CN102031757A - 一种顶进框架桥的底板导向层的施工方法 - Google Patents

一种顶进框架桥的底板导向层的施工方法 Download PDF

Info

Publication number
CN102031757A
CN102031757A CN 201110001494 CN201110001494A CN102031757A CN 102031757 A CN102031757 A CN 102031757A CN 201110001494 CN201110001494 CN 201110001494 CN 201110001494 A CN201110001494 A CN 201110001494A CN 102031757 A CN102031757 A CN 102031757A
Authority
CN
China
Prior art keywords
frame bridge
steel pipe
guiding steel
locator
manhole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN 201110001494
Other languages
English (en)
Other versions
CN102031757B (zh
Inventor
李家稳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
North China University of Technology
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN2011100014941A priority Critical patent/CN102031757B/zh
Publication of CN102031757A publication Critical patent/CN102031757A/zh
Application granted granted Critical
Publication of CN102031757B publication Critical patent/CN102031757B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

本发明涉及一种顶进框架桥的底板导向层的施工方法,包括:在两侧施工工作地坑内分别固定第一定位器和第二定位器,第一定位器或第二定位器都设有一排水平的圆形通孔,圆形通孔的内壁与导向钢管外圆柱面滑动配合,两侧圆形通孔外边的距离比预制框架桥宽度小10-40cm;将导向钢管装入第一定位器的每个圆形通孔,2-5根的一排水平导向钢管的上部表面比预制框架桥的底板低0--5cm;用千斤顶对安放在第一定位器每个圆形通孔中的导向钢管逐节顶推,直至导向钢管穿出路基土层,进入第二定位器的圆形通孔。本发明能保证框架桥准确定向到位,避免偏移、返工,确保顶进框架桥的施工质量;底板导向层坚固耐用、施工方便、工期短、成本低。

