CN108643929A - A kind of compound stratum shield sediment improvement construction system and its construction method - Google Patents

A kind of compound stratum shield sediment improvement construction system and its construction method Download PDF

Info

Publication number
CN108643929A
CN108643929A CN201810422054.5A CN201810422054A CN108643929A CN 108643929 A CN108643929 A CN 108643929A CN 201810422054 A CN201810422054 A CN 201810422054A CN 108643929 A CN108643929 A CN 108643929A
Authority
CN
China
Prior art keywords
bentonite
foam
shield
sediment improvement
compound stratum
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810422054.5A
Other languages
Chinese (zh)
Inventor
李宏飞
张隽
赵香萍
赵峰峰
李晓
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 12th Bureau Group Co Ltd
Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
Original Assignee
China Railway 12th Bureau Group Co Ltd
Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 12th Bureau Group Co Ltd, Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd filed Critical China Railway 12th Bureau Group Co Ltd
Priority to CN201810422054.5A priority Critical patent/CN108643929A/en
Publication of CN108643929A publication Critical patent/CN108643929A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • E21D9/08Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining with additional boring or cutting means other than the conventional cutting edge of the shield
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • E21D9/0642Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining the shield having means for additional processing at the front end
    • E21D9/0678Adding additives, e.g. chemical compositions, to the slurry or the cuttings

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • General Chemical & Material Sciences (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The present invention relates to technical field of building construction, more specifically, it is related to a kind of compound stratum shield sediment improvement construction system and its construction method, the system includes bentonite system and foam injection systems, further include Tu Cang displacement knife-changing systems, Tu Cang displacement knife-changing systems are combined with bentonite system and foam injection systems, injection foam solution and after bentonite slurry is stirred, replacement cutter can be carried out, replacing construction is reduced, effectively demonstrate,proves driving speed;And using foaming agent and P1 polymer and flyash is mixed, stream plasticity, consistency, lower water penetration and the smaller frictional resistance for so that the dregs that shield is cut has been had.

