JP2913216B2 - Building construction method - Google Patents

Building construction method

Info

Publication number
JP2913216B2
JP2913216B2 JP2687491A JP2687491A JP2913216B2 JP 2913216 B2 JP2913216 B2 JP 2913216B2 JP 2687491 A JP2687491 A JP 2687491A JP 2687491 A JP2687491 A JP 2687491A JP 2913216 B2 JP2913216 B2 JP 2913216B2
Authority
JP
Japan
Prior art keywords
building
floor
erection
erection structure
main
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP2687491A
Other languages
Japanese (ja)
Other versions
JPH059981A (en
Inventor
竹二 松本
広毅 村本
美徳 向谷
洋一 関
純一郎 前田
弘司 近藤
信博 奥山
愛和 阿部
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Mitsubishi Heavy Industries Ltd
Original Assignee
Shimizu Construction Co Ltd
Mitsubishi Heavy Industries Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Mitsubishi Heavy Industries Ltd filed Critical Shimizu Construction Co Ltd
Priority to JP2687491A priority Critical patent/JP2913216B2/en
Publication of JPH059981A publication Critical patent/JPH059981A/en
Application granted granted Critical
Publication of JP2913216B2 publication Critical patent/JP2913216B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】本発明は、ビルの建設方法、特に
高層ビルの建設に好適な建設方法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for building a building, and more particularly to a method suitable for building a high-rise building.

【0002】[0002]

【従来の技術】一般に高層ビルの建設は、クライミング
クレーンを使用して、柱、梁、床等の躯体部材を地上か
ら吊上げ、ビルを下層階から上層階へ順次積上げ建造す
る方法により行なわれてきた。またこのようなビルの建
設を風雨に左右されずに行なう方法としては、建設され
るビルの屋根付き最上階を油圧ジャッキで押上げなが
ら、その下側に部材を挿入する建設方法 (特開平2−7
0844号公報)等も提案されている。
2. Description of the Related Art Generally, construction of high-rise buildings is carried out by using a climbing crane to lift frame members such as pillars, beams and floors from the ground, and to build and build the buildings sequentially from a lower floor to an upper floor. Was. Further, as a method of constructing such a building without being affected by the weather, there is a construction method of inserting a member under the roof while pushing up the top floor with a hydraulic jack of the building to be constructed (Japanese Unexamined Patent Publication No. -7
No. 0844) has also been proposed.

【0003】[0003]

【発明が解決しようとする課題】しかしながら、上記従
来の方法は、いずれも地上から高所へビルの柱、梁、床
等の部材を順を追って運び上げたうえ、高所の作業階で
は一部材ずつ順々に積上げて接合を行なうため、部材の
運び上げ搬送に時間がかかり、作業時間および工期の短
縮が難しい問題がある。
However, in the above-mentioned conventional methods, the members such as pillars, beams, floors, etc. of the building are all carried in order from the ground to a high place. Since members are sequentially stacked and joined, it takes time to carry and convey the members, and there is a problem that it is difficult to shorten the working time and the construction period.

【0004】また、この高所作業階での作業の効率を高
めるために、大型の機械や設備を高所作業階に持ち上げ
て使用すると、工事完成時期には、建造階上でこれらの
機械設備が作業の邪魔となり、干渉を避ける手間が生じ
たり、狭いスペースの中ではこれら機械設備の解体撤去
が困難になるなどの問題もある。本発明は、このような
ビル建設に用いる装置と建設作業との無益な干渉をなく
すること、ならびにビル建設の工期を単縮することを目
的としたものである。
[0004] In order to increase the efficiency of work on the high-floor work floor, large machines and equipment are lifted to the high-floor work floor and used. However, there is a problem that it interferes with the work, and it takes time to avoid interference, and it becomes difficult to disassemble and remove these mechanical equipment in a narrow space. An object of the present invention is to eliminate useless interference between such equipment used for building construction and construction work, and to shorten the building construction period.

【0005】[0005]

【課題を解決するための手段】上記目的を達成するた
め、本発明に係わるビルの建設方法は、ビルの最上層一
階分の架設用構造体を形成し、この架設用構造体に、複
数の本設柱を個別に貫通させるガイドと、これらガイド
と接近して上記架設用構造体の層上部に立設された昇降
装置と、上記架設用構造体の屋上部に設けられたジブク
レーンと、上記架設用構造体の下面に付設された水平搬
送装置とをそれぞれ設け、上記ガイドを貫通して建付け
た上記本設柱に上記昇降装置を係合駆動して上記架設用
構造体をこれら本設柱沿いに上昇させ、上記昇降装置を
固定結合して上記本設柱に上記架設用構造体を支持した
うえ、ビル側部に接して地上から上記架設用構造体の側
部へ垂直搬送装置を延長し、この垂直搬送装置および上
記ジブクレーンを経由して部材を搬送することにより、
上記屋上部において上記本設柱を積上げ建造し、上記垂
直搬送装置および上記水平搬送装置を経由して部材を搬
送することにより上記架設用構造体の下方において他の
ビル躯体部を積上げ建造した後、再び上記昇降装置を駆
動させて上記架設用構造体を上昇させ、上記同様の工程
を繰返す構成となっており、上記架設用構造体下方にお
いてビル躯体部の積上げ建造を行うに際しては、あらか
じめ、上記架設用構造体の屋上梁の下面に水平走行可能
な昇降式足場装置を設けておき、この昇降式足場装置
を、建造階における部材の水平搬送時には、上記架設用
構造体内に上昇退避させる一方、建造階における部材の
位置合わせ時および接合作業時には、随時降下させて使
用することを特徴としている。
Means for Solving the Problems To achieve the above object,
Therefore, the construction method of the building according to the present invention
A erection structure for floors is formed, and the erection structure is
Guides that individually penetrate a number of main pillars, and these guides
Up and down on the upper layer of the erection structure
The device and a jibuku provided on the rooftop of the erection structure
Lane and horizontal transport attached to the underside of the erection structure
And a feeder, respectively, and penetrate the above guides and build
The elevating device is engaged with the main pillar to drive the
The structure is raised along these main pillars, and the elevating device is
Fixedly coupled to support the erection structure on the main column
In addition, in contact with the side of the building,
Extend the vertical transport device to the
By transporting the members via the jib crane,
At the rooftop, the main columns are stacked and built.
The members are transferred via the direct transfer device and the horizontal transfer device.
By sending, the other below the erection structure
After stacking and building the building frame, drive the elevating device again.
To raise the erection structure,
The structure is repeated below the erection structure.
When building and building the building frame,
First, it can run horizontally on the underside of the roof beam of the above construction structure
A vertical lifting scaffolding device
During the horizontal transfer of members on the building floor,
While moving up and down into the structure,
Lower it at any time during alignment and joining work.
It is characterized by using.