Description

一种顶进框架桥的底板导向层的施工方法
技术领域
本发明涉及一种道路立交工程施工方法,特别是一种顶进框架桥的底板导向层的施工方法。
背景技术
在道路立交工程施工中,需要将预制的框架桥顶进、穿过现有铁路或者公路的路基,预制的框架桥顶进施工过程中,经常遇到“扎头(前端下沉)”和“抬头(前端抬起)”的现象,不能平稳顺利地顶进框架桥。在遇到基础地基土质较松时,容易引起“扎头”现象,在遇到基础地基土质较硬时,容易引起“抬头”现象,这些现象严重地影响了顶进的效果和质量,有的甚至导致返工或报废。为了解决这些问题,也提出了一些改进措施,但多数是针对框架桥地板土体进行处理,例如采用旋喷桩或压钢筋混凝土桩等对地基进行加固,这些措施都较复杂、工期长、成本高,效果不明显。
发明内容
本发明的目的是提供一种施工方便、工期短、成本低,效果好的顶进框架桥的底板导向层的施工方法。
本发明的技术方案是:一种顶进框架桥的底板导向层的施工方法,其施工步骤为: 
[1] 在需要穿过的现有铁路或者公路路基两侧挖好施工工作地坑;
[2] 在一侧施工工作地坑内、施工图纸设定的预制框架桥的前方固定第一定位器,在另一侧施工工作地坑内、施工图纸设定的预制框架桥的另一侧固定第二定位器;第一定位器或者第二定位器都设有一排水平的圆形通孔,圆形通孔的内壁与导向钢管外圆柱面滑动配合;一排水平的圆形通孔靠最外边的两个圆形通孔的外侧距离比预制框架桥4的宽度小10-40 cm,导向钢管和圆形通孔的数量相等,为2-5根/个,并按预制框架桥(4)的宽度均布;
 [3] 将导向钢管装入第一定位器的每个圆形通孔,一排水平导向钢管的上部表面比预制框架桥的底板低0--5cm;
[4] 采用千斤顶沿预制框架桥设定的方向,在路基土层中,对安放在第一定位器的每一个圆形通孔中的导向钢管逐节顶推,逐节顶推的导向钢管的长度每节为1—3m,导向钢管外径为20—50cm;同时将推入导向钢管内部的泥土及时取出外运,直至导向钢管穿出路基土层,进入第二定位器的圆形通孔;穿出路基土层,进入第二定位器圆形通孔的一排水平导向钢管构成顶进框架桥的底板导向层;
 [5]在第一节导向钢管的前端内腔设有测量标杆,顶推导向钢管并取出其内部的泥土后,根据测量标杆,从顶推端可观察或者测量顶推方向的偏移量,并适时纠偏。
根据框架桥大小,在未顶进前,先沿施工图纸设定的框架桥底板下方顶进2-5根导向钢管,一般4米以内宽度的预制框架桥采用两根导向钢管;4-8米宽度的预制框架桥采用三根导向钢管;大于8米宽度的预制框架桥采用4-5根导向钢管。具体导向钢管的根数要根据框架桥底板下的土体性质和导向钢管的外径决定。如果框架桥底板下的土体性质较软、导向钢管的外径小、需要的导向钢管根数就较多。
本发明的有益效果是: 
1、 本发明的顶进框架桥的底板导向层能保证框架桥精确定向到位,克服了传统顶进施工过程中 “扎头“或者“抬头”现象,避免返工或报废,确保顶进框架桥的施工质量;
2、 本发明的顶进框架桥的底板导向层坚固耐用、施工方便、工期短、成本低,效果好。
附图说明
图1是本发明的施工示意图。
图2是定位器的结构及安放导向钢管的示意图。
图3是图2的左视图。
具体实施方式
下面结合附图和实施例对本发明进一步说明。
实施例如附图1-3所示:一种顶进框架桥的底板导向层的施工方法,其施工步骤为: 
[1] 框架桥4的宽度为5m,在未顶进前,根据框架桥宽度和地基土质情况先计算出沿施工图纸设定的预制框架桥底板下方顶进三根外径为30cm的圆钢管3;
[2] 在需要穿过的现有铁路或者公路路基两侧挖好施工工作地坑;
[3] 在一侧施工工作地坑内、施工图纸设定的预制框架桥4的前方固定钢管第一定位器2,在另一侧施工工作地坑内、施工图纸设定的预制框架桥4的另一侧固定钢管第二定位器5;第一定位器2或者第二定位器5都设有三个一排的水平圆形通孔7,三个圆形通孔7的内壁与导向钢管3外圆柱面滑动配合。三个一排的水平圆形通孔7靠最外边的两个圆形通孔7的外侧距离比预制框架桥4的宽度小20 cm,导向钢管3与圆形通孔7的数量相等,为三根/个,并按预制框架桥4宽度均布;
[4] 将导向钢管3装入第一定位器2的每个圆形通孔7,一排水平导向钢管3的上部表面比预制框架桥4的底板低3cm,在施工标准允差范围之内;导向钢管3长度每节为2m;
[5] 采用千斤顶1沿预制框架桥设定的方向,在路基土层6中,对对装入第一定位器2的每一个圆形通孔7中的导向钢管3逐节顶推,同时将推入导向钢管3内部的泥土及时取出外运,直至导向钢管3穿出路基土层6,进入第二定位器5的圆形通孔7。穿出路基土层6,进入第二定位器5的圆形通孔7的一排水平导向钢管3构成顶进框架桥的底板导向层。
 在第一节导向钢管3的前端内腔设有测量标杆,顶推导向钢管3并取出其内部的泥土后,根据测量标杆从顶推端可观察或者测量顶推方向的偏移量,并适时纠偏,有效控制钢管顶进过程中不致于偏离预定方向。

Claims (2)