Description

A kind of compound stratum shield sediment improvement construction system and its construction method
Technical field
The present invention relates to technical field of building construction, more specifically, are related to a kind of compound stratum shield sediment improvement and apply Work system and its construction method.
Background technology
Sediment improvement is exactly the dedicated unit that is configured by shield to cutterhead face, is injected in native storehouse or in screw conveyor The additives such as water, foam, bentonite, high molecular polymer utilize the Stirring of cutterhead, native storehouse agitating device or spiral transferring Send machine selection stirring that additive is made to be mixed with soil slag, make stream plasticity, suitable consistency that the dregs that shield is cut had, Lower water penetration and smaller frictional resistance.Sediment improvement is to ensure the safe and smooth quick important means of shield-tunneling construction, is had The impermeabilisation ability for improving dregs in native storehouse, avoids excavation face from causing larger ground settlement because of discharging consolidation or thing of caving in Therefore prevented also from or mitigate screw conveyor casting when spewing phenomenon;The workability for improving dregs in native storehouse reduces in native storehouse Dregs and the cohesion for excavating the soil body, and make dregs that there is preferable earth pressure balance effect.
Compound stratum refer to by within the scope of excavated section and excavate extending direction on, by two or more Different Strata Composition, and the bottom combination that the features such as the rock-soil mechanics on these stratum, engineering geology and hydrogeology differ greatly.It is generally divided into Three categories:One kind is the combination of the Different Strata in the vertical direction of end face;One kind is the various combination of bottom in the horizontal direction; One kind is that above-mentioned the two haves both at the same time.Compound stratum shield-tunneling construction needs often transformation shield-tunneling construction pattern, in addition shield machine Configuration is also required to make adjustment appropriate, needs constantly to adjust cutterhead aperture opening ratio, for special compound stratum, it is also necessary to carry out Some auxiliary methods, especially " upper soft lower hard " stratum, which has the following aspects:(1)It greatly reduces Driving speed causes construction delay;(2)The damage for easily causing shield cutter, cutterhead causes long-time shutdown to handle, expense It is high, and it is susceptible to security risk;(3)It is be easy to cause ground cave-in accident, it is dangerous high.Therefore, it is a kind of that there is an urgent need for designs It is various to solve the problems, such as that " upper soft lower hard " chronostratigraphic zone comes with synthesis for new technical solution.
Invention content
In the presence of overcoming the shortcomings of the prior art, the present invention provides a kind of compound stratum shield sediment improvement construction System and its construction method, solve that driving speed existing in the prior art is full, shield cutter damage is serious and leads to ground Cave-in accident problem.
In order to solve the above-mentioned technical problem, the technical solution adopted in the present invention is:
A kind of compound stratum shield sediment improvement construction system, including bentonite system and foam injection systems, further include Tu Cang Knife-changing system is replaced, the bentonite system includes bentonite stirring system and bentonite injected system;The bentonite stirring System is connected by pipeline with the bentonite storage tank of shield machine;The bentonite injected system include bentonite agitator tank and Bentonite fermentation tank, the bentonite agitator tank are connected by grout outlet with bentonite fermentation tank, the bentonite storage tank It is connected between bentonite fermentation tank and slurry is sent to manage;The foam injection systems include foam pump and foam generating system, described Foam pump coordinates the foam generating system to use, and the foam solution that foam generating system generates is injected in front of the cutterhead In face and native storehouse;The Tu Cang displacements knife-changing system includes shield tail synchronous grouting system, cuts device and particle loaded fluid injection Device fills in the particle loaded fluid injection device and sets particle loaded fluid, the particle loaded fluid by shield tail synchronous grouting system in native storehouse into Row filling.
Further, the foam solution includes foaming agent, P1 polymer and water, above-mentioned foaming agent, P1 polymer and water Volume ratio is 3:5:92.
The injection rate of the foam solution is that amount and dregs inject 350~500L foam solutions per square excavation side.
Install bentonite slurry in bentonite storage tank, the bentonite slurry include water, bentonite, mixing flyash and Additive, the water:Bentonite:Mix flyash:The weight ratio of additive is 3.5:0.8:1.2:0.05;The weight of cement mortar Amount is than being cement:Bentonite:Mix flyash:Sand=5:12:18:66.
Further, the mixing flyash includes level-one flyash and second class powered coal ash, wherein level-one flyash and two level The weight ratio of flyash is 4:6.
A kind of construction method of compound stratum shield sediment improvement construction system, includes the following steps:
S1, foam solution, bentonite slurry and cement mortar are made;
S2, foam solution, bentonite slurry and cement mortar are transported to shield machine;
