CN115595993A - Replacement pile structure of tunnel-passing slope slide-resistant pile and construction method - Google Patents

Replacement pile structure of tunnel-passing slope slide-resistant pile and construction method Download PDF

Info

Publication number
CN115595993A
CN115595993A CN202211247982.5A CN202211247982A CN115595993A CN 115595993 A CN115595993 A CN 115595993A CN 202211247982 A CN202211247982 A CN 202211247982A CN 115595993 A CN115595993 A CN 115595993A
Authority
CN
China
Prior art keywords
pile
construction
rotary
tunnel
cast
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202211247982.5A
Other languages
Chinese (zh)
Inventor
沈琦
张立军
钟仕明
邓亚军
王盼
刘毅
宋战平
王怀正
田小旭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xian University of Architecture and Technology
Sinohydro Bureau 7 Co Ltd
Chengdu Hydropower Construction Engineering Co Ltd of Sinohydro Bureau 7 Co Ltd
Original Assignee
Xian University of Architecture and Technology
Chengdu Hydropower Construction Engineering Co Ltd of Sinohydro Bureau 7 Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xian University of Architecture and Technology, Chengdu Hydropower Construction Engineering Co Ltd of Sinohydro Bureau 7 Co Ltd filed Critical Xian University of Architecture and Technology
Priority to CN202211247982.5A priority Critical patent/CN115595993A/en
Publication of CN115595993A publication Critical patent/CN115595993A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • E02D17/207Securing of slopes or inclines with means incorporating sheet piles or piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0258Retaining or protecting walls characterised by constructional features
    • E02D29/0266Retaining or protecting walls characterised by constructional features made up of preformed elements
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D33/00Testing foundations or foundation structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

The invention discloses a replacement pile structure of a tunnel-through slope slide-resistant pile, which is arranged below an existing building and comprises a counterfort retaining wall and a rotary-excavating filling pile, wherein the counterfort retaining wall comprises a beam, a heel plate, a wall panel and a counterfort, the beam is arranged between the heel plate and the wall panel, one side of the beam is fixedly connected with the heel plate, the top of the beam is fixedly connected with the bottom of a front panel, the counterfort is fixedly arranged at the top of the heel plate, the counterfort is fixedly connected with the wall panel, the top of the rotary-excavating filling pile penetrates through the bottom of the heel plate, and the top of the rotary-excavating filling pile is fixedly connected with the heel plate. The replacement pile structure provided by the invention can furthest reduce the influence of the original slide-resistant pile on the original structure in the tunnel construction process, and ensure the safety and stability of the original structure and the tunnel in the tunnel construction process.

Description

一种隧道穿越边坡抗滑桩的置换桩结构及施工方法A replacement pile structure and construction method for tunnel crossing slope anti-slide piles

技术领域technical field

本发明属于隧道施工技术领域,具体涉及一种隧道穿越边坡抗滑桩的置换桩结构及施工方法。The invention belongs to the technical field of tunnel construction, and in particular relates to a displacement pile structure and a construction method for tunnel crossing slope anti-slide piles.

背景技术Background technique

随着城市的快速发展,为满足人们日常出行的需求,越来越多的高速公路、铁路、地铁等开始在城市中建设。这些隧道往往需要下穿已有建筑物或者构筑物,因此涉及对原有桩基础的破除和保护。桩基础对建筑物的安全稳定起着至关重要的作用,如何在不破坏原有建筑物或构筑物安全甚至保障原结构在隧道施工期间仍能正常使用成为一大难题。若保护不得到,隧道施工过程可能威胁原建筑物的正常使用,甚至危害原建筑物的安全,造成重大的经济损失和人员伤亡。因此,发明一种隧道穿越边坡抗滑桩的置换桩结构及施工方法,对于该类型的隧道设计和施工具有重要意义。With the rapid development of cities, in order to meet people's daily travel needs, more and more highways, railways, subways, etc. have begun to be built in cities. These tunnels often need to pass through existing buildings or structures, so it involves the demolition and protection of the original pile foundation. Pile foundations play a vital role in the safety and stability of buildings. How to ensure the normal use of the original structures without destroying the safety of the original buildings or structures or even during tunnel construction has become a major problem. If the protection is not obtained, the tunnel construction process may threaten the normal use of the original building, or even endanger the safety of the original building, causing heavy economic losses and casualties. Therefore, it is of great significance for the design and construction of this type of tunnel to invent a replacement pile structure and construction method for tunnel crossing slope anti-slide piles.

发明内容Contents of the invention

本发明的目的在于克服现有技术的不足,提供一种隧道穿越边坡抗滑桩的置换桩结构及施工方法。The purpose of the present invention is to overcome the deficiencies of the prior art, and provide a replacement pile structure and construction method for tunnel crossing slope anti-slide piles.

本发明的第一个目的是提供一种隧道穿越边坡抗滑桩的置换桩结构,包括扶壁式挡土墙和旋挖灌注桩;The first object of the present invention is to provide a replacement pile structure for tunnel crossing slope anti-slide piles, including buttress-type retaining walls and rotary-dug cast-in-place piles;

所述扶壁式挡土墙包含梁、踵板、墙面板和扶壁,所述梁设置于踵板与墙面板之间,梁的一侧与踵板固定连接,梁的顶部与前面板的底部固定连接,扶壁固定设置于踵板的顶部,扶壁与墙面板固定连接,旋挖灌注桩的顶部贯穿踵板的底部,且旋挖灌注桩的顶部与踵板固定连接。The buttress retaining wall comprises a beam, a heel plate, a wall panel and a buttress, the beam is arranged between the heel plate and the wall panel, one side of the beam is fixedly connected to the heel plate, and the top of the beam is connected to the front panel The bottom is fixedly connected, the buttress is fixedly arranged on the top of the heel plate, the buttress is fixedly connected with the wall panel, the top of the rotary-dug cast-in-place pile runs through the bottom of the heel-plate, and the top of the rotary-dug cast-in-situ pile is fixedly connected with the heel plate.