【0006】[0006]

【0007】[0007]

【作用】本発明のビルの建設方法では、まずビル最上階
一階分の架設用構造体を、ガイドを貫通して上へ延長さ
せた数本の本設柱に沿って、架設用構造体の屋上部に立
設固定された昇降装置により上昇させ、架設用構造体の
下側に2階高さ分余りの作業空間を確保して本設柱上に
支持する。
In the building construction method of the present invention, first, the erection structure of the top floor of the building is extended along several main pillars extending upward through the guides. It is raised by an elevating device that is erected and fixed on the roof of the building, and a work space more than the height of the second floor is secured below the erection structure and supported on the main pillar.

【0008】次に、上昇した架設用構造体の側部に、地
上から延長した垂直搬送装置により2階高さ分の柱部
材、梁部材、床部材を運び上げる。屋上へ貫通するコア
部柱部材は、架設用構造体下の建造階床を仮置場として
屋上のクレーンが仮置場から屋上へ取上げ、屋上におい
て本設柱の上へ順に積上げ接合してゆく。
Next, a column member, a beam member, and a floor member corresponding to the height of the second floor are carried up to the side of the raised erection structure by a vertical transport device extending from the ground. The core column members penetrating to the roof are taken up by the rooftop crane from the temporary storage area to the rooftop using the building floor below the erection structure as a temporary storage area, and are sequentially stacked and joined on the main columns on the rooftop.

【0009】建造階用のビル躯体部材は、垂直搬送装置
から水平搬送装置へ複数のホイストが乗り移って水平方
向へ搬送し、建造階上の複数の場所で並行して、梁、
床、その他の柱部材を順次積上げ接合する。これによ
り、屋上階と建造階の各作業を並行して進めることがで
きる。このとき、建造階では架設用構造体を支える数本
の本設柱以外に水平搬送を妨げるものは何も存在しない
から、水平搬送と上積建造作業は円滑に能率良く行え、
作業サイクルが短縮できる。また、この場合、上積建造
作業を、架設用構造体の屋上梁の下面に設けておいた水
平走行可能な昇降式足場装置を用いて行うようにしたの
で、作業者がこれに乗り込み、作業を行うことができ
る。さらに、建設部材の水平搬送時には、この昇降式足
場装置を上昇退避させるようにしたので、足場が水平搬
送の障害となることがない。
[0009] A plurality of hoists transfer from a vertical transport device to a horizontal transport device and are transported in the horizontal direction by a building carrier member for a building floor.
The floor and other pillar members are sequentially stacked and joined. Thereby, each work of the rooftop floor and the construction floor can be advanced in parallel. At this time, on the building floor, there is nothing that hinders horizontal transport other than the several main pillars that support the erection structure, so horizontal transport and top-building work can be performed smoothly and efficiently.
Work cycle can be shortened. In this case,
The work was carried out on the underside of the roof beam of the erection structure.
It was done by using a lifting type scaffolding device that can run flat.
So that the worker can get in and work on it.
You. When transporting construction materials horizontally, the lifting foot
The platform was raised and evacuated so that the scaffold could be transported horizontally.
There is no obstacle to transmission.

【0010】また、ビル建設の最終段階では、建造階で
上積建造した本設柱上に架設用構造体を接合固定し、屋
上ジブクレーンで昇降装置を解体して吊り降し、最上階
の仕上げ作業を終えた上でジブクレーンを解体すれば良
い。
[0010] In the final stage of building construction, the erection structure is joined and fixed on the main pillars built on the building floor, and the lifting device is dismantled and suspended by the roof jib crane to finish the top floor. After completing the work, disassemble the jib crane.

【0011】[0011]

【実施例】以下、本発明に係わるビルの建設方法の一実
施例を説明する。図1および図2は、この実施例の方法
に使用する設備を示し、建設方法の説明に先立ち、これ
ら設備の構成から順に説明する。これらの図において、
符号1は、建設すべきビルの最上階2と屋上階3の梁組
を含む最上層一階分の架設用構造体であり、この架設用
構造体1には、建設するビルの中央コア部の計6本の本
設柱5に合わせて、各本設柱5を貫通させたガイド4が
固定されている。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS One embodiment of a building construction method according to the present invention will be described below. 1 and 2 show equipment used in the method of this embodiment. Prior to the description of the construction method, the construction of these equipment will be described in order. In these figures,
Reference numeral 1 denotes an erecting structure for the uppermost floor including a beam set of a top floor 2 and a rooftop floor 3 of a building to be constructed. The erecting structure 1 includes a central core portion of a building to be constructed. The guides 4 penetrating the main pillars 5 are fixed in accordance with the six main pillars 5 in total.