It replaces in S3, native storehouse, using shield tail synchronous grouting system to carrying out filling particle loaded fluid in native storehouse, and is let out by top ball valve Water;
S4, pre-grouting carry out stratum consolidation, by the pre-grouting hole in front of shield machine, are carried out using secondary injection pulp grinder advanced Slip casting selects 1 point and 11 points of pre-grouting hole to carry out slip casting;
S5, it Dewatering well, draws water, when ground is had ready conditions, face water pressure is reduced in cutterhead men working dewatering well;
S6, the cleaning that opens a position, tool changing are drawn water situation according to dewatering well, are checked first Tu Cang before opening a position, and open on native bulkhead Two ball valves, pounded into native storehouse using reinforcing bar into according to the case where judging to solidify into situation is pounded, if slurries become moulding shape and nothing Water flows out, then carries out the work that opens a position;
S7, broken rock are abolished hard soil layer rock, the cutter more renewed after abolishing in advance;
S8, restore to promote, the air pressure of 1.5bar will be established in native storehouse, promoted again later.
Injecting paste material is prefabricated steel floral tube in above-mentioned S4, uses triangle cloth hole on the steel floral tube, aperture 6mm, Spacing between each hole is 8cm;The mixture of filling concrete mortar and cement-sodium silicate double liquid in the steel floral tube, wherein Cement mortar and the weight ratio of cement-sodium silicate double liquid are 6:4.
It needs to check soil body situation in storehouse after opening a position in above-mentioned S6, multiple using drill rod punching, whether there is or not spewing phenomenons for observation, if No spewing phenomenon and face situation are stablized, then directly carry out manual cleaning to the soil body in native storehouse, cleaning sequence for from left to right, From top to bottom.
Compared with prior art, the advantageous effect of present invention is that:
A kind of compound stratum shield sediment improvement construction system of present invention offer and its construction method, knife-changing system is replaced by Tu Cang Combine with bentonite system and foam injection systems, driving speed can be effectively improved, to carrying out pre-treatment in native storehouse so that Tool changing operation is simple and efficient, and can quickly carry out blade exchange;And using mixing flyash, can effectively improve cement mortar and The using effect of bentonite slurry;Meanwhile foam solution is used using foaming agent and P1 mixed with polymers so that unearthed effect obtains To significantly improving.The construction method of compound stratum shield sediment improvement construction system of the present invention, it is simple and practicable, it is easy for construction, Soil cabin displacement knife-changing system is added on the basis of water-rich sand layer shield sediment improvement system, is improved driving speed, is ensured driving Quality, and preferably shield cutter and cutterhead can be protected, reduce maintenance cost.
Description of the drawings
Fig. 1 is that compound stratum shield of the present invention improves construction flow chart;
Fig. 2 is the structural schematic diagram of steel floral tube of the present invention.
Specific implementation mode
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation describes, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other Embodiment shall fall within the protection scope of the present invention.
As shown in Figure 1, a kind of compound stratum shield sediment improvement construction system, including bentonite system and foam injection system System further includes Tu Cang displacement knife-changing systems, and the bentonite system includes bentonite stirring system and bentonite injected system;Institute Bentonite stirring system is stated by pipeline to be connected with the bentonite storage tank of shield machine;The bentonite injected system includes swollen The native agitator tank of profit and bentonite fermentation tank, the bentonite agitator tank is connected by grout outlet with bentonite fermentation tank, described It is connected between bentonite storage tank and bentonite fermentation tank and slurry is sent to manage;The foam injection systems include foam pump and foam hair Raw system, the foam pump coordinate the foam generating system to use, and the foam solution that foam generating system is generated injects institute It states in the face and native storehouse in front of cutterhead;The Tu Cang displacements knife-changing system includes shield tail synchronous grouting system, cuts device It with particle loaded fluid injection device, fills in the particle loaded fluid injection device and sets cement mortar, the cement mortar passes through shield tail and synchronizes note Slurry system in native storehouse to filling.
Foam solution includes foaming agent, P1 polymer and water, and the volume ratio of above-mentioned foaming agent, P1 polymer and water is 3:5: 92;The injection rate of the foam solution is that amount and dregs inject 350~500L foam solutions per square excavation side;By foaming agent and P1 mixed with polymers uses, and using the excellent greasy property of foam, can effectively reduce cutter head torque, improve driving speed, separately The outer compressibility having using foam itself also has positive effect to the stabilization of soil pressure.