优选的,踵板的底部固定设置有垫层,旋挖灌注桩的顶部贯穿垫层,且与垫层紧密接触。Preferably, the bottom of the heel plate is fixedly provided with a cushion, and the top of the rotary-dug cast-in-place pile penetrates the cushion and is in close contact with the cushion.

优选的,旋挖灌注桩伸入踵板内部的长度为20cm。Preferably, the length of the rotary-dug cast-in-place pile extending into the heel plate is 20cm.

本发明的第二个目的是提供一种上述隧道穿越边坡抗滑桩的置换桩结构的施工方法,包括以下步骤:Second object of the present invention is to provide a kind of construction method of the above-mentioned tunnel passing through the replacement pile structure of the slope anti-slide pile, comprising the following steps:

S1、施工准备S1. Construction preparation

对施工场地和施工便道分别进行布置和建设,根据施工设计图复核土方填筑范围及旋挖灌注桩桩位,并进行测量放样交底;Arrange and construct the construction site and construction access road respectively, review the earthwork filling range and rotary excavation pile positions according to the construction design drawing, and carry out measurement and stakeout;

S2、土方填筑S2. Earthwork filling

在步骤S1完成测量放样后,填筑临时工作平台,并进行碾压;After the measurement and stakeout is completed in step S1, the temporary working platform is filled and rolled;

S3、旋挖灌注桩施工S3. Construction of rotary excavation cast-in-place piles

在步骤S2完成碾压后,进行旋挖灌注桩施工;After the rolling is completed in step S2, the rotary excavation pile construction is carried out;

S4、桩基检测S4. Pile foundation detection

在步骤S3旋挖灌注桩施工完成后,在满足检测条件后对旋挖灌注桩的桩基采用超声波和低应变法进行检测;After the construction of the rotary-dug cast-in-place pile in step S3 is completed, the pile foundation of the rotary-dig cast-in-situ pile is detected by ultrasonic and low-strain methods after the detection conditions are met;

S5、扶壁式挡土墙施工S5. Construction of buttress retaining wall

在步骤S4的旋挖灌注桩的桩基检测合格后,在进行扶壁式挡土墙施工时依次进行基础开挖、基底处理、基础件、墙面板、扶壁以及墙背回填施工;After the pile foundation of the rotary excavation cast-in-situ pile in step S4 is qualified, foundation excavation, foundation treatment, foundation parts, wall panels, buttresses and backfill construction of the wall are sequentially carried out during construction of the buttress-type retaining wall;

S6、隧道开挖及原桩基础拆除S6. Tunnel excavation and original pile foundation removal

待步骤S5扶壁式挡土墙施工完成后,且应力应变趋向稳定后开始隧道开挖并拆除原抗滑桩。After the construction of the buttress-type retaining wall in step S5 is completed, and the stress and strain tend to be stable, start tunnel excavation and remove the original anti-slide piles.

优选的,步骤S3中,所述旋挖灌注桩施工具体包含以下步骤:Preferably, in step S3, the construction of the rotary-dug cast-in-place pile specifically includes the following steps:

S31、场地处理:在步骤S2完成碾压后,对地面进行平整压实,地面高程需高出设计桩顶60cm以上;S31. Site treatment: After the rolling is completed in step S2, the ground is leveled and compacted, and the ground elevation must be higher than the designed pile top by more than 60 cm;

S32、桩位放样:对桩位的中心位置进行放样,向四个不同方向引四个距离相同的点作为护桩,将相对的两个护桩均用细绳连接,两个细绳的交叉点即为桩位点;S32. Pile position stakeout: Stake out the central position of the pile position, lead four points with the same distance to four different directions as protective piles, connect the two opposite protective piles with thin ropes, and cross the two thin ropes. The point is the pile point;

S33、埋设护筒:根据桩位编号布置图,施工顺序采用隔孔施工,对待施工桩位点进行旋挖钻孔,将护筒放入已挖好的孔内,地面线下埋设4700mm,露出地面上300mm,然后对护筒的底部和外侧四周采用黏质土回填并分层夯实;S33. Buried casing: according to the layout of the pile position numbers, the construction sequence adopts the construction of separated holes, and the piles to be constructed are drilled by rotary drilling, and the casing is placed in the dug hole, and the ground line is buried 4700mm below the ground line. 300mm above the ground, and then backfill the bottom and outer sides of the casing with clay soil and compact it layer by layer;

S34、第一次清孔:采用换浆法对护筒内部的原泥浆进行清除;S34, cleaning the hole for the first time: the original mud inside the casing is removed by the mud changing method;

S35、在第一次清孔完成后,对钢筋笼骨架和导管依次进行安装,安装完成后进行第二次清孔,桩清孔后孔底沉渣厚度不得大于50mm;S35. After the first hole cleaning is completed, the steel cage skeleton and the conduit are installed in sequence. After the installation is completed, the second hole cleaning is carried out. After the pile holes are cleaned, the thickness of the sediment at the bottom of the hole must not exceed 50mm;

S36、混凝土灌注:向护筒内灌注混凝土,灌注完成后,得到旋挖灌注桩。S36. Concrete pouring: concrete is poured into the casing, and after the pouring is completed, a rotary-dug cast-in-place pile is obtained.

优选的,步骤S4中,所述检测条件为桩基混凝土的强度大于设计强度70%且不低于15Mpa。Preferably, in step S4, the detection condition is that the strength of the pile foundation concrete is greater than 70% of the design strength and not lower than 15Mpa.

