CN104250971A - 地下室围护支撑体封闭拆除方法 - Google Patents

地下室围护支撑体封闭拆除方法 Download PDF

Info

Publication number
CN104250971A
CN104250971A CN201310257993.6A CN201310257993A CN104250971A CN 104250971 A CN104250971 A CN 104250971A CN 201310257993 A CN201310257993 A CN 201310257993A CN 104250971 A CN104250971 A CN 104250971A
Authority
CN
China
Prior art keywords
basement
construction
concrete
supports
closed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201310257993.6A
Other languages
English (en)
Inventor
梁峰
侯宪伟
陈哨兵
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC20 Group Corp Ltd
Original Assignee
China MCC20 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC20 Group Corp Ltd filed Critical China MCC20 Group Corp Ltd
Priority to CN201310257993.6A priority Critical patent/CN104250971A/zh
Publication of CN104250971A publication Critical patent/CN104250971A/zh
Pending legal-status Critical Current

Links

Landscapes

  • Working Measures On Existing Buildindgs (AREA)

Abstract

本发明涉及地下室施工,尤其涉及地下室围护支撑体的拆除方法。一种地下室围护支撑体封闭拆除方法,它包括:步骤一,施工完砼支撑下部地下室结构并换撑完毕后,人工拆除与地下室外墙相交部位的砼非主支撑;步骤二,继续地下室结构施工,部分位于支撑下面的竖向结构如砼柱、砼墙等需在前期施工楼板相应位置预留砼浇捣空、预留搭接钢筋,在支撑室内破除、清渣完成后再进行结构补做,即要提前做好留设施工缝的深化设计;步骤三,地下室结构施工完后,在地下室内进行封闭式拆除砼支撑;步骤四,废钢筋和渣土利用已施工完成的地下室车道外运。本发明不需要大面积搭设防护棚,支撑拆除、垃圾清理等工作与上部结构同时施工,不占用工程主线路工期,减少了支撑拆除工序对结构施工关键线路的影响,加快总体施工进度。

Description

地下室围护支撑体封闭拆除方法
技术领域
本发明涉及地下室施工,尤其涉及地下室围护支撑体的拆除方法。
背景技术
对于超深有多道钢筋砼水平支撑的地下室基坑,当前多采用敞开式拆除支撑方法,需要搭防护棚,垃圾清理占用工程主线路工期,对地下室施工工期及整体结构施工进度相当制约。
发明内容
本发明旨在解决现有技术的上述问题,提供一种地下室围护支撑体封闭拆除方法。本发明不需要大面积搭设防护棚,支撑拆除、垃圾清理等工作与上部结构同时施工,不占用工程主线路工期,减少了支撑拆除工序对结构施工关键线路的影响,加快总体施工进度。
为了解决上述技术问题,本发明一种地下室围护支撑体封闭拆除方法,它包括:
步骤一,施工完砼支撑下部地下室结构并换撑完毕后,人工拆除与地下室外墙相交部位的砼非主支撑;
步骤二,继续地下室结构施工,部分位于支撑下面的的竖向结构如砼柱、砼墙需在前期施工楼板相应位置预留砼浇捣空、预留搭接钢筋,在支撑室内破除、清渣完成后再进行结构补做,即要提前做好留设施工缝的深化设计;
步骤三,地下室结构施工完后,在地下室内进行封闭式拆除砼支撑;
步骤四,废钢筋和渣土利用已施工完成的地下室车道外运。
本发明提高拆除工作效率,缩短施工工期。保证了安全要求,有效控制拆除过程中飞石以及扬尘的危害性,将对周边环境的影响降至最小。降低施工措施成本,能取得良好的经济效益和社会效益。
具体实施方式
   下面,结合具体方式对本发明作进一步的说明:
一种地下室围护支撑体封闭拆除方法,它包括:
步骤一,施工完砼支撑下部地下室结构并换撑完毕后,人工拆除与地下室外墙相交部位的砼非主支撑;
步骤二,继续地下室结构施工,部分位于支撑下面的的竖向结构如砼柱、砼墙等需在前期施工楼板相应位置预留砼浇捣空、预留搭接钢筋,在支撑室内破除、清渣完成后再进行结构补做,即要提前做好留设施工缝的深化设计;
步骤三,地下室结构施工完后,在地下室内进行封闭式拆除砼支撑;运用非电毫秒延期微差爆破方式,分段延时起爆,利用炮孔中的炸药爆炸产生的能量从支撑内部膨胀直接破碎介质(钢筋混凝土),采用粉碎性破碎与松动破碎相结合的爆破方案,把爆破震动、冲击波、飞石和噪音等对环境危害程度控制在规定的范围之内;
步骤四,废钢筋和渣土利用已施工完成的地下室车道外运。

Claims (1)

