CN101736755A - 清水孔桩基施工方法 - Google Patents

清水孔桩基施工方法 Download PDF

Info

Publication number
CN101736755A
CN101736755A CN 200910259819 CN200910259819A CN101736755A CN 101736755 A CN101736755 A CN 101736755A CN 200910259819 CN200910259819 CN 200910259819 CN 200910259819 A CN200910259819 A CN 200910259819A CN 101736755 A CN101736755 A CN 101736755A
Authority
CN
China
Prior art keywords
steel casing
crane barge
casing
drilling
crane
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN 200910259819
Other languages
English (en)
Other versions
CN101736755B (zh
Inventor
应虹
阎王虎
彭立志
李勇
田连民
王俊伟
檀兴华
樊俊丽
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Road and Bridge International Co Ltd
China Communications Road and Bridge North China Engineering Co Ltd
Original Assignee
Road and Bridge International Co Ltd
China Communications Road and Bridge North China Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Road and Bridge International Co Ltd, China Communications Road and Bridge North China Engineering Co Ltd filed Critical Road and Bridge International Co Ltd
Priority to CN 200910259819 priority Critical patent/CN101736755B/zh
Publication of CN101736755A publication Critical patent/CN101736755A/zh
Application granted granted Critical
Publication of CN101736755B publication Critical patent/CN101736755B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
  • Earth Drilling (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

清水孔桩基施工方法,包括以下步骤:(1)利用浮吊拉锚定位,确定钻孔施工的桩位;(2)用履带吊吊装钢护筒至浮吊上,调整并保持钢护筒的垂直度,用浮吊悬吊振桩锤在桩位振沉钢护筒,使护筒落在基岩上或嵌入基岩内;(3)利用钢护筒和钢管桩沿江面搭设钻孔施工平台;(4)在钢护筒上沿江面开孔,使钢护筒内水头高度与江水平齐;(5)采用全液压冲击反循环钻机进行钻孔施工,钻孔施工过程不用泥浆护壁;(6)钻进至设计标高后,清除孔底的钻渣,然后下放钢筋笼,浇注混凝土。本发明适用于河床覆盖层很少甚至没有的情况,特别适用于河床岩面不平整的情况。