优选的,步骤S5中,所述扶壁式挡土墙施工具体包含以下步骤:Preferably, in step S5, the construction of the buttress type retaining wall specifically includes the following steps:

S51、基础开挖:在步骤S4的旋挖灌注桩的桩基检测合格后,根据开挖基坑深度按1:0.75坡比以及踵板和梁的结构尺寸向外扩1m到设计标高进行开挖,开挖前在灌注桩填筑面顶明显标示桩位置基坑,待挖至底板底上20cm后采用人工清理踵板和梁底部渣土至设计标高;S51. Foundation excavation: After the pile foundation of the rotary excavation pile in step S4 is qualified, the excavation is carried out according to the depth of the excavated foundation pit according to the slope ratio of 1:0.75 and the structural size of the heel plate and beam by 1m to the design elevation. Excavation. Before excavation, clearly mark the pile position foundation pit on the top of the pouring pile filling surface. After digging to 20cm above the bottom of the floor, manually clean up the muck at the bottom of the heel plate and the beam to the design elevation;

S52、基底处理:通过人工对旋挖灌注桩的桩头上的渣土进行清理,清理完成后,旋挖灌注桩的桩基采用风镐和人工钢钻进行清凿桩头;S52. Base treatment: manually clean the muck on the head of the rotary-dug cast-in-place pile. After the cleaning is completed, the pile foundation of the rotary-dug cast-in-place pile is cleared with a pick and an artificial steel drill;

S53、基础件施工:凿除桩头后,露出的钢筋伸入垫层与踵板,将旋挖灌注桩与扶壁式挡土墙连接,然后将梁、踵板与混凝土同步绑扎和浇筑;S53. Construction of foundation parts: after removing the pile head, the exposed steel bars extend into the cushion layer and the heel plate, connect the rotary-dug cast-in-situ pile with the buttress-type retaining wall, and then bind and pour the beam, heel plate and concrete synchronously;

S54、墙面板和扶壁施工:墙面板、护壁钢筋、混凝土同步绑扎和浇筑;S54. Construction of wall panels and buttresses: synchronous binding and pouring of wall panels, retaining reinforcement bars, and concrete;

S55、墙背回填施工:挡土墙拆模后混凝土强度达到设计要求后进行墙背回填,回填位置为墙面板背部至边坡之间。S55. Backfill construction at the back of the wall: After the retaining wall is demolished, the concrete strength meets the design requirements, and then backfill the back of the wall. The backfill position is between the back of the wall panel and the side slope.

优选的,步骤S53和步骤S54中,所述梁、踵板、墙面板和护壁所采用的模板均为组合钢模。Preferably, in step S53 and step S54, the templates used for the beams, heel plates, wall panels and retaining walls are composite steel molds.

本发明与现有技术相比,其有益效果在于:Compared with the prior art, the present invention has the beneficial effects of:

(1)本发明提供的隧道穿越边坡抗滑桩的置换桩结构及施工方法,最大程度降低隧道施工过程中破除原抗滑桩对原结构的影响,保障隧道施工过程中原结构和隧道本身的安全稳定;(1) The replacement pile structure and construction method of the tunnel passing through the slope anti-slide piles provided by the present invention can minimize the impact of breaking the original anti-slide piles on the original structure during the tunnel construction process, and ensure the integrity of the original structure and the tunnel itself during the tunnel construction process. safe and stable;

(2)本发明提供的置换桩结构,通过扶壁式挡土墙与旋挖灌注桩的联合设计,能够进一步提高原边坡结构的稳定性,增加原边坡的安全冗余度;(2) The replacement pile structure provided by the present invention can further improve the stability of the original slope structure and increase the safety redundancy of the original slope through the joint design of buttress type retaining wall and rotary excavation cast-in-situ pile;

(3)本发明提供的置换桩结构的结构简单、设计合理、施工方便,能够有效解决隧道施工需破除抗滑桩的受力转换问题。(3) The replacement pile structure provided by the present invention is simple in structure, reasonable in design, and convenient in construction, and can effectively solve the problem of force transformation of anti-slide piles that need to be broken during tunnel construction.

附图说明Description of drawings

图1为本发明实施例提供的隧道穿越边坡抗滑桩的置换桩结构的平面结构示意图;Fig. 1 is the plane structure diagram of the replacement pile structure of the tunnel passing through the slope anti-slide pile provided by the embodiment of the present invention;

图2为本发明实施例提供的置换桩结构的剖面图;Fig. 2 is the sectional view of the replacement pile structure that the embodiment of the present invention provides;

图3为本发明实施例提供的置换桩结构的三维效果图;Fig. 3 is the three-dimensional rendering of the replacement pile structure provided by the embodiment of the present invention;

图4为本发明实施例提供的隧道穿越边坡抗滑桩的置换桩结构的施工流程图;Fig. 4 is the construction flowchart of the replacement pile structure of the tunnel passing through the slope anti-slide pile provided by the embodiment of the present invention;

图中:1、旋挖灌注桩;2、扶壁式挡土墙;3、原抗滑桩;4、踵板;5、墙面板;6、扶壁;7、垫层;8、梁;9、隧道。In the figure: 1. Rotary excavation pile; 2. Buttress retaining wall; 3. Original anti-slide pile; 4. Heel plate; 5. Wall panel; 6. Buttress; 7. Cushion; 8. Beam; 9. Tunnel.

具体实施方式detailed description

为了使本发明的目的、技术方案及优点更加清楚明白,以下结合附图及实施例,对本发明进行进一步详细说明。应当理解,此处所描述的具体实施例仅用以解释本发明,并不用于限定本发明。In order to make the object, technical solution and advantages of the present invention clearer, the present invention will be further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described here are only used to explain the present invention, not to limit the present invention.

