CN102277867B - A construction method of collapsible loess foundation - Google Patents

A construction method of collapsible loess foundation Download PDF

Info

Publication number
CN102277867B
CN102277867B CN 201110123842 CN201110123842A CN102277867B CN 102277867 B CN102277867 B CN 102277867B CN 201110123842 CN201110123842 CN 201110123842 CN 201110123842 A CN201110123842 A CN 201110123842A CN 102277867 B CN102277867 B CN 102277867B
Authority
CN
China
Prior art keywords
pile
grouting
stake
construction
mud jacking
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201110123842
Other languages
Chinese (zh)
Other versions
CN102277867A (en
Inventor
胡长明
李修波
梅源
林�源
赵浩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xian University of Architecture and Technology
Original Assignee
Xian University of Architecture and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xian University of Architecture and Technology filed Critical Xian University of Architecture and Technology
Priority to CN 201110123842 priority Critical patent/CN102277867B/en
Publication of CN102277867A publication Critical patent/CN102277867A/en
Application granted granted Critical
Publication of CN102277867B publication Critical patent/CN102277867B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

本发明公开了一种湿陷性黄土地基的施工方法,该方法首先采用SDDC桩对具有湿陷性的黄土场地进行地基处理;然后,在现场采集原状土,按规范进行室内试验,测得桩间土挤密系数、SDDC桩桩体压实系数,并进行湿陷性评价,若三项指标中有不满足设计要求时,则进行SDDC桩补桩施工,直至满足设计要求;最后,进行灌注桩后压浆施工。该方法具有经济环保、处理深度大、处理效果好、承载潜力大、抵御复杂荷载能力强等优势。运用该方法能够消除深厚湿陷性黄土场地的湿陷性所造成的各种负面效应,能够满足上部高层建筑物对地基承载力及沉降要求。

Figure 201110123842

The invention discloses a construction method of collapsible loess foundation. In the method, SDDC piles are firstly used to treat the foundation of the collapsible loess site; Intersoil compaction coefficient, SDDC pile body compaction coefficient, and evaluation of collapsibility. If any of the three indicators do not meet the design requirements, the SDDC pile filling construction will be carried out until the design requirements are met; finally, pouring Post-pile grouting construction. This method has the advantages of economy and environmental protection, large treatment depth, good treatment effect, large bearing potential and strong ability to resist complex loads. Using this method can eliminate various negative effects caused by the collapsibility of the deep collapsible loess site, and can meet the requirements of the upper high-rise buildings on the bearing capacity and settlement of the foundation.

Figure 201110123842

Description

一种湿陷性黄土地基的施工方法A construction method of collapsible loess foundation

技术领域 technical field

本发明涉及建筑地基处理领域,具体为一种采用SDDC桩和灌注桩后压浆技术联合联合处理黄土地基湿陷性的施工方法。 The invention relates to the field of building foundation treatment, in particular to a construction method for jointly treating loess foundation collapsibility by adopting SDDC piles and cast-in-situ pile post-grouting technology.

背景技术 Background technique

在西北、华北地区常会遇到黄土地基处理问题,通常包括低湿度湿陷性黄土以消除或减小湿陷变形危害为主要目的,同时需提高地基承载力的地基处理问题,以及高湿度软弱黄土(尤其是饱和黄土,多由湿陷性黄土饱水转化而成,饱和度Sr﹥80%)以提高地基承载力、减少有害压缩变形为目的的地基处理问题。由于后者的工程特性多与一般粘性土类似,主要应考虑地基的压缩变形,可按软弱粘性土对待,而前者则主要应考虑地基受水浸湿后的湿陷变形。 Loess foundation treatment problems are often encountered in Northwest and North China, usually including low-humidity collapsible loess with the main purpose of eliminating or reducing the damage of collapsible deformation, and at the same time need to improve foundation bearing capacity, and high-humidity soft loess (Especially saturated loess, which is mostly transformed from collapsible loess saturated with water, and the saturation degree S r ﹥80%) is a foundation treatment problem aimed at improving the bearing capacity of the foundation and reducing harmful compression deformation. Since the engineering characteristics of the latter are mostly similar to those of ordinary cohesive soils, the compression deformation of the foundation should be mainly considered, and can be treated as weak cohesive soils, while the former should mainly consider the subsidence deformation of the foundation after being soaked by water.

传统的湿陷性黄土地基的处理方法主要有以下方法: The traditional treatment methods for collapsible loess foundation mainly include the following methods:

(1)垫层,(2)重锤表层夯实,(3)强夯,(4)挤密桩,(5)化学加固,(6)预浸水,(7)桩基础。 (1) cushion layer, (2) heavy hammer surface compaction, (3) dynamic compaction, (4) compaction pile, (5) chemical reinforcement, (6) pre-soaked water, (7) pile foundation.

以上对湿陷性黄土地基的处理方法中,方法(1)和方法(2)处理深度浅,不宜用于湿陷性黄土深厚的场地;方法(3)对环境的负面影响大,不宜在已有建筑物周围及市区使用;方法(4)所用填料单一,且对桩间土的挤密效果不理想,仅能有限的消除地基湿陷性;方法(5)处理费用昂贵,一般不予采用;方法(6)浸水时场地周围地表下沉开裂,并容易造成“跑水”穿洞,影响周围建筑物的安全;方法(7)处理深厚湿陷性黄土地区,尤其在自重湿陷性黄土场地,为克服负摩擦力带来的不利影响,所需桩较长,经济性差。 Among the above treatment methods for collapsible loess foundations, method (1) and method (2) have shallow treatment depths and are not suitable for sites with deep collapsible loess; method (3) has a large negative impact on the environment and is not suitable for existing It is used around buildings and urban areas; method (4) uses a single filler, and the compaction effect on the soil between piles is not ideal, and can only eliminate the subsidence of the foundation to a limited extent; method (5) is expensive to deal with, and is generally not accepted Adopted; method (6) when the ground around the site sinks and cracks when flooded, it is easy to cause "running water" to penetrate holes and affect the safety of surrounding buildings; method (7) deal with deep collapsible loess areas, especially in self-weight collapsible loess areas In loess field, in order to overcome the adverse effects of negative friction, the required piles are long and the economy is poor.

以上针对湿陷性黄土地基的传统处理方法中,尤其对自重湿陷性黄土深厚的场地,尚无经济有效的地基处理方法能够满足高层建筑物(高耸构筑物)对地基承载力及沉降量的要求,因此,寻找一种新的湿陷性黄土地基的处理方法是本领域技术人员关注的热点。 Among the above traditional treatment methods for collapsible loess foundations, especially for sites with deep self-weight collapsible loess, there is no economical and effective foundation treatment method that can meet the requirements of high-rise buildings (tall structures) for foundation bearing capacity and settlement , Therefore, finding a new treatment method for collapsible loess foundation is a hotspot that those skilled in the art pay attention to.

发明内容 Contents of the invention

针对上述现有技术存在的缺点或不足,本发明的目的在于提供一种采用SDDC桩和灌注桩后压浆技术联合处理湿陷性黄土地基的施工方法。 In view of the shortcomings or deficiencies in the above-mentioned prior art, the object of the present invention is to provide a construction method for joint treatment of collapsible loess foundations using SDDC piles and post-grouting technology for cast-in-place piles.

为了实现上述任务,本发明通过以下的技术方案得以实现: In order to achieve the above tasks, the present invention is achieved through the following technical solutions:

一种湿陷性黄土地基的施工方法,其特征在于,该方法首先采用SDDC桩法对具有湿陷性的黄土场地进行地基处理;然后,在现场采集原状土,按规范进行室内试验,测得桩间土挤密系数、SDDC桩桩体压实系数,并进行湿陷性评价,若三项指标中有不满足设计规范时,则进行SDDC桩的补桩施工,直至满足设计要求;然后进行灌注桩后压浆施工。 A construction method for a collapsible loess foundation, characterized in that the method first adopts the SDDC pile method to carry out foundation treatment on a collapsible loess site; then, collect undisturbed soil on site, conduct indoor tests according to specifications, and measure Soil compaction coefficient between piles, SDDC pile body compaction coefficient, and collapsibility evaluation. If any of the three indicators do not meet the design specifications, the SDDC pile will be repaired until the design requirements are met; then carry out Grouting construction after pouring piles.

