CN102936894A - 小直径灌注桩与基岩的锚固方法 - Google Patents

小直径灌注桩与基岩的锚固方法 Download PDF

Info

Publication number
CN102936894A
CN102936894A CN2012104899474A CN201210489947A CN102936894A CN 102936894 A CN102936894 A CN 102936894A CN 2012104899474 A CN2012104899474 A CN 2012104899474A CN 201210489947 A CN201210489947 A CN 201210489947A CN 102936894 A CN102936894 A CN 102936894A
Authority
CN
China
Prior art keywords
anchoring
steel casing
pile
basement rock
hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2012104899474A
Other languages
English (en)
Inventor
唐俊
刘明友
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fifth Engineering Co Ltd of Shanghai Civil Engineering Co Ltd of CREC
Original Assignee
No5 Branch China Railway Engineering Bureau Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by No5 Branch China Railway Engineering Bureau Ltd filed Critical No5 Branch China Railway Engineering Bureau Ltd
Priority to CN2012104899474A priority Critical patent/CN102936894A/zh
Publication of CN102936894A publication Critical patent/CN102936894A/zh
Pending legal-status Critical Current

Links

Images

Abstract

本发明公开了一种小直径灌注桩与基岩的锚固方法,其特征在于:对于直径≤150mm灌注桩与基岩的锚固方法包括钢管桩的钢护筒定位、打锚杆孔和植入锚杆、锚固成桩的步骤;对于150mm<直径≤1000mm灌注桩与基岩的锚固方法包括钢管桩的钢护筒定位、打钢筋笼孔和锚固成桩的步骤。该方法结合地质特点采用不同的地质钻机在基岩中成小孔或大孔,小孔内放置锚杆压浆锚固,解决了小孔冲击钻孔难的问题,速度快,同时也达到了设计要求的锚固力。大孔放置钢筋笼其整体性较好,采用GSDⅡ型地质钻机钻大孔,大孔放置钢筋笼灌注混凝土锚固的锚固方法,克服了钻机扭矩大的要求。高效经济地解决了灌注桩与基岩的锚固的问题。

