CN101759079A - Method for integrally assembling and installing steel structure elevator derrick on the ground - Google Patents

Method for integrally assembling and installing steel structure elevator derrick on the ground Download PDF

Info

Publication number
CN101759079A
CN101759079A CN200910261825A CN200910261825A CN101759079A CN 101759079 A CN101759079 A CN 101759079A CN 200910261825 A CN200910261825 A CN 200910261825A CN 200910261825 A CN200910261825 A CN 200910261825A CN 101759079 A CN101759079 A CN 101759079A
Authority
CN
China
Prior art keywords
column
ground
steel structure
crossbeam
vertical post
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN200910261825A
Other languages
Chinese (zh)
Other versions
CN101759079B (en
Inventor
庄利军
卫芷
王续东
常彦妮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Shanxi Sijian Group Co Ltd
Shanxi Construction Engineering Group Co Ltd
Original Assignee
China Shanxi Sijian Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Shanxi Sijian Group Co Ltd filed Critical China Shanxi Sijian Group Co Ltd
Priority to CN 200910261825 priority Critical patent/CN101759079B/en
Publication of CN101759079A publication Critical patent/CN101759079A/en
Application granted granted Critical
Publication of CN101759079B publication Critical patent/CN101759079B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention relates to a method for integrally assembling and installing a steel structure elevator derrick on the ground, belonging to the construction method and aiming at solving the problem existing in the prior art that the elevator derrick is difficult to assemble and install vertically with good quality. The method for integrally assembling and installing the steel structure elevator derrick on the ground comprises the following steps: assembling and installing a platform on the ground, installing a first vertical post and a second vertical post on the platform, and installing sections of cross beams on the first vertical post and the second vertical post; assembling the cross beams on the vertical surfaces of both the first vertical post and the second vertical post, assembling a third vertical post and a fourth vertical post on the other side, supplementing other cross beams, and rechecking again; welding the upper parts and the lower parts of the cross beams in the middle of the steel structure elevator derrick with the vertical posts, and hoisting the welded components to the appropriate position. The invention can ensure that the steel structure elevator derrick can be assembled and installed on the ground rather than above the ground, reduce the construction difficulty, effectively control the welding deformation, greatly reduce the vertical transportation volume and accelerate the construction progress.

