CN115354650A - Building foundation reinforcing method - Google Patents

Building foundation reinforcing method Download PDF

Info

Publication number
CN115354650A
CN115354650A CN202211039455.5A CN202211039455A CN115354650A CN 115354650 A CN115354650 A CN 115354650A CN 202211039455 A CN202211039455 A CN 202211039455A CN 115354650 A CN115354650 A CN 115354650A
Authority
CN
China
Prior art keywords
foundation
underground continuous
continuous wall
building
reinforcing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202211039455.5A
Other languages
Chinese (zh)
Inventor
田术永
姜义高
张志臣
丁兆军
孙杰
吴晓玲
李彦春
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Civil Engineering Construction Corp
Original Assignee
China Civil Engineering Construction Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Civil Engineering Construction Corp filed Critical China Civil Engineering Construction Corp
Priority to CN202211039455.5A priority Critical patent/CN115354650A/en
Publication of CN115354650A publication Critical patent/CN115354650A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/18Bulkheads or similar walls made solely of concrete in situ
    • E02D5/187Bulkheads or similar walls made solely of concrete in situ the bulkheads or walls being made continuously, e.g. excavating and constructing bulkheads or walls in the same process, without joints
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D1/00Investigation of foundation soil in situ
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil

Abstract

The application provides a building foundation reinforcing method, which comprises the following steps: surveying the foundation soil of the project to be built to obtain soil parameters; the soil parameters comprise soil cohesive force, an internal friction angle, a compression modulus and foundation bearing capacity; establishing an initial model of a proposed site foundation according to soil parameters; trial calculation is carried out on the established initial model to obtain the sliding arc depth, position and thrust; determining the specific position and size of the underground continuous wall according to parameters such as the depth, position and thrust of the sliding arc; constructing the underground continuous wall according to the specific position and size of the underground continuous wall; and constructing the building structure. According to the building foundation reinforcing method, the closed underground continuous walls are arranged on the periphery of the existing building, the foundation breaking sliding surface is technically moved downwards, the anti-sliding capacity and stability of the foundation can be improved, and the bearing capacity of the foundation is further improved; the construction process is simple, quick, efficient and feasible.