【0012】符号6は各ガイド4に接近して屋上階3上
に固定して設けられた昇降装置、7は屋上階3上に設け
られた走行型ジブクレーン、8は架設用構造体1の下面
に付設されたIレール9とホイスト10からなる水平搬
送装置、11は屋上階3の梁下に設けたIレール、12
はIレール11上を走行するホイスト、13はホイスト
12に支持された走行式昇降足場装置である。
Reference numeral 6 denotes a lifting / lowering device fixedly provided on the rooftop floor 3 approaching each guide 4, 7 denotes a traveling jib crane provided on the rooftop floor 3, 8 denotes a lower surface of the erection structure 1. , A horizontal transfer device comprising an I-rail 9 and a hoist 10 attached to the roof, 11 is an I-rail provided under a beam on the rooftop floor 3, 12
Reference numeral denotes a hoist that runs on the I-rail 11, and reference numeral 13 denotes a traveling type lifting scaffolding device supported by the hoist 12.

【0013】さらに図2において、14は地上から架設
用構造体の側部までビル側面沿いに延長させて設けら
れた垂直搬送装置、15は架設用構造体1の周辺に吊り
支えた遮蔽シート、16はコア部の本設柱5沿いに昇降
装置6により上昇させた架設用構造体1の下部に形成さ
れる約2階分余りの建造階空間、17,18はそれぞれ
建造階空間で積上げ建造される柱と梁である。
Furthermore in FIG. 2, the shielding sheet 14 is a vertical conveying device which is provided to extend along the building side from the ground to the side of the installation for structure 1, 15 that supported hanging around the erection for structure 1 , 16 are approximately two floors of floor space formed below the erection structure 1 raised by the elevating device 6 along the main pillars 5 of the core, and 17 and 18 are stacked floor spaces respectively. Pillars and beams to be built.

【0014】これら図1および図2では、ビルの中央付
近にコア部を有する例を示しているが、コア部がビルの
外周寄りにある場合には、ビルの外周部に対称に設けら
れた本設柱5を架設用構造体1の支柱に用いるように、
各ガイド4と昇降装置6の位置を変更すればよい。
FIGS. 1 and 2 show an example in which a core is provided near the center of the building. However, when the core is located near the outer periphery of the building, the core is provided symmetrically on the outer periphery of the building. In order to use the main column 5 as a column of the erection structure 1,
What is necessary is just to change the position of each guide 4 and the raising / lowering device 6.

【0015】図3ないし図7は、上記ガイド4と昇降装
置6の実施例の詳細を示す図である。図3ないし図5に
示すように、ガイド4は、角筒状の外殻4bの外周面
を、屋上階3または最上階2の梁に突き合わせてそれぞ
れ接合し、上下方向に延びる共通軸線上に配置したもの
であり、外殻4bの内部には、本設柱5および本設柱5
の側面に設けられた梁取付ブラケット19を共に上下に
貫通移動させることができる十字状の孔4aが形成され
ている。
FIGS. 3 to 7 are views showing details of an embodiment of the guide 4 and the lifting / lowering device 6. FIG. As shown in FIGS. 3 to 5, the guide 4 joins the outer peripheral surface of the outer shell 4 b in the shape of a rectangular tube to the beam on the rooftop floor 3 or the top floor 2 and joins them, and on the common axis extending in the vertical direction The main column 5 and the main column 5 are arranged inside the outer shell 4b.
A cross-shaped hole 4a is formed so that both the beam mounting brackets 19 provided on the side surfaces can be vertically moved.

【0016】一方、昇降装置6は、図3、図4、図6お
よび図7に示すように、各ガイド4をはさんで対称に屋
上階3に立設固定された断面コ字状をなす一対のトラス
柱20と、各トラス柱20の頂部と屋上階梁3との間に
鉛直方向に掛け渡して固定された一対のステップロッド
21と、これらステップロッド21のそれぞれに係脱可
能に取り付けられた昇降シリンダ22と、これら昇降シ
リンダ22により昇降可能に支持された柱押え23と、
昇降シリンダ22とロッド21との係合解除時に柱押え
23を昇降させるためのウインチ24および巻上ワイヤ
25と、上部ガイド4の外殻4bと柱5のそれぞれに形
成された横孔26に油圧シリンダ(図示略)等により着脱
可能に挿入されるロックピン27と、柱押え23上に設
けられた柱押え兼用のセンタリング梁28とにより構成
されている。
On the other hand, as shown in FIG. 3, FIG. 4, FIG. 6, and FIG. 7, the lifting device 6 has a U-shaped section which is symmetrically erected on the roof floor 3 with each guide 4 interposed therebetween. A pair of truss pillars 20, a pair of step rods 21 vertically fixed between the top of each truss pillar 20 and the rooftop beam 3, and detachably attached to each of these step rods 21 A lifting cylinder 22, a column holder 23 supported by the lifting cylinder 22 so as to be vertically movable,
A winch 24 and a hoisting wire 25 for raising and lowering the column holder 23 when the lifting cylinder 22 is disengaged from the rod 21, and a horizontal hole 26 formed in the outer shell 4 b of the upper guide 4 and the column 5 respectively. It is composed of a lock pin 27 which is removably inserted by a cylinder (not shown) or the like, and a centering beam 28 provided on the column holder 23 and also serving as a column holder.

