JP3225455B2 - How to build a building - Google Patents

How to build a building

Info

Publication number
JP3225455B2
JP3225455B2 JP24168094A JP24168094A JP3225455B2 JP 3225455 B2 JP3225455 B2 JP 3225455B2 JP 24168094 A JP24168094 A JP 24168094A JP 24168094 A JP24168094 A JP 24168094A JP 3225455 B2 JP3225455 B2 JP 3225455B2
Authority
JP
Japan
Prior art keywords
pillar
building
constructing
column
equipment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP24168094A
Other languages
Japanese (ja)
Other versions
JPH08105228A (en
Inventor
保義 嶋崎
一彦 大沢
博 木村
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Corp
Original Assignee
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Corp filed Critical Shimizu Corp
Priority to JP24168094A priority Critical patent/JP3225455B2/en
Publication of JPH08105228A publication Critical patent/JPH08105228A/en
Application granted granted Critical
Publication of JP3225455B2 publication Critical patent/JP3225455B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】本発明は、例えば、火力発電所に
備えるボイラー等、大型の機器や設備等を収容する建屋
を構築するのに用いて好適な建屋の構築方法に関するも
のである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a building suitable for constructing a building for accommodating large-scale equipment and equipment, such as a boiler for a thermal power plant.

【0002】[0002]

【従来の技術】一般に、火力発電所のボイラー等、大型
の機器や設備を収容する建屋は、大断面を有した鉄骨か
ら構成されている。従来、このような鉄骨造の建屋を構
築するには、大型の揚重機を用いて鉄骨を下方から上方
に向けて建方していき、建方が完了した後、機器や設備
を内部に搬入・設置していた。
2. Description of the Related Art In general, a building for accommodating large-scale equipment and facilities, such as a boiler of a thermal power plant, is formed of a steel frame having a large cross section. Conventionally, to build such a steel-framed building, a large lifting machine was used to construct the steel frame from below to above, and after the construction was completed, equipment and facilities were brought inside.・ It was installed.

【0003】[0003]

【発明が解決しようとする課題】しかしながら、上述し
たような従来の建屋の構築方法には、以下のような問題
が存在する。まず、建屋を構成する鉄骨を建方するため
には、これら鉄骨が大断面であるため、大型の揚重機を
用いる必要がある。このため、構築すべき建屋の敷地が
狭隘な場合には、揚重機を設置するスペースの確保が困
難となったり、また、仮設用地が不足したりするという
問題が発生する。また、屋根架構を施工するに際して
は、この作業が高所作業となるため、安全性の面で向上
の余地がある。さらには、機器や設備の早期の運転開始
が望まれる場合には、機器や設備の搬入を早める必要が
ある。しかし、搬入時に大型の機器や設備の荷重を支持
するためには、建屋が所要の強度を有していなければな
らない。このため、建屋の構築完了前に機器や設備の搬
入作業を行うには、大量の仮設の補強部材を用いて建屋
を補強しなければならず、これには非常に手間がかかる
ものとなっていた。このため、建屋の構築作業が完了す
るまでは機器や設備の搬入作業を行えないのが実情であ
り、したがって機器や設備の運転開始の早期化を図るの
は困難であった。本発明は、以上のような点を考慮して
なされたもので、狭隘な敷地であっても施工が可能で、
かつその施工作業を安全に行うことができ、さらには収
容した機器や設備の早期の運転開始を可能とする建屋の
構築方法を提供することを目的とする。
However, the conventional building construction method as described above has the following problems. First, in order to construct the steel frames constituting the building, it is necessary to use a large lifting machine because these steel frames have a large cross section. For this reason, when the site of the building to be constructed is narrow, there is a problem that it is difficult to secure a space for installing the hoisting machine, and there is a shortage of temporary premises. In addition, when installing the roof frame, since this work is performed at a high place, there is room for improvement in terms of safety. Further, when it is desired to start the operation of the equipment or the facility at an early stage, it is necessary to accelerate the loading of the equipment or the equipment. However, in order to support the load of large-sized equipment and equipment at the time of loading, the building must have a required strength. For this reason, in order to carry in the equipment and facilities before the building is completed, the building must be reinforced with a large number of temporary reinforcing members, which is very time-consuming. Was. For this reason, in reality, it is difficult to carry in the equipment and facilities until the construction work of the building is completed. Therefore, it has been difficult to promptly start the operation of the equipment and facilities. The present invention has been made in consideration of the above points, and can be constructed even on a narrow site,
It is another object of the present invention to provide a method for constructing a building that can safely perform the construction work and that can start operation of the housed equipment and facilities at an early stage.

【0004】[0004]

【課題を解決するための手段】請求項1に係る発明は、
大型の機器や設備等を収容する建屋の構築方法であっ
て、前記建屋の柱を構築した後に、予め地組した屋根架
構を前記柱に備えた揚重手段で揚重して設置する第一の
工程と、収容すべき前記機器,設備を前記屋根架構に備
えた吊下手段で吊り込んで定められた位置に設置する第
二の工程と、前記建屋の外周をなす外周架構を構築する
第三の工程とからなり、前記第一の工程において前記柱
を構築するに際しては、まず、前記柱の全長のうちの一
部を立設し、しかる後に、該柱の側方に立設した仮設支
柱に備えたジャッキアップ手段で、前記柱をプッシュア
ップさせるプッシュアップ作業と、プッシュアップさせ
た前記柱の下方において前記柱を延長構築する柱延長作
業とを交互に繰り返すようにしたことを特徴としてい
る。
The invention according to claim 1 is
A method for constructing a building accommodating large-scale equipment, equipment, and the like, wherein a pillar of the building is constructed, and a roof frame that has been prefabricated is lifted and installed by a lifting means provided on the pillar. And a second step of suspending the equipment and facilities to be accommodated by suspending means provided on the roof frame and installing it at a predetermined position, and a second step of constructing an outer frame forming the outer periphery of the building. When constructing the pillar in the first step, firstly, a part of the entire length of the pillar is erected, and then the temporary erection is established on the side of the pillar. With a jack-up means provided on a support, a push-up operation of pushing up the column and a column extension operation of extending and building the column below the pushed-up column are alternately repeated. I have.

【0005】請求項2に係る発明は、請求項1記載の建
屋の構築方法において、前記第一の工程の後に、前記第
一の工程で構築した屋根架構の下面に前記外周架構の一
部を先付けして前記柱と一体化し、しかる後に前記第二
の工程を行うことを特徴としている。
According to a second aspect of the present invention, in the method for constructing a building according to the first aspect, after the first step, a part of the outer peripheral frame is attached to a lower surface of the roof frame constructed in the first step. It is characterized in that it is pre-attached and integrated with the pillar, and then the second step is performed.