Description

清水孔桩基施工方法
技术领域
本发明涉及一种水中桩基施工方法,特别是一种清水孔桩基施工方法。
背景技术
桥梁基础普遍采用桩基型式。桩基可以将桥梁的上部结构重量及荷载,传至持力层,确保桥梁的正常运转。桥梁的桩基大多位于河床中。近几年,水中桩基施工多采用冲孔灌注桩施工方法,目前冲孔灌注桩施工普遍采用泥浆钻孔,施工过程中利用泥浆将钻渣带出,并保护孔壁不致坍塌,钻孔完成后,向孔内浇筑混凝土,完成钻孔灌注桩的施工。采用泥浆钻孔会对施工区域水域造成污染,而且该种施工方法仅适合河床较平整和覆盖层较厚的情况。在河床覆盖层很少甚至没有,及河床面不平整的情况下,由于该种地层不能自行造浆,采用现有的泥浆钻孔,必须制备优质泥浆来护孔,不仅增加了施工工作量以及设备的投入,而且影响施工进度。
发明内容
本发明的目的在于,针对现有泥浆钻孔所存在的问题,提供一种桩基施工方法,适用于河床覆盖层较浅或没有覆盖层,以及河床岩面不平整的地质情况下的钻孔施工。
本发明所提供的桩基施工方法是由如下技术方案来实现的。
清水孔桩基施工方法,其特征在于包括以下步骤:
(1)利用浮吊拉锚定位,确定钻孔施工的桩位;
(2)用履带吊吊装钢护筒至浮吊上,调整并保持钢护筒的垂直度,用浮吊悬吊振桩锤在桩位振沉钢护筒,使护筒落在基岩上或嵌入基岩内;
(3)利用钢护筒和钢管桩沿江面搭设钻孔施工平台;
(4)在钢护筒上沿江面开孔,使钢护筒内水头高度与江水平齐;
(5)采用全液压冲击反循环钻机进行钻孔施工,钻孔施工过程不用泥浆护壁;
(6)钻进至设计标高后,清除孔底的钻渣,然后下放钢筋笼,浇注混凝土。
上述施工方法,进一步还包括以下特征:
所述步骤(1)中,所述的浮吊拉锚定位,具体方法是:浮吊在水中共抛5个锚,包括:在浮吊船头向前抛出一定位锚,并使定位锚与浮吊船身在一条直线上;浮吊船头向两侧各抛一边锚,在浮吊尾部两侧向河流下游各抛一尾锚;通过所述定位锚的拉紧和放松,调节浮吊的前进和后退,通过所述两边锚和尾锚的拉紧和放松,调节桩位的左右偏差。
所述步骤(2)中,先用履带吊吊装悬臂导向支架并固定所述导向支架于浮吊上,然后利用履带吊吊装钢护筒至浮吊上,并利用导向支架夹持钢护筒和保持钢护筒的垂直度。
所述步骤(2)中,振沉钢护筒时,先利用钢管桩的自重下沉,然后开动振动锤使桩下沉。
所述步骤(5)中,钻孔施工过程中根据不同土层选择与之相适应的进尺和转速,对于软弱层,采用低档慢速、大泵量,以免发生先扩孔后缩孔现象;在护筒底口和不同地层交接处附近,采用低档慢速、小进尺钻进,每小时进尺不大于0.5m。
所述步骤(6)中,在钢筋笼下放前,先下潜水工探明护筒与岩层接触面至接触面以下1米的孔壁情况,若有有缺口及时处理。
本发明的优点在于:
1、钻孔施工过程中,由于不用泥浆护壁,减少了泥浆配制工作,从而大大压缩了成桩工期,同时减少了泥浆对施工区域水域的污染。
2、在最后的清孔过程中,由于没有泥浆护壁,会提高清孔的的质量,清孔的时间会大大压缩,同时也保证了混凝土浇筑质量。
3、由于工期的缩短,减少了机械和其他辅助设备的投入。
4、降低了护筒内的水头高度和孔内泥浆浓度,消除了护筒内外的压力差,成功的解决了钻孔施工过程中的液面反穿问题。
本发明适用于河床覆盖层很少甚至没有的情况下,钢护筒落在岩层上,或钻进时直接进入岩层,特别适用于河床岩面不平整的情况。
附图说明
图1是本发明清水孔桩基施工方法步骤图。
具体实施方式
以下通过具体实施方式对本发明详细说明。
在以下实施例中,需要用到以下设备:
(1)钻机设备
