CN101476331B - 地下室基坑砼内支撑封闭爆破拆除方法 - Google Patents

地下室基坑砼内支撑封闭爆破拆除方法 Download PDF

Info

Publication number
CN101476331B
CN101476331B CN2007101721341A CN200710172134A CN101476331B CN 101476331 B CN101476331 B CN 101476331B CN 2007101721341 A CN2007101721341 A CN 2007101721341A CN 200710172134 A CN200710172134 A CN 200710172134A CN 101476331 B CN101476331 B CN 101476331B
Authority
CN
China
Prior art keywords
basement
concrete
support
closed
foundation pit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2007101721341A
Other languages
English (en)
Other versions
CN101476331A (zh
Inventor
胡开彪
尹亚鸿
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC20 Group Corp Ltd
Original Assignee
China MCC20 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC20 Group Corp Ltd filed Critical China MCC20 Group Corp Ltd
Priority to CN2007101721341A priority Critical patent/CN101476331B/zh
Publication of CN101476331A publication Critical patent/CN101476331A/zh
Application granted granted Critical
Publication of CN101476331B publication Critical patent/CN101476331B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Working Measures On Existing Buildindgs (AREA)

Abstract

本发明涉及地下室施工,尤其涉及一种地下室基坑砼内支撑拆除方法。一种地下室基坑砼内支撑封闭爆破拆除方法,所述地下室基坑采用排桩与板墙式及砼内支撑基坑支护体系,所述拆除方法主要包括下列步骤:结构换撑步骤,利用地下室回填及传力带完成结构换撑;拆除部分基坑支护砼内支撑步骤;传力带以上部分地下室结构施工步骤;封闭式爆破拆除砼内支撑步骤。本发明地下室基坑砼内支撑封闭爆破拆除方法缩短了施工工期、保证了安全。

Description

地下室基坑砼内支撑封闭爆破拆除方法
技术领域
本发明涉及地下室施工,尤其涉及一种地下室基坑砼内支撑拆除方法。
背景技术
在软土地区进行地下室施工时,排桩与板墙式加砼内支撑基坑支护体系应用较多。砼内支撑为临时结构,当地下室结构施工到一定阶段时,其需要拆除。常规施工时的施工顺序为:施工完砼内支撑下部地下室结构并换撑完毕后,大面积敞开拆除砼内支撑,再进入后续的地下室结构施工。常规施工方法的弊端为:①、先大面积拆除砼内支撑后,才能进行后续的地下室结构施工,工序多、时间长的大面积敞开拆除砼内支撑,会影响到地下室结构施工进度。②、大面积敞开爆破除砼内支撑,安全隐患多,需要做细致的安全警戒工作,告知附近居民,并搭设防护棚,防止爆破飞石破坏四周建筑物,伤害行人。而砼内支撑封闭爆破法则不影响到地下室结构施工进度,并相对常规施工方法安全。
发明内容
本发明旨在解决所述传统的支撑拆除方法的缺陷,提供一种地下室基坑砼内支撑封闭爆破拆除方法。本发明地下室基坑砼内支撑封闭爆破拆除方法缩短了施工工期、保证了安全。
本发明是这样实现的:
一种地下室基坑砼内支撑封闭爆破拆除方法,所述地下室基坑采用排桩与板墙式及砼内支撑基坑支护体系,所述拆除方法主要包括下列步骤:
结构换撑步骤,利用地下室回填及传力带完成结构换撑;
拆除部分基坑支护砼内支撑步骤;
传力带以上部分地下室结构施工步骤;
封闭式爆破拆除砼内支撑步骤。
所述的地下室基坑砼内支撑封闭爆破拆除方法,所述拆除方法在结构换撑步骤之前还包括找出需处理的重叠部位并调整内支撑梁的位置步骤。
所述的地下室基坑砼内支撑封闭爆破拆除方法,所述拆除部分基坑支护砼内支撑步骤包括:
通长搭设临时支架步骤;
凿除支撑梁步骤,按照先凿除上排钢筋保护层砼,再电焊截断上排主筋,后凿除钢筋内砼,最后电焊截断下排主筋的顺序进行操作。
所述的地下室基坑砼内支撑封闭爆破拆除方法,所述封闭式爆破拆除砼内支撑步骤包括:
双层钢管防护搭设步骤;
在需爆破的内支撑梁上用覆盖物整体覆盖步骤;
在爆破的内支撑梁侧面及顶部搭设双排钢管防护架步骤;
全封闭防护层构建步骤,在架子上敷设竹篱笆,竹篱笆之间搭接不小于10cm,用铁丝箍紧。
所述的地下室基坑砼内支撑封闭爆破拆除方法,所述双排钢管防护架离待爆支撑梁2m以上。
本发明地下室基坑支护砼内支撑爆破法不影响地下室结构的施工,可缩短地下室的施工工期;在地下室结构施工完后,在地下室内封闭爆破基坑支护砼内支撑,比较安全。爆破噪音小,不会引起周围居民的恐慌和不适。
附图说明
下面,结合具体实施方式对本发明作进一步的说明;
图1为本发明示意图。
具体实施方式
请参考图1,一种地下室基坑砼内支撑封闭爆破拆除方法,所述地下室3基坑采用排桩与板墙1式及砼内支撑2基坑支护体系,图中5为支撑立柱,所述拆除方法为:
首先熟悉基坑支护和结构图纸,整理基坑支护内支撑与结构柱墙的关系,找出需处理的重叠部位。如支撑过多与内部独立柱重叠,宜在早期沟通支护设计单位,在不影响基坑支护安全性的前提下,适当调整内支撑梁的位置。
(1)、利用地下室回填及传力带完成结构换撑。
换撑需开挖土体至底板下基坑底面后,在地下室底板与围护体之间周边设置素混凝土板式传力带,传力带的面、底标高与地下室底板标高相同,传力带在地下室底板混凝土浇捣时同时进行施工。
接着施工地下室二层的墙和顶板结构,地下室二层侧墙外侧回填碎石混合料,但在地下室二层顶板大梁、板面以下1米左右的位置与围护体之间周边用素混凝土浇筑,浇筑厚度1.1~1.2米。地下室二层侧墙外侧回填时应严格控制含泥量,回填料含泥量应控制在3%~5%。碎石混合料合理级配既可避免压实后颗粒间缺少砂粒充填而形成的架空结构,也保证了砂粉细粒间有足够大颗粒以形成骨架,满足强度要求。
待传力所浇的混凝土达到足够强度(85%)后,才能开始人工拆除部分基坑支护砼内支撑。
(2)、人工拆除部分基坑支护砼内支撑,避让地下室结构外墙。
人工凿除支撑需搭设临时支架,临时支架需通长搭设,避免人工凿除后悬臂支撑梁断落,压损楼板。
人工风镐凿除支撑梁4,按照先凿除上排钢筋保护层砼,再电焊截断上排主筋,后凿除钢筋内砼,最后电焊截断下排主筋的顺序进行操作。
(3)、传力带以上部分地下室结构施工。
(4)、爆破参数设计,在地下室内实施封闭式爆破拆除砼支撑。
在实施地下室全封闭砼内支撑控制微爆前需搭设双层钢管防护。在需爆破的内支撑梁上用废旧麻袋整体覆盖,麻袋之间重叠搭接不少于10cm。在爆破的内支撑梁侧面及顶部搭设双排钢管防护架,并在架子上敷设竹芭,竹芭之间搭接不小于10cm,用铁丝箍紧,形成全封闭防护层。防护架应离待爆支撑梁2m以上。