【0006】請求項3に係る発明は、請求項1または2
記載の建屋の構築方法において、前記第一の工程で、上
下方向に一定長を有した筒状の鋼管からなる柱部材が四
隅に配され、かつこれら柱部材間に梁部材が架設された
構成からなる柱ユニットを上下に定められた数接続した
後、前記各柱部材内にコンクリートを打設することによ
り、前記柱を構築するようにしたことを特徴としてい
る。
[0006] The invention according to claim 3 is the invention according to claim 1 or 2.
In the method for constructing a building described in the above, in the first step, pillar members made of a tubular steel pipe having a certain length in the vertical direction are arranged at four corners, and a beam member is erected between these pillar members. After connecting a predetermined number of column units consisting of up and down, concrete is poured into each of the column members, whereby the columns are constructed.

【0007】[0007]

【作用】請求項1記載の発明では、第一の工程で建屋の
柱と屋根架構とを構築し、第二の工程で屋根架構に備え
た吊下手段で機器,設備を吊り込んでこれを定められた
位置に設置し、第三の工程で外周架構を構築することに
よって、建屋を構築する構成とした。このようにして、
建屋の柱と屋根架構を構築した時点で、外周架構の構築
に先立って機器,設備を設置するようにしたので、機
器,設備の試運転などを早期から行うことが可能とな
る。また、第一の工程において前記柱を構築するに際し
て、まず、本設の柱の全長のうちの一部を立設し、しか
る後に柱の側方に立設した仮設支柱に備えたジャッキア
ップ手段で、柱をプッシュアップさせるプッシュアップ
作業と、プッシュアップさせた柱の下方において柱を延
長構築する柱延長作業とを交互に繰り返す構成とした。
これにより、地上において柱の構築作業を行うことがで
きる。さらに、屋根架構を予め地組しておき、これを柱
に備えた揚重手段で揚重して設置する構成としたので、
高所における屋根架構の組立作業を最小限とすることが
できる。
According to the first aspect of the present invention, in the first step, the pillars and the roof frame of the building are constructed, and in the second step, the equipment and facilities are suspended by the suspension means provided on the roof frame, and this is suspended. The building was constructed by installing it at a predetermined position and constructing the outer frame in the third step. In this way,
When the pillars and the roof frame of the building are constructed, the equipment and facilities are installed prior to the construction of the outer frame, so that the test operation of the equipment and facilities can be performed from an early stage. Further, when constructing the pillar in the first step, firstly, a part of the total length of the main pillar is erected, and then a jack-up means provided on a temporary support pillar erected on the side of the pillar. Thus, a push-up operation of pushing up the pillar and a pillar extension operation of extending and building the pillar below the pushed-up pillar are alternately repeated.
Thereby, the construction work of the pillar can be performed on the ground. Furthermore, since the roof frame was previously grounded, and this was lifted and installed by the lifting means provided on the pillar,
The work of assembling the roof frame at a high place can be minimized.

【0008】請求項2記載の発明では、第一の工程の後
に、構築した屋根架構の下面に一定長の外周架構を先付
けして柱と一体化し、しかる後に第二の工程を行う構成
とした。これにより、先付けした外周架構によって、屋
根架構と柱とから構成される架構が補強されて強固なも
のとなり、第二の工程で機器や設備を吊り込むに際し
て、その荷重に抗することが可能となる。
According to the second aspect of the present invention, after the first step, an outer peripheral frame having a predetermined length is attached to the lower surface of the constructed roof frame to be integrated with the pillar, and then the second step is performed. . With this, the frame consisting of the roof frame and the pillars is reinforced by the pre-installed outer frame and becomes strong, and it is possible to withstand the load when suspending equipment and facilities in the second step. Become.

【0009】請求項3記載の発明では、第一の工程にお
いて、上下方向に一定長を有した鋼管からなる柱部材が
四隅に配され、かつこれら柱部材間に梁部材が架設され
た構成からなる柱ユニットを上下に定められた数接続し
た後、各柱部材内にコンクリートを打設するようにし
た。これにより、各柱には、柱部材内にコンクリートが
充填された充填鋼管コンクリート柱が四本備えられるこ
とになり、各柱が高い強度を有したものとなる。しか
も、柱ユニットを接続した後にコンクリートを打設する
ようにしたので、各柱ユニット自体は軽量なものとな
り、その設置時に大掛かりな揚重設備を用いる必要がな
い。
According to the third aspect of the present invention, in the first step, a column member made of a steel pipe having a certain length in the vertical direction is arranged at four corners, and a beam member is erected between these column members. After connecting a predetermined number of vertical column units, concrete was poured into each column member. As a result, each column is provided with four filled steel pipe concrete columns in which the column members are filled with concrete, and each column has a high strength. In addition, since the concrete is cast after connecting the pillar units, each pillar unit itself becomes lightweight, and it is not necessary to use a large-scale lifting equipment at the time of installation.

【0010】[0010]

【実施例】以下、本発明を図面に示す一実施例を参照し
て説明する。ここでは、例えば、火力発電所に備えるボ
イラーを収容するための建屋を構築する場合の実施例を
用いて説明する。図1は、本発明に係る建屋の構築方法
を適用して構築した建屋を示すものである。この図にお
いて、符号1は、ボイラー(機器)、2はボイラー1を
収容する建屋を示している。
DESCRIPTION OF THE PREFERRED EMBODIMENTS The present invention will be described below with reference to an embodiment shown in the drawings. Here, for example, an example in which a building for housing a boiler provided in a thermal power plant is constructed will be described. FIG. 1 shows a building constructed by applying the building construction method according to the present invention. In this figure, reference numeral 1 denotes a boiler (equipment), and 2 denotes a building that houses the boiler 1.

【0011】建屋2は、その四隅にコア柱(柱)3,
3,…が配され、コア柱3,3間には建屋2の外周部を
なす外周架構4が配され、さらにこれらコア柱3と外周
架構4の上端部には、建屋2全体の上面を覆う屋根架構
5が設けられた構成からなっている。
The building 2 has core pillars (pillars) 3 at its four corners.
Are arranged between the core pillars 3, 3, and an outer peripheral frame 4 that forms the outer peripheral portion of the building 2 is arranged. It has a configuration in which a covering roof frame 5 is provided.