Description

小直径灌注桩与基岩的锚固方法
技术领域
本发明一种桩与基岩的锚固方法,尤其是小直径灌注桩与基岩的锚固方法。
背景技术
目前,桩径小于1米的灌注桩入岩均采用冲击成孔灌注水混凝土的方法;施工中,由于冲锤重量较轻,势能不足,导致难成孔,工效低;当桩径越小工效越低,施工难度越大;若遇溶蚀地层或河床岩面倾斜、起伏大、无覆盖层时,成孔施工措施成本将大幅增加大,难度增大。为降低施工难度、减小成本投入,在满足设计安全、质量前提下,急需研发一种既高效又经济的小直径桩入岩锚固方法。
比如,国内广西柳州市静兰大桥和双拥大桥施工场地均位于柳江水域,水位较高,河床基岩溶蚀性地质发达,岩面倾斜、起伏大、无覆盖层或覆盖层较浅。桩径小于1米的小直径灌注桩在岩面以下需要5米以上的锚固深度,采用常规的冲击钻机成孔由于冲锤重量不足很难成孔,工效越低,且溶蚀地质采用冲击钻机成孔容易造成卡锤,施工措施成本很大,影响工程进度。
发明内容
本发明避免了上述现有技术所存在的不足之处,提供一种小直径灌注桩与基岩的锚固方法,高效经济地解决灌注桩与基岩的锚固,特别是在河床基岩地质不良,岩面倾斜、起伏大、无覆盖层时的小直径灌注桩与基岩锚固,效果明显。
为达到上述目的,申请人经过多年的探索、研究和和实践,将小直径灌注桩分为直径≤150mm为小孔、150mm<直径≤1000mm为大孔来两种桩来制作,并与基岩的锚固,效率较高。具体技术方案如下:
一种小直径灌注桩与基岩的锚固方法,其特征在于:
对于直径≤150mm灌注桩与基岩的锚固方法包括以下步骤:
(1)钢护筒定位,在定桩处吊入钢管桩的小钢护筒,并作插打或临时固定,当小钢护筒插打至基岩,若岩面倾斜、起伏,小钢护筒底口漏浆时,浇筑水下不分散混凝土封底;
(2)基岩上打锚杆孔,在浮式平台上采用普通地质钻机在小钢护筒内的基岩面上,垂直打若干个数米深的锚杆孔;
(3)锚杆植入,在各锚杆孔中置入与孔径匹配的锚杆,并在锚杆孔中注入微膨胀水泥浆,水泥凝固后定位锚杆,完成锚杆在锚杆孔中的植入;
(4)钢护筒内的清理,在各锚杆孔中完成锚杆植入后,采用钢丝清洗球将小钢护筒内的浮浆和杂物清洗干净;
(5)锚固成桩,在小钢护筒内的基岩上面置入小钢筋笼后,浇筑水下混凝土即完成该桩与基岩的锚固;
对于150mm<直径≤1000mm灌注桩与基岩的锚固方法包括以下步骤:
(1)钢护筒定位,在定桩处吊入钢管桩的大钢护筒,并作插打或临时固定,当大钢护筒插打至基岩,若岩面倾斜、起伏,大钢护筒底口漏浆时,浇筑水下不分散混凝土封底;
(2)基岩上打钢筋笼孔,在浮式平台上采用GSDⅡ型地质钻机在钢护筒内的基岩面上,垂直钻一个数米深的钢筋笼孔;
(3)钢护筒内的清理,采用水下清洗法将钢筋笼孔内及大钢护筒内杂物清洗干净;
(4)锚固成桩,在大钢护筒中和钢筋笼孔内吊入钢筋笼并定位牢固,浇筑水下混凝土即完成该桩与基岩基础的锚固。
水下不分散混凝土是不会因外界过度振动或遇水而砂、石、水泥分开,即常说的不离析混凝土。它是在普通混凝土中加入具有特定性能的抗分散剂,使之与水泥颗粒发生反应,提高其黏聚力,在水中不分散、自流平、自密实、不泌水的混凝土。可广泛用于水下混凝土施工和建筑物的水下修补。
所述的微膨胀水泥是水化硬化过程中能够产生体积膨胀的水泥。按矿物体系不同,可分为膨胀硅酸盐水泥、膨胀铝酸盐水泥、低热微膨胀水泥、明矾石膨胀水泥、石膏矾土膨胀水泥、硫铝酸盐膨胀水泥、铁铝酸盐膨胀水泥、铝酸盐自应力水泥。
所述的水下清洗法是利用地质钻杆前端安装钢丝球,在钻杆旋转时钢丝球即可清洗孔壁上的杂物等。
所述的水下混凝土是在水中浇筑的混凝土,混凝土遇水时不会离析,其它性能与常规混凝土相似。
本发明结合地质特点采用不同的地质钻机在基岩中成小孔或大孔,小孔内放置锚杆压浆锚固,解决了小孔冲击钻孔难的问题,速度快,同时也达到了设计要求的锚固力。大孔放置钢筋笼其整体性较好,采用GSDⅡ型地质钻机钻大孔,大孔放置钢筋笼灌注混凝土锚固的锚固方法,克服了钻机扭矩大的要求。
与已有技术相比,本发明的效益体现在:
1、本发明使小直径灌注桩基与基岩的锚固强度得到保证,对于直径≤150mm的灌注桩,通过锚杆的连接作用使基岩与桩基牢固连接;对于150mm<直径≤1000mm的灌注桩,通过钢筋笼与基岩的粘接使桩基与基岩形成整体。使桩基与基岩的锚固形式灵活、简单和适用性强;
2、本发明施工难度低,工效高,其钻孔过程操作方便、易于实施,保证施工进度,小孔采用普通地质钻孔一天能成孔15m即一根桩的小孔,大孔采用GSDⅡ型地质钻机一天能成二个大孔,即10m。
附图说明
图1是本发明小孔放置锚杆压浆桩与基岩锚固方法的结构示意图;
图2是本发明大孔放置钢筋笼灌压浆桩与基岩锚固方法的结构示意图;
在图中,水面1,小钢护筒2,水下混凝土3,小钢筋笼4,河床面5,基岩6,锚杆孔7,锚杆8,微膨胀水泥9,不分散混凝土10,大钢护筒11,大钢筋笼12,钢筋笼孔13。
具体实施方式
下面结合附图,对本发明作进一步说明。
图1所示,是本发明小孔放置锚杆压浆桩与基岩锚固方法的结构示意图;在桩基岩层设计位置按孔径和锚固深度要求进行钻孔,孔内设置钢管或型钢锚杆,锚杆规格按实际要求选取,保证其足够的锚固强度。制作直径≤150mm小直径灌注桩通常是在水面1及河床5下的基岩6上进行,直径≤150mm小直径灌注桩与基岩6锚固的方法为:
对于直径≤150mm的灌注桩与基岩锚固方法包括以下步骤:
(1)钢护筒定位,在定桩处吊入钢管桩的小钢护筒2,并作插打或临时固定,当小钢护筒2插打至基岩6,若岩面倾斜、起伏,小钢护筒2底口漏浆时,浇筑水下不分散混凝土10封底;
(2)基岩上打锚杆孔,在浮式平台上采用普通地质钻机在小钢护筒2内的基岩5面上,垂直打三个五米深的锚杆孔7;
(3)锚杆植入,在各锚杆孔7中置入与孔径匹配的锚杆8,并在锚杆孔7中注入微膨胀水泥9,水泥凝固后定位锚杆8,完成锚杆8在锚杆孔7中的植入;
(4)钢护筒内的清理,在各锚杆孔7中完成锚杆植入后,采用钢丝清洗球将小钢护筒2内的浮浆和杂物清洗干净;
(5)锚固成桩,在小钢护筒2内的基岩6上面置入小钢筋笼4后,浇筑水下混凝土3即完成该桩与基岩的锚固。
图2所示,是本发明大孔放置钢筋笼灌压浆桩与基岩锚固方法的结构示意图;它是在同图1的基本条件下进行的,但是,图中的大钢护筒11大于图1中的小钢护筒2,大钢筋笼11代替了图1中的小钢筋笼4,一个钢筋笼大孔13代替了图1中的多个锚杆孔7。同理,制作150mm<直径≤1000mm小直径灌注桩,通常也是在水面1下及河床5下的基岩6上进行,该小直径灌注桩与基岩6锚固的方法为:
对于150mm<直径≤1000mm的灌注桩与基岩锚固方法包括以下步骤:
(1)钢护筒定位,在定桩处吊入钢管桩的大钢护筒11,并作插打或临时固定,当大钢护筒11插打至基岩6,若岩面倾斜、起伏,大钢护筒11底口漏浆时,浇筑水下不分散混凝土10封底;
(2)基岩上打钢筋笼孔,在浮式平台上采用GSDⅡ型地质钻机在大钢护筒11内的基岩面上,垂直钻一个5米深的钢筋笼孔13;
(3)钢护筒内的清理,采用水下清洗法将钢筋笼孔13内及大钢护筒11内杂物清洗干净;
(4)锚固成桩,在大钢护筒11中和钢筋笼孔13内吊入大钢筋笼12并定位牢固,浇筑水下混凝土3即完成该桩与基岩的锚固。

