CN101509381B - Composite shield structure suitable for complicated stratum construction - Google Patents

Composite shield structure suitable for complicated stratum construction Download PDF

Info

Publication number
CN101509381B
CN101509381B CN 200810187506 CN200810187506A CN101509381B CN 101509381 B CN101509381 B CN 101509381B CN 200810187506 CN200810187506 CN 200810187506 CN 200810187506 A CN200810187506 A CN 200810187506A CN 101509381 B CN101509381 B CN 101509381B
Authority
CN
China
Prior art keywords
soil
cabin
cutterhead
construction
quarrel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN 200810187506
Other languages
Chinese (zh)
Other versions
CN101509381A (en
Inventor
李建斌
韩亚丽
张志国
陈馈
张红星
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Engineering Equipment Group Co Ltd CREG
China Railway Tunnel Group Co Ltd CRTG
Original Assignee
China Railway Tunnel Group Co Ltd CRTG
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Tunnel Group Co Ltd CRTG filed Critical China Railway Tunnel Group Co Ltd CRTG
Priority to CN 200810187506 priority Critical patent/CN101509381B/en
Publication of CN101509381A publication Critical patent/CN101509381A/en
Application granted granted Critical
Publication of CN101509381B publication Critical patent/CN101509381B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention provides a compound tunnel shield suitable for construction of complex formation, relating to an architectural construction machinery. The compound tunnel shield comprises a compound cutter head suitable for construction of soft soil formation, hard rock formation, formation with uneven hardness and compound formation with both soft soil and hard rock; 3 excavation modes adopting an open mode, a local atmospheric pressure mode or an excavated surface stabilization mode of an earth pressure balance mode according to different geological characteristics of the geology, and a ground conditioning system; the cutter head is respectively provided with a soft soil layer construction tool and a hard rock layer construction tool, cutters are changed to adapt to different formations in the process of the construction thereof; addition agent is injected into the cutter head surface, a soil chamber or a screw conveyer and the addition agent and muck are mixed by rotary stirring of the cutter head, the soil chamber or the screw conveyer to adapt to different formations through ground conditioning. The invention solves the problem of safe construction of the tunnel shield in soft soil, decomposed rock, formations with uneven hardness, sand layer and sand gravel formation, etc.