其具体施工的步骤如下: The specific construction steps are as follows:

步骤一,核查地质资料,结合设计参数,选择合适的成孔施工机具; Step 1: Check the geological data, combine with the design parameters, and select the appropriate hole-forming construction equipment;

步骤二,平整场地,清除地上障碍物,标记处理场地范围内的地下构造物及管线,保持场地平整; Step 2: Level the site, remove obstacles on the ground, mark and deal with underground structures and pipelines within the scope of the site, and keep the site level;

步骤三,测量放线,定出控制轴线、打桩场地边线并标识; Step 3: Measure and set out the line, determine the control axis and the sideline of the piling site and mark it;

步骤四,应用步骤一中选择的施工机具,冲击成孔。成孔施工机具一般采用带桩架的桩机,冲击锤选用橄榄形超重锤。桩机就位、对正、调平后,起吊重锤到达设计高度(一般可提升至10m~18m),橄榄形超重锤自动脱钩,借助橄榄形超重锤的动能冲入土中,反复进行上述操作,直至孔深达到设计要求; Step 4, use the construction machine tool selected in Step 1 to impact and form holes. The hole-forming construction equipment generally adopts a pile driver with a pile frame, and the impact hammer adopts an olive-shaped overweight hammer. After the pile driver is in place, aligned and leveled, the hoisting hammer reaches the design height (generally it can be lifted to 10m~18m), the olive-shaped overweight hammer is automatically unhooked, and the kinetic energy of the olive-shaped overweight hammer is used to rush into the soil, and the above-mentioned steps are repeated. Operate until the hole depth meets the design requirements;

步骤五,分层填料,夯击成桩: Step five, layered filling, compacted into piles:

用标准料斗或运料车将按设计拌和好的定量填料分层填入桩孔,然后用成孔时的橄榄形超重锤将填料逐一分层夯实,直至成SDDC桩。且每个桩孔应夯填至桩顶设计标高以上至少0.5m;其中,成孔及填料夯实的施工顺序间隔进行; Use a standard hopper or a transport truck to fill the pile hole with the quantitative filler mixed according to the design layer by layer, and then use the olive-shaped overweight hammer when forming the hole to tamp the filler layer by layer until the SDDC pile is formed. And each pile hole should be rammed and filled to at least 0.5m above the design elevation of the pile top; among them, the construction sequence of hole forming and filling tamping is carried out at intervals;

步骤六,施工机械移至下一个桩位,重复步骤四、步骤五,直至SDDC桩全部完成; Step 6, the construction machinery moves to the next pile position, and repeats steps 4 and 5 until all SDDC piles are completed;

步骤七,开挖探井采集SDDC桩的桩身填料试样和桩间土试样,做室内常规土工试验,具体要求如下: Step 7: Excavate exploratory wells to collect pile body filler samples and soil samples between piles of SDDC piles, and do indoor routine geotechnical tests. The specific requirements are as follows:

(1)按规范取桩间土及SDDC桩的桩身填料试样若干,做室内常规土工试验,其结果应满足桩间土的挤密系数不小于0.93,SDDC桩的桩身的压密系数不小于0.97; (1) According to the specifications, take some samples of the soil between the piles and the pile body filler of the SDDC pile, and do indoor routine geotechnical tests. The results should meet the compaction coefficient of the soil between the piles not less than 0.93, and the compaction coefficient of the pile body of the SDDC pile Not less than 0.97;

(2)湿陷性评价。为进一步确定湿陷性的消除程度,在场地上开挖探井采集三SDDC桩形心处桩间土的不扰动土试样,进行室内常规土工试验,根据室内试验结果,判定湿陷性的消除程度是否满足设计要求。 (2) Collapsibility evaluation. In order to further determine the elimination degree of collapsibility, excavate exploratory wells on the site to collect undisturbed soil samples of the soil between the three SDDC piles at the centroid, conduct indoor routine geotechnical tests, and determine the degree of collapsibility elimination according to the indoor test results Whether it meets the design requirements.

若以上各指标已满足设计要求,则进行灌注桩后压浆的施工;否则进行SDDC桩的补桩施工; If the above indicators have met the design requirements, carry out the construction of grouting after pouring piles; otherwise, carry out the construction of supplementary piles of SDDC piles;

步骤八,在进行灌注桩施工之前,采用100mm厚C15混凝土对已采用SDDC桩处理过的地面进行硬化处理; Step 8, before the construction of cast-in-situ piles, use 100mm thick C15 concrete to harden the ground that has been treated with SDDC piles;

步骤九,采用全站仪利用指定的轴线交点作控制点,对灌注桩桩位放样、定位,灌注桩的桩位方向距离误差不小于5mm,并用长钉对桩位进行一一标记; Step 9: Use the total station to use the specified axis intersection as the control point to stake out and position the cast-in-place piles. The distance error of the pile position direction of the cast-in-place piles is not less than 5mm, and mark the pile positions one by one with spikes;

步骤十,制作钢筋笼,验收待用。采用桩身预埋管压浆法,即按设计的压浆深度要求,将压浆管固定在钢筋笼上,压浆装置随钢筋笼一起下放。压浆管之间采用丝扣连接避免焊接; Step 10, make the reinforcement cage, check and accept it for use. The pile body pre-buried pipe grouting method is used, that is, the grouting pipe is fixed on the steel cage according to the designed grouting depth, and the grouting device is lowered together with the steel cage. Screw connections are used between grouting pipes to avoid welding;

步骤十一,成孔机具就位,并保持成孔机械平稳,不发生倾斜、位移; Step 11, the hole-forming machine is in place, and the hole-forming machine is kept stable without tilting or displacement;

步骤十二,调整成孔机械,用对位圈对好灌注桩桩位,开动成孔机械,达到控制深度后,进行清孔作业; Step 12, adjust the hole forming machine, use the alignment ring to align the pile position of the cast-in-situ pile, start the hole forming machine, and perform hole cleaning after reaching the controlled depth;

步骤十三,移动成孔机具到下一灌注桩桩位,重复步骤十一和步骤十二,直至完成所有灌注桩的成孔作业; Step 13, move the hole forming machine to the next cast-in-situ pile position, repeat step 11 and step 12, until the hole-forming operation of all cast-in-situ piles is completed;

步骤十四,将事先制作的安装好注浆管的钢筋笼吊装下放,钢筋笼放入前绑好砂浆垫块或塑料卡,吊放钢筋笼时,要对准孔位,吊直扶稳,缓慢下沉,避免碰撞孔壁;钢筋笼放到设计位置时,应立即固定;在两段钢筋笼之间的连接处进行焊接,以确保钢筋笼的位置正确,保证保护层厚度符合要求; Step 14: Hoist and lower the pre-fabricated reinforcement cage with grouting pipes installed. Before placing the reinforcement cage, tie mortar pads or plastic cards. Sink to avoid colliding with the hole wall; when the steel cage is placed in the design position, it should be fixed immediately; weld the joint between the two steel cages to ensure that the position of the steel cage is correct and the thickness of the protective layer meets the requirements;

步骤十五,压浆管试水。每节压浆管随钢筋笼下放时应做试水试验,若发现水柱下降或水柱消失,则应检查压浆管是否有砂眼、丝扣连接是否密封。 Step fifteen, test the water of the grouting pipe. When each section of the grouting pipe is lowered with the steel cage, a water test should be done. If the water column is found to drop or disappear, check whether the grouting pipe has sand holes and whether the screw connection is sealed.

钢筋笼放置完毕后孔内进行第二次清孔完成后需再次检查孔内水面,无异常后用堵头封住压浆管上口; After the reinforcement cage is placed, carry out the second cleaning in the hole, and then check the water surface in the hole again, and seal the upper opening of the grouting pipe with a plug if there is no abnormality;

步骤十六,浇筑混凝土灌注桩。用放溜筒浇筑混凝土灌注桩,在放溜筒前再次检查和测量钻孔内虚土的厚度,达到设计要求时进行,混凝土浇筑采用连续进行,混凝土浇筑到灌注桩的桩顶时,应适当超过灌注桩的桩顶设计标高,以保证在凿除浮浆后,灌注桩的桩顶标高符合设计要求。同时,制作同一配合比的试块,每班不得少于一组; Step sixteen, pouring concrete pouring piles. Concrete cast-in-situ piles are poured with a release tube, and the thickness of the virtual soil in the drilled hole is checked and measured again before the release of the tube. When the design requirements are met, the concrete pouring is carried out continuously. When pouring concrete to the top of the cast-in-place pile, proper Exceed the design elevation of the pile top of the cast-in-situ pile to ensure that the pile top elevation of the cast-in-place pile meets the design requirements after the laitance is removed. At the same time, make no less than one group of test blocks with the same mix ratio;

步骤十七,压水试验,压水试验在成桩后24小时内进行。正式压浆前必须进行压水试验,以检查管路及单向阀的畅通状况。 Step seventeen, pressurized water test, the pressurized water test is carried out within 24 hours after pile formation. Before formal grouting, a water pressure test must be carried out to check the smoothness of the pipeline and check valve.

若在桩侧或桩端发生扩孔、塌孔或充盈系数较大的情况时,需特别注意提前进行压水试验,在混凝土浇筑完的5小时内进行以确保能冲开较厚的混凝土覆盖层。 If hole expansion, hole collapse or large filling coefficient occurs on the pile side or pile end, special attention should be paid to the pressure water test in advance, and it should be carried out within 5 hours after the concrete is poured to ensure that the thicker concrete cover can be washed away layer.

试验时由专人记录冲破压力值及管道畅通情况; During the test, a special person shall record the breakthrough pressure value and the smoothness of the pipeline;

步骤十八,重复步骤十四、步骤十五、步骤十六、步骤十七,完成各灌注桩的成桩工作,同时为后压浆施工做好准备工作; Step 18, repeat step 14, step 15, step 16, and step 17 to complete the pile-forming work of each cast-in-place pile and prepare for post-grouting construction at the same time;

步骤十九,后压浆施工。采取二次注浆的方式,以充分发挥注浆的作用,获得更佳效果。 Step nineteen, post grouting construction. The method of secondary grouting is adopted to give full play to the effect of grouting and obtain better results.