【0012】図1(b)に示したように、各コア柱3
は、上下方向に接続された所定数の柱ユニット6から構
成されている。図2に示すように、各柱ユニット6は、
上下方向に一定長を有した断面視矩形の鋼管からなる柱
部材7,7,…が四隅に配され、互いに隣接する柱部材
7,7間の上下には、梁部材8,8が架設された構成と
なっている。なお、この柱ユニット6の下側に位置する
梁部材8aには、大梁としての断面寸法を有したものが
用いられ、上側に位置する梁部材8bには、つなぎ材と
しての断面寸法を有したものが用いられている。図1に
示したように、上下方向に所定数接続された柱ユニット
6,6,…において、その四隅で上下に連続する各柱部
材7内にはコンクリートが打設充填されている。これに
より、コア柱3には充填鋼管コンクリート造の柱10が
四本備えられた構成となっている。
As shown in FIG. 1B, each core pillar 3
Is composed of a predetermined number of pillar units 6 connected in the vertical direction. As shown in FIG. 2, each pillar unit 6
Column members 7, 7,... Made of a steel pipe having a certain length in the vertical direction and having a rectangular cross section are arranged at four corners, and beam members 8, 8 are erected above and below between the adjacent column members 7, 7. Configuration. The beam member 8a located on the lower side of the column unit 6 has a cross-sectional dimension as a large beam, and the beam member 8b located on the upper side has a cross-sectional dimension as a connecting member. Things are used. As shown in FIG. 1, in the column units 6, 6,... Connected in a predetermined number in the vertical direction, concrete is poured and filled in the column members 7 that are vertically continuous at the four corners. Thus, the core pillar 3 has a configuration in which four pillars 10 made of filled steel pipe concrete are provided.

【0013】外周架構4は、複数のブロック状の外周モ
ジュール11から形成されている。各外周モジュール1
1は、鉄骨造で、外周架構4の柱を構成する鉛直部材1
2と、梁を構成する水平部材13と、これらを補強する
ブレース材14とから形成されている。
The outer frame 4 is formed from a plurality of block-shaped outer modules 11. Each peripheral module 1
Reference numeral 1 denotes a vertical member 1 which is a steel frame and forms a column of an outer frame 4.
2, a horizontal member 13 forming a beam, and a brace member 14 for reinforcing these members.

【0014】屋根架構5は、鉄骨造で、上弦材15と、
下弦材16と、これらを連結する連結部材17と、ラチ
ス材18とがトラス状に組まれて形成されている。
The roof frame 5 is made of a steel frame and has an upper chord material 15 and
A lower chord member 16, a connecting member 17 for connecting these members, and a lattice member 18 are formed in a truss shape.

【0015】前記ボイラー1は、上記のような構成から
なる建屋2の中央部に収容されており、支持台19上に
設置されている。
The boiler 1 is accommodated in the center of the building 2 having the above-described configuration, and is installed on a support 19.

【0016】次に、上記の建屋2のコア柱3を構築する
に際して用いる仮設支柱20について、図3ないし図6
を参照して説明する。図3および図4に示すように、仮
設支柱20は、上下方向に一定長を有する支柱本体21
と、支柱本体21の一側面に沿って支柱本体21と一体
に設けられたガイド部材22と、ガイド部材22の両側
に沿って設けられたレール部材23とから構成されてい
る。
Next, a temporary support 20 used when constructing the core column 3 of the building 2 will be described with reference to FIGS.
This will be described with reference to FIG. As shown in FIGS. 3 and 4, the temporary support 20 is a support main body 21 having a certain length in the vertical direction.
And a guide member 22 provided integrally with the column main body 21 along one side surface of the column main body 21, and a rail member 23 provided along both sides of the guide member 22.

【0017】図4に示したように、ガイド部材22は、
断面視略コ字状で、支柱本体21の一側面21aに沿っ
た基部22aと、基部22aの両端部からこれと直交す
る方向に延出する側板部22b,22bとから形成され
ている。そして、図3に示すように、対向する側板部2
2b,22bには、それぞれ上下方向に一定間隔毎に、
矩形のストッパ穴24,24,…が形成されている。
As shown in FIG. 4, the guide member 22 is
It has a substantially U-shape in cross section, and includes a base 22a extending along one side surface 21a of the support body 21 and side plate portions 22b, 22b extending from both ends of the base 22a in a direction orthogonal to the base 22a. Then, as shown in FIG.
2b and 22b are provided at regular intervals in the vertical direction, respectively.
A rectangular stopper hole 24 is formed.

【0018】そして、ガイド部材22の側板部22b,
22b間には、上下方向に伸縮自在なジャッキ装置(ジ
ャッキアップ手段)25が配設されている。図5に示す
ように、ジャッキ装置25は、上端部と下端部とに、上
部ストッパ26,下部ストッパ27を具備した構成とさ
れている。上部ストッパ26,下部ストッパ27には、
それぞれ、相対向する水平方向に出没自在なストッパ部
材28,28が備えられている。
The side plate 22b of the guide member 22,
A jack device (jack-up means) 25 that is vertically expandable and contractible is provided between the terminals 22b. As shown in FIG. 5, the jack device 25 has an upper stopper 26 and a lower stopper 27 at an upper end and a lower end. The upper stopper 26 and the lower stopper 27
Each is provided with opposing stopper members 28, 28 which can be retracted in the horizontal direction.

【0019】このようなジャッキ装置25は、上部スト
ッパ26,下部ストッパ27それぞれのストッパ部材2
8,28を突出させてガイド部材22のストッパ穴2
4,24に挿入することによって、ガイド部材22,す
なわち仮設支柱20に係合するようになっている。そし
て、この状態から、ジャッキ装置25を下記〜の手
順で操作することにより、これをガイド部材22の側板
部22b,22b間において上昇させることができるよ
うになっている。 上部ストッパ26のストッパ部材28,28をスト
ッパ穴24,24から退去させる。 ジャッキ装置25を、ガイド部材22のストッパ穴
24,24の間隔と同寸法だけ伸長させる。 上部ストッパ26のストッパ部材28,28を突出
させてストッパ穴24,24に挿入させる。 下部ストッパ27のストッパ部材28,28をスト
ッパ穴24,24から退去させる。 ジャッキ装置25を、ガイド部材22のストッパ穴
24,24の間隔と同寸法だけ収縮させる。 下部ストッパ27のストッパ部材28,28を突出
させてストッパ穴24,24に挿入させる。
Such a jack device 25 includes a stopper member 2 for each of an upper stopper 26 and a lower stopper 27.
8 and 28 are projected so that the stopper hole 2 of the guide member 22 is formed.
The guide members 22, that is, the temporary support columns 20 are engaged with the guide members 22 by inserting them into the support members 4, 24. In this state, the jack device 25 can be raised between the side plates 22b and 22b of the guide member 22 by operating the jack device 25 in the following procedures. The stopper members 28, 28 of the upper stopper 26 are retreated from the stopper holes 24, 24. The jack device 25 is extended by the same dimension as the interval between the stopper holes 24 of the guide member 22. The stopper members 28, 28 of the upper stopper 26 are made to protrude and inserted into the stopper holes 24, 24. The stopper members, of the lower stopper 27 are retreated from the stopper holes,. The jack device 25 is contracted by the same dimension as the interval between the stopper holes 24 of the guide member 22. The stopper members 28, 28 of the lower stopper 27 are made to protrude and inserted into the stopper holes 24, 24.