Description

The whole splicing in steel structure elevator well frame ground installation method
Technical field
The present invention relates to a kind of construction method, be specially the whole splicing in a kind of steel structure elevator well frame ground installation method.
Background technology
In public building, sightseeing elevator is used more and more widely, and this elevator adopts steel structure derrick more.Traditional installation method generally is that column is installed earlier, adorns beam then, the segmentation butt joint.Along with the height of building is more and more higher, produce bigger vertical transport amount, and the sectional area of column is less, operation easier was bigger when the workmen carried out butt welding aloft, and is dangerous high, and welding quality is difficult to guarantee, bigger deflection appears, often the out of reach acceptance requirement.
Summary of the invention
The present invention installs problems such as the difficulty of construction of bringing is big, of poor quality and the whole splicing in a kind of steel structure elevator well frame ground installation method is provided in order to solve the elevator well frame vertical cartel that exists in the prior art.
The present invention is realized that by following technical scheme the whole splicing in a kind of steel structure elevator well frame ground installation method comprises the steps:
1, at ground assembling platform for lining, described platform is some supporting traverses;
2, on platform, adorn first column, second column earlier, two root post end part aligning, the other end is reserved and is not more than 1 meter gap;
3, on two root posts, emit the crossbeam position line, each section crossbeam is installed;
4, begin the crossbeam of assembly unit facade direction on two root posts then, weigh down the squareness of controlling both direction with theodolite and magnetic line of force;
5, the 3rd column of assembly unit opposite side, the 4th column are again formed the elevator well frame lattice;
6, all the other crossbeams of polishing between upper strata the 3rd column, the 4th column, the reversible deformation that adds angle steel or steel pipe in the column outside is supported; Interim diagonal ligament is set in lattice, prevents welding deformation.
6a, for the two terraced structure of forming by 6 root posts, to the in-plane expansion, on platform, continue the 5th column is installed behind the intact lattice of assembly unit, the crossbeam between the 5th column and first column is installed again;
6b, again the 5th column upper beam and the 6th column are being installed, method and measure of control are with step 4, step 5;
Crossbeam between 6c, installation the 6th column and the 4th column; And add interim support between each column,
7, before the formal welding, check the levelness of oad He each member of structure once more, squareness, and it is poor to check the diagonal line of lattice, prevents structural distortion.
8, finish earlier the derrick middle beam up and down with the welding of column, two people weld to bilateral symmetry from the derrick middle part simultaneously then; Stress is discharged laterally from the middle part, prevent that the excessive member that causes of local stress from twisting.
9, welding finishes, and checks scantling and distortion situation, the back that meets the requirements 50T crane 14 hoisted in position.Prevent during lifting that the deflection distortion is excessive, hang ground and establish an auxiliary suspension centre in front at the middle part, with the auxiliary lifting of a 16T crane.When member and ground angle during greater than 75 °, unclamp auxiliary suspension centre, it is in place progressively to make member vertically hang ground by a crane.
10, the above derrick of 25m divides two sections assembly units, aerial butt joint.Joint form is with 45 ° of mitre joints, the two adjacent upright stitching position 1m that staggers.For guaranteeing that shaft is vertical up and down, mismatch do not occur, respectively add a connection of weldering otic placode in both sides up and down, sandwich gad in connection otic placode side at the joint location shaft, by knocking gad lower prop is aligned, and from both direction is whole vertical with two theodolite control shafts in length and breadth.Be symmetrically welded simultaneously from both sides by two people during the pillar butt joint, prevent distortion.After butt joint is finished, prescind the connection otic placode, polish flat.
Adopt the horizontal assembling method of field ground of the present invention, elevator well frame is assembled welding finish on the installation on ground platform, disposable hoisted in position highly surpasses 30m, can be divided into two sections assembly units and finish, and finishes butt joint in the air at height.With this kind method highly bigger structure has been carried out the conversion of plane and facade, uprising idle job is Ground Operation, has reduced difficulty of construction.Can effectively control welding deformation, significantly reduce the vertical transport amount, accelerating construction progress.
Description of drawings
Fig. 1 is that the component locations of the method for the invention is installed one of graph of a relation
Fig. 2 is the left view of Fig. 1
Fig. 3 is the birds-eye view of Fig. 1
