CN103061514B - Long-span steel structure corridor construction method - Google Patents

Long-span steel structure corridor construction method Download PDF

Info

Publication number
CN103061514B
CN103061514B CN201210447112.2A CN201210447112A CN103061514B CN 103061514 B CN103061514 B CN 103061514B CN 201210447112 A CN201210447112 A CN 201210447112A CN 103061514 B CN103061514 B CN 103061514B
Authority
CN
China
Prior art keywords
steel
transverse horizontal
girder
girder steel
horizontal girder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201210447112.2A
Other languages
Chinese (zh)
Other versions
CN103061514A (en
Inventor
寿建军
孙占利
郦挺
张升前
寿雪光
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ZHEJIANG BADA CONSTRUCTION GROUP CO Ltd
Original Assignee
ZHEJIANG BADA CONSTRUCTION GROUP CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZHEJIANG BADA CONSTRUCTION GROUP CO Ltd filed Critical ZHEJIANG BADA CONSTRUCTION GROUP CO Ltd
Priority to CN201210447112.2A priority Critical patent/CN103061514B/en
Publication of CN103061514A publication Critical patent/CN103061514A/en
Application granted granted Critical
Publication of CN103061514B publication Critical patent/CN103061514B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

Long-span steel structure corridor construction method designed by the present invention, first the brace steel post of span both sides is installed, then transverse horizontal girder steel is lifted, support steel beam between transverse horizontal girder steel and diagonal brace girder steel are then installed, vertical equity girder steel between two transverse horizontal girder steels is installed again and across girt, the horizontal girder steel that last installation needs, it is characterized in that after installation brace steel post, first between two brace steel posts, auxiliary girder is installed, take auxiliary girder as suspension centre lifting transverse horizontal girder steel, auxiliary girder is removed after installing support steel beam between transverse horizontal girder steel and diagonal brace girder steel again.The feature of this construction method is the transverse horizontal girder steel utilizing auxiliary girder installation volume maximum, and whole steel work then adopts loose mail lifting mode, reducing the place needs to constructing around, also reducing the requirement to loop wheel machine.

Description

大跨度钢结构连廊施工方法Construction method of long-span steel structure corridor

技术领域technical field

本发明涉及一种钢结构施工方法,特别是一种大跨度钢结构连廊施工方法。The invention relates to a steel structure construction method, in particular to a long-span steel structure corridor construction method.

背景技术Background technique

现有技术中的高空大跨度多层钢结构施工时一般都是现场组装后在通过吊机直接吊装,这种方式存在以下缺点,现场需要有比较大的安装场地,才能完成安装。另一方面使用的吊机也需要占用巨大的场地。所以这种施工方式并不适合在一些使用中的公共设施周围使用。The high-altitude and large-span multi-layer steel structure in the prior art is generally assembled on site and then directly hoisted by a crane. This method has the following disadvantages. The site needs a relatively large installation site to complete the installation. On the other hand, the crane used also needs to take up a huge space. Therefore, this construction method is not suitable for use around some public facilities in use.

发明内容Contents of the invention

本发明的目的是为了解决上述技术的不足而提供一种施工方便,占用施工场地少,且使用吊机小,安装后结构牢固的大跨度钢结构连廊施工方法。The object of the present invention is to provide a construction method for a long-span steel structure corridor that is convenient for construction, occupies less construction site, uses a small crane, and has a firm structure after installation.