【0020】そして、図4に示したように、柱ユニット
6の各柱部材7に上記構成の仮設支柱20をそれぞれ配
し、各仮設支柱20のジャッキ装置25の上端部でそれ
ぞれ柱部材7の側面に形成された梁ブラケット29を支
持して、各ジャッキ装置25を上述したようにして一斉
に上昇させることにより、柱ユニット6をプッシュアッ
プできるようになっている。
Then, as shown in FIG. 4, the temporary columns 20 having the above-mentioned construction are respectively arranged on the respective column members 7 of the column unit 6, and the upper ends of the jack devices 25 of the respective temporary columns 20 are respectively provided for the column members 7. The column unit 6 can be pushed up by supporting the beam bracket 29 formed on the side surface and simultaneously raising the jack devices 25 as described above.

【0021】図3に示したように、前記ガイド部材23
は、断面視略コ字状で、上下方向に一定長にわたって支
柱本体21に設けられている。図6に示すように、柱ユ
ニット6の、ガイド部材23と対向した位置には、水平
方向に伸縮自在なジャッキ機構30が備えられ、その先
端部にはガイドローラ31が回転自在に設けられてい
る。そして、ジャッキ機構30を伸長させてガイドロー
ラ31をガイド部材23内に位置させることにより、前
記柱ユニット6の上昇時にこれをガイドするようになっ
ている。
As shown in FIG. 3, the guide member 23
Is substantially U-shaped in cross section, and is provided on the column body 21 over a certain length in the vertical direction. As shown in FIG. 6, the column unit 6 is provided with a jack mechanism 30 which can be extended and contracted in the horizontal direction at a position facing the guide member 23, and a guide roller 31 is rotatably provided at a tip end thereof. I have. By extending the jack mechanism 30 and positioning the guide roller 31 in the guide member 23, the column unit 6 is guided when the column unit 6 is raised.

【0022】次いで、前記建屋2の構築方法について、
図1ないし図13を参照して説明する。 [第一の工程]まず、図7に示すように、地上におい
て、立設すべきコア柱3,3,…のうち、一箇所におい
て、所定の位置に仮設支柱20,20,…を配置する。
そして、柱ユニット6を仮設支柱20,20,…のジャ
ッキ装置25,25,…(図5参照)上にセットする。
次いで、ジャッキ装置25,25,…を一斉に作動させ
て柱ユニット6をプッシュアップさせる。続いて、プッ
シュアップした柱ユニット6の下方の地上に新たに他の
柱ユニット6をセットし、上下の柱ユニット6,6を接
続する。そして、各仮設支柱20のジャッキ装置25を
ガイド部材22に沿って下降させ、下方の柱ユニット6
に盛り替える(図3)。
Next, the construction method of the building 2 will be described.
This will be described with reference to FIGS. [First Step] First, as shown in FIG. 7, on the ground, among the core pillars 3, 3,... To be erected, temporary pillars 20, 20,. .
Then, the column unit 6 is set on the jack devices 25, 25,... (See FIG. 5) of the temporary columns 20, 20,.
Next, the jack devices 25, 25,... Are operated simultaneously to push up the column unit 6. Subsequently, another pillar unit 6 is newly set on the ground below the pushed up pillar unit 6, and the upper and lower pillar units 6, 6 are connected. Then, the jack device 25 of each temporary support 20 is lowered along the guide member 22, and the lower column unit 6
(Fig. 3).

【0023】この後、上記と同様に、柱ユニット6のプ
ッシュアップ作業,新たな柱ユニット6の接続作業(柱
延長作業),ジャッキ装置25の盛り替え作業を順次繰
り返していき、接続した柱ユニット6,6,…の高さが
所定の高さに達したら、上方から柱ユニット6の各柱部
材7内にコンクリートを打設充填する。このようにし
て、その四隅に充填鋼管コンクリート造の柱10を有し
たコア柱3が立設されたことになる。
Thereafter, in the same manner as described above, the push-up operation of the column unit 6, the connection operation of the new column unit 6 (post extension operation), and the rearrangement operation of the jack device 25 are sequentially repeated, and the connected column units are sequentially repeated. When the height of 6, 6,... Reaches a predetermined height, concrete is poured and filled into each column member 7 of the column unit 6 from above. Thus, the core pillar 3 having the pillars 10 made of concrete filled with steel pipes at the four corners is erected.

【0024】この後、上記と全く同様にして、他のコア
柱3,3,3を順次構築していく。このとき、柱ユニッ
ト6のプッシュアップに用いる仮設支柱20,20,…
は、順次転用していくようにする。
Thereafter, the other core pillars 3, 3, 3 are sequentially constructed in exactly the same manner as described above. At this time, the temporary columns 20, 20,.
Are diverted sequentially.

【0025】図8に示すように、このようにして構築し
た各コア柱3の上面には、例えばウインチ等からなる揚
重機構(揚重手段)32をそれぞれ設置する。
As shown in FIG. 8, a lifting mechanism (lifting means) 32 composed of, for example, a winch is installed on the upper surface of each core pillar 3 constructed in this manner.

【0026】次いで、構築すべき建屋2の相対向する側
面A,Bにおいて、それぞれ、隣接するコア柱3,3の
上端部間に、外周架構4の最上層部を構成する外周モジ
ュール11aを揚重機構32で吊り上げて架設する。
Next, on the opposing side surfaces A and B of the building 2 to be constructed, the outer peripheral module 11a constituting the uppermost layer of the outer peripheral frame 4 is lifted between the upper ends of the adjacent core pillars 3 and 3, respectively. It is suspended by the heavy mechanism 32 and installed.