在河床覆盖层很少甚至没有的情况下,及河床岩面不平整的情况,施工区地层以中砂和砂岩为主,为保证基桩施工质量和加快进度,采用本发明的方法,宜选用冲击钻机进行工程的基桩成孔施工。如果采用普通的回旋钻机,由于其以扭矩为动力,在钻头进入中、微风化泥质粉砂岩后,因岩石岩质较硬,会导致钻头磨损严重,钻进速度慢,如经常对钻头进行补强,势必延误成孔时间,增加成孔周期和成桩成本。而冲击钻机的原理是冲锤在冲击作用下对土体和岩体进行破碎,同时还能起到挤密孔壁土体的作用。因此结合地质情况,拟选用YCJF-25型全液压冲击反循环钻机,该钻采用液压传动,集中液电复合操纵,安全可靠。该种机型采用反循环清孔工艺,适应各种地层,尤其适用于卵石层和岩层。其主要技术参数如下:
口径:1.2-2.5m
孔深:80m
锤重:7t
冲击频率:手动:10-25次/分
自动:16-24次/分
电机功率:75kW;卷扬提升能力:90kN
(2)钢护筒振沉设备:
根据实际地质情况和护筒重量,为保证钢护筒能有效的落在岩面之上,且保证钢护筒的垂直度,钢护筒振沉采用DZ-135振桩锤。振沉过程采用50T履带吊配合300T浮吊施工。
图1是本发明所提供的清水孔桩基施工方法流程图,包括:
步骤1、利用浮吊拉锚定位,确定钻孔施工的桩位。
浮吊的定位方法是:浮吊在水中共抛5个锚,包括:在浮吊船头向前抛出一定位锚,并使定位锚与浮吊船身在一条直线上;浮吊船头向两侧各抛一边锚,在浮吊尾部两侧向河流下游各抛一尾锚;通过所述定位锚的拉紧和放松使浮吊的前进和后退,调节桩位的前后偏差,通过所述两边锚和尾锚的拉紧和放松,调节桩位的左右偏差。
步骤二、吊装并振沉钢护筒。准确定位出钢管桩桩位后,用履带吊吊装钢护筒至浮吊上,调整并保持钢护筒的垂直度,用浮吊悬吊振桩锤在桩位振沉钢护筒,使护筒落在基岩上或嵌入基岩内。
具体操作步骤为:用履带吊吊装悬臂导向支架,并固定导向支架于浮吊上,复测桩位,利用50T履带吊吊装钢护筒至浮吊上,在调整钢护筒垂直度满足要求后,开动振桩锤进行钢护筒振沉。
振沉钢护筒采用悬打法施工,采用履带吊配合浮吊施工,利用悬臂导向支架保证钢管桩基础位置精确,用浮吊悬吊振桩锤施打钢护筒。
钢护筒振沉施工要点如下:
a.振桩开始时,吊装振桩锤和夹具与护筒顶连接牢固,先利用桩的自重下沉,然后开动振动锤使桩下沉。如果施工中出现异常情况,可根据实际施工情况进行相应调整。
b.每根护筒的下沉一气呵成,不可中途间歇时间过长,以免桩周的土恢复,继续下沉困难。振动的持续时间长短应根据不同地质情况决定。
c.振动锤与桩头连接牢固,以免影响振动力的传递,从而影响钢护筒下沉,也易振坏,在振动锤振动过程中,如发现护筒顶有局部变形或损坏,要及时修复。
d.悬臂导向支架与浮吊固定牢固,以便振沉时稳定钢护筒桩身,确保桩的位置和垂直度满足要求;但钢护筒在导向支架上不应钳制过死,施打时,导向支架不能发生位移或转动。同时,控制浮吊不得偏移。
e.在钢护筒振沉过程中要不断地检测桩位和护筒桩的垂直度,并控制好护筒顶标高。下沉时如钢护筒倾斜,及时牵引校正。
步骤三、利用钢护筒和钢管桩沿江面搭设钻孔施工平台。
步骤四、在钢护筒上沿江面开孔,使钢护筒内水头高度与江水平齐。
步骤五、清水孔钻孔施工。采用全液压冲击反循环钻机进行钻孔施工,钻孔施工过程中不用泥浆。
钻进过程中需根据不同土层选择与之相适应的进尺和转速。对于软弱层,采用低档慢速、大泵量,以免发生先扩孔后缩孔现象;护筒底口和不同地层交接处附近,采用低档慢速、小进尺钻进,防止扩孔、塌孔和偏斜孔,每小时进尺不大于0.5m。
步骤六、向桩孔灌注混凝土。钻进至设计标高后,清除孔底的钻渣,然后下放钢筋笼,浇注混凝土。
当钻进至设计标高时,对成孔深度进行复核,确认到位后应及时清除孔底的钻渣,清水孔由于没有泥浆护壁,清除钻渣速度和效率较高。在钢筋笼下放前,必须下潜水工检查探明护筒与岩层接触面至接触面以下1米的孔壁情况,若有有缺口及时处理。确保基桩在混凝土灌注时顺畅,不漏浆。然后下放钢筋笼,浇注混凝土。