为了达到上述目的,本发明所设计的大跨度钢结构连廊施工方法,首先安装跨度两侧的支撑钢柱,然后吊装横向水平钢梁,接着安装横向水平钢梁之间的支撑钢梁及斜撑钢梁,再安装两根横向水平钢梁之间的纵向水平钢梁以及跨水平拉杆,最后安装施工需要的横向钢梁,其特征是在安装支撑钢柱之后,先在两支撑钢柱之间安装辅助桁架,以辅助桁架为吊点吊装横向水平钢梁,再安装完横向水平钢梁之间的支撑钢梁及斜撑钢梁后拆除辅助桁架。这种施工方法的特点在于利用辅助桁架安装体积最大的横向水平钢梁,整个钢结构则采用散件吊装方式,降低了对周围施工的场地需要,也降低了对吊机的要求。In order to achieve the above purpose, the construction method of the large-span steel structure corridor designed by the present invention first installs the supporting steel columns on both sides of the span, then hoisting the horizontal horizontal steel beams, and then installing the supporting steel beams between the horizontal horizontal steel beams and the inclined Support steel beams, then install the longitudinal horizontal steel beams between the two horizontal steel beams and the horizontal tie rods, and finally install the horizontal steel beams required for construction. Install the auxiliary truss between them, use the auxiliary truss as the lifting point to hoist the horizontal steel beam, and then remove the auxiliary truss after installing the supporting steel beams and diagonal steel beams between the horizontal steel beams. The feature of this construction method is to use the auxiliary truss to install the largest horizontal steel beam, and the entire steel structure is hoisted in pieces, which reduces the need for surrounding construction sites and cranes.

为了提高施工完成后得到的钢结构的结构稳定性,施工前通过计算得到高空钢梁因自重形成的弹性形变,然后在施工时以辅助桁架为吊点时安装时,分别根据计算结果调整横向水平钢梁的形变。同时所述的根据计算结果调整横向水平钢梁的形变,是通过拉力葫芦调整横向水平钢梁的位置。这种方式在施工时预测了钢梁的形变影响,直接在施工时为钢梁形变提供预留余量,使得施工完成后的整个结构稳定。In order to improve the structural stability of the steel structure obtained after the construction is completed, the elastic deformation of the high-altitude steel beam due to its own weight is obtained through calculation before construction, and then when the auxiliary truss is used as the lifting point during construction, the horizontal level is adjusted according to the calculation results. Deformation of steel beams. At the same time, the adjustment of the deformation of the horizontal steel beam according to the calculation result is to adjust the position of the horizontal steel beam through a pull hoist. This method predicts the influence of the deformation of the steel beam during construction, and directly provides a reserve margin for the deformation of the steel beam during construction, making the entire structure stable after construction.

本发明所得到的大跨度钢结构连廊施工方法,通过散件吊装的方法,并利用安装较为简便的辅助桁架作为吊点,安装跨度巨大的横向水平钢梁,并预先设置了钢梁形变的余量,使得大部分情况下,支撑钢柱之间都有横向连接支撑存在,使得整个钢结构在散件吊装时就处于比较稳定的结构状态下,并最终完成整施工。另外,由于可以利用辅助桁架作为吊点,降低了吊装的难度,也为事先调整钢梁形变余量创造了条件。综上所述,本发明所得到的大跨度钢结构连廊施工方法具有设计合理,施工场地小,速度快,成本低,且施工得到的钢结构稳定性好的特点。The construction method of the large-span steel structure corridor obtained in the present invention adopts the method of hoisting parts, and uses the auxiliary truss which is relatively easy to install as the hoisting point, installs the horizontal steel beam with a huge span, and pre-sets the deformation of the steel beam. In most cases, there are horizontal connection supports between the supporting steel columns, so that the entire steel structure is in a relatively stable structural state when the parts are hoisted, and the whole construction is finally completed. In addition, since the auxiliary truss can be used as the lifting point, the difficulty of lifting is reduced, and it also creates conditions for adjusting the deformation allowance of the steel beam in advance. In summary, the construction method of the long-span steel structure corridor obtained by the present invention has the characteristics of reasonable design, small construction site, high speed, low cost, and good stability of the steel structure obtained by construction.

附图说明Description of drawings

图1是本发明的主视图;Fig. 1 is the front view of the present invention;

图2是本发明使用辅助桁架结构示意图;Fig. 2 is a schematic diagram of the auxiliary truss structure used in the present invention;

图3是本发明拆除辅助桁架后施工结构示意图。Fig. 3 is a schematic diagram of the construction structure after the auxiliary truss is removed according to the present invention.

具体实施方式Detailed ways

下面通过实施例结合附图对本发明作进一步的描述。The present invention will be further described below with reference to the accompanying drawings.

实施例1:Example 1:

如图所示,本实施例描述的大跨度钢结构连廊施工方法,如图1所示,首先安装跨度两侧的支撑钢柱1,在两支撑钢柱1之间安装辅助桁架2。然后如图2所示,以辅助桁架2为吊点7吊装横向水平钢梁3,接着安装上下两根横向水平钢梁3之间的支撑钢梁8及斜撑钢梁4。接着如图3所示,拆除辅助桁架2,再安装两根横向水平钢梁3之间的纵向水平钢梁以及跨水平拉杆,最后安装施工需要的横向钢梁6。As shown in the figure, the construction method of the long-span steel structure corridor described in this embodiment, as shown in Figure 1, first installs the supporting steel columns 1 on both sides of the span, and installs the auxiliary truss 2 between the two supporting steel columns 1. Then as shown in Figure 2, the horizontal horizontal steel beam 3 is hoisted with the auxiliary truss 2 as the lifting point 7, and then the supporting steel beam 8 and the diagonal steel beam 4 between the upper and lower horizontal horizontal steel beams 3 are installed. Then, as shown in FIG. 3 , the auxiliary truss 2 is removed, and then the longitudinal horizontal steel beam between the two horizontal horizontal steel beams 3 and the horizontal tie rods are installed, and finally the horizontal steel beam 6 required for construction is installed.

另一方面,通过计算得到高空钢梁因自重形成的弹性形变,以辅助桁架2为吊点安装时,分别根据计算结果通过拉力葫芦调整横向水平钢梁3的位置,以调整横向水平钢梁3的形变。On the other hand, the elastic deformation of the high-altitude steel beam due to its own weight is obtained through calculation. When the auxiliary truss 2 is used as the lifting point for installation, the position of the horizontal steel beam 3 is adjusted through the pull hoist respectively according to the calculation results to adjust the horizontal steel beam 3. deformation.

Claims (3)

1. a long-span steel structure corridor construction method, first the brace steel post of span both sides is installed, then transverse horizontal girder steel is lifted, support steel beam between transverse horizontal girder steel and diagonal brace girder steel are then installed, vertical equity girder steel between two transverse horizontal girder steels is installed again and across girt, the horizontal girder steel that last installation needs, it is characterized in that after installation brace steel post, first between two brace steel posts, auxiliary girder is installed, take auxiliary girder as suspension centre lifting transverse horizontal girder steel, auxiliary girder is removed after installing support steel beam between transverse horizontal girder steel and diagonal brace girder steel again.
2. long-span steel structure corridor construction method according to claim 1, it is characterized in that the elastic deformation formed because of deadweight by calculating transverse horizontal girder steel, then with auxiliary girder be suspension centre install time, respectively according to the deformation of result of calculation adjustment transverse horizontal girder steel.
3. long-span steel structure corridor construction method according to claim 2, is characterized in that the described deformation according to result of calculation adjustment transverse horizontal girder steel, is the position by pulling force cucurbit adjustment transverse horizontal girder steel.
CN201210447112.2A 2012-11-09 2012-11-09 Long-span steel structure corridor construction method Active CN103061514B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210447112.2A CN103061514B (en) 2012-11-09 2012-11-09 Long-span steel structure corridor construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210447112.2A CN103061514B (en) 2012-11-09 2012-11-09 Long-span steel structure corridor construction method

Publications (2)

Publication Number Publication Date
CN103061514A CN103061514A (en) 2013-04-24
CN103061514B true CN103061514B (en) 2015-12-02

Family

ID=48104376

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210447112.2A Active CN103061514B (en) 2012-11-09 2012-11-09 Long-span steel structure corridor construction method

Country Status (1)

Country Link
CN (1) CN103061514B (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103912128B (en) * 2014-02-28 2015-12-30 中国建筑第五工程局有限公司广州分公司 The construction method of high-altitude disjunctor steel truss
CN105507600A (en) * 2016-01-27 2016-04-20 中国中铁航空港建设集团有限公司 Hoisting system and hoisting construction method for large steel corridor trusses
CN107012949B (en) * 2017-05-10 2019-06-07 中国建筑第二工程局有限公司 Lifting method of large-span steel corridor
CN110017024A (en) * 2019-04-22 2019-07-16 上海建工一建集团有限公司 The construction method of the horizontal girder steel of contrary sequence method basement
CN110984589A (en) * 2019-11-29 2020-04-10 中国二十二冶集团有限公司 Method for mounting assembly platform of super-long steel beam high altitude
CN117780113A (en) * 2023-12-22 2024-03-29 中建八局第三建设有限公司 An overall lifting method for indoor large-span steel connecting bridges with tie rods

