CN105804089B - 一种原深基坑施工后局部增深支护体系及其施工方法 - Google Patents
一种原深基坑施工后局部增深支护体系及其施工方法 Download PDFInfo
- Publication number
- CN105804089B CN105804089B CN201610190808.XA CN201610190808A CN105804089B CN 105804089 B CN105804089 B CN 105804089B CN 201610190808 A CN201610190808 A CN 201610190808A CN 105804089 B CN105804089 B CN 105804089B
- Authority
- CN
- China
- Prior art keywords
- support
- pile
- foundation pit
- original
- piles
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
- E02D17/04—Bordering surfacing or stiffening the sides of foundation pits
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2220/00—Temporary installations or constructions
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Foundations (AREA)
- Piles And Underground Anchors (AREA)
Abstract
Description
Claims (10)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201610190808.XA CN105804089B (zh) | 2016-03-30 | 2016-03-30 | 一种原深基坑施工后局部增深支护体系及其施工方法 |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201610190808.XA CN105804089B (zh) | 2016-03-30 | 2016-03-30 | 一种原深基坑施工后局部增深支护体系及其施工方法 |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN105804089A CN105804089A (zh) | 2016-07-27 |
| CN105804089B true CN105804089B (zh) | 2018-01-12 |
Family
ID=56455085
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201610190808.XA Expired - Fee Related CN105804089B (zh) | 2016-03-30 | 2016-03-30 | 一种原深基坑施工后局部增深支护体系及其施工方法 |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN105804089B (zh) |
Families Citing this family (10)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN106638610B (zh) * | 2017-03-13 | 2018-07-31 | 中国建筑第七工程局有限公司 | 高差错接结构及其施工方法 |
| CN106988318B (zh) * | 2017-03-28 | 2019-12-17 | 广东省基础工程集团有限公司 | 一种先施工抛撑后施工围护的基坑支护方法 |
| CN107313432B (zh) * | 2017-08-09 | 2023-11-03 | 中铁四局集团有限公司 | 一种上软下硬地层基坑支护结构及其施工方法 |
| CN107700498A (zh) * | 2017-11-03 | 2018-02-16 | 中铁第勘察设计院集团有限公司 | 多线立体交叉异型深基坑支护结构及其施工方法 |
| CN108487256B (zh) * | 2018-03-07 | 2023-09-12 | 中冶集团武汉勘察研究院有限公司 | 一种基坑加深超挖的加固结构及方法 |
| CN109403348A (zh) * | 2018-12-10 | 2019-03-01 | 中建局集团建设发展有限公司 | 一种上刚下柔的深基坑支护体系及其施工方法 |
| CN111005388A (zh) * | 2019-12-12 | 2020-04-14 | 中冶天工集团有限公司 | 一种深基坑整体支撑装置及其支撑方法 |
| CN111411630A (zh) * | 2020-03-31 | 2020-07-14 | 上海二十冶建设有限公司 | 深基坑中的局部加深区域的支护方法 |
| CN113216197B (zh) * | 2021-05-08 | 2022-04-19 | 浙江大学建筑设计研究院有限公司 | 一种通过分坑围护桩开洞设置斜坡道的出土防护结构 |
| CN115387347A (zh) * | 2022-06-06 | 2022-11-25 | 中煤江南建设发展集团有限公司 | 一种基于受限空间的深基坑支护方法 |
Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN104099935A (zh) * | 2014-04-01 | 2014-10-15 | 浙江省建筑设计研究院 | 一种基坑加深后的立柱加固方法 |
| JP2015148099A (ja) * | 2014-02-07 | 2015-08-20 | 鹿島建設株式会社 | 山留め支保工およびそれに使用する端部金物 |
| CN204753603U (zh) * | 2015-05-22 | 2015-11-11 | 中建三局第一建设工程有限责任公司 | 深基坑再加深支护结构 |