Fig. 4 is that the component locations of the method for the invention is installed two of graph of a relation
Fig. 5 is the left view of Fig. 4
Fig. 6 is the birds-eye view of Fig. 4
Fig. 7 is that the component locations of the method for the invention is installed three of graph of a relation
Fig. 8 is the left view of Fig. 7
Fig. 9 is the birds-eye view of Fig. 7
Figure 10 is that the component locations of the method for the invention is installed four of graph of a relation
Figure 11 is the right elevation of Figure 10
Figure 12 is that the component locations of the method for the invention is installed five of graph of a relation
Figure 13 is the right elevation of Figure 12
Figure 14 is that the component locations of the method for the invention is installed six of graph of a relation
Figure 15 is the right elevation of Figure 14
Figure 16 is the lifting scheme drawing
Figure 17 is the splicing scheme drawing
The specific embodiment
A kind of being applicable in the height 50m, the whole splicing in the steel structure elevator well frame ground of the indoor and outdoor elevator well frame that welding or hot-rolled steel section are formed installation method may further comprise the steps:
1, anticipate as shown in Figure 1, 2, 3, at ground assembling platform for lining 1, described platform 1 is some supporting traverses, requires planeness, levelness deviation control in 2mm;
2, as Fig. 2,3 signals, on platform 1, adorn first column, 2, the second columns, 3, two root post end part aligning earlier, the other end is reserved and is not more than 1 meter gap, is controlled in the 2mm with the levelness of engineer's spirit level with two root posts during assembly unit, and available 1mm approaches the parallels adjustment;
3, on first column 2, second column 3, emit the crossbeam position line, each section crossbeam 4 is installed, measure diagonal line with steel ruler, require crossbeam 4 to keep horizontal surface vertical, upright with first column 2, second column 3, only each member is positioned weldering in the assembly unit process, guarantee in construction, to reduce fusion length under the not open circuited situation as far as possible.
4, as Fig. 4,5,6 signals, the crossbeam 5 of beginning assembly unit facade direction on first column 2, second column 3 weighs down the squareness of controlling both direction with theodolite and magnetic line of force;
5, as Fig. 7,8,9 signals, at assembly unit opposite side the 3rd column 6, the 4th column 8, form the elevator well frame lattice, the 3rd column 6, the 4th column 8 usefulness engineer's spirit level controlling level degree are in 2mm;
6, all the other crossbeams 7 of polishing between the 3rd column 6, the 4th column 8, the reversible deformation that adds angle steel or steel pipe in the column outside is supported; Interim diagonal ligament is set in lattice, prevents welding deformation.
7, as Figure 10,11,12 signals, for the two terraced structure of forming by 6 root posts, to the in-plane expansion, the 5th column 10 is installed on platform behind the intact lattice of assembly unit, the crossbeam 9 between the 5th column 10 and first column 2 is installed.Same guarantee the 5th column 10, first column 2, and crossbeam 9 between levelness and crossbeam 9,4 and column vertical, upright.
8, the 5th column 10 upper beam 11 and the 6th column 12 are installed, method and measure of control are with step 4, step 5;
9,, crossbeam 13 between the 6th column 12 and the 4th column 8 is installed, and is added the interim support between each column as Figure 14,15 signals.
10, before the formal welding, check the levelness of oad He each member of structure once more, squareness, and it is poor to check the diagonal line of lattice, prevents structural distortion.
11, finish earlier the derrick middle beam up and down with the welding of column, two people weld to bilateral symmetry from the derrick middle part simultaneously then; Stress is discharged laterally from the middle part, prevent that the excessive member that causes of local stress from twisting.And in welding process measuring deformation amount at any time, surpass the flame correction that carries out of distortion allowed band.
12, as Figure 16, welding finishes, and checks scantling and distortion situation, the back that meets the requirements 50T crane 14 hoisted in position.Prevent during lifting that the deflection distortion is excessive, hang ground and establish an auxiliary suspension centre in front at the middle part, with the auxiliary lifting of a 16T crane.When member and ground angle during greater than 75 °, unclamp auxiliary suspension centre, it is in place progressively to make member vertically hang ground by a crane.
13, as schematically shown in Figure 17, the above derrick of 25m divides two sections assembly units, aerial butt joint.Joint form is with 45 ° of mitre joints, the two adjacent upright stitching position 1m that staggers.For guaranteeing that shaft is vertical up and down, mismatch do not occur, respectively add a connection of weldering otic placode in both sides up and down, sandwich gad in connection otic placode side at the joint location shaft, by knocking gad lower prop is aligned, and from both direction is whole vertical with two theodolite control shafts in length and breadth.Be symmetrically welded simultaneously from both sides by two people during the pillar butt joint, prevent distortion.After butt joint is finished, prescind the connection otic placode, polish flat.