Description

A kind of composite shield that is applicable to bad ground construction
Technical field
The present invention relates to a kind of construction machine, more particularly, is a kind ofly can adapt to weak soil, can adapt to the combined type earth pressure balanced shield, EPBS of bad ground constructions such as decomposed rock, hard-soft heterogeneous ground, layer of sand and sand-pebble layer again.
Background technology
China region is vast, engineering geology and hydrogeological conditions are quite complicated, geological conditions characteristics according to China, shield structure application technology can roughly be divided into three big stratum: the weak soil layer of promptly above Haiti Qu Wei representative, with the area, Guangzhou is the decomposed rock and the hard-soft heterogeneous ground of representative, is layer of sand, the sand-pebble layer of representative with the Beijing area.Because the geological conditions complexity, therefore, each engineering all should be selected suitable shield structure for use according to the hydrology, the geological conditions of engineering.Chinese patent ZL200510130590.0 has announced " a kind of composite balancing earth-pressure shielding machine ", and this patent has just solved high permeable gravelly sand soil layer or the normal driving problem in ovum (gravel) the stone soil layer.But the composite shield that does not also have simultaneous adaptation weak soil, decomposed rock, hard-soft heterogeneous ground, layer of sand and sand-pebble layer at present.
Summary of the invention
The object of the present invention is to provide a kind of composite shield that is applicable to bad ground construction.The present invention solves the shield structure safe construction problem in Different Strata such as weak soil, decomposed rock, hard-soft heterogeneous ground, layer of sand and sand-pebble layer.
A kind of composite shield that is applicable to bad ground construction of the present invention comprises, cutterhead, shield shell, people cabin, belt conveyor, imitation-shaped knife, conveying worm and Tu Cang, and this shield structure also comprises:
Combined type cutterhead, described cutterhead are the combined type cutterhead, are fit to Different Strata constructions such as weak soil, hard rock, are separately installed with weak soil layer construction tool and ground consisting of hard rock construction tool on the cutterhead, change cutter when Different Strata is constructed;
Three kinds of excavation patterns are according to the excavation face stable mode of different geology employing its open mode, partial pressure pattern or earth pressure balance pattern;
The good system of quarrel land reform, by in cutterhead face, Tu Cang or conveying worm, injecting additive, and the rotation that utilizes cutterhead is stirred, native storehouse mixing plant stirs or conveying worm rotation stirring makes additive mix with the soil quarrel, and is good by the quarrel land reform, to adapt to different stratum.
The present invention is a kind of composite shield that is applicable to bad ground construction, also has following characteristics: the combined type cutterhead comprises cutterhead, wear rib, cutting knife, arc scraper, hobboing cutter and imitation-shaped knife; The cutterhead periphery is equipped with wear rib; Actiniform at least two row's grooves of the notch are arranged on cutterhead, two row's cutting knifes are installed in each bar groove of the notch, be positioned at the cutterhead edge in each row cutting knife end the arc scraper is installed; Between per two grooves of the notch of cutterhead periphery, peripheral openings is arranged, the arc scraper is arranged in each peripheral openings; On cutterhead, be cross arrangement and be provided with hobboing cutter, in the groove of the notch, between two row's cutting knifes imitation-shaped knife is installed.
Three kinds of excavation patterns are respectively:
(1) open type construction is stability rock stratum preferably at the excavation face, need not adjust native storehouse pressure, promptly the excavation face is not carried out the continuous pressure balance, and the shield structure cuts the quarrel soil that gets off and enters in the native storehouse and discharged by conveying worm at once;
(2) partial pressure pattern construction, the quarrel soil of maintenance 60%-70% native storehouse in runs into adjoining rock stability but is rich in phreatic stratum in the driving; The most of adjoining rock stability on the section of perhaps constructing, only there is the part stratum of decompression collapse can occur, perhaps zone of fracture, increase fltting speed in the hope of passing through fast this moment, and temporarily stop screw machine and be unearthed, close the screw machine gate that is unearthed, make the bottom of Tu Cang be full of quarrel stone, inject an amount of interpolation material and compressed air in excavation face and native storehouse, described interpolation material is foam, polymer, swell soil, mud or additive; And then the control screw machine slowly runs to guarantee forming " soil plug " in screw machine;
(3) earth pressure balance pattern construction, for excavating the formation stability difference or more phreatic weak soil or soft rock strata being arranged, the shield structure is in the driving excavation face soil body, the quarrel soil that tunnels is full of in the native storehouse, and make in the native storehouse quarrel soil density as far as possible with the tunnel excavation face on density of soil approaching; Under the thrust that advances oil cylinder, the quarrel soil that is full of in the native storehouse forms certain pressure, and quarrel soil pressure in the native storehouse and the water on the tunnel excavation face, soil pressure realize dynamic equilibrium.When adopting the earth pressure balance pattern, when differently the quality section is tunneled, add foaming agent, polymer, swell soil etc. as required to improve quarrel soil nature energy.
The good system of quarrel land reform comprises: soil pressure case, swell soil system interface, foam maker, foaming agent pump, water pump, foaming agent case and water tank, soil pressure case is installed on cutterhead, the swell soil system interface connects by pipeline, foam maker connects the swell soil system interface by pipeline, and the foaming agent case is connected the swell soil system interface through the foaming agent pump respectively with water tank with water pump.
A kind of composite shield that is applicable to bad ground construction of the present invention also comprises being with and compresses into the cabin security system; This system is made of main cabin, import cabin, excavation cabin and pressure-retaining system; The excavation freight space is in the cutterhead next door, and main cabin is connected with the excavation cabin, and main cabin is connected with the import cabin, between excavation cabin and main cabin, main cabin and the import cabin manhole door is arranged, and manhole door is closely closed; Pressure-retaining system connects the excavation cabin.
A kind of composite shield that is applicable to bad ground construction of the present invention, stable mechanism by excavation face in the research shield-tunneling construction, a kind of combined type earth pressure balanced shield, EPBS that has high-adaptability in bad ground is provided, at the characteristics of different geological conditionss, the safe construction system of energy simultaneous adaptation weak soil, decomposed rock, hard-soft heterogeneous ground, layer of sand and sand-pebble layer.
A kind of composite shield that is applicable to bad ground construction of the present invention, by adopting different excavation face stable modes and different cutter layouts and the good system of land reform that is cut to adapt to Different Strata, and design has band to compress into the cabin security system, can carry out the maintenance of inspection, replacing and other parts of cutter or the eliminating of underground obstacle safely and reliably fast.
Composite shield of the present invention, its geological adaptability is very wide, has broad application prospects in China.
Description of drawings
Fig. 1 is the structural representation of main frame of the present invention;
Fig. 2 is the structural representation of combined type cutterhead;