【0017】センタリング梁28は、図6に示すよう
に、柱押え23のフレーム上のモータ29およびギヤー
30,31により連動回転される一対の平行な逆ねじロ
ッド32上に、互いに接近離間するように取り付けられ
た一対の平面視凹形の梁である。これらセンタリング梁
28を柱押え梁として使用するときは、図7に示すよう
に本設柱5の上端に合致する位置に移動させる。一方、
センタリング梁として機能させるときには、図6に示す
ように、それらの凹部で本設柱5の両側面をはさみつけ
てこれを固定する。なお、図6中符号33はガイドロー
ラであり、トラス柱20に上下方向に固定されたレール
34に沿って転がる。
As shown in FIG. 6, the centering beams 28 are moved toward and away from each other on a pair of parallel reverse screw rods 32 which are rotated by the motor 29 and the gears 30, 31 on the frame of the column holder 23. Are a pair of beams having a concave shape in plan view. When these centering beams 28 are used as column holding beams, they are moved to positions matching the upper ends of the main columns 5 as shown in FIG. on the other hand,
When functioning as a centering beam, as shown in FIG. 6, both side surfaces of the main pillar 5 are clamped by these concave portions and fixed. Reference numeral 33 in FIG. 6 denotes a guide roller, which rolls along a rail 34 fixed to the truss column 20 in the vertical direction.

【0018】次に、図8および図9は、水平搬送装置8
および垂直搬送装置14の一例を示している。水平搬送
装置8は、架設用構造物1の下面に縦横に配置されたI
レール9と、これらIレール9の交叉部に設けられた旋
回切換レール9Rとを具備し、複数のホイスト10を走
行させて水平搬送を行なうものである。図9中符号35
は切換レール9Rを操作するためのシリンダである。
Next, FIG. 8 and FIG.
And an example of the vertical transport device 14. The horizontal transport device 8 includes I and I arranged vertically and horizontally on the lower surface of the erection structure 1.
A rail 9 and a swing switching rail 9R provided at an intersection of the I-rails 9 are used to carry a plurality of hoists 10 to perform horizontal conveyance. Reference numeral 35 in FIG.
Is a cylinder for operating the switching rail 9R.

【0019】一方、垂直搬送装置14は、ビル外壁部に
支持され地上から下継ぎすることにより順次押し上げ延
長される門形架構36と、この門形架構36の内部に配
置されて地上のウインチ(図示略)から繰出される巻上索
37で昇降される吊ビーム38とを備えている。この吊
ビーム38の下面には、水平搬送装置8のIレール9と
整合する短いIレール9Sが取り付けられ、このIレー
ル9Sにホイスト10を乗り込ませ、吊ビーム38で昇
降することにより、部材の垂直搬送を行なう。例えば、
図8に示す位置で部材を吊った垂直搬送装置14上のホ
イスト10は、水平搬送装置8のIレール9上に移さ
れ、さらに図2に示すように建造階の仮置き床16Fへ
部材を降して仮置きする。
On the other hand, the vertical transport device 14 is supported on the outer wall of the building, and is sequentially pushed up and extended by being spliced from the ground. A vertical winch ( (Not shown) and a suspension beam 38 which is raised and lowered by a hoisting cable 37. A short I-rail 9S that is aligned with the I-rail 9 of the horizontal transfer device 8 is attached to the lower surface of the suspension beam 38. The hoist 10 is loaded on the I-rail 9S, Perform vertical transport. For example,
The hoist 10 on the vertical transport device 14 in which the members are suspended at the position shown in FIG. 8 is transferred onto the I-rail 9 of the horizontal transport device 8, and further, as shown in FIG. Put down and place temporarily.

【0020】上記各設備を用いたビルの建設方法を説明
する。この方法ではまず、上述したビル最上層一階分の
架設用構造体1に、上記本設柱貫通用のガイド4、昇降
装置6、ジブクレーン7、水平搬送装置8を組み立て
る。次いで、上記ガイド4を貫通させて建付けたビルの
本設柱5に昇降装置6を結合駆動し、本設柱5を支えと
して架設用構造体1を上昇させた後、昇降装置6を本設
柱5と固定結合し、架設用構造体1を数本の本設柱5上
に支持する。
A method of building a building using each of the above facilities will be described. In this method, first, the guide 4 for penetrating the main columns, the elevating device 6, the jib crane 7, and the horizontal transfer device 8 are assembled on the erection structure 1 on the first floor of the building. Next, the lifting / lowering device 6 is connected and driven to the main pillar 5 of the building constructed by passing the guide 4 therethrough, and the erection structure 1 is raised with the main pillar 5 as a support. It is fixedly connected to the pillars 5 and supports the erection structure 1 on several pillars 5.

【0021】次に、昇降装置6の各センタリング梁28
を、図7に示すように本設柱5の上端上に移動させ、図
3に示す昇降シリンダ22を各ステップロッド21に沿
ってそれぞれ降下させることにより、架設用構造体1を
上昇させる。そして上昇位置において、昇降シリンダ2
2をステップロッド21に対して固定し、複数の本設柱
5上に架設用構造体1を安定的に支持する。
Next, each centering beam 28 of the lifting device 6
Is moved over the upper end of the main pillar 5 as shown in FIG. 7, and the lifting cylinder 22 shown in FIG. 3 is lowered along each step rod 21 to raise the erection structure 1. Then, in the raised position, the lifting cylinder 2
2 is fixed to the step rod 21 and the erection structure 1 is stably supported on the plurality of main columns 5.