Install bentonite slurry in bentonite storage tank, the bentonite slurry include water, bentonite, mixing flyash and Additive, the water:Bentonite:Mix flyash:The weight ratio of additive is 3.5:0.8:1.2:0.05;The weight of cement mortar Amount is than being cement:Bentonite:Mix flyash:Sand=5:12:18:66;The water of bentonite slurry, bentonite, mixing in the present invention The weight ratio of flyash and additive and the difference used usually, because of the use of mixing flyash so that various dosages subtract It is few, it can but reach good improved effect, in addition can reduce the use of bentonite and additive, reduce cost.
It includes level-one flyash and second class powered coal ash, the wherein weight of level-one flyash and second class powered coal ash to mix flyash Than being 4:6;Level-one flyash is used in combination with second class powered coal ash, finer level-one flyash is deep into mixed liquor, Second class powered coal ash is used for and various composition mixing, and two-layer effect is using more obvious, after being bentonite slurry and cement mortar The continuous basis firm using offer.
The construction method of the specific compound stratum shield sediment improvement construction system includes the following steps:
(1)Make foam solution, bentonite slurry and cement mortar;
(2)Foam solution, bentonite slurry and cement mortar are transported to shield machine;
(3)It replaces in native storehouse, using shield tail synchronous grouting system to carrying out filling particle loaded fluid in native storehouse, and is let out by top ball valve Water;
(4)Pre-grouting carries out stratum consolidation, by the pre-grouting hole in front of shield machine, is carried out using secondary injection pulp grinder advanced Slip casting selects 1 point and 11 points of pre-grouting hole to carry out slip casting;Risk can effectively be reduced using pre-grouting, carried out soft Hard special formation preparation of construction down;
(5)Dewatering well draws water, and when ground is had ready conditions, face water pressure is reduced in cutterhead men working dewatering well;
(6)Open a position cleaning, tool changing, is drawn water situation according to dewatering well, is checked first Tu Cang before opening a position, and opens on native bulkhead Two ball valves, using the reinforcing bar of thickness 10mm pounded into native storehouse into, according to pound into situation judge solidify the case where, if slurries become For modeling shape and anhydrous outflow, then the work that opens a position is carried out;
(7)Broken rock is abolished hard soil layer rock, the cutter more renewed after abolishing in advance;
(8)Restore to promote, the air pressure of 1.5bar will be established in native storehouse, promoted again later.
Above-mentioned steps(4)Middle injecting paste material is prefabricated steel floral tube, as shown in Fig. 2, using triangle on the steel floral tube Cloth hole, aperture 6mm, the spacing between each hole are 8cm;Fill slurries in the steel floral tube, the slurries be cement mortar and The weight ratio of the mixture of cement-sodium silicate double liquid, wherein cement mortar and cement-sodium silicate double liquid is 6:4;It will be prefabricated Steel floral tube squeeze into pre-grouting hole carry out slip casting, first cement injection, grouting pressure control in 0.3~0.4Mpa, pressure stability Slip casting is persistently carried out afterwards, until after pressure rises, then 35min is noted, finally note dual slurry sealing of hole.
Specific implementation method, above-mentioned steps(6)The middle native door first opened in people's lock, observes soil body situation in storehouse, uses Drill rod punching is multiple, and whether there is or not spewing phenomenons for observation, if without spewing phenomenon and face situation stabilization, directly to the soil body in native storehouse Manual cleaning is carried out, cleaning sequence is from left to right, from top to bottom.It brings down stocks, using device is cut, to cut device and such as raise pick, iron Spade is manually sent to belt feeder, then be sent to slag-soil truck by belt feeder using knitting bagged soil, during bringing down stocks, retains cutterhead opening And cement at notch ring, the soil body at cutterhead opening and notch ring is not disturbed as possible, if chisel is crossed in some areas during cutting. It is blocked immediately with quick-hardening cement, when being cleaned to the ball valve of 9 points, the soil body around ball valve is cleaned out, exhaust fan is connect To the outside of ball valve, the ventilation in native storehouse is carried out.According to circumstances, it clears up to be blocked to face weak spot, protects on one side It demonstrate,proves face to stablize, if water exudation is arranged at bottom during bringing down stocks, uses pumping for water pump in time.During bringing down stocks, so as to It cuts to carry out demolition and replacement to cutter, for being difficult to the cutter installed, first removes, wait for rotating knife after the completion of Tu Cang cleanings Disk is replaced.
The present invention is applied to upper soft lower hard composite bottom layer shield machine and uses balancing earth-pressure shielding machine, and shield machine is in pre-large post-small Taper structure design, it is ensured that in the advance ability of each tool wear condition shield machine of certain cutter head;And shield Machine takes half storehouse gas pressure pattern to promote when passing through upper soft lower hardcore, keeps under-voltage, at the uniform velocity, continuously promotes, strictly to control Railway and municipal pipeline safety are protected in surface subsidence.
Only presently preferred embodiments of the present invention is explained in detail above, but the present invention is not limited to above-described embodiment, Within the knowledge of a person skilled in the art, it can also make without departing from the purpose of the present invention each Kind variation, various change should all be included in the protection scope of the present invention.

