JPH04153460A - Constructing method for building, and its equipment - Google Patents

Constructing method for building, and its equipment

Info

Publication number
JPH04153460A
JPH04153460A JP27846590A JP27846590A JPH04153460A JP H04153460 A JPH04153460 A JP H04153460A JP 27846590 A JP27846590 A JP 27846590A JP 27846590 A JP27846590 A JP 27846590A JP H04153460 A JPH04153460 A JP H04153460A
Authority
JP
Japan
Prior art keywords
columns
beams
composite
column
combined
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP27846590A
Other languages
Japanese (ja)
Other versions
JP2916591B2 (en
Inventor
Takeji Matsumoto
松本 竹二
Hiroki Muramoto
村本 広毅
Yoshinori Mukoya
向谷 美徳
Yoichi Seki
洋一 関
Yoji Moroi
陽児 諸井
Masaaki Nakanishi
正明 中西
Koji Kondo
弘司 近藤
Junichiro Maeda
純一郎 前田
Shigeki Otsuka
大塚 成喜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Mitsubishi Heavy Industries Ltd
Shimizu Corp
Original Assignee
Shimizu Construction Co Ltd
Mitsubishi Heavy Industries Ltd
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Mitsubishi Heavy Industries Ltd, Shimizu Corp filed Critical Shimizu Construction Co Ltd
Priority to JP27846590A priority Critical patent/JP2916591B2/en
Publication of JPH04153460A publication Critical patent/JPH04153460A/en
Application granted granted Critical
Publication of JP2916591B2 publication Critical patent/JP2916591B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

PURPOSE:To enable work to be easily executed with safety by jointing columns and beams to each other between respective combined beams, after combined columns have been previously constructed, and the combined beams have been lifted up in a state that the space of component for a plurality of floors is set along the combined columns. CONSTITUTION:After main beams 2a and temporarily-set braces 2b are inserted into four columns 4 on the ground and combined columns 5 are assembled, they are lifted with tower cranes 10. Besides, on the ground, the beams 3 of component for two floors are connected to each other set by set, and combined beams 7 are assembled, and into spaces between the beams 3, main columns 4a and braces 4b are inserted. Then, in order from the lower side combined- beams 7, they are jointed to the combined columns 5 at specified level positions. Besides, by using hoists 16 to be moved along horizontally carrying means 18 at the lower ends of the combined beams 7, layer main-columns 8 and main- beams 9 are erected.

Description

【発明の詳細な説明】 [産業−にの利用分野j 本発明は、建築物の躯体を構築する際に用いて好適な建
築物の施工方法及びその装置に関する。
DETAILED DESCRIPTION OF THE INVENTION [Field of Application in Industry] The present invention relates to a building construction method and apparatus suitable for use in constructing a building frame.

「従来の技術及びその課題」 従来、建築物の躯体を構築する際、柱を構築した後に、
下方から順次梁を組み立てることとしていた。
"Conventional technology and its problems" Conventionally, when constructing the frame of a building, after constructing the pillars,
The plan was to assemble the beams sequentially from the bottom.

したがって、下方を行うのは最上階に限られており、こ
のため、階数が増えろと下方も階数分繰り返すこととな
り、高層になると工期がかかっていた。
Therefore, the work on the lower part was limited to the top floor, and for this reason, if the number of floors was to increase, the work on the lower part had to be repeated for the number of floors, which increased the construction period for higher floors.

また、先行施工した−1−階の柱に下階の柱を建込む際
には、クレーンとウィンチとを組み合わせて柱を横引き
にして入れていたり、バランス治具を用いて吊込むこと
としていた。
In addition, when erecting columns on the lower floor onto the columns on the first floor that were previously constructed, the columns are pulled horizontally using a combination of a crane and a winch, or they are suspended using a balance jig. there was.

このため、前者の場合は作業に熟柿を要ずろとともに、
柱の安全な吊方ではないので、危険作業となっており、
後者の場合は、特別の治具を必要とし、かつバランス治
具の重心位置と柱の重心位置が平面上でずれるので、柱
をバランス治具から外すと柱にアンバランスを生じて作
業か複連とナー、ていた。
For this reason, in the former case, along with the need for ripe persimmons,
This is dangerous work as it is not a safe way to hang the pillar.
In the latter case, a special jig is required, and the center of gravity of the balance jig and the center of gravity of the column are shifted on the plane, so if the column is removed from the balance jig, the column will become unbalanced and the work will be complicated. Ren and Na were there.

