JP2778842B2 - Building construction method - Google Patents

Building construction method

Info

Publication number
JP2778842B2
JP2778842B2 JP3010371A JP1037191A JP2778842B2 JP 2778842 B2 JP2778842 B2 JP 2778842B2 JP 3010371 A JP3010371 A JP 3010371A JP 1037191 A JP1037191 A JP 1037191A JP 2778842 B2 JP2778842 B2 JP 2778842B2
Authority
JP
Japan
Prior art keywords
temporary
pillar
rooftop
building
column
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP3010371A
Other languages
Japanese (ja)
Other versions
JPH04238929A (en
Inventor
政喜 石井
隆明 丸田
竹二 松本
廣毅 村本
美徳 向谷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitsubishi Heavy Industries Ltd
Original Assignee
Mitsubishi Heavy Industries Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitsubishi Heavy Industries Ltd filed Critical Mitsubishi Heavy Industries Ltd
Priority to JP3010371A priority Critical patent/JP2778842B2/en
Publication of JPH04238929A publication Critical patent/JPH04238929A/en
Application granted granted Critical
Publication of JP2778842B2 publication Critical patent/JP2778842B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】本発明はビルの建設方法に関し、
特に高層ビルの建設に用いて好適なものである。
BACKGROUND OF THE INVENTION The present invention relates to a method for building a building.
It is particularly suitable for use in the construction of high-rise buildings.

【0002】[0002]

【従来の技術】一般に高層ビルの建設は、クライミング
クレーンを使用してビルの柱,梁,床等のく体部材を地
上から吊り上げ、ビルを下層階から上層階へ順次部材単
位で積上げて建造する方法が行なわれている。このよう
なビルの建設を効率良く行なうことを狙って、建設され
るビルの最上階を油圧ジャッキで押上げながら、その下
側でビルの建造を進める建設方法(特開平2−7084
4)が提案されている。
2. Description of the Related Art In general, a high-rise building is constructed by using a climbing crane to lift building members such as pillars, beams, floors and the like from the ground, and building the building sequentially from a lower floor to an upper floor in units of members. There is a way to be done. With the aim of efficiently constructing such a building, a construction method in which the top floor of the building to be constructed is pushed up with a hydraulic jack and the building is advanced below the building (Japanese Patent Laid-Open No. 2-7084)
4) has been proposed.

【0003】[0003]

【発明が解決しようとする課題】上記従来の方法は何れ
も地上から高所へビルの柱,梁,床等の部材を順を追っ
て運び上げ、高所の建造階で一部材ずつ順々に積上げ接
合していくため、部材の運び上げ搬送に時間が掛かり、
工期が長びき、作業時間と工期を短縮し難いものであっ
た。また、ビルの最上階をジャッキアップさせながら建
造を進めるために、油圧ジャッキやクレーン等大型の仮
設機材を高所作業階に持上げて使用する必要があるが、
この場合、高所作業階での部材の搬入、接合作業の邪魔
となり、干渉を避けるために作業の進め方が複雑にな
り、危険が多くなっていた。また、ビル建設の最終段階
では、これら仮設機材の解体、撤去が狭いスペースの中
で困難になる等の問題点があった。
In each of the above-mentioned conventional methods, members such as pillars, beams, floors, etc. of a building are carried in order from the ground to a high place, and one member at a time on a building floor at a high place. Since the components are stacked and joined, it takes time to carry and transport the components.
The construction period was long, and it was difficult to shorten the working time and the construction period. In addition, in order to proceed with construction while jacking up the top floor of the building, it is necessary to lift large temporary equipment such as hydraulic jacks and cranes to work on high places,
In this case, it becomes a hindrance to carrying in and joining members on the working floor at a high place, and the way of working is complicated to avoid interference, which has increased the danger. In the final stage of building construction, there were also problems such as the difficulty in dismantling and removing these temporary equipment in a narrow space.

【0004】[0004]