1.一种地下室围护支撑体封闭拆除方法,其特征在于,它包括:
步骤一,施工完砼支撑下部地下室结构并换撑完毕后,人工拆除与地下室外墙相交部位的砼非主支撑;
步骤二,继续地下室结构施工,部分位于支撑下面的的竖向结构如砼柱、砼墙需在前期施工楼板相应位置预留砼浇捣空、预留搭接钢筋,在支撑室内破除、清渣完成后再进行结构补做,即要提前做好留设施工缝的深化设计;
步骤三,地下室结构施工完后,在地下室内进行封闭式拆除砼支撑;
步骤四,废钢筋和渣土利用已施工完成的地下室车道外运。
CN201310257993.6A 2013-06-26 2013-06-26 地下室围护支撑体封闭拆除方法 Pending CN104250971A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310257993.6A CN104250971A (zh) 2013-06-26 2013-06-26 地下室围护支撑体封闭拆除方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310257993.6A CN104250971A (zh) 2013-06-26 2013-06-26 地下室围护支撑体封闭拆除方法

Publications (1)

Publication Number Publication Date
CN104250971A true CN104250971A (zh) 2014-12-31

Family

ID=52186204

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310257993.6A Pending CN104250971A (zh) 2013-06-26 2013-06-26 地下室围护支撑体封闭拆除方法

Country Status (1)

Country Link
CN (1) CN104250971A (zh)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104895092A (zh) * 2015-06-02 2015-09-09 中建四局第六建筑工程有限公司 一种内支撑临时格构柱用作永久结构柱的方法

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH02274916A (ja) * 1989-04-18 1990-11-09 Toda Constr Co Ltd 山留め支保工の解体工法
CN101476331A (zh) * 2007-12-12 2009-07-08 中国二十冶建设有限公司 地下室基坑砼内支撑封闭爆破拆除方法
CN102747736A (zh) * 2012-07-12 2012-10-24 中建一局集团第三建筑有限公司 一种组合工具式的内支撑换撑方法

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH02274916A (ja) * 1989-04-18 1990-11-09 Toda Constr Co Ltd 山留め支保工の解体工法
CN101476331A (zh) * 2007-12-12 2009-07-08 中国二十冶建设有限公司 地下室基坑砼内支撑封闭爆破拆除方法
CN102747736A (zh) * 2012-07-12 2012-10-24 中建一局集团第三建筑有限公司 一种组合工具式的内支撑换撑方法

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
汪宏友 等: "临近地铁隧道钢筋混凝土支撑梁爆破拆除施工技术", 《施工技术》, vol. 40, 30 June 2011 (2011-06-30), pages 116 - 118 *
陈冲: "大型基坑内支撑体系爆破拆除技术", 《探矿工程(岩土钻掘工程)》, vol. 39, no. 2, 29 February 2012 (2012-02-29), pages 80 - 84 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104895092A (zh) * 2015-06-02 2015-09-09 中建四局第六建筑工程有限公司 一种内支撑临时格构柱用作永久结构柱的方法

Similar Documents

Publication Publication Date Title
CN109139104B (zh) 一种穿越碎屑岩陡倾逆冲富水断层隧道排水施工方法
CN105003272A (zh) 一种在地铁区间盾构隧道基础上扩挖车站的逆作施工方法
CN105089670B (zh) 一种在并行区间盾构隧道基础上扩挖地铁车站施工方法
CN101413393A (zh) 煤层综放工作面沿空留巷巷帮支护法
CN102587691A (zh) 一种爆破拆除建筑物的防尘方法
CN102733399A (zh) 静态膨胀拆除内支撑混凝土的方法
CN204154197U (zh) 钢筋混凝土梁拆除爆破炮孔装药、堵塞和压渣结构
CN106499199A (zh) 临近地铁超深基坑中隔墙临时换撑及其施工方法
CN203130086U (zh) 一种双连拱隧道的无导洞开挖结构
CN104250971A (zh) 地下室围护支撑体封闭拆除方法
CN103790176A (zh) 一种预埋短肢柱结构及其施工方法
CN103046765B (zh) 防空洞加固后继续使用的施工工艺
CN103422508B (zh) 深基坑内支撑平台结构机械闷拆方法及结构
CN104405402A (zh) 隐式中墙连拱隧道对称中隔壁施工方法
CN104500071A (zh) 煤层开采避开动压影响的沿空留巷方法
CN207793942U (zh) 可拆卸式钢管混凝土防撞柱
CN103397661B (zh) 型钢-混凝土地下组合外墙结构的施工工艺
CN104047273B (zh) 水电站消能防冲墙及其施工方法
CN115306428A (zh) 一种适用于双侧壁导坑法隧道二衬安全快速施工方法
KR20020013618A (ko) 화약에 의한 건물발파해체 방법
Sinitsyn Drilling-and-blasting method of demolition
CN204386611U (zh) 一种隧洞喷射混凝土免拆模板
CN106759526A (zh) 一种深基坑支撑梁爆破拆除前的围檩保护预处理方法
CN109083155B (zh) 一种基坑内支撑结构及其爆破拆除方法
CN207728116U (zh) 一种用于岩土工程勘察的钻机围挡装置

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20141231