(1)初注:灌注桩桩身混凝土养护3~5天后开始压浆,将按设计配置好的水泥浆通过高压泵和预埋压浆管注入到桩底或桩侧土层中去,若为复式压浆,则一般先进行桩侧压浆,12小时后再进行桩底压浆。初注时压力要小,浆液由稀到稠。初注时要密切注意注浆压力、注浆量的变化,并注意注浆节奏。桩底注浆时应设置百分表检测桩的上抬量,避免过大。 (1) Initial injection: After 3 to 5 days of concrete curing for cast-in-situ piles, grouting will start, and the cement slurry configured according to the design will be injected into the bottom of the pile or the soil layer on the side of the pile through a high-pressure pump and a pre-embedded grouting pipe. For compound grouting, the pile side grouting is generally carried out first, and the pile bottom grouting is carried out after 12 hours. The pressure at the initial injection should be small, and the slurry will be thin to thick. During the initial injection, pay close attention to the changes of the grouting pressure and the amount of grouting, and pay attention to the grouting rhythm. When grouting at the bottom of the pile, a dial indicator should be set to detect the lifting amount of the pile to avoid excessive.

(2)二次注浆:第二次注浆的注浆管最好与第一次注浆的注浆管成对称分布。第二次注浆量一般为第一次的1∕3~1∕4,水灰比可适当提高。 (2) Secondary grouting: The grouting pipes for the second grouting should preferably be distributed symmetrically with the grouting pipes for the first grouting. The amount of grouting for the second time is generally 1/3~1/4 of the first time, and the water-cement ratio can be increased appropriately.

(3)同一根桩的压浆顺序:先对上侧管进行压浆,然后下侧管,最后进行端管压浆;同一承台桩的压浆顺序:先四周桩后中心桩。 (3) The grouting sequence of the same pile: grouting the upper pipe first, then the lower pipe, and finally the end pipe; the grouting sequence of the same pile cap: first the surrounding piles and then the central pile.

步骤二十,终止压浆。终止压浆的总的控制原则以压浆量为主,压力控制为辅。但压浆参数还应根据地质条件合理选择,如若桩端为密实的砾石卵石层时,应以压浆量为主要控制指标;桩侧为密实的黄土层时则应以压浆压力为主要控制指标。 Step 20, stop grouting. The general control principle of terminating grouting is mainly based on grouting volume, supplemented by pressure control. However, the grouting parameters should also be reasonably selected according to the geological conditions. For example, if the pile end is a dense gravel and pebble layer, the grouting amount should be the main control index; if the pile side is a dense loess layer, the grouting pressure should be the main control index. index.

压浆完毕后立即给压浆管拧上堵头,以免因回浆而降低压浆效果。 Immediately after the grouting is completed, screw the plug on the grouting pipe to avoid reducing the grouting effect due to grouting back.

步骤二十一,重复步骤十九、步骤二十,连续完成各个灌注桩后压浆的施工工作。 In step 21, repeat steps 19 and 20 to continuously complete the post-grouting construction work of each cast-in-place pile.

采用本发明的方法能有效解决深厚湿陷性黄土场地上的高层建筑物(高耸构筑物)对地基承载力、沉降量、环境影响等方面要求苛刻的问题。又因采用这种方法后可有效缩短桩长,所以其所带来的经济效益较其他方法更为显著。 The method of the invention can effectively solve the problem that high-rise buildings (tall structures) on the deep collapsible loess site have strict requirements on foundation bearing capacity, settlement, environmental impact and the like. And because the pile length can be effectively shortened after adopting this method, the economic benefit brought by it is more significant than other methods.

附图说明 Description of drawings

图1是SDDC桩平面布置示意图; Figure 1 is a schematic diagram of the layout of SDDC piles;

图2是地基处理剖面示意图; Fig. 2 is a schematic sectional view of foundation treatment;

图3是压浆管埋设示意图。 Figure 3 is a schematic diagram of the embedding of the grouting pipe.

图中的标记分别表示:1、桩间土,2 、SDDC桩,3、地基下部无湿陷性的天然土层4、灌注桩,5、注浆管。 The marks in the figure represent respectively: 1. soil between piles, 2. SDDC pile, 3. natural soil layer without collapsibility in the lower part of the foundation , 4. cast-in-place pile, 5. grouting pipe.

下面参照附图和实施例对本发明进行详细说明。 The present invention will be described in detail below with reference to the accompanying drawings and embodiments.

具体实施方式 Detailed ways

孔内深层超强夯法(Super Down-hole Dynamic Compaction,简称SDDC),它是以高动能、超压强、强挤密的作用机理通过冲击成孔,由深到浅,逐层强夯成桩,在超压强的动能强夯过程中使桩间土侧面产生很大的动态被动土压力,迫使填料向下和周边压密挤出,使桩间土物理力学指标得到充分的改善。可广泛应用于杂填、液化、湿陷软弱、膨胀等各类特殊地基的处理。该方法适应性强、处理深度大、处理效果好、绿色环保、对环境影响小、经济效益好等优点,近年来被逐渐人们所认识,且处理效果良好。本发明将孔内深层超强夯法引入桩基础方法中,对黄土地基湿陷性进行处理,经实践证明,得到了满意的效果。 Super Down-hole Dynamic Compaction (Super Down-hole Dynamic Compaction, referred to as SDDC), which uses the mechanism of high kinetic energy, super pressure, and strong compaction to form holes through impact, from deep to shallow, and form piles layer by layer. , In the process of overpressure kinetic energy dynamic compaction, a large dynamic passive earth pressure is generated on the side of the soil between the piles, forcing the filler to compact and extrude downward and around, so that the physical and mechanical indicators of the soil between the piles are fully improved. It can be widely used in the treatment of various special foundations such as miscellaneous filling, liquefaction, weak subsidence, and expansion. This method has the advantages of strong adaptability, large treatment depth, good treatment effect, environmental protection, little impact on the environment, and good economic benefits. It has been gradually recognized by people in recent years, and the treatment effect is good. The invention introduces the in-hole deep ultra-strong compaction method into the pile foundation method to treat the collapsibility of the loess foundation, and it is proved by practice that a satisfactory effect is obtained.

本发明中桩基础型式视具体要求,可以采取桩—柱基础、桩—梁基础、桩—墙基础、桩—筏基础、桩—箱基础等,相应布桩方式可采用柱下布桩、墙下布桩、满堂布桩、局部满堂布桩等方式。 The type of pile foundation in the present invention depends on specific requirements, and can adopt pile-column foundation, pile-beam foundation, pile-wall foundation, pile-raft foundation, pile-box foundation, etc. Bottom piles, full house piles, partial full house piles and other methods.

参见图1、图2和图3,本发明的湿陷性黄土地基的施工方法,采用SDDC桩和灌注桩(以钻孔灌注桩为例)后压浆技术联合处理湿陷性黄土地基的湿陷性,具体包括下列步骤: Referring to Fig. 1, Fig. 2 and Fig. 3, the construction method of the collapsible loess foundation of the present invention uses SDDC piles and cast-in-situ piles (taking bored cast-in-situ piles as an example) post-grouting technology to jointly treat the wetness of collapsible loess foundations. Trapped, specifically include the following steps:

一、SDDC桩2的施工。 1. Construction of SDDC pile 2.

步骤一,核查地质资料,结合设计参数,选择合适的成孔施工机具; Step 1: Check the geological data, combine with the design parameters, and select the appropriate hole-forming construction equipment;

步骤二,平整场地,清除地上障碍物,标记处理场地范围内的地下构造物及管线,保持场地平整; Step 2: Level the site, remove obstacles on the ground, mark and deal with underground structures and pipelines within the scope of the site, and keep the site level;

步骤三,测量放线,定出控制轴线、打桩场地边线并标识; Step 3: Measure and set out the line, determine the control axis and the sideline of the piling site and mark it;

步骤四,应用步骤一中选择的施工机具,冲击成孔。成孔施工机具一般采用带桩架的桩机,冲击锤选用橄榄形超重锤。桩机就位、对正、调平后,起吊重锤到达设计高度(一般可提升至10m~18m),橄榄形超重锤自动脱钩,借助橄榄形超重锤的动能冲入土中,反复进行上述操作,直至孔深达到设计要求; Step 4, use the construction machine tool selected in Step 1 to impact and form holes. The hole-forming construction equipment generally adopts a pile driver with a pile frame, and the impact hammer adopts an olive-shaped overweight hammer. After the pile driver is in place, aligned and leveled, the hoisting hammer reaches the design height (generally it can be lifted to 10m~18m), the olive-shaped overweight hammer is automatically unhooked, and the kinetic energy of the olive-shaped overweight hammer is used to rush into the soil, and the above-mentioned steps are repeated. Operate until the hole depth meets the design requirements;

步骤五,分层填料,夯击成桩。用标准料斗或运料车将按设计拌和好的定量填料(不可选用砖块、毛石、混凝土块等大块坚硬材料作为填料)分层填入桩孔,然后用成孔时的橄榄形超重锤将填料逐一分层夯实,直至成SDDC桩2。每个桩孔应夯填至桩顶设计标高以上至少0.5m;其中,成孔及填料夯实的施工顺序间隔进行; Step 5: fill in layers and ram them into piles. Use a standard hopper or a transport truck to fill the quantitative filler mixed according to the design (bricks, rough stones, concrete blocks and other large hard materials cannot be used as fillers) into the pile holes in layers, and then use the olive-shaped overweight when the holes are formed. The hammer tamps the filler layer by layer until it becomes SDDC pile 2. Each pile hole should be tamped to at least 0.5m above the design elevation of the pile top; among them, the construction sequence of hole formation and filling tamping is carried out at intervals;

步骤六,施工机械移位。重复步骤四、步骤五,直至SDDC桩2全部完成; Step six, shifting the construction machinery. Repeat steps 4 and 5 until all SDDC piles 2 are completed;

步骤七,开挖探井采集SDDC桩2的桩身填料试样和桩间土1(上部具有湿陷性的土体)试样,做室内常规土工试验,具体要求如下: Step 7: Excavate exploratory wells to collect pile body filler samples of SDDC pile 2 and soil between piles 1 (soil with collapsibility in the upper part) samples, and do indoor routine geotechnical tests. The specific requirements are as follows:

(1)按规范取桩间土1及SDDC桩2桩身填料试样若干,做室内常规土工试验,其结果应满足桩间土1的挤密系数不小于0.93,SDDC桩2的桩身的压密系数不小于0.97; (1) According to the specifications, take a number of filling samples of soil between piles 1 and pile body of SDDC pile 2, and do indoor routine geotechnical tests. The results should satisfy that the compaction coefficient of soil between piles 1 and The compaction coefficient is not less than 0.97;

(2)湿陷性评价。为进一步确定湿陷性的消除程度,在场地上开挖探井采集三SDDC桩2形心处桩间土1的不扰动土试样,进行室内常规土工试验,根据室内试验结果,判定湿陷性的消除程度是否满足设计要求。 (2) Collapsibility evaluation. In order to further determine the degree of collapsibility elimination, exploratory wells were excavated on the site to collect undisturbed soil samples of the soil 1 between the piles at the centroid of the three SDDC piles 2, and the indoor routine geotechnical test was carried out. According to the indoor test results, the collapsibility was determined Whether the degree of elimination meets the design requirements.