Claims (1)

1.一种小直径灌注桩与基岩的锚固方法,其特征在于:
对于直径≤150mm灌注桩与基岩的锚固方法包括以下步骤:
(A)钢护筒定位,在定桩处吊入钢管桩的小钢护筒(2),并作插打或临时固定,当小钢护筒(2)插打至基岩(6),若岩面倾斜、起伏,小钢护筒(2)底口漏浆时,浇筑水下不分散混凝土(10)封底;
(B)基岩上打锚杆孔,在浮式平台上采用普通地质钻机在小钢护筒(2)内的基岩(5)面上,垂直打若干个数米深的锚杆孔(7);
(C)锚杆植入,在各锚杆孔(7)中置入与孔径匹配的锚杆(8),并在锚杆孔(7)中注入微膨胀水泥(9),水泥凝固后定位锚杆(8),完成锚杆(8)在锚杆孔(7)中的植入;
(D)钢护筒内的清理,在各锚杆孔(7)中完成锚杆植入后,采用钢丝清洗球将小钢护筒(2)内的浮浆和杂物清洗干净;
(E)锚固成桩,在小钢护筒(2)内的基岩(6)上面置入小钢筋笼(4)后,浇筑水下混凝土(3)即完成该桩与基岩的锚固;
对于150mm<直径≤1000mm灌注桩与基岩的锚固方法包括以下步骤:
(A)钢护筒定位,在定桩处吊入钢管桩的大钢护筒(11),并作插打或临时固定,当大钢护筒(11)插打至基岩(6),若岩面倾斜、起伏,大钢护筒(11)底口漏浆时,浇筑水下不分散混凝土(10)封底;
(B)基岩上打钢筋笼孔,在浮式平台上采用GSDⅡ型地质钻机在大钢护筒(11)内的基岩面上,垂直钻一个若干米深的钢筋笼孔(13);
(C)钢护筒内的清理,采用水下清洗法将钢筋笼孔(13)内及大钢护筒(11)内杂物清洗干净;
(D)锚固成桩,在大钢护筒(11)中和钢筋笼孔(13)内吊入大钢筋笼(12)并定位牢固,浇筑水下混凝土(3)即完成该桩与基岩的锚固。
CN2012104899474A 2012-11-27 2012-11-27 小直径灌注桩与基岩的锚固方法 Pending CN102936894A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012104899474A CN102936894A (zh) 2012-11-27 2012-11-27 小直径灌注桩与基岩的锚固方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012104899474A CN102936894A (zh) 2012-11-27 2012-11-27 小直径灌注桩与基岩的锚固方法