Fig. 3 is the lateral view of Fig. 2;
Fig. 4 is the schematic diagram of open type construction;
Fig. 5 is the schematic diagram of partial pressure pattern construction;
Fig. 6 is the schematic diagram of earth pressure balance pattern construction;
Fig. 7 is the schematic diagram of the good system of quarrel land reform;
Fig. 8 is the schematic diagram that band is compressed into the cabin security system;
Fig. 9 is the structural representation that band is compressed into the cabin security system;
Figure 10 is that band is compressed into cabin security system flow chart.
Among the figure: cutterhead 1, shield shell 2, people cabin 3, advance oil cylinder 4, pin joint 5, shield tail 6, rounding device 7, expansion bend 8, shield tail sealing 9, conveying worm driving mechanism 10, belt conveyor 11, early gate 13, conveying worm 14, hinged oil cylinder 15, section of jurisdiction fitting machine 16, installation head 17, section of jurisdiction conveyer 18, wear rib 19, foam mouth 20, stirring rod 21, cutting knife 22, the groove of the notch 23, arc scrapes 24, peripheral openings 25, hobboing cutter 26, imitation-shaped knife 27, cutter plate driver 28, soil pressure case 29, slew gear 30, swell soil system interface 31, foaming agent pump 32, water pump 33, foaming agent case 34, water tank 35, foam maker 36, main cabin 37, import cabin 38, excavation cabin 39, pressure-retaining system 40, mud salt 41, soil storehouse 42, manhole door 43.
The specific embodiment
With illustrated embodiments the present invention is done detailed explanation below:
Consult Fig. 1, a kind of composite shield that is applicable to bad ground construction comprises, cutterhead 1, shield shell 2, people cabin 3, belt conveyor 11, profiling 27, conveying worm 14 and native storehouse 42, and this system also comprises:
The combined type cutterhead, described cutterhead 1 is the combined type cutterhead, is fit to soft soil layer construction and ground consisting of hard rock construction, is separately installed with weak soil layer construction tool and ground consisting of hard rock construction tool on the cutterhead, changes cutter when Different Strata is constructed;
Three kinds of excavation patterns are according to the excavation face stable mode of different geology employing its open mode, partial pressure pattern or earth pressure balance pattern;
The good system of quarrel land reform, by in cutterhead face, Tu Cang or conveying worm, injecting additive, and the rotation that utilizes cutterhead is stirred, native storehouse mixing plant stirs or conveying worm rotation stirring makes additive mix with the soil quarrel, and is good by the quarrel land reform, to adapt to different stratum.
Consult Fig. 2 and Fig. 3, the combined type cutterhead comprises cutterhead 1, wear rib 19, cutting knife 22, arc scraper 24, hobboing cutter 26 and imitation-shaped knife 27; Cutterhead 1 periphery is equipped with wear rib 19; Actiniform at least two row's grooves of the notch 23 are arranged on cutterhead 1, two row's cutting knifes 22 are installed in each bar groove of the notch 23, be positioned at cutterhead 1 edge in each row cutting knife 22 end arc scraper 24 is installed; Between per two grooves of the notch 23 of cutterhead 1 periphery, peripheral openings 25 is arranged, in each peripheral openings 25, arc scraper 24 is arranged; On cutterhead 1, be cross arrangement and be provided with hobboing cutter 26, in the groove of the notch 23, between two row's cutting knifes 22 imitation-shaped knife 27 is installed.
Consult Fig. 4, Fig. 5 and Fig. 6, three kinds of excavation patterns are respectively:
(1) open type construction is stability rock stratum preferably at the excavation face, need not adjust native storehouse pressure, promptly the excavation face is not carried out the continuous pressure balance, and the shield structure cuts the quarrel soil that gets off and enters in the native storehouse and discharged by conveying worm at once;
(2) partial pressure pattern construction, the quarrel soil of maintenance 60%-70% native storehouse in runs into adjoining rock stability but is rich in phreatic stratum in the driving; The most of adjoining rock stability on the section of perhaps constructing only has the part stratum of decompression collapse can occur; Perhaps zone of fracture, increase fltting speed in the hope of passing through fast this moment, and temporarily stop screw machine and be unearthed, close the screw machine gate that is unearthed, make the bottom of Tu Cang be full of quarrel stone, inject an amount of interpolation material and compressed air in excavation face and native storehouse, described interpolation material is foam, polymer, swell soil, mud or additive; Controlling screw machine again slowly runs to guarantee forming " soil plug " in screw machine;
(3) or, the construction of earth pressure balance pattern, for excavating the formation stability difference or more phreatic weak soil or soft rock strata being arranged, the shield structure is in the driving excavation face soil body, the quarrel soil that tunnels is full of in the native storehouse, and make in the native storehouse quarrel soil density as far as possible with the tunnel excavation face on density of soil approaching; Under the thrust that advances oil cylinder, the quarrel soil that is full of in the native storehouse forms certain pressure, and quarrel soil pressure in the native storehouse and the water on the tunnel excavation face, soil pressure realize dynamic equilibrium.
Consult Fig. 7, the good system of quarrel land reform comprises: soil pressure case 29, swell soil system interface 31, foam maker 36, foaming agent pump 32, water pump 33, foaming agent case 34 and water tank 35, soil pressure case 29 is installed on cutterhead 1, swell soil system interface 31 connects 42 by pipeline, foam maker 36 connects the swell soil system by pipeline and connects 31, and foaming agent case 34 is connected the swell soil system through foaming agent pump 32 with water pump 33 respectively with water tank 35 and connects 31.
Consult Fig. 8 and Fig. 9, a kind of composite shield that is applicable to bad ground construction also comprises being with and compresses into the cabin security system; This system is made of main cabin 37, import cabin 38, excavation cabin 39 and pressure-retaining system 40; Excavation cabin 39 is positioned at cutterhead 1 next door, and main cabin 37 is connected with excavation cabin 39, and main cabin 37 is connected with import cabin 38, between excavation cabin 39 and main cabin 37, main cabin 37 and the import cabin 38 manhole door is arranged, and manhole door is closely closed; Pressure-retaining system 40 connects excavation cabin 39.
The main frame of composite shield provided by the present invention mainly comprises: shield shell, cutterhead, cutter plate driver, conveying worm, belt conveyor, section of jurisdiction fitting machine, people storehouse etc.See Fig. 1.
Composite shield of the present invention, its cutterhead is the combined type cutterhead, sees Fig. 2 and Fig. 3.Adopting the combined type cutterhead is one of main feature of composite shield.The weak soil cutter both had been installed on cutterhead,, hard rock cutter (hobboing cutter) had been installed again as cutting knife and scraper, imitation-shaped knife.Arrange to adapt to Different Strata by different cutters.When soft soil layer was constructed, the hard rock hobboing cutter on the combined type cutterhead is replaceable to be cutter in advance (serrated knife, tear cutter or shell cutter).
Composite shield of the present invention has three kinds of excavation face stable modes (seeing Fig. 4,5,6).In shield-tunneling construction, can adopt different excavation face stable modes according to different geology.Two of the main feature that adopts various modes and can be composite shield according to the different conversion work patterns of geology.
Three kinds of excavation face stable modes are respectively its open mode, partial pressure pattern and earth pressure balance pattern, and each stable mode has different characteristics and suitable different stratum.
1) open type