Claims (6)

1.清水孔桩基施工方法,其特征在于包括以下步骤:
(1)利用浮吊拉锚定位,确定钻孔施工的桩位;
(2)用履带吊吊装钢护筒至浮吊上,调整并保持钢护筒的垂直度,用浮吊悬吊振桩锤在桩位振沉钢护筒,使护筒落在基岩上或嵌入基岩内;
(3)利用钢护筒和钢管桩沿江面搭设钻孔施工平台;
(4)在钢护筒上沿江面开孔,使钢护筒内水头高度与江水平齐;
(5)采用全液压冲击反循环钻机进行钻孔施工,钻孔施工过程不用泥浆护壁;
(6)钻进至设计标高后,清除孔底的钻渣,然后下放钢筋笼,浇注混凝土。
2.根据权利要求1所述的清水孔桩基施工方法,其特征在于,步骤(1)所述的浮吊拉锚定位,具体方法是:浮吊在水中共抛5个锚,包括:在浮吊船头向前抛出一定位锚,并使定位锚与浮吊船身在一条直线上;浮吊船头向两侧各抛一边锚,在浮吊尾部两侧向河流下游各抛一尾锚;通过所述定位锚的拉紧和放松,调节浮吊的前进和后退,通过所述两边锚和尾锚的拉紧和放松,调节桩位的左右偏差。
3.根据权利要求1所述的清水孔桩基施工方法,其特征在于:所述步骤(2)中,先用履带吊吊装悬臂导向支架并固定所述导向支架于浮吊上,然后利用履带吊吊装钢护筒至浮吊上,并利用导向支架夹持钢护筒和保持钢护筒的垂直度。
4.根据权利要求1所述的清水孔桩基施工方法,其特征在于:所述步骤(2)中,振沉钢护筒时,先利用钢管桩的自重下沉,然后开动振动锤使桩下沉。
5.根据权利要求1所述的清水孔桩基施工方法,其特征在于:所述步骤(5)中,钻孔施工过程中根据不同土层选择与之相适应的进尺和转速,对于软弱层,采用低档慢速、大泵量,以免发生先扩孔后缩孔现象;在护筒底口和不同地层交接处附近,采用低档慢速、小进尺钻进,每小时进尺不大于0.5m。
6.根据权利要求1所述的清水孔桩基施工方法,其特征在于:所述步骤(6)中,在钢筋笼下放前,先检查护筒与岩层接触面至接触面以下1米的孔壁情况,若有缺口及时处理。
CN 200910259819 2009-12-15 2009-12-15 清水孔桩基施工方法 Active CN101736755B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 200910259819 CN101736755B (zh) 2009-12-15 2009-12-15 清水孔桩基施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 200910259819 CN101736755B (zh) 2009-12-15 2009-12-15 清水孔桩基施工方法

Publications (2)

Publication Number Publication Date
CN101736755A true CN101736755A (zh) 2010-06-16
CN101736755B CN101736755B (zh) 2011-09-28

Family

ID=42460741

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 200910259819 Active CN101736755B (zh) 2009-12-15 2009-12-15 清水孔桩基施工方法

Country Status (1)

Country Link
CN (1) CN101736755B (zh)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102936894A (zh) * 2012-11-27 2013-02-20 中铁上海工程局有限公司第五分公司 小直径灌注桩与基岩的锚固方法
CN104674845A (zh) * 2015-02-09 2015-06-03 中国建筑第八工程局有限公司 液压振动逆作插柱辅助施工方法
CN106320187A (zh) * 2016-10-27 2017-01-11 朱育盼 用于特殊地层中的桥梁施工方法和装置
CN107447751A (zh) * 2017-08-18 2017-12-08 新地能源工程技术有限公司 海上抛石区灌注桩漏浆控制装置和方法
CN108049398A (zh) * 2017-12-05 2018-05-18 中交第四公路工程局有限公司 桥位处于泥浆区的桩基施工方法
CN110331736A (zh) * 2019-07-24 2019-10-15 中铁四局集团有限公司 一种用于水中桩基施工的泥浆循环装置及相应施工工法
CN111305754A (zh) * 2020-02-27 2020-06-19 中铁建大桥工程局集团第五工程有限公司 一种基于全液压动力头钻机的灌注桩施工方法
CN111677439A (zh) * 2020-06-24 2020-09-18 中建四局土木工程有限公司 反循环回旋钻机钻进成孔方法
CN111794115A (zh) * 2020-07-22 2020-10-20 上海同罡建筑工程有限公司 一种水中临时支墩施工方法
CN113981961A (zh) * 2021-10-08 2022-01-28 中交路桥华南工程有限公司 深水裸岩的驳船式植桩方法