さらに、柱や梁をタワークレーン等の揚重手段によって
下から順次積み」−げるように組み立てるようにして作
業を行っていたため、次のような問題があった。すなわ
ち、同時に1−下方向に複数の層間で下方を行うため、
タワークレーンては下層において部材を組み立て位置に
移動することができないこと、ならびに、トロリーホイ
スト搬送に使う場合にも垂直揚重後に玉掛(Jをやり直
す必要があったことである。
Furthermore, since the columns and beams were assembled by being stacked one by one from the bottom using lifting means such as a tower crane, the following problems occurred. That is, to simultaneously perform the downward movement between multiple layers,
Tower cranes cannot move members to the assembly position on the lower level, and even when used for trolley hoist transportation, it is necessary to redo the slinging (J) after vertical lifting.

本発明は、前記事情に鑑みてなされたものであって、複
数層において同時に下方を行うことができるとともに、
作業者に危険を及ぼすことなく安全かつ容易に行うこと
のできる建築物の施工方法及びその装置を提供すること
を14的としている。
The present invention has been made in view of the above-mentioned circumstances, and is capable of simultaneously performing lowering on multiple layers, and
Its 14th purpose is to provide a method and apparatus for constructing a building that can be carried out safely and easily without posing danger to workers.

「課題を解決するための手段」 本発明に係る建築物の施工方法は、複数本の柱を連結し
て複合柱を組み立て、複数本の梁を連結して複合梁を組
み立て、前記複合柱を先行して構築し、当該複合柱に沿
って複数階分の間隔をあけた状態で前記複合梁をリフト
アップし、この後、各複合梁の間に柱、梁を接合するこ
とを特徴としている。
"Means for Solving the Problems" A method for constructing a building according to the present invention includes connecting a plurality of columns to assemble a composite column, connecting a plurality of beams to assemble a composite beam, and assembling the composite column. The method is characterized in that the composite beams are constructed in advance, the composite beams are lifted up along the composite columns at intervals of multiple stories, and then the columns and beams are joined between each composite beam. .

また、本発明に係る建築物の施工方法は、先行施工され
た上階の柱の下方に下階の柱を建込むにあたり、予め複
数本の柱が接合された梁からなる柱梁ユニットを設け、
この柱梁ユニットを前記下階部分に搬送し、当該柱梁ユ
ニットの柱と前記上階の柱とを一致させた状態で接合す
ることとしてもよい。
Furthermore, in the construction method of a building according to the present invention, when erecting a lower floor column below a previously constructed upper floor column, a column-beam unit consisting of a beam in which a plurality of columns are joined is installed in advance. ,
This column-beam unit may be transported to the lower floor portion, and the columns of the column-beam unit and the columns of the upper floor may be aligned and joined.

さらに、本発明に係る建築物の施工装置は、複数本の柱
が連結部材によって連結された複合柱と、複数本の梁が
連結部材によって連結された複合梁とを用いて建築物を
施工するにあたり、部材を保持する部材保持装置と、こ
の部材保持装置を水平搬送する水平搬送手段が前記複合
梁に設(」られ、前記部材保持装置を垂直搬送する垂直
搬送手段が前記複合柱の上部位置に配置され、前記部+
4保持装置は前記水平搬送手段と垂直搬送手段とを相互
に移送自在に構成されているこ七を特徴としている。
Further, the building construction apparatus according to the present invention constructs a building using a composite column in which a plurality of columns are connected by a connecting member, and a composite beam in which a plurality of beams are connected by a connecting member. In this case, a member holding device for holding a member and a horizontal transporting means for horizontally transporting the member holding device are installed on the composite beam, and a vertical transporting means for vertically transporting the member holding device is installed at an upper position of the composite column. located in the above part +
4. The holding device is characterized in that the horizontal conveyance means and the vertical conveyance means are configured to be mutually transferable.