Claims (4)

1.一种地下室基坑砼内支撑封闭爆破拆除方法,所述地下室基坑采用排桩与板墙式及砼内支撑基坑支护体系,其特征在于,所述拆除方法主要包括下列步骤:
一,找出基坑支护内支撑与结构柱墙的需处理的重叠部位并调整内支撑梁的位置步骤;
结构换撑步骤,利用地下室回填及传力带完成结构换撑;
二,人工拆除部分基坑支护砼内支撑步骤;
三,传力带以上部分地下室结构施工步骤;
四,封闭式爆破拆除砼内支撑步骤。
2.根据权利要求1所述的地下室基坑砼内支撑封闭爆破拆除方法,其特征在于,所述二,人工拆除部分基坑支护砼内支撑步骤包括:
通长搭设临时支架步骤和凿除支撑梁步骤,按照先凿除上排钢筋保护层砼,再电焊截断上排主筋,后凿除钢筋内砼,最后电焊截断下排主筋的顺序进行操作。
3.根据权利要求1所述的地下室基坑砼内支撑封闭爆破拆除方法,其特征在于,所述四,封闭式爆破拆除砼内支撑步骤包括:
双层钢管防护搭设步骤;
在需爆破的内支撑梁上用覆盖物整体覆盖步骤;
在爆破的内支撑梁侧面及顶部搭设双排钢管防护架步骤;
全封闭防护层构建步骤,在架子上敷设竹芭,竹芭之间搭接不小于10cm,用铁丝箍紧。
4.根据权利要求3所述的地下室基坑砼内支撑封闭爆破拆除方法,其特征在于,所述双排钢管防护架离待爆内支撑梁2m以上。
CN2007101721341A 2007-12-12 2007-12-12 地下室基坑砼内支撑封闭爆破拆除方法 Expired - Fee Related CN101476331B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2007101721341A CN101476331B (zh) 2007-12-12 2007-12-12 地下室基坑砼内支撑封闭爆破拆除方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2007101721341A CN101476331B (zh) 2007-12-12 2007-12-12 地下室基坑砼内支撑封闭爆破拆除方法

Publications (2)

Publication Number Publication Date
CN101476331A CN101476331A (zh) 2009-07-08
CN101476331B true CN101476331B (zh) 2012-07-04

Family

ID=40837106

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2007101721341A Expired - Fee Related CN101476331B (zh) 2007-12-12 2007-12-12 地下室基坑砼内支撑封闭爆破拆除方法

Country Status (1)

Country Link
CN (1) CN101476331B (zh)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104404965A (zh) * 2014-11-05 2015-03-11 浙江海洋学院 基坑支护内钢筋混凝土支撑梁拆除方法