Description

Building foundation reinforcing method
Technical Field
The application belongs to the technical field of civil engineering, and particularly relates to a building foundation reinforcing method.
Background
The foundation refers to a soil body or a rock body which can bear the whole load of a building, does not belong to the building, but plays a very important role in ensuring the firmness and durability of the building and is a part of the earth. From the point of view of field construction, the foundation can be divided into natural foundation and artificial foundation, when the geological condition of the soil layer is good and the bearing capacity is strong, the natural foundation can be adopted, and under the condition of poor geological condition, such as slope, sand or silt geology, or when the upper load is too large although the texture of the soil layer is good, the foundation is artificially reinforced in order to have sufficient bearing capacity. When the foundation is reinforced, operations such as ground pit digging, hole drilling, ground tamping, reinforcing steel bar filling, cement pouring, foundation reinforcement and the like are required.
At present, people need to reinforce the building foundation either for improving the building standard or for reconstructing and expanding the existing building due to functional requirements, or for reinforcing and enclosing the building due to different degrees of damage or problems of the building, so that a simple, quick, efficient and feasible method for reinforcing the building foundation is needed to be developed.
Content of application
To overcome, at least to some extent, the problems in the related art, the present application provides a method for reinforcing a building foundation.
According to an embodiment of the present application, there is provided a building foundation reinforcing method, including the steps of:
surveying the foundation soil of the project to be built to obtain soil body parameters; the soil parameters comprise soil cohesive force, an internal friction angle, a compression modulus and foundation bearing capacity;
establishing an initial model of a proposed site foundation according to soil parameters;
trial calculation is carried out on the established initial model to obtain the sliding arc depth, position and thrust;
determining the specific position and size of the underground continuous wall according to parameters such as the depth, position and thrust of the sliding arc;
constructing the underground continuous wall according to the specific position and size of the underground continuous wall;
and constructing the building structure.
In the above method for reinforcing a building foundation, the process of obtaining the depth, position and thrust of the sliding arc by performing trial calculation on the established initial model is as follows:
drawing up a construction step in an initial model;
sequentially adding underground continuous walls and upper part loads in the initial model and simulating excavation to obtain the sliding arc depth, position and thrust of the lower sliding body;
and judging whether the obtained parameters such as the sliding arc depth, the position, the thrust and the like of the lower sliding body meet the construction requirements, and if so, determining the specific position and the size of the underground diaphragm wall according to the parameters such as the sliding arc depth, the position, the thrust and the like.
Further, when the sliding surface of the lower sliding body is an original sliding surface when the foundation is damaged or a sliding surface of a new reinforced foundation when the foundation is damaged, the sliding arc depth and the sliding arc position of the lower sliding body are determined by adopting a simplified BISHOP method or a JANBU strip method according to the cohesive force and the internal friction angle of the foundation soil.
Furthermore, the depth of the underground continuous wall is larger than the sliding surface when the foundation is damaged and extends into 1-3 m below the sliding surface.
Furthermore, the reinforcing range of the underground continuous wall is larger than the outer 4 m-6 m of the edge of the underground foundation.
Furthermore, the process of constructing the underground continuous wall according to the specific position and size of the underground continuous wall comprises the following steps:
and measuring and lofting, clearing the surface, reinforcing the ground, excavating a groove, binding reinforcing steel bars, pouring concrete, removing a formwork and arranging a support frame to finish the construction of the underground diaphragm wall.
Furthermore, the main process of constructing the underground continuous wall is as follows:
digging a groove, wherein the dug groove is provided with a groove wall;
a reinforcement cage is placed in the groove, one end or two ends of the reinforcement cage are provided with connectors, and adjacent reinforcement cages are connected through the connectors;
an isolation device is arranged between the reinforcement cage and the wall of the groove, two ends of the isolation device are respectively connected with the end part of the reinforcement cage or a connector, and the isolation device is matched with the connector to seal at least one side of the reinforcement cage;
filling concrete into the reinforcement cage to enable the reinforcement cage to be wrapped by the concrete; and forming the underground continuous wall after the concrete is solidified.
Furthermore, the firmness of the building foundation is increased by adopting a combined grouting mode, grouting is carried out between the underground continuous wall and the structure foundation, and grouting is carried out on the outer side of the underground continuous wall.
Still further, for a building having a basement range and a planar dimension that is much larger than a corresponding planar dimension of an upper high-rise building, the building foundation reinforcement method further includes:
according to the space required by the current underground continuous wall construction equipment, partial basement beam plates are partially dismantled, the underground continuous wall is recovered after the construction is finished, and the foundation or the basement is subjected to reinforcement design according to the requirement.
Furthermore, the reinforcement cage of the underground continuous wall is hoisted by adopting sectional binding and is connected by a sleeve
According to the above embodiments of the present application, at least the following advantages are obtained: according to the building foundation reinforcing method provided by the application, the closed underground continuous wall is arranged on the periphery of the existing building, and the foundation breaking sliding surface moves downwards technically, so that the anti-sliding capacity and stability of the foundation can be improved, and the bearing capacity of the foundation is further improved; when the building foundation reinforcing method provided by the application is adopted, the construction process is simple, quick, efficient and feasible.