Claims (9)

1. a kind of compound stratum shield sediment improvement construction system, it is characterised in that:Including bentonite system, foam injection systems Knife-changing system is replaced with Tu Cang, the bentonite system includes bentonite stirring system and bentonite injected system;The swelling Native stirring system is connected by pipeline with the bentonite storage tank of shield machine;The bentonite injected system includes that bentonite stirs Tank and bentonite fermentation tank are mixed, the bentonite agitator tank is connected by grout outlet with bentonite fermentation tank, the bentonite It is connected between storage tank and bentonite fermentation tank and slurry is sent to manage;The foam injection systems include foam pump and foam system System, the foam pump coordinate the foam generating system to use, and the foam solution that foam generating system is generated injects the knife In face and native storehouse in front of disk;The Tu Cang displacements knife-changing system includes shield tail synchronous grouting system, cuts device and sand Slurries injection device fills in the particle loaded fluid injection device and sets particle loaded fluid, and the particle loaded fluid passes through shield tail synchronous grouting system pair It is filled in native storehouse.
2. compound stratum shield sediment improvement construction system according to claim 1, it is characterised in that:The foam solution Including foaming agent, P1 polymer and water, the volume ratio of foaming agent, P1 polymer and water is 3:5:92.
3. compound stratum shield sediment improvement construction system according to claim 1, it is characterised in that:The foam solution Injection rate be per square excavation side amount and dregs inject 350~500L foam solutions.
4. compound stratum shield sediment improvement construction system according to claim 1, it is characterised in that:The bentonite is deposited Bentonite slurry is installed in storage tank, the bentonite slurry includes water, bentonite, mixing flyash and additive, the water:It is swollen Profit soil:Mix flyash:The weight ratio of additive is 3.5:0.8:1.2:0.05.
5. compound stratum shield sediment improvement construction system according to claim 4, it is characterised in that:The mixing fine coal Ash includes level-one flyash and second class powered coal ash, and the wherein weight ratio of level-one flyash and second class powered coal ash is 4:6.
6. compound stratum shield sediment improvement construction system according to claim 1, it is characterised in that:The particle loaded fluid is The weight ratio of the mixture of cement mortar and cement-sodium silicate double liquid, the cement mortar is cement:Bentonite:Mixed powder Coal ash:Sand=5:12:18:66.
7. a kind of construction method of compound stratum shield sediment improvement construction system, it is characterised in that:Include the following steps:
S1, foam solution, bentonite slurry and cement mortar are made;
S2, by foam solution, bentonite slurry and cement mortar transport to shield machine;
It replaces in S3, native storehouse, using shield tail synchronous grouting system to carrying out particle loaded fluid in native storehouse, and is sluiced by top ball valve;
S4, pre-grouting carry out stratum consolidation, by the pre-grouting hole in front of shield machine, are carried out using secondary injection pulp grinder advanced Slip casting selects 1 point and 11 points of pre-grouting hole to carry out slip casting;
S5, it Dewatering well, draws water, when ground is had ready conditions, face water pressure is reduced in cutterhead men working dewatering well;
S6, the cleaning that opens a position, tool changing are drawn water situation according to dewatering well, are checked first Tu Cang before opening a position, and open on native bulkhead Two ball valves, pounded into native storehouse using reinforcing bar into according to the case where judging to solidify into situation is pounded, if slurries become moulding shape and nothing Water flows out, then carries out the work that opens a position;
S7, broken rock are abolished hard soil layer rock, the cutter more renewed after abolishing in advance;
S8, restore to promote, the air pressure of 1.5bar will be established in native storehouse, promoted again later.
8. the construction method of compound stratum shield sediment improvement construction system according to claim 7, it is characterised in that:S4 Middle injecting paste material is prefabricated steel floral tube, uses triangle cloth hole on the steel floral tube, aperture 6mm, the spacing between each hole For 8cm;The mixture of filling concrete mortar and cement-sodium silicate double liquid in the steel floral tube, wherein cement mortar and cement- The weight ratio of waterglass dual slurry is 6:4.
9. the construction method of compound stratum shield sediment improvement construction system according to claim 7, it is characterised in that:S6 In open a position after need check storehouse in soil body situation, using drill rod punch it is multiple, observation whether there is or not spewing phenomenons, if without spewing phenomenon and the palm Sub- face situation is stablized, then directly carries out manual cleaning to the soil body in native storehouse, and cleaning sequence is from left to right, from top to bottom.
CN201810422054.5A 2018-05-04 2018-05-04 A kind of compound stratum shield sediment improvement construction system and its construction method Pending CN108643929A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810422054.5A CN108643929A (en) 2018-05-04 2018-05-04 A kind of compound stratum shield sediment improvement construction system and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810422054.5A CN108643929A (en) 2018-05-04 2018-05-04 A kind of compound stratum shield sediment improvement construction system and its construction method