1作用」 本発明に係る建築物の施工方法及びその装置ては、建築
物の複数層の層間で下方作業を同時に行うことができる
1. The method and apparatus for constructing a building according to the present invention can simultaneously perform downward work between multiple layers of a building.

「実施例」 以下、本発明の一実施例について図面を参照して説明す
る。
"Embodiment" An embodiment of the present invention will be described below with reference to the drawings.

第1図ないし第5図中、符号1は建築物の躯体を構成す
る柱、符号3は柱1と同様に建築物の躯体を構成する梁
を示している。
In FIGS. 1 to 5, the reference numeral 1 indicates a column that constitutes the frame of the building, and the reference numeral 3 indicates a beam that constitutes the frame of the building similarly to the column 1.

柱lは、複数本が互いに離間された状態で本設梁2a(
連結部材)及び仮設のプレース2bによって連結されて
複合柱5を構成している。
A plurality of columns l are spaced apart from each other, and the main beam 2a (
connecting member) and a temporary place 2b to form a composite column 5.

梁3は、複数本が互いに離間された状態で本設柱4a(
連結部材)及び仮設のプレース4bによって連結されて
複合梁7を構成している。この複合梁7は、各数層間鉄
骨を除いた状態で鉄骨の下方が行なわれる。
A plurality of beams 3 are installed at a main column 4a (
connecting member) and a temporary place 4b to form a composite beam 7. This composite beam 7 is constructed under the steel frame with the steel frames between several layers removed.

複合柱5の上部には、タワークレーン10(揚重機)が
設置されている。このタワークレーンIOから垂下され
たワイヤー12の下端部には、鉤状のフック部材14が
取り付けられている。このフック部材】4には、複合柱
5等の建築部材や、ホイスト16(部材保持装置)が係
止されて使用に供される。
A tower crane 10 (lifting machine) is installed at the top of the composite column 5. A hook-shaped hook member 14 is attached to the lower end of the wire 12 hanging from the tower crane IO. A building member such as a composite column 5 or a hoist 16 (member holding device) is secured to the hook member 4 for use.

ホイスト16は、柱、梁等の建築部材Uを支持するもの
であって、第4図に示すように、タワークレーン10か
ら複合梁7の下面に設けられた水平搬送手段+8(後述
する)へ七乗り入れ自在に構成されている。このホイス
ト16は、第5図に示すように、建築部材(例えば本設
梁9)を玉掛(Jする玉掛は部+6aと、水平搬送手段
18に係合して自走する自走部+6bと、前記フック部
4A’ + 4に係止する係止部16cとを備えた構成
どなっている。
The hoist 16 supports the construction members U such as columns and beams, and as shown in FIG. It is configured so that seven people can enter it freely. As shown in FIG. 5, this hoist 16 has a sling part +6a for slinging building members (for example, the main beam 9), and a self-propelled part +6b that engages with the horizontal conveying means 18 and moves by itself. , and a locking portion 16c that locks onto the hook portion 4A'+4.

水平搬送手段I8は、複合梁7の下面に設(Jられた案
内軌道であって、前記自走部+6bを係合支持可能なよ
うに下面に開]」する開口溝(図示路)が形成されてい
る。
The horizontal conveyance means I8 is formed with an opening groove (path shown) provided on the lower surface of the composite beam 7. has been done.

そして、ホイスト16は、前記タワークレーン10から
垂下されたフック部材14に係止部16Cを係止した状
態で垂直搬送され、所定高ざにおいて自走部+6bを前
記水平搬送手段■8に載置するとともにフック部材14
との係合を解く。この後、自走部+6bを作動させて水
平搬送手段18に沿って自走し、所定位置に本設柱8、
本設梁9等の建築部材を搬送することができる。
Then, the hoist 16 is vertically transported with the locking portion 16C locked to the hook member 14 hanging down from the tower crane 10, and the self-propelled portion +6b is placed on the horizontal transport means 8 at a predetermined height. At the same time, the hook member 14
disengage with. After that, the self-propelled part +6b is activated to self-propel along the horizontal conveyance means 18, and the main pillar 8,
Architectural components such as the main beam 9 can be transported.

次に、本実施例による建築物の施工方法について、第1
図及び第2図を参照して説明する。
Next, regarding the construction method of the building according to this example, the first
This will be explained with reference to the drawings and FIG.