Composite shield can adopt the open type construction in the face of the excavation face is a stability preferably during the rock stratum, need not adjust native storehouse pressure.The open type pattern generally is used for the stratum from the steady reasonable occasion of condition, even the excavation face is not carried out the continuous pressure balance, also can guarantee not unstability of excavation face at short notice, and the soil body does not cave in.Can adopt this pattern from the stratum steady, that underground water is few more.The shield structure cuts the quarrel soil that gets off and enters in the native storehouse and discharged by conveying worm at once, and the quarrel soil of minute quantity is only arranged in the native storehouse, and Tu Cang is in the state of emptying substantially, and the suffered anti-torsion of cutterhead and conveying worm is less in the driving.When adopting its open mode driving,, adopt high rotating speed, low moment of torsion and suitable conveying worm rotating speed to advance based on the broken rock of hobboing cutter; During synchronous grouting, slurries may seepage flow to space between shield shell and surrounding rock body even cutterhead place, can take suitably to increase slurry viscosity for avoiding this phenomenon to take place, shorten slurries time of setting, adjust method such as grouting pressure, section of jurisdiction additional slip casting behind and solve.
2) partial pressure pattern
Also claim semi-open-type.Composite shield has certain self-stability for the excavation mask, can adopt semi-open-type; The rotating speed of adjustable screw conveyer keeps about 2/3 quarrel soil in the native storehouse.If run into adjoining rock stability but be rich in phreatic stratum in the driving; The most of adjoining rock stability on the section of perhaps constructing only has the part stratum of decompression collapse can occur; Perhaps zone of fracture.Should increase fltting speed in the hope of passing through fast this moment, and temporarily stop screw machine and be unearthed, close the screw machine gate that is unearthed, make the bottom of Tu Cang be full of quarrel stone, in excavation face and native storehouse, inject an amount of interpolation material (as swell soil, mud or additive) and compressed air, the dense water of quarrel soil in the native storehouse is increased, also make simultaneously the interpolation material infilter excavation face stratum under pressure, on the excavation face, produce " the mud film " of one deck densification.By the generation of air pressure and the mud film prevention excavation face water burst and the phenomenon of caving in, control screw machine again and slowly run to guarantee in screw machine, forming " soil plug ", be can pass through this badness stratum safely and fast fully.Quarrel soil underfill Tu Cang in the driving in the native storehouse still has certain space, excavates face and prevents that underground water from infiltrating by input compressed air in native storehouse and the native together support of quarrel.This driving pattern is applicable to have certain self-stable ability and the not too high stratum of groundwater pressure, and its effect that prevents that underground water from infiltrating depends primarily on compressed-air actuated pressure, when the last soft construction of hard formation down adopts this pattern more.Breaking rock with hobboing cutter when last soft following hard formation is constructed is main broken hard rock, is the main cutting soil layer with serrated knife, scraper.When the river bed section is tunneled, need to add the sealing that foaming agent, polymer, swell soil etc. improve quarrel soil, so that the pressure stability balance in the native storehouse.
3) earth pressure balance pattern
Composite shield is bad or when more phreatic soft rock stratum is arranged for the excavation formation stability, needs to adopt the earth pressure balance pattern; Need the difference according to the stratum, front this moment, keeps different native storehouse pressure.
The shield structure is full of in the native storehouse quarrel soil that tunnel in the driving excavation face soil body, and make in the native storehouse the native density of quarrel as far as possible with the tunnel excavation face on density of soil approaching.Under the thrust that advances oil cylinder, the quarrel soil that is full of in the soil storehouse forms certain pressure, quarrel soil pressure in the soil storehouse and the water on the tunnel excavation face, soil pressure realize dynamic equilibrium, soil on the excavation face just can not collapse easily like this, reaches the unstability of not only finishing driving but also can not causing the excavation face soil body.
Pressure in the soil storehouse can be regulated by the driving speed of change shield structure or the rotating speed (deslagging amount soil) of screw machine, by measuring (comprising the mud material amount that adds) corresponding deslagging amount continuous excavation with shield structure digging soil, assurance makes digging soil amount corresponding with the deslagging amount, make the soil pressure of the creeping quarrel soil in the native storehouse can be all the time with the excavation face on water and soil pressure keep balance, the stability that keeps the excavation face, the pressure size obtains according to the pressure sensor that is installed on the native bulkhead, and screw machine rotating speed (casting amount) is regulated automatically according to the soil pressure that pressure sensor obtains.
When adopting the earth pressure balance pattern, be the main cutting soil layer, advance with the slow-speed of revolution, high pulling torque with serrated knife, cutting knife.The soil pressure value should be slightly larger than hydrostatic pressure and stratum soil pressure sum in the soil storehouse, when differently the quality section is tunneled, add foaming agent, polymer, swell soil etc. as required to improve quarrel soil nature energy, also the sealing pressurizer can be installed on conveying worm, so that the pressure stability balance in the native storehouse.
Composite shield of the present invention has the good system of quarrel land reform (see figure 7).Adopt the good system of quarrel land reform be composite shield the major technique characteristics three.
The good system of quarrel land reform is by injecting additive such as foam, swell soil or polymer etc. in cutterhead face, Tu Cang or conveying worm, and the rotation that utilizes cutterhead is stirred, native storehouse mixing plant stirs or conveying worm rotation stirring makes additive mix with the soil quarrel, good by the quarrel land reform, to adapt to different stratum.
The good system of quarrel land reform of composite shield can improve the native creeping of quarrel, improves sealing, reduces the cutterhead moment of torsion, reduces the wearing and tearing of knife disc tool and conveying worm, and to the good result of face sealing.
1. foaming system
Foaming system is mixed with a certain proportion of water by screw pump pumping foam, and through foam maker, the foaming of pressure-air blow pressure produces a large amount of foams, is transported to cutterhead front, Tu Cang or conveying worm by pipeline and mixes with quarrel soil.Foam has following advantage:
◆ because the lubricant effect of bubble has reduced the native angle of internal friction of quarrel, improve the flowability of quarrel soil, thereby reduced the moment of torsion of cutterhead, improved shield structure job parameter;
◆ reduce the permeability of quarrel soil, make whole spoil power transmission even, the face pressure fluctuation is little, helps adjusting native storehouse pressure, guarantees shield excavation attitude, the control ground settlement;
◆ reduce the viscosity of clay, help being unearthed;
◆ foam is nontoxic, can decompose disappearance voluntarily after 2 hours, and is pollution-free to soil environment.
Foaming system mainly comprises foaming agent jar, foaming agent pump, water pump, solution metering control valve, air dose control valve, fluid flowmeter, gas flowmeter, foam maker and connecting line.