Families Citing this family (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102296644B (zh) * 2010-06-28 2016-06-08 上海隧道工程有限公司 基坑内支撑爆破拆除振动安全监测体系和监测方法
CN101886392B (zh) * 2010-06-30 2012-03-21 济南鼎汇土木工程技术有限公司 一种基坑支护体系的拆撑设计与施工方法
CN102116027A (zh) * 2010-12-17 2011-07-06 上海市第四建筑有限公司 框架式组合换撑体系及其施工方法
CN102191776A (zh) * 2011-05-11 2011-09-21 中天建设集团有限公司 一种用型钢托换钢筋混凝土内支撑的结构和它的施工方法
CN102444130B (zh) * 2011-10-20 2014-01-01 中建六局第三建筑工程有限公司 深基坑工程中的快速换撑施工方法
CN103184739A (zh) * 2011-12-29 2013-07-03 五冶集团上海有限公司 一种钢筋混凝土支撑爆破拆除方法
CN102587420B (zh) * 2012-02-13 2014-03-26 中天建设集团有限公司 一种以钻孔灌注桩作分隔围护的分期施工地下室换撑方法
CN102720201B (zh) * 2012-07-02 2014-10-29 中建三局第二建设工程有限责任公司 一种利用建筑物主体结构换撑施工的建造方法
CN104250971A (zh) * 2013-06-26 2014-12-31 中国二十冶集团有限公司 地下室围护支撑体封闭拆除方法
CN104514228A (zh) * 2013-09-29 2015-04-15 浙江宝业建设集团有限公司 大底盘多塔建筑施工方法及结构
CN104895089B (zh) * 2015-04-08 2017-08-29 山东大学 地下室楼板与支护桩共同工作的永久支护体系的施工方法
CN106055801B (zh) * 2016-06-03 2018-12-14 武汉科技大学 一种深基坑支撑梁爆破拆除顺序的确定方法
CN106088098A (zh) * 2016-06-15 2016-11-09 龙元建设集团股份有限公司 支撑拆除施工方法
CN106869110A (zh) * 2016-12-29 2017-06-20 上海市基础工程集团有限公司 既有地下结构的地下连续墙施工方法
CN107761741A (zh) * 2017-10-18 2018-03-06 中铁八局集团建筑工程有限公司 一种人工破除内支撑梁方法
CN109083155B (zh) * 2018-08-28 2024-01-05 中建二局第三建筑工程有限公司 一种基坑内支撑结构及其爆破拆除方法
CN109235926B (zh) * 2018-10-19 2019-10-22 洛阳理工学院 钢筋混凝土框架结构单向倒塌爆破拆除防后座的施工方法
CN110130364A (zh) * 2019-05-28 2019-08-16 中国二十冶集团有限公司 基坑单撑换撑施工方法

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104404965A (zh) * 2014-11-05 2015-03-11 浙江海洋学院 基坑支护内钢筋混凝土支撑梁拆除方法

Also Published As

Publication number Publication date
CN101476331A (zh) 2009-07-08

Similar Documents

Publication Publication Date Title
CN101476331B (zh) 地下室基坑砼内支撑封闭爆破拆除方法
CN106869172A (zh) 现浇预制拼装组合式地铁地下车站施工方法
CN105804089B (zh) 一种原深基坑施工后局部增深支护体系及其施工方法
CN108505805B (zh) 膨胀加强带控裂大型现浇水池及其施工方法
CN206495682U (zh) 一种用于隧道塌方快速处理的台架
CN207647522U (zh) 一种可重复使用的伸缩式临时钢架仰拱结构
CN109629576B (zh) 横穿基坑给水管悬吊保护体系及施工方法
CN206144583U (zh) 一种高地应力隧道支护结构
CN110904867A (zh) 上跨既有线拱桥拆除施工方法
CN201943086U (zh) 一种地下建筑墙体
CN208072415U (zh) 深基坑钢筋混凝土支撑局部拆换结构
CN110985060A (zh) 隧道上部溶洞的防护结构
CN110158656A (zh) 一种一体化模板管廊及其建造方法
CN110952995A (zh) 一种外接式洞门后浇环梁施工方法
CN104032767A (zh) 一种深基坑内塔吊基础及其施工方法
CN109441110A (zh) 一种地下室剪力墙后浇带预制外模施工法
CN112983467A (zh) 隧道关门式大塌方的处治方法
CN105040709A (zh) 一种深基坑围护桩支护换撑的施工方法
CN103452326A (zh) 超长吊柱顺做法施工方法及其设备
CN109930610A (zh) 受限环境基坑采用混凝土加钢管混合斜撑支护的施工方法
CN204919559U (zh) 地裂缝的修复系统
CN203891047U (zh) 搭设钢平台进行陆上桥梁基础施工设备
CN104963344B (zh) 砼支撑拆除和结构施工同步进行的深基坑地下施工方法
CN204282371U (zh) 一种用于基坑的预应力支撑
CN211777473U (zh) 隧道上部溶洞的防护结构

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20120704