind of high-pressure high-flow water gushing channelway
CN103526766B (en) Method for plugging relief well of deep foundation pit
CN103277120A (en) Post-unfreezing water burst prevention method of non-full-depth freezing vertical shaft
CN103334770A (en) Construction method of superhigh water pressure water-affluent crushed zones of long-large counter-slope tunnels
CN103899321A (en) Jacking pulling combined rectangular jacking pipe tunnel construction method
CN201310362Y (en) Installing device of high pressure water burst drill hole bore pipe
CN106121722A (en) A kind of method quickly constructing fire dam
CN103362117A (en) Full-section grouting method for grouting section
CN202787334U (en) Sealing structure of deep well casing used during tunnel construction
CN102051879B (en) Process for constructing soil anchor
CN101793154A (en) Method for grouting for stopping up water by using geological parameters of tunnel surrounding rocks and setting relief holes
CN205422815U (en) Big flood underground mine tunnel waterwall
CN104895118A (en) Underground diaphragm wall internal corner position piping plug structure and grouting processing method thereof
CN114109442B (en) Tunnel karst crushing belt sliding collapse half-section curtain progressive grouting reinforcement treatment method
CN106837340B (en) The construction method of wall clearance grouting waterproof and reinforcing shaft wall structure under frost wall protection
CN206616565U (en) Door font double-row pile and double high-pressed spin-spewing water-stopping curtain combined retaining structure
CN103114553B (en) Earth and rockfill dam piping burst field test method
CN204959787U (en) Novel tower crane combination formula basis
CN102174818A (en) Controlled impermeable leaking stoppage grout-extruding water-stopping technology of strong water permeable stratum of quaternary system
CN105605335A (en) Large-caliber prestressed steel cylinder concrete pipe for jacking construction
CN113266417A (en) Construction method of karst cave pile foundation
CN206157860U (en) Drainage pipeline
CN204753654U (en) Underground continuous wall reentrant corner position piping block structure
CN206722881U (en) A kind of underground mine roadway grouting wall for grouting structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20151118