CN104032767A - 一种深基坑内塔吊基础及其施工方法 - Google Patents

一种深基坑内塔吊基础及其施工方法 Download PDF

Info

Publication number
CN104032767A
CN104032767A CN201410280801.8A CN201410280801A CN104032767A CN 104032767 A CN104032767 A CN 104032767A CN 201410280801 A CN201410280801 A CN 201410280801A CN 104032767 A CN104032767 A CN 104032767A
Authority
CN
China
Prior art keywords
tower crane
foundation
order
described basic
standard section
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410280801.8A
Other languages
English (en)
Inventor
吕立军
徐宏伟
付奎胜
丁志雄
张怀勇
李景秋
赵珊珊
程明
孙超
姜连伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianjin MCC20 Construction Co Ltd
Original Assignee
Tianjin MCC20 Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianjin MCC20 Construction Co Ltd filed Critical Tianjin MCC20 Construction Co Ltd
Priority to CN201410280801.8A priority Critical patent/CN104032767A/zh
Publication of CN104032767A publication Critical patent/CN104032767A/zh
Pending legal-status Critical Current

Links

Landscapes

  • Foundations (AREA)

Abstract

本发明公开了一种深基坑内塔吊基础及其施工方法,塔吊基础包括由下到上依次连接的基础一阶、基础二阶和预埋件;基础一阶和基础二阶均为钢筋混凝土结构,固定设置于基础垫层上,预埋件由塔吊标准节以中间位置截断制成,埋设于基础二阶中且顶面露出于基础二阶以连接塔吊标准节;该塔吊基础的施工方法为土方开挖后安装基础一阶和基础二阶的模板,然后将预埋件固定安装;最后绑扎基础一阶和基础二阶的钢筋并浇筑混凝土。本发明节省了塔吊底座的使用;避免塔吊拆除时的各种困难,如不必进行土方开挖,不必截断塔身而造成浪费等;在土方回填时也不必砌筑围护结构;结构简单,受力明确,施工方便,适于普遍推广使用。