【課題を解決するための手段】上記課題を解決するため
の本発明のビルの建設方法は、屋上階部を架設用構造体
として地上で組立て、ビル本設柱上に下端が嵌合可能な
外側仮柱と内側仮柱を前記屋上階部を貫通して昇降自在
に設け、前記屋上階部に対して前記外側仮柱と前記内側
仮柱の昇降駆動を行なう昇降固定手段を備え、前記屋上
階部の架下に前記外側仮柱と前記内側仮柱の並設方向に
延びる走行レールを設け、巻上装置を備えた走行手段を
前記走行レールに備え、前記外側仮柱の下端を前記ビル
本設柱上に嵌合し前記昇降固定手段によって該外側仮柱
の最上段に前記屋上階部を位置させて第一状態とし、該
第一状態で前記内側仮柱が位置しない部位に前記走行手
段を移動させて前記巻上装置によって第一本設ブロック
を架設し、前記内側仮柱の下端を前記第一本設ブロック
上に嵌合し前記外側仮柱を上方に引上げると共に前記昇
降固定手段によって該内側仮柱の最上段に前記屋上階部
を位置させて第二状態とし、該第二状態で前記外側仮柱
が位置しない部位に前記走行手段を移動させて前記巻上
装置によって第二本設ブロックを架設し、前記外側仮柱
の下端を前記第二本設ブロック上に嵌合し前記内側仮柱
を上方に引上げると共に前記昇降固定手段によって前記
外側仮柱の最上段に前記屋上階部を位置させて再び第一
状態とし、上記動作を順次繰り返すことによりビルの建
設を行なうことを特徴とする。
According to the present invention, there is provided a method for constructing a building, comprising assembling a rooftop floor on the ground as an erecting structure, and a lower end capable of being fitted on a main building pillar. An outer temporary column and an inner temporary column are provided so as to be able to move up and down by penetrating the rooftop section, and elevating and fixing means for vertically driving the outer temporary column and the inner temporary column with respect to the rooftop section are provided. A traveling rail extending in a direction in which the outer temporary pillar and the inner temporary pillar are arranged under a floor portion, a traveling means having a hoisting device is provided on the traveling rail, and a lower end of the outer temporary pillar is attached to the building. The roof floor portion is positioned at the uppermost stage of the outer temporary column by the elevating and fixing means and fitted on the main column to be in the first state, and the traveling is performed at a position where the inner temporary column is not located in the first state. By moving the means, the first permanent block is erected by the hoisting device, The lower end of the temporary column is fitted onto the first permanent block, the outer temporary column is pulled upward, and the roof top floor is positioned at the uppermost stage of the inner temporary column by the elevating and fixing means. In the second state, the traveling means is moved to a position where the outer temporary column is not located, a second permanent block is erected by the hoisting device, and a lower end of the outer temporary column is fixed to the second permanent block. By fitting the upper part and pulling the inner temporary column upward, the roof top floor portion is positioned at the uppermost stage of the outer temporary column by the elevating and lowering means, and the first state is again set. Characterized by the construction of

【0005】[0005]

【実施例】図1には本発明の一実施例に係るビルの建設
方法を実施している状態の正面、図2にはその平面、図
3にはその側面を示してある。
1 is a front view showing a state in which a building construction method according to an embodiment of the present invention is performed, FIG. 2 is a plan view thereof, and FIG. 3 is a side view thereof.

【0006】図において、1はペントハウスを含む地上
組みされた屋上階部、2は建設すべきビルのビル本設柱
4の配置に一致して複数本対称に設けられた外側仮柱
で、外側仮柱2は屋上階部1を貫通して昇降可能になっ
ている。3は外側仮柱2の内側でビル本設柱4の配置に
一致して複数本対称に設けられた内側仮柱で、内側仮柱
3は屋上階部1を貫通して昇降可能になっている。5は
屋上階部1と外側仮柱2とに亘って仮設され、屋上階部
1に対する外側仮柱2の相対的な昇降駆動と固定を行な
う昇降固定手段としての昇降装置である。6は内側仮柱
3の下端を巻上ワイヤ7で支持し屋上階部1に対する内
側仮柱3の相対的な昇降駆動を行なう昇降固定手段とし
ての第二昇降装置であり、8は屋上階部1と内側仮柱3
を内側仮柱3の上端付近及び中間付近で固定を行なう固
定装置である。外側仮柱2の有効長さは、屋上階部1の
下側に2階高さ分のコアブロックを積上げ建設できるよ
うになっており、内側仮柱3の有効長さは、中央部に建
付けた2階高さのブロック上に乗って同じ高さが維持で
きるようになっている。外側仮柱2及び内側仮柱3の下
端はビル本設柱4の上端に対し着脱可能となっている。
尚、図3で示した状態は、外側仮柱2の列で屋上階部1
をビル本設柱4上に支持し、内側仮柱3を屋上階部1内
へ引上げた状態になっている。
In the figure, reference numeral 1 denotes a rooftop part assembled above the ground including a penthouse, and 2 denotes a plurality of temporary temporary columns provided symmetrically in accordance with the arrangement of the main building columns 4 of the building to be constructed. The temporary column 2 can be moved up and down through the rooftop floor 1. Reference numeral 3 denotes an inner temporary pillar provided inside the outer temporary pillar 2 and symmetrically provided in plural in accordance with the arrangement of the main building pillar 4, and the inner temporary pillar 3 can be moved up and down through the rooftop section 1. I have. Reference numeral 5 denotes an elevating device which is temporarily provided between the rooftop section 1 and the outer temporary columns 2 and serves as an elevating and lowering fixing means for performing relative driving and fixing of the outer temporary columns 2 with respect to the rooftop section 1. Reference numeral 6 denotes a second lifting / lowering device as lifting / lowering fixing means for supporting the lower end of the inner temporary pillar 3 with a hoisting wire 7 and driving the inner temporary pillar 3 to move up and down relative to the rooftop section 1; 1 and inner temporary column 3
Is fixed near the upper end and near the middle of the inner temporary column 3. The effective length of the outer temporary pillars 2 is such that core blocks equivalent to the height of the second floor can be stacked and constructed under the rooftop section 1, and the effective length of the inner temporary pillars 3 is built in the center. The same height can be maintained by riding on the attached second floor block. The lower ends of the outer temporary pillar 2 and the inner temporary pillar 3 are detachable from the upper end of the main building pillar 4.
In addition, the state shown in FIG.
Is supported on the main building pillar 4, and the inner temporary pillar 3 is pulled up into the rooftop floor 1.