【0022】次いで、垂直搬送装置14を、上昇した架
設用構造体1の高さに合わせて延長し、本設柱5用の部
材は垂直搬送装置14を介して地上から建造階16へ搬
送したうえ、仮置き床16Fに一旦仮置きし、ここから
屋上ジブクレーン7で屋上へ吊上げ、屋上で本設柱5へ
積み上げて接合する。また建造階用の他の部材は、垂直
搬送装置14から水平搬送装置8へ複数のホイスト10
を乗り入れさせ、建造階16内へ水平搬送し、既設のビ
ル躯体部上に積み上げて接合する。
Next, the vertical transport device 14 is extended in accordance with the height of the raised construction structure 1, and the members for the main pillar 5 are transported from the ground to the building floor 16 via the vertical transport device 14. Then, the jig is temporarily temporarily placed on the temporary storage floor 16F, lifted from there to the roof by the roof jib crane 7, and piled up on the main pillar 5 and joined on the roof. Another member for the building floor is a plurality of hoists 10 from the vertical transport device 14 to the horizontal transport device 8.
Are transported horizontally into the building floor 16 and stacked and joined on the existing building frame.

【0023】屋上で本設柱5を接続するには、図3にお
いて各本設柱5とガイド4の横孔26にロックピン27
を挿入するとともに、昇降シリンダ22をステップロッ
ド21から開放し、ウインチ24を駆動して柱押え23
を若干上昇させ、図6に示すように各センタリング梁2
8を開き、これらの間隙を通して本設柱5の部材を挿入
できるようにする。この状態で、ジブクレーン7により
吊り下げた本設柱5の部材の下端を各センタリング梁2
8の間へ降し、センタリング梁28を閉じることにより
部材の下端芯合せを行なう。
In order to connect the main pillars 5 on the roof, a lock pin 27 is inserted into each of the main pillars 5 and the horizontal hole 26 of the guide 4 in FIG.
And the lifting cylinder 22 is released from the step rod 21, and the winch 24 is driven to
Is slightly raised, and as shown in FIG.
8 is opened so that the members of the main pillar 5 can be inserted through these gaps. In this state, the lower end of the member of the main pillar 5 suspended by the jib crane 7 is fixed to each centering beam 2.
8 and the centering beam 28 is closed to center the lower end of the member.

【0024】その後、各センタリング梁28を再び開
き、ウインチ24を駆動させて柱押え23を本設柱5の
部材の上端寄りまで上昇させ、上記と同じようにセンタ
リング梁28を閉じて部材の上部芯合せを行ない、この
状態のまま柱部材の下端を本設柱5の上端につなげて溶
接する。
Thereafter, each centering beam 28 is reopened, the winch 24 is driven to raise the column holder 23 to a position near the upper end of the member of the main pillar 5, and the centering beam 28 is closed and the upper portion of the member is closed in the same manner as described above. Alignment is performed, and the lower end of the column member is connected to the upper end of the main column 5 and welded in this state.

【0025】溶接完了後、柱押え23を上昇させ、延長
された本設柱5の上端へ図7のように各センタリング梁
28を閉じて乗せ、昇降シリンダ22をステップロッド
21に対し上下動不能に固定する。さらに、ウインチ2
4を巻出して解放し、全てのロックピン27を抜き取
る。以上の要領で、各本設柱5を一本ずつ順に積み上げ
て延長する。
After welding is completed, the column holder 23 is raised, and each centering beam 28 is closed and placed on the upper end of the extended main column 5 as shown in FIG. Fixed to. In addition, winch 2
4 is unwound and released, and all the lock pins 27 are removed. In the above manner, the main pillars 5 are sequentially stacked one by one and extended.

【0026】上記のような最上階での作業と並行して、
建造階16では、垂直搬送装置14から水平搬送装置8
へと複数のホイスト10を移送して部材を水平搬送し、
複数の場所で同時にビル躯体部の積上げ接合を行なう。
昇降式足場装置13は、建造階16内で部材が水平搬送
される時は、架設用構造体1内の位置に退避させる一
方、部材の位置合せあるいは接合を行なう時には、随時
作業者が乗り込んでこれを下降させ、作業にあたる。
In parallel with the work on the top floor as described above,
On the building floor 16, the vertical transport device 14 moves to the horizontal transport device 8.
To transport a plurality of hoists 10 horizontally
Building joints are simultaneously made at multiple locations.
The elevating type scaffolding device 13 retreats to a position in the erection structure 1 when the members are horizontally conveyed in the building floor 16, while an operator gets in at any time when positioning or joining the members. This is lowered and work is performed.

【0027】屋上階で数本の本設柱5の積上げ延長が終
了し、かつ建造階でビルの他の躯体部の2階高さ分の上
積延長が終了したら、昇降装置6を駆動させて再び2階
高さ分、本設柱5を支点として架設用構造体1を上昇さ
せ、上記と同様の工程を繰返して行く。
When the stacking and extension of several main pillars 5 are completed on the rooftop floor and the stacking and extending of the other building part of the building at the height of the second floor are completed on the building floor, the elevator 6 is driven. Then, the erection structure 1 is moved up again by the height of the second floor by the height of the second pillar, and the same steps as above are repeated.