The building foundation reinforcement can be solved in the practical application process, especially, the building in the urban core area and the foundation reinforcement needed by reconstruction and extension are favorable for improving the value of the building, and the influence of the foundation reinforcement process on the surrounding environment is reduced.
It is to be understood that both the foregoing general description and the following detailed description are exemplary and explanatory only and are not restrictive of the scope of the invention, as claimed.
Drawings
The accompanying drawings, which are incorporated in and constitute a part of the specification of the application, illustrate embodiments of the application and together with the description, serve to explain the principles of the application.
Fig. 1 is a flowchart of a method for reinforcing a building foundation according to an embodiment of the present disclosure.
Fig. 2 is a schematic view of an application state of a building foundation reinforcing method according to an embodiment of the present disclosure.
Fig. 3 is a second schematic view of an application state of the building foundation reinforcing method according to the embodiment of the present application.
Description of reference numerals:
1. an existing building; 2. building heightening, function changing and the like cause equivalent load increasing parts; 3. a ground line; 4. sliding surface when original foundation is damaged; 5. an underground diaphragm wall; 6. sliding surface when new foundation is damaged after being reinforced; 7. basement of original structure; 8. basement beam slab.
Detailed Description
Reference will now be made in detail to the exemplary embodiments, examples of which are illustrated in the accompanying drawings. When the following description refers to the accompanying drawings, like numbers in different drawings represent the same or similar elements unless otherwise indicated. The embodiments described in the following exemplary embodiments do not represent all embodiments consistent with the present application. Rather, they are merely examples of apparatus and methods consistent with certain aspects of the present application, as detailed in the appended claims.
At present, when foundation stabilization treatment is carried out on the existing building foundation, a deep grouting method and a pile foundation replacement method are mainly adopted. The deep grouting method can improve the soil mechanics property of foundation soil, improve the bearing capacity of the foundation, is convenient to construct and is suitable for reinforcement with lower requirement on the bearing capacity of the foundation; however, the uniformity of the treatment by this method is affected by the soil texture and the improvement of the bearing capacity of the foundation is limited. The pile foundation replacement method can theoretically well improve the bearing capacity according to requirements; however, this method is generally only suitable for reinforcing the periphery of buildings, and most high-rise buildings have basements, and the replacement of the corresponding pile positions in the basements is difficult and the operation space is limited.
As shown in fig. 1, an embodiment of the present application provides a building foundation reinforcing method, which includes the following steps:
s1, surveying the foundation soil of the project to be built to obtain soil body parameters.
The soil parameters comprise soil cohesive force, internal friction angle, compression modulus, foundation bearing capacity and other parameters.
S2, establishing an initial model of the proposed site foundation according to the soil body parameters.
S3, trial calculation is carried out on the established initial model to obtain parameters such as sliding arc depth, position and thrust, and the specific process is as follows:
s31, setting up a construction step in the initial model.
And S32, sequentially adding elements such as an underground continuous wall, an upper load and the like in the initial model, and simulating excavation to obtain parameters such as the sliding arc depth, the position, the thrust and the like of the lower sliding body.
Specifically, when the sliding surface is broken when the lower sliding body is an original foundation, the sliding arc depth, position and the like of the sliding surface can be determined by using a simplified BISHOP method or a JANBU strip method according to the cohesive force and the internal friction angle of the foundation soil. When the lower sliding body is a sliding surface when the reinforced new foundation is damaged, the sliding arc depth, the sliding arc position and the like of the sliding surface when the reinforced new foundation is damaged can be determined by adopting a simplified BISHOP method or a JANBU strip method according to the cohesive force and the internal friction angle of the foundation soil.
S33, judging whether the obtained parameters such as the sliding arc depth, the position and the thrust of the lower sliding body meet the construction requirements, and if so, entering the step S4; otherwise, returning to the step S2, and establishing the initial model of the proposed site foundation again according to the soil parameters.
And S4, determining parameters such as specific position, size and the like of the underground continuous wall according to parameters such as the sliding arc depth, the position and the thrust.
The dimensions of the underground continuous wall include the depth and thickness of the underground continuous wall.
This application adopts underground continuous wall to consolidate the ground, retrains the enclosure within that underground continuous wall founds with the foundation soil. The position and the degree of depth of underground continuous wall set up as required, and its setting principle does: the depth of the underground continuous wall is greater than the sliding surface when the foundation is damaged and extends into 1 m-3 m below the sliding surface (2 m is preferably selected) so that the stabilized coefficient after reinforcement meets the requirement; the reinforcing range of the underground continuous wall is larger than 4-6 m (preferably 5 m) outside the edge of the underground foundation, and the original sliding arc is prevented from sliding out of the inner side of the reinforcing range of the underground continuous wall. The anti-slip capability of the foundation soil is improved by reinforcing the underground continuous wall, and finally the bearing capacity of the foundation is improved.
