CN103061514A - Long-span steel structure corridor construction method - Google Patents

Long-span steel structure corridor construction method Download PDF

Info

Publication number
CN103061514A
CN103061514A CN2012104471122A CN201210447112A CN103061514A CN 103061514 A CN103061514 A CN 103061514A CN 2012104471122 A CN2012104471122 A CN 2012104471122A CN 201210447112 A CN201210447112 A CN 201210447112A CN 103061514 A CN103061514 A CN 103061514A
Authority
CN
China
Prior art keywords
steel
transverse horizontal
steel beams
span
girder steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2012104471122A
Other languages
Chinese (zh)
Other versions
CN103061514B (en
Inventor
寿建军
孙占利
郦挺
张升前
寿雪光
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ZHEJIANG BADA CONSTRUCTION GROUP CO Ltd
Original Assignee
ZHEJIANG BADA CONSTRUCTION GROUP CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZHEJIANG BADA CONSTRUCTION GROUP CO Ltd filed Critical ZHEJIANG BADA CONSTRUCTION GROUP CO Ltd
Priority to CN201210447112.2A priority Critical patent/CN103061514B/en
Publication of CN103061514A publication Critical patent/CN103061514A/en
Application granted granted Critical
Publication of CN103061514B publication Critical patent/CN103061514B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention provides a long-span steel structure corridor construction method. Support steel columns on two sides of a span are firstly installed, then transverse horizontal steel beams are hoisted, support steel beams and oblique support steel beams among the transverse horizontal steel beams are installed, a vertical horizontal steel beam and a striding horizontal draw rod are further installed between two transverse horizontal steel beams, and finally transverse steel beams required by construction are installed. The long-span steel structure corridor construction method is characterized in that auxiliary trusses are installed between the support steel beams after the support steel beams are installed, and the auxiliary trusses serve as hanging points to hoist the transverse horizontal steel beams and then dismantled after the support steel beams and the oblique support steel beams are further installed between the transverse horizontal steel beams. The long-span steel structure corridor construction method has the advantages of utilizing the auxiliary trusses to install the transverse horizontal steel beams with largest volume, adopting a spare part hoisting mode for an overall steel structure and reducing the field requirement of surrounding construction and the requirement for a crane.

Description

Large-span steel corridor construction method
Technical field
The present invention relates to a kind of Construction of Steel Structure method, particularly a kind of large-span steel corridor construction method.
Background technology
Generally all be directly to lift by loop wheel machine behind the Assembling during high-altitude long-span multi-storey steel structure construction of the prior art, there is following shortcoming in this mode, and need to there be larger fabricating yard at the scene, just can finish installation.The loop wheel machine that uses on the other hand also needs to take huge place.So the communal facility that this form of construction work is not adapted in some uses is used on every side.
Summary of the invention
The objective of the invention is provides a kind of easy construction for the deficiency that solves above-mentioned technology, and it is few to take the construction plant, and uses loop wheel machine little, and mounted configuration is large-span steel corridor construction method firmly.
In order to achieve the above object, the large-span steel corridor construction method that the present invention is designed, the brace steel post of span both sides at first is installed, then lift the transverse horizontal girder steel, support steel beam and diagonal brace girder steel between the transverse horizontal girder steel then are installed, install again two between the transverse horizontal girder steel the vertical levels girder steel and stride girt, the horizontal girder steel that last installation needs, it is characterized in that after brace steel post is installed, first between two brace steel posts, auxiliary girder is installed, the lifting transverse horizontal girder steel take auxiliary girder as suspension centre is removed auxiliary girder after installing support steel beam between the transverse horizontal girder steel and diagonal brace girder steel again.The characteristics of this job practices are to utilize the transverse horizontal girder steel of auxiliary girder installation volume maximum, and whole steel work then adopts the loose mail lifting mode, have reduced the place needs of constructing on every side, have also reduced the requirement to loop wheel machine.
In order to improve the structural stability of the steel work that obtains after construction is finished, the elastic deformation that forms because of deadweight by calculating the high-altitude girder steel before the construction, when then installing during take auxiliary girder as suspension centre in when construction, adjust respectively the deformation of transverse horizontal girder steel according to result of calculation.Simultaneously described deformation according to result of calculation adjustment transverse horizontal girder steel is the position of adjusting the transverse horizontal girder steel by the pulling force cucurbit.This mode has been predicted the influence of crust deformation of girder steel when construction, directly provide pre-made allowance for girder steel deformation when construction, so that the total of constructing after finishing is stable.
The resulting large-span steel corridor construction of the present invention method, method by the loose mail lifting, and utilize and comparatively easy auxiliary girder is installed as suspension centre, the huge transverse horizontal girder steel of span is installed, and set in advance the surplus of girder steel deformation, so that in most of situation, there is horizontal connection to support between the brace steel post and exists, so that whole steel work just is under the more stable structural behavior, and finally finish whole construction when loose mail lifts.In addition, owing to can utilize auxiliary girder as suspension centre, reduce the difficulty of lifting, also created condition for adjusting in advance girder steel deformation surplus.In sum, the resulting large-span steel corridor construction of the present invention method has reasonable in design, and the construction plant is little, and speed is fast, and cost is low, and the characteristics of the steel work good stability that obtains of construction.
Description of drawings
Fig. 1 is front view of the present invention;
Fig. 2 is that the present invention uses the auxiliary girder structural representation;
Fig. 3 is that the present invention removes constructing structure schematic diagram behind the auxiliary girder.
The specific embodiment
The invention will be further described by reference to the accompanying drawings below by embodiment.
Embodiment 1:
As shown in the figure, the large-span steel corridor construction method that present embodiment is described as shown in Figure 1, is at first installed the brace steel post 1 of span both sides, and auxiliary girder 2 is installed between two brace steel posts 1.Then as shown in Figure 2,7 lifting transverse horizontal girder steels 3 are then installed support steel beam 8 and diagonal brace girder steel 4 between lower two transverse horizontal girder steels 3 take auxiliary girder 2 as suspension centre.Then as shown in Figure 3, remove auxiliary girder 2, install again two between the transverse horizontal girder steel 3 the vertical levels girder steel and stride girt, the horizontal girder steel 6 that last installation needs.
On the other hand, the elastic deformation that forms because of deadweight by calculating the high-altitude girder steel is when installing take auxiliary girder 2 as suspension centre, respectively according to the position of result of calculation by pulling force cucurbit adjustment transverse horizontal girder steel 3, to adjust the deformation of transverse horizontal girder steel 3.

Claims (3)

1. large-span steel corridor construction method, the brace steel post of span both sides at first is installed, then lift the transverse horizontal girder steel, support steel beam and diagonal brace girder steel between the transverse horizontal girder steel then are installed, install again two between the transverse horizontal girder steel the vertical levels girder steel and stride girt, the horizontal girder steel that last installation needs, it is characterized in that after brace steel post is installed, first between two brace steel posts, auxiliary girder is installed, the lifting transverse horizontal girder steel take auxiliary girder as suspension centre is removed auxiliary girder after installing support steel beam between the transverse horizontal girder steel and diagonal brace girder steel again.
2. large-span steel corridor construction method according to claim 1, it is characterized in that by calculating the high-altitude girder steel because of the elastic deformation of deadweight formation, then when installing take auxiliary girder as suspension centre, adjust respectively the deformation of transverse horizontal girder steel according to result of calculation.
3. large-span steel corridor construction method according to claim 2 is characterized in that described deformation according to result of calculation adjustment transverse horizontal girder steel, is the position of adjusting the transverse horizontal girder steel by the pulling force cucurbit.
CN201210447112.2A 2012-11-09 2012-11-09 Long-span steel structure corridor construction method Active CN103061514B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210447112.2A CN103061514B (en) 2012-11-09 2012-11-09 Long-span steel structure corridor construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210447112.2A CN103061514B (en) 2012-11-09 2012-11-09 Long-span steel structure corridor construction method

Publications (2)

Publication Number Publication Date
CN103061514A true CN103061514A (en) 2013-04-24
CN103061514B CN103061514B (en) 2015-12-02

Family

ID=48104376

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210447112.2A Active CN103061514B (en) 2012-11-09 2012-11-09 Long-span steel structure corridor construction method

Country Status (1)

Country Link
CN (1) CN103061514B (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103912128A (en) * 2014-02-28 2014-07-09 中国建筑第五工程局有限公司广州分公司 Construction method of high-altitude one-piece steel truss
CN105507600A (en) * 2016-01-27 2016-04-20 中国中铁航空港建设集团有限公司 Hoisting system and hoisting construction method for large steel corridor trusses
CN107012949A (en) * 2017-05-10 2017-08-04 中国建筑第二工程局有限公司 Lifting method of large-span steel corridor
CN110017024A (en) * 2019-04-22 2019-07-16 上海建工一建集团有限公司 The construction method of the horizontal girder steel of contrary sequence method basement
CN110984589A (en) * 2019-11-29 2020-04-10 中国二十二冶集团有限公司 Method for mounting assembly platform of super-long steel beam high altitude

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04153460A (en) * 1990-10-17 1992-05-26 Mitsubishi Heavy Ind Ltd Constructing method for building, and its equipment
JPH0882100A (en) * 1994-09-08 1996-03-26 Takenaka Komuten Co Ltd Lift-up method for constructing catwalk
CN101033636A (en) * 2007-03-23 2007-09-12 北京城建集团有限责任公司 Large span bidirectional string stretching girders rope accumulation slippage construction method
CN101446135A (en) * 2008-12-25 2009-06-03 上海市第一建筑有限公司 Integral hoisting system for superaltitude overlong jumbo beam by truss method and construction method thereof

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04153460A (en) * 1990-10-17 1992-05-26 Mitsubishi Heavy Ind Ltd Constructing method for building, and its equipment
JPH0882100A (en) * 1994-09-08 1996-03-26 Takenaka Komuten Co Ltd Lift-up method for constructing catwalk
CN101033636A (en) * 2007-03-23 2007-09-12 北京城建集团有限责任公司 Large span bidirectional string stretching girders rope accumulation slippage construction method
CN101446135A (en) * 2008-12-25 2009-06-03 上海市第一建筑有限公司 Integral hoisting system for superaltitude overlong jumbo beam by truss method and construction method thereof

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103912128A (en) * 2014-02-28 2014-07-09 中国建筑第五工程局有限公司广州分公司 Construction method of high-altitude one-piece steel truss
CN105507600A (en) * 2016-01-27 2016-04-20 中国中铁航空港建设集团有限公司 Hoisting system and hoisting construction method for large steel corridor trusses
CN107012949A (en) * 2017-05-10 2017-08-04 中国建筑第二工程局有限公司 Lifting method of large-span steel corridor
CN107012949B (en) * 2017-05-10 2019-06-07 中国建筑第二工程局有限公司 Lifting method of large-span steel corridor
CN110017024A (en) * 2019-04-22 2019-07-16 上海建工一建集团有限公司 The construction method of the horizontal girder steel of contrary sequence method basement
CN110984589A (en) * 2019-11-29 2020-04-10 中国二十二冶集团有限公司 Method for mounting assembly platform of super-long steel beam high altitude

Also Published As

Publication number Publication date
CN103061514B (en) 2015-12-02

Similar Documents

Publication Publication Date Title
CN204940886U (en) A kind of mechanism of handling vestibule
CN108560719A (en) The support installation method of super large span double-layer Bidirectional hanging rope structure
CN203462764U (en) Large cantilever promotion counter-force frame
CN103061514A (en) Long-span steel structure corridor construction method
CN203296361U (en) Long-span steel structure cross assembling hoisting platform
CN108049666B (en) A kind of echelon installation method of super plane multilayer steel truss electronic workshop steel construction
CN105256933B (en) A kind of construction method of system of folding house roof bascule
CN102777037B (en) Simple and practical hoisting construction method of long-span steel girder
CN104989111B (en) Steel construction high level construction method for hanging
CN201144515Y (en) Steel structure high altitude construction platform
CN101333869A (en) Construction method for integrally hoisting steel platform and integrally traversing girders layer
CN103669882A (en) Method for conducting component installation with steel wire ropes serving as rails in industrial factory building
CN104775363A (en) Assembling method of upper tower column reinforcing steel bar segment
CN204126297U (en) A kind of temporary support of steel truss roof
CN202899639U (en) Concrete column structure
CN102259794B (en) Method for installing overall combined type crane beam
CN105625732A (en) Supporting-free construction method of ultrahigh overhung steel-structure truss
CN201817201U (en) Trolley slippage construction device
CN105162033A (en) Mechanized self-lifting portal crossing frame
CN205575534U (en) Lattice formula groined type support body lifting means
CN105220609B (en) Combined beam self-anchored suspension bridge and construction process thereof
CN204754150U (en) Dish -type node formula scaffold
CN102733612B (en) Mounting method of electric hoist orbit
CN204174848U (en) A kind of precast reinforced skeleton of sets of brackets on top of the columns of building in the style of the ancients
CN208122299U (en) A kind of concrete of crossing soars aloft beam from climbing monoblock type tub system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
PP01 Preservation of patent right

Effective date of registration: 20161103

Granted publication date: 20151202

RINS Preservation of patent right or utility model and its discharge
PD01 Discharge of preservation of patent
PD01 Discharge of preservation of patent

Date of cancellation: 20170503

Granted publication date: 20151202

PP01 Preservation of patent right
PP01 Preservation of patent right

Effective date of registration: 20191031

Granted publication date: 20151202

PD01 Discharge of preservation of patent
PD01 Discharge of preservation of patent

Date of cancellation: 20221031

Granted publication date: 20151202