CN102268993A - 一种高液限土中隧道开挖方法 - Google Patents

一种高液限土中隧道开挖方法 Download PDF

Info

Publication number
CN102268993A
CN102268993A CN201110181729XA CN201110181729A CN102268993A CN 102268993 A CN102268993 A CN 102268993A CN 201110181729X A CN201110181729X A CN 201110181729XA CN 201110181729 A CN201110181729 A CN 201110181729A CN 102268993 A CN102268993 A CN 102268993A
Authority
CN
China
Prior art keywords
excavation
tunnel
excavating
concrete
carried out
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201110181729XA
Other languages
English (en)
Other versions
CN102268993B (zh
Inventor
曹亮宏
吴定略
陈培冲
吕世明
卢自立
孙江涛
徐志元
徐光波
曹志月
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Changda Highway Engineering Co Ltd
Original Assignee
Guangdong Changda Highway Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Changda Highway Engineering Co Ltd filed Critical Guangdong Changda Highway Engineering Co Ltd
Priority to CN 201110181729 priority Critical patent/CN102268993B/zh
Publication of CN102268993A publication Critical patent/CN102268993A/zh
Application granted granted Critical
Publication of CN102268993B publication Critical patent/CN102268993B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

本发明公开了一种高液限土中隧道开挖方法,包括以下步骤:A、对隧道的左侧上部进行开挖;B、对上述段进行拱顶的初期支护;C、对隧道的右侧上部进行开挖;D、完成拱顶的初期支护;E、对隧道的下部进行开挖:分为下部左侧部分、核心土部分、下部右侧部分,首先开挖下部左侧部分,然后开挖下部右侧部分,最后对核心土部分进行开挖;F、对仰拱绑扎钢筋,安装模板,浇注C25混凝土,完成仰拱二衬,回填混凝土。本发明主要依赖挖掘机代替人工手持风洞挖掘工具开挖,辅助以人工修饰,大大提高了施工效率;仰供开挖增加了中间核心土部分,保证了在封闭成环过程中围岩的稳定,施工安全性大大提高;本发明的应用还提高了施工的效率和降低了施工成本。