1. 一种顶进框架桥的底板导向层的施工方法,包括预制框架桥,其施工步骤为: 
[1] 在需要穿过的现有铁路或者公路路基的两侧挖好施工工作地坑;
[2] 在一侧施工工作地坑内、施工图纸设定的预制框架桥(4)的前方固定第一定位器(2),在另一侧施工工作地坑内、施工图纸设定的预制框架桥(4)的另一侧固定第二定位器(5);第一定位器(2)或者第二定位器(5)都设有一排水平的圆形通孔(7),圆形通孔(7)的内壁与导向钢管(3)外圆柱面滑动配合;一排水平的圆形通孔(7)靠最外边的两个圆形通孔(7)的外侧距离比预制框架桥(4)的宽度小10--40 cm,导向钢管(3)和圆形通孔(7)的数量相等,为2-5根/个,并按预制框架桥(4)的宽度均布;
[3] 将导向钢管(3)装入第一定位器(2)的每个圆形通孔(7),一排水平导向钢管(3)的上部表面比按施工图纸设定的预制框架桥(4)的底板低0--5cm;
[4] 采用千斤顶(1)沿预制框架桥(4)设定的方向,在路基土层(6)中,对装入第一定位器(2)的每一个圆形通孔(7)中的导向钢管(3)逐节顶推,同时将推入导向钢管(3)内部的泥土及时取出外运,直至导向钢管(3)穿出路基土层(6),进入第二定位器(5)的圆形通孔(7);穿出路基土层(6),进入第二定位器(5)圆形通孔(7)的一排水平导向钢管(3)构成顶进框架桥(4)的底板导向层;
 [5] 在第一节导向钢管(3)的前端内腔设有测量标杆,顶推导向钢管(3)并取出其内部的泥土后,根据测量标杆,从顶推端可观察或者测量顶推方向的偏移量,并适时纠偏。
2.根据权利要求1所述一种顶进框架桥的底板导向层的施工方法,其特征在于:所述对装入第一定位器(2)的每一个圆形通孔(7)中的导向钢管(3)逐节顶推,逐节顶推的导向钢管(3)的长度每节为1—3m,导向钢管(3)外径为20—50cm。
CN2011100014941A 2011-01-06 2011-01-06 一种顶进框架桥的底板导向层的施工方法 Expired - Fee Related CN102031757B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011100014941A CN102031757B (zh) 2011-01-06 2011-01-06 一种顶进框架桥的底板导向层的施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011100014941A CN102031757B (zh) 2011-01-06 2011-01-06 一种顶进框架桥的底板导向层的施工方法

Publications (2)

Publication Number Publication Date
CN102031757A true CN102031757A (zh) 2011-04-27
CN102031757B CN102031757B (zh) 2012-05-30

Family

ID=43885160

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011100014941A Expired - Fee Related CN102031757B (zh) 2011-01-06 2011-01-06 一种顶进框架桥的底板导向层的施工方法

Country Status (1)

Country Link
CN (1) CN102031757B (zh)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103410096A (zh) * 2013-08-15 2013-11-27 中铁六局集团天津铁路建设有限公司 斜交顶进过程中在偏转端利用顶镐进行纠偏的箱体顶进法
CN103866694A (zh) * 2014-03-18 2014-06-18 中铁二十二局集团第一工程有限公司 深水粉砂层地质大跨度多线路加固系统及顶进涵施工方法
CN104652279A (zh) * 2013-11-25 2015-05-27 北京城建设计发展集团股份有限公司 一种新建框架桥上穿既有地铁结构箱涵顶进施工方法
CN104878701A (zh) * 2015-06-26 2015-09-02 东南大学 一种下穿既有线桥涵顶进水平导向纠偏系统

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1807838A (zh) * 2005-10-31 2006-07-26 胡麓山 箱型桥梁的桥式盾构施工方法
CN101343861A (zh) * 2008-08-22 2009-01-14 中铁六局集团有限公司 一种既有铁路线路下新框架桥置换旧框架桥的施工方法
JP2009185564A (ja) * 2008-02-08 2009-08-20 Ihi Corp 橋梁の送り出し工法
CN201530993U (zh) * 2009-11-10 2010-07-21 中铁六局集团有限公司 框架桥箱体顶进设备