【0028】上記構成からなるビルの建設方法によれ
ば、図1に示すように、地上レベルで所定位置に数本の
2階高さ分の本設柱5を建て付け、地上の架台40上に
最上階一階高さの架設用構造体1を組み立て、各設備を
設けた状態から、直ちに屋上部のジブクレーン7および
昇降装置6を使用して本設柱5の積上げ延長を行なった
うえ、昇降装置6により架設用構造体1の上昇を開始で
きる。また、上昇させた位置において、屋上階と建造階
との各作業を並行して行なうことができ、建造階では複
数のホイスト10による積上げ、および部材の接合を複
数の位置で並行して進行させることが可能であるから、
全体としての作業能率を高め、短期間で建設が行なえ
る。
According to the construction method for a building having the above-described structure, as shown in FIG. 1, several two-story permanent columns 5 are erected at predetermined positions on the ground level, and In the state where the construction structure 1 having the height of the first floor and the height of the first floor is assembled, and the facilities are provided, the jib crane 7 and the elevating device 6 on the roof are used to immediately extend and extend the stack of the main pillar 5. The elevating device 6 can start raising the erection structure 1. Further, in the raised position, each operation of the rooftop floor and the building floor can be performed in parallel, and in the building floor, the stacking by the plurality of hoists 10 and the joining of the members proceed in parallel at the plurality of positions. Because it is possible
Work efficiency as a whole is improved, and construction can be performed in a short time.

【0029】また、図2で示すように、建造階16上で
所定の階までの建造が済んだ際に、例えば昇降装置6に
より架設構造体1を降下させ、所定階の本設柱5上にそ
のまま接合固定することができる。この時、屋上部の昇
降装置6、ジブクレーン7は建造階の仕上作業に対し全
く障害とならないうえ、屋上部でジブクレーン7を、昇
降装置6その他の設備の解体、撤収、および屋上仕上工
事に有効に利用することが可能であるという利点も有す
る。
As shown in FIG. 2, when the building up to the predetermined floor is completed on the building floor 16, the erection structure 1 is lowered by, for example, the elevating device 6, and Can be fixed as they are. At this time, the elevator 6 and the jib crane 7 on the roof do not hinder the finishing work of the building floor at all, and the jib crane 7 on the roof is effective for dismantling, removing, and finishing the roof 6 and other equipment. It also has the advantage that it can be used for

【0030】なお、本発明は上記実施例のみに限定され
るものではなく、各部の構成や形状等は必要に応じて適
宜変更してよい。
The present invention is not limited to only the above-described embodiment, and the configuration, shape, and the like of each part may be appropriately changed as necessary.

【0031】[0031]

【発明の効果】以上説明したように、本発明に係わるビ
ルの建設方法は、以下のような優れた効果を奏する。
As described above, the building construction method according to the present invention has the following excellent effects.

【0032】(a) 建設するビルの最上部一階分を架設
用構造体とし、数本の本設柱を貫通させるガイドと、ガ
イドまわりの屋上に立設した昇降装置およびジブクレー
ンとを設け、屋上に突出した本設柱と昇降装置とを結合
して架設用構造体を上昇させて支持させるため、地上で
上記架設用構造体を組立てたあと、1階レベルから直ち
に同一手順の工程による建設工事を開始することがで
き、現地工事が単純化して容易になるうえ、架設用構造
体と各本設柱との結合が確実に行なえるから、水平力に
対し安定性が大きい。
(A) The uppermost floor of the building to be constructed is an erecting structure, and a guide for penetrating several main pillars, an elevating device and a jib crane standing on a roof around the guide are provided. To assemble the erection structure on the ground and assemble the erection structure to assemble the erecting device by connecting the main pillar protruding to the roof and the elevating device, immediately follow the same procedure from the first floor level to construct the erection structure The construction can be started, the construction on site is simplified and facilitated, and the connection between the erection structure and each of the main pillars can be surely performed, so that stability against horizontal force is large.

【0033】(b) 垂直搬送装置による部材の垂直搬送
と、ジブクレーンによる屋上階でのビル躯体部の積上げ
建造とを並行して進め、また、建造階では水平搬送装置
の複数の搬送機により同時並行的に複数位置で建造作業
を行なえるから、各建造階毎の作業能率が上り、工期短
縮が可能になる。
(B) The vertical transfer of the members by the vertical transfer device and the stacking and building of the building frame on the roof floor by the jib crane proceed in parallel. Since the construction work can be performed at a plurality of positions in parallel, the work efficiency of each building floor increases, and the construction period can be shortened.

【0034】(c) 水平搬送装置と走行式昇降足場装置
とを除いた他の装置は、全てビル屋上あるいはビル外側
に位置するから、建造階上で使用する設備と建造作業と
の干渉がなく、ビル建設の最終段階においても空間のと
り合い等による困難性が生じない。
(C) All of the other devices except the horizontal transfer device and the traveling scaffolding device are located on the building roof or outside the building, so that there is no interference between the equipment used on the building floor and the building work. Also, even in the final stage of building construction, there is no difficulty due to space and the like.

【0035】(d) 建造階では、水平搬送の邪魔になら
ないように、部材の位置合せ接合時に、随時作業者が架
設用構造体内から走行式昇降足場装置を操作して、建造
階の作業現場へ往復できるから建設階への作業者の出入
り、及び作業も安全になり、容易になる。
(D) On the building floor, the worker operates the traveling climbing scaffolding device from the erection structure at any time when aligning and joining the members so as not to hinder the horizontal transportation, and Since it is possible to reciprocate to and from the construction floor, it is also safe and easy for workers to enter and exit the construction floor.