Publications (1)

Publication Number Publication Date
CN108643929A true CN108643929A (en) 2018-10-12

Family

ID=63749464

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810422054.5A Pending CN108643929A (en) 2018-05-04 2018-05-04 A kind of compound stratum shield sediment improvement construction system and its construction method

Country Status (1)

Country Link
CN (1) CN108643929A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109611113A (en) * 2019-01-09 2019-04-12 康明克斯(北京)环保技术有限公司 A kind of earth pressure balanced shield, EPBS dregs continuous conveying equipment
CN110566211A (en) * 2019-09-04 2019-12-13 中交一公局第三工程有限公司 Earth pressure shield muck flow plasticity improvement method suitable for sandy gravel stratum
CN111022064A (en) * 2020-01-01 2020-04-17 中铁四局集团有限公司 Mud sinking prevention and grouting slurry for shield construction
CN112282774A (en) * 2020-09-16 2021-01-29 中铁十九局集团轨道交通工程有限公司 Shield notch slurry suitable for sandy water-rich stratum
CN113503177A (en) * 2021-08-25 2021-10-15 中铁十七局集团有限公司 In-hole treatment method for liquefiable stratum shield tunnel
CN113847047A (en) * 2021-09-17 2021-12-28 中铁二十局集团有限公司 Warehouse opening tool changing method
CN115901303A (en) * 2022-11-14 2023-04-04 中国水利水电第三工程局有限公司 Soil pressure balance shield that can simulate improver injection prevents gushing test device

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102052079A (en) * 2010-11-19 2011-05-11 中铁一局集团有限公司 Method for exchanging tool of shield machine for tunnel construction
CN105545314A (en) * 2015-12-24 2016-05-04 中铁二十二局集团第一工程有限公司 Construction system and construction method for improving water-enriched sand layer shield waste soil
CN105927236A (en) * 2016-06-03 2016-09-07 粤水电轨道交通建设有限公司 Grouting bin filling tool changing method for tunnel shield construction machine
CN106761782A (en) * 2016-12-30 2017-05-31 中铁二局集团有限公司 A kind of tunneling construction method for wearing operation tunnel under shield in rich water powder land floor
JP2018062760A (en) * 2016-10-12 2018-04-19 花王株式会社 Foam shield construction method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102052079A (en) * 2010-11-19 2011-05-11 中铁一局集团有限公司 Method for exchanging tool of shield machine for tunnel construction
CN105545314A (en) * 2015-12-24 2016-05-04 中铁二十二局集团第一工程有限公司 Construction system and construction method for improving water-enriched sand layer shield waste soil
CN105927236A (en) * 2016-06-03 2016-09-07 粤水电轨道交通建设有限公司 Grouting bin filling tool changing method for tunnel shield construction machine
JP2018062760A (en) * 2016-10-12 2018-04-19 花王株式会社 Foam shield construction method
CN106761782A (en) * 2016-12-30 2017-05-31 中铁二局集团有限公司 A kind of tunneling construction method for wearing operation tunnel under shield in rich water powder land floor

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
工程资料下载: "复合地层盾构施工技术", 《豆丁网豆丁建筑》 *