如图1至图3所示,本发明实施例提供了一种隧道穿越边坡抗滑桩的置换桩结构,包括扶壁式挡土墙2和旋挖灌注桩1;As shown in Figures 1 to 3, the embodiment of the present invention provides a replacement pile structure for tunnel crossing slope anti-slide piles, including a buttress-type retaining wall 2 and a rotary-dug cast-in-place pile 1;

所述扶壁式挡土墙2包含梁8、踵板4、墙面板5和扶壁6,所述梁8设置于踵板4与墙面板5之间,梁8的一侧与踵板4固定连接,梁8的顶部与墙面板5的底部固定连接,扶壁6固定设置于踵板4的顶部,扶壁6与墙面板5固定连接,旋挖灌注桩1的顶部贯穿踵板4的底部,且旋挖灌注桩1的顶部与踵板4固定连接。The buttress type retaining wall 2 comprises a beam 8, a heel plate 4, a wall panel 5 and a buttress 6, the beam 8 is arranged between the heel plate 4 and the wall panel 5, and one side of the beam 8 is connected to the heel plate 4 Fixed connection, the top of the beam 8 is fixedly connected with the bottom of the wall panel 5, the buttress 6 is fixedly arranged on the top of the heel panel 4, the buttress 6 is fixedly connected with the wall panel 5, and the top of the rotary drilling pile 1 runs through the bottom of the heel panel 4 bottom, and the top of the rotary drilling cast-in-situ pile 1 is fixedly connected with the heel plate 4.

踵板4的底部固定设置有垫层7,旋挖灌注桩1的顶部贯穿垫层7,且与垫层7紧密接触。The bottom of the heel plate 4 is fixedly provided with a cushion layer 7 , and the top of the rotary-dug cast-in-place pile 1 penetrates the cushion layer 7 and is in close contact with the cushion layer 7 .

旋挖灌注桩1伸入踵板4内部的长度为20cm。The length that the rotary-dug cast-in-situ pile 1 extends into the heel plate 4 is 20cm.

本发明实施例还提供了一种上述隧道穿越边坡抗滑桩的置换桩结构的施工方法,具体包括以下步骤:The embodiment of the present invention also provides a construction method of the above-mentioned tunnel passing through the replacement pile structure of the slope anti-slide pile, which specifically includes the following steps:

S1、施工准备S1. Construction preparation

对施工场地和施工便道分别进行布置和建设,完成前期的“三通一平”(即在正式施工以前,施工现场应达到水通、电通、道路通和场地平整等条件)、材料堆放场地、工器具的安装调试准备工作,根据施工设计图复核土方填筑范围及钻孔灌注桩桩位,并进行测量放样交底;Arrange and build the construction site and construction access road respectively, and complete the "three connections and one leveling" in the early stage (that is, before the official construction, the construction site should meet the conditions of water, electricity, road access and site leveling), material stacking site, Preparation for installation and commissioning of tools and equipment, review the earthwork filling range and bored pile positions according to the construction design drawing, and carry out measurement and lofting disclosure;

S2、土方填筑S2. Earthwork filling

在步骤S1完成测量放样后,填筑临时工作平台,并进行碾压,碾压遵循“先轻后重、先两边后中间、先静压后振压”的原则,碾压分为初压、复压和终压;After the measurement and stakeout is completed in step S1, fill the temporary working platform and carry out rolling. The rolling follows the principle of "light first, then heavy, first both sides, then the middle, first static pressure, then vibratory pressure". The rolling is divided into initial pressure, Re-pressure and final pressure;

S3、旋挖灌注桩施工S3. Construction of rotary excavation cast-in-place piles

在步骤S2完成碾压后,进行旋挖灌注桩1施工,旋挖灌注桩1施工具体包含以下步骤:After the rolling is completed in step S2, the construction of the rotary-dug cast-in-situ pile 1 is carried out, and the construction of the rotary-dug cast-in-situ pile 1 specifically includes the following steps:

S31、场地处理:在步骤S2完成碾压后,对地面进行平整压实,地面高程需高出设计桩顶60cm以上,桩基施工前每桩须预埋4根声测管用于超声波检测;S31. Site treatment: After the rolling is completed in step S2, the ground is leveled and compacted. The ground elevation must be higher than the design pile top by more than 60 cm. Before the pile foundation construction, 4 acoustic measuring tubes must be embedded in each pile for ultrasonic detection;

S32、桩位放样:采用全站仪对桩位的中心位置进行放样,向四个不同方向引四个距离相同的点作为护桩,将相对的两个护桩均用细绳连接,两个细绳的交叉点即为桩位点;S32. Pile position stakeout: Use a total station to stake out the central position of the pile position, lead four points with the same distance to four different directions as protective piles, and connect the two opposite protective piles with thin ropes. The intersection point of the string is the stake point;

S33、埋设护筒:根据桩位编号布置图,施工顺序采用隔孔施工,对待施工桩位点进行旋挖钻孔,将护筒放入已挖好的孔内,地面线下埋设4700mm,露出地面上300mm,护筒在埋设定位时,护筒中心与桩中心的平面位置偏差不大于50mm,护筒在竖直方向的倾斜度不大于1%,然后对护筒的底部和外侧四周采用黏质土回填并分层夯实,护筒采用钢板卷制,其内直径为2700mm,高5000mm,壁厚20mm,护筒制作加工时,其椭圆度小于d/100;直径允许偏差为±10mm;筒体端面的倾斜度允许偏差为3mm,纵轴线弯曲矢高应不大于护筒长度的0.1%,且不大于30mm;护筒对接时的错边量不大于0.2倍钢板厚度,且不大于4mm;S33. Buried casing: according to the layout of the pile position numbers, the construction sequence adopts the construction of separated holes, and the piles to be constructed are drilled by rotary drilling, and the casing is placed in the dug hole, and the ground line is buried 4700mm below the ground line. 300mm above the ground, when the casing is buried and positioned, the plane position deviation between the center of the casing and the center of the pile is not more than 50mm, and the inclination of the casing in the vertical direction is not more than 1%. The soil is backfilled and compacted in layers. The casing is made of steel plates with an inner diameter of 2700mm, a height of 5000mm, and a wall thickness of 20mm. When the casing is manufactured and processed, its ellipticity is less than d/100; the allowable deviation of the diameter is ±10mm; The allowable deviation of the inclination of the body end face is 3mm, and the bending sagittal height of the longitudinal axis shall not be greater than 0.1% of the length of the casing, and shall not be greater than 30mm; the amount of misalignment of the butt joint of the casing shall not be greater than 0.2 times the thickness of the steel plate, and shall not be greater than 4mm;