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102936894A (zh) * 2012-11-27 2013-02-20 中铁上海工程局有限公司第五分公司 小直径灌注桩与基岩的锚固方法
CN104674845A (zh) * 2015-02-09 2015-06-03 中国建筑第八工程局有限公司 液压振动逆作插柱辅助施工方法
CN106320187A (zh) * 2016-10-27 2017-01-11 朱育盼 用于特殊地层中的桥梁施工方法和装置
CN107447751B (zh) * 2017-08-18 2023-04-14 新地能源工程技术有限公司 海上抛石区灌注桩漏浆控制装置和方法
CN107447751A (zh) * 2017-08-18 2017-12-08 新地能源工程技术有限公司 海上抛石区灌注桩漏浆控制装置和方法
CN108049398A (zh) * 2017-12-05 2018-05-18 中交第四公路工程局有限公司 桥位处于泥浆区的桩基施工方法
CN110331736A (zh) * 2019-07-24 2019-10-15 中铁四局集团有限公司 一种用于水中桩基施工的泥浆循环装置及相应施工工法
CN110331736B (zh) * 2019-07-24 2024-02-09 中铁四局集团有限公司 一种用于水中桩基施工的泥浆循环装置及相应施工工法
CN111305754A (zh) * 2020-02-27 2020-06-19 中铁建大桥工程局集团第五工程有限公司 一种基于全液压动力头钻机的灌注桩施工方法
CN111677439A (zh) * 2020-06-24 2020-09-18 中建四局土木工程有限公司 反循环回旋钻机钻进成孔方法
CN111794115A (zh) * 2020-07-22 2020-10-20 上海同罡建筑工程有限公司 一种水中临时支墩施工方法
CN113981961A (zh) * 2021-10-08 2022-01-28 中交路桥华南工程有限公司 深水裸岩的驳船式植桩方法
CN113981961B (zh) * 2021-10-08 2023-06-23 中交路桥华南工程有限公司 深水裸岩的驳船式植桩方法

Also Published As

Publication number Publication date
CN101736755B (zh) 2011-09-28

Similar Documents

Publication Publication Date Title
CN101736755B (zh) 清水孔桩基施工方法
US20210348355A1 (en) Grouting consolidation method for full casing borehole guide prefabricated pile and prefabricated pile therefor
CN108360972A (zh) 一种旋挖钻机与冲击钻机组合进行钻孔灌注桩施工方法
CN110158582A (zh) 一种在无覆盖层河床上设置栈桥钢管桩的方法
CN108978644B (zh) 节能环保型钻孔灌注桩施工方法
CN203174607U (zh) 管内冲击锤破碎土振动挤扩沉管桩机
CN101696578A (zh) 在深水倾斜河床上浇筑桥梁主塔墩基础的施工方法
CN102644275A (zh) 复杂地质条件下旋挖组合成桩施工方法
CN105780763A (zh) 中孔振动套管护壁长螺旋钻孔压灌桩的施工方法
CN102121251A (zh) 一种在深水倾斜河床上浇筑桥梁主塔墩基础的施工方法
CN110984133A (zh) 一种深水浅覆盖层栈桥基础施工方法
CN107514006A (zh) 一种用于浅海或浅河桥梁基础的筑岛作业施工方法
CN106545007A (zh) 在下部为硬质岩层的地层中成桩的方法
CN111594041A (zh) 一种岩溶地质下大直径深孔桩基的快速成孔施工方法
CN103290840A (zh) 孤石群地质条件下预应力管桩施工方法
CN111236216A (zh) 桥梁钻孔桩的施工方法
CN111058458A (zh) 基于绞吸式地连墙局部替代排桩支护的施工方法及结构
CN104047542A (zh) 嵌岩斜桩冲击钻管锤系统及嵌岩斜桩冲击施工方法
CN112281880A (zh) 一种复杂地层长螺旋引孔插打锁口钢管桩围堰的施工方法
CN102733391B (zh) 一种桩体水下切割的施工方法
WO2023207250A1 (zh) 一种斜基面裸岩上栈桥钢管桩快速植桩工法
CN117107748A (zh) 砂岩地区锚固桩机械干作业成孔施工工法
WO2023109014A1 (zh) 一种裸岩河床钢管桩施工设备及施工方法
CN112709252B (zh) 一种半水淹陡峻岩质边坡内的承台施工方法
CN108894230B (zh) 一种护筒下沉遇孤石的处理方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: CCCC ROAD AND BRIDGE CONSTRUCTION CO., LTD.

Free format text: FORMER OWNER: ROAD + BRIDGE GROUP INTERNATIONAL CONSTRUCTION CO., LTD.

Effective date: 20120713

C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20120713

Address after: 101100 auspicious garden 19, Beijing, Tongzhou District

Co-patentee after: Road & Bridge International Co., Ltd.

Patentee after: China Communications Road and Bridge North China Engineering Co., Ltd.

Address before: 101100 auspicious garden 19, Beijing, Tongzhou District

Co-patentee before: CRBC International Co., Ltd.

Patentee before: China Communications Road and Bridge North China Engineering Co., Ltd.