Description

一种深基坑内塔吊基础及其施工方法
技术领域
本发明涉及一种塔吊基础及其施工方法,具体的说,是涉及受建筑物限制,只能将塔吊布置在大开挖坡面时的一种深基坑内塔吊基础及其施工方法。
背景技术
深基坑工程中,塔吊应用十分广泛。对于有支护结构的工程来说,塔吊基础可布置在基坑上部或是基坑内部;对于无支护结构的工程来说,塔吊基础可以布置在基坑内。但是,由于相邻主体结构或周围建筑物影响,有时综合考虑,将塔吊基础布置在基坑开挖坡面一侧相对合理的情况。然而,布置在开挖坡面上经常引出的问题是:基坑结构工程施工完毕后,回填土前必须将塔吊地下部分进行砌筑围护,然后回填至自然地面高度。但后期地上主体结构施工完毕后,由于现场布置或是地下管网及路面施工完,塔吊基础处不具备大开挖条件,此时不得不将塔吊标准节阶段,地下部分的塔身及基础钢支座等全部浪费。
发明内容
本发明要解决的是现有深基坑工程中,塔吊拆除时造成浪费和施工难度大的技术问题,提供一种深基坑内塔吊基础及其施工方法。
为了解决上述技术问题,本发明通过以下的技术方案予以实现:
一种深基坑内塔吊基础,包括由下到上依次设置的基础一阶、基础二阶和预埋件;
所述基础一阶为钢筋混凝土结构,固定设置于基础垫层上,其截面尺寸为5000×5000mm~6000×6000mm,高度为1200~1500mm;
所述基础二阶为钢筋混凝土结构,固定设置于所述基础一阶上,其截面尺寸为塔吊标准节截面尺寸外扩150~300mm,其顶面标高为自然地面标高至低于自然地面标高1000mm范围内;
所述预埋件由塔吊标准节以中间位置截断制成,截面尺寸与塔吊标准节相同,高度为塔吊标准节高度的1/2;所述预埋件埋设于所述基础二阶中,底部通过固定架固定于基础垫层;所述预埋件顶面露出于所述基础二阶顶面200~500mm,用于通过螺栓连接塔吊标准节。
一种所述深基坑内塔吊基础的施工方法,包括如下步骤:
(1)根据基础垫层标高和自然地面标高,设计所述基础一阶和所述基础二阶的尺寸,并计算校核;
(2)土方开挖;
(3)安装所述基础一阶和所述基础二阶的模板;
(4)将所述预埋件通过固定架固定安装于基础垫层;
(5)绑扎所述基础一阶和所述基础二阶的钢筋;
(6)浇筑所述基础一阶和所述基础二阶的混凝土;
(7)混凝土强度满足要求后,将塔吊标准节安装于所述预埋件顶端。
本发明的有益效果是:
(一)本发明的深基坑内塔吊基础采用基础一阶和基础二阶的结构,并通过预埋件直接连接塔吊标准节,从而节省了塔吊底座(钢十字梁及拉杆)的使用;
(二)本发明在塔吊拆除时,直接将塔吊标准节从预埋件上拆除即可,避免了塔吊拆除时的各种困难,如不必或者很少量的进行土方开挖,不必截断塔身而造成浪费等;
(三)本发明在土方回填时,将塔吊基础一并回填至自然地面或自然地面以下的一段高度即可,不必砌筑围护结构;
(四)本发明的结构简单,受力明确,施工方便,适于普遍推广使用。
附图说明
附图是本发明所提供的深基坑内塔吊基础的结构示意图。
图中:1、自然地面;2、开挖坡面;3、塔吊标准节;4、预埋件;5、基础二阶;6、固定架;7、基础一阶;8、地下主体结构;9、基础垫层。
具体实施方式
为能进一步了解本发明的发明内容、特点及效果,兹例举以下实施例,并配合附图详细说明如下:
如附图所示,本实施例首先公开了一种深基坑内塔吊基础,该塔吊基础由于受到地下主体结构8的影响,需要布置在基坑开挖坡面2一侧相对合理的位置,主要包括由下到上依次设置的基础一阶7、基础二阶5和预埋件4。
基础一阶7为钢筋混凝土结构,浇筑于基础垫层9上。基础一阶7截面尺寸为5000×5000mm,高度为1200mm。基础一阶7截面尺寸通常在5000×5000mm~6000×6000mm范围内,高度通常在1200~1500mm范围内,具体规格尺寸可根据设计方案确定。
基础二阶5同样为钢筋混凝土结构,固定设置于基础一阶7上,与基础一阶7共同浇筑施工。基础二阶5的高度与自然地面1高度相同,其截面尺寸为塔吊标准节3四周尺寸外扩200mm。通常地,基础二阶5的顶面标高可根据实际施工情况,作至自然地面1标高至低于自然地面1标高1000mm范围内,只要满足后期开挖要求即可;而基础二阶5的截面尺寸一般是塔吊标准节3截面尺寸外扩150~300mm。
预埋件4需提前制作,可由塔吊标准节3从中间位置截断制成。因此,预埋件4的截面尺寸与塔吊标准节3相同,高度为塔吊标准节3高度的1/2。预埋件4埋设于基础二阶5中(若基础二阶5高度不够则延伸至基础一阶7内),其底部通过固定架6固定于基础垫层9。固定架6是由角钢或槽钢预制而成的常见结构,具体形式不限,只要能够起到可靠支撑连接的作用即可。预埋件4的顶面露出于基础二阶5顶面300mm,用于通过螺栓连接塔吊标准节3。一般情况下,预埋件4露出基础二阶5顶面200~500mm即可,以满足与上部塔吊标准节3的连接。
采用上述深基坑内塔吊基础,在基坑结构施工完后,土方回填可将塔吊基础一并回填至自然地面1,后期拆除塔吊则直接在自然地面1处操作即可。具体地,上述深基坑内塔吊基础的施工步骤如下:
根据基础垫层9标高和自然地面1标高,设计基础一阶7和基础二阶5的尺寸,并计算校核满足要求后,开始施工;
土方开挖后,安装基础一阶7和基础二阶5的模板;
将提前预制好的预埋件4通过固定架6固定安装于基础垫层9;
绑扎基础一阶7和基础二阶5的钢筋后,浇筑混凝土;
混凝土强度满足要求后,将一个塔吊标准节3通过螺栓固定于预埋件4顶端,并逐节完成上部其他塔吊标准节3的安装,即可正常运作,以供应地下主体结构8工程施工。
这样,土方回填时,将本实施例的塔吊基础一并回填至自然地面1或自然地面1以下的一段高度,即可正常施工地上主体部分。塔吊拆除时,直接在自然地面1或自然地面1以下的一段高度进行,就可以将塔吊标准节3与预埋件4拆除分离,再次土方开挖量没有或很少,并且避免了塔吊标准节3的浪费。
尽管上面结合附图对本发明的优选实施例进行了描述,但是本发明并不局限于上述的具体实施方式,上述的具体实施方式仅仅是示意性的,并不是限制性的,本领域的普通技术人员在本发明的启示下,在不脱离本发明宗旨和权利要求所保护的范围情况下,还可以作出很多形式的具体变换,这些均属于本发明的保护范围之内。