S34、第一次清孔:采用换浆法对护筒内部的原泥浆进行清除,直至孔内排出或抽出的泥浆手摸无颗粒感觉,泥浆比重、粘度、含砂率控制在要求范围内;S34. Cleaning the hole for the first time: Use the slurry changing method to clean the original mud inside the casing until the mud discharged or extracted from the hole has no grainy feel to the touch, and the specific gravity, viscosity, and sand content of the mud are controlled within the required range;

S35、在第一次清孔完成后,对钢筋笼骨架和导管依次进行安装,安装完成后进行第二次清孔,桩清孔后孔底沉渣厚度不得大于50mm;S35. After the first hole cleaning is completed, the steel cage skeleton and the conduit are installed in sequence. After the installation is completed, the second hole cleaning is carried out. After the pile holes are cleaned, the thickness of the sediment at the bottom of the hole must not exceed 50mm;

S36、混凝土灌注:向护筒内灌注混凝土,灌注完成后,得到旋挖灌注桩1,混凝土采用C35混凝土,钢筋主要采用HRB400和HPB300,主筋保护层厚度70mm。S36. Concrete pouring: pour concrete into the casing. After the pouring is completed, a rotary-dug cast-in-situ pile 1 is obtained. The concrete is C35 concrete, the steel bars are mainly HRB400 and HPB300, and the thickness of the main reinforcement protective layer is 70mm.

S4、桩基检测S4. Pile foundation detection

在步骤S3旋挖灌注桩1施工完成后,在桩基混凝土强度大于设计强度70%且不低于15MPa后,对旋挖灌注桩的桩基采用超声波和低应变法进行检测,具体按《建筑基桩检测技术规范》JGJ106-2014等相关规程规范进行桩基完整性检测,且50%桩基采用低应变完整性检测,50%桩基采用超声波完整性检测,检测合格后仍须抽取不少于总桩数的10%桩基进行钻芯取样。钻芯取样桩基混凝土龄期不少于28天;After the construction of the rotary-dig cast-in-place pile 1 in step S3 is completed, after the concrete strength of the pile foundation is greater than 70% of the design strength and not lower than 15MPa, the pile foundation of the rotary-dig cast-in-situ pile is detected by ultrasonic and low-strain methods, specifically according to "Building Integrity testing of pile foundations is carried out in JGJ106-2014 and other relevant regulations and specifications, and 50% of pile foundations use low-strain integrity testing, and 50% of pile foundations use ultrasonic integrity testing. Core drilling samples were taken on 10% of the pile foundations of the total number of piles. The concrete age of the pile foundation for core sampling shall not be less than 28 days;

S5、扶壁式挡土墙施工S5. Construction of buttress retaining wall

在步骤S4的旋挖灌注桩的桩基检测合格后,在进行扶壁式挡土墙2施工时依次进行基础开挖、基底处理、基础件、墙面板5、扶壁6以及墙背回填施工,在本发明实施例中扶壁式挡土墙2施工具体包含以下步骤:After the pile foundation of the rotary excavation cast-in-place pile in step S4 is qualified, foundation excavation, foundation treatment, foundation parts, wall panels 5, buttresses 6 and backfill construction of the wall are sequentially carried out during construction of the buttress-type retaining wall 2 , in the embodiment of the present invention, the construction of the buttress type retaining wall 2 specifically includes the following steps:

S51、基础开挖:在步骤S4的旋挖灌注桩1的桩基检测合格后,即在所有桩基础砼强度达到75%以上后,根据开挖基坑深度按1:0.75坡比以及踵板4和梁8的结构尺寸向外扩1m到设计标高进行开挖,开挖前在灌注桩填筑面顶明显标示桩位置基坑,待挖至底板底上20cm后采用人工清理踵板4和梁8底部渣土至设计标高;S51, foundation excavation: after the pile foundation of the rotary excavation cast-in-place pile 1 in step S4 is qualified, that is, after the concrete strength of all pile foundations reaches more than 75%, according to the excavation depth of the foundation pit according to the slope ratio of 1:0.75 and the heel plate The structural dimensions of 4 and beam 8 are expanded 1m outward to the design elevation for excavation. Before excavation, the pile position foundation pit is clearly marked on the top of the filling surface of the cast-in-situ piles. The muck at the bottom of beam 8 reaches the design elevation;

S52、基底处理:通过人工对旋挖灌注桩1的桩头上的渣土进行清理后,桩基采用风镐和人工钢钻进行清凿桩头;S52. Base treatment: after the muck on the pile head of the rotary-dug cast-in-place pile 1 is manually cleaned, the pile foundation is cleared and chiseled with a pneumatic pick and an artificial steel drill;