Description

一种高液限土中隧道开挖方法
技术领域
本发明涉及一种高液限土中隧道开挖方法,具体是一种对CRD开挖方法的改进。 
背景技术
CRD法开挖主要是采用人工开挖,施工时除非遇到孤石等特殊情况,否则严禁爆破。应使用钢管脚手架搭设施工平台,人工手持风动挖掘工具开挖,挖掘机扒渣,自卸车出渣。隧道开挖分左右导坑上下台阶施工,分部开挖间距3-5m,实际施工中根据具体情况调整。其施工工艺如下:如图2和图3所示,(1)开挖Ⅰ(①)部分,对掌子面进行喷射C25混凝土防护,然后架工字钢,打锚杆,再喷射钢纤维混凝土进行初期支护。架工字钢同时设置临时仰拱和中隔墙,临时仰拱中埋设钢支撑,并施作10cm厚25号喷射砼;中隔墙结构主要由钢支撑组成,钢支撑间设φ8钢筋网,喷射厚20cm的25号砼,必要时使用临时锚杆对导坑围岩进行加固;(2)开挖Ⅱ(②)部分,同上对掌子面进行喷射C25混凝土防护,然后架工字钢,打锚杆,再喷射钢纤维混凝土进行初期支护。架工字钢同时设置中隔墙结构,并对中隔墙进行挂网喷锚支护;(3)开挖Ⅲ(③)部分,同上对掌子面进行喷射C25混凝土防护,然后架工字钢,打锚杆,再喷射钢纤维混凝土进行初期支护。工字钢同时设置临时仰拱并施作10cm厚25号喷射砼;(4)开挖Ⅳ(④)部分,同上对掌子面进行喷射C25混凝土防护,然后架工字钢,打锚杆,再喷射钢纤维混凝土进行初期支护。 
    上述隧道前期进洞一直采用CRD法施工,主要存在以下几个问题:(1)工艺较简单,但循环过多,且要求人工开挖,严重影响施工进度;(2)按照隧道技术交底要求,掌子面距离仰拱不能超过12m,全断面开挖完成10m 左右就要施做仰拱,这就要求必须提前完成仰拱的浇注,而仰拱一旦浇注,出渣自卸车无法进入掌子面,即进尺无法进行,影响开挖进度;(3)即使挖掘机、自卸车可以到达掌子面,由于不可能使仰拱紧跟掌子面浇注,机械设备不可避免的直接碾压初衬,这对初衬无疑是一种破坏,这是隧道施工最忌讳的。 
发明内容
为了克服上述之不足,本发明提供一种高液限土中隧道开挖方法,该方法通过对CRD开挖方法的改进,以提高施工的效率和降低施工成本。 
为解决上述技术问题,本发明所采用以下的技术方案: 
一种高液限土中隧道开挖方法,包括以下步骤:
A、对隧道的左侧上部进行开挖:以挖掘机为主并配合人工开挖的开挖方式,开挖一段距离后,立即对掌子面及边墙围岩进行喷射混凝土防护,然后对中隔墙进行喷锚支护;
B、对上述段进行工字钢的安装,然后对拱顶部分打锚杆注浆,喷射钢纤维混凝土,完成拱顶的初期支护;
C、对隧道的右侧上部进行开挖,以挖掘机为主并配合人工开挖的开挖方式,开挖一段距离后,立即对掌子面及边墙围岩进行喷射混凝土防护,然后对中隔墙进行喷锚支护;
D、按照步骤B的方法,完成拱顶的初期支护;
E、对隧道的下部进行开挖:将传统的下部左侧和下部右侧两部分开挖的方式,改成下部左侧部分、核心土部分、下部右侧部分,三部分开挖的方式,首先开挖下部左侧部分,然后开挖下部右侧部分,最后对核心土部分进行开挖,开挖核心土部分时,分左右两部分,其间依然设中隔墙;上述各部分开挖都是以挖掘机为主并配合人工开挖的开挖方式,开挖一段距离后,立即对掌子面及边墙围岩进行喷射混凝土防护,然后对中隔墙进行喷锚支护,喷射混凝土防护,并完成对仰拱初期支护;
F、对仰拱绑扎钢筋,安装模板,浇注C25混凝土,完成仰拱二衬,回填混凝土。
   所述步骤E中,开挖处距离掌子面的距离为18米。 
   所述步骤F中,浇注过程中所用的混凝土为C25混凝土;回填过程中所用的混凝土为C10混凝土。 
本发明的有益效果在于:由于本发明在保持原有CRD设立中隔墙等辅助实物减少单次开挖量等优点的基础上,对CRD开挖方法作了改进后还具有以下特点:改进后的CRD法开挖主要依赖挖掘机代替人工手持风洞挖掘工具开挖;辅助以人工修饰,大大提高了施工效率;改进后的CRD法扩大了Ⅰ、Ⅲ部分的横向面积,更有利于开挖;仰供开挖增加了中间核心土部分,保证了在封闭成环过程中围岩的稳定,施工安全性大大提高。 
附图说明
下面结合附图和具体实施方式对本发明作进一步详细说明: 
图1为本发明的施工示意图;
图2为传统CRD开挖方法的开挖施工示意图;
图3为图2所示的侧视图。
具体实施方式
如图1所示,一种高液限土中隧道开挖方法,包括以下步骤: 
A、挖掘机辅以人工开挖边墙以上部分围岩,仍需设置中隔墙,开挖时先进行左侧上部Ⅰ的开挖,完成后立即进行喷射混凝土防护掌子面及开挖的新鲜围岩,对中隔墙进行喷锚支护;
B、对左侧上部Ⅰ部分进行工字钢的安装,然后打锚杆注浆,喷射钢纤维混凝土,完成Ⅰ部分拱顶的初期支护;
C、对隧道的右侧上部Ⅲ进行开挖,以挖掘机为主并配合人工开挖的开挖方式,开挖一段距离后,立即对掌子面及边墙围岩进行喷射混凝土防护,然后对中隔墙进行喷锚支护;
D、按照步骤B的方法,架设工字钢,打锚杆注浆,喷射钢纤维混凝土,完成右侧上部Ⅲ的初期支护;
E、在距离掌子面18m左右进行下部的开挖,改进后的仰供部分开挖将原来的下部左侧和下部右侧的部分分成三部分开挖,分别为下部左侧Ⅱ、核心土V、下部右侧Ⅳ;先以挖掘机配合人工开挖下部左侧Ⅱ,喷射混凝土防护,架设工字钢,打锚杆注浆,喷射钢纤维混凝土,完成下部左侧Ⅱ初支;再开挖下部右侧Ⅳ,喷射混凝土防护,架设工字钢,打锚杆注浆,喷射钢纤维混凝土,完成下部右侧Ⅳ初期支护;最后开挖中间核心土V的部分,喷射混凝土防护,架设工字钢,打锚杆注浆,喷射钢纤维混凝土,完成核心土部分初期支护;
F、仰供绑扎钢筋,安装模板,浇注C25混凝土,完成仰供二衬,回填C10混凝土。
  