若以上各指标已满足设计要求,则进行钻孔灌注桩后压浆的施工;否则进行SDDC桩2的补桩施工; If the above indicators have met the design requirements, carry out the construction of grouting after the bored pile; otherwise, carry out the construction of SDDC pile 2;

步骤八,在进行钻孔灌注桩4施工之前,采用100mm厚C15混凝土对已采用SDDC桩2处理过的地面进行硬化处理; Step eight, before carrying out the construction of the bored pile 4, use 100mm thick C15 concrete to harden the ground that has been treated with the SDDC pile 2;

二、钻孔灌注桩4后压浆施工 2. Post grouting construction of bored pile 4

步骤九,采用全站仪利用指定的轴线交点作控制点,对钻孔灌注桩4桩位放样、定位,钻孔灌注桩4的桩位方向距离误差不小于5mm,并用长钉对桩位进行一一标记; Step 9: Use the total station to use the designated axis intersection as the control point to stake out and position the 4 pile positions of the bored piles. mark one by one;

步骤十,钢筋笼制作、验收: Step 10, production and acceptance of reinforcement cage:

采用桩身预埋管压浆法,即按设计的压浆深度要求,将注浆管5固定在钢筋笼上,压浆装置随钢筋笼一起下放。注浆管5之间采用丝扣连接避免焊接; The pile body pre-buried pipe grouting method is used, that is, the grouting pipe 5 is fixed on the steel cage according to the designed grouting depth, and the grouting device is lowered together with the steel cage. The grouting pipes 5 are connected by screw to avoid welding;

步骤十一,钻孔机就位,并保持钻孔机平稳,不发生倾斜、位移; Step eleven, the drilling machine is in place, and the drilling machine is kept stable without tilting or displacement;

步骤十二,调直钻孔机架挺杆,用对位圈对好钻孔灌注桩4桩位,开动钻孔机钻进、出土,达到控制深度后,在孔底处进行空转清土后停钻、提钻;成孔质量保证措施是: Step 12: Straighten the tappets of the drilling frame, use the alignment ring to align the 4 pile positions of the bored piles, start the drilling machine to drill and excavate, and after reaching the control depth, perform idling at the bottom of the hole to clear the soil Drilling stops and drilling; hole quality assurance measures are:

1)用测深绳/锤测孔深及虚土厚度不应超过100mm; 1) The depth of the hole measured with the sounding rope/hammer and the thickness of the virtual soil should not exceed 100mm;

2)保持孔内泥浆液面的高度防止缩孔、塌孔; 2) Keep the height of the mud liquid level in the hole to prevent shrinkage and collapse;

步骤十三,移动钻孔机到下一钻孔灌注桩4桩位,重复步骤十一和步骤十二,直至完成所有钻孔灌注桩4的成孔作业; Step 13, move the drilling machine to the next bored pile 4 pile position, repeat step 11 and step 12, until the hole-forming operation of all bored piles 4 is completed;

步骤十四,将事先制作的安装好注浆管5的钢筋笼吊装下放,钢筋笼放入前绑好砂浆垫块或塑料卡,吊放钢筋笼时,要对准孔位,吊直扶稳,缓慢下沉,避免碰撞孔壁;钢筋笼放到设计位置时,应立即固定;在两段钢筋笼之间的连接处进行焊接,以确保钢筋笼的位置正确,保证保护层厚度符合要求; Step 14: Hoist and lower the prefabricated reinforcement cage installed with the grouting pipe 5. Before placing the reinforcement cage, tie the mortar block or plastic card. Slowly sink to avoid collision with the hole wall; when the steel cage is placed in the design position, it should be fixed immediately; weld the joint between the two steel cages to ensure that the position of the steel cage is correct and the thickness of the protective layer meets the requirements;

步骤十五,注浆管5试水。每节压浆管5随钢筋笼下放时应做试水试验,若发现水柱下降或水柱消失,则应检查压浆管5是否有砂眼、丝扣连接是否密封。 Step fifteen, the grouting pipe 5 tests the water. When each section of the grouting pipe 5 is lowered with the steel cage, a water test should be done. If the water column is found to drop or disappear, check whether the grouting pipe 5 has sand holes and whether the screw connection is sealed.

钢筋笼放置完毕后孔内进行第二次清孔完成后需再次检查孔内水面,无异常后用堵头封住注浆管5上口; After the reinforcement cage is placed, carry out the second cleaning in the hole, and then check the water surface in the hole again. If there is no abnormality, seal the upper opening of the grouting pipe 5 with a plug;

步骤十六,浇筑混凝土。用放溜筒浇筑混凝土,在放溜筒前再次检查和测量钻孔内虚土的厚度,达到设计要求时进行,混凝土浇筑采用连续进行,混凝土浇筑到钻孔灌注桩4的桩顶时,应适当超过钻孔灌注桩4的桩顶设计标高,以保证在凿除浮浆后,钻孔灌注桩4的桩顶标高符合设计要求。同时,制作同一配合比的试块,每班不得少于一组; Step sixteen, pouring concrete. Concrete is poured with a chute, and the thickness of the virtual soil in the borehole is checked and measured again before the chute is released, and it is carried out when the design requirements are met. The concrete pouring is carried out continuously. When the concrete is poured to the top of the bored pile 4, the Appropriately exceed the design elevation of the pile top of the bored pile 4 to ensure that the pile top elevation of the bored pile 4 meets the design requirements after the laitance is removed. At the same time, make no less than one group of test blocks with the same mix ratio;

步骤十七,压水试验:压水试验在成桩后24小时内进行。正式压浆前必须进行压水试验,以检查管路及单向阀的畅通状况。 Step seventeen, water pressure test: the water pressure test is carried out within 24 hours after the pile is formed. Before formal grouting, a water pressure test must be carried out to check the smoothness of the pipeline and check valve.

若在桩侧或桩端发生扩孔、塌孔或充盈系数较大的情况时,需特别注意提前进行压水试验,在混凝土浇筑完的5小时内进行以确保能冲开较厚的混凝土覆盖层。 If hole expansion, hole collapse or large filling coefficient occurs on the pile side or pile end, special attention should be paid to the pressure water test in advance, and it should be carried out within 5 hours after the concrete is poured to ensure that the thicker concrete cover can be washed away layer.

试验时由专人记录冲破压力值及管道畅通情况; During the test, a special person shall record the breakthrough pressure value and the smoothness of the pipeline;

步骤十八,重复步骤十四、步骤十五、步骤十六、步骤十七,完成各钻孔灌注桩4的成桩工作,同时为后压浆施工做好准备工作; Step 18, repeat step 14, step 15, step 16, and step 17, complete the pile-forming work of each bored pile 4, and prepare for post-grouting construction at the same time;

步骤十九,后压浆施工。采取二次注浆的方式,以充分发挥注浆的作用,获得更佳效果。 Step nineteen, post grouting construction. The method of secondary grouting is adopted to give full play to the effect of grouting and obtain better results.

(1)初注:钻孔灌注桩4桩身混凝土养护3~5天后开始压浆,将按设计配置好的水泥浆通过高压泵和预埋压浆管5注入到桩底或桩侧土层中去,若为复式压浆,则一般先进行桩侧压浆,12小时后再进行桩底压浆。初注时压力要小,浆液由稀到稠。初注时要密切注意注浆压力、注浆量的变化,并注意注浆节奏。桩底注浆时应设置百分表检测桩的上抬量,避免过大。 (1) Preliminary injection: After 3 to 5 days of concrete curing for the bored cast-in-place pile 4, grouting will start, and the cement slurry configured according to the design will be injected into the bottom of the pile or the soil layer on the side of the pile through the high-pressure pump and the pre-embedded grouting pipe 5 In the middle, if it is compound grouting, the pile side grouting is generally carried out first, and the pile bottom grouting is carried out after 12 hours. The pressure at the initial injection should be small, and the slurry will be thin to thick. During the initial injection, pay close attention to the changes of the grouting pressure and the amount of grouting, and pay attention to the grouting rhythm. When grouting at the bottom of the pile, a dial indicator should be set to detect the lifting amount of the pile to avoid excessive.

(2)二次注浆:第二次注浆的注浆管5最好与第一次注浆的注浆管5成对称分布。第二次注浆量一般为第一次的1∕3~1∕4,水灰比可适当提高。 (2) Secondary grouting: the grouting pipes 5 for the second grouting are preferably distributed symmetrically with the grouting pipes 5 for the first grouting. The amount of grouting for the second time is generally 1/3~1/4 of the first time, and the water-cement ratio can be increased appropriately.

(3)同一根桩的压浆顺序:先对上侧管进行压浆,然后下侧管,最后进行端管压浆;同一承台桩的压浆顺序:先四周桩后中心桩。 (3) The grouting sequence of the same pile: grouting the upper pipe first, then the lower pipe, and finally the end pipe; the grouting sequence of the same pile cap: first the surrounding piles and then the central pile.

步骤二十,终止压浆。终止压浆的总的控制原则以压浆量为主,压力控制为辅。但压浆参数还应根据地质条件合理选择,如若桩端为密实的砾石卵石层时,应以压浆量为主要控制指标;因桩侧为密实的黄土层时则应以压浆压力为主要控制指标。 Step 20, stop grouting. The general control principle of terminating grouting is mainly based on grouting volume, supplemented by pressure control. However, the grouting parameters should also be reasonably selected according to the geological conditions. For example, if the pile end is a dense gravel and pebble layer, the grouting amount should be the main control index; if the pile side is a dense loess layer, the grouting pressure should be the main control index. control indicators.

压浆完毕后立即给压浆管5拧上堵头,以免因回浆而降低压浆效果。 Immediately after the grouting is finished, screw the plug on the grouting pipe 5, so as not to reduce the grouting effect due to grouting back.

步骤二十一,重复步骤十九、步骤二十,连续完成各个钻孔灌注桩4后压浆的施工工作。 In step 21, repeat steps 19 and 20 to continuously complete the post-grouting construction work of each bored pile 4 .

冬、雨期施工注意事项: Precautions for construction in winter and rainy seasons:

(1)冬期当温度低于0℃以下浇筑棍凝土时,应采取加热保温措施。浇筑时,混凝土的温度按冬施工方案规定执行。在桩顶未达到设计强度50%以前不得受冻;当气温尚于30℃时应根据具体情况对混凝土采取缓凝措施。 (1) In winter, when the temperature is lower than 0°C and concrete is poured, heating and heat preservation measures should be taken. When pouring, the temperature of concrete shall be carried out according to the winter construction plan. Before the pile top reaches 50% of the design strength, it must not be frozen; when the temperature is still above 30°C, the concrete should be retarded according to the specific situation.

(2)雨期严格坚持随钻随浇筑混凝土的规定,以防成孔后灌水造成塌孔。现场必须有排水的各种措施,防止地面水流入槽内,造成边坡塌方或基土沉陷、成孔机械倾斜等。 (2) During the rainy season, strictly adhere to the regulations of pouring concrete while drilling to prevent the hole from collapsing after the hole is filled with water. There must be various drainage measures on site to prevent ground water from flowing into the tank, causing slope collapse or subsidence of foundation soil, and tilting of hole-forming machinery.

另外在雨期当场地有积水或土层含水量较高时,冲击成孔吸锤现象严重,此时可采用钻机钻孔,但必须适当增加对孔内填料的夯击次数; In addition, during the rainy season, when there is water on the site or the water content of the soil layer is high, the phenomenon of impacting the hole-forming suction hammer is serious. At this time, drilling rigs can be used to drill holes, but the number of times of tamping on the filler in the hole must be appropriately increased;

采用本发明的方法进行施工时,SDDC桩2的填料不选用砖块、毛石、混凝土块或其他大块坚硬材料。 When adopting the method of the present invention to carry out construction, the filler of SDDC pile 2 does not select brick, rubble, concrete block or other large hard materials for use.

灌注桩基础设计时,将SDDC桩2处理后的地基视为复合地基,且不考虑SDDC桩2的桩位布置,处理区土体物理力学指标采用平均值,地基下部无湿陷性的天然土层3的物理力学指标采用地质勘察报告提供的数据。 In the design of cast-in-situ pile foundation, the foundation treated by SDDC pile 2 is regarded as a composite foundation, and the pile position layout of SDDC pile 2 is not considered. The physical and mechanical indicators of layer 3 adopt the data provided by the geological survey report.

上面以举例方式对本发明进行了具体说明,但本发明不限于上述具体实施例。 The present invention has been specifically described above by way of examples, but the present invention is not limited to the above specific examples.

下面是对本发明的原理进行说明。 The principle of the present invention is explained below.

孔内深层超强夯法(SDDC)在成孔过程中,迫使孔内原状土侧向挤出,使桩周一定范围内的土体受到挤压、扰动和重塑,在填料时,迫使孔内填料再次侧向挤压孔壁,使桩周更大范围内的土体再次受到挤压、扰动和重塑,强夯巨大的夯击能量产生的波和动应力反复作用,迫使土骨架产生塑性变形,从而提高土的密实度和抗剪强度,改善土的变形特性,形成的串珠状桩体与桩间土相咬合,承载力高,因成孔时的强挤密作用,此法消除黄土湿陷性效果方面较其他方法更为有效。其加固机理主要有以下四点: In-hole deep super dynamic compaction method (SDDC) forces the undisturbed soil in the hole to extrude laterally during the hole forming process, so that the soil within a certain range around the pile is squeezed, disturbed and reshaped. When filling, the hole is forced to The inner filler squeezes the hole wall laterally again, causing the soil in a larger area around the pile to be squeezed, disturbed and reshaped again. The waves and dynamic stress generated by the huge ramming energy of dynamic compaction act repeatedly, forcing the soil skeleton to form Plastic deformation, thereby improving the compactness and shear strength of the soil, improving the deformation characteristics of the soil, and the formed beaded piles are interlocked with the soil between the piles, and the bearing capacity is high. Due to the strong compaction during hole formation, this method eliminates The effect of loess collapsibility is more effective than other methods. Its reinforcement mechanism mainly has the following four points:

(1)成孔及成桩过程中对原上的动力挤密作用; (1) The dynamic compaction effect on the original during the process of hole formation and pile formation;

(2)桩体充填置换作用(包括桩身及挤入桩间土的骨料); (2) Pile body filling and displacement (including the pile body and the aggregate squeezed into the soil between the piles);

(3)采用灰土时,生石灰的水化和胶凝作用(化学置换)。在湿陷性黄土地区,通过SDDC法处理的地基在改善土体物理力学性状的同时能够有效消除湿陷性。然后,在形成的SDDC桩复合地基上进行采用后压浆技术联合的灌注桩的设计与施工。 (3) When lime soil is used, the hydration and gelation of quicklime (chemical replacement). In the collapsible loess area, the foundation treated by the SDDC method can effectively eliminate the collapsibility while improving the physical and mechanical properties of the soil. Then, on the formed SDDC pile composite foundation, the design and construction of the cast-in-place pile combined with post-grouting technology are carried out.

后压浆施工过程中采用复式压浆技术的灌注桩加固机理主要有: The reinforcement mechanism of cast-in-situ piles using compound grouting technology in post-grouting construction mainly includes:

(1)渗透固结作用; (1) Osmotic consolidation;

(2)挤密充填作用; (2) Compact filling effect;

(3)劈裂加筋作用; (3) Splitting and reinforcing effect;

(4)扩底扩径效应。 (4) The effect of expanding the bottom and expanding the diameter.

在上述机理作用下,使地基土体的物理力学性状得到进一步改善,使注浆处黄土的湿陷性得到进一步消除,灌注桩的承载力得到大幅提高,相同荷载下桩基础沉降量大幅减小。 Under the action of the above mechanism, the physical and mechanical properties of the foundation soil are further improved, the collapsibility of the loess at the grouting place is further eliminated, the bearing capacity of the cast-in-situ pile is greatly improved, and the settlement of the pile foundation is greatly reduced under the same load .

综上所述,采用本发明的黄土地基湿陷性的施工方法与传统的方法相比,其创新性贡献为: In summary, compared with the traditional method, the innovative contribution of the loess foundation collapsible construction method of the present invention is as follows:

(1)在上述两方面作用下,黄土地基的湿陷性得以消除,进而因黄土地基湿陷性所造成的桩侧负摩阻力问题得以解决,因此桩基础可按不考虑负摩擦力的常规桩基础进行设计; (1) Under the effects of the above two aspects, the collapsibility of the loess foundation can be eliminated, and then the problem of negative friction on the pile side caused by the collapsibility of the loess foundation can be solved. pile foundation design;

(2)因为灌注桩采用了SDDC桩和灌注桩后压浆技术联合联合处理,所以桩承载力的大幅提高、相同荷载作用下桩基础沉降量大幅减小。因此,在满足规范要求的前提下可有效缩短桩长,大幅提高经济效益。又因桩基础具有承载力大和抵御复杂荷载能力强的特点,根据工程特点进行合理设计后,能够满足上部高层建筑物(高耸构筑物)对基础的稳定性和差异性沉降的要求。 (2) Because the cast-in-place piles are treated jointly with SDDC piles and the post-grouting technology of the cast-in-place piles, the bearing capacity of the piles is greatly improved, and the settlement of the pile foundation is greatly reduced under the same load. Therefore, the pile length can be effectively shortened under the premise of meeting the specification requirements, and the economic benefit can be greatly improved. And because the pile foundation has the characteristics of large bearing capacity and strong ability to resist complex loads, after reasonable design according to engineering characteristics, it can meet the stability and differential settlement requirements of the upper high-rise buildings (tall structures) on the foundation.

