CN104047273B - 水电站消能防冲墙及其施工方法 - Google Patents
水电站消能防冲墙及其施工方法 Download PDFInfo
- Publication number
- CN104047273B CN104047273B CN201310079431.7A CN201310079431A CN104047273B CN 104047273 B CN104047273 B CN 104047273B CN 201310079431 A CN201310079431 A CN 201310079431A CN 104047273 B CN104047273 B CN 104047273B
- Authority
- CN
- China
- Prior art keywords
- dissipation
- scouring
- wall
- anchor pole
- scouring wall
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000009991 scouring Methods 0.000 title claims abstract description 73
- 238000010276 construction Methods 0.000 title claims abstract description 28
- 239000004567 concrete Substances 0.000 claims abstract description 27
- 239000011435 rock Substances 0.000 claims abstract description 11
- 230000021715 photosynthesis, light harvesting Effects 0.000 claims abstract description 8
- 238000007599 discharging Methods 0.000 claims abstract description 5
- 238000009412 basement excavation Methods 0.000 claims description 12
- 238000007596 consolidation process Methods 0.000 claims description 8
- 230000003466 anti-cipated effect Effects 0.000 claims description 3
- 239000000725 suspension Substances 0.000 claims description 3
- 238000000034 method Methods 0.000 claims 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 abstract description 3
- 238000005406 washing Methods 0.000 description 4
- 229910000831 Steel Inorganic materials 0.000 description 2
- 238000005266 casting Methods 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 239000011210 fiber-reinforced concrete Substances 0.000 description 2
- 239000011159 matrix material Substances 0.000 description 2
- 239000010959 steel Substances 0.000 description 2
- 230000007812 deficiency Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000012407 engineering method Methods 0.000 description 1
- 230000002787 reinforcement Effects 0.000 description 1
- 230000009466 transformation Effects 0.000 description 1
Landscapes
- Revetment (AREA)
Abstract
本发明公开了一种水电站消能防冲墙,包括水电站泄流消能区岸坡的混凝土护坡(2),特征是在该混凝土护坡(2)的尾部设有竖直向下埋藏入下游河床底部基岩中的消能防冲墙(1),该消能防冲墙(1)为C35混凝土结构,厚1~3m。本发明还公开了该水电站消能防冲墙的施工方法。这种消能防冲结构不需要清除河床全部的覆盖层,工程量小,而且混凝土施工方便,保证混凝土的浇筑质量,节约了投资,下泄洪水时保证了泄洪消能防冲区的结构安全。
Description
技术领域
本发明涉及一种应用于水利水电工程中的消能防冲结构及其施工方法,特别是涉及一种水电站消能防冲墙及其施工方法。
背景技术
水电工程中,泄洪消能防冲结构是水利水电工程中常见的水工建筑物,通常水电站泄洪消能区防冲结构为两岸岸坡采用混凝土护坡,底部采用混凝土护底,这种结构通常要清除河床覆盖层,工程量大,并且进行混凝土底板施工时,由于河道狭窄,混凝土底板的施工难度大,混凝土质量很难保证,经常由于质量问题泄洪时混凝土底板遭到破坏,需要后期进行修复,增加工程投资。
发明内容
本发明的目的是提供一种可保证消能防冲区消能防冲结构的稳定,减少护坡工程量,方便施工,节省工程投资,并且具有良好适应性的水电站消能防冲墙及其施工方法,以克服现有技术的不足。
本发明的结构是与水电站泄流消能区岸坡的混凝土护坡形成整体的消能防冲结构,它是在该混凝土护坡的尾部设有竖直向下埋藏入下游河床底部基岩中的消能防冲墙,从而形成一种埋藏式的消能防冲墙,该消能防冲墙为C35混凝土结构,厚1~3m。在该消能防冲墙的前后两侧设有水平锚杆,在该消能防冲墙的底部设有竖直锚杆,水平锚杆和竖直锚杆均是Ф25钢筋结构。由于埋藏式的消能防冲墙与水电站泄流消能区岸坡的混凝土护坡形成整体受力结构,再通过锚杆与周围岩体之间形成进一步的加固结构,使该结构在泄洪消能时可以有效抵抗水流淘涮,从而保证消能防冲结构的稳定。
前述的水平锚杆长度为2~3m,深入所述消能防冲墙两侧的岩石1.5~2.5m,外露0.5m,间排距2m;前述竖直锚杆长度为5~7m,深入岩石4~6m,外露1.0m,间排距2m。这样可以保证锚杆起到有效的加固作用。
本发明的水电站消能防冲墙,在施工时包括以下步骤:
首先在进行消能防冲墙坑槽基础开挖前先进行河床侧壁基础挖前锚杆和固结灌浆的施工,固结灌浆孔深入新鲜基岩;
再按照消能防冲墙尺寸进行消能防冲墙坑槽基础开挖;开挖时在消能防冲区河道两岸坡底部深挖至预计的冲坑深度以下2~3m,以保证埋藏深度,防止消能防冲墙在泄流冲击下发生坍塌或滑移。
然后完成消能防冲墙坑槽基础支护;其中槽挖采用锚喷支护,其余开挖采用锚杆支护,喷混凝土为C25钢纤维混凝土,厚10cm。
最后按照常规浇筑工艺完成消能防冲墙混凝土浇筑,并在消能防冲墙上每隔10~20m设施工缝,20~40m设伸缩缝,在消能防冲墙表层配构造钢筋。形成的消能防冲墙墙厚1~3m,墙顶与混凝土护坡相接从而形成整体受力结构,以抵抗水流的冲刷,保证消能防冲结构稳定。
本发明采用埋藏式消能防冲结构,将消能防冲墙与底部基岩通过锚杆和固结灌浆结合成整体结构,消能防冲墙顶与混凝土护坡相接形成整体受力结构,以抵抗水流的冲刷,保证消能防冲结构稳定。下泄洪水时,抵抗水流冲刷,岸坡不会发生破坏,这种消能防冲结构不需要清除河床全部的覆盖层,工程量小,而且混凝土施工方便,保证混凝土的浇筑质量,节约了投资,下泄洪水时保证了泄洪消能防冲区的结构安全。
附图说明
图1是深埋式消能防冲墙结构图;
图2是深埋式消能防冲墙开挖支护图。
附图中的标记为:1-消能防冲墙、2-混凝土护坡、3-水平锚杆、4-竖直锚杆、5-挖前锚杆、6-固结灌浆孔。
具体实施方式
下面结合附图和实施例对本发明作进一步的详细说明。
看图1,图1展示了本发明的深埋式消能防冲墙结构,它包括水电站泄流消能区岸坡的混凝土护坡2,它在该混凝土护坡2的尾部设有竖直向下埋藏入下游河床底部基岩中的消能防冲墙1,该消能防冲墙1为C35混凝土结构,厚1~3m。它还在消能防冲墙1的前后两侧设有水平锚杆3,在消能防冲墙1的底部设有竖直锚杆4,水平锚杆3和竖直锚杆4均是Ф25钢筋结构。
本发明的埋藏式消能防冲墙,其核心要素是控制施工工艺和质量,为保证形成消能防冲墙与基岩成整体,本发明采用如下的施工方法:
首先在进行消能防冲墙1坑槽基础开挖前先进行河床侧壁基础挖前锚杆5和固结灌浆的施工;挖前锚杆5和固结灌浆孔6的布置如图2所示。其中挖前锚杆5为φ25钢筋结构,L=9.0m,间排距2.0m,梅花形布设,固结灌浆孔6深入新鲜基岩,间距2.5m,排距2.0m,梅花形布设。
再按照消能防冲墙1的尺寸进行消能防冲墙1坑槽基础开挖;开挖时在消能防冲区河道两岸坡底部深挖至预计的冲坑深度以下2~3m,以保证埋藏深度,防止消能防冲墙1在泄流冲击下发生坍塌或滑移。
然后完成消能防冲墙1坑槽基础支护;其中槽挖采用锚喷支护,其余开挖采用锚杆支护,喷混凝土为C25钢纤维混凝土,厚10cm。
最后按照常规浇筑工艺完成消能防冲墙1混凝土浇筑,并在消能防冲墙1上每隔10~20m设施工缝,20~40m设伸缩缝,在消能防冲墙1表层配构造钢筋。钢筋混凝土的应严格施工按国家现行相关规范进行施工和验收。形成的消能防冲墙1墙厚1~3m,墙顶与混凝土护坡2相接从而形成整体受力结构,以抵抗水流的冲刷,保证消能防冲结构稳定。
当然,以上只是本发明的具体应用范例,本发明还有其他的实施方式,凡采用等同替换或等效变换形成的实施方式,均落在本发明所要求的保护范围之内。
Claims (2)
1.一种水电站消能防冲墙,包括水电站泄流消能区岸坡的混凝土护坡(2),其特征在于:它采用埋藏式消能防冲结构,在所述混凝土护坡(2)的尾部设有竖直向下埋藏入下游河床底部基岩中的消能防冲墙(1),该消能防冲墙(1)为C35混凝土结构,厚1~3m;在所述消能防冲墙(1)的前后两侧设有水平锚杆(3),在所述消能防冲墙(1)的底部设有竖直锚杆(4),水平锚杆(3)和竖直锚杆(4)均是Ф25钢筋结构;该埋藏式消能防冲结构是这样形成的:先进行河床侧壁基础挖前锚杆(5)和固结灌浆的施工,再按照消能防冲墙(1)尺寸进行消能防冲墙(1)坑槽基础开挖,开挖时在消能防冲区河道两岸坡底部深挖至预计的冲坑深度以下2~3m,以保证埋藏深度,然后完成消能防冲墙(1)坑槽基础支护,其中槽挖采用锚喷支护,其余开挖采用锚杆支护,然后按照常规工艺完成消能防冲墙(1)混凝土浇筑。
2.根据权利要求1所述的水电站消能防冲墙,其特征在于:所述水平锚杆(3)长度为2~3m,深入所述消能防冲墙(1)两侧的岩石1.5~2.5m,外露0.5m,间排距2m;所述竖直锚杆(4)长度为5~7m,深入岩石4~6m,外露1.0m,间排距2m。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310079431.7A CN104047273B (zh) | 2013-03-13 | 2013-03-13 | 水电站消能防冲墙及其施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310079431.7A CN104047273B (zh) | 2013-03-13 | 2013-03-13 | 水电站消能防冲墙及其施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104047273A CN104047273A (zh) | 2014-09-17 |
CN104047273B true CN104047273B (zh) | 2016-12-28 |
Family
ID=51500644
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310079431.7A Active CN104047273B (zh) | 2013-03-13 | 2013-03-13 | 水电站消能防冲墙及其施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104047273B (zh) |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109356091B (zh) * | 2018-11-21 | 2024-01-19 | 中国电建集团成都勘测设计研究院有限公司 | 山溪河流堤防工程 |
CN110847066A (zh) * | 2019-11-27 | 2020-02-28 | 中国电建集团成都勘测设计研究院有限公司 | 用于高挡墙涵洞的出口结构 |
CN111576361A (zh) * | 2020-06-02 | 2020-08-25 | 广州地理研究所 | 一种泄洪闸消能防冲设备 |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
SU1625936A1 (ru) * | 1988-08-15 | 1991-02-07 | Восточно-Сибирское Отделение Всесоюзного Проектно-Изыскательского И Научно-Исследовательского Института "Гидропроект" Им.С.Я.Жука | Открытый водосброс на скальном основании |
CN101831892A (zh) * | 2010-04-08 | 2010-09-15 | 重庆交通大学 | 水电站岸坡消能结构 |
CN102733361A (zh) * | 2012-07-20 | 2012-10-17 | 中国水电顾问集团北京勘测设计研究院 | 窄河谷、深尾水的高拱坝泄洪消能结构 |
-
2013
- 2013-03-13 CN CN201310079431.7A patent/CN104047273B/zh active Active
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