对本发明的实验和监测,并与传统的CRD开挖方法相比较,其结果如下:
    通过监测可知,次步隧道运用CRD法施工时左洞LK132+834、LK132+842断面拱顶下沉本周累计值较小,本周累计最大值为0.1mm,拱顶下沉平均位移速率均不大于0.15mm/d;在运用改进后CRD法施工时次步隧道左洞LK132+874断面本周周边位移累计最大值为0.87mm,各测线平均位移速率均不大于0.2mm/d。
   通过对周边位移量的监测数据得知,次步隧道运用CRD法施工时左洞LK132+834和LK132+842断面周边位移累计最大值为0.25mm,周边位移平均位移速率均不大于0.1mm/d;次步隧道运用改进后的CRD法施工时左洞LK132+874断面本周周边位移累计最大值为0.87mm,各测线平均位移速率均不大于0.2mm/d。 
通过对两份监测报告的比较分析来看,改进后的CRD法开挖断面拱顶下沉量和周边位移略有增大,但仍能满足施工设计要求。 
采用改进后的CRD法进行隧道的洞身开挖后,节约C20喷射混凝土828m3、6.5钢筋网10.076t、22药卷式锚杆32223m、临时支护I18钢拱架384.7t,合计节约费用约5619634元,比原设计节约了将近3/4。大大降低了隧道造价。 

Claims (3)

1.一种高液限土中隧道开挖方法,其特征在于:包括以下步骤:
A、对隧道的左侧上部进行开挖:以挖掘机为主并配合人工开挖的开挖方式,开挖一段距离后,立即对掌子面及边墙围岩进行喷射混凝土防护,然后对中隔墙进行喷锚支护;
B、对上述段进行工字钢的安装,然后对拱顶部分打锚杆注浆,喷射钢纤维混凝土,完成拱顶的初期支护;
C、对隧道的右侧上部进行开挖,以挖掘机为主并配合人工开挖的开挖方式,开挖一段距离后,立即对掌子面及边墙围岩进行喷射混凝土防护,然后对中隔墙进行喷锚支护;
D、按照步骤B的方法,完成拱顶的初期支护;
E、对隧道的下部进行开挖:将传统的下部左侧和下部右侧两部分开挖的方式,改成下部左侧部分、核心土部分、下部右侧部分,三部分开挖的方式,首先开挖下部左侧部分,然后开挖下部右侧部分,最后对核心土部分进行开挖,开挖核心土部分时,分左右两部分,其间依然设中隔墙;上述各部分开挖都是以挖掘机为主并配合人工开挖的开挖方式,开挖一段距离后,立即对掌子面及边墙围岩进行喷射混凝土防护,然后对中隔墙进行喷锚支护,喷射混凝土防护,并完成对仰拱初期支护;
F、对仰拱绑扎钢筋,安装模板,浇注混凝土,完成仰拱二衬,回填混凝土。
2.根据权利要求1所述的高液限土中隧道开挖方法,其特征在于:所述步骤E中,开挖处距离掌子面的距离为18米。
3.根据权利要求1所述的高液限土中隧道开挖方法,其特征在于:所述步骤F中,浇注过程中所用的混凝土为C25混凝土;回填过程中所用的混凝土为C10混凝土。
CN 201110181729 2011-06-30 2011-06-30 一种高液限土中隧道开挖方法 Active CN102268993B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201110181729 CN102268993B (zh) 2011-06-30 2011-06-30 一种高液限土中隧道开挖方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201110181729 CN102268993B (zh) 2011-06-30 2011-06-30 一种高液限土中隧道开挖方法

Publications (2)

Publication Number Publication Date
CN102268993A true CN102268993A (zh) 2011-12-07
CN102268993B CN102268993B (zh) 2013-10-23

Family

ID=45051418

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201110181729 Active CN102268993B (zh) 2011-06-30 2011-06-30 一种高液限土中隧道开挖方法