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04153460A (en) * 1990-10-17 1992-05-26 Mitsubishi Heavy Ind Ltd Building construction methods and equipment
JPH0882100A (en) * 1994-09-08 1996-03-26 Takenaka Komuten Co Ltd Lift-up method for constructing catwalk
CN101033636A (en) * 2007-03-23 2007-09-12 北京城建集团有限责任公司 Large span bidirectional string stretching girders rope accumulation slippage construction method
CN101446135A (en) * 2008-12-25 2009-06-03 上海市第一建筑有限公司 Integral hoisting system for superaltitude overlong jumbo beam by truss method and construction method thereof

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04153460A (en) * 1990-10-17 1992-05-26 Mitsubishi Heavy Ind Ltd Building construction methods and equipment
JPH0882100A (en) * 1994-09-08 1996-03-26 Takenaka Komuten Co Ltd Lift-up method for constructing catwalk
CN101033636A (en) * 2007-03-23 2007-09-12 北京城建集团有限责任公司 Large span bidirectional string stretching girders rope accumulation slippage construction method
CN101446135A (en) * 2008-12-25 2009-06-03 上海市第一建筑有限公司 Integral hoisting system for superaltitude overlong jumbo beam by truss method and construction method thereof

Also Published As

Publication number Publication date
CN103061514A (en) 2013-04-24

Similar Documents

Publication Publication Date Title
CN103061514B (en) Long-span steel structure corridor construction method
CN106436573B (en) Construction method of steel truss support for super high cable tower with large span upper beam corbel
CN102661054B (en) Lateral reinforcing structure in whole lifting of plane steel truss and whole lifting method
CN103643800B (en) The erection & lift system of buckling-restrained bracing member and construction method thereof
CN104746883B (en) A kind of arcuate space truss lifts construction method of installation with three machines
CN204940886U (en) A kind of mechanism of handling vestibule
CN102733615B (en) Unsymmetrical integral lifting construction method
CN103352428A (en) Suspension bridge cable bent tower beam non-support construction method
CN106193284B (en) The installation method and mounting structure of large span space drop level continuous truss frame
CN103469735A (en) Method for mounting curve ultrahigh hollow column plate type pier top solid section template
CN102777050B (en) Assembly type jig frame for longspan pipe truss roof girder
CN203497959U (en) Support structure without inclined rod for tower crane
CN101633483A (en) Integral lifting apparatus for steel structure net rack
CN105040591A (en) Positioning device for waveform steel web and positioning method thereof
CN202899639U (en) Concrete column structure
CN202785387U (en) Indoor cantilever crane
CN105464215A (en) Reverse construction method construction method of hanging structure incapable of being provided with vertical temporary support
CN105625732B (en) Superelevation overhanging steel structure truss support free construction method
CN205329549U (en) Corbel frame device is deposited to steel case roof beam temporarily
CN204690594U (en) A kind of simple and easy door frame of the Slidable for the installation of framing type steel box-girder crossbeam
CN206220461U (en) A kind of packaged type I-steel hoistway operation platform
CN203890893U (en) Supporting bracket for integral lifting of hollow slab girder
CN204455850U (en) The interim suspension connection device of Large Steel box beam erection
CN205367459U (en) Sharing of many hoisting points of bridge truss steel construction promotes hoist
CN203795318U (en) Integral hoisting system for rebar cage for large members

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
PP01 Preservation of patent right

Effective date of registration: 20161103

Granted publication date: 20151202

RINS Preservation of patent right or utility model and its discharge
PD01 Discharge of preservation of patent
PD01 Discharge of preservation of patent

Date of cancellation: 20170503

Granted publication date: 20151202

PP01 Preservation of patent right
PP01 Preservation of patent right

Effective date of registration: 20191031

Granted publication date: 20151202

PD01 Discharge of preservation of patent
PD01 Discharge of preservation of patent

Date of cancellation: 20221031

Granted publication date: 20151202