CN101333869A - Construction method for integrally hoisting steel platform and integrally traversing girders layer - Google Patents
Construction method for integrally hoisting steel platform and integrally traversing girders layer Download PDFInfo
- Publication number
- CN101333869A CN101333869A CNA2008100401711A CN200810040171A CN101333869A CN 101333869 A CN101333869 A CN 101333869A CN A2008100401711 A CNA2008100401711 A CN A2008100401711A CN 200810040171 A CN200810040171 A CN 200810040171A CN 101333869 A CN101333869 A CN 101333869A
- Authority
- CN
- China
- Prior art keywords
- layer
- platform
- steel
- construction
- truss
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The invention relates to a construction method which integrally lifts the steel platform to cross the truss layer entirely; the steps are as follows: 1. the core tube construction is processed to reach a concrete segment under the truss layer; a steel truss is mounted and a temporal stable butt joint is arranged; 2. a lattice column, a plate lifting machine support and a plate lifting machine used for crossing the truss layer are mounted; a long lead screw is connected and the platform steel girder is hung; 3. the platform girder part contacted with the truss is demounted; the steel platform is lifted to each segment and stopped in each layer for marking the height; then the platform girder is reset and the steel platform is fixed; a reinforced steel bar of the vertical segment layer is bound; a large mould plate is lifted and the concrete is cast; 4. the step 3 is repeated until the steel platform pass through the truss layer; 5. the construction method turns into the general standard construction flow. The construction method in the invention can effectively reduce the aloft work risk and furthest guarantee the construction safety; the process is simple; the construction period of the truss layer is shorten and the construction cost is reduced effectively.
Description
Technical field
The present invention relates to a kind of job platform of super highrise building cylindrical shell construction, especially a kind of is that supporting, Lift-slab machine are the job practices of the integrally hoisting steel platform of power by the stiffness lattice column.
Background technology
Develop by Shanghai construction engineering group, by the stiffness lattice column is that supporting, Lift-slab machine are the integrally hoisting steel platform system of power, as a kind of job platform system that is applicable to the construction of superelevation layer nuclear core cylindrical shell, be successfully applied to high-rise nuclear core cylindrical shell construction such as Oriental Pearl, Jin Mao Tower, Global Finance center.Yet, run into include the stiffness truss after, conventional job practices (Fig. 1) is to realize integrally hoisting steel platform, and need stiffness cylindricality formula and Lift-slab machine arrangement be adjusted, so that the steel platform satisfies the construction needs at cylindrical shell girders layer section, and not configuration template, pin hand separately.
Summary of the invention
The present invention will solve after running into the stiffness truss, makes the steel plateform system can be in the whole technical problem that promotes of girders layer, and a kind of integrally hoisting steel platform and integrally traversing girders layer job practices is provided.
For solving technical problem of the present invention, the technical scheme that is adopted is as follows:
A kind of integrally hoisting steel platform and integrally traversing girders layer job practices, concrete steps are:
1. core tube construction concrete segmentation to girders layer, and steel truss is installed and is provided with interim stable to support;
2. lattice column, Lift-slab machine carriage and Lift-slab machine that girders layer is used were installed, and the spreading screw mandrel is hung the platform girder steel;
3. remove the landing beam parts of colliding, promote steel platform to each segmentation and stop a layer absolute altitude, then landing beam is resetted and fixing steel platform with truss, and the reinforcing bar of a vertical section layer of colligation, large form and fluid concrete promoted;
4. repeat third step to passing through girders layer;
5. enter the conventional criteria construction process.
After above-mentioned the 4th step, before entering the conventional criteria construction process, lattice column is converted to the typical floor lattice column, and Lift-slab machine is converted to typical floor construction state.
The invention has the beneficial effects as follows:
1. effectively reduce the work high above the ground risk, ensured construction safety to greatest extent
Integrated lifting steel plateform system puts in place according to successively whole lifting of each vertical section of girders layer, the solid broad operation platform and the operating environment of complete closed are provided, avoided simultaneously the steel platform being split the combination operation in the high-altitude, compare with the job practices of routine, construction risk is reduced to minimum.
2. technology is easy, has shortened the girders layer construction period
Compare with the cylindrical shell construction of general floor, only need are adjusted the form of the supporting member-lattice column of steel platform and the position of Hoisting System-Lift-slab machine, and need not carry out big transformation to steel plateform system, can realize that steel plateform system integral body successively promoted girders layer.Simultaneously, with the construction of the above level of girders layer be connected very smooth and easy, thereby the large form and the pin hand that can directly utilize steel plateform system to carry have improved mechanization degree greatly, have shortened the duration.
3. effectively reduce construction cost
Use job practices of the present invention, the large form and the sealing pin hand that can directly use steel plateform system to carry, and mechanization degree is higher, compares with conventional method, has saved a large amount of templates, pin hand and labour cost.
Description of drawings
Fig. 1 is an integrally hoisting steel platform system conventional method construction schematic diagram;
Fig. 2 is a construction schematic diagram of the present invention;
Fig. 3 is a process chart of the present invention;
Fig. 4 to Fig. 9 is a work progress schematic diagram of the present invention.
The specific embodiment
Below in conjunction with specific embodiment, further set forth the present invention.Should be understood that these embodiment only to be used to the present invention is described and be not used in and limit the scope of the invention.Should be understood that in addition those skilled in the art can make various changes or modifications the present invention after the content of having read the present invention's instruction, these equivalent form of values fall within the application's appended claims institute restricted portion equally.
Technological principle of the present invention:
Job practices central principle of the present invention is: after running into the stiffness truss, adjust the arrangement form of lattice column and plateform system, make it to avoid truss, and the arrangement of transformation Lift-slab machine, steel plateform system can be promoted in girders layer integral body, thereby realize utilizing steel plateform system that girders layer is carried out section construction (shown in Figure 2).
The concrete steps of integrally hoisting steel platform and integrally traversing girders layer job practices of the present invention are as shown in Figure 3:
(1) core tube construction concrete segmentation to girders layer, and steel truss 2 is installed and is provided with interim stable to support (Fig. 4);
(2) lattice column 3, Lift-slab machine carriage and the Lift-slab machine 4 that girders layer is used was installed, spreading screw mandrel 5 is hung platform girder steel (Fig. 5);
(3) remove the landing beam parts of colliding, promote steel platform 1 to each segmentation and stop a layer absolute altitude, then platform 1 beam is resetted and fixing steel platform 1 with truss, and the reinforcing bar of a vertical section layer of colligation, large form 6 and fluid concrete (Fig. 6) promoted;
(4) repeat third step to passing through girders layer 7 (Fig. 7,8);
(5) enter the conventional criteria construction process.
After above-mentioned the 4th step, before entering the conventional criteria construction process, lattice column is converted to the typical floor lattice column, and Lift-slab machine is converted to typical floor construction state (Fig. 9).
The scope of application of the present invention:
Be applicable to the core tube of high-rise building structure construction that contains stiffness girders layer section, or the structure construction of other analog structure forms.
Claims (2)
1. integrally hoisting steel platform and integrally traversing girders layer job practices is characterized in that concrete steps are:
(1) core tube construction concrete segmentation to girders layer, and steel truss is installed and is provided with interim stable to support;
(2) lattice column, Lift-slab machine carriage and the Lift-slab machine that girders layer is used was installed, the spreading screw mandrel is hung the platform girder steel;
(3) remove the landing beam parts of colliding, promote steel platform to each segmentation and stop a layer absolute altitude, then landing beam is resetted and fixing steel platform with truss, and the reinforcing bar of a vertical section layer of colligation, large form and fluid concrete promoted;
(4) repeat third step to passing through girders layer;
(5) enter the conventional criteria construction process.
2. the integrally hoisting steel platform and integrally traversing girders layer job practices that goes up according to claim 1, it is characterized in that, after above-mentioned the 4th step, before entering the conventional criteria construction process, lattice column is converted to the typical floor lattice column, and Lift-slab machine is converted to typical floor construction state.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNA2008100401711A CN101333869A (en) | 2008-07-03 | 2008-07-03 | Construction method for integrally hoisting steel platform and integrally traversing girders layer |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNA2008100401711A CN101333869A (en) | 2008-07-03 | 2008-07-03 | Construction method for integrally hoisting steel platform and integrally traversing girders layer |
Publications (1)
Publication Number | Publication Date |
---|---|
CN101333869A true CN101333869A (en) | 2008-12-31 |
Family
ID=40196710
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CNA2008100401711A Pending CN101333869A (en) | 2008-07-03 | 2008-07-03 | Construction method for integrally hoisting steel platform and integrally traversing girders layer |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101333869A (en) |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101838986A (en) * | 2009-03-17 | 2010-09-22 | 上海市机械施工有限公司 | Disassembling tool type lattice column and construction method thereof |
CN101906820A (en) * | 2010-07-29 | 2010-12-08 | 中建三局建设工程股份有限公司 | System capable of constructing in vertical structure and horizontal structure simultaneously in core tube |
CN102454294A (en) * | 2010-10-18 | 2012-05-16 | 五冶集团上海有限公司 | Construction method of reinforced concrete and steel structure storage bin combined frame structure |
CN103291076A (en) * | 2013-07-03 | 2013-09-11 | 江苏南通六建建设集团有限公司 | Multilayer steel truss fragmented reverse hoisting construction method in arc-shaped frame |
CN106013450A (en) * | 2016-07-14 | 2016-10-12 | 中国建筑第八工程局有限公司 | Core tube skip-floor construction method |
CN106337563A (en) * | 2016-09-12 | 2017-01-18 | 天津城建大学 | Lifting device with spatial truss structure |
CN107630510A (en) * | 2017-09-28 | 2018-01-26 | 中国建筑第八工程局有限公司 | High-rise building Core Walls Structure shear wall construction form frame system is revealed all the details platform stop layers construction method |
CN108442530A (en) * | 2018-04-17 | 2018-08-24 | 中冶天工集团天津有限公司 | A kind of frame or cylinder load-bearing high level modular architectural construction method and structure |
-
2008
- 2008-07-03 CN CNA2008100401711A patent/CN101333869A/en active Pending
Cited By (14)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101838986A (en) * | 2009-03-17 | 2010-09-22 | 上海市机械施工有限公司 | Disassembling tool type lattice column and construction method thereof |
CN101838986B (en) * | 2009-03-17 | 2014-03-12 | 上海市机械施工有限公司 | Disassembling tool type lattice column and construction method thereof |
CN101906820A (en) * | 2010-07-29 | 2010-12-08 | 中建三局建设工程股份有限公司 | System capable of constructing in vertical structure and horizontal structure simultaneously in core tube |
CN101906820B (en) * | 2010-07-29 | 2013-12-04 | 中建三局建设工程股份有限公司 | System capable of constructing in vertical structure and horizontal structure simultaneously in core tube |
CN102454294B (en) * | 2010-10-18 | 2015-08-12 | 五冶集团上海有限公司 | Steel concrete and steel structure storage bin combined frame structure construction method |
CN102454294A (en) * | 2010-10-18 | 2012-05-16 | 五冶集团上海有限公司 | Construction method of reinforced concrete and steel structure storage bin combined frame structure |
CN103291076A (en) * | 2013-07-03 | 2013-09-11 | 江苏南通六建建设集团有限公司 | Multilayer steel truss fragmented reverse hoisting construction method in arc-shaped frame |
CN106013450A (en) * | 2016-07-14 | 2016-10-12 | 中国建筑第八工程局有限公司 | Core tube skip-floor construction method |
CN106013450B (en) * | 2016-07-14 | 2019-05-10 | 中国建筑第八工程局有限公司 | Core Walls Structure skip floor construction method |
CN106337563A (en) * | 2016-09-12 | 2017-01-18 | 天津城建大学 | Lifting device with spatial truss structure |
CN106337563B (en) * | 2016-09-12 | 2018-05-25 | 天津城建大学 | A kind of lifting device of space grid structure |
CN107630510A (en) * | 2017-09-28 | 2018-01-26 | 中国建筑第八工程局有限公司 | High-rise building Core Walls Structure shear wall construction form frame system is revealed all the details platform stop layers construction method |
CN107630510B (en) * | 2017-09-28 | 2019-07-30 | 中国建筑第八工程局有限公司 | Super high-rise building Core Walls Structure shear wall construction form frame system is revealed all the details platform stop layers construction method |
CN108442530A (en) * | 2018-04-17 | 2018-08-24 | 中冶天工集团天津有限公司 | A kind of frame or cylinder load-bearing high level modular architectural construction method and structure |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101333869A (en) | Construction method for integrally hoisting steel platform and integrally traversing girders layer | |
CN106437130A (en) | Inner roof external climbing type formwork construction platform for super high-rise building construction | |
CN102704676A (en) | Jacking formwork mechanism | |
CN102154990B (en) | Electing method for side span overhang-middle span cable-stayed three-tower self-anchored type combination suspension bridge | |
CN103938875A (en) | Ground single body tensioning lifting construction method of single layer suspendome | |
CN103485574B (en) | A kind of granulation tower tower top structure of reinforced concrete method | |
CN106436573A (en) | Construction method of bracket steel truss support of long-span upper beam of ultrahigh cable tower | |
CN103806639A (en) | Steel tube truss support system for silo top and construction method of steel tube truss support system | |
CN109138454A (en) | A kind of installation method of super high-rise building outline border bandy truss | |
CN202544854U (en) | Lining trolley for subway station | |
CN101294443A (en) | High altitude platform mounting method | |
CN205348727U (en) | A promote formula operation platform for in shaft | |
CN103615111A (en) | Silo top construction method | |
CN204781927U (en) | Elevartor shaft formwork and elevartor shaft concrete placement operation platform | |
CN103266799A (en) | Mast and installation technology thereof | |
CN202509754U (en) | High-altitude steel structure node construction working platform | |
CN106544959B (en) | The construction method of king-tower lifting segment and bridge main tower saddle containing saddle | |
CN101298796A (en) | Self-bearing type preprocessing component, self-bearing type preprocessing concrete structure and construction method thereof | |
CN103061514A (en) | Long-span steel structure corridor construction method | |
CN102691267A (en) | High pier construction method for external whole operation platform | |
CN203129580U (en) | Formwork system | |
CN201714056U (en) | Truss-type operating platform | |
CN202718385U (en) | Jack-raising formwork mechanism | |
CN105464215A (en) | Reverse construction method construction method of hanging structure incapable of being provided with vertical temporary support | |
CN205114897U (en) | That climbs formula braced system in tower built -in is put has bad luck device certainly |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C02 | Deemed withdrawal of patent application after publication (patent law 2001) | ||
WD01 | Invention patent application deemed withdrawn after publication |
Open date: 20081231 |