Claims (4)

1. the whole splicing in a steel structure elevator well frame ground installation method comprises the steps:
(1), at ground assembling platform for lining (1), described platform (1) is some supporting traverses;
(2), on platform (1), adorn first column (2), second column (3) earlier, two root post end part aligning, the other end is reserved and is not more than 1 meter gap;
(3), on two root posts, emit the crossbeam position line, each section crossbeam (4) is installed;
(4), then begin the crossbeam (5) of assembly unit facade direction on two root posts, weigh down the squareness of controlling both direction with theodolite and magnetic line of force;
(5), the 3rd column (6), the 4th column (8) of assembly unit opposite side again, form the elevator well frame lattice;
(6), between upper strata the 3rd column (6), the 4th column (8) all the other crossbeams of polishing (7), the reversible deformation that adds angle steel or steel pipe in the column outside is supported; Interim diagonal ligament is set in lattice, prevents welding deformation;
(7), before the formal welding, check the levelness of oad He each member of structure once more, squareness, and it is poor to check the diagonal line of lattice, prevents structural distortion;
Finish (8), earlier the derrick middle beam up and down with the welding of column, two people weld to bilateral symmetry from the derrick middle part simultaneously then; Stress is discharged laterally from the middle part, prevent that the excessive member that causes of local stress from twisting;
(9), welding finishes, with 50T crane (14) hoisted in position, prevent during lifting that the deflection distortion is excessive, hang ground and establish an auxiliary suspension centre in front at the middle part, with the auxiliary lifting of a 16T crane, when member and ground angle during greater than 75 °, unclamp auxiliary suspension centre, it is in place progressively to make member vertically hang ground by a crane.
2. the whole splicing in steel structure elevator well frame according to claim 1 ground installation method also comprises the steps:
(10), the above derrick of 25m divides two sections assembly units, aerial butt joint.
3. the whole splicing in steel structure elevator well frame according to claim 2 ground installation method also comprises the steps:
Joint form is with 45 ° of mitre joints, the two adjacent upright stitching position 1m that staggers, respectively add a connection of weldering otic placode (15) in both sides up and down at the joint location shaft, sandwich gad in connection otic placode side, lower prop is aligned by knocking gad, and from both direction is whole vertical with two theodolites control shafts in length and breadth, be symmetrically welded simultaneously from both sides by two people during the pillar butt joint, after butt joint is finished, prescind the connection otic placode, polish flat.
4. the whole splicing in steel structure elevator well frame according to claim 1 and 2 ground installation method is characterized in that: after finishing, step (6) also continues following steps,
(6a), for the two terraced structure of forming by 6 root posts, to the in-plane expansion, on platform, continue the 5th column (10) is installed behind the intact lattice of assembly unit, the crossbeam (9) between the 5th column (10) and first column (2) is installed again;
(6b), again the 5th column (10) upper beam (11) and the 6th column (12), the same step of method and measure of control (4), step (5) are being installed;
(6c), crossbeam between the 6th column (12) and the 4th column (8) is installed; And add interim support between each column, continue step (7) then.
CN 200910261825 2009-12-30 2009-12-30 Method for integrally assembling and installing steel structure elevator derrick on the ground Active CN101759079B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 200910261825 CN101759079B (en) 2009-12-30 2009-12-30 Method for integrally assembling and installing steel structure elevator derrick on the ground

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 200910261825 CN101759079B (en) 2009-12-30 2009-12-30 Method for integrally assembling and installing steel structure elevator derrick on the ground

Publications (2)

Publication Number Publication Date
CN101759079A true CN101759079A (en) 2010-06-30
CN101759079B CN101759079B (en) 2012-05-30

Family

ID=42490488

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 200910261825 Active CN101759079B (en) 2009-12-30 2009-12-30 Method for integrally assembling and installing steel structure elevator derrick on the ground

Country Status (1)