Claims (2)

1.一种深基坑内塔吊基础,其特征在于,包括由下到上依次设置的基础一阶、基础二阶和预埋件;
所述基础一阶为钢筋混凝土结构,固定设置于基础垫层上,其截面尺寸为5000×5000mm~6000×6000mm,高度为1200~1500mm;
所述基础二阶为钢筋混凝土结构,固定设置于所述基础一阶上,其截面尺寸为塔吊标准节截面尺寸外扩150~300mm,其顶面标高为自然地面标高至低于自然地面标高1000mm范围内;
所述预埋件由塔吊标准节以中间位置截断制成,截面尺寸与塔吊标准节相同,高度为塔吊标准节高度的1/2;所述预埋件埋设于所述基础二阶中,底部通过固定架固定于基础垫层;所述预埋件顶面露出于所述基础二阶顶面200~500mm,用于通过螺栓连接塔吊标准节。
2.一种如权利要求1所述深基坑内塔吊基础的施工方法,其特征在于,包括如下步骤:
(1)根据基础垫层标高和自然地面标高,设计所述基础一阶和所述基础二阶的尺寸,并计算校核;
(2)土方开挖;
(3)安装所述基础一阶和所述基础二阶的模板;
(4)将所述预埋件通过固定架固定安装于基础垫层;
(5)绑扎所述基础一阶和所述基础二阶的钢筋;
(6)浇筑所述基础一阶和所述基础二阶的混凝土;
(7)混凝土强度满足要求后,将塔吊标准节安装于所述预埋件顶端。
CN201410280801.8A 2014-06-20 2014-06-20 一种深基坑内塔吊基础及其施工方法 Pending CN104032767A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410280801.8A CN104032767A (zh) 2014-06-20 2014-06-20 一种深基坑内塔吊基础及其施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410280801.8A CN104032767A (zh) 2014-06-20 2014-06-20 一种深基坑内塔吊基础及其施工方法

Publications (1)

Publication Number Publication Date
CN104032767A true CN104032767A (zh) 2014-09-10

Family

ID=51463744

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410280801.8A Pending CN104032767A (zh) 2014-06-20 2014-06-20 一种深基坑内塔吊基础及其施工方法

Country Status (1)

Country Link
CN (1) CN104032767A (zh)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104314315A (zh) * 2014-10-11 2015-01-28 中国建筑第八工程局有限公司 钢拱架安装的施工方法
CN106836264A (zh) * 2017-01-09 2017-06-13 国网山东省电力公司烟台供电公司 一种杆塔基础施工方法
CN107700519A (zh) * 2017-10-10 2018-02-16 中建四局第六建筑工程有限公司 一种举升塔吊基础安装方法
CN111847197A (zh) * 2020-07-03 2020-10-30 中建三局集团有限公司 重载运载设备及其施工方法
CN112279038A (zh) * 2020-11-26 2021-01-29 江西省丰和泰重工科技有限公司 一种防风型施工升降机基座

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5505033A (en) * 1988-12-06 1996-04-09 501 Hitachi Metals Ltd. Column base structure and connection arrangement
JP2000314141A (ja) * 1999-04-30 2000-11-14 Nobuo Takayama 基礎用コンクリートブロック及びその施工方法
KR100588445B1 (ko) * 2005-09-21 2006-06-12 한국전파기지국주식회사 환경친화적 전주 설치 공법
CN201502065U (zh) * 2009-09-25 2010-06-09 中国电力科学研究院 一种锚杆联合开挖类复合基础
CN203129166U (zh) * 2013-04-12 2013-08-14 肥城鲁泰科技有限公司 大弯矩底部法兰盘电杆预制基础

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5505033A (en) * 1988-12-06 1996-04-09 501 Hitachi Metals Ltd. Column base structure and connection arrangement
JP2000314141A (ja) * 1999-04-30 2000-11-14 Nobuo Takayama 基礎用コンクリートブロック及びその施工方法
KR100588445B1 (ko) * 2005-09-21 2006-06-12 한국전파기지국주식회사 환경친화적 전주 설치 공법
CN201502065U (zh) * 2009-09-25 2010-06-09 中国电力科学研究院 一种锚杆联合开挖类复合基础
CN203129166U (zh) * 2013-04-12 2013-08-14 肥城鲁泰科技有限公司 大弯矩底部法兰盘电杆预制基础

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
涂泽军: "塔吊基础节与承台支座连接采用预埋基础节连接方案的论证", 《城市建设理论研究(电子版)》, no. 16, 30 June 2011 (2011-06-30) *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104314315A (zh) * 2014-10-11 2015-01-28 中国建筑第八工程局有限公司 钢拱架安装的施工方法
CN104314315B (zh) * 2014-10-11 2016-08-17 中国建筑第八工程局有限公司 钢拱架安装的施工方法
CN106836264A (zh) * 2017-01-09 2017-06-13 国网山东省电力公司烟台供电公司 一种杆塔基础施工方法
CN107700519A (zh) * 2017-10-10 2018-02-16 中建四局第六建筑工程有限公司 一种举升塔吊基础安装方法
CN111847197A (zh) * 2020-07-03 2020-10-30 中建三局集团有限公司 重载运载设备及其施工方法
CN112279038A (zh) * 2020-11-26 2021-01-29 江西省丰和泰重工科技有限公司 一种防风型施工升降机基座

Similar Documents

Publication Publication Date Title
CN103195076B (zh) 淤泥质深基坑塔吊基础施工方法
CN103195158B (zh) 一种市政排水管线泥水平衡顶管施工方法
CN101691751B (zh) 超长人工挖孔桩穿越溶洞施工方法及穿越溶洞的超长桩
CN102434717B (zh) 工字钢顶管工作坑的施工方法
CN207777770U (zh) 一种预制拼接管件顶进系统
CN103696784B (zh) 一种浅埋大跨隧道下穿建构筑物的大直径长管幕施工方法
CN104452809A (zh) 一种超浅埋隧道盖挖施工方法
CN101509263A (zh) 钢盖板盖挖法基坑结构及其施工方法
CN103711056B (zh) 钢质工具式临时施工道路及其施工方法
CN104032767A (zh) 一种深基坑内塔吊基础及其施工方法
CN104594361B (zh) 一种工字型围护桩以及围护结构兼做主体结构的施工方法
CN106988334B (zh) 一种沉井支撑结构及沉井施工方法
CN102505704A (zh) 软弱地质竖井中大型沉井施工方法
CN104563146A (zh) 定直埋式雨污水泵站沉井工程施工方法
CN104264683B (zh) 三面环绕文保建筑凹字形超深基坑分区支护方法
CN104131571B (zh) 一种深基坑支护施工方法
CN109706952A (zh) 大型沉井施工方法
CN206635599U (zh) 一种塌方道路的路面抢险支固装置
CN101824825B (zh) 一种深基坑明挖施工方法
CN106164380A (zh) 风力发电机预制基座
CN104818729B (zh) 可供大小塔吊转换的共用基础
CN105908752B (zh) 一种用于侧墙混泥土浇筑的支模拆模系统及其工作过程
CN102296600A (zh) 一种铺盖法修建地铁车站中间桩定位方法
CN106522572A (zh) 历史保护建筑物有限空间内构筑大空间地下通道施工方法
CN203891047U (zh) 搭设钢平台进行陆上桥梁基础施工设备

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20140910