S53、基础件施工:凿除桩头后,露出的钢筋伸入垫层7与踵板4,将旋挖灌注桩1与扶壁式挡土墙2连接,然后将梁8、踵板4与混凝土同步绑扎和浇筑;S53. Construction of foundation parts: After the pile head is removed, the exposed steel bars extend into the cushion layer 7 and the heel plate 4, and the rotary excavation pile 1 is connected with the buttress retaining wall 2, and then the beam 8, the heel plate 4 and the buttress retaining wall 2 are connected. Simultaneous binding and pouring of concrete;

S54、墙面板和扶壁施工:墙面板5和扶壁钢筋、混凝土同步绑扎和浇筑,模板均采用组合钢模,拉杆对拉,背部支撑加固方法;S54. Wall panel and buttress construction: wall panel 5 and buttress reinforcement and concrete are bound and poured synchronously, the templates are all combined steel molds, the tie rods are pulled in opposite directions, and the back support is reinforced;

S55、墙背回填施工:挡土墙拆模后混凝土强度达到设计要求后进行墙背回填,回填采用泡沫土,回填位置为墙面板背部至边坡之间;S55. Backfill construction at the back of the wall: after the formwork removal of the retaining wall, the concrete strength meets the design requirements, and then backfill the back of the wall. Foam soil is used for the backfill, and the backfill position is between the back of the wall panel and the side slope;

S6、隧道开挖及原桩基础拆除S6. Tunnel excavation and original pile foundation removal

待步骤S5扶壁式挡土墙2施工完成后,且应力应变趋向稳定后开始隧道9开挖并拆除原抗滑桩3,拆除原抗滑桩时应加强对边坡和置换结构的监控量测,监控量测具体包括:After the construction of the buttress-type retaining wall 2 in step S5 is completed, and the stress and strain tend to be stable, the excavation of the tunnel 9 is started and the original anti-slide pile 3 is removed. When the original anti-slide pile is removed, the monitoring of the slope and the replacement structure should be strengthened Measurement, monitoring and measurement specifically include:

(1)洞内外观察:洞内观察包括开挖面观察和初期支护完成区段观察等,开挖面观察每次开挖后进行一次,观察后应绘制开挖面略图,填写工作面状态记录及围岩级别判定卡,初期支护完成区段观察每天至少进行一次,观察内容包括喷砼、锚杆、钢架的状态。洞外观察包括洞口地表情况、地表沉陷、边坡、仰坡的稳定、地表水渗漏的观察等。(1) Observation inside and outside the cave: The observation in the cave includes the observation of the excavation surface and the observation of the section where the initial support is completed. The observation of the excavation surface is carried out once after each excavation. Records and determination cards of surrounding rock grades, observation of the section where the initial support is completed shall be carried out at least once a day, and the observation content includes the status of sprayed concrete, anchor rods, and steel frames. The observation outside the cave includes the observation of the surface conditions at the entrance of the cave, surface subsidence, stability of side slopes and uphill slopes, and surface water seepage.

(2)周边位移量测:量测坑道断面的收敛情况,包括量测拱顶下沉、净空水平收敛以及底板鼓起(必要时)。(2) Peripheral displacement measurement: measure the convergence of the section of the tunnel, including the measurement of the sinking of the vault, the convergence of the headroom level and the swelling of the floor (if necessary).

(3)地表下沉量测:地表下沉量测应在开挖面前方隧道埋置深度与隧道开挖高度之和处开始,直到衬砌结构封闭、下沉基本停止为止。采用全站仪监测各固定点的坐标、高程,利用直尺量测裂缝宽度变化情况,可参考道路测设的BM点。并在间隔平台上设置测斜管。(3) Surface subsidence measurement: The surface subsidence measurement should start at the sum of the tunnel embedment depth in front of the excavation face and the tunnel excavation height until the lining structure is closed and the subsidence basically stops. A total station is used to monitor the coordinates and elevation of each fixed point, and a ruler is used to measure the change of crack width, which can refer to the BM point of the road survey. And set the inclinometer tube on the interval platform.

(4)超前地质预报:采取以地质调查分析法为基础,结合TSP、地质雷达等物探手段,辅以超前钻孔等综合地质预报手段。其中:TSP间隔100-150m设一个断面,地质雷达间隔30m设一个断面,超前钻孔根据需要增加。(4) Advance geological forecast: Based on the geological survey and analysis method, combined with geophysical means such as TSP and geological radar, supplemented by comprehensive geological forecast means such as advanced drilling. Among them: set a section at an interval of 100-150m for TSP, set a section at an interval of 30m for ground radar, and add more advanced drilling holes as needed.

综上所述,本发明实施例所提供的隧道穿越边坡抗滑桩的置换结构是在传统扶壁式挡土墙的基础上根据工程实际情况提出的优化方案,通过扶壁式挡土墙和旋挖桩孔灌注桩的组合受力结构替换原有边坡抗滑桩,扶壁式挡土墙和旋挖灌注桩的布置都根据边坡情况、抗滑桩位置以及隧道所在位置进行设计,在隧道开挖破除原有抗滑桩时保护边坡安全,提高边坡稳定性。In summary, the replacement structure of anti-slide piles for tunnel crossing slopes provided by the embodiment of the present invention is an optimization scheme proposed on the basis of traditional buttress-type retaining walls according to actual engineering conditions. The original slope anti-slide piles are replaced by the combined force-bearing structure of the rotary-dug pile hole grouting piles. The layout of the buttress retaining wall and the rotary-dug grouting piles is designed according to the slope conditions, the location of the anti-slide piles and the location of the tunnel. , to protect the safety of the slope and improve the stability of the slope when the original anti-slide piles are excavated in the tunnel.

显然,本领域的技术人员可以对本发明进行各种改动和变型而不脱离本发明的精神和范围。这样,倘若本发明的这些修改和变型属于本发明权利要求及其等同技术的范围之内,则本发明也意图包含这些改动和变型在内。Obviously, those skilled in the art can make various changes and modifications to the present invention without departing from the spirit and scope of the present invention. Thus, if these modifications and variations of the present invention fall within the scope of the claims of the present invention and their equivalent technologies, the present invention also intends to include these modifications and variations.