The foaming agent pump pumps foaming agent from the foaming agent jar, and the water that pumps with water pump mixes formation solution in the ratio of shield structure driver operation instruction, control system is to measure the flow of water pump water outlet by the fluid flowmeter that is installed in the pump outlet place, and finishes this mixed proportion instruction according to the output quantity of this flow-control foaming agent pump.When mixed solution is fed forward, be assigned with and be transported in 4 pipelines, behind solution adjustable valve and fluid flowmeter, be transported in 4 foam makers again respectively, mix the generation foam with the compressed air that is transfused to simultaneously in foam maker, compressed air also will pass through gas flowmeter and air dose control valve earlier before entering foam maker.Foaming agent solution and compressed air also are to mix in the ratio of shield structure driver operation instruction, and this instruction needs to receive the information of fluid flowmeter and gas flowmeter and control the air dose control valve and the solution adjustable valve is finished by shield structure control system.At last, foam,, is injected in the excavation chamber again by the opening on the cutterhead by the cutterhead swivel joint along 4 pipelines.In the control room, operating personnel also can select arbitrarily from four pipelines as required, add foam to the excavation chamber.
2. swell soil system
The swell soil system comprises swell soil case, swell soil pump, pneumatic swell soil pipe-line control valve and connecting line.The shared 1 cover filling line of swell soil system and foaming system.
When needing to inject swell soil, swell soil by the swell soil pump along pipeline to front pump to the shield body, operating personnel can be as required, on the operating console in control room, by controlling the switch of pneumatic swell soil pipe-line control valve, swell soil is joined in excavation chamber, clay bin or the conveying worm.
3. polymer system
Polymer system utilizes this height of polymer bleed performance, makes the quarrel local products give birth to plasticity, is used to prevent to gush generation.Effect is more obvious aspect the generation that this system prevents to be cut in high hydraulic pressure Fu Shui stratum, water is gushed.Be used for hinged sealing place and Tu Cang.
Composite shield of the present invention has band and compresses into cabin security system (Fig. 8,9).Described people storehouse is the two chamber Ren Cang of two gas circuits, and the people storehouse is the pith that band is compressed into the cabin security system.For solving the risk of shield-tunneling construction, safely and reliably in the maintenance of depressing very much the inspection, replacing and other parts that carry out cutter fast or the eliminating of underground obstacle, composite shield of the present invention has adopted safe and reliable two gas circuit people storehouse and automatic pressure-retaining system.
Adopt the two chamber Ren Cang of two gas circuits when band is compressed into the cabin, personnel enter into the excavation cabin that is in high pressure from atmospheric area, should pass through the pressure period; Enter into atmospheric area from the excavation cabin that is in high pressure, should pass through decompression phase.Otherwise injured by air pressure, produce dysbarism.Must adopt the two chamber Ren Cang of two gas circuits so band is compressed into the cabin, the two chamber Ren Cang of two gas circuits have the airlock structure.Adding the decompression phase process carries out in airlock.
The airlock of the two storehouses, people from chamber of two gas circuits of shield structure and other form or the manned pressure vessel of other form are not had interchangeability.The two storehouses, people from chamber of two gas circuits of shield structure must adapt with the design feature of shield structure.
The two chamber Ren Cang of two gas circuits have at least two direct interconnected cabins to form.A cabin is as normal main cabin of reducing pressure, and a cabin is as the import cabin, and this cabin can be used as urgent decompression cabin.Main cabin is made up of the structure space in separate type cabin and the shield structure.Structure space in the shield structure by the excavation cabin partition wall and on every side steel work form, have plane coupling flange wall.The separate type cabin has two cabins.The separate type cabin connects by the flange wall in bolt and the shield machine, and seals with seal.On the corresponding wall in main cabin and import cabin manhole and manhole door are arranged, manhole door can closely be closed.The staff can open manhole door and enter into main cabin and import cabin or enter into the excavation cabin.
Be with the safety of compressing into cabin work for ensureing, the control system in the two storehouses, people from chamber of two gas circuits should have:
1) aerating, exhaust system.The equilibrium pressure that needs in the cabin is provided, breathe air is provided, ensure amount of fresh air.
2) fire fighting system.Prevent fire.Water fire fighting system and hand-held fire extinguisher are arranged.
3) air-conditioning system.The indoor air themperature of support module is in suitable scope.Suitable personnel carry out work.
4) gas pressure, temperature measurement system in the cabin.Measure display module indoor gas pressure, temperature in real time, be convenient to grasp the cabin personnel operation.The temperature that keep-ups pressure is in suitable scope.
5) communication system.Have explosion-proof communication system and acoustic energy communication system, ensure that each cabin is unimpeded with outside communication.
6) illumination and emergency lighting system.The time of emergency lighting should not be lower than 1 hour.
7) oxygen uptake system.Be used for the fast decompression process, or anoxic environment.
8) gas detecting analytical system.Whether pernicious gases such as check and analysis gas, carbon dioxide exceed standard, and whether oxygen content is suitable.
9) time display system.Be convenient to grasp add, activity duration of decompression time or staff.
Composite shield of the present invention has band and compresses into cabin auxiliary security guarantee control system.
According to the operating principle of shield method, compress into the safety of cabin work for ensureing band, the auxiliary security of airlock ensures that control system has:
1) mud injected system
With the quarrel soil in the special mud displacement excavation cabin, and at the comparatively stable mud film of the anterior formation of cutterhead.Make face have good impervious and firm performance.
2) air-pressure controlling system
Muddy water with the first half in the compressed air slurry displacement excavation cabin provides personnel working space.Ensure and breathe compressed-air actuated supply, guarantee to keep the pressure balance in the excavation cabin.
It is a kind of job that requires special skills mode that band is compressed into cabin work, should follow corresponding security step and measure.China does not also have the shield method band to compress into the technical specification file of aspect, cabin at present, and the scene is generally with reference to diving aspect technical specification.
Consult Figure 10, band is compressed into cabin safe procedures figure.
Compress into the cabin process at band, have according to concrete condition of construction what time to should be noted that:
1) chooses the qualified cabin personnel that advance.Advance the cabin personnel and not only should grasp into cabin job content, also should have good physical qualification.
2) operate according to the decompression table of science.
3) utilize mud to form the thicker impervious mud film of one deck, guarantee bubble-tight effect thereby reach at the excavation face.
4) compressed air pressure in the excavation cabin requires than calculating about the high 0.1~0.2bar of soil pressure.In the operation process that opens the cabin, should keep this pressure as far as possible, and the changing value of air pressure is controlled within the controlled range by the operation of admission valve; The compressed air that enters the excavation cabin should be to breathe compressed air.
5) determine the stability of excavation face by the Structural Engineer, whether need to carry out ground stabilization.
6) two above communication lines are set, in the storehouse that keep-ups pressure, the contact that reaches extraneous relevant departments outside the storehouse is unimpeded.
And establish the special messenger to ground monitoring and tour, and note abnormalities, in time ask processing for instructions.