Country Status (1)

Country Link
CN (1) CN102268993B (zh)

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102758638A (zh) * 2012-07-19 2012-10-31 中铁十六局集团有限公司 一种crd仰拱施工方法
CN103775092A (zh) * 2014-01-09 2014-05-07 长业建设集团有限公司 隧道浅埋暗挖预留核心土改良crd施工工法
CN104533465A (zh) * 2015-01-14 2015-04-22 中南大学 隧道施工中的临时支护结构
CN107060825A (zh) * 2017-05-04 2017-08-18 山东省交通规划设计院 一种应用于ⅲ级围岩的单洞四车道隧道分部协调施工方法
CN107060771A (zh) * 2016-12-28 2017-08-18 广东省长大公路工程有限公司 中短隧道单向出洞开挖方法
CN107060773A (zh) * 2017-04-28 2017-08-18 广东省长大公路工程有限公司 一种静力爆破预裂隔震的地下硐室钻爆法减震开挖方法
CN107218064A (zh) * 2017-07-19 2017-09-29 北京建工土木工程有限公司 一种大断面隧道拆换撑及二衬施工方法
CN107489433A (zh) * 2017-06-28 2017-12-19 厦门理工学院 一种隧道crd工法防渗漏结构及防渗漏方法
CN108035733A (zh) * 2017-11-01 2018-05-15 中铁四局集团有限公司 一种岩质超大断面隧道钢架岩墙组合竖撑分部开挖方法
CN109026029A (zh) * 2018-10-09 2018-12-18 中建地下空间有限公司 一种适用于破碎围岩隧道开挖支护的施工方法
CN109882186A (zh) * 2019-03-25 2019-06-14 长安大学 一种公路隧道的洞口结构及隧道的单向出洞方法
CN110821502A (zh) * 2019-11-29 2020-02-21 中铁隧道局集团有限公司 一种软弱围岩大跨山岭隧道进洞口段新型施工方法

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE4412880A1 (de) * 1994-04-14 1995-10-19 Friedrich Wassermann Bauuntern Verfahren zum Auffahren eines unterirdischen Hohlraumes
JPH08170484A (ja) * 1994-12-19 1996-07-02 Shimizu Corp 大断面トンネルの構築方法
CN101666232A (zh) * 2009-09-27 2010-03-10 中铁四局集团有限公司 超大断面隧道六部开挖的施工方法
CN201738932U (zh) * 2010-08-09 2011-02-09 中铁第一勘察设计院集团有限公司 一种特大断面黄土隧道的支护结构
CN102042019A (zh) * 2010-11-11 2011-05-04 中铁十三局集团第四工程有限公司 浅埋大跨软塑粘土隧道两台阶五步开挖的施工方法

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE4412880A1 (de) * 1994-04-14 1995-10-19 Friedrich Wassermann Bauuntern Verfahren zum Auffahren eines unterirdischen Hohlraumes
JPH08170484A (ja) * 1994-12-19 1996-07-02 Shimizu Corp 大断面トンネルの構築方法
CN101666232A (zh) * 2009-09-27 2010-03-10 中铁四局集团有限公司 超大断面隧道六部开挖的施工方法
CN201738932U (zh) * 2010-08-09 2011-02-09 中铁第一勘察设计院集团有限公司 一种特大断面黄土隧道的支护结构
CN102042019A (zh) * 2010-11-11 2011-05-04 中铁十三局集团第四工程有限公司 浅埋大跨软塑粘土隧道两台阶五步开挖的施工方法

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
吴荣锋: "隧道洞口施工技术", 《铁道工程学报》, no. 11, 15 November 2008 (2008-11-15) *
曹均念 等: "隆百高速公路隧道Ⅴ级围岩开挖施工方法探讨", 《黑龙江科技信息》, no. 34, 5 December 2008 (2008-12-05) *