Publications (1)

Publication Number Publication Date
CN102936894A true CN102936894A (zh) 2013-02-20

Family

ID=47695815

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012104899474A Pending CN102936894A (zh) 2012-11-27 2012-11-27 小直径灌注桩与基岩的锚固方法

Country Status (1)

Country Link
CN (1) CN102936894A (zh)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103088813A (zh) * 2013-02-21 2013-05-08 北京鑫实路桥建设有限公司 制作钻孔灌注桩的钢筋笼锚固法
CN103397634A (zh) * 2013-08-16 2013-11-20 中铁上海工程局有限公司 一种锁扣钢管桩围堰的锚固施工方法
CN104131554A (zh) * 2014-07-18 2014-11-05 中建港务建设有限公司 钢护筒锚固工艺
CN108457674A (zh) * 2018-03-14 2018-08-28 山东交通学院 一种断层破碎带岩体灾后注浆止浆墙及其施作方法
CN111794115A (zh) * 2020-07-22 2020-10-20 上海同罡建筑工程有限公司 一种水中临时支墩施工方法
CN112081101A (zh) * 2020-09-14 2020-12-15 重庆大学 钢管临时支护约束体系

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1069092A (zh) * 1992-02-19 1993-02-17 浙江海港养护大队 管柱锚固基岩灌注桩和制造方法及应用
US6299385B1 (en) * 1999-08-04 2001-10-09 Paragon Engineering Services Incorporated Mini-jacket and method for installation using caisson
CN101078211A (zh) * 2007-04-23 2007-11-28 中铁大桥局集团第二工程有限公司 水中锚碇系统辅助的板凳结构平台及其施工方法
CN101122131A (zh) * 2007-08-14 2008-02-13 蓝冰 一种用管件桩嵌岩的基坑支护桩
CN101736755A (zh) * 2009-12-15 2010-06-16 中交路桥华北工程有限公司 清水孔桩基施工方法

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1069092A (zh) * 1992-02-19 1993-02-17 浙江海港养护大队 管柱锚固基岩灌注桩和制造方法及应用
US6299385B1 (en) * 1999-08-04 2001-10-09 Paragon Engineering Services Incorporated Mini-jacket and method for installation using caisson
CN101078211A (zh) * 2007-04-23 2007-11-28 中铁大桥局集团第二工程有限公司 水中锚碇系统辅助的板凳结构平台及其施工方法
CN101122131A (zh) * 2007-08-14 2008-02-13 蓝冰 一种用管件桩嵌岩的基坑支护桩
CN101736755A (zh) * 2009-12-15 2010-06-16 中交路桥华北工程有限公司 清水孔桩基施工方法

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
周宏等: ""深水裸岩河床上钻孔桩护筒施工平台的搭设"", 《施工技术》 *
罗根传: ""钻孔平台(栈桥)钢管及桩基钢护筒底部固结方案"", 《西部交通科技》 *