SU1625936A1 (ru) * | 1988-08-15 | 1991-02-07 | Восточно-Сибирское Отделение Всесоюзного Проектно-Изыскательского И Научно-Исследовательского Института "Гидропроект" Им.С.Я.Жука | Открытый водосброс на скальном основании |
CN101831892A (zh) * | 2010-04-08 | 2010-09-15 | 重庆交通大学 | 水电站岸坡消能结构 |
CN102733361A (zh) * | 2012-07-20 | 2012-10-17 | 中国水电顾问集团北京勘测设计研究院 | 窄河谷、深尾水的高拱坝泄洪消能结构 |
Non-Patent Citations (2)
Title |
---|
水布垭水电站防淘墙设计与施工;曾祥虎等;《水力发电》;20070831;第33卷(第8期);第22-24页 * |
水布垭防淘墙顶混凝土护坡工程施工技术;赵献勇;《人民长江》;20070430;第38卷(第4期);第27-28页 * |
Also Published As
Publication number | Publication date |
---|---|
CN104047273A (zh) | 2014-09-17 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US10138616B2 (en) | Inverse construction method for deep, large and long pit assembling structure of suspension-type envelope enclosure | |
CN103981898B (zh) | 一种整体明挖节点逆作的地下工程施工方法 | |
CN203334322U (zh) | 地下连续墙防渗流止浆装置 | |
CN102966108A (zh) | 紧临既有建筑物以地下结构为内支撑的深基坑施工方法 | |
CN104594361B (zh) | 一种工字型围护桩以及围护结构兼做主体结构的施工方法 | |
CN110374112B (zh) | 软弱土场地深基坑支护体系及其施工方法 | |
CN110004991B (zh) | 基于外凸式翼脚板的地下结构抗浮体系及构建方法 | |
CN103103988A (zh) | 利用中心岛楼板水平支撑结构的基坑施工方法 | |
CN104818728A (zh) | 一种地下室楼板与支护桩共同工作的永久支护体系 | |
CN108797641A (zh) | 一种地铁暗挖车站施工期间全车站止水的结构及其施工方法 | |
CN203729306U (zh) | 抗滑桩和挡土板支护结构 | |
CN104790435A (zh) | 沉降后浇带超前止水抗渗混凝土结构及其施工工艺 | |
CN204780933U (zh) | 基坑支撑栈桥体系 | |
CN104047273B (zh) | 水电站消能防冲墙及其施工方法 | |
CN203904971U (zh) | 控制地下连续墙缩颈、漏筋、夹泥的钢筋笼保护装置 | |
CN103898915B (zh) | 建筑物小面积深基坑抗浮止水施工方法 | |
KR101262865B1 (ko) | 수중 가물막이 공법 | |
CN209941754U (zh) | 一种高压电力管涵原地保护结构 | |
CN105507329A (zh) | 深基坑支护施工中淤泥质土层基坑底板换撑系统 | |
CN217150275U (zh) | 一种高水位软弱地基基坑支护装置 | |
CN104846837A (zh) | 一种明排水基坑中超深井坑的施工方法 | |
CN106638670B (zh) | 半预制管廊及施工方法 | |
CN106088762B (zh) | 一种插槽式外包钢板预制装配式圆形地下粮仓 | |
CN203144981U (zh) | 埋藏式消能防冲结构 | |
CN210122735U (zh) | 一种基于外凸式翼脚板的地下结构抗浮体系 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CP03 | Change of name, title or address |
Address after: 550081 Guizhou Province, Guiyang City Lake District Xingqian Road No. 16 Patentee after: POWERCHINA GUIYANG ENGINEERING CORPORATION LIMITED Address before: 550081 No. 16 Xing Qian Road, Jinyang New District, Guizhou, Guiyang Patentee before: HydroChina Guiyang Engineering Corp. |