【0036】(e) 屋上のジブクレーンは、本設柱の継
ぎ足し作業のほか、ペントハウスの建付け、機器の搬
入、昇降装置や搬送装置等の解体や地上への吊り降し等
にも使用できるうえ、最終的には、ジブクレーン自体も
屋上で解体し、搬入口からホイスト等で地上へ降せば良
いから、ビルの建造に非常にうまく利用できる。
(E) The roof jib crane can be used not only for adding pillars, but also for building penthouses, loading equipment, dismantling lifting devices and transporting devices, and hanging them on the ground. Eventually, the jib crane itself can be dismantled on the rooftop and lowered to the ground with a hoist from the loading entrance, which can be used very well for building buildings.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の実施例の方法に使用する設備を示す側
面図である。
FIG. 1 is a side view showing equipment used in a method according to an embodiment of the present invention.

【図2】同設備において建造作業が進行した状態を示す
側面図である。
FIG. 2 is a side view showing a state in which construction work has progressed in the facility.

【図3】同設備の昇降装置回りを示す側面図である。FIG. 3 is a side view showing the periphery of a lifting device of the facility.

【図4】図3中のIV−IV線に沿う側面図である。FIG. 4 is a side view taken along the line IV-IV in FIG. 3;

【図5】図3中のV−V線に沿う平面図である。FIG. 5 is a plan view along the line VV in FIG. 3;

【図6】図3中のVI−VI線に沿う拡大平面図であ
る。
FIG. 6 is an enlarged plan view taken along the line VI-VI in FIG. 3;

【図7】図6において一部を操作した状態を示す平面図
である。
FIG. 7 is a plan view showing a state where a part is operated in FIG. 6;

【図8】垂直搬送装置および水平搬送装置を示す説明図
である。
FIG. 8 is an explanatory diagram showing a vertical transport device and a horizontal transport device.

【図9】図8のIX−IX線に沿う平面図である。FIG. 9 is a plan view along the line IX-IX in FIG. 8;

【符号の説明】[Explanation of symbols]

1 最上階一階分の架設用構造体 2 最上階梁組 3 屋上階梁組 4 ガイド 5 本設柱 6 昇降装置 7 ジブクレーン 8 水平搬送装置 9 Iレール 9S Iレール 11 Iレール 9R 旋回切換えレール 10,12 ホイスト 13 昇降足場 14 垂直搬送装置 16 建造階 20 トラス柱 21 ステップロッド 22 昇降シリンダ 23 柱押え 24 ウインチ 25 巻上ワイヤ 27 ロックピン 28 センタリング梁 DESCRIPTION OF SYMBOLS 1 Construction structure for one floor of the top floor 2 Top floor beam group 3 Roof floor beam group 4 Guide 5 Main pillar 6 Elevating device 7 Jib crane 8 Horizontal transfer device 9 I rail 9S I rail 11 I rail 9R Rotation switching rail 10 , 12 Hoist 13 Elevating Scaffolding 14 Vertical Conveyor 16 Building Floor 20 Truss Column 21 Step Rod 22 Elevating Cylinder 23 Column Holder 24 Winch 25 Hoisting Wire 27 Lock Pin 28 Centering Beam

───────────────────────────────────────────────────── フロントページの続き (72)発明者 向谷 美徳 広島県広島市西区観音新町4丁目6番22 号 三菱重工業株式会社 広島製作所内 (72)発明者 関 洋一 東京都中央区京橋二丁目16番1号 清水 建設株式会社内 (72)発明者 前田 純一郎 東京都中央区京橋二丁目16番1号 清水 建設株式会社内 (72)発明者 近藤 弘司 東京都中央区京橋二丁目16番1号 清水 建設株式会社内 (72)発明者 奥山 信博 東京都中央区京橋二丁目16番1号 清水 建設株式会社内 (72)発明者 阿部 愛和 東京都中央区京橋二丁目16番1号 清水 建設株式会社内 (56)参考文献 特開 平1−235748(JP,A) 特公 昭50−27652(JP,B2) (58)調査した分野(Int.Cl.6,DB名) E04B 1/35 E04G 21/14 - 21/16 ──────────────────────────────────────────────────続 き Continuing on the front page (72) Inventor Yoshinori Mukai 4-6-22 Kannon Shinmachi, Nishi-ku, Hiroshima-shi, Hiroshima Mitsubishi Heavy Industries, Ltd. Hiroshima Works (72) Inventor Yoichi Seki 2--16 Kyobashi, Chuo-ku, Tokyo No. 1 Inside Shimizu Construction Co., Ltd. (72) Inventor Junichiro Maeda 2-6-1 Kyobashi, Chuo-ku, Tokyo Shimizu Construction Co., Ltd. (72) Koji Kondo 2-161 Kyobashi, Chuo-ku, Tokyo Shimizu Construction Inside (72) Inventor Nobuhiro Okuyama 2-16-1, Kyobashi, Chuo-ku, Tokyo Shimizu Construction Co., Ltd. (72) Inventor Abe In-house 2-16-1, Kyobashi, Chuo-ku, Tokyo Shimizu Corporation (56) References JP-A-1-235748 (JP, A) JP-B-50-27652 (JP, B2) (58) Fields investigated (Int. Cl. 6 , DB name) E04B 1/35 E04G 21 / 14 - 21/16