And determining the thickness and reinforcing bars of the underground continuous wall according to the landslide thrust, the shearing force and the bending moment generated by the tail end of the slip arc on the underground continuous wall, and ensuring that the use requirements are met. The building foundation reinforcing method is reliable in theory and convenient to implement.
And S5, constructing the underground continuous wall according to parameters such as specific position, size and the like of the underground continuous wall.
Specifically, the construction of the underground diaphragm wall is completed after the steps of measuring and lofting, clearing the surface, reinforcing the ground, digging grooves, binding reinforcing steel bars, pouring concrete, removing a formwork, arranging a support frame and the like.
The main process of constructing the underground continuous wall comprises the following steps:
s51, digging a groove, wherein the dug groove is provided with a groove wall.
S52, placing reinforcement cages in the grooves, wherein one ends or two ends of the reinforcement cages are provided with connectors, and adjacent reinforcement cages are connected through the connectors. The connector not only can be used for connecting two adjacent steel reinforcement cages, but also can be used for preventing two adjacent steel reinforcement cages from leaking at the junction after filling concrete.
S53, an isolating device is arranged between the steel reinforcement cage and the groove wall, two ends of the isolating device are respectively connected with the end portion or the connector of the steel reinforcement cage, the isolating device is matched with the connector to seal at least one side of the steel reinforcement cage, and the isolating device is used for preventing concrete filled into the steel reinforcement cage from flowing to other steel reinforcement cages from the side or concrete poured at the adjacent steel reinforcement cage from flowing to the section of the steel reinforcement cage.
Wherein, the isolation device can be one of geotextile, plastic cloth and woven cloth.
S54, filling concrete into the reinforcement cage to enable the reinforcement cage to be wrapped by the concrete; and forming the underground continuous wall after the concrete is solidified.
Preferably, a combined grouting mode can be adopted to increase the firmness of the building foundation. Grouting between the underground diaphragm wall and the structural foundation to increase the strength of the soil body in the active area, improve the cohesive force of the soil body and reduce the sliding force of the soil body; and grouting is performed on the outer side of the underground diaphragm wall so as to increase the strength of the soil body in the passive area and increase the anti-sliding force of the soil body.
And S6, constructing the building structure.
Particularly, the partition reinforcement can be reasonably planned according to the plane shape, the height and the geological condition of the building.
As shown in fig. 2, an existing building 1 is installed on a ground line 3, and in the method for reinforcing a building foundation provided by the embodiment of the present invention, a closed underground continuous wall 5 is installed around an equivalent load increasing part 2 caused by the increase of the existing building 1 or the increase of the building height, the change of functions, and the like, so that a sliding surface 4 in the foundation breaking process is moved downward from the technology to a sliding surface 6 in the new foundation breaking process after the foundation is reinforced, thereby improving the sliding resistance and stability of the foundation and further improving the bearing capacity of the foundation.
This application can solve building foundation reinforcement at the practical application in-process, especially city core district building to and the foundation reinforcement of rebuilding and expansion needs, be favorable to promoting the building value, reduce the influence to the building is peripheral.
For the building foundation with a smaller basement range, the underground diaphragm wall 5 can be arranged around the basement 7 of the original structure for outdoor construction, and the basement 7 of the original structure is reinforced according to needs, for example, supports, concrete walls and the like are additionally arranged.
As shown in fig. 3, for a building having a large basement area and a plane size much larger than that of a high-rise building at the upper part, it is preferable to work in the basement in order to enhance the reinforcement effect of the building foundation. Determining the plane position, the depth and the thickness of the underground continuous wall 5 according to the design condition of the original building structure and the new foundation base design; according to the space required by the current underground continuous wall construction equipment (the operation height of the equipment is 9-18 m, for example, the height of a CSC30/40HDS60 type short hydraulic slot milling machine is 9 m), partial basement beam plates 8 are partially dismantled, the underground continuous wall 5 is recovered after the construction is finished, and the foundation or the basement is reinforced according to the requirement. The reinforcement cage of the underground continuous wall 5 can be lifted by section binding and connected by a sleeve.
It is understood that the same or similar parts in the above embodiments may be mutually referred to, and the same or similar parts in other embodiments may be referred to for the content which is not described in detail in some embodiments.
It should be noted that, in the description of the present application, the terms "first", "second", etc. are used for descriptive purposes only and are not to be construed as indicating or implying relative importance. Further, in the description of the present application, the meaning of "a plurality" means at least two unless otherwise specified.
In the description herein, reference to the description of the term "one embodiment," "some embodiments," "an example," "a specific example," or "some examples," etc., means that a particular feature, structure, material, or characteristic described in connection with the embodiment or example is included in at least one embodiment or example of the application. In this specification, the schematic representations of the terms used above do not necessarily refer to the same embodiment or example. Furthermore, the particular features, structures, materials, or characteristics described may be combined in any suitable manner in any one or more embodiments or examples.
Although embodiments of the present application have been shown and described above, it is understood that the above embodiments are exemplary and should not be construed as limiting the present application, and that variations, modifications, substitutions and alterations may be made to the above embodiments by those of ordinary skill in the art within the scope of the present invention.