Claims (2)

1. the job practices of a collapsible loess foundation is characterized in that, this method at first adopts SDDC stake method that ground is carried out in the loess place with settlement by soaking and handles; Then, gather undisturbed soil at the scene, carry out laboratory test by standard, record the compacted coefficient of inter-pile soil and SDDC stake pile body coefficient of consolidation, and carry out the settlement by soaking evaluation, if having when not satisfying design specifications in three indexs, then carry out the piling construction of SDDC stake, until meeting design requirement; Carry out the construction of filling pile ' s after grouting then; Concrete job practices may further comprise the steps:
Step 1 is verified geologic information, in conjunction with design parameters, selects suitable drilling construction facility;
Step 2, obstruction is on the ground removed in smooth place, and undreground works and pipeline in the scope of mark disposal field keep levelling of the land;
Step 3 is measured unwrapping wire, makes control axis, piling site boundary and sign;
Step 4, the construction equipment of selecting in the applying step one, impact holing, drilling construction facility adopt the stake machine of band pile frame, and jump bit is selected the overweight hammer of olive shape for use, pile-forming machine perching, align, after the leveling, the lifting weight arrives design height, and the overweight hammer of olive shape is automatically-unhooked, pours in the soil by the kinetic energy of the overweight hammer of olive shape, carry out aforesaid operations repeatedly, reach designing requirement until hole depth;
Step 5, the layering filler, ram pile:
To insert a hole by the quantitative filler layering that design is mixed and stirred with standard hopper or dumper, the overweight hammer of the olive shape when using pore-forming then is with filler compaction in layers one by one, until pile; And each hole should be rammed and be filled to more than the design elevation of top 0.5m at least; Wherein, the sequence of construction of pore-forming and filling tamped is carried out at interval;
Step 6, construction machinery move to next stake position, and repeating step four, step 5 are all finished until stake;
Step 7, pile body filler sample and the inter-pile soil sample of excavation prospect pit collecting pile are done indoor conventional soil test, and specific requirement is as follows:
(1) it is some to get the pile body filler sample of inter-pile soil and stake by standard, does indoor conventional soil test, and the compacted coefficient that its result should satisfy inter-pile soil is not less than 0.93, and the coefficient of consolidation of pile body of stake is not less than 0.97;
(2) settlement by soaking evaluation: for further determining the elimination degree of settlement by soaking, the not disturbed soil sample of three stake centre of form place inter-pile soils is gathered in ground on the scene excavation prospect pit, carry out indoor conventional soil test, according to laboratory test results, judge whether the elimination degree of settlement by soaking meets design requirement;
If above each index meets design requirement, then carry out the construction of filling pile ' s after grouting; Otherwise carry out the piling construction of stake;
Step 8 before carrying out filling pile construction, adopts the thick C15 concrete of 100mm that cure process is carried out on the ground of adopting pile and handling;
Step 9 adopts total powerstation to utilize the crossing point of axes of appointment to do the control point, and to the setting-out of grout pile position, location, the stake position direction range error of castinplace pile is not less than 5mm, and with spike mark is one by one carried out in the stake position;
Step 10 adopts the pre-pipe laying mud jacking of pile body, namely by the mud jacking degree of depth requirement of design, madjack pipe is fixed on the reinforcing cage, and squeezing unit is transferred with reinforcing cage, adopts screwed connection to avoid welding between the madjack pipe;
Step 11, the pore-forming facility are in place, and keep boring machine steady, not run-off the straight, displacement;
Step 12 is adjusted boring machine, to good grout pile position, starts boring machine with the contraposition circle, reach controlling depth after, carry out hole operation clearly;
Step 13, mobile pore-forming facility are to next castinplace pile position, and repeating step 11 and step 12 are until the pore-forming operation of finishing all castinplace piles;
Step 14 is transferred the reinforcing bar cage hoisting of making in advance that installs Grouting Pipe, ties up mortar cushion block or plastic clip before reinforcing cage is put into, and during install reinforcing cage, the mating holes position, hangs and directly holds up surely, slowly sinks, and avoids colliding hole wall; When reinforcing cage is put into design attitude, should fix immediately; Weld junction between two sections reinforcing cages, to guarantee the correct position of reinforcing cage, guarantees that protective layer thickness meets the requirements;
Step 15, madjack pipe tries the water: should do the test of trying the water when every joint madjack pipe is transferred with reinforcing cage, if find that water column descends or water column disappears, should check then whether madjack pipe has sand holes, screwed connection whether to seal;
Reinforcing cage is placed and is carried out in the metapore that finishes needing again the water surface in the inspection eye after the second time, finished in clear hole, and it is suitable for reading that no abnormal back seals madjack pipe with plug;
Step 10 six, concreting: with putting a slide tube concreting, before putting the slide tube, check and measure the thickness of loosened soil in the boring again, carry out when reaching designing requirement, concreting is adopted and is carried out continuously, when concreting is pushed up to the stake of castinplace pile, should suitably surpass the stake top design elevation of castinplace pile, to guarantee that after cutting laitance the stake top mark height of castinplace pile adheres to specification; Simultaneously, make the test block of same match ratio, per tour must not be less than one group;
Step 10 seven, packer permeability test: packer permeability test carries out in 24 hours behind pile, must carry out packer permeability test before the formal mud jacking, to check the unimpeded situation of pipeline and one way valve, if during the situation that in stake side or stake end reaming takes place, collapse hole or fullness coefficient is bigger, need pay special attention to carry out in advance packer permeability test, carry out guaranteeing to wash open thicker concrete coating in concreting in intact 5 hours; Break through force value and the unimpeded situation of pipeline by special messenger's record during test;
Step 10 eight, repeating step 14, step 15, step 10 six, step 10 seven are finished the pile work of each castinplace pile, are the ready work of back mud jacking construction simultaneously;
Step 10 nine, back mud jacking construction: take the mode of secondary grouting, comprising:
(1) just annotate: the concrete curing of castinplace pile pile body began mud jacking after 3~5 days, at the bottom of will being injected into by high-pressure pump and pre-buried madjack pipe by the good cement paste of design configurations or go in the stake side soil layer, if adopt compound mud jacking, then carry out a side pressure slurry earlier, carry out pile base grouting after 12 hours again; Pressure is little when just annotating, slurries by rare to thick; To keep a close eye on the variation of grouting pressure, grouting amount when just annotating, and note slip casting rhythm, should arrange during pile grouting dial gage detect stake on the amount of lifting, avoid excessive;
(2) secondary grouting: the Grouting Pipe of slip casting for the second time is symmetrically distributed with the Grouting Pipe of slip casting for the first time, and grouting amount is generally primary 1 ∕, 3~1 ∕ 4 for the second time, and water/binder ratio suitably improves;
(3) mud jacking of same pile order: earlier last side pipe is carried out mud jacking, descend side pipe then, hold the pipe mud jacking at last; The mud jacking order of same cushion cap stake: stake rear center stake earlier;
Step 2 ten stops mud jacking: the total control principle that stops mud jacking is that pressure is controlled to be auxilliary based on the mud jacking amount, but the mud jacking parameter is according to the geological conditions choose reasonable, if the stake end during for closely knit gravel boulder bed, should be the major control index with the mud jacking amount; The stake side should be the major control index with mud jacking pressure then when being closely knit loess formation;
After mud jacking finishes immediately to the madjack pipe plug of screwing on, in order to avoid reduce squeezing quality because of overfall;
Step 2 11, repeating step 19, step 2 ten are finished the construction working of each filling pile ' s after grouting continuously.
2. the method for claim 1 is characterized in that, the filler of described pile is not selected fragment of brick, rubble, concrete block or other bulk stiff materials for use.
CN 201110123842 2011-05-13 2011-05-13 A construction method of collapsible loess foundation Expired - Fee Related CN102277867B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201110123842 CN102277867B (en) 2011-05-13 2011-05-13 A construction method of collapsible loess foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201110123842 CN102277867B (en) 2011-05-13 2011-05-13 A construction method of collapsible loess foundation

Publications (2)

Publication Number Publication Date
CN102277867A CN102277867A (en) 2011-12-14
CN102277867B true CN102277867B (en) 2013-10-09

Family

ID=45103570

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201110123842 Expired - Fee Related CN102277867B (en) 2011-05-13 2011-05-13 A construction method of collapsible loess foundation

Country Status (1)

Country Link
CN (1) CN102277867B (en)