Claims (1)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 ビルの最上層一階分の架設用構造体を形
成し、この架設用構造体に、複数の本設柱を個別に貫通
させるガイドと、これらガイドと接近して上記架設用構
造体の層上部に立設された昇降装置と、上記架設用構造
体の屋上部に設けられたジブクレーンと、上記架設用構
造体の下面に付設された水平搬送装置とをそれぞれ設
け、 上記ガイドを貫通して建付けた上記本設柱に上記昇降装
置を係合駆動して上記架設用構造体をこれら本設柱沿い
に上昇させ、上記昇降装置を固定結合して上記本設柱に
上記架設用構造体を支持したうえ、 ビル側部に接して地上から上記架設用構造体の側部へ垂
直搬送装置を延長し、この垂直搬送装置および上記ジブ
クレーンを経由して部材を搬送することにより上記屋上
部において上記本設柱を積上げ建造し、 上記垂直搬送装置および上記水平搬送装置を経由して部
材を搬送することにより上記架設用構造体の下方におい
て他のビル躯体部を積上げ建造し、 再び上記昇降装置を駆動させて上記架設用構造体を上昇
させ、上記同様の工程を繰返す構成となっており、 上記架設用構造体下方においてビル躯体部の積上げ建造
を行うに際しては、あらかじめ、上記架設用構造体の屋
上梁の下面に水平走行可能な昇降式足場装置を設けてお
き、この昇降式足場装置を、建造階における部材の水平
搬送時には、上記架設用構造体内に上昇退避させる一
方、建造階における部材の位置合わせ時および接合作業
時には、随時降下させて使用することを特徴とするビル
の建設方法。
1. A erection structure for the first floor of a building is formed, and a guide for individually penetrating a plurality of main pillars is provided in the erection structure. An elevating device erected on the upper layer of the structure, a jib crane provided on the roof of the erection structure, and a horizontal transfer device attached to a lower surface of the erection structure, respectively, The raising and lowering device is driven to engage with the main column built through the main column to raise the erection structure along these main columns, and the lifting device is fixedly connected to the main column, and By supporting the erection structure, extending the vertical transfer device from the ground to the side of the erection structure in contact with the side of the building, and transferring the members via the vertical transfer device and the jib crane, Stack and build the main pillar on the rooftop By transporting the members via the vertical transport device and the horizontal transport device, another building frame is stacked and built below the erection structure, and the elevating device is driven again to drive the erection structure. body was elevated to the has a structure which repeats the same process, accumulation of the building skeleton portion in the structure below for the erection construction
Before carrying out the work, the building structure
An elevating scaffolding device that can run horizontally is installed on the underside of the upper beam.
The lifting type scaffolding equipment is
At the time of transportation, the
When aligning and joining members on the building floor
Buildings that are sometimes dropped and used at any time
Construction method.
JP2687491A 1991-01-28 1991-01-28 Building construction method Expired - Lifetime JP2913216B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2687491A JP2913216B2 (en) 1991-01-28 1991-01-28 Building construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2687491A JP2913216B2 (en) 1991-01-28 1991-01-28 Building construction method

Publications (2)

Publication Number Publication Date
JPH059981A JPH059981A (en) 1993-01-19
JP2913216B2 true JP2913216B2 (en) 1999-06-28

Family

ID=12205441

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2687491A Expired - Lifetime JP2913216B2 (en) 1991-01-28 1991-01-28 Building construction method

Country Status (1)

Country Link
JP (1) JP2913216B2 (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5881504A (en) * 1995-05-15 1999-03-16 Obayashi Corporation Temporary frame system for construction
JP4518960B2 (en) * 2005-01-11 2010-08-04 旭化成ホームズ株式会社 Exterior wall panel position adjustment structure and exterior wall panel mounting method
JP2007262688A (en) * 2006-03-27 2007-10-11 Ohbayashi Corp Demolition method for building
CN106065668B (en) * 2016-08-01 2019-03-19 中建八局第四建设有限公司 A kind of construction techniques
JP6920118B2 (en) * 2017-07-11 2021-08-18 大成建設株式会社 Demolition system for existing structures

Also Published As

Publication number Publication date
JPH059981A (en) 1993-01-19

Similar Documents

Publication Publication Date Title
EP0487516B1 (en) Construction apparatus and construction method
US5881504A (en) Temporary frame system for construction
JP2913216B2 (en) Building construction method
JP2916591B2 (en) Building construction method and device
JP3841242B2 (en) Elevator parking elevating work table and construction method using it
JP3225456B2 (en) How to build a building
JPH0733688B2 (en) Push-up method
JP3326730B2 (en) Material transportation method
JP2778842B2 (en) Building construction method
JPH05113026A (en) Temporary scaffold structure
JP2761518B2 (en) Construction method of building
JPH062434A (en) Method of building steel structure roof
JPH10152981A (en) Vertically moving scaffold
JP2750472B2 (en) Building construction method and device
JPH10140839A (en) Device for vertically hoisting form material and pipe support
JPH1037527A (en) Method for constructing inner and outer cylinder of chimney simultaneously
JPH05263531A (en) Automatic construction method and lifting-up device of structure
JP3225455B2 (en) How to build a building
JP2717156B2 (en) Building construction method
JPH07150814A (en) Erection equipment of tower structure
JPH05163839A (en) Method and device for conveying provisionally equipped material of building under construction to upper floor
JPH08199854A (en) Method and device for building towerlike construction
JPH07324490A (en) Conveying system and building construction method based on the system
JPH03107034A (en) Constructing method for structure
JPH04336167A (en) Construction of building and elevation device to be used for same construction

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 19990216