Claims (8)

1. A replacement pile structure of an anti-slide pile for a tunnel to pass through a side slope is arranged below an existing building and is characterized by comprising a buttress retaining wall (2) and a rotary excavating filling pile (1);
buttress formula retaining wall (2) contain roof beam (8), heel board (4), shingle nail (5) and buttress (6), roof beam (8) set up between heel board (4) and shingle nail (5), one side and heel board (4) fixed connection of roof beam (8), the top of roof beam (8) and the bottom fixed connection of shingle nail (5), buttress (6) fixed set up in the top of heel board (4), buttress (6) and shingle nail (5) fixed connection, the bottom of heel board (4) is run through at the top of bored concrete pile (1) soon, and dig the top of bored concrete pile (1) soon and heel board (4) fixed connection.
2. The replacement pile structure of the tunnel-crossing slope slide-resistant pile according to claim 1, wherein a cushion layer (7) is fixedly arranged at the bottom of the heel plate (4), and the top of the rotary-digging cast-in-place pile (1) penetrates through the cushion layer (7) and is in close contact with the cushion layer (7).
3. The replacement pile structure of the tunnel-crossing slope slide pile according to claim 1, wherein the length of the rotary excavating cast-in-place pile (1) extending into the heel plate (4) is 20cm.
4. The method for constructing a replacement pile structure of a tunnel-crossing slope slide pile according to claim 1, which comprises the following steps:
s1, preparation for construction
Respectively arranging and constructing a construction site and a construction sidewalk, rechecking an earthwork filling range and a pile position of a rotary excavating cast-in-place pile (1) according to a construction design drawing, and measuring, lofting and mating the bottom;
s2, filling earthwork
After the step S1 of measurement lofting is finished, filling a temporary working platform and rolling;
s3, construction of rotary digging cast-in-place pile
After the rolling is finished in the step S2, construction of the rotary excavating cast-in-place pile (1) is carried out;
s4, pile foundation detection
After the construction of the rotary excavating filling pile (1) is completed in the step S3, detecting a pile foundation of the rotary excavating filling pile (1) by adopting an ultrasonic wave and low strain method after detection conditions are met;
s5, counterfort retaining wall construction
After the pile foundation of the rotary excavating filling pile (1) in the step S4 is detected to be qualified, foundation excavation, substrate treatment, foundation pieces, wall panels (5), buttresses (6) and wall back backfill construction are sequentially carried out when the buttress retaining wall (2) is constructed;
s6, tunnel excavation and original pile foundation demolition
And (5) after the construction of the counterfort retaining wall (2) in the step (S5) is completed, and after the stress and strain tend to be stable, starting tunnel excavation and dismantling the original anti-slide pile (3).
5. The method for constructing the replacement pile structure of the tunnel-crossing slope slide-resistant pile according to claim 4, wherein in the step S3, the rotary excavating cast-in-place pile construction specifically comprises the following steps:
s31, site processing: after the rolling is finished in the step S2, leveling and compacting the ground, wherein the ground elevation needs to be higher than the designed pile top by more than 60 cm;
s32, pile position lofting: lofting the center position of a pile position, guiding four points with the same distance to four different directions to serve as guard piles, connecting two opposite guard piles by using thin ropes, wherein the intersection point of the two thin ropes is a pile position point;
s33, embedding a protection tube: according to the pile position numbering layout, adopting hole isolation construction according to the construction sequence, carrying out rotary drilling on the pile position to be constructed, placing a pile casing into the excavated hole, burying 4700mm below the ground line, exposing 300mm above the ground, backfilling the bottom and the periphery of the outer side of the pile casing with clay soil, and compacting in layers;
s34, cleaning holes for the first time: removing the original slurry in the protective cylinder by adopting a slurry changing method;
s35, after the hole cleaning is finished for the first time, sequentially installing the reinforcement cage framework and the guide pipe, and after the hole cleaning is finished for the second time, cleaning the hole, wherein the thickness of the sediment at the bottom of the hole is not more than 50mm after the hole is cleaned;
s36, pouring concrete: and (3) pouring concrete into the pile casing, and obtaining the rotary excavating cast-in-place pile (1) after pouring.
6. The method for constructing a replacement pile structure of a tunnel-crossing slope slide-resistant pile according to claim 4, wherein in the step S4, the detection condition is that the strength of the pile foundation concrete is greater than 70% of the design strength and not lower than 15MPa.
7. The method for constructing a replacement pile structure of a tunnel-through slope slide pile according to claim 4, wherein in the step S5, the counterfort retaining wall construction specifically comprises the following steps:
s51, foundation excavation: after the pile foundation of the rotary-excavating cast-in-place pile in the step S4 is detected to be qualified, excavating according to the depth of an excavation foundation pit, the slope ratio of 1.75 and the structural sizes of the heel plate (4) and the beam (8) which are expanded by 1m outwards to a designed elevation, obviously marking a pile position foundation pit on the top of the filling surface of the cast-in-place pile before excavating, and manually cleaning the heel plate (4) and the bottom of the beam (8) to the designed elevation after excavating to 20cm from the bottom of the bottom plate;
s52, substrate treatment: cleaning up the slag soil on the pile head of the rotary-digging cast-in-place pile (1) manually, and after the cleaning up is completed, cleaning up the pile head of the rotary-digging cast-in-place pile (1) by adopting an air pick and a manual steel drill;
s53, constructing a foundation part: after a pile head is chiseled off, exposed reinforcing steel bars extend into the cushion layer (7) and the heel plate (4), the rotary-digging cast-in-place pile (1) is connected with the counterfort retaining wall (2), and then the beam (8) and the heel plate (4) are synchronously bound and poured with concrete;
s54, wall panel and buttress construction: synchronously binding and pouring the wall panel (5), the wall protection reinforcing steel bars and the concrete;
s55, wall back backfilling construction: and backfilling the wall back after the concrete strength of the retaining wall after the form removal reaches the design requirement, wherein the backfilling position is between the back of the wall panel (5) and the side slope.
8. The method for constructing the replacement pile structure of the tunnel-through slope slide-resistant pile according to claim 4, wherein the templates adopted by the beam (8), the heel plate (4), the wall panel (5) and the retaining wall (6) in the steps S53 and S54 are all combined steel molds.
CN202211247982.5A 2022-10-12 2022-10-12 Replacement pile structure of tunnel-passing slope slide-resistant pile and construction method Pending CN115595993A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211247982.5A CN115595993A (en) 2022-10-12 2022-10-12 Replacement pile structure of tunnel-passing slope slide-resistant pile and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211247982.5A CN115595993A (en) 2022-10-12 2022-10-12 Replacement pile structure of tunnel-passing slope slide-resistant pile and construction method