【0027】続いて、図9に示すように、建屋2の側面
C,Dにおいて隣接するコア柱3,3間で外周架構4の
最上層部を構成する外周モジュール11b,11bと、
屋根架構5とを、揚重機構32,32で吊り上げて架設
する。このとき、外周モジュール11b,11bと屋根
架構5は、地上において一体に組み立てておくものとす
る。この時点で、コア柱3,3,…と、屋根架構5と、
外周架構4の上層部とが一体に構築されて、ボイラー1
(図1参照)を搬入するときにその荷重を支持するため
のコア架構33(図10参照)が構成されたことにな
る。そして、外周架構4の上層部を構成する外周モジュ
ール11a,11a,11b,11bによって、コア架
構33のコア柱3と屋根架構5との接合部が補強された
ことになる。
Next, as shown in FIG. 9, the outer peripheral modules 11b, 11b constituting the uppermost layer of the outer frame 4 between the adjacent core pillars 3, 3 on the side surfaces C, D of the building 2,
The roof frame 5 is suspended and lifted by the lifting mechanisms 32, 32. At this time, the outer peripheral modules 11b, 11b and the roof frame 5 are to be assembled integrally on the ground. At this point, the core pillars 3, 3, ..., the roof frame 5,
The upper layer of the outer frame 4 is integrally constructed, and the boiler 1
This means that a core frame 33 (see FIG. 10) for supporting the load when carrying in (see FIG. 1) is configured. Then, the joint between the core column 3 of the core frame 33 and the roof frame 5 is reinforced by the outer modules 11a, 11a, 11b, 11b constituting the upper layer of the outer frame 4.

【0028】[第二の工程]次に、このようにして構築
したコア架構33の内方に、ボイラー1を搬入・設置す
る。これに先立ち、まず、図10に示すように、側面B
側において、先に取り付けた外周モジュール11aの下
方に、外周モジュール11,11,…を上方から下方に
向けて順次取り付ける。ただし、これは、構築すべき建
屋2の敷地が狭隘で、側面B側からは資材を搬入するこ
とができない場合にのみ行う。
[Second Step] Next, the boiler 1 is loaded and installed inside the core frame 33 constructed as described above. Prior to this, first, as shown in FIG.
On the side, the outer peripheral modules 11, 11,... Are sequentially mounted from the upper side to the lower side below the previously mounted outer peripheral module 11a. However, this is performed only when the site of the building 2 to be constructed is narrow and it is not possible to carry in materials from the side B side.

【0029】続いて、図11に示すように、設置すべき
ボイラー1の上半部1aを移動台車35上に搭載し、こ
れを側面A側から図中矢印方向に移動させて建屋2内の
所定の位置まで搬入する。そして、このボイラー1の上
半部1aを、屋根架構5に備えた揚重機構34(吊下手
段)で吊り上げて保持する。
Subsequently, as shown in FIG. 11, the upper half 1a of the boiler 1 to be installed is mounted on a movable carriage 35, and is moved from the side A in the direction of the arrow in FIG. Carry in to a predetermined position. Then, the upper half 1a of the boiler 1 is lifted and held by a lifting mechanism 34 (suspension means) provided on the roof frame 5.

【0030】次いで、図12に示すように、ボイラー1
の下半部1bを、同様にして側面A側から建屋2内の所
定位置まで移動台車35で搬入する。そして、吊り上げ
ていたボイラー1の上半部1aを下降させて下半部1b
に当接させた後、上半部1aと下半部1bとを溶接して
一体化する。この後、一体化したボイラー1を揚重機構
34で吊り上げておいて、その下方から移動台車35を
引き出す。そして、図13に示すように、ボイラー1を
下降させて支持台19上にボイラー1を載置・固定す
る。
Next, as shown in FIG.
The lower half 1b is similarly carried in from the side A to a predetermined position in the building 2 by the movable carriage 35. Then, the upper half 1a of the boiler 1 that has been lifted is lowered to lower half 1b.
After that, the upper half 1a and the lower half 1b are welded and integrated. Thereafter, the integrated boiler 1 is lifted by the lifting mechanism 34, and the movable carriage 35 is pulled out from below. Then, as shown in FIG. 13, the boiler 1 is lowered to place and fix the boiler 1 on the support base 19.

【0031】[第三の工程]このようにしてボイラー1
を設置した後、外周架構4を構築する。側面C,D側に
おいて、それぞれ、外周モジュール11,11,…を揚
重機構32で揚重して順次上方から下方に取り付けてい
く。そして最後に、同様にして外周モジュール11,1
1,…を側面A側に取り付けていく。このようにして、
図1に示したように、外周架構4の構築が完了した後、
揚重機構32,34を解体,撤去することによって、建
屋2の構築が完了する。
[Third Step] In this manner, the boiler 1
After the installation, the outer frame 4 is constructed. On the side surfaces C and D, the outer peripheral modules 11, 11,... Are lifted by the lifting mechanism 32 and are sequentially attached from above to below. And finally, in the same manner, the outer peripheral modules 11, 1
Are attached to the side A side. In this way,
As shown in FIG. 1, after the construction of the outer frame 4 is completed,
By dismantling and removing the lifting mechanisms 32 and 34, the construction of the building 2 is completed.

【0032】上述した建屋2の構築方法では、第一の工
程でコア柱3と屋根架構5とを構築してコア架構33を
形成し、第二の工程でコア架構33にボイラー1を吊り
込んでこれを定められた位置に設置し、第三の工程で外
周架構4を構築することによって、建屋2を構築する構
成とした。このようにして、建屋2のコア柱3と屋根架
構5とを構築してコア架構33を構築した時点で、外周
架構4の構築に先立ってボイラー1を設置するようにし
たので、外周架構4の構築作業と並行してボイラー1の
試運転等を行うことができ、これによってボイラー1の
運転開始を早期化することが可能となる。
In the construction method of the building 2 described above, the core pillar 3 and the roof frame 5 are constructed in the first step to form the core frame 33, and the boiler 1 is suspended in the core frame 33 in the second step. In the third step, the building 2 was constructed by installing the apparatus at a predetermined position and constructing the outer frame 4 in the third step. In this way, when the core pillar 3 and the roof frame 5 of the building 2 are constructed and the core frame 33 is constructed, the boiler 1 is installed prior to the construction of the outer frame 4. The trial operation of the boiler 1 and the like can be performed in parallel with the construction work of the above, so that the operation start of the boiler 1 can be accelerated.

【0033】また、第一の工程でコア架構33を構築し
た後に、屋根架構5の下面に外周架構4の上層部を構成
する外周モジュール11a,11bを先付けする構成と
した。これにより、先付けした外周モジュール11a,
11bによってコア架構33が強化され、第二の工程で
ボイラー1を吊り込むに際して、その荷重に抗すること
が可能となる。この結果、ボイラー1を吊り込むための
剛性確保のためだけに設置する仮設の補強部材を最小限
とすることができ、これとともに屋根架構5を構成する
部材の断面を最小限まで小さすることにより、コストを
抑さえることが可能となる。
After the core frame 33 is constructed in the first step, the outer modules 11a and 11b constituting the upper layer of the outer frame 4 are attached to the lower surface of the roof frame 5 in advance. As a result, the outer peripheral modules 11a,
11b reinforces the core frame 33, and when the boiler 1 is suspended in the second step, it becomes possible to withstand the load. As a result, it is possible to minimize the number of temporary reinforcing members installed only for securing the rigidity for suspending the boiler 1, and to reduce the cross section of the members constituting the roof frame 5 to a minimum. Thus, the cost can be suppressed.