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109611113A (en) * 2019-01-09 2019-04-12 康明克斯(北京)环保技术有限公司 A kind of earth pressure balanced shield, EPBS dregs continuous conveying equipment
CN110566211A (en) * 2019-09-04 2019-12-13 中交一公局第三工程有限公司 Earth pressure shield muck flow plasticity improvement method suitable for sandy gravel stratum
CN110566211B (en) * 2019-09-04 2020-11-24 中交一公局第三工程有限公司 Earth pressure shield muck flow plasticity improvement method suitable for sandy gravel stratum
CN111022064A (en) * 2020-01-01 2020-04-17 中铁四局集团有限公司 Mud sinking prevention and grouting slurry for shield construction
CN112282774A (en) * 2020-09-16 2021-01-29 中铁十九局集团轨道交通工程有限公司 Shield notch slurry suitable for sandy water-rich stratum
CN113503177A (en) * 2021-08-25 2021-10-15 中铁十七局集团有限公司 In-hole treatment method for liquefiable stratum shield tunnel
CN113847047A (en) * 2021-09-17 2021-12-28 中铁二十局集团有限公司 Warehouse opening tool changing method
CN115901303A (en) * 2022-11-14 2023-04-04 中国水利水电第三工程局有限公司 Soil pressure balance shield that can simulate improver injection prevents gushing test device
CN115901303B (en) * 2022-11-14 2023-09-19 中国水利水电第三工程局有限公司 Soil pressure balance shield blowout prevention test device capable of simulating modifier injection

Similar Documents

Publication Publication Date Title
CN108643929A (en) A kind of compound stratum shield sediment improvement construction system and its construction method
CN102052079B (en) Method for exchanging tool of shield machine for tunnel construction
CN100591866C (en) Drifting sand layer and gravel stratum water-moving double-liquid high pressure slip-casting water-blocking construction method
CN101509381B (en) Composite shield structure suitable for complicated stratum construction
CN104265307B (en) Non-uniform-hardness stratum earth pressure balance shield tunnel underpassing railway existing line construction method
CN105927236B (en) A kind of tunnel shield machine slip casting is filled in barn cutter replacing method
CN101967978B (en) Construction method for improving shield soil in composite sand gravel stratum
CN105736004A (en) Balanced shield mud air-pressure cabin opening pressure maintaining and wall protecting construction method for shield tunneling
CN209195416U (en) The compound stratum shield Multiple Combination retaining wall ruggedized construction with pressure that opens a position
CN103485336A (en) Drilling pile drilling construction method of bead-type karst area
CN107842374B (en) The novel inert slurry of shield and combination grouting process for upper soft lower hard water rich strata
CN105257308B (en) Native storehouse mortar mixes the shield machine tool changing construction method of bentonite mud film in a kind of layer of sand
CN105484269B (en) Foundation pit enclosure structure seepage prevention and treatment construction method under blasting condition
KR101421173B1 (en) Drill Stirrer for the Hard Soil Layers
Li et al. Creating a working space for modifying and maintaining the cutterhead of a large-diameter slurry shield: A case study of Beijing railway tunnel construction
CN102337732A (en) Seawall construction method with top pipes penetrating through block stone
CN104594912A (en) Method for grinding and penetrating through pile groups through shield tunneling machine
CN105221157B (en) WSS grouting and reinforcings assist gas pressure cutter replacing method in shield tunnel
CN106437796B (en) A kind of lithostratigraphy shield tunnel end ruggedized construction and reinforcement means
CN112682055B (en) Small-clear-distance parallel tunnel shield tunneling construction method
KR20100122068A (en) Grouting method using enlarged concrete consolidation grouting apparatus
CN108868796A (en) For wearing skyscraper group construction method under the shield sharp radius curve and heavy grade under water-rich sand layer
CN106007639A (en) Preparation method of high-viscosity thixotropic slurry
CN104631479B (en) The construction method of the water-stop curtain of soil removal and replacement stirring
JP2020139320A (en) Shield excavator and shield construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20181012

RJ01 Rejection of invention patent application after publication