Claims (3)

1. a composite shield that is applicable to bad ground construction comprises, cutterhead (1), shield shell (2), people cabin (3), belt conveyor (11), imitation-shaped knife (27), conveying worm (14) He Tucang (42) is characterized in that:
Described cutterhead (1) is the combined type cutterhead, is fit to weak soil, the construction of hard rock Different Strata, is separately installed with weak soil layer construction tool and ground consisting of hard rock construction tool on the cutterhead, changes cutter when Different Strata is constructed;
Three kinds of excavation patterns are according to the excavation face stable mode of different geology employing its open mode, partial pressure pattern or earth pressure balance pattern;
The good system of quarrel land reform, by in cutterhead face, Tu Cang or conveying worm, injecting additive, and the rotation that utilizes cutterhead is stirred, native storehouse mixing plant stirs or conveying worm rotation stirring makes additive mix with the soil quarrel, and is good by the quarrel land reform, to adapt to different stratum;
Also comprise being with and compress into the cabin security system; This system is made of main cabin (37), import cabin (38), excavation cabin (39) and pressure-retaining system (40); Excavation cabin (39) is positioned at cutterhead (1) next door, main cabin (37) is connected with excavation cabin (39), main cabin (37) is connected with import cabin (38), between excavation cabin (39) and main cabin (37), main cabin (37) and import cabin (38) manhole door (43) is arranged, manhole door (43) is closely closed; Pressure-retaining system (40) connects excavation cabin (39).
2. a kind of composite shield that is applicable to bad ground construction as claimed in claim 1 is characterized in that, the combined type cutterhead comprises cutterhead (1), wear rib (19), cutting knife (22), arc scraper (24), hobboing cutter (26) and imitation-shaped knife (27); Cutterhead (1) periphery is equipped with wear rib (19); Actiniform at least two row's grooves of the notch (23) are arranged on cutterhead (1), two row's cutting knifes (22) are installed in each bar groove of the notch (23), be positioned at cutterhead (1) edge in each row cutting knife (22) end arc scraper (24) is installed; Between cutterhead (1) per two grooves of the notch of periphery (23), peripheral openings (25) is arranged, arc scraper (24) is arranged in each peripheral openings (25); On cutterhead (1), be cross arrangement and be provided with hobboing cutter (26), in the groove of the notch (23), between two row's cutting knifes (22) imitation-shaped knife (27) is installed.
3. a kind of composite shield that is applicable to bad ground construction as claimed in claim 1 is characterized in that, three kinds of excavation patterns are respectively:
(1) its open mode construction is stability rock stratum preferably at the excavation face, need not adjust native storehouse pressure, promptly the excavation face is not carried out the continuous pressure balance, and the shield structure cuts the quarrel soil that gets off and enters in the native storehouse and discharged by conveying worm at once;
(2) partial pressure pattern construction, the quarrel soil of maintenance 60%-70% native storehouse in runs into adjoining rock stability but is rich in phreatic stratum in the driving; The most of adjoining rock stability on the section of perhaps constructing, only there is the part stratum of decompression collapse can occur, perhaps zone of fracture, increase fltting speed in the hope of passing through fast this moment, and temporarily stop conveying worm and be unearthed, close the conveying worm gate that is unearthed, make the bottom of Tu Cang be full of quarrel stone, inject an amount of interpolation material and compressed air in excavation face and native storehouse, described interpolation material is foam, polymer, swell soil, mud or additive; And then the control conveying worm slowly runs to guarantee forming " soil plug " in conveying worm;
(3) earth pressure balance pattern construction, for excavating the formation stability difference or more phreatic weak soil or soft rock strata being arranged, the shield structure is in the driving excavation face soil body, the quarrel soil that tunnels is full of in the native storehouse, and make in the native storehouse quarrel soil density as far as possible with the tunnel excavation face on density of soil approaching; Under the thrust that advances oil cylinder, the quarrel soil that is full of in the soil storehouse forms certain pressure, quarrel soil pressure in the soil storehouse and the water on the tunnel excavation face, soil pressure realize dynamic equilibrium, when adopting the earth pressure balance pattern, when differently the quality section is tunneled, add foaming agent, polymer, swell soil as required to improve quarrel soil nature energy.
CN 200810187506 2008-12-24 2008-12-24 Composite shield structure suitable for complicated stratum construction Active CN101509381B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 200810187506 CN101509381B (en) 2008-12-24 2008-12-24 Composite shield structure suitable for complicated stratum construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 200810187506 CN101509381B (en) 2008-12-24 2008-12-24 Composite shield structure suitable for complicated stratum construction