Cited By (55)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US11079725B2 (en) 2019-04-10 2021-08-03 Deere & Company Machine control using real-time model
US11178818B2 (en) 2018-10-26 2021-11-23 Deere & Company Harvesting machine control system with fill level processing based on yield data
US11234366B2 (en) 2019-04-10 2022-02-01 Deere & Company Image selection for machine control
US11240961B2 (en) 2018-10-26 2022-02-08 Deere & Company Controlling a harvesting machine based on a geo-spatial representation indicating where the harvesting machine is likely to reach capacity
US11467605B2 (en) 2019-04-10 2022-10-11 Deere & Company Zonal machine control
US11474523B2 (en) 2020-10-09 2022-10-18 Deere & Company Machine control using a predictive speed map
US11477940B2 (en) 2020-03-26 2022-10-25 Deere & Company Mobile work machine control based on zone parameter modification
US11592822B2 (en) 2020-10-09 2023-02-28 Deere & Company Machine control using a predictive map
US11641800B2 (en) 2020-02-06 2023-05-09 Deere & Company Agricultural harvesting machine with pre-emergence weed detection and mitigation system
US11650587B2 (en) 2020-10-09 2023-05-16 Deere & Company Predictive power map generation and control system
US11653588B2 (en) 2018-10-26 2023-05-23 Deere & Company Yield map generation and control system
US11672203B2 (en) 2018-10-26 2023-06-13 Deere & Company Predictive map generation and control
US11675354B2 (en) 2020-10-09 2023-06-13 Deere & Company Machine control using a predictive map
US11711995B2 (en) 2020-10-09 2023-08-01 Deere & Company Machine control using a predictive map
US11727680B2 (en) 2020-10-09 2023-08-15 Deere & Company Predictive map generation based on seeding characteristics and control
US11778945B2 (en) 2019-04-10 2023-10-10 Deere & Company Machine control using real-time model
US11825768B2 (en) 2020-10-09 2023-11-28 Deere & Company Machine control using a predictive map
US11845449B2 (en) 2020-10-09 2023-12-19 Deere & Company Map generation and control system
US11844311B2 (en) 2020-10-09 2023-12-19 Deere & Company Machine control using a predictive map
US11849672B2 (en) 2020-10-09 2023-12-26 Deere & Company Machine control using a predictive map
US11849671B2 (en) 2020-10-09 2023-12-26 Deere & Company Crop state map generation and control system
US11864483B2 (en) 2020-10-09 2024-01-09 Deere & Company Predictive map generation and control system
US11871697B2 (en) 2020-10-09 2024-01-16 Deere & Company Crop moisture map generation and control system
US11874669B2 (en) 2020-10-09 2024-01-16 Deere & Company Map generation and control system
US11889788B2 (en) 2020-10-09 2024-02-06 Deere & Company Predictive biomass map generation and control
US11889787B2 (en) 2020-10-09 2024-02-06 Deere & Company Predictive speed map generation and control system
US11895948B2 (en) 2020-10-09 2024-02-13 Deere & Company Predictive map generation and control based on soil properties
US11927459B2 (en) 2020-10-09 2024-03-12 Deere & Company Machine control using a predictive map
US11946747B2 (en) 2020-10-09 2024-04-02 Deere & Company Crop constituent map generation and control system
US11957072B2 (en) 2020-02-06 2024-04-16 Deere & Company Pre-emergence weed detection and mitigation system
US11983009B2 (en) 2020-10-09 2024-05-14 Deere & Company Map generation and control system
US12010947B2 (en) 2018-10-26 2024-06-18 Deere & Company Predictive machine characteristic map generation and control system
US12013245B2 (en) 2020-10-09 2024-06-18 Deere & Company Predictive map generation and control system
US12035648B2 (en) 2020-02-06 2024-07-16 Deere & Company Predictive weed map generation and control system
US12058951B2 (en) 2022-04-08 2024-08-13 Deere & Company Predictive nutrient map and control
US12069978B2 (en) 2018-10-26 2024-08-27 Deere & Company Predictive environmental characteristic map generation and control system
US12069986B2 (en) 2020-10-09 2024-08-27 Deere & Company Map generation and control system
US12082531B2 (en) 2022-01-26 2024-09-10 Deere & Company Systems and methods for predicting material dynamics
US12127500B2 (en) 2021-01-27 2024-10-29 Deere & Company Machine control using a map with regime zones
US12178158B2 (en) 2020-10-09 2024-12-31 Deere & Company Predictive map generation and control system for an agricultural work machine
US12225846B2 (en) 2020-02-06 2025-02-18 Deere & Company Machine control using a predictive map
US12229886B2 (en) 2021-10-01 2025-02-18 Deere & Company Historical crop state model, predictive crop state map generation and control system
US12245549B2 (en) 2022-01-11 2025-03-11 Deere & Company Predictive response map generation and control system
US12250905B2 (en) 2020-10-09 2025-03-18 Deere & Company Machine control using a predictive map
US12284934B2 (en) 2022-04-08 2025-04-29 Deere & Company Systems and methods for predictive tractive characteristics and control
US12298767B2 (en) 2022-04-08 2025-05-13 Deere & Company Predictive material consumption map and control
US12295288B2 (en) 2022-04-05 2025-05-13 Deere &Company Predictive machine setting map generation and control system
US12302791B2 (en) 2021-12-20 2025-05-20 Deere & Company Crop constituents, predictive mapping, and agricultural harvester control
US12310286B2 (en) 2021-12-14 2025-05-27 Deere & Company Crop constituent sensing
US12329148B2 (en) 2020-02-06 2025-06-17 Deere & Company Predictive weed map and material application machine control
US12358493B2 (en) 2022-04-08 2025-07-15 Deere & Company Systems and methods for predictive power requirements and control
US12386354B2 (en) 2020-10-09 2025-08-12 Deere & Company Predictive power map generation and control system
US12419220B2 (en) 2020-10-09 2025-09-23 Deere & Company Predictive map generation and control system
US12422847B2 (en) 2020-10-09 2025-09-23 Deere & Company Predictive agricultural model and map generation
US12520759B2 (en) 2022-01-26 2026-01-13 Deere & Company Systems and methods for predicting material dynamics

Families Citing this family (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102535315B (en) * 2012-01-10 2015-01-21 江苏建筑职业技术学院 Treatment method for suspending concrete pavement slab
CN103790148A (en) * 2014-01-07 2014-05-14 西安科技大学 Combined treatment construction method for collapsible loess foundation
CN104727295B (en) * 2015-03-26 2016-10-26 中化岩土工程股份有限公司 Preexisting hole filler displacement hammer flattener heavy-tamping method
CN105954499B (en) * 2016-06-26 2019-01-18 兰州理工大学 Saturated yielding Loess Site carries out saturated yielding place evaluating method and device after fracture grouting reinforcing
CN107059912A (en) * 2017-03-20 2017-08-18 中国十七冶集团有限公司 A kind of people's goods elevator foundation slip casting reinforcing and processing method for being seated soft soil horizon
CN106989993B (en) * 2017-05-22 2023-08-11 嘉兴学院 A layered in-situ test device and test method for loess collapsibility coefficient
CN107974888A (en) * 2017-12-01 2018-05-01 江苏中路工程技术研究院有限公司 Construction method of the strength concrete pile as roadbed filling
CN110106882A (en) * 2019-04-28 2019-08-09 云南建投第一勘察设计有限公司 A kind of gas lift reverse circulation device for cast-in-situ bored pile
CN112227356A (en) * 2019-07-15 2021-01-15 河北建设勘察研究院有限公司 Gravel grouting steel pipe pile and preparation method thereof
US11635765B2 (en) 2020-10-09 2023-04-25 Deere & Company Crop state map generation and control system
CN113494134A (en) * 2021-07-05 2021-10-12 浙江东南网架股份有限公司 Inverse installation method of variable cross-section steel pipe forked support column
CN113931164B (en) * 2021-11-01 2023-03-03 西宁碧胜房地产开发有限公司 Club-footed pile construction method for pre-soaking and compacting collapsible loess
CN114016489B (en) * 2021-11-24 2024-12-17 华侨大学 Datum point fixing device for sedimentation monitoring
CN114859016B (en) * 2022-06-21 2024-08-27 西安理工大学 Test method for collapsibility of loess
CN115305761A (en) * 2022-06-23 2022-11-08 中化地质河南局集团有限公司 Collapsible loess roadbed construction method
CN115478532A (en) * 2022-10-08 2022-12-16 中建新疆建工(集团)有限公司 Semi-enhanced non-soil-extrusion pile for eliminating negative friction resistance in collapsible loess area and construction method
CN116927180A (en) * 2023-07-07 2023-10-24 中建三局集团有限公司 Construction method of SDDC pile and long spiral bored pile sleeve pile
CN118017240A (en) * 2024-04-08 2024-05-10 陕西达昊华建筑工程有限公司 Microwave sintering device and method for collapsible loess
CN120801686B (en) * 2025-09-12 2026-01-13 西安理工大学 A Method and System for Evaluating Loess Collapsibility Based on Geophysical Testing Technology

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1116674A (en) * 1995-10-04 1996-02-14 司炳文 Method for handling foundation
JP2003129461A (en) * 2001-10-25 2003-05-08 Tanaka Juki Kensetsu Kk Ground compaction method
JP2003147756A (en) * 2001-11-19 2003-05-21 Fudo Constr Co Ltd Compaction sand pile construction method
CN101660307A (en) * 2009-08-06 2010-03-03 新兴河北工程技术有限公司 Treatment method of collapsible loess foundation

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1116674A (en) * 1995-10-04 1996-02-14 司炳文 Method for handling foundation
JP2003129461A (en) * 2001-10-25 2003-05-08 Tanaka Juki Kensetsu Kk Ground compaction method
JP2003147756A (en) * 2001-11-19 2003-05-21 Fudo Constr Co Ltd Compaction sand pile construction method
CN101660307A (en) * 2009-08-06 2010-03-03 新兴河北工程技术有限公司 Treatment method of collapsible loess foundation

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
俞宗卫等,1.孔内深层超强夯法在湿陷性黄土地区工程中的应用.《建筑结构》.2009,第39卷(第01期),96-98.
孔内深层超强夯法在湿陷性黄土地区工程中的应用;俞宗卫等,1;《建筑结构》;20090125;第39卷(第01期);96-98 *