【0034】さらに、第一の工程においてコア柱3を構
築するに際して、まず、柱ユニット6を設置し、しかる
後に仮設支柱20,20,…に備えたジャッキ装置2
5,25,…で柱ユニット6をプッシュアップさせるプ
ッシュアップ作業と、プッシュアップした柱ユニット6
の下方に新たに柱ユニット6を設置してコア柱3を延長
する柱延長作業とを交互に繰り返す構成とした。これに
より、地上においてコア柱3の構築作業を行うことがで
き、高所における作業を削減して安全性を高めることが
できる。また、屋根架構5を予め地組しておき、これを
コア柱3に備えた揚重機構32で揚重して設置する構成
としたので、高所における屋根架構3の組立作業を最小
限とすることができる。この点からも作業の安全性を高
めることが可能となる。さらに、コア柱3,屋根架構5
に揚重機構32,34を備える構成としたので、特に他
の揚重機器等を地上に設置することなく建屋2の施工を
行うことができ、従来の工法では建屋2を構築すること
ができなかった狭隘な敷地であっても建屋2を構築する
ことが可能となる。
Further, in constructing the core pillar 3 in the first step, first, the pillar unit 6 is installed, and then the jack device 2 provided on the temporary pillars 20, 20,.
The push-up operation of pushing up the pillar unit 6 with 5, 25,... And the pushed-up pillar unit 6
And a column extension operation of newly installing a column unit 6 below and extending the core column 3 is alternately repeated. Thereby, the construction work of the core pillar 3 can be performed on the ground, and the work at high places can be reduced and safety can be improved. In addition, since the roof frame 5 is laid in advance and is lifted and installed by the lifting mechanism 32 provided on the core column 3, the work of assembling the roof frame 3 at a high place can be minimized. can do. From this point as well, it is possible to enhance the safety of work. Furthermore, core pillar 3, roof frame 5
Since the structure is provided with the lifting mechanisms 32 and 34, the building 2 can be constructed without installing other lifting equipment and the like on the ground, and the building 2 can be constructed by the conventional construction method. The building 2 can be constructed even on a narrow site that has not been found.

【0035】加えて、外周架構4を多数の外周モジュー
ル11から構成するようにしたので、作業の効率化を図
るとともに、この点からも高所作業を削減して作業の安
全性を向上させることができる。
In addition, since the outer frame 4 is composed of a large number of outer modules 11, work efficiency can be improved, and work in high places can be reduced, and work safety can be improved. Can be.

【0036】また、第一の工程でコア柱3を構築するに
際し、所定数の柱ユニット6,6,…を上下に接続した
後、柱ユニット6の四隅に配した鋼管からなる各柱部材
7内にコンクリートを打設するようにした。これによ
り、各コア柱3には、充填鋼管コンクリート造の柱10
が四本備えられることになり、各コア柱3が高い強度を
有したものとなる。しかも、各柱ユニット6自体が軽量
なものとなり、その取り扱いも容易であるので、設置時
に大掛かりな揚重設備を用いる必要がなく、高い強度を
有したコア柱3を容易に構築することができる。
In constructing the core column 3 in the first step, a predetermined number of column units 6, 6,... Are connected up and down, and then each column member 7 made of a steel pipe arranged at the four corners of the column unit 6. Concrete was poured inside. As a result, each core column 3 has a filled steel tube concrete column 10
Are provided, and each core column 3 has high strength. Moreover, since each pillar unit 6 itself is lightweight and easy to handle, there is no need to use a large-scale lifting equipment at the time of installation, and the core pillar 3 having high strength can be easily constructed. .

【0037】なお、上記実施例において、建屋2の用途
は上記に限定するものではなく、ボイラー1以外の機器
や設備を収納する構成としてもよいのは言うまでもな
い。また、仮設支柱20を用いたコア柱3の構築方法
は、上記のような構成の建屋2だけでなく、上下方向に
長い柱を有した架構構造物等においても効果的に適用す
ることができる。
In the above embodiment, the use of the building 2 is not limited to the above, and it goes without saying that the building 2 may be configured to accommodate equipment and facilities other than the boiler 1. In addition, the method of constructing the core pillar 3 using the temporary support pillars 20 can be effectively applied to not only the building 2 having the above-described configuration but also a frame structure having columns vertically long. .

【0038】[0038]

【発明の効果】以上説明したように、請求項1に係る建
屋の構築方法によれば、第一の工程で建屋の柱と屋根架
構とを構築し、第二の工程で屋根架構に備えた吊下手段
で機器,設備を吊り込んでこれを定められた位置に設置
し、第三の工程で外周架構を構築することによって、建
屋を構築する構成とした。このようにして、建屋の柱と
屋根架構を構築した時点で、外周架構の構築に先立って
機器,設備を設置するようにしたので、外周架構の構築
作業と並行して機器,設備の試運転等を行うことがで
き、これによって機器,設備の運転開始を早期化するこ
とが可能となる。また、第一の工程において前記柱を構
築するに際して、まず、本設の柱の全長のうちの一部を
立設し、しかる後に仮設支柱に備えたジャッキアップ手
段で、柱をプッシュアップさせるプッシュアップ作業
と、プッシュアップさせた柱の下方において柱を延長構
築する柱延長作業とを交互に繰り返す構成とした。これ
により、地上において柱の構築作業を行うことができ高
所作業を大幅に削減して作業の安全性を向上させること
ができる。また、屋根架構を予め地組しておき、これを
柱に備えた揚重手段で揚重して設置する構成としたの
で、高所における屋根架構の組立作業を最小限とするこ
とができ、この点からも作業の安全性を大幅に向上させ
ることができる。さらには、このようにして柱や屋根架
構に例えばウインチ等の揚重手段を備えることによっ
て、特に他の揚重機器等を地上に設置することなく建屋
の施工を行うことができ、従来の工法では建屋を構築す
ることができなかった狭隘な敷地であっても建屋を構築
することが可能となる。
As described above, according to the building construction method of the first aspect, the pillars and the roof frame of the building are constructed in the first step, and the roof frame is provided in the second step. The building is constructed by suspending the equipment and facilities by the suspending means, installing them at predetermined positions, and constructing the outer frame in the third step. In this way, when the pillars and the roof frame of the building are constructed, the equipment and facilities are installed prior to the construction of the outer frame, so that the equipment and facilities are tested in parallel with the construction of the outer frame. This makes it possible to early start the operation of the devices and equipment. Further, when constructing the pillar in the first step, firstly, a part of the total length of the main pillar is erected, and then the push-up means for pushing up the pillar by jack-up means provided on the temporary pillar is provided. The up work and the pillar extension work of extending and constructing the pillar below the pushed-up pillar are alternately repeated. Thereby, the construction work of the pillar can be performed on the ground, and the work at height can be significantly reduced, and the safety of the work can be improved. In addition, since the roof frame is pre-grounded and lifted and installed by the lifting means provided on the pillars, assembly work of the roof frame at a high place can be minimized. From this point of view, the safety of work can be greatly improved. Furthermore, by providing a lifting means such as a winch on the pillar or the roof frame in this way, the building can be constructed without installing other lifting equipment and the like in particular on the ground. Then, it is possible to build a building even on a narrow site where a building could not be built.