| CN205576934U (zh) * | 2016-03-30 | 2016-09-14 | 广东华固工程有限公司 | 一种原深基坑施工后局部增深支护体系 |
Family Cites Families (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| KR100813664B1 (ko) * | 2006-12-12 | 2008-03-14 | 장지건 | 단면 2차 모멘트가 강화된 흙막이 시공 방법 |
-
2016
- 2016-03-30 CN CN201610190808.XA patent/CN105804089B/zh not_active Expired - Fee Related
Patent Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2015148099A (ja) * | 2014-02-07 | 2015-08-20 | 鹿島建設株式会社 | 山留め支保工およびそれに使用する端部金物 |
| CN104099935A (zh) * | 2014-04-01 | 2014-10-15 | 浙江省建筑设计研究院 | 一种基坑加深后的立柱加固方法 |
| CN204753603U (zh) * | 2015-05-22 | 2015-11-11 | 中建三局第一建设工程有限责任公司 | 深基坑再加深支护结构 |
| CN205576934U (zh) * | 2016-03-30 | 2016-09-14 | 广东华固工程有限公司 | 一种原深基坑施工后局部增深支护体系 |
Also Published As
| Publication number | Publication date |
|---|---|
| CN105804089A (zh) | 2016-07-27 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN107542108B (zh) | 一种建筑物地下室结构的逆向施工方法 | |
| CN103343544B (zh) | 一种大型沉井的施工方法 | |
| CN105804089A (zh) | 一种原深基坑施工后局部增深支护体系及其施工方法 | |
| CN102031784B (zh) | 深基坑灌注护坡桩加锚索支护施工方法 | |
| CN112502777B (zh) | 隧道突涌冒顶关门处治的方法 | |
| WO2023077552A1 (zh) | 一种基坑围护及土方开挖的施工方法 | |
| CN103147442B (zh) | 超深基坑压灌桩与预应力锚杆联合支护施工方法 | |
| CN106958256A (zh) | 一种分层浇筑、多次下沉的沉井施工工艺 | |
| CN105201513A (zh) | 一种轨道交通的竖井施工方法 | |
| CN108867814A (zh) | 新建截污次支管与既有污水管网接驳工法 | |
| CN101215834A (zh) | 支腿式地下连续墙施工工法 | |
| CN111576431A (zh) | 四层地铁站基坑开挖方法 | |
| CN118110193A (zh) | 复杂地质陆上大直径沉井全过程施工工法 | |
| CN102430277B (zh) | 一种用于污水物理处理的粗格栅沉井及其施工方法 | |
| CN105155550A (zh) | 联合支护开挖大厚度强风化砂岩层深基坑的施工方法 | |
| CN110778328A (zh) | 穿越滑坡体的黄土隧道进洞口段施工方法 | |
| CN112160324A (zh) | 一种深基坑支护的施工方法 | |
| CN105714769A (zh) | 一种抗滑灌注桩施工方法 | |
| CN119435012B (zh) | 一种三层六洞地铁车站暗挖方法 | |
| CN114622572A (zh) | 一种大型圆基坑三轴搅拌桩支护结构及其施工方法 | |
| CN116446434A (zh) | 一种富水砂层沉井施工方法 | |
| CN113898007B (zh) | 一种沿街大跨度连廊结构半逆作施工方法 | |
| CN103215958A (zh) | 膨胀土地区深基坑降水与支护施工方法 | |
| CN101994314A (zh) | 深孔矩形联排抗滑桩不跳桩开挖施工 | |
| CN113338340A (zh) | 一种保证现有管线正常使用的竖井逆作施工方法 |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| CB03 | Change of inventor or designer information |
Inventor after: Fan Chunqing Inventor after: Huang Zirong Inventor after: Xu Qingren Inventor after: Ma Jin Ju Inventor after: Xu Qingqiang Inventor after: Shi Junjian Inventor after: Zhang Xianghong Inventor after: Lin Chenglin Inventor after: Yi Jiemin Inventor before: Fan Chunqing Inventor before: Yi Jiemin Inventor before: Huang Zirong Inventor before: Li Wei Inventor before: Xu Qingren Inventor before: Ma Jin Ju Inventor before: Xu Qingqiang Inventor before: Shi Junjian Inventor before: Zhang Xianghong Inventor before: Lin Chenglin |
|
| COR | Change of bibliographic data | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180112 |