【0007】図2において、1aは外側仮柱2の列方向
両端における屋上階部1に設けた張出し部である。9は
内側仮柱3の列の間における中央部と内側仮柱3よりも
外側におけるウイング部との屋上階部1の下面にそれぞ
れ布設されたレール、10は中央部のレール9上を走行
する天井走行ガーダ、11はウイング部のレール9上を
走行する天井走行ガーダである。12は天井走行ガーダ
10,11に設けられた横行用レール、12aは内側仮
柱3の列の延長線上の位置で屋上階部1の下面に固定配
置された乗移り用レールである。13は乗移り用レール
12aを介して天井走行ガーダ10,11上に乗移り可
能な巻上トロリで、巻上トロリ13は中央の張出部位置
において地上から屋上階部1のすぐ下の建造階まで、地
上で予め組立てられたビルく体部ブロックを吊り上げ可
能なリフトと容量(例えば50ton)の巻上機を備えてい
る。
In FIG. 2, reference numerals 1a denote projecting portions provided on the rooftop floor 1 at both ends in the row direction of the outer temporary columns 2. Reference numeral 9 denotes rails laid on the lower surface of the rooftop section 1 at the central portion between the rows of the inner temporary columns 3 and the wing portion outside the inner temporary columns 3, and 10 runs on the rail 9 at the central portion. An overhead traveling girder 11 is an overhead traveling girder that travels on the rail 9 of the wing portion. Reference numeral 12 denotes a traversing rail provided on the ceiling traveling girder 10, 11, and reference numeral 12a denotes a transfer rail fixed to the lower surface of the rooftop section 1 at a position on an extension of a row of the inner temporary columns 3. Reference numeral 13 denotes a hoisting trolley which can be transferred onto the overhead traveling girder 10, 11 via a transfer rail 12a. The hoisting trolley 13 is constructed from the ground to just below the rooftop floor 1 at the center overhang portion. It is equipped with a lift capable of lifting a building block pre-assembled on the ground to the floor and a hoist of a capacity (for example, 50 tons).

【0008】図4、図5に基づいて昇降装置を具体的に
説明する。図4には昇降装置の平面、図5にはその正面
を示してある。
The lifting device will be described in detail with reference to FIGS. FIG. 4 shows a plan view of the lifting device, and FIG. 5 shows a front view thereof.

【0009】外側仮柱2の両面には長さ方向に一定のピ
ッチでピン受孔14が設けられ、屋上階部1には外側仮
柱2が貫通する柱ガイド1bが設けられている。。昇降
装置5には上下の環状梁15,16が備えられ、環状梁
15,16は油圧シリンダ17によって連結されてい
る。各環状梁15,16にはピン受孔14に着脱挿入さ
れるピンシリンダ18が設けられ、下部の環状梁16は
屋上階部1に固定されている。
On both sides of the outer temporary column 2, pin receiving holes 14 are provided at a constant pitch in the length direction, and on the rooftop section 1, a column guide 1b through which the outer temporary column 2 penetrates is provided. . The lifting device 5 includes upper and lower annular beams 15 and 16, and the annular beams 15 and 16 are connected by a hydraulic cylinder 17. Each of the annular beams 15 and 16 is provided with a pin cylinder 18 which is detachably inserted into the pin receiving hole 14, and the lower annular beam 16 is fixed to the rooftop section 1.

【0010】図6,図7に基づいて固定装置8を具体的
に説明する。図6には固定装置の平面、図7にはその正
面を示してある。
The fixing device 8 will be described in detail with reference to FIGS. FIG. 6 shows a plan view of the fixing device, and FIG. 7 shows a front view thereof.

【0011】内側仮柱3の上端近傍及び中間近傍の両面
にはピン受孔101が設けられ、屋上階部1には内側仮
柱3が貫通する柱ガイド1Sが設けられている。内側仮
柱3には環状梁19が嵌合し、環状梁19は屋上階部1
に固定されている。環状梁19にはピン受孔101に着
脱挿入されるピンシリンダ108が設けられている。
A pin receiving hole 101 is provided on both surfaces near the upper end and near the middle of the inner temporary column 3, and a column guide 1S through which the inner temporary column 3 penetrates is provided on the rooftop floor portion 1. An annular beam 19 is fitted to the inner temporary pillar 3, and the annular beam 19 is
It is fixed to. The annular beam 19 is provided with a pin cylinder 108 which is inserted into and removed from the pin receiving hole 101.

【0012】尚、昇降装置5及び固定装置8の構成は上
記構成に限定されず他の任意の機構を用いることも可能
である。
The structures of the lifting device 5 and the fixing device 8 are not limited to the above-mentioned structures, and any other mechanism can be used.

【0013】次に図8乃至図16に基づいて本発明のビ
ルの建設方法を具体的に説明する。図8乃至図16には
本発明の一実施例に係るビルの建設方法の工程説明を示
してある。
Next, a method for constructing a building according to the present invention will be described in detail with reference to FIGS. 8 to 16 show steps of a building construction method according to an embodiment of the present invention.

【0014】図8に示すように、建設すべきビルの屋上
階部1を、適当な高さの地上に配置した架台20上に組
立て、屋上階部1とビル本設柱4の位置を一致させる。
屋上階部1に図1乃至図8で示した要領で外側仮柱2、
内側仮柱3、天井走行ガーダ10,11、巻上トロリ1
3を仮設する。昇降装置5による外側仮柱2の一斉押下
げにより屋上階部1を外側仮柱2の上端近傍まで上昇さ
せ、昇降装置5の下部のピンシリンダ18をピン受孔1
4へ挿入結合して屋上階部1を外側仮柱2の列に固定す
る。即ち図9の状態(第一状態)にする。
As shown in FIG. 8, a rooftop section 1 of a building to be constructed is assembled on a gantry 20 arranged on the ground at an appropriate height, and the positions of the rooftop section 1 and the main building pillars 4 coincide. Let it.
The outer temporary pillar 2, as shown in FIG. 1 to FIG.
Inner temporary pillar 3, overhead traveling girder 10, 11, hoisting trolley 1
3 is provisionally set. The roof temporary floor 2 is raised to the vicinity of the upper end of the outer temporary column 2 by simultaneously pushing down the outer temporary column 2 by the elevating device 5, and the pin cylinder 18 below the elevating device 5 is moved into the pin receiving hole 1.
4 to secure the rooftop section 1 to the row of outer temporary columns 2. That is, the state shown in FIG. 9 (first state) is set.

【0015】図9に示すように、中央部の天井走行ガー
ダ10と巻上トロリ13を用いてブロック組みされた中
央部のコアブロック21(第一本設ブロック)を運び入
れビル本設柱4上に建付ける。
As shown in FIG. 9, a central core block 21 (first permanent block) assembled into a block by using a ceiling traveling girder 10 and a hoisting trolley 13 in the central part is carried in, and the main building pillar 4 is installed. Build on top.

【0016】図10に示すように、内側仮柱3の列を一
斉に屋上階部1から降下させ、内側仮柱3の下端部を建
付けの済んだ中央コアブロック21のビル本設柱4上に
嵌着させる。この位置で内側仮柱3の上端と屋上階部1
を固定装置8で固定し、外側仮柱2を一斉にもしくは順
に屋上階部1内へ引上げ(第二状態)、中央部の天井走
行ガーダ10からウイング部の走行ガーダ11へ乗り移
りレール12aを経て巻上トロリ13を移動させ、地上
で組立てられたウイング部用のコアブロック21′(第
二本設ブロック)を運び入れて建付ける。
As shown in FIG. 10, the rows of the inner temporary pillars 3 are simultaneously lowered from the rooftop section 1, and the lower end of the inner temporary pillars 3 is completely installed on the central building block 4 of the central core block 21. Fit on top. At this position, the upper end of the inner temporary pillar 3 and the rooftop 1
Is fixed by a fixing device 8, and the outer temporary pillars 2 are simultaneously or sequentially pulled up into the rooftop section 1 (second state), transferred from the ceiling traveling girder 10 in the center to the traveling girder 11 in the wing section, and passed through the rail 12a. The hoisting trolley 13 is moved, and the wing core block 21 '(second permanent block) assembled on the ground is carried in and installed.

【0017】図9、図10の工程の時、屋上階部1の下
の作業空間は列に正しく並んだ外側仮柱2または内側仮
柱3だけが存在し、図9の状態では中央部の天井走行ガ
ーダ10の走路に全く邪魔が無く、図10の状態ではウ
イング部の天井走行ガーダ11の走路に全く邪魔がな
く、コアブロック21,21′の搬入,建付けを安全に
且つ円滑に進められる。
At the time of the steps shown in FIGS. 9 and 10, the working space below the rooftop section 1 has only the outer temporary pillars 2 or the inner temporary pillars 3 which are correctly arranged in a line, and in the state of FIG. The running path of the ceiling traveling girder 10 has no obstruction at all, and in the state of FIG. 10, there is no obstruction on the running path of the ceiling traveling girder 11 of the wing portion, and the loading and building of the core blocks 21 and 21 ′ can be safely and smoothly performed. Can be

【0018】図11に示すように、ウイング部のコアブ
ロックの建付けが済んだ後、屋上階部1を再び外側仮柱
2の上端に移動させて図9、図10の工程を繰り返して
ビルの積上げ建造を進める。
As shown in FIG. 11, after the core block of the wing portion has been assembled, the rooftop floor 1 is moved to the upper end of the outer temporary column 2 again, and the steps shown in FIGS. 9 and 10 are repeated. We will proceed with stacking construction.

【0019】図12乃至図16はビル建造の最終段階を
示してある。即ち図12は屋上階部1のすぐ下の階が建
造階になった場合の、屋上階部1の持ち上げが済んだ状
態である。この時、中央のコアブロック21は屋上階部
1と接続すべき柱を上端とするブロックで建付け、屋上
階部1の支持を図13のように内側仮柱3の列に変え、
ウイング部も同様なブロック21′として建付ける。
FIGS. 12 to 16 show the final stage of building construction. That is, FIG. 12 shows a state where the rooftop floor 1 has been lifted when the floor immediately below the rooftop floor 1 has become the building floor. At this time, the core block 21 at the center is built with blocks having the pillars to be connected to the rooftop section 1 as upper ends, and the support of the rooftop section 1 is changed to the rows of the inner temporary pillars 3 as shown in FIG.
The wing is also constructed as a similar block 21 '.

【0020】図14は屋上階部1のすぐ下の階のブロッ
クの建付けが済んで、内側仮柱3から外側仮柱2へ屋上
階部1を支持替えし、天井走行ガーダ10,11、横行
用レール12を撤去した状態である。図15は外側仮柱
2に沿って屋上階部1を降ろし、外側仮柱2、内側仮柱
3とビル本設柱4及び屋上階部1、屋上階部1とビル本
設柱4を溶接し、昇降装置5及び第二昇降装置6を撤去
した状態である。図16は屋上階部1から上へ突出して
残った外側仮柱2及び内側仮柱3の部分を撤去した完了
状態である。
FIG. 14 shows that the blocks on the floor immediately below the rooftop section 1 have been assembled, the rooftop section 1 has been supported from the inner temporary pillars 3 to the outer temporary pillars 2, and the ceiling traveling girder 10, 11, This is a state in which the traversing rail 12 has been removed. FIG. 15 lowers the rooftop section 1 along the outer temporary pillar 2 and welds the outer temporary pillar 2, the inner temporary pillar 3 and the main building pillar 4 and the rooftop floor 1, and the rooftop floor section 1 and the main building pillar 4 Then, the lifting device 5 and the second lifting device 6 are removed. FIG. 16 shows a completed state in which the portions of the outer temporary pillar 2 and the inner temporary pillar 3 that protrude upward from the rooftop floor 1 and have been removed are removed.

【0021】上述した工程でビルの建設を進めることに
より、屋上階部1の真下の階のブロック建付時(図1
2、図13)、及び機械撤去時(図14、図15、図1
6)に相互の干渉がなくなり工程が整然としたものにな
り危険が減少し作業が容易に且つスムーズに行なえる。
By proceeding with the construction of the building in the above-described process, the blocks can be built on the floor directly below the rooftop section 1 (FIG. 1).
2, FIG. 13), and when removing the machine (FIGS. 14, 15, and 1)
In 6), the mutual interference is eliminated, the process becomes orderly, the risk is reduced, and the operation can be performed easily and smoothly.

【0022】屋上階部1と外側仮柱2及び内側仮柱3の
関係は、例えば図17に示すように、屋上階部の両端に
外側仮柱が配されるような場であっても同様な効果が得
られる。
The relationship between the rooftop 1 and the outer temporary pillars 2 and the inner temporary pillars 3 is the same even when the outer temporary pillars are arranged at both ends of the rooftop as shown in FIG. Effects can be obtained.

【0023】[0023]

【発明の効果】本発明のビル建設方法は、屋上階部を架
設用構造体として地上で組立て、ビル本設柱上に下端が
嵌合可能な外側仮柱と内側仮柱を屋上階部を貫通して昇
降自在に設け、屋上階部に対して外側仮柱と内側仮柱の
昇降駆動を行なう昇降固定手段を備え、屋上階部の架下
に外側仮柱と内側仮柱の並設方向に延びる走行レールを
設け、巻上装置を備えた走行手段を走行レールに備え、
外側仮柱の下端をビル本設柱上に嵌合し昇降固定手段に
よって外側仮柱の最上段に屋上階部を位置させて第一状
態とし、第一状態で内側仮柱が位置しない部位に走行手
段を移動させて巻上装置によって第一本設ブロックを架
設し、内側仮柱の下端を第一本設ブロック上に嵌合し外
側仮柱を上方に引上げると共に昇降固定手段によって該
内側仮柱の最上段に屋上階部を位置させて第二状態と
し、第二状態で外側仮柱が位置しない部位に走行手段を
移動させて巻上装置によって第二本設ブロックを架設
し、外側仮柱の下端を第二本設ブロック上に嵌合し内側
仮柱を上方に引上げると共に昇降固定手段によって外側
仮柱の最上段に屋上階部を位置させて再び第一状態と
し、これら動作を順次繰り返すことによりビルの建設を
行なうようにしたので、屋上階部の構造体の機械設備の
組立てが済んだ後にビルの一階から直ちに同一手順の工
程で建設工事を行なうことができ、現地工事が単純化し
容易となる。また本設ブロックの搬送作業も単純化し、
巻上装置の巻上能力が高め易くなり、大ブロック単位で
搬送、建付が行なえ大幅な工期の短縮が可能になる。ま
た、外側仮柱と内側仮柱を本設ブロックに嵌合支持して
交互に使用するため、屋上階部の支持が安定し且つ屋上
階部の下の建造階での搬送,建付作業時の邪魔がなくな
り、作業が安全で容易になる。特に、ビル建造の最終段
階において、搬送,建付物と架設用構造体との干渉がな
くなり、仮設機械の解体撤去,屋上階部の接合固定が非
常に行ないやすくスムーズになる。
According to the building construction method of the present invention, the rooftop floor is assembled on the ground as a erection structure, and the outer temporary pillar and the inner temporary pillar, the lower ends of which can be fitted on the main building pillar, are formed on the rooftop floor. It is provided so as to be able to penetrate and move up and down freely, and is equipped with elevating and fixing means for raising and lowering the outer temporary column and the inner temporary column with respect to the rooftop section, and the direction in which the outer temporary column and the inner temporary column are juxtaposed under the rooftop section. A traveling rail extending to the traveling rail is provided with traveling means having a hoisting device,
The lower end of the outer temporary pillar is fitted onto the main building pillar, and the roof floor is located at the top of the outer temporary pillar by the elevating and fixing means to be in the first state. By moving the traveling means, the first permanent block is erected by the hoisting device, the lower end of the inner temporary column is fitted on the first permanent block, the outer temporary column is pulled upward, and the inner temporary column is raised by the vertical fixing means. The rooftop section is positioned at the top of the temporary column, and the second state is established.The traveling means is moved to a position where the external temporary column is not located in the second state, and the second permanent block is erected by the hoisting device. The lower end of the temporary column is fitted onto the second permanent block, the inner temporary column is pulled upward, and the roof floor is located at the top of the outer temporary column by the elevating and lowering means so as to be in the first state again. The building was constructed by repeating Can be performed immediately construction in the process of the same procedures come after the assembly of the mechanical equipment of the structure of the upper floor portion from a floor of the building, site work is simplified easily. Also, the work of transporting the main block has been simplified,
The hoisting capacity of the hoisting device can be easily increased, and transport and installation can be performed in units of large blocks, thereby greatly shortening the construction period. In addition, since the outer temporary pillars and the inner temporary pillars are used alternately while being fitted to and supported by the permanent block, the support of the rooftop floor is stable, and the transportation and installation work is performed on the building floor below the rooftop floor. Work is safe and easy. In particular, in the final stage of building construction, there is no interference between the transport, the building and the erection structure, and the dismantling and removal of the temporary machine and the joining and fixing of the rooftop are very easy and smooth.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の一実施例に係るビルの建設方法を実施
している状態の正面図。
FIG. 1 is a front view showing a state in which a building construction method according to an embodiment of the present invention is performed.

【図2】図1の平面図。FIG. 2 is a plan view of FIG. 1;

【図3】図1の側面図。FIG. 3 is a side view of FIG. 1;

【図4】昇降装置の平面図。FIG. 4 is a plan view of the lifting device.

【図5】図4の正面図。FIG. 5 is a front view of FIG. 4;

【図6】固定装置の平面図。FIG. 6 is a plan view of the fixing device.

【図7】図6の正面図。FIG. 7 is a front view of FIG. 6;

【図8】本発明の一実施例に係るビルの建設方法の工程
説明図。
FIG. 8 is a process explanatory view of a building construction method according to one embodiment of the present invention.

【図9】本発明の一実施例に係るビルの建設方法の工程
説明図。
FIG. 9 is a process explanatory view of a building construction method according to one embodiment of the present invention.

【図10】本発明の一実施例に係るビルの建設方法の工
程説明図。
FIG. 10 is a process explanatory view of a building construction method according to one embodiment of the present invention.

【図11】本発明の一実施例に係るビルの建設方法の工
程説明図。
FIG. 11 is a process explanatory view of a building construction method according to an embodiment of the present invention.

【図12】本発明の一実施例に係るビルの建設方法の工
程説明図。
FIG. 12 is an explanatory diagram showing steps of a building construction method according to an embodiment of the present invention.

【図13】本発明の一実施例に係るビルの建設方法の工
程説明図。
FIG. 13 is a process explanatory view of a building construction method according to an embodiment of the present invention.

【図14】本発明の一実施例に係るビルの建設方法の工
程説明図。
FIG. 14 is an explanatory diagram showing steps of a building construction method according to an embodiment of the present invention.

【図15】本発明の一実施例に係るビルの建設方法の工
程説明図。
FIG. 15 is a process explanatory view of a building construction method according to one embodiment of the present invention.

【図16】本発明の一実施例に係るビルの建設方法の工
程説明図。
FIG. 16 is an explanatory diagram showing steps of a building construction method according to an embodiment of the present invention.

【図17】本発明の他実施例に係るビルの建設方法を実
施している状態の正面図。
FIG. 17 is a front view of a state in which a building construction method according to another embodiment of the present invention is being performed.

【符号の説明】[Explanation of symbols]

1 屋上階部 2 外側仮柱 3 内側仮柱 4 ビル本設柱 5 昇降装置 6 第二昇降装置 8 固定装置 10,11 天井走行ガーダ 13 巻上トロリ DESCRIPTION OF SYMBOLS 1 Roof floor part 2 Outer temporary pillar 3 Inner temporary pillar 4 Building main pillar 5 Elevating device 6 Second elevating device 8 Fixing device 10,11 Ceiling traveling girder 13 Hoisting trolley

───────────────────────────────────────────────────── フロントページの続き (72)発明者 村本 廣毅 広島県広島市西区観音新町四丁目6番22 号 三菱重工業株式会社 広島製作所内 (72)発明者 向谷 美徳 広島県広島市西区観音新町四丁目6番22 号 三菱重工業株式会社 広島製作所内 (56)参考文献 特開 平3−87438(JP,A) (58)調査した分野(Int.Cl.6,DB名) E04B 1/35──────────────────────────────────────────────────続 き Continuing on the front page (72) Inventor Hiroki Muramoto 4-22, Kannonshinmachi, Nishi-ku, Hiroshima-shi, Hiroshima Mitsubishi Heavy Industries, Ltd. Hiroshima Works No. 4-6-22 Mitsubishi Heavy Industries, Ltd. Hiroshima Works (56) References JP-A-3-87438 (JP, A) (58) Fields investigated (Int. Cl. 6 , DB name) E04B 1/35

Claims (1)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 屋上階部を架設用構造体として地上で組
立て、ビル本設柱上に下端が嵌合可能な外側仮柱と内側
仮柱を前記屋上階部を貫通して昇降自在に設け、前記屋
上階部に対して前記外側仮柱と前記内側仮柱の昇降駆動
を行なう昇降固定手段を備え、前記屋上階部の架下に前
記外側仮柱と前記内側仮柱の並設方向に延びる走行レー
ルを設け、巻上装置を備えた走行手段を前記走行レール
に備え、前記外側仮柱の下端を前記ビル本設柱上に嵌合
し前記昇降固定手段によって該外側仮柱の最上段に前記
屋上階部を位置させて第一状態とし、該第一状態で前記
内側仮柱が位置しない部位に前記走行手段を移動させて
前記巻上装置によって第一本設ブロックを架設し、前記
内側仮柱の下端を前記第一本設ブロック上に嵌合し前記
外側仮柱を上方に引上げると共に前記昇降固定手段によ
って該内側仮柱の最上段に前記屋上階部を位置させて第
二状態とし、該第二状態で前記外側仮柱が位置しない部
位に前記走行手段を移動させて前記巻上装置によって第
二本設ブロックを架設し、前記外側仮柱の下端を前記第
二本設ブロック上に嵌合し前記内側仮柱を上方に引上げ
ると共に前記昇降固定手段によって前記外側仮柱の最上
段に前記屋上階部を位置させて再び第一状態とし、上記
動作を順次繰り返すことによりビルの建設を行なうこと
を特徴とするビルの建設方法。
1. A rooftop floor is assembled on the ground as an erecting structure, and an outer temporary pillar and an inner temporary pillar whose lower end is fittable on a main building pillar are provided so as to be vertically movable through the rooftop floor. And elevating and fixing means for raising and lowering the outer temporary column and the inner temporary column with respect to the rooftop portion, in a direction in which the outer temporary column and the inner temporary column are arranged under the rooftop portion. An extending running rail is provided, running means having a hoisting device is provided on the running rail, and a lower end of the outer temporary column is fitted on the main building pillar, and the uppermost stage of the outer temporary column is fixed by the elevating and lowering means. The rooftop floor portion is located in the first state, and the first temporary block is erected by the hoisting device by moving the traveling means to a portion where the inner temporary column is not located in the first state, The lower end of the inner temporary pillar is fitted on the first permanent block, and the outer temporary pillar is pulled upward. Raise and move the traveling means to a position where the outer temporary pillar is not located in the second state by positioning the rooftop at the top of the inner temporary pillar by the raising and lowering fixing means, and in the second state. A second permanent block is erected by a hoisting device, the lower end of the outer temporary column is fitted onto the second temporary block, the inner temporary column is pulled upward, and the outer temporary column is fixed by the lifting and lowering means. The rooftop floor is located at the top of the building, the building is brought into the first state again, and a building is constructed by repeating the above operations sequentially.
JP3010371A 1991-01-07 1991-01-07 Building construction method Expired - Fee Related JP2778842B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP3010371A JP2778842B2 (en) 1991-01-07 1991-01-07 Building construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP3010371A JP2778842B2 (en) 1991-01-07 1991-01-07 Building construction method

Publications (2)

Publication Number Publication Date
JPH04238929A JPH04238929A (en) 1992-08-26
JP2778842B2 true JP2778842B2 (en) 1998-07-23

Family

ID=11748297

Family Applications (1)

Application Number Title Priority Date Filing Date
JP3010371A Expired - Fee Related JP2778842B2 (en) 1991-01-07 1991-01-07 Building construction method

Country Status (1)

Country Link
JP (1) JP2778842B2 (en)

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0387438A (en) * 1989-08-31 1991-04-12 Hitachi Zosen Corp Construction method for structural steel members in multi-storied building

Also Published As

Publication number Publication date
JPH04238929A (en) 1992-08-26

Similar Documents

Publication Publication Date Title
EP2969884B1 (en) Self erecting jacking tower
JP2778842B2 (en) Building construction method
JP2913216B2 (en) Building construction method
JP2985110B2 (en) Construction method of steel roof
JPH0812262A (en) Installing method for overhead traveller and its device
JPH1061193A (en) Method of building steel frame structure and device therefor
JPH08333898A (en) Trestle for vertically and horizontally conveying building blocks
JP2703102B2 (en) Building construction method and construction transfer device
JP2796448B2 (en) Building construction method and building construction equipment used for the construction method
JP3841242B2 (en) Elevator parking elevating work table and construction method using it
JP2761518B2 (en) Construction method of building
JP2796449B2 (en) Building construction method and elevating device used for the construction method
JP7158304B2 (en) Transport system and installation method
JPH05113026A (en) Temporary scaffold structure
JP2872886B2 (en) Construction lift equipment
JP3179814B2 (en) Column and beam construction method and apparatus
JP2832278B2 (en) Building method
JPS5844102A (en) Apparatus and method of constructing traverse taking type track
JPS6237439A (en) Traveling method
JP2776128B2 (en) Lifting device for building frame
JP2781671B2 (en) Building erection method and building elevating device
JPH08312146A (en) Temporary frame device for construction
JP2717157B2 (en) Horizontal transport device for building construction
JP2676600B2 (en) How to lift and connect beams between columns
JPH04118438A (en) Method and apparatus for construction of building

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 19980407

LAPS Cancellation because of no payment of annual fees