Publications (1)

Publication Number Publication Date
CN115595993A true CN115595993A (en) 2023-01-13

Family

ID=84846933

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211247982.5A Pending CN115595993A (en) 2022-10-12 2022-10-12 Replacement pile structure of tunnel-passing slope slide-resistant pile and construction method

Country Status (1)

Country Link
CN (1) CN115595993A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117052421A (en) * 2023-10-13 2023-11-14 湖南省通盛工程有限公司 Tunnel portal supporting structure in deep slippage and large bias state and construction method
CN117634987A (en) * 2024-01-25 2024-03-01 中建安装集团有限公司 Building high slope construction evaluation management system and method based on Internet of things

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117052421A (en) * 2023-10-13 2023-11-14 湖南省通盛工程有限公司 Tunnel portal supporting structure in deep slippage and large bias state and construction method
CN117052421B (en) * 2023-10-13 2024-01-09 湖南省通盛工程有限公司 Tunnel portal supporting structure in deep slippage and large bias state and construction method
CN117634987A (en) * 2024-01-25 2024-03-01 中建安装集团有限公司 Building high slope construction evaluation management system and method based on Internet of things
CN117634987B (en) * 2024-01-25 2024-04-02 中建安装集团有限公司 Building high slope construction evaluation management system and method based on Internet of things

Similar Documents

Publication Publication Date Title
CN108842819B (en) Urban rail transit cable line tunnel construction method
CN104846829B (en) Shield-reserved penetration composite type foundation pit support wall and construction method thereof
CN102535477B (en) Safety construction method for cutting off anchor cables of support of excavating foundation pit
CN105672348A (en) Construction method for cropping bridge pile foundation at sandy gravel stratum of abyssal region
CN101215834A (en) Construction Method of Outrigger Type Diaphragm Wall
CN107130613A (en) Large span tunnel is just wearing the retaining structure and its construction method of existing barricade
CN109914161B (en) Construction method of high-speed railway filling roadbed in soft soil area
CN211144503U (en) High steep topography bridge tunnel meets section open cut tunnel and connects long structure
US11959243B2 (en) Method for constructing large-span station with two-wing open type half-cover excavation and half-reverse construction
CN115595993A (en) Replacement pile structure of tunnel-passing slope slide-resistant pile and construction method
CN114411761B (en) Advanced pre-supporting system and method for subway tunnel to be built in new building construction
CN111794774A (en) A kind of half-cut single-pressure type Myeongdong tunnel rapid tunnel entry protection structure and construction method
CN112575670A (en) T-shaped rigid frame bridge suitable for tunnel to pass through giant karst cave and construction technology thereof
CN115539048A (en) Construction method for shallow-buried bias tunnel portal
CN112576265A (en) Sedimentation control method for old villages penetrated by shield
CN115450221B (en) Construction method for subway crossing river channel
CN109577322A (en) A kind of constructing device for inside soil body existing pile foundation pile extension
CN216765941U (en) Tunnel decompression load shedding structure under bias voltage state
CN113898007B (en) Semi-inverse construction method for long-span corridor structure along street
CN215906845U (en) Large-span vestibule mounting structure in foundation pit
CN114922195A (en) A construction method for deep and large foundation pit in soft soil close to protection object
CN113550764A (en) Method for starting shield concrete sleeve to enter hole and building structure
CN112627002A (en) Continuous beam bridge suitable for tunnel to pass through giant karst cave and construction technical method thereof
CN114855778B (en) Pile replacing construction method under complex geological condition of hillside slope
CN219343473U (en) Cross-street corridor mounting structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right

Effective date of registration: 20240718

Address after: 611700 No. 349, Chengguan East Road, North Street, Pitong Town, Pidu District, Chengdu, Sichuan

Applicant after: SINOHYDRO BUREAU 7 Co.,Ltd.

Country or region after: China

Applicant after: CHENGDU HYDROPOWER CONSTRUCTION ENGINEERING CO., LTD., SINOHYDRO BUREAU 7 Co.,Ltd.

Applicant after: XIAN University OF ARCHITECTURE AND TECHNOLOG

Address before: 611130 No. 9, West Section of Fair Huadu Avenue, Wenjiang, Chengdu, Sichuan Province (Rongxin Smart Plaza)

Applicant before: CHENGDU HYDROPOWER CONSTRUCTION ENGINEERING CO., LTD., SINOHYDRO BUREAU 7 Co.,Ltd.

Country or region before: China

Applicant before: XIAN University OF ARCHITECTURE AND TECHNOLOG

TA01 Transfer of patent application right