Publications (2)

Publication Number Publication Date
CN101509381A CN101509381A (en) 2009-08-19
CN101509381B true CN101509381B (en) 2011-07-27

Family

ID=41001900

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 200810187506 Active CN101509381B (en) 2008-12-24 2008-12-24 Composite shield structure suitable for complicated stratum construction

Country Status (1)

Country Link
CN (1) CN101509381B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102733813A (en) * 2012-06-29 2012-10-17 中铁隧道装备制造有限公司 Opened shield sealing device

Families Citing this family (45)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101713292B (en) * 2009-10-19 2011-06-29 清华大学 Full-time propulsion system structure used in earth pressure balanced shield
CN102230384B (en) * 2011-07-01 2014-02-19 河海大学 Earth pressure balance/ muddy water pressurization continuously-switching shield construction method
CN102359925B (en) * 2011-07-14 2012-12-26 北京工业大学 Soil mass improvement test method of complete earth pressure balance shield construction
CN102305083A (en) * 2011-08-01 2012-01-04 北京市三一重机有限公司 Shield machine and anterior shield system thereof
CN102330558B (en) * 2011-09-20 2016-08-03 海瑞克(广州)隧道设备有限公司 Shield machine is with six arm cutterheads
CN102383805B (en) * 2011-10-19 2013-12-04 中铁隧道装备制造有限公司 Mixed TBM (Tunnel Boring Machine) with multiple-boring mode and tunnel supporting mode
CN102364049B (en) * 2011-10-19 2014-03-12 中铁隧道装备制造有限公司 Hard rock composite TBM (Tunnel Boring Machine) suitable for composite stratum and tunneling mode thereof
CN102410027B (en) * 2011-10-19 2013-10-30 中铁隧道装备制造有限公司 Dual-mode TBM (tunnel boring machine) and control method thereof
CN102926761B (en) * 2012-11-21 2015-07-01 中国铁建重工集团有限公司 Double-mode cutterhead suitable for long-distance and great-gradient inclined well tunnel construction
CN103291313B (en) * 2013-06-08 2016-03-02 中铁工程装备集团有限公司 EPB shield tunneling excavation pressure vault support system and construction method thereof
CN104100276A (en) * 2014-07-02 2014-10-15 北京城建设计发展集团股份有限公司 Uneven soft or hard mutual intrusion composite rock stratum shield cutterhead type selection and cutting tool configuration technology
CN104265313A (en) * 2014-09-25 2015-01-07 无锡市翱宇特新科技发展有限公司 Soil agitating structure of shield
CN104526297B (en) * 2014-12-05 2017-02-22 徐工集团凯宫重工南京有限公司 Auxiliary cutter replacing device for shield tunneling machine cutter in tunnel
CN104775824B (en) * 2015-04-30 2017-01-04 中铁工程装备集团有限公司 A kind of slurry shield main frame that can be used for upper-soft lower-hard ground
CN105041326A (en) * 2015-06-12 2015-11-11 北京城建设计发展集团股份有限公司 Water-rich diabase and slate irregular mutual invasion rock shield residue soil improving method
CN105673026B (en) * 2016-01-13 2017-12-26 上海隧道工程有限公司 A kind of soil pressure autocompensation installation for being used to adjust class rectangle shield soil pressure
CN105781561B (en) * 2016-03-28 2018-05-01 中南大学 Study the indoor earth pressure balanced shield, EPBS driving simulation system of soft stratum stress response
CN105909264B (en) * 2016-06-08 2018-06-15 中国铁建重工集团有限公司 Broken agitating device, slurry balance shield machine and multi-mode shield machine
CN106869953A (en) * 2017-03-23 2017-06-20 中铁局集团城市轨道交通工程有限公司 Soft lower hard and tunneling boring hard rock balance driving method of calming the anger on earth pressure balanced shield, EPBS
CN106812173A (en) * 2017-04-10 2017-06-09 中国水利水电第七工程局成都水电建设工程有限公司 A kind of modified earth tunnel excavates auxiliary equipment
CN107100638A (en) * 2017-04-25 2017-08-29 封鸿涛 Automatic soil layer mole and method
CN107313781B (en) * 2017-06-23 2023-07-14 山河智能装备股份有限公司 One-step molding tunneling machine and tunneling method for shallow stratum pipe gallery
CN109281685B (en) * 2017-07-21 2024-03-12 中国铁建重工集团股份有限公司 Step-by-step decompression type shield tunneling machine
CN107387105B (en) * 2017-08-11 2023-12-22 中交天和机械设备制造有限公司 Soil pressure shield bentonite pressure maintaining equipment and method
CN108756916B (en) * 2018-06-12 2019-11-05 中铁隧道局集团有限公司 High-intensitive basement rock protrusion stratum shield construction method
CN108868797B (en) * 2018-06-29 2020-05-01 中铁工程装备集团有限公司 Shield machine host system
CN108756918B (en) * 2018-07-19 2024-02-13 中国铁建重工集团股份有限公司 Pipe-free sheet assembling device and shield tunneling machine
CN109184716B (en) * 2018-11-12 2020-07-14 嘉兴麦瑞网络科技有限公司 External tunneling assembly of shield tunneling machine cutter head
CN109630149B (en) * 2018-12-21 2021-02-09 广州轨道交通建设监理有限公司 Multi-mode shield constructs machine
CN109403994B (en) * 2018-12-29 2021-01-22 中国铁建重工集团股份有限公司 Tunneling construction method for slurry balance shield machine
CN110145320A (en) * 2019-06-24 2019-08-20 中铁隧道局集团有限公司 A kind of TBM crosses the construction method of complicated geological
CN110905532A (en) * 2019-11-11 2020-03-24 中交第四航务工程局有限公司 Shield constructs screw machine with prevent gushing device
CN111305858B (en) * 2020-03-15 2021-01-01 南宁中铁广发轨道装备有限公司 Mixed mold shield machine
CN111577304A (en) * 2020-05-07 2020-08-25 中铁隧道局集团有限公司 Shield tunneling machine capable of prolonging service life of cutter and using method thereof
CN111594192A (en) * 2020-05-27 2020-08-28 重庆交通建设(集团)有限责任公司 Double-mode switching shield tunneling machine system
CN111561325B (en) * 2020-07-02 2022-02-08 中铁工程装备集团有限公司 Muck stirring monitoring device and stirring detection method thereof
CN111852494B (en) * 2020-07-30 2022-07-26 中铁工程装备集团有限公司 Earth pressure balance shield machine
CN112360495B (en) * 2020-11-12 2022-11-22 安徽唐兴装备科技股份有限公司 Equipment for conveying excavated materials in tunneling
CN112709537B (en) * 2020-12-24 2023-02-03 中国十九冶集团有限公司 Anchor hole drilling device
CN112664215A (en) * 2020-12-29 2021-04-16 天津倚通科技发展有限公司 Laying method of trenchless new pipeline
CN113309530B (en) * 2020-12-30 2023-03-28 中铁工程装备集团有限公司 Multi-mode heading machine soil pressure monitoring system and working method thereof
CN112855188B (en) * 2021-01-13 2022-04-29 中铁广州工程局集团有限公司 Subway engineering soft soil stratum earth pressure balance shield construction method
CN112963161B (en) * 2021-03-01 2023-02-17 中交(广州)建设有限公司 Method for maintaining hinged sealing structure of shield machine in working well
CN112983446A (en) * 2021-04-22 2021-06-18 中铁一局集团第二工程有限公司 Construction method for shield cutting of existing station reinforced concrete fender post
CN114033406B (en) * 2021-11-17 2024-01-23 中交天和机械设备制造有限公司 Shield machine and method for improving slag soil of large-boulder sandy pebble stratum by using same