Cited By (66)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US12178156B2 (en) 2018-10-26 2024-12-31 Deere & Company Predictive map generation and control
US12171153B2 (en) 2018-10-26 2024-12-24 Deere & Company Yield map generation and control system
US11672203B2 (en) 2018-10-26 2023-06-13 Deere & Company Predictive map generation and control
US11240961B2 (en) 2018-10-26 2022-02-08 Deere & Company Controlling a harvesting machine based on a geo-spatial representation indicating where the harvesting machine is likely to reach capacity
US11653588B2 (en) 2018-10-26 2023-05-23 Deere & Company Yield map generation and control system
US12069978B2 (en) 2018-10-26 2024-08-27 Deere & Company Predictive environmental characteristic map generation and control system
US11178818B2 (en) 2018-10-26 2021-11-23 Deere & Company Harvesting machine control system with fill level processing based on yield data
US12010947B2 (en) 2018-10-26 2024-06-18 Deere & Company Predictive machine characteristic map generation and control system
US11778945B2 (en) 2019-04-10 2023-10-10 Deere & Company Machine control using real-time model
US11650553B2 (en) 2019-04-10 2023-05-16 Deere & Company Machine control using real-time model
US12495733B2 (en) 2019-04-10 2025-12-16 Deere & Company Predictive map and machine control
US11467605B2 (en) 2019-04-10 2022-10-11 Deere & Company Zonal machine control
US11234366B2 (en) 2019-04-10 2022-02-01 Deere & Company Image selection for machine control
US11079725B2 (en) 2019-04-10 2021-08-03 Deere & Company Machine control using real-time model
US11829112B2 (en) 2019-04-10 2023-11-28 Deere & Company Machine control using real-time model
US11957072B2 (en) 2020-02-06 2024-04-16 Deere & Company Pre-emergence weed detection and mitigation system
US12035648B2 (en) 2020-02-06 2024-07-16 Deere & Company Predictive weed map generation and control system
US12329148B2 (en) 2020-02-06 2025-06-17 Deere & Company Predictive weed map and material application machine control
US12225846B2 (en) 2020-02-06 2025-02-18 Deere & Company Machine control using a predictive map
US11641800B2 (en) 2020-02-06 2023-05-09 Deere & Company Agricultural harvesting machine with pre-emergence weed detection and mitigation system
US11477940B2 (en) 2020-03-26 2022-10-25 Deere & Company Mobile work machine control based on zone parameter modification
US12069986B2 (en) 2020-10-09 2024-08-27 Deere & Company Map generation and control system
US11849672B2 (en) 2020-10-09 2023-12-26 Deere & Company Machine control using a predictive map
US11864483B2 (en) 2020-10-09 2024-01-09 Deere & Company Predictive map generation and control system
US11871697B2 (en) 2020-10-09 2024-01-16 Deere & Company Crop moisture map generation and control system
US11874669B2 (en) 2020-10-09 2024-01-16 Deere & Company Map generation and control system
US11889788B2 (en) 2020-10-09 2024-02-06 Deere & Company Predictive biomass map generation and control
US11889787B2 (en) 2020-10-09 2024-02-06 Deere & Company Predictive speed map generation and control system
US11895948B2 (en) 2020-10-09 2024-02-13 Deere & Company Predictive map generation and control based on soil properties
US11927459B2 (en) 2020-10-09 2024-03-12 Deere & Company Machine control using a predictive map
US11946747B2 (en) 2020-10-09 2024-04-02 Deere & Company Crop constituent map generation and control system
US11675354B2 (en) 2020-10-09 2023-06-13 Deere & Company Machine control using a predictive map
US11983009B2 (en) 2020-10-09 2024-05-14 Deere & Company Map generation and control system
US11650587B2 (en) 2020-10-09 2023-05-16 Deere & Company Predictive power map generation and control system
US12178158B2 (en) 2020-10-09 2024-12-31 Deere & Company Predictive map generation and control system for an agricultural work machine
US12013698B2 (en) 2020-10-09 2024-06-18 Deere & Company Machine control using a predictive map
US11592822B2 (en) 2020-10-09 2023-02-28 Deere & Company Machine control using a predictive map
US12048271B2 (en) 2020-10-09 2024-07-30 Deere &Company Crop moisture map generation and control system
US11474523B2 (en) 2020-10-09 2022-10-18 Deere & Company Machine control using a predictive speed map
US11844311B2 (en) 2020-10-09 2023-12-19 Deere & Company Machine control using a predictive map
US11727680B2 (en) 2020-10-09 2023-08-15 Deere & Company Predictive map generation based on seeding characteristics and control
US12080062B2 (en) 2020-10-09 2024-09-03 Deere & Company Predictive map generation based on seeding characteristics and control
US12422847B2 (en) 2020-10-09 2025-09-23 Deere & Company Predictive agricultural model and map generation
US11849671B2 (en) 2020-10-09 2023-12-26 Deere & Company Crop state map generation and control system
US12419220B2 (en) 2020-10-09 2025-09-23 Deere & Company Predictive map generation and control system
US12013245B2 (en) 2020-10-09 2024-06-18 Deere & Company Predictive map generation and control system
US11845449B2 (en) 2020-10-09 2023-12-19 Deere & Company Map generation and control system
US12193350B2 (en) 2020-10-09 2025-01-14 Deere & Company Machine control using a predictive map
US12216472B2 (en) 2020-10-09 2025-02-04 Deere & Company Map generation and control system
US11825768B2 (en) 2020-10-09 2023-11-28 Deere & Company Machine control using a predictive map
US12386354B2 (en) 2020-10-09 2025-08-12 Deere & Company Predictive power map generation and control system
US11711995B2 (en) 2020-10-09 2023-08-01 Deere & Company Machine control using a predictive map
US12250905B2 (en) 2020-10-09 2025-03-18 Deere & Company Machine control using a predictive map
US12271196B2 (en) 2020-10-09 2025-04-08 Deere &Company Machine control using a predictive map
US12127500B2 (en) 2021-01-27 2024-10-29 Deere & Company Machine control using a map with regime zones
US12229886B2 (en) 2021-10-01 2025-02-18 Deere & Company Historical crop state model, predictive crop state map generation and control system
US12310286B2 (en) 2021-12-14 2025-05-27 Deere & Company Crop constituent sensing
US12302791B2 (en) 2021-12-20 2025-05-20 Deere & Company Crop constituents, predictive mapping, and agricultural harvester control
US12245549B2 (en) 2022-01-11 2025-03-11 Deere & Company Predictive response map generation and control system
US12082531B2 (en) 2022-01-26 2024-09-10 Deere & Company Systems and methods for predicting material dynamics
US12520759B2 (en) 2022-01-26 2026-01-13 Deere & Company Systems and methods for predicting material dynamics
US12295288B2 (en) 2022-04-05 2025-05-13 Deere &Company Predictive machine setting map generation and control system
US12284934B2 (en) 2022-04-08 2025-04-29 Deere & Company Systems and methods for predictive tractive characteristics and control
US12298767B2 (en) 2022-04-08 2025-05-13 Deere & Company Predictive material consumption map and control
US12358493B2 (en) 2022-04-08 2025-07-15 Deere & Company Systems and methods for predictive power requirements and control
US12058951B2 (en) 2022-04-08 2024-08-13 Deere & Company Predictive nutrient map and control

Also Published As

Publication number Publication date
CN102277867A (en) 2011-12-14

Similar Documents

Publication Publication Date Title
CN102277867B (en) A construction method of collapsible loess foundation
CN102080373B (en) Construction method for jointly treating collapsibility of loess foundation by using DDC (Downhole Dynamic Compaction) pile and pile foundation
CN110230309B (en) Karst area bridge karst cave pile foundation construction method
CN103184734B (en) A kind of construction method implanting slip casting compound pile
CN108797587A (en) A kind of novel sinking construction technology of static pressed pile
CN108894214B (en) Karst cave geological environment cast-in-place pile and pile-forming construction method thereof
CN106988302A (en) A kind of high inclination-angle competent bed rotary digging pile driving construction engineering method
CN108517877B (en) Supporting construction method combining consolidation grouting of hybrid filling ultra-deep foundation pit with double-row steel pipe piles
CN104532957B (en) Existing building sets up basement reversed construction method
CN104895055A (en) Building grouting pile foundation construction method
CN102226336A (en) Ground reinforcement treatment method
CN206070508U (en) Device for reinforcing foundation
CN112281829A (en) Composite pile foundation structure and construction method thereof
CN114108609B (en) A construction method for multi-stage and segmental precise filling deep piles in goaf
CN203213101U (en) Embedding grouting combined pile
CN102400462A (en) Secondary grouting small pile construction process in foundation anti-seismic reinforcement treatment
CN113846618A (en) A kind of foundation treatment dynamic compaction replacement reinforcement method
CN103790148A (en) Combined treatment construction method for collapsible loess foundation
CN115538422A (en) Construction method of cast-in-situ bored pile with bead type karst cave communicated with thick gravel covering layer
CN102995647B (en) A Groundwater Control Method for Pile Hole Grouting and Seepage Isolation
CN112144559B (en) Well construction method in high-water-rich loess sand pebble stratum pressure-variable pipe well
CN114575355B (en) Soil protection construction method
CN209162869U (en) Pile End Construction Recycled Materials Compact and Expand Composite Pile Foundation
CN201339186Y (en) Soft rock concrete replacement pile composite foundation
CN105064332A (en) Construction method for bearing base piles of square pile bodies

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20131009

Termination date: 20140513