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1807838A (zh) * 2005-10-31 2006-07-26 胡麓山 箱型桥梁的桥式盾构施工方法
JP2009185564A (ja) * 2008-02-08 2009-08-20 Ihi Corp 橋梁の送り出し工法
CN101343861A (zh) * 2008-08-22 2009-01-14 中铁六局集团有限公司 一种既有铁路线路下新框架桥置换旧框架桥的施工方法
CN201530993U (zh) * 2009-11-10 2010-07-21 中铁六局集团有限公司 框架桥箱体顶进设备

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
《铁道标准设计》 20090420 李家稳等 管棚和盾构法框架桥设计与施工技术的研究 , 第04期 2 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103410096A (zh) * 2013-08-15 2013-11-27 中铁六局集团天津铁路建设有限公司 斜交顶进过程中在偏转端利用顶镐进行纠偏的箱体顶进法
CN103410096B (zh) * 2013-08-15 2015-06-03 中铁六局集团天津铁路建设有限公司 斜交顶进过程中在偏转端利用顶镐进行纠偏的箱体顶进法
CN104652279A (zh) * 2013-11-25 2015-05-27 北京城建设计发展集团股份有限公司 一种新建框架桥上穿既有地铁结构箱涵顶进施工方法
CN104652279B (zh) * 2013-11-25 2016-08-17 北京城建设计发展集团股份有限公司 一种新建框架桥上穿既有地铁结构箱涵顶进施工方法
CN103866694A (zh) * 2014-03-18 2014-06-18 中铁二十二局集团第一工程有限公司 深水粉砂层地质大跨度多线路加固系统及顶进涵施工方法
CN104878701A (zh) * 2015-06-26 2015-09-02 东南大学 一种下穿既有线桥涵顶进水平导向纠偏系统

Also Published As

Publication number Publication date
CN102031757B (zh) 2012-05-30

Similar Documents

Publication Publication Date Title
CN105421470B (zh) 装配式锚杆拱形骨架复合式生态护坡施工方法
CN103556579A (zh) 一种综合注浆保压加管幕支护的箱涵顶推工法
CN204356594U (zh) 无砟轨道膨胀土路堑-基床构造
CN106522242A (zh) 用于软弱地层紧邻地下结构的基坑支护体系及其施工方法
CN102425082A (zh) 高速铁路岩溶强烈发育车站道岔区路基加固构造
CN202416195U (zh) 一种桥墩偏位纠正与加固系统
CN204199335U (zh) 一种减小phc管桩施工挤土效应的泄压井
CN105804119A (zh) 一桩二用地下廊道结构及其施工方法
CN103806347A (zh) 一种适用于岩质陡坡路堤的侧向桩板结构
CN104294769B (zh) 一种补桩与增大台帽组合加固已建桥台结构的施工方法
CN104131499A (zh) 一种用于沉降无砟轨道中线偏移纠偏方法
CN103952986A (zh) 一种减载式刚性涵洞结构
CN102031757B (zh) 一种顶进框架桥的底板导向层的施工方法
CN105804048B (zh) 一种软弱地基排水板加固方法
CN202247575U (zh) 高速铁路岩溶强烈发育车站道岔区路基加固构造
CN205243528U (zh) 隧道底部沉降衬砌开裂加固结构
CN202450485U (zh) 板桩加固防汛墙
CN207267975U (zh) 一种用于盾构隧道下穿河流的河床加固结构
CN210194361U (zh) 道路加宽新旧路基拼接结构
CN203960921U (zh) 一种既有路堑边坡桩板墙加固结构
CN104652181A (zh) 填土地基上既有铁路车站路基轻型支档结构
CN204097889U (zh) 一种补桩与增大台帽组合加固已建桥台结构
CN105735383A (zh) 一种保留结构体系的局部地下清障施工方法
CN205714282U (zh) 一种软弱地层隧底防排水结构
CN102817298A (zh) 一种在冻土上的施工方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20160224

Address after: 100144 Beijing City, Shijingshan District Jin Yuan Zhuang Road No. 5

Patentee after: Beifang Polytechnic Univ.

Address before: 100000 Beijing city Haidian District Fuhai international port Daliushu Road 306

Patentee before: Li Jiawen

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20120530

Termination date: 20170106