Claims (10)

1. A building foundation reinforcing method is characterized by comprising the following steps:
surveying the foundation soil of the project to be built to obtain soil body parameters; the soil parameters comprise soil cohesive force, an internal friction angle, a compression modulus and foundation bearing capacity;
establishing an initial model of a proposed site foundation according to soil parameters;
trial calculation is carried out on the established initial model to obtain the sliding arc depth, position and thrust;
determining the specific position and size of the underground continuous wall according to parameters such as the depth, position and thrust of the sliding arc;
constructing the underground continuous wall according to the specific position and size of the underground continuous wall;
and constructing the building structure.
2. The building foundation reinforcement method according to claim 1, wherein the process of trial calculation of the established initial model to obtain the depth, position and thrust of the sliding arc is as follows:
drawing up a construction step in an initial model;
sequentially adding an underground continuous wall and an upper load in the initial model and simulating excavation to obtain the sliding arc depth, position and thrust of the lower sliding body;
and judging whether the obtained parameters such as the sliding arc depth, the position, the thrust and the like of the lower sliding body meet the construction requirements, and if so, determining the specific position and the size of the underground diaphragm wall according to the parameters such as the sliding arc depth, the position, the thrust and the like.
3. The method for reinforcing building foundation according to claim 2, wherein when the lower slider is a sliding surface at the time of failure of an original foundation or a sliding surface at the time of failure of a new foundation after reinforcement, the depth and position of the sliding arc of the lower slider are determined by a simplified BISHOP method or a JANBU strip method according to the cohesive force and the internal friction angle of the foundation soil.
4. The method for reinforcing a building foundation according to claim 3, wherein the underground diaphragm wall has a depth greater than a sliding surface at the time of foundation failure and extends 1m to 3m below the sliding surface.
5. The method for reinforcing building foundation according to claim 3, wherein the reinforcement range of the underground continuous wall is greater than 4m to 6m outside the edge of the underground foundation.
6. The method for reinforcing the building foundation according to claim 3, wherein the process of constructing the underground continuous wall according to the specific position and size of the underground continuous wall comprises the following steps:
measuring and lofting, clearing the surface, reinforcing the ground, excavating a groove, binding reinforcing steel bars, pouring concrete, and removing a formwork to establish a support frame to complete the construction of the underground diaphragm wall.
7. The method for reinforcing building foundation according to claim 6, wherein the main process of constructing the underground continuous wall is:
digging a groove, wherein the dug groove is provided with a groove wall;
a reinforcement cage is placed in the groove, one end or two ends of the reinforcement cage are provided with connectors, and adjacent reinforcement cages are connected through the connectors;
an isolation device is arranged between the reinforcement cage and the wall of the groove, two ends of the isolation device are respectively connected with the end part of the reinforcement cage or a connector, and the isolation device is matched with the connector to seal at least one side of the reinforcement cage;
filling concrete into the reinforcement cage to enable the concrete to wrap the reinforcement cage; and forming the underground continuous wall after the concrete is solidified.
8. The method for reinforcing the building foundation according to claim 7, wherein the firmness of the building foundation is increased by means of combined grouting, the grouting is performed between the underground continuous wall and the structural foundation, and the grouting is performed outside the underground continuous wall.
9. The method of building foundation reinforcement of claim 7, wherein for buildings having basement dimensions and planar dimensions substantially larger than the planar dimensions corresponding to the upper tall building, the method further comprises:
according to the space required by the current underground continuous wall construction equipment, partial basement beam plates are partially dismantled, the underground continuous wall is recovered after the construction is finished, and the foundation or the basement is subjected to reinforcement design according to the requirement.
10. The method for reinforcing the building foundation according to claim 9, wherein the reinforcement cage of the underground continuous wall is hoisted by sectional binding and connected by a sleeve.
CN202211039455.5A 2022-08-29 2022-08-29 Building foundation reinforcing method Pending CN115354650A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211039455.5A CN115354650A (en) 2022-08-29 2022-08-29 Building foundation reinforcing method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211039455.5A CN115354650A (en) 2022-08-29 2022-08-29 Building foundation reinforcing method

Publications (1)

Publication Number Publication Date
CN115354650A true CN115354650A (en) 2022-11-18

Family

ID=84005109

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211039455.5A Pending CN115354650A (en) 2022-08-29 2022-08-29 Building foundation reinforcing method

Country Status (1)

Country Link
CN (1) CN115354650A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116289966A (en) * 2023-05-15 2023-06-23 山东建筑大学 Method for controlling retaining pile for causing deformation of underlying underground structure by earth surface excavation