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103088813A (zh) * 2013-02-21 2013-05-08 北京鑫实路桥建设有限公司 制作钻孔灌注桩的钢筋笼锚固法
CN103397634A (zh) * 2013-08-16 2013-11-20 中铁上海工程局有限公司 一种锁扣钢管桩围堰的锚固施工方法
CN104131554A (zh) * 2014-07-18 2014-11-05 中建港务建设有限公司 钢护筒锚固工艺
CN104131554B (zh) * 2014-07-18 2017-02-15 中建港务建设有限公司 钢护筒锚固工艺
CN108457674A (zh) * 2018-03-14 2018-08-28 山东交通学院 一种断层破碎带岩体灾后注浆止浆墙及其施作方法
CN111794115A (zh) * 2020-07-22 2020-10-20 上海同罡建筑工程有限公司 一种水中临时支墩施工方法
CN112081101A (zh) * 2020-09-14 2020-12-15 重庆大学 钢管临时支护约束体系
CN112081101B (zh) * 2020-09-14 2021-10-19 重庆大学 钢管临时支护约束体系

Similar Documents

Publication Publication Date Title
CN102936894A (zh) 小直径灌注桩与基岩的锚固方法
CN104747088B (zh) 一种钻孔灌注桩单腰多叶筒式钻头及成孔施工方法
CN110344400B (zh) 旋挖钻机遇坚硬岩成孔成桩施工工艺
CN102953341B (zh) 一种设置于深水急流无覆盖层陡峭裸岩上的高位栈桥结构
CN101812843B (zh) 中心灌注后压浆桩施工方法及其使用的灌注器和注浆器
CN102518135A (zh) 水平旋喷土锚和灌注桩复合基坑支护施工工法
CN101130991A (zh) 基于基床升浆的沉箱围堰及其施工方法
CN105350584A (zh) 一种抗浮锚杆的施工方法
CN104631438B (zh) 长螺旋钻孔压灌混凝土抗拔桩施工方法
CN107503362A (zh) 一种适用于库岸边坡的复合抗滑桩墙支挡结构及施工方法
CN102392458A (zh) 一种水中裸岩基础施工用钢板桩围堰施工方法
CN102966111A (zh) 一种在深水急流无覆盖层陡峭裸岩上的钢管桩锚固施工方法
CN106837382B (zh) 一种地铁隧道围岩地面预注浆加固工艺
CN102979039A (zh) 一种在深水急流无覆盖层陡峭裸岩上的高位栈桥施工方法
CN112392400A (zh) 复杂地质环境护坡桩成孔施工工艺
CN203049443U (zh) 一种设置于深水急流无覆盖层陡峭裸岩上的高位栈桥结构
CN106638717A (zh) 一种用于基础抗浮的施工方法
CN207211165U (zh) 一种适用于库岸边坡的复合抗滑桩墙支挡结构
CN104762956B (zh) 一种基于建筑垃圾再生骨料桩的成桩方法
CN201459749U (zh) 一种深水钢管桩施工平台稳定结构
CN101793032A (zh) 一种小场地深基坑施工方法
CN202672132U (zh) 一种地下室回填土的加固结构
CN201801843U (zh) 一种带锚碇结构的水上重力式挡土结构
CN208379624U (zh) 一种回填杂土复合地基结构
CN1141460C (zh) 一种用于支护基坑侧壁的无根护壁桩及其施工方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
ASS Succession or assignment of patent right

Owner name: CHINA RAILWAY SHANGHAI ENGINEERING BUREAU GROUP FI

Free format text: FORMER OWNER: NO 5 BRANCH OF SHANGHAI CIVIL ENGINEERING CO., LTD. OF CREC

Effective date: 20140514

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 530031 NANNING, GUANGXI ZHUANG AUTONOMOUS REGION TO: 530000 NANNING, GUANGXI ZHUANG AUTONOMOUS REGION

TA01 Transfer of patent application right

Effective date of registration: 20140514

Address after: 530000, No. 56, Sau Road, Nanning, the Guangxi Zhuang Autonomous Region

Applicant after: China Railway Shanghai Engineering Bureau Group Fifth Engineering Co., Ltd.

Address before: 530031, the Guangxi Zhuang Autonomous Region, Nanning Jiangnan District Wuyi Road, No. 5 South Avenue, Yonghe Bridge at the end of the four Railway Bureau

Applicant before: No.5 Branch, China Railway Engineering Bureau Ltd.

C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20130220