Cited By (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102758638B (zh) * 2012-07-19 2014-12-10 中铁十六局集团地铁工程有限公司 一种crd仰拱施工方法
CN102758638A (zh) * 2012-07-19 2012-10-31 中铁十六局集团有限公司 一种crd仰拱施工方法
CN103775092A (zh) * 2014-01-09 2014-05-07 长业建设集团有限公司 隧道浅埋暗挖预留核心土改良crd施工工法
CN103775092B (zh) * 2014-01-09 2016-01-20 长业建设集团有限公司 隧道浅埋暗挖预留核心土改良crd施工工法
CN104533465A (zh) * 2015-01-14 2015-04-22 中南大学 隧道施工中的临时支护结构
CN107060771A (zh) * 2016-12-28 2017-08-18 广东省长大公路工程有限公司 中短隧道单向出洞开挖方法
CN107060773A (zh) * 2017-04-28 2017-08-18 广东省长大公路工程有限公司 一种静力爆破预裂隔震的地下硐室钻爆法减震开挖方法
CN107060825A (zh) * 2017-05-04 2017-08-18 山东省交通规划设计院 一种应用于ⅲ级围岩的单洞四车道隧道分部协调施工方法
CN107060825B (zh) * 2017-05-04 2024-02-02 山东省交通规划设计院 一种应用于ⅲ级围岩的单洞四车道隧道分部协调施工方法
CN107489433B (zh) * 2017-06-28 2023-05-23 厦门理工学院 一种隧道crd工法防渗漏结构及防渗漏方法
CN107489433A (zh) * 2017-06-28 2017-12-19 厦门理工学院 一种隧道crd工法防渗漏结构及防渗漏方法
CN107218064A (zh) * 2017-07-19 2017-09-29 北京建工土木工程有限公司 一种大断面隧道拆换撑及二衬施工方法
CN108035733B (zh) * 2017-11-01 2019-10-25 中铁四局集团有限公司 一种岩质超大断面隧道钢架岩墙组合竖撑分部开挖方法
CN108035733A (zh) * 2017-11-01 2018-05-15 中铁四局集团有限公司 一种岩质超大断面隧道钢架岩墙组合竖撑分部开挖方法
CN109026029A (zh) * 2018-10-09 2018-12-18 中建地下空间有限公司 一种适用于破碎围岩隧道开挖支护的施工方法
CN109882186A (zh) * 2019-03-25 2019-06-14 长安大学 一种公路隧道的洞口结构及隧道的单向出洞方法
CN110821502A (zh) * 2019-11-29 2020-02-21 中铁隧道局集团有限公司 一种软弱围岩大跨山岭隧道进洞口段新型施工方法

Also Published As

Publication number Publication date
CN102268993B (zh) 2013-10-23

Similar Documents

Publication Publication Date Title
CN102268993B (zh) 一种高液限土中隧道开挖方法
CN101349064B (zh) 软弱岩石地质条件下水电站调压室竖井的施工方法
CN102562099B (zh) 黄土隧道双排小导管快速进洞施工方法
CN110017144B (zh) 一种考虑基底加固处理的黄土隧道三台阶施工方法
CN102182472B (zh) 隧道塌方空腔的回填修复方法
CN103696784B (zh) 一种浅埋大跨隧道下穿建构筑物的大直径长管幕施工方法
CN102926757A (zh) 山岭软弱大跨隧道两台阶四步开挖支护的施工方法
CN113153308B (zh) 双联拱隧道塌方段施工方法
CN106246201A (zh) 小型溶洞位于开挖隧道四周时隧道的开挖与溶洞处理方法
CN102373930A (zh) 一种软弱围岩大断面连拱隧道的快速施工方法
CN102305077A (zh) 一种大断面连拱隧道的快速施工方法
CN102345460A (zh) 一种浅埋大断面黄土隧道沉降控制方法
CN103628885A (zh) 一种超浅埋隧道出洞盖挖施工方法
CN102505704A (zh) 软弱地质竖井中大型沉井施工方法
CN101539021B (zh) 公路隧道开挖方法
CN102966365B (zh) 新型的风桥施工方法
CN102678126A (zh) 山岭隧道软弱围岩破碎带或浅埋偏压地段的开挖方法
CN102400694A (zh) 盾构隧道与矿山法隧道结合部的加固方法
CN106837341B (zh) 一种地铁暗挖施工用竖井井壁的施工方法
CN110469341A (zh) 一种地铁暗挖车站装配与浇筑组合集成结构及施工方法
CN205895242U (zh) 一种小角度交叉口隧道结构
CN110230497A (zh) 一种线隧道正洞身双侧壁导坑施工方法
CN109667587A (zh) 采用预制装配仰拱的钻爆法隧道结构
CN111472801A (zh) 浅埋暗挖排水廊道下穿既有线的施工方法
CN104141500A (zh) 一种板结砂砾石地层洞室施工方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant