CN102071813B - Method for constructing underground garage under old building - Google Patents

Method for constructing underground garage under old building Download PDF

Info

Publication number
CN102071813B
CN102071813B CN2010105641418A CN201010564141A CN102071813B CN 102071813 B CN102071813 B CN 102071813B CN 2010105641418 A CN2010105641418 A CN 2010105641418A CN 201010564141 A CN201010564141 A CN 201010564141A CN 102071813 B CN102071813 B CN 102071813B
Authority
CN
China
Prior art keywords
building
underground
wall
ground
crossbeam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN2010105641418A
Other languages
Chinese (zh)
Other versions
CN102071813A (en
Inventor
潘金龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Geotechnical Technology Co ltd
Original Assignee
HANGZHOU GEOTECHNICAL ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HANGZHOU GEOTECHNICAL ENGINEERING Co Ltd filed Critical HANGZHOU GEOTECHNICAL ENGINEERING Co Ltd
Priority to CN2010105641418A priority Critical patent/CN102071813B/en
Publication of CN102071813A publication Critical patent/CN102071813A/en
Application granted granted Critical
Publication of CN102071813B publication Critical patent/CN102071813B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Abstract

The invention relates to a method for constructing an underground garage, which has the characteristics that: structural stability of the original building, high construction speed and low cost are guaranteed. According to a technical scheme, the method for constructing the underground garage under the old building is characterized by comprising the following steps that: a, an underground diaphragm wall or a sheet-pile wall is poured at a position which is at least 1m away from an exterior wall around the building; b, a group of cross beams are poured at the foundation at the bottom of an overhead layer of the building, and the cross beams are integrally connected with foundation soil, the underground diaphragm wall or the sheet-pile wall to support the building; c, underground space is dug below the foundation soil of the building, an entire plate foundation layer is poured at the bottom of the underground space, and the entire plate foundation with underground piles and the underground diaphragm wall or the sheet-pile wall are integrally connected; d, a part of the underground piles are cut off between the foundation soil and the entire plate foundation and the rest underground piles are reinforced; and e, a slope is arranged on the ground and the slope is communicated with the underground space to be served as a passage for entrance and exit of vehicles.

Description

A kind of method of under old building, building underground garage
Technical field
The present invention relates to a kind of job practices, especially under old building, build the method for underground garage.
Background technology
Along with the development of society, people's living standard is also increasingly high; In recent years, the quantity of private car increases year by year, when being convenient for people to go on a journey, has also brought some social concerns.At present, the problem of parking difficulty is increasingly serious in the city, and parking space, ground and underground parking space are nervous, and it is higher to charge, and brings inconvenience for people's work and life.Particularly some ages community resident building and office more of a specified duration; Do not build underground garage under the original ground building, the problem of parking difficulty is particularly outstanding, and car owners can only be with on the road of vehicle parking in the sub-district; Near the perhaps roadside the sub-district; The road of sub-district is become block up, the accident that vehicle scratches takes place easily, cause some unnecessary disputes.
Summary of the invention
Technical problem to be solved by this invention is the deficiency that overcomes the above-mentioned background technology; A kind of method of under old building, building underground garage is provided; This method should be able to guarantee the Stability Analysis of Structures of existing building, and has the advantages that construction is quick, construction cost is low, to alleviate the problem of present parking difficulty.
The present invention provides following technical scheme:
A kind of method of under old building, building underground garage is characterized in that: may further comprise the steps:
A, diaphragm wall or sheet pile wall are built at least 1 meter of exterior wall around the building, and the upper end of said diaphragm wall or sheet pile wall is embedded with the joint bar that upwards stretches out;
B, on the ground of building Stilt layer bottom, build one group of crossbeam; This crossbeam and said ground, diaphragm wall or sheet pile wall fuse with support of buildings;
C, below the ground of building, excavate out the underground space that is used to park cars, build the whole plate base of one deck afterwards in the bottom of the underground space, said whole plate base links into an integrated entity with underground and diaphragm wall or sheet pile wall;
D, cut off between ground and the whole plate base partly following are beneficial to vehicle parking, and remaining underground stake are reinforced;
E, offer a slope from ground and be communicated with, as the passage of vehicle turnover with the said underground space.
The construction sequence of said crossbeam is: earlier the reinforcing bar at the cage of reinforcement two ends of each crossbeam pre-buried joint bar when building diaphragm wall or sheet pile wall firmly is connected; Said ground firmly is being connected with the cage of reinforcement of crossbeam with the intersection of the crossbeam mode through the boring bar planting, and concreting makes crossbeam and ground, diaphragm wall or sheet pile wall fuse with support of buildings afterwards.
The invention has the beneficial effects as follows:
Construction method provided by the invention utilizes the Stilt layer and the underground pilework of old building, under old building, build underground garage apace, and construction cost is lower, can alleviate the problem of present parking difficulty greatly, has vast market prospect.In addition, the present invention reinforces the ground of building through crossbeam and diaphragm wall or sheet pile wall, has guaranteed the Stability Analysis of Structures of existing building, makes that also the underground garage safety of building up is higher.
Description of drawings
Fig. 1 is the vertical profile structural representation of old building.
Fig. 2 is that old building is used the vertical profile structural scheme of mechanism behind the construction sequence a among the present invention.
Fig. 3 is that old building is used the vertical profile structural representation behind the construction sequence b among the present invention.
Fig. 4 is that old building is used the vertical profile structural representation behind the construction sequence c among the present invention.
Fig. 5 is that old building is used the vertical profile structural representation behind the construction sequence d among the present invention.
Fig. 6 is the structure for amplifying sketch map of A portion among Fig. 3.
The specific embodiment
Below in conjunction with Figure of description, the present invention is described further.
Like Fig. 2-shown in Figure 5, a kind of method of under old building, building underground garage of the present invention may further comprise the steps:
A, exterior wall is built diaphragm wall or sheet pile wall 4 around the building, and the upper end of said diaphragm wall or sheet pile wall is embedded with the joint bar 7 (conventional job practices) that upwards stretches out;
Distance between diaphragm wall or sheet pile wall and the skin is recommended as 1 meter, and the height of diaphragm wall or sheet pile wall and thickness of wall body are confirmed (like depth of building, area, soil property situation etc.) according to the actual conditions of building;
B, on the ground 1 of building Stilt layer 3 bottoms, build one group of crossbeam 5; Earlier the reinforcing bar at the cage of reinforcement two ends of each crossbeam pre-buried joint bar when building diaphragm wall or sheet pile wall firmly is connected; Said ground is connected firmly through the mode of boring bar planting and the cage of reinforcement of crossbeam in the intersection with crossbeam, and concreting makes crossbeam and ground, diaphragm wall or sheet pile wall fuse with support of buildings afterwards;
Like Fig. 3, shown in Figure 6; During construction, can be in advance the boring bar planting (conventional job practices) in the intersection of ground and crossbeam, afterwards with the cage of reinforcement of crossbeam be connected firmly with the bar planting 6 of implanting ground (welding or iron wire are tightened); And the cage of reinforcement of crossbeam and the pre-buried joint bar 7 of diaphragm wall or sheet pile wall upper end be connected firmly; Last concreting makes building crossbeam and ground fuse, together support of buildings; The radical of said crossbeam and layout type are confirmed according to the actual conditions of building;
C, below the ground of building, excavate out the underground space 8 that is used to park cars, build the whole plate base 9 of one deck level afterwards in the bottom of the underground space, said whole plate base and underground stake and diaphragm wall or sheet pile wall link into an integrated entity;
The height of the said underground space confirms that according to actual conditions recommending highly is 3-5m; Vehicle parking is on said whole plate base;
D, cut off between ground and the whole plate base partly following 2 are beneficial to vehicle parking, and remaining underground stake are reinforced to strengthen the support to building;
E, offer a slope from ground and be communicated with, as the passage of vehicle turnover with the said underground space.Conventional job practices is omitted among the figure and is not drawn.
In addition, can also set up ventilation equipment and fire fighting equipment, specifically confirm according to actual needs in the bottom of ground.

Claims (1)

1. method of under old building, building underground garage is characterized in that: may further comprise the steps:
A, diaphragm wall or sheet pile wall (4) are built at least 1 meter of exterior wall around the building, and the upper end of said diaphragm wall or sheet pile wall is embedded with the joint bar (7) that upwards stretches out;
B, on the ground (1) of building Stilt layer (3) bottom, build one group of crossbeam (5); This crossbeam and said ground, diaphragm wall or sheet pile wall fuse with support of buildings;
C, below the ground of building, excavate out the underground space (8) that is used to park cars, build the whole plate base (9) of one deck afterwards in the bottom of the underground space, said whole plate base links into an integrated entity with underground and diaphragm wall or sheet pile wall;
D, partly following (2) of cutting off between ground and the whole plate base are beneficial to vehicle parking, and remaining underground stake is reinforced;
E, offer a slope from ground and be communicated with, as the passage of vehicle turnover with the said underground space;
The construction sequence of said crossbeam is: earlier the reinforcing bar at the cage of reinforcement two ends of each crossbeam pre-buried joint bar when building diaphragm wall or sheet pile wall firmly is connected; Said ground firmly is being connected with the cage of reinforcement of crossbeam with the intersection of the crossbeam mode through the boring bar planting, and concreting makes crossbeam and ground, diaphragm wall or sheet pile wall fuse with support of buildings afterwards.
CN2010105641418A 2010-11-18 2010-11-18 Method for constructing underground garage under old building Active CN102071813B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010105641418A CN102071813B (en) 2010-11-18 2010-11-18 Method for constructing underground garage under old building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010105641418A CN102071813B (en) 2010-11-18 2010-11-18 Method for constructing underground garage under old building

Publications (2)

Publication Number Publication Date
CN102071813A CN102071813A (en) 2011-05-25
CN102071813B true CN102071813B (en) 2012-04-25

Family

ID=44030553

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010105641418A Active CN102071813B (en) 2010-11-18 2010-11-18 Method for constructing underground garage under old building

Country Status (1)

Country Link
CN (1) CN102071813B (en)

Families Citing this family (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102913000B (en) * 2012-10-23 2014-08-06 山东建筑大学 Method for development and utilization of underground space by building moving
CN102900100B (en) * 2012-10-26 2014-10-22 岩土科技股份有限公司 Method for building underground room under old building by using pipe sheds
CN105256826A (en) * 2014-01-24 2016-01-20 刘献刚 Building structure of underground space
CN103924617B (en) * 2014-03-21 2015-10-21 刘献刚 A kind of building pile body construction method of the underground space and underground space building structure
CN103912134B (en) * 2014-03-21 2016-09-14 上海建工四建集团有限公司 Existing building underground space structure and construction method in situ
CN104120738A (en) * 2014-08-19 2014-10-29 广东南方电信规划咨询设计院有限公司 Non-migration-type supporting and protecting system and method of communication man/hand hole
CN104878776B (en) * 2015-05-27 2017-03-15 中建地下空间有限公司 A kind of underground shallow layer automatic parking garage the library structure
CN106088650B (en) * 2016-07-19 2018-02-09 山东建筑大学 A kind of method and building suitable for building with brick-concrete structure underground increasing layer
CN106245927B (en) * 2016-07-19 2018-06-01 山东建筑大学 A kind of method and building suitable for frame structure building underground increasing layer
CN106480976B (en) * 2016-10-14 2019-03-05 岩土科技股份有限公司 A kind of building well-sinking basis with underground garage
CN110306820A (en) * 2019-06-12 2019-10-08 上海市建筑装饰工程集团有限公司 A kind of reinforcement means of historical building blocking partition wall
CN110424765A (en) * 2019-08-19 2019-11-08 岩土科技股份有限公司 The method that one layer and grade reconstruction underground garage are built in old residential area
CN110616739B (en) * 2019-09-12 2021-08-31 上海建工集团股份有限公司 Vertical construction method for underground space of existing building
CN111321762A (en) * 2020-03-02 2020-06-23 广州市胜特建筑科技开发有限公司 Accurate basement building method
CN111335670A (en) * 2020-03-18 2020-06-26 同济大学建筑设计研究院(集团)有限公司 Method for constructing foundation pit and newly adding underground structure in situ under existing reserved building
CN113356290B (en) * 2021-06-25 2023-03-10 中铁二院华东勘察设计有限责任公司 Longitudinal wall beam type pile foundation underpinning construction method for underground passage construction
CN113914392A (en) * 2021-10-13 2022-01-11 浙江高专建筑设计研究院有限公司 Existing building transformation method
CN115354650A (en) * 2022-08-29 2022-11-18 中国土木工程集团有限公司 Building foundation reinforcing method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2929069Y (en) * 2006-07-26 2007-08-01 邓海燕 Garage structure for old residence reforming and rebuilding
DE202007010092U1 (en) * 2007-07-18 2007-10-04 Jürgens, Bu-Ja Device for overbuilding open parking decks
CN201095770Y (en) * 2007-09-06 2008-08-06 长业建设集团有限公司 Embedded single-layer basement wooden pile composite brad wall structure
CN101614019A (en) * 2008-11-11 2009-12-30 中铁四局集团建筑工程有限公司 The multilayer underground structure next to existing building self-supporting construction method

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05202631A (en) * 1992-01-28 1993-08-10 Kumagai Gumi Co Ltd Underground parking garage

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2929069Y (en) * 2006-07-26 2007-08-01 邓海燕 Garage structure for old residence reforming and rebuilding
DE202007010092U1 (en) * 2007-07-18 2007-10-04 Jürgens, Bu-Ja Device for overbuilding open parking decks
CN201095770Y (en) * 2007-09-06 2008-08-06 长业建设集团有限公司 Embedded single-layer basement wooden pile composite brad wall structure
CN101614019A (en) * 2008-11-11 2009-12-30 中铁四局集团建筑工程有限公司 The multilayer underground structure next to existing building self-supporting construction method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
JP特开平5-202631A 1993.08.10

Also Published As

Publication number Publication date
CN102071813A (en) 2011-05-25

Similar Documents

Publication Publication Date Title
CN102071813B (en) Method for constructing underground garage under old building
CN105862910B (en) A kind of the inverse of assembled stereoscopic underground garage makees formula method of construction
CN105041349B (en) A kind of excavating construction method that station is digged on the basis of Subway Tunnel shield tunnel
CN105064397B (en) Open excavation construction method for expanding excavation of station on metro interzone shield tunnel foundation
CN109235499A (en) A kind of open cut hypogee Standard formula construction method
CN105926669A (en) Construction method of subway station
CN107059667A (en) Door shape assembled armored concrete box culvert and its construction method
KR101344063B1 (en) The construction method of steel-concrete underpass
CN104878776B (en) A kind of underground shallow layer automatic parking garage the library structure
CN103452130B (en) The deformed bar net board-like barricade of reinforcement earth pillar
CN110578339A (en) construction method of shaft type underground stereo garage
CN110397148A (en) A kind of prefabricated assembled catch pit structure and construction method
CN204125872U (en) A kind of highway barrier bracing means
CN104153311A (en) Road guardrail reinforcing device and reinforcing method thereof
CN110820471A (en) Crossing plate, level crossing structure and laying method
CN105888281A (en) Method for utilizing jacking storey-adding technique to promote integrated function of community
CN112681376A (en) Construction method of shaft type underground stereo garage
CN214302989U (en) Build assembled garage parking on ground additional
CN111501782A (en) Foundation pit supporting and construction road integrated structure and construction method
CN107313454B (en) Construction method of underground garage
CN206503160U (en) A kind of continuous underground wall structure with measure of anti float
CN215906845U (en) Large-span vestibule mounting structure in foundation pit
CN210636440U (en) Annular deep foundation pit excavation construction structure
CN105133645B (en) The shaft main body structure of built-in lattice column and inverse make formula construction method
CN111058386B (en) Viaduct construction method for overpass existing ground bridge

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee

Owner name: GEOTECHNICAL TECHNOLOGY CO., LTD.

Free format text: FORMER NAME: HANGZHOU GEOTECHNICAL ENGINEERING CO., LTD.

CP03 Change of name, title or address

Address after: 310024, Hangzhou, Zhejiang province Xihu District transferred to the streets of Liuzhou Wu Long Industrial Park

Patentee after: GEOTECHNICAL TECHNOLOGY Co.,Ltd.

Address before: City of Chao Wang Road 310014 Hangzhou city of Zhejiang province No. 59-1 East Verde writer Pavilion 2C

Patentee before: HANGZHOU GEOTECHNICAL ENGINEERING Co.,Ltd.

PE01 Entry into force of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: A method of constructing underground garage under old buildings

Effective date of registration: 20220704

Granted publication date: 20120425

Pledgee: China Construction Bank Co.,Ltd. Fuyang Branch of Hangzhou

Pledgor: GEOTECHNICAL TECHNOLOGY Co.,Ltd.

Registration number: Y2022980009767

PC01 Cancellation of the registration of the contract for pledge of patent right
PC01 Cancellation of the registration of the contract for pledge of patent right

Granted publication date: 20120425

Pledgee: China Construction Bank Co.,Ltd. Fuyang Branch of Hangzhou

Pledgor: GEOTECHNICAL TECHNOLOGY Co.,Ltd.

Registration number: Y2022980009767

PE01 Entry into force of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: A method of constructing an underground garage under an old building

Granted publication date: 20120425

Pledgee: China Construction Bank Co.,Ltd. Fuyang Branch of Hangzhou

Pledgor: GEOTECHNICAL TECHNOLOGY Co.,Ltd.

Registration number: Y2024980026444