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102733813A (en) * 2012-06-29 2012-10-17 中铁隧道装备制造有限公司 Opened shield sealing device

Also Published As

Publication number Publication date
CN101509381A (en) 2009-08-19

Similar Documents

Publication Publication Date Title
CN101509381B (en) Composite shield structure suitable for complicated stratum construction
CN105736004B (en) Shield is opened a position pressurize panelling construction method with weighing apparatus shield mud air pressure
CN102052079B (en) Method for exchanging tool of shield machine for tunnel construction
CN101967978B (en) Construction method for improving shield soil in composite sand gravel stratum
CN209195416U (en) The compound stratum shield Multiple Combination retaining wall ruggedized construction with pressure that opens a position
CN103061776B (en) Method for repairing TBM (tunnel boring machine) cutter head in intra-tunnel high-pressure environment
CN204002831U (en) A kind of screw machine blowout prevention structure
CN102536250B (en) Construction method for tunnels with karst and gas simultaneously
CN108643929A (en) A kind of compound stratum shield sediment improvement construction system and its construction method
CN110159284A (en) Strand hydraulic reclamation stratum shield machine is ultra-shallow earth-covered, big longitudinal slope originates construction method
CN109763828A (en) Push-bench tunneling construction method
CN108590706A (en) One kind being used for speciality single-track railway tunnel drifter with booms Construction Techniques of Grouting in Heavy Curtain
CN110645005A (en) High-water-rich round gravel stratum earth pressure balance shield rapid tunneling construction method
CN111335910A (en) Method for opening cabin of shield tunneling machine to overhaul and replace cutter
CN112682055B (en) Small-clear-distance parallel tunnel shield tunneling construction method
CN112922616B (en) Method for controlling shield crossing construction
CN110030006B (en) Shield excavation method through water-saturated sand layer and with a large number of boulders in sand layer
CN108222954B (en) Construction method for shield to penetrate through sandstone material backfill area
CN106007639A (en) Preparation method of high-viscosity thixotropic slurry
CN110284893A (en) A kind of underwater shield tunnel ultra high water pressure condition driving cutter replacing method
CN113323680B (en) Disposal method for long-time shutdown of shield machine in tunneling tunnel
Chen et al. Shield construction techniques in tunneling
CN114352293A (en) Mud film reinforcement construction method for shield cutter changing tunnel face and mud film component
Maid Design features of the Botlek rail tunnel in the Betuweroute
CN113818889B (en) Construction method for crossing underground shield tunnel through civil air defense roadway

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: CHINA RAILWAY MANUFACTURING EQUIPMENT GROUP CO., L

Effective date: 20140313

C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20140313

Address after: 471009 No. 3 Cemetery Road East, Henan, Luoyang

Patentee after: Zhongtie Tunnel Group Co., Ltd.

Patentee after: China Railway Manufacturing Equipment Group Co., Ltd.

Address before: 471009 No. 3 Cemetery Road East, Henan, Luoyang

Patentee before: Zhongtie Tunnel Group Co., Ltd.