【0039】請求項2に係る建屋の構築方法によれば、
第一の工程の後に、構築した屋根架構の下面に一定長の
外周架構を先付けし、しかる後に第二の工程を行う構成
とした。これにより、先付けした外周架構によって屋根
架構と柱とから構成される架構が強固なものとなり、第
二の工程で機器や設備を吊り込むに際して、その荷重に
抗することが可能となる。この結果、機器や設備を吊り
込むための剛性確保のためだけに設置する仮設の補強部
材を最小限とすることができ、これとともに屋根架構等
を構成する部材の断面を最小限まで小さくしてコストを
抑さえることが可能となる。
According to the building construction method of the second aspect,
After the first step, a fixed-length outer peripheral frame was attached to the lower surface of the constructed roof frame, and then the second step was performed. Thus, the frame composed of the roof frame and the pillars is strengthened by the attached outer frame, and it becomes possible to withstand the load when suspending equipment and facilities in the second step. As a result, it is possible to minimize the number of temporary reinforcing members installed only for securing rigidity for suspending equipment and facilities, and to reduce the cross section of members constituting the roof frame and the like to the minimum. Costs can be reduced.

【0040】請求項3に係る建屋の構築方法によれば、
第一の工程で柱を構築するに際し、柱ユニットを上下に
複数接続した後、柱ユニットの四隅に配した鋼管からな
る各柱部材内にコンクリートを打設するようにした。こ
れにより、各柱には、充填鋼管コンクリート柱が四本備
えられることになり、各柱が高い強度を有したものとな
る。しかも、各柱ユニットが軽量なものとなり、その取
り扱いも容易で、設置時に大掛かりな揚重設備を用いる
必要がない。したがって、高い強度を有した柱を容易に
構築することができる。
According to the building construction method of the third aspect,
In constructing a pillar in the first step, after connecting a plurality of pillar units up and down, concrete was poured into each pillar member composed of steel pipes arranged at the four corners of the pillar unit. As a result, each column is provided with four filled steel pipe concrete columns, and each column has a high strength. Moreover, each pillar unit is lightweight, easy to handle, and does not require large-scale lifting equipment at the time of installation. Therefore, a pillar having high strength can be easily constructed.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明に係る建屋の構築方法を適用して構築し
た建屋の一例を示す図であって、(a)平面図,(b)
正面図である。
FIG. 1 is a diagram showing an example of a building constructed by applying a building construction method according to the present invention, wherein FIG.
It is a front view.

【図2】前記建屋の柱を構成する柱ユニットを示す斜視
図である。
FIG. 2 is a perspective view showing a pillar unit constituting the pillar of the building.

【図3】前記柱ユニットを設置するのに用いる仮設支柱
を示す正面図である。
FIG. 3 is a front view showing a temporary support used for installing the column unit.

【図4】前記仮設支柱の設置状態を示す平面図である。FIG. 4 is a plan view showing an installation state of the temporary support.

【図5】前記仮設支柱に備えたジャッキアップ手段を示
す図であって、(a)正面図,(b)側面図である。
FIGS. 5A and 5B are diagrams showing jack-up means provided on the temporary support column, wherein FIG. 5A is a front view and FIG. 5B is a side view.

【図6】前記仮設支柱に備えたガイド機構を示す図であ
って、(a)正面図,(b)平面図である。
FIGS. 6A and 6B are views showing a guide mechanism provided on the temporary support column, wherein FIG. 6A is a front view and FIG.

【図7】前記建屋の構築方法の工程を示す図であって、
柱を構築している状態を示す図であって、(a)平面
図,(b)側面図である。
FIG. 7 is a diagram showing steps of the building construction method,
It is a figure which shows the state which is constructing a pillar, (a) is a top view, (b) is a side view.

【図8】同、柱の全長の構築が完了し、最上部の外周架
構を取り付けている状態を示す図であって、(a)平面
図,(b)側面図である。
FIG. 8 is a view showing a state in which the construction of the entire length of the pillar has been completed and the outermost frame at the top has been mounted, and FIG. 8 (a) is a plan view and FIG.

【図9】同、前記最上部の他の外周架構および屋根架構
を取り付けている状態を示す図であって、(a)平面
図,(b)正面図である。
FIG. 9 is a view showing a state in which another outer peripheral frame and a roof frame are attached to the uppermost part, in which (a) is a plan view and (b) is a front view.

【図10】同、前記外周架構を取り付けている状態を示
す図であって、(a)平面図,(b)背面図である。
FIG. 10 is a view showing a state where the outer frame is attached, in which FIG. 10 (a) is a plan view and FIG. 10 (b) is a rear view.

【図11】同、建屋に収容する機器の上半部を搬入した
状態を示す図であって、(a)平面図,(b)側面図で
ある。
FIG. 11 is a view showing a state where the upper half of the equipment housed in the building has been carried in, (a) a plan view and (b) a side view.

【図12】同、前記機器の下半部を搬入した状態を示す
図であって、(a)平面図,(b)側面図である。
FIG. 12 is a view showing a state in which the lower half of the device is carried in, in which (a) is a plan view and (b) is a side view.

【図13】同、前記機器の設置が完了した状態を示す図
であって、(a)平面図,(b)側面図である。
FIG. 13 is a diagram showing a state in which the installation of the device is completed, wherein (a) is a plan view and (b) is a side view.

【符号の説明】[Explanation of symbols]

1 ボイラー(機器) 2 建屋 3 コア柱(柱) 4 外周架構 5 屋根架構 6 柱ユニット 7 柱部材 8 梁部材 9 コンクリート 20 仮設支柱 25 ジャッキ装置(ジャッキアップ手段) 32 揚重機構(揚重手段) 34 揚重機構(吊下手段) DESCRIPTION OF SYMBOLS 1 Boiler (equipment) 2 Building 3 Core pillar (column) 4 Perimeter frame 5 Roof frame 6 Column unit 7 Column member 8 Beam member 9 Concrete 20 Temporary support 25 Jack device (jack-up means) 32 Lifting mechanism (lifting means) 34 Lifting mechanism (suspension means)

───────────────────────────────────────────────────── フロントページの続き (56)参考文献 特開 平6−185124(JP,A) 特開 平6−158733(JP,A) (58)調査した分野(Int.Cl.7,DB名) E04H 5/02 E04B 1/35 ────────────────────────────────────────────────── ─── Continuation of the front page (56) References JP-A-6-185124 (JP, A) JP-A-6-158733 (JP, A) (58) Fields investigated (Int. Cl. 7 , DB name) E04H 5/02 E04B 1/35

Claims (3)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 大型の機器や設備等を収容する建屋の構
築方法であって、前記建屋の柱を構築した後に、予め地
組した屋根架構を前記柱に備えた揚重手段で揚重して設
置する第一の工程と、収容すべき前記機器,設備を前記
屋根架構に備えた吊下手段で吊り込んで定められた位置
に設置する第二の工程と、前記建屋の外周をなす外周架
構を構築する第三の工程とからなり、 前記第一の工程において前記柱を構築するに際しては、
まず、前記柱の全長のうちの一部を立設し、しかる後
に、該柱の側方に立設した仮設支柱に備えたジャッキア
ップ手段で、前記柱をプッシュアップさせるプッシュア
ップ作業と、プッシュアップさせた前記柱の下方におい
て前記柱を延長構築する柱延長作業とを交互に繰り返す
ようにしたことを特徴とする建屋の構築方法。
1. A method of constructing a building for accommodating large-scale equipment, equipment, and the like, comprising: constructing a pillar of the building, and then lifting a prefabricated roof frame by a lifting means provided on the pillar. A first step of installing the equipment and facilities to be accommodated, and a second step of suspending the equipment and facilities to be accommodated by hanging means provided on the roof frame and installing the equipment and facilities at predetermined positions, and forming an outer periphery of the building And a third step of constructing a frame. In constructing the pillar in the first step,
First, a part of the entire length of the pillar is erected, and thereafter, a push-up operation of pushing up the pillar by a jack-up means provided on a temporary support pillar erected on the side of the pillar, A method of constructing a building, wherein a column extension operation of extending and constructing the pillar is alternately repeated below the pillar that has been raised.
【請求項2】 請求項1記載の建屋の構築方法におい
て、前記第一の工程の後に、前記第一の工程で構築した
屋根架構の下面に前記外周架構の一部を先付けして前記
柱と一体化し、しかる後に前記第二の工程を行うことを
特徴とする建屋の構築方法。
2. The method for building a building according to claim 1, wherein after the first step, a part of the outer peripheral frame is pre-attached to a lower surface of the roof frame constructed in the first step, and the column is formed. A method for constructing a building, comprising integrating and then performing the second step.
【請求項3】 請求項1または2記載の建屋の構築方法
において、前記第一の工程で、上下方向に一定長を有し
た筒状の鋼管からなる柱部材が四隅に配され、かつこれ
ら柱部材間に梁部材が架設された構成からなる柱ユニッ
トを上下に定められた数接続した後、前記各柱部材内に
コンクリートを打設することにより、前記柱を構築する
ようにしたことを特徴とする建屋の構築方法。
3. The method for constructing a building according to claim 1, wherein in the first step, pillar members made of a tubular steel pipe having a certain length in the vertical direction are arranged at four corners, and these pillars are provided. After connecting a predetermined number of column units having a configuration in which a beam member is erected between members, a concrete is poured into each of the column members, thereby constructing the columns. And how to build the building.
JP24168094A 1994-10-05 1994-10-05 How to build a building Expired - Fee Related JP3225455B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP24168094A JP3225455B2 (en) 1994-10-05 1994-10-05 How to build a building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP24168094A JP3225455B2 (en) 1994-10-05 1994-10-05 How to build a building

Publications (2)

Publication Number Publication Date
JPH08105228A JPH08105228A (en) 1996-04-23
JP3225455B2 true JP3225455B2 (en) 2001-11-05

Family

ID=17077927

Family Applications (1)

Application Number Title Priority Date Filing Date
JP24168094A Expired - Fee Related JP3225455B2 (en) 1994-10-05 1994-10-05 How to build a building

Country Status (1)

Country Link
JP (1) JP3225455B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US8312509B2 (en) 2006-09-21 2012-11-13 Intel Corporation High integrity firmware

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US8312509B2 (en) 2006-09-21 2012-11-13 Intel Corporation High integrity firmware

Also Published As

Publication number Publication date
JPH08105228A (en) 1996-04-23

Similar Documents

Publication Publication Date Title
EP0487516B1 (en) Construction apparatus and construction method
JP3225455B2 (en) How to build a building
JP3225456B2 (en) How to build a building
JPH1061193A (en) Method of building steel frame structure and device therefor
JPH04161566A (en) Constructing apparatus for large space building
JP2678403B2 (en) Construction method of building structure and connection method of pillar members
JP3073371B2 (en) Tower-like structure erection method and equipment
JP2008214932A (en) Construction method for building
JPH06146578A (en) Method of constructing climbing-stage of cylindrical structure and construction of chimney
JP3239154B2 (en) Lift-up device for all-weather temporary roof
JPH08165662A (en) Construction method of underground structure
JP3543247B2 (en) Temporary living support bracket
JP3179814B2 (en) Column and beam construction method and apparatus
JP2884396B2 (en) Construction method of building structure and lifting device of building structure
JP2777516B2 (en) Construction method of high-rise structure
JP2871468B2 (en) How to build a building
JP2884398B2 (en) Construction method of building structure and lifting device of building structure
JP3715378B2 (en) Automatic roof raising device and method of building a building by raising the roof
JP3192543B2 (en) Building demolition method
JP2876991B2 (en) Steel frame method for high-rise buildings
JP2761527B2 (en) How to build structures
JP2939752B2 (en) Lift-up method in which an outer wall plate is attached to the floor plate
JP2842034B2 (en) Lifting device for building frame
JP2946372B2 (en) Construction method of structure
JP3781497B2 (en) How to install beams

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20010724

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110831

Year of fee payment: 10

LAPS Cancellation because of no payment of annual fees