)複合柱5の下方 地」−において4本の柱1に本設梁2a及び仮設のプレ
ース211を入れて複合柱5を組み立てた後、大型タワ
ークレーン10によって揚重を行う。
) After assembling the composite column 5 by inserting the permanent beams 2a and temporary places 211 into the four columns 1 at the lower part of the composite column 5, the large tower crane 10 lifts it.

建築物の4隅に前記複合柱5を配置ケる。The composite columns 5 are arranged at the four corners of the building.

)複合梁7の下方 地−Lにおいて2階分の梁3を1組づつで連結して複合
梁7を組み立てる。このとき、粱3.3の」1下間には
、本設柱4aを入れ、剪断ツノの大きさに応じて本設ま
たは仮設のプレース41)を入れる。
) The composite beam 7 is assembled by connecting the beams 3 for two floors one set at a time at the lower part -L of the composite beam 7. At this time, a permanent pillar 4a is inserted between the bottom part of 3.3 and a permanent or temporary place 41) is inserted depending on the size of the shearing horn.

さらに、梁3に作用する荷重による梁3の変形を防止す
るために、PS鋼線(図示路)と油圧ジヤツキ(図示路
)をnij記複合柱5にセットして、リフトアップした
後に次の複合梁7を組み立てる。
Furthermore, in order to prevent deformation of the beam 3 due to the load acting on the beam 3, a PS steel wire (path shown) and a hydraulic jack (path shown) are set on the composite column 5, and after lifting it up, the next Assemble the composite beam 7.

複合梁7を4組組み終わった後、下方の複合梁7から順
次所定の高さ位置にて複合柱5と接合する。
After assembling four sets of composite beams 7, the composite beams 7 are sequentially joined to the composite columns 5 at predetermined height positions starting from the lower composite beam 7.

11)層間鉄骨下方 複合梁7の下方が終rしたものから順次複合梁7下端の
水平搬送手段18に沿って移動するポイスト16を使用
して層間の本設柱8、本設梁9の下方を行う。
11) Lower inter-story steel frame The lower part of the composite beam 7 is moved sequentially from the lower part of the composite beam 7 along the horizontal conveying means 18 at the lower end using the point 16 to install the lower part of the main pillar 8 and the main beam 9 between the stories. I do.

層間鉄骨の重量は、複合梁7を通して複合柱5に伝達さ
れる。
The weight of the interstory steel frame is transferred to the composite column 5 through the composite beam 7.

荷重による複合梁7のたわみ変形を上むくりになるよう
にプレストレスをt−jえ、緊張力を、−Jr、+整4
′ることにより鉄骨の接合時の有害な変形を防く。
Set the prestress t-j so that the deflection deformation of the composite beam 7 due to the load is upward, and set the tension force to -Jr, +4
This prevents harmful deformation when joining steel frames.

最終の本設柱8を入れることにより、複合梁7で受けて
いた荷重が本設柱8、Iを通じて地盤に伝達できるよう
になる。
By inserting the final permanent column 8, the load received by the composite beam 7 can be transmitted to the ground through the permanent column 8, I.

iv)仮設材撤去 層間鉄骨の最終の本設柱8を組み立てた後、複合梁7の
プレストレスを解除して、仮設のプレース2 b、4b
を撤去する。これらの撤去後に床のコンクリート打設を
開始することにより、複合梁7の仮設使用時の負担荷重
を少なくすることかできる。
iv) Removal of temporary materials After assembling the final permanent pillar 8 of the interstory steel frame, the prestress of the composite beam 7 is released and the temporary places 2b and 4b are removed.
to be removed. By starting concrete pouring for the floor after these are removed, the load borne by the composite beam 7 during temporary use can be reduced.

本実施例によれば、各複合梁7の層間にお〔jろ本設柱
8、本設梁9の接合作業を複層において同時に進行する
ことができるので工期の短縮を図ることができる。
According to this embodiment, the work of joining the main columns 8 and main beams 9 between the layers of each composite beam 7 can be performed simultaneously in multiple layers, so that the construction period can be shortened.