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0220768A (en) * 1988-07-08 1990-01-24 Takenaka Komuten Co Ltd Basement extension method for existing building
JP2003055998A (en) * 2001-08-08 2003-02-26 Pacific Consultants Co Ltd Reinforcing structure of existing structure
CN102071813A (en) * 2010-11-18 2011-05-25 杭州岩土工程有限公司 Method for constructing underground garage under old building
CN104573319A (en) * 2014-12-03 2015-04-29 中南大学 Method for designing grooving construction slurry parameters for underground diaphragm wall of water-rich sand gravel stratum based on overall stability of groove wall
CN110331715A (en) * 2019-07-05 2019-10-15 广州穗岩土木科技股份有限公司 A kind of construction method of underground continuous wall in urban construction
CN114091164A (en) * 2021-11-29 2022-02-25 上海隧道工程有限公司 Method for judging local stability of water-rich soft soil stratum
CN114837165A (en) * 2022-05-10 2022-08-02 中交一公局集团有限公司 Structure and method for improving bearing capacity of single-chamber closed underground diaphragm wall foundation by reinforcing stressed soil body through post-grouting

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0220768A (en) * 1988-07-08 1990-01-24 Takenaka Komuten Co Ltd Basement extension method for existing building
JP2003055998A (en) * 2001-08-08 2003-02-26 Pacific Consultants Co Ltd Reinforcing structure of existing structure
CN102071813A (en) * 2010-11-18 2011-05-25 杭州岩土工程有限公司 Method for constructing underground garage under old building
CN104573319A (en) * 2014-12-03 2015-04-29 中南大学 Method for designing grooving construction slurry parameters for underground diaphragm wall of water-rich sand gravel stratum based on overall stability of groove wall
CN110331715A (en) * 2019-07-05 2019-10-15 广州穗岩土木科技股份有限公司 A kind of construction method of underground continuous wall in urban construction
CN114091164A (en) * 2021-11-29 2022-02-25 上海隧道工程有限公司 Method for judging local stability of water-rich soft soil stratum
CN114837165A (en) * 2022-05-10 2022-08-02 中交一公局集团有限公司 Structure and method for improving bearing capacity of single-chamber closed underground diaphragm wall foundation by reinforcing stressed soil body through post-grouting

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
王珊主编: "地基处理新技术及其工程实例实用手册 第1卷", 哈尔滨:黑龙江人民出版社, pages: 400 - 405 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116289966A (en) * 2023-05-15 2023-06-23 山东建筑大学 Method for controlling retaining pile for causing deformation of underlying underground structure by earth surface excavation
CN116289966B (en) * 2023-05-15 2023-08-15 山东建筑大学 Method for controlling retaining pile for causing deformation of underlying underground structure by earth surface excavation

Similar Documents

Publication Publication Date Title
CN102966119B (en) Geogrid reinforced wall and construction method thereof
CN105464686B (en) Multi-layer underground space curtain posture excavating construction method and supporting construction under existing facility
CN102277867B (en) Construction method for collapsible loess foundation
CN104264688B (en) Manually digging hole non-uniform pile support construction process
CN110004991B (en) Underground structure anti-floating system based on convex wing foot plate and construction method
CN207331740U (en) A kind of heightening and consolidation structure of in-service reinforced concrete retaining wall
CN115595993A (en) Replacement pile structure of tunnel-passing slope slide-resistant pile and construction method
CN112227401A (en) Method for constructing bearing platform by filling stones in underwater stone abrupt slope area
CN115354650A (en) Building foundation reinforcing method
CN207484290U (en) The hollow clump of piles anchorage of super-large diameter
CN112392060A (en) Shallow excavation foundation reinforcing structure and reinforcing method
CN110306989B (en) Non-open-cut assembled pipe trench excavation supporting and reinforcing method
RU2371547C1 (en) Method for strengthening of slopes and slot maker for its realisation
CN107143149B (en) A kind of existing masonry structure building adds the construction method of basement
CN105484270A (en) Reinforcement protection construction method of high steep old rubble retaining wall adjacent to deep foundation pit
CN210031875U (en) Open caisson device for pushing
CN209324377U (en) Ledge method tunneling subway station arch springing ruggedized construction
CN110130397A (en) Tilt hexagon piping lane system and its construction method of the supporting in conjunction with main structure
CN111441794A (en) Underground excavation construction method and structure for rebuilding existing tunnel into double-layer tunnel
CN110258621B (en) Assembled retaining wall convenient to quick construction
Michalak et al. Forecasting the impact of buildings with multi-storey underground parts on the displacement of subsoil using modern numerical tools
CN216428327U (en) Slope protection reinforced concrete structure
CN111733830B (en) Super high-rise building foundation pit bearing and enclosing system
CN115217114B (en) Construction method of foundation pit rescue back pressure platform
CN112609706B (en) Construction method of opposite-bracing angle brace concrete horizontal supporting structure of foundation pit in sea reclamation area

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination