JPS6237439A - Traveling method - Google Patents

Traveling method

Info

Publication number
JPS6237439A
JPS6237439A JP17526485A JP17526485A JPS6237439A JP S6237439 A JPS6237439 A JP S6237439A JP 17526485 A JP17526485 A JP 17526485A JP 17526485 A JP17526485 A JP 17526485A JP S6237439 A JPS6237439 A JP S6237439A
Authority
JP
Japan
Prior art keywords
frame
block
work
assembled
steel frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP17526485A
Other languages
Japanese (ja)
Inventor
宗一 木谷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Komuten Co Ltd
Original Assignee
Takenaka Komuten Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Komuten Co Ltd filed Critical Takenaka Komuten Co Ltd
Priority to JP17526485A priority Critical patent/JPS6237439A/en
Publication of JPS6237439A publication Critical patent/JPS6237439A/en
Pending legal-status Critical Current

Links

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 「産業上の利用分野」 この発明は1−ラベリング工法の改善に関する。[Detailed description of the invention] "Industrial application field" This invention relates to 1-improvement of the labeling method.

「従来の技術」 トラベリング工法とは、躯体上に架設する大架構をいく
つかのブロックに分割してクレーン操作の可能な場所に
組立て、躯体上部に設置した走行レールに載せて順次移
動させながら組立ててゆく方法である。手順としては、
まず分割した第1ブロックをあらかじめ施工された1匠
体の端部に設けたステージ上で組立て1 これを油圧ジ
ヤツキ等によって1ブロックだけの横移動させ、空いた
ステージで次の第2ブロックを組立て、順次横移動させ
、架設する方法である。
``Conventional technology'' The traveling construction method is a method in which a large frame to be erected on a building structure is divided into several blocks, assembled at a location where crane operation is possible, and then moved sequentially by placing them on traveling rails installed on the top of the building structure. This is the way to proceed. The steps are:
First, assemble the divided first block on a stage set up at the end of a pre-constructed 1st block. This is moved laterally by one block using hydraulic jacks, etc., and the next second block is assembled on the empty stage. This method involves sequentially moving laterally and constructing the structure.

本出願人にあっても特開昭57−116847号にて提
案している。
The present applicant also proposed this in Japanese Patent Laid-Open No. 57-116847.

叩ち、トラベリング工法にあっては第2図ないし第3図
に示したように、予め施工された鉄筋コンクリート造の
躯体Bの一側妻側上端部に地組みした鉄骨トラスのユニ
ット1を載置可能に、かつトラス組立可能に押体Bの一
例部におけるギヤラリ−2の足場3を組立て、該足場3
上に、地組した1ユニット1.・・・を躯体B外側に設
置したクレーン(図示省略)により吊り上げて載置し、
更に載置したユニット1.1相互を連結するとしており
、従来2例えば体育館等大空間の鉄骨造屋根を架構する
場合としては、大型クレーンを建物内部に入場させ、屋
根下全面に大掛りな仮設支保工と。
In the hammering and traveling construction method, as shown in Figures 2 and 3, a steel truss unit 1 assembled into the ground is placed on the upper end of one gable side of a reinforced concrete frame B that has been constructed in advance. Assemble the scaffolding 3 of the gear rally 2 in an example part of the pusher B so that the truss assembly is possible, and the scaffolding 3
1 unit assembled on the ground 1. . . . is lifted and placed by a crane (not shown) installed on the outside of the frame B,
In addition, the installed units 1.1 are connected to each other. Conventionally, 2. For example, when constructing a steel roof for a large space such as a gymnasium, a large crane is entered inside the building and large-scale temporary construction is carried out under the roof. With shoring.

作業足場を組立て、該作業足場上で鉄骨組立を行なう工
法と、予め鉄骨を地組し、これを吊り上げ。
One method involves assembling a work scaffold and assembling the steel frame on the work scaffold, and the other involves assembling the steel frame in advance and hoisting it up.

又は押し上げて架構するところのりフトアソブ・ブノシ
ュアップ工法が知られているが、これ等の従来工法に比
較して仮設足場の縮少、工費の節減。
Alternatively, the glue-and-bunch-up construction method is known, in which the frame is pushed up, but compared to these conventional construction methods, it reduces the need for temporary scaffolding and reduces construction costs.

定位置同一作業の繰返しによる安全性及び施工精度の向
上、工期短縮等を計り得る。
By repeating the same work in the same position, it is possible to improve safety and construction accuracy, and shorten the construction period.

面、上述図中5は梁、6は移動用レールを示す。In the above figure, 5 indicates a beam, and 6 indicates a moving rail.

「発明が解決しようとする問題点」 しかるに、叙上の諸利点は、鉄骨本体(屋根トラス、架
構)、床のデツキ等の仮設についてであり。
``Problems to be solved by the invention'' However, the advantages mentioned above are related to the temporary construction of the steel frame body (roof truss, frame), floor decking, etc.

仕上工事については既述の従来手段でとり行わねばなら
ない。
Finishing work must be carried out using the conventional means described above.

しかして、鉄骨工事及び床工事完了後に仕上工事にかか
るため工期の短縮は不可能であり、また。
However, it is impossible to shorten the construction period because finishing work will be required after the steel frame work and floor work are completed.

仕上工事のため仮設面においても全面水平・垂直足場が
必要であったり、移動足場が必要になったりして、この
分のコストの低減は困難である。さらに、全面水平・垂
直足場が必要な場合はそれだけ作業所の高所作業の行動
半径も広まり、安全面においても緻密な管理が必要とな
る。
For the finishing work, horizontal and vertical scaffolding is required on the entire surface of the temporary construction site, as well as movable scaffolding, making it difficult to reduce costs accordingly. Furthermore, if full-scale horizontal and vertical scaffolding is required, the radius of action for high-place work in the workplace will be expanded accordingly, requiring careful management in terms of safety.

「問題点を解決するための手段」、「作用」本発明は叙
−上の事情に鑑みなされたもので、その要旨とするとこ
ろは、大架構をいくつかのブロックに分割してクレーン
操作の可能な場所に組立て、 1gX体上部に設置した
走行レールに載せて順次移動させながら組立ててゆくト
ラベリング工法に於いて、走行レール上に待機の自走走
行車上にて組立てると共に仕上をした架構1ブロックを
完成させたところで、順次この架fi 1ブロックを枢
体上の所定位置に搬送、セットするとして、トラベリン
グ後の仕上工事の大部分を不必要化することにより、従
来のトラベリング工法より、工期短縮。
``Means for Solving the Problems'' and ``Operations'' The present invention was made in view of the above circumstances, and its gist is that the large frame is divided into several blocks and crane operation is possible. In the traveling construction method, which is assembled in a place where it is possible, placed on a traveling rail installed on the top of the 1gX body, and moved sequentially, the frame 1 was assembled and finished on a self-propelled vehicle waiting on the traveling rail. Once the blocks are completed, each block is sequentially transported and set in a predetermined position on the pivot.By eliminating the need for most of the finishing work after traveling, the construction time is shorter than with the conventional traveling construction method. shortening.

コストの低減、施工精度の向上、安全作業の確保(高所
作業面積の低減)が期し得るとした点にある。
This technology is expected to reduce costs, improve construction accuracy, and ensure safe work (reducing the area required for work in high places).

すなわち2本発明工法では、建物本体の外周には、最低
限度(鉄骨1ブロック分)の足場を設置し、内部もこれ
と同様とする。
That is, in the construction method of the second invention, a minimum amount of scaffolding (one block of steel frame) is installed around the outer periphery of the building body, and the same goes for the inside.

しかして、鉄骨1ブロックが走行レール上に待機の自走
走行車(図示省略)上にて組立てられ。
Thus, one block of steel frame is assembled on the traveling rail on a waiting self-propelled vehicle (not shown).

鉄骨工事完了後に塗装・屋根工事・チソシュ工事が施工
され、さらに外壁まで完成される訳である。
After the steel frame work is completed, painting, roofing, and dusting work will be carried out, and the exterior walls will also be completed.

また1足場においては、内外共1スパンですべてをまか
なうことができる。内部足場は特にステージ形式にすれ
ば、鉄骨の本締め、塗装・水平養生を兼用でき、屋根工
事も高所作業のイメージをもつことなく作業ができる。
Also, with one scaffold, one span can cover both the interior and exterior. In particular, if the internal scaffolding is made into a stage format, it can be used for the final tightening of steel frames, painting, and horizontal curing, and roof work can be done without having to worry about working at heights.

このようにして仕上された架構1ブロックは。One block of the frame finished in this way.

順次自走走行台車に乗って相体上の所定位置に搬送され
、セットされる。
They are sequentially transported on a self-propelled trolley to a predetermined position on the target and set.

柱脚等への固定方法は油圧ジヤツキで所定の高さに仮に
上げておき、柱脚が所定の位置にセットできたら1ブロ
ックずつ油圧で下げる。脚部は溶接または、ボルト接合
でよい。仕上部、つまり屋根・外壁取合部は1ブロック
が完全にセット完了時に、内外部移動足場にて取合い部
を施工する。
The method of fixing it to a column base is to temporarily raise it to a predetermined height using a hydraulic jack, and once the column base is set in the specified position, lower it one block at a time using hydraulics. The legs may be welded or bolted. The finished part, that is, the roof/exterior wall joint, will be constructed using internal and external movable scaffolding when one block is completely set.

以下1次の1ブロックも同様に処理されていく。Subsequent blocks of the first order are processed in the same manner.

「実施薊」 以下、これを図に基づいて詳細に説明する。"Implementation" This will be explained in detail below based on the drawings.

第1図a、bは本発明工法の実施現場の平面図。Figures 1a and 1b are plan views of the site where the construction method of the present invention is implemented.

側面図で1図中10は建物本体11の外周に設置の外部
足場、12は外部足場10に対応して設置の内部足場で
ある。
In the side view, 10 in Figure 1 is an external scaffold installed around the outer periphery of the building body 11, and 12 is an internal scaffold installed corresponding to the external scaffold 10.

13、14は鉄骨地組用クレーン、地組完了鉄骨持ち込
みクレーンである。
Reference numerals 13 and 14 are cranes for steel frame assembly and cranes for bringing in steel frames once the ground assembly has been completed.

鉄骨1ブロック15では、待機の自走走行車上にクレー
ン14より持ち込まれた鉄骨部材の組立て。
In the steel frame 1 block 15, steel frame members brought in from the crane 14 are assembled onto a waiting self-propelled vehicle.

若しくは組立て完了の鉄骨の受載が行われ、さらに塗装
、屋根工事、サソシエエ事が施工される。
Alternatively, the assembled steel frame is received, and further painting, roofing, and sassy work is carried out.

よって、ブロック15に於いて、16は鉄骨、17は鉄
骨16を覆った屋根材を示す。
Therefore, in the block 15, 16 indicates a steel frame, and 17 indicates a roof material covering the steel frame 16.

しかして、仕上工事までを済ませた架構ブロックが完成
される訳である。
In this way, the structural block, which has undergone finishing work, is completed.

この際、内部足場12をステージ形式にすると鉄骨の本
締め、塗装、水平養生を兼用でき、高所作業のイメージ
を解消できる。
At this time, if the internal scaffolding 12 is made into a stage type, it can be used for final tightening of the steel frame, painting, and horizontal curing, eliminating the image of working at heights.

仕上架構1ブロックには自走走行台車(図示省略)に乗
せられて所定位置に搬送され、先ず油圧ジヤツキで所定
の高さに仮に上げておき、柱脚が所定の位置にセットで
きたら下げてセットする。
One block of the finished frame is transported to a predetermined position on a self-propelled trolley (not shown), first temporarily raised to a predetermined height using hydraulic jacks, and then lowered once the column bases are set in the predetermined positions. set.

脚部は溶接またはボルト接合でよい。The legs may be welded or bolted.

解放された自走走行車は(y帰し2次のブロックの施工
にとりかかる。
The freed self-propelled vehicle returns to work on the construction of the second block.

かかるトラベリングを終了すると2本発明では既に仕上
工事が済んでいるので屋根間、外壁間取合い、外壁と床
との取合いのみが残るだけとなるが、これは、簡易な内
外部移動足場18.19で行えば良い。
When such traveling is completed, the finishing work has already been completed in the present invention, so only the connections between the roofs, the exterior walls, and the exterior walls and floors remain. You can do it with

尚、外部足場10が嵩高で不安定となる場合には。In addition, if the external scaffold 10 is bulky and becomes unstable.

仕上工事を受けた鉄骨側面にガイドレールとしてのチャ
ンネルを水平取付は仮設し、これに足場より先端に摺動
ローラー等を付設した連結バーを持ち出して係合させる
等の移動体に対する連結手段で処理すれば良い。
Temporarily install a channel as a guide rail horizontally on the side of the steel frame that has undergone finishing work, and connect it to the moving object by bringing out a connecting bar with sliding rollers, etc. at the tip from the scaffolding and engaging it. Just do it.

しかして、トラベリング後にほとんどの仕上工事が不要
にして、建物が完成することとなる。
As a result, the building will be completed without the need for most of the finishing work after traveling.

「発明の効果」 以上の如き本発明工法によるならば、以下列記の諸効果
を奏し2得る。
"Effects of the Invention" According to the construction method of the present invention as described above, the following effects can be obtained.

i)従来工法に比べ、工程を約15%程度短縮できる。i) Compared to conventional construction methods, the process can be shortened by approximately 15%.

ii )内外部1片・垂直水平養生・クレーン等の仮設
員を大巾にコストダウンできる。
ii) Costs can be significantly reduced by requiring temporary staff such as one piece of interior and exterior, vertical and horizontal curing, and cranes.

iii )高所作業の範囲を最少限度にとどめることが
できるため、安全管理がしやすい。
iii) Safety management is easier because the scope of work at height can be kept to a minimum.

iv)同パターンの繰返しにより精度のバラツキを少な
くできる。
iv) Variations in accuracy can be reduced by repeating the same pattern.

【図面の簡単な説明】[Brief explanation of drawings]

第1図a、bは本発明実施現場の平面図、側面図、第2
[Ja、bは従来のトラベリング工法のユニット連結用
足場を示す正面図、同足場の平面図。 第3図は同工法の足場と鉄骨トラスユニットのスライド
及び連結状態を示す側面図である。 1・・・ユニット、2・・・ギヤラリ−13・・・足場
、5・・・梁、6・・・移動用レール、10・・・外部
足場、11・・・建物本体、12・・・内部足場、13
・・・鉄骨地組用クレーン。 14・・・地組完了鉄骨持ち込みクレーン、15・・・
ブロック、16・・・鉄骨、17・・・屋根材、B・・
・躯体、K・・・仕上架構ニブロック、18・・・内部
移動足場、19・・・外部移動足場。
Figures 1a and b are a plan view and a side view of the site where the present invention is implemented;
[Ja and b are a front view and a plan view of the scaffold for unit connection of the conventional traveling construction method. FIG. 3 is a side view showing the sliding and connected state of the scaffold and steel truss unit of the same construction method. 1... Unit, 2... Gear rally, 13... Scaffolding, 5... Beam, 6... Movement rail, 10... External scaffolding, 11... Building body, 12... Internal scaffolding, 13
...Crane for steel frame assembly. 14... Ground assembly completed steel frame brought in crane, 15...
Block, 16... Steel frame, 17... Roofing material, B...
- Frame, K... Finished frame block, 18... Internal movable scaffold, 19... External movable scaffold.

Claims (1)

【特許請求の範囲】 大架構をいくつかのブロックに分割してクレーン操作の
可能な場所に組立て、躯体上部に設置した走行レールに
載せて順次移動させながら組立ててゆく工法に於いて、 走行レール上に待機の自走走行車上にて組立てると共に
仕上をした架構1ブロックを完成させたところで、順次
この架構1ブロックを躯体上の所定位置に搬送、セット
するとしてなることを特徴とするトラベリング工法。
[Claims] In a construction method in which a large frame is divided into several blocks, assembled at a location where a crane can be operated, and assembled while being placed on a running rail installed on the top of the frame and moved sequentially, the running rail A traveling construction method characterized in that once one frame block is assembled and finished on a self-propelled vehicle waiting on the top, the one frame block is sequentially transported and set at a predetermined position on the frame. .
JP17526485A 1985-08-09 1985-08-09 Traveling method Pending JPS6237439A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP17526485A JPS6237439A (en) 1985-08-09 1985-08-09 Traveling method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP17526485A JPS6237439A (en) 1985-08-09 1985-08-09 Traveling method

Publications (1)

Publication Number Publication Date
JPS6237439A true JPS6237439A (en) 1987-02-18

Family

ID=15993110

Family Applications (1)

Application Number Title Priority Date Filing Date
JP17526485A Pending JPS6237439A (en) 1985-08-09 1985-08-09 Traveling method

Country Status (1)

Country Link
JP (1) JPS6237439A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01148361A (en) * 1987-12-02 1989-06-09 Taikisha Ltd Method for constructing coating equipment
JPH07207761A (en) * 1994-01-10 1995-08-08 Kajima Corp Roof truss construction method
JP2010013870A (en) * 2008-07-04 2010-01-21 Kajima Corp Roof frame construction method, and movement prevention device and lift prevention device for use in the same
JP2018080490A (en) * 2016-11-15 2018-05-24 株式会社竹中工務店 Construction method for roof frame structure

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5985053A (en) * 1982-11-05 1984-05-16 鹿島建設株式会社 Construction of roof

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5985053A (en) * 1982-11-05 1984-05-16 鹿島建設株式会社 Construction of roof

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01148361A (en) * 1987-12-02 1989-06-09 Taikisha Ltd Method for constructing coating equipment
JPH07207761A (en) * 1994-01-10 1995-08-08 Kajima Corp Roof truss construction method
JP2010013870A (en) * 2008-07-04 2010-01-21 Kajima Corp Roof frame construction method, and movement prevention device and lift prevention device for use in the same
JP2018080490A (en) * 2016-11-15 2018-05-24 株式会社竹中工務店 Construction method for roof frame structure

Similar Documents

Publication Publication Date Title
JPS6237439A (en) Traveling method
JP3732586B2 (en) Method and apparatus for constructing steel structure
JPH08333898A (en) Trestle for vertically and horizontally conveying building blocks
AU597836B2 (en) Wall casting system
JP2657577B2 (en) Large roof self-elevating device for construction work and method of constructing middle and high-rise building
JPS61277772A (en) Traveling construction method
JP2768281B2 (en) Bridge construction method
JP3192543B2 (en) Building demolition method
JPS6114300B2 (en)
JPH09137506A (en) Construction method of building
JP2761526B2 (en) How to build structures
JPH0733688B2 (en) Push-up method
SU1263793A1 (en) Method of erecting buildings with prefabricated solid skeleton
JP2778842B2 (en) Building construction method
SU617516A1 (en) Method of constructing hollow structures and structure erected by this method
JPS62244942A (en) Push-up method and apparatus
JP3318133B2 (en) How to build artificial ground
JP2761527B2 (en) How to build structures
CN115807558A (en) High formwork support body based on complex structure and channel construction method
JP2874830B2 (en) Push-up method
JPS61270432A (en) Construction of building
JPH04319172A (en) Skeleton building construction workbench
CN116876818A (en) Construction method of movable high and large formwork
JPH05141092A (en) Construction of structure
JPH06101280A (en) Method of erection construction