また、各層間における本設柱8及び本設梁9をホイスト
16で支持するとともにタワークレーンIOと水平搬送
手段I8とで所定位置に搬送することができるので、安
全確実に建築部材の搬送作業を行うことができる。
In addition, the main pillars 8 and beams 9 between each floor can be supported by the hoist 16 and transported to a predetermined position by the tower crane IO and the horizontal transport means I8, so the work of transporting construction components can be carried out safely and reliably. It can be carried out.

次に、本発明の他の実施例について説明する。Next, other embodiments of the present invention will be described.

本実施例は、−ヒ階の柱の下方に下階の柱及び梁を建込
む際に用いて好適な方法である。
This embodiment is a method suitable for use when building columns and beams on the lower floor below the columns on the first floor.

まず、第6図に示すように、1本の梁20の両端部に2
本の柱22.22を接合して柱梁ユニット24を組み立
てる。この柱梁ユニット24は左右対称とされているた
め重心が中心位置にくる。
First, as shown in FIG.
The pillars 22 and 22 are joined to assemble the pillar and beam unit 24. Since the column and beam unit 24 is symmetrical, the center of gravity is located at the center.

前記水平搬送手段I8に配置されたホイスl−16で、
この柱梁ユニット24を吊り下げ支持する。
A whistle l-16 disposed on the horizontal conveyance means I8,
This column and beam unit 24 is suspended and supported.

一方、先行施工された本設柱8.8の間隔を、建込む柱
22.22の長さよりも長くなるように仮受はザボート
部拐26で支持する。
On the other hand, the temporary support is supported by the boat support 26 so that the interval between the previously constructed main columns 8.8 is longer than the length of the columns 22.22 to be erected.

柱梁ユニット24の中心位置においてホイスト16で吊
ることによって、柱22.22を垂直に保持することが
できる。
The columns 22.22 can be held vertically by hanging them with hoists 16 at the center of the column and beam units 24.

ホイスト16を水平搬送手段18に沿って移動させ、所
定位置まで柱梁ユニット24を搬送する。
The hoist 16 is moved along the horizontal transport means 18 to transport the column and beam unit 24 to a predetermined position.

前記仮受はザボー上部材26の長さを調整して、先行施
工された本設柱8.8の間隔を正規の位置にする。
The temporary support adjusts the length of the upper support member 26 to set the interval between the previously constructed main pillars 8.8 to the regular position.

この上うな柱梁ユニット24を用いて建築物の施工を行
う場合、第7図に示すように、他の建築部材Uと同様に
タワークレーン10で揚重し、所定階数においてホイス
ト16を水平搬送手段18に移送することにより所定位
置において柱梁ユニット24の接合作業を行う。
When constructing a building using this upper pillar and beam unit 24, as shown in FIG. By transferring it to the means 18, the beam and column units 24 are joined at a predetermined position.

本実施例によれば、先行施工した1−階の本設柱8の下
方に下階の柱を建込む際に、柱梁ユニッ1へ24をタワ
ークレーンIO1水平搬送手段18によって安全に搬送
した後に作業を行うので、作業に熟練を要することなく
通常の建込み作業と同様に容易に行うことができる。
According to this embodiment, when the pillars on the lower floor were erected below the main pillars 8 on the first floor that had been constructed in advance, the columns 24 were safely transported to the column and beam unit 1 by the horizontal transport means 18 of the tower crane IO1. Since the work is carried out later, the work can be easily carried out in the same way as normal construction work without requiring any skill.

さらに、柱梁ユニット24が左右対称に組み立てられて
いるので、ホイスト16で吊りI、げろ際に何等特別な
バランス治具を必要としなくても容易にバランスをとる
ことかでき、作業の安全性を向トさせろごとができる。
Furthermore, since the column and beam units 24 are assembled symmetrically, they can be easily balanced without the need for any special balancing jig when hoisting I and gating with the hoist 16, which improves work safety. I can do things by directing people.

「発明の効果」 本発明に係る建築物の施−■一方法及びその装置によれ
ば、各複合梁の層間にお(」る柱、粱の接合作業を複層
において同時に進行することができるので工期の短縮を
図ることかできる。
"Effects of the Invention" According to the method and device for constructing a building according to the present invention, it is possible to simultaneously perform the work of joining columns and beams located between the layers of each composite beam in multiple layers. Therefore, it is possible to shorten the construction period.

また、各層間における柱及び梁を部材保持装置で支持す
るとともに垂直搬送手段と水平搬送手段とで所定位置に
搬送することができるので、安全確実に建築部材の搬送
作業を行うことができる。
Further, since the pillars and beams between each layer can be supported by the member holding device and transported to a predetermined position by the vertical transport means and the horizontal transport means, the work of transporting the building members can be carried out safely and reliably.

先行施工した−1−階の本設柱の下方に下階の柱を建込
む際に、柱梁ユニットを垂直搬送手段及び水平搬送手段
によって安全に搬送した後に作業を行うので、作業に熟
練を要することなく通常の建込み作業と同様に容易に行
うことができる。
When erecting the pillars on the lower floor below the main pillars on the -1st floor that were previously constructed, the work is carried out after the column and beam units have been safely transported by vertical and horizontal transport means, so it is necessary to be skilled in the work. It can be easily performed in the same way as normal construction work without requiring any work.

さらに、柱梁ユニットを左右対称に組み立てることによ
り部材保持装置で吊り上げる際に何等特別なバランス治
具を必要としなくても容易にバランスをとることができ
、作業の安全性を同士さU−ることかできる。
Furthermore, by assembling the column and beam units symmetrically, the balance can be easily maintained without the need for any special balancing jig when lifting using the member holding device, which improves work safety. I can do it.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図ないし第5図は、本発明の一実施例を示す図であ
って、第1図及び第2図(」構築途中の躯体の正面図、
第3図及び第4図は同部分拡大図、第5図は部材保持装
置の斜視図、第6図は本発明の他の実施例を示す部分拡
大正面図、第7図は同全体正面図である。 1  ・   ・・ 3  ・・  ・ 5  ・・  ・ I O・・ ・ 柱、 梁、 複合柱、 複合梁、 タワ−クレーン0■直搬送手段) ホイスト(部材保持装置)、 水平搬送手段。 出顆人 三菱重上業株式会社 〆IIt水建設株式会月
1 to 5 are diagrams showing one embodiment of the present invention, and FIGS. 1 and 2 ("front view of a frame under construction,
3 and 4 are partially enlarged views, FIG. 5 is a perspective view of the member holding device, FIG. 6 is a partially enlarged front view showing another embodiment of the present invention, and FIG. 7 is an overall front view of the same. It is. 1... 3... Mitsubishi Heavy Industries Co., Ltd.〆IIt Water Construction Co., Ltd.

Claims (3)

【特許請求の範囲】[Claims] (1)複数本の柱を連結して複合柱を組み立て、複数本
の梁を連結して複合梁を組み立て、前記複合柱を先行し
て構築し、当該複合柱に沿って複数階分の間隔をあけた
状態で前記複合梁をリフトアップし、この後、各複合梁
の間に柱、梁を接合することを特徴とする建築物の施工
方法。
(1) Assembling a composite column by connecting multiple columns, assembling a composite beam by connecting multiple beams, constructing the composite column in advance, and spacing multiple stories along the composite column. A construction method for a building, characterized in that the composite beams are lifted up with the openings opened, and then columns and beams are joined between each composite beam.
(2)先行施工された上階の柱の下方に下階の柱を建込
むにあたり、予め複数本の柱が接合された梁からなる柱
梁ユニットを設け、この柱梁ユニットを前記下階部分に
搬送し、当該柱梁ユニットの柱と前記上階の柱とを一致
させた状態で接合することを特徴とする請求項1記載の
建築物の施工方法。
(2) When erecting the lower floor columns below the previously constructed upper floor columns, a column-beam unit consisting of a beam made by joining multiple columns is installed in advance, and this column-beam unit is attached to the lower floor. 2. The method of constructing a building according to claim 1, wherein the pillars of the pillar-and-beam unit are aligned with the pillars of the upper floor and then joined.
(3)複数本の柱が連結部材によって連結された複合柱
と、複数本の梁が連結部材によって連結された複合梁と
を用いて建築物を施工するにあたり、部材を保持する部
材保持装置と、この部材保持装置を水平搬送する水平搬
送手段が前記複合梁に設けられ、前記部材保持装置を垂
直搬送する垂直搬送手段が前記複合柱の上部位置に配置
され、前記部材保持装置は前記水平搬送手段と垂直搬送
手段とを相互に移送自在に構成されていることを特徴と
する建築物の施工装置。
(3) When constructing a building using a composite column in which multiple columns are connected by a connecting member and a composite beam in which multiple beams are connected by a connecting member, a member holding device that holds the members is provided. , a horizontal conveying means for horizontally conveying the member holding device is provided on the composite beam, a vertical conveying means for vertically conveying the member holding device is disposed at an upper position of the composite column, and the member holding device is provided on the horizontal conveying device. A building construction device characterized in that the means and the vertical conveying means are configured to be mutually transferable.
JP27846590A 1990-10-17 1990-10-17 Building construction method and device Expired - Fee Related JP2916591B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP27846590A JP2916591B2 (en) 1990-10-17 1990-10-17 Building construction method and device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP27846590A JP2916591B2 (en) 1990-10-17 1990-10-17 Building construction method and device