Country Link
CN (1) CN101759079B (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102418317A (en) * 2011-11-10 2012-04-18 中铁二十三局集团有限公司 Field manufacturing method for lattice pier
CN104074331A (en) * 2014-06-24 2014-10-01 中铁四局集团钢结构有限公司 Construction method of panoramic lift structure decoration factorization operation
CN105781555A (en) * 2014-12-24 2016-07-20 中国瑞林工程技术有限公司 Modular installation method for circular steel tube and inclined column steel headframe
CN106586767A (en) * 2017-02-24 2017-04-26 富士电梯(四川)有限公司 Elevator mounting device assembly capable of being used for shaft-free building and elevator mounting method
CN107675890A (en) * 2017-10-16 2018-02-09 山东电力建设第工程公司 A kind of method at aerial regulation steel truss mast-up angle of inclination
CN109914694A (en) * 2019-03-05 2019-06-21 贵州建工集团第一建筑工程有限责任公司 A kind of steel-structure factory building load-bearing pillar and its manufacturing method
CN110924630A (en) * 2019-12-05 2020-03-27 北京亟光电梯科技有限公司 Integrated steel structure hoistway with waiting hall and construction process thereof
CN113148806A (en) * 2021-04-26 2021-07-23 海阳中集来福士海洋工程有限公司 Method for installing elevator

Family Cites Families (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3959134B2 (en) * 1996-07-08 2007-08-15 ミサワホーム株式会社 Airtight structure of elevator shaft
JP4265832B2 (en) * 1998-12-25 2009-05-20 三菱電機株式会社 Elevator installation method
JP3345395B2 (en) * 1999-12-20 2002-11-18 株式会社熊谷組 Elevator tower construction method
JP2004244208A (en) * 2003-02-17 2004-09-02 Nippon Steel Corp External elevator and method of its construction
CN2675628Y (en) * 2003-05-07 2005-02-02 苏州市东南液压电梯制造有限公司 Household elevator aluminium alloy tower frame
CN2695422Y (en) * 2004-05-09 2005-04-27 宋建华 Elevator steel frame shaft
CN200954968Y (en) * 2006-06-26 2007-10-03 肖俊祥 Double-basket well type lifter derrick structure
CN200988716Y (en) * 2006-12-19 2007-12-12 上海长江斯迈普电梯有限公司 Well head device for outdoor lift
CN201250038Y (en) * 2008-05-06 2009-06-03 苏州台菱电梯有限公司 Wall-attached elevator hoistway

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102418317A (en) * 2011-11-10 2012-04-18 中铁二十三局集团有限公司 Field manufacturing method for lattice pier
CN104074331A (en) * 2014-06-24 2014-10-01 中铁四局集团钢结构有限公司 Construction method of panoramic lift structure decoration factorization operation
CN105781555A (en) * 2014-12-24 2016-07-20 中国瑞林工程技术有限公司 Modular installation method for circular steel tube and inclined column steel headframe
CN105781555B (en) * 2014-12-24 2017-12-29 中国瑞林工程技术有限公司 Round steel pipe batter post steel headframe modularization installation method
CN106586767A (en) * 2017-02-24 2017-04-26 富士电梯(四川)有限公司 Elevator mounting device assembly capable of being used for shaft-free building and elevator mounting method
CN106586767B (en) * 2017-02-24 2023-10-03 富士电梯(四川)有限公司 Elevator installation device assembly and elevator installation method for hoistway-free building
CN107675890A (en) * 2017-10-16 2018-02-09 山东电力建设第工程公司 A kind of method at aerial regulation steel truss mast-up angle of inclination
CN109914694A (en) * 2019-03-05 2019-06-21 贵州建工集团第一建筑工程有限责任公司 A kind of steel-structure factory building load-bearing pillar and its manufacturing method
CN110924630A (en) * 2019-12-05 2020-03-27 北京亟光电梯科技有限公司 Integrated steel structure hoistway with waiting hall and construction process thereof
CN113148806A (en) * 2021-04-26 2021-07-23 海阳中集来福士海洋工程有限公司 Method for installing elevator

Also Published As

Publication number Publication date
CN101759079B (en) 2012-05-30

Similar Documents

Publication Publication Date Title
CN101759079B (en) Method for integrally assembling and installing steel structure elevator derrick on the ground
CN101845849B (en) Large-span steel gallery erected between new building and old building and construction method thereof
CN101126279B (en) Silo slipform construction technique
CN106460384A (en) Structural modular building connector
CN100572256C (en) The installation method of giant crane beam
CN107663951A (en) The support system and construction technology of superimposed sheet and wallboard formed by integrally casting
CN106703416A (en) Lifting method of steel structure roof truss pulling bar in narrow space
CN101440667A (en) Mounting method for wide span single layer rain shed reticulated shell structure
CN114232805B (en) Construction method of ultrahigh-height large-span steel concrete beam hanging structure
CN107013038A (en) A kind of steel structure slipping of building roof lighting Zhongting changes column construction method
CN104674665A (en) Installation method for corridor bridge of large space steel structure
CN107419893A (en) A kind of elevator steel platform and preparation method thereof
CN115162182B (en) Cantilever type steel box girder high-precision cable hoisting construction method
CN110374612A (en) It is a kind of applied to the shield machine receiving platform and construction technology that face under dummy status
CN102242540A (en) Large-span steel-structure box beam and collision-prevention wall integrated construction technology
CN105018115A (en) Dry quenching primary deduster fragment hoisting method
CN106544959A (en) The construction method of the lifting sections of the king-tower containing saddle and bridge main tower saddle
CN107419907B (en) A kind of steel-making tower steel structure platform is staggered installation of welding method
CN107795005A (en) A kind of steel core concrete column and reinforced concrete column concrete core cylinder mixed structure and installation method
CN107587770A (en) Disjunctor storehouse synchronization slding form operation method
CN107881914B (en) Wire-dividing tube type cable saddle back field assembly type positioning device and assembly method
CN207568213U (en) The support system of superimposed sheet and wallboard formed by integrally casting
CN209907886U (en) Adjustable assembled stair construction platform
CN209384617U (en) Multi-functional construction operation platform for vertical hoistway
CN219509006U (en) High-altitude large-span daylighting skylight space truss steel platform construction system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
ASS Succession or assignment of patent right

Owner name: SHANXI CONSTRUCTION ENGINEERING (GROUP) CO., LTD.

C41 Transfer of patent application or patent right or utility model
TA01 Transfer of patent application right

Effective date of registration: 20110127

Address after: 030012 Shanxi city of Taiyuan Province Sports No. 7 North Street

Applicant after: Shanxi Sijian Group Co., Ltd.

Co-applicant after: Shanxi Construction Engineering (Group) Corporation

Address before: 030012 Shanxi city of Taiyuan Province Sports No. 7 North Street

Applicant before: Shanxi Sijian Group Co., Ltd.

C14 Grant of patent or utility model
GR01 Patent grant
C53 Correction of patent for invention or patent application
CB03 Change of inventor or designer information

Inventor after: Hao Yinghua

Inventor after: Wei Zhi

Inventor after: Zhuang Lijun

Inventor after: Wang Xudong

Inventor after: Chang Yanni

Inventor before: Zhuang Lijun

Inventor before: Wei Zhi

Inventor before: Wang Xudong

Inventor before: Chang Yanni

COR Change of bibliographic data

Free format text: CORRECT: INVENTOR; FROM: ZHUANG LIJUN WEI ZHI WANG XUDONG CHANG YANNI TO: HAO YINGHUA WEI ZHI ZHUANG LIJUN WANG XUDONG CHANG YANNI

CB03 Change of inventor or designer information

Inventor after: Zhuang Lijun

Inventor after: Wei Zhi

Inventor after: Hao Yinghua

Inventor after: Wang Xudong

Inventor after: Chang Yanni

Inventor before: Hao Yinghua

Inventor before: Wei Zhi

Inventor before: Zhuang Lijun

Inventor before: Wang Xudong

Inventor before: Chang Yanni

CB03 Change of inventor or designer information