Publications (2)

Publication Number Publication Date
JPH04153460A true JPH04153460A (en) 1992-05-26
JP2916591B2 JP2916591B2 (en) 1999-07-05

Family

ID=17597710

Family Applications (1)

Application Number Title Priority Date Filing Date
JP27846590A Expired - Fee Related JP2916591B2 (en) 1990-10-17 1990-10-17 Building construction method and device

Country Status (1)

Country Link
JP (1) JP2916591B2 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08270081A (en) * 1995-04-04 1996-10-15 Shimizu Corp Construction method of frame structure
JPH10205429A (en) * 1997-01-27 1998-08-04 Nkk Corp Construction method for wind power generator
CN103061514A (en) * 2012-11-09 2013-04-24 浙江八达建设集团有限公司 Long-span steel structure corridor construction method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08270081A (en) * 1995-04-04 1996-10-15 Shimizu Corp Construction method of frame structure
JPH10205429A (en) * 1997-01-27 1998-08-04 Nkk Corp Construction method for wind power generator
CN103061514A (en) * 2012-11-09 2013-04-24 浙江八达建设集团有限公司 Long-span steel structure corridor construction method
CN103061514B (en) * 2012-11-09 2015-12-02 浙江八达建设集团有限公司 Long-span steel structure corridor construction method

Also Published As

Publication number Publication date
JP2916591B2 (en) 1999-07-05

Similar Documents

Publication Publication Date Title
JP7241154B2 (en) MOVEMENT SYSTEMS, METHODS FOR MOVEMENT OF ARTICLES, AND RELATED COMPONENTS
US2472843A (en) Material handling device
JP3579816B2 (en) Multipurpose stage for building frame
US20070096006A1 (en) Overhead beam assembly
JPH04153460A (en) Constructing method for building, and its equipment
JP3180203B2 (en) Material lifting assembly equipment used for construction of high-rise structures
JP2913216B2 (en) Building construction method
JPH05113026A (en) Temporary scaffold structure
JP3220397B2 (en) Elevating scaffold
JP5150313B2 (en) Three-dimensional parking device in void and its construction method
JP3841242B2 (en) Elevator parking elevating work table and construction method using it
KR100334121B1 (en) Workbench for quick assembly and installation method
JPH10140839A (en) Device for vertically hoisting form material and pipe support
JPH0681481A (en) Material hoisting/lowering equipment
US20210331900A1 (en) Roof-Mounted Building Access System
CN211712485U (en) A cantilever loop wheel machine for house decoration
JPH10167668A (en) Vertical and horizontal transporting device and its operation
JP2843042B2 (en) Steel framing unit scaffolding method
JPH0726727A (en) Building lifting device and construction using thereof
JP2000053375A (en) Vertical carrier system corresponding to slewing overhead crane
DE2600095A1 (en) Flat item hoisting equipment - has rope reeved over pulley on beam mounted in building top floor
JPH09302936A (en) Construction method of building
JPH07217230A (en) Hanging stair and erecting method thereof
JPH01158177A (en) Elevation type scaffold
JP2020063648A (en) Folding unit house

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees