CN101250880B - Method for embedding and fixing steel tube concrete pile and steel tube pile anchor - Google Patents

Method for embedding and fixing steel tube concrete pile and steel tube pile anchor Download PDF

Info

Publication number
CN101250880B
CN101250880B CN2007103000060A CN200710300006A CN101250880B CN 101250880 B CN101250880 B CN 101250880B CN 2007103000060 A CN2007103000060 A CN 2007103000060A CN 200710300006 A CN200710300006 A CN 200710300006A CN 101250880 B CN101250880 B CN 101250880B
Authority
CN
China
Prior art keywords
steel pipe
concrete
steel
pile
pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN2007103000060A
Other languages
Chinese (zh)
Other versions
CN101250880A (en
Inventor
冯广胜
李艳哲
周功建
刘晓阳
郭煜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
No1 Engineering Co Ltd Zhongtie Bridge Bureau Group
1st Engineering Co Ltd of MBEC
Original Assignee
No1 Engineering Co Ltd Zhongtie Bridge Bureau Group
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by No1 Engineering Co Ltd Zhongtie Bridge Bureau Group filed Critical No1 Engineering Co Ltd Zhongtie Bridge Bureau Group
Priority to CN2007103000060A priority Critical patent/CN101250880B/en
Publication of CN101250880A publication Critical patent/CN101250880A/en
Application granted granted Critical
Publication of CN101250880B publication Critical patent/CN101250880B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The invention relates to a method for mounting a steel pipe concrete pile and a steel pipe pile anchor rock, wherein a steel casing is firstly nailed, then holes are drilled by a dustpan suction drill, after the dustpan suction forms the hole, a steel pipe is put into a design elevation (the steel pipe concrete pile needs to put a steel reinforcement cage at the same time), underwater concrete ispoured into the steel pipe, after the underwater concrete is upturned to a certain height along the outer wall of the steel pipe and the hole wall of a drilling, the whole pile concrete is poured, the steel casing is pulled out, and the pile is formed through solidification. The method for mounting a steel pipe concrete pile and a steel pipe pile anchor rock has the advantages that: 1, the problem that the depth which the steel pipe is nailed into the rock and the inclination is difficult to control is solved. 2, the concrete in the steel pipe is outward turned to a certain height, thereby solving the problem that the anchor rock of the steel pipe concrete pile is difficult to mount, and increasing the anti-push rigidity and a bearing capacity of the steel pipe concrete pile. 3, after a ring which is arranged between the steel pipe and the hole wall of the drilling is filled with cast-detritus, a small pipe is used to mudjack, a build-in enhanced measure that the underwater concrete is poured by the small pipe which is arranged in the ring between the steel pipe and the hole wall of the drilling, the build-in method of the anchor rock of the steel pipe concrete pile is more reliable and has more maneuverability.

Description

Steel tube concrete pile and steel pipe piled anchor rock build-in method
Technical field
The present invention relates to the anchor rock build-in method of a kind of steel tube concrete pile under water and steel pipe pile.
Background technology
In Foundation Designs such as bridge, harbour, offshore platform, foundation pile form commonly used has drilled pile and driven pile.In drilled pile conventional anchor rock job practices, general inserting earlier beaten the steel casing, utilize again towards sucking drilling machine and hole, make the follow-up of steel casing in the boring procedure as required, behind the pore-forming, transfer and be anchored in the basement rock at the bottom of making drilled pile behind reinforcing cage, the underwater casting concrete, but this method invar casing is gone into the rock degree of depth, anchor rock build-in is difficult to reach ideal effect, therefore need steel casing and drilled pile common when stressed when design, then be difficult to provide reliable resisting to push away rigidity and bearing capacity.
In steel pipe pile conventional anchor rock job practices, the general stake point that is provided with in the steel pipe pile bottom earlier, directly utilize pile driving equipment to insert then and play steel pipe, this method is only applicable to than incompetent bed or weathered rock formation, when running into than hard formation, steel pipe is gone into the rock degree of depth and is difficult to guarantee, thereby has reduced the anti-rigidity and the bearing capacity of pushing away of steel pipe pile.
Summary of the invention
The purpose of this invention is to provide a kind of new steel tube concrete pile and the anchor rock build-in method of steel pipe pile.
The anchor rock build-in of steel tube concrete pile adopts following technical scheme among the present invention: a kind of concrete filled steel tube piled anchor rock build-in method, at first insert and beat the steel casing, utilize again towards sucking drilling machine and hole, behind the sucking drilling machine pore-forming, transfer steel pipe and reinforcing cage to design altitude, pouring underwater concrete in steel pipe, treat that underwater concrete turns over to certain altitude between outer wall of steel pipe and borehole wall, whole pile concrete cast finishes, and extracts the steel casing, is frozen into steel tube concrete pile.
In order to obtain the relevant parameter guiding construction, before transferring steel pipe and reinforcing cage, determine the parameter of back-pressure head height in concrete mix, the steel pipe, reinforcing cage bottom reinforcement bars spacing by simulated test.
For making the underwater concrete in the steel pipe be easy to turn up, vertically have rectangular hole in described steel pipe bottom.
For the concrete that guarantees to turn up reaches the requirement height, guarantee anchor rock build-in effect, when transferring reinforcing cage, between steel casing and steel pipe, transfer ductule to absolute altitude, treat whole stake pour into a mould finish after, from pouring underwater concrete in the ductule to design elevation.
For the concrete that guarantees to turn up reaches the requirement height, guarantee anchor rock build-in effect, when transferring reinforcing cage, between steel casing and steel pipe, transfer madjack pipe to absolute altitude, after treating that whole stake cast finishes, fill out the throwing rubble in the ring between steel pipe and borehole wall, then in madjack pipe to rubble mud jacking to design elevation.
A kind of steel pipe piled anchor rock build-in method, at first insert and beat the steel casing, utilize again towards sucking drilling machine and hole, behind the sucking drilling machine pore-forming, transfer steel pipe to design altitude, pouring underwater concrete in steel pipe is treated that underwater concrete turns over to certain altitude between outer wall of steel pipe and borehole wall to stop, extract the steel casing, make steel pipe bottom concrete setting anchor rock become steel pipe pile.
In order to obtain the relevant parameter guiding construction, before transferring steel pipe, determine back-pressure head height parameter in underwater concrete match ratio, the steel pipe by simulated test.
For making the underwater concrete in the steel pipe be easy to turn up, vertically have rectangular hole in described steel pipe bottom.
For the concrete that guarantees to turn up reaches the requirement height, guarantee anchor rock build-in effect, after transferring steel pipe, between steel casing and steel pipe, transfer ductule to absolute altitude, treat the steel pipe inner concrete pour into a mould finish after, from pouring underwater concrete in the ductule to design elevation.
For the concrete that guarantees to turn up reaches the requirement height, guarantee anchor rock build-in effect, after transferring steel pipe, between steel casing and steel pipe, transfer madjack pipe to absolute altitude, after treating that the cast of steel pipe inner concrete finishes, fill out the throwing rubble in the ring between steel pipe and borehole wall, then in madjack pipe to rubble mud jacking to design elevation.
The invention has the advantages that: 1, the steel casing is set outside steel tube concrete pile, utilizes and behind the sucking drilling machine pore-forming, directly transfer steel pipe, solved steel pipe and gone into the rock degree of depth and the unmanageable problem of gradient.2, pouring underwater concrete in steel pipe makes the steel pipe inner concrete certain altitude that turns up by taking the correlation technique measure, has solved the anchor rock build-in difficult problem of steel tube concrete pile, has improved the anti-rigidity and the bearing capacity of pushing away of steel tube concrete pile.3, fill out in the ring between steel pipe and borehole wall and utilize the build-in enhancement measures that the ductule pouring underwater concrete is set in ductule mud jacking, the ring between steel pipe and borehole wall after throwing rubble, make the anchor rock build-in method of steel tube concrete pile more reliable, have more operability.4, the anchor rock build-in method to steel tube concrete pile is equally applicable to steel pipe pile among the present invention.
Description of drawings
Figure 1 shows that steel tube concrete pile shaping structures figure of the present invention;
Figure 2 shows that vertical rectangular hole, steel pipe bottom arrangement diagram among the present invention;
Figure 3 shows that steel pipe pile shaping structures figure of the present invention.
The specific embodiment
As shown in Figure 1, 2, the concrete job practices of concrete filled steel tube piled anchor rock is as follows: at first set up conventional over-water construction platform, insert and to beat steel casing 1 to design elevation 8, in the basement rock internal drilling to design elevation 14, hole clearly.Following steel pipe 2 is to design elevation 13, and steel pipe 2 bottoms are welded with stiffening plate 15, vertically has rectangular hole 16 on the stiffening plate 15.Descending reinforcing cage 3 in steel pipe 2, transfer ductule (or madjack pipe) 5 to absolute altitude 10 between steel pipe 2 and steel casing 1, pouring underwater concrete 4 in steel pipe 2 then, and it is turned over to certain altitude 9 in the ring of 6 of steel pipe 2 outer walls and borehole walls.After whole pile concrete cast finishes, utilize ductule 5 pouring underwater concretes to design elevation 7 (or throw between steel pipe 2 and the borehole wall 6 fill out rubble after, utilize again madjack pipe 5 in rubble mud jacking to design elevation 7), absolute altitude 7 generally need exceed scar 12 and riverbed face 11.
Realize can selecting to take following measure in the above-mentioned concrete filled steel tube piled anchor rock procedure:
1, can adopt the model with main body steel pipe pile proportional (as 1: 2) to carry out the simulation process test, come guiding construction, make underwater concrete highly easily reach designing requirement along turning on the steel pipe external annulus with the proportioning parameter that obtains underwater concrete.In the simulated test, workability, the slump of emphasis control underwater concrete, highly too for a short time when not reaching designing requirement when turning up, adjust proportioning to increase the concrete slump and flowability; When turning up when highly too big, also need adjust proportioning to reduce the concrete slump and flowability, by test of many times, can obtain the needed underwater concrete proportioning of engineering like this.Also can check steel pipe walls and the bonding situation between concrete of turning up by test simultaneously, the density of underwater concrete and mechanical property etc.
2, fill out in the ring between steel pipe and borehole wall and throw rubble and (utilize the build-in enhancement measures that the ductule pouring underwater concrete is set in ductule mud jacking or the ring between steel pipe and borehole wall behind the general 5mm of particle diameter~25mm), can carry out the simulation process test with measure 1 shared same model, to obtain the relevant parameter of rubble, mud jacking, underwater concrete.In the test of rubble mud jacking, can satisfy the designing requirement of rubble mud jacking by adjustment ballast grain sizes, mud jacking proportioning, pressure size according to the actual compactness of mud jacking.In the test of ductule pouring underwater concrete, can according to the ductule inner concrete in the steel pipe external annulus on turn over and mobility status, compactness, adjust aggregate size, the slump of underwater concrete, so that the ductule inner concrete is easy to turn over and flow, thereby make the height of ductule concrete perfusion in the steel pipe external annulus reach designing requirement.
3, in steel pipe during pouring underwater concrete, can take that the measure of head back-pressure makes underwater concrete highly reach designing requirement along turning on the steel pipe external annulus in the steel pipe.
4, adjust reinforcing cage bottom reinforcement bars spacing, as the main muscle in bottom also being cancelled the bottom stirrup than top master's muscle doubling range interval, so that underwater concrete is easy to turn up in the steel pipe.
5, vertically join out rectangular hole in the steel pipe bottom, so that underwater concrete is easy to turn up in the steel pipe.
6, steel casing diameter D2 is generally than the big 0.8~1.2m of diameter of steel tube D1, and diameter of steel tube D1 is generally than the little 0.6~1.0m of boring aperture D3.
Shown in Fig. 2,3, the concrete job practices of steel pipe piled anchor rock is as follows: at first set up conventional over-water construction platform, insert and to beat steel casing 1 to design elevation 8, in the basement rock internal drilling to design elevation 14, hole clearly.Following steel pipe 2 is to design elevation 13, and steel pipe 2 bottoms are welded with stiffening plate 15, vertically has rectangular hole 16.Between steel pipe 2 and steel casing 1, transfer ductule (or madjack pipe) 5 to absolute altitude 10, pouring underwater concrete 4 in steel pipe 2 then, and it is turned over to certain altitude 9 in the ring of 6 of steel pipe 2 outer walls and borehole walls stop, utilize ductule 5 pouring underwater concretes to design elevation 7 (or throw between steel pipe 2 and the borehole wall 6 fill out rubble after, utilize again madjack pipe 5 in rubble mud jacking to design elevation 7), absolute altitude 7 generally need exceed scar 12 and riverbed face 11.
The measure of being taked in the concrete filled steel tube piled anchor rock method is vertically joined out rectangular hole, steel casing and diameter of steel tube relative size etc. and all is equally applicable to steel pipe pile as head back-pressure, steel pipe bottom in simulation process test, the steel pipe.

Claims (2)

1. steel pipe piled anchor rock build-in method, at first insert and beat steel casing (1), utilize again towards sucking drilling machine and hole, it is characterized in that: behind the sucking drilling machine pore-forming, determine underwater concrete (4) match ratio by simulated test, the interior back-pressure head height of steel pipe (2) parameter, transfer steel pipe (2) to design altitude, pouring underwater concrete (4) in steel pipe (2), treating that underwater concrete (4) turns over to certain altitude between steel pipe (2) outer wall and borehole wall (6) stops, extract steel casing (1), make steel pipe bottom concrete setting anchor rock become steel pipe pile, vertically have rectangular hole (16) in described steel pipe (2) bottom, after transferring steel pipe (2), between steel casing (1) and steel pipe (2), transfer ductule (5) to absolute altitude (10), after treating that steel pipe inner concrete cast finishes, from the interior pouring underwater concrete of ductule (5) to design elevation (7).
2. steel pipe piled anchor rock build-in method, at first insert and beat steel casing (1), utilize again towards sucking drilling machine and hole, it is characterized in that: behind the sucking drilling machine pore-forming, determine underwater concrete (4) match ratio by simulated test, the interior back-pressure head height of steel pipe (2) parameter, transfer steel pipe (2) to design altitude, pouring underwater concrete (4) in steel pipe (2), treating that underwater concrete (4) turns over to certain altitude between steel pipe (2) outer wall and borehole wall (6) stops, extract steel casing (1), make steel pipe bottom concrete setting anchor rock become steel pipe pile, vertically have rectangular hole (16) in described steel pipe (2) bottom, after transferring steel pipe (2), between steel casing (1) and steel pipe (2), transfer madjack pipe (5) to absolute altitude (10), after treating that steel pipe (2) inner concrete cast finishes, fill out the throwing rubble in the ring between steel pipe (2) and borehole wall (6), then from madjack pipe (5) interior to rubble mud jacking to design elevation (7).
CN2007103000060A 2007-12-19 2007-12-19 Method for embedding and fixing steel tube concrete pile and steel tube pile anchor Active CN101250880B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2007103000060A CN101250880B (en) 2007-12-19 2007-12-19 Method for embedding and fixing steel tube concrete pile and steel tube pile anchor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2007103000060A CN101250880B (en) 2007-12-19 2007-12-19 Method for embedding and fixing steel tube concrete pile and steel tube pile anchor

Publications (2)

Publication Number Publication Date
CN101250880A CN101250880A (en) 2008-08-27
CN101250880B true CN101250880B (en) 2010-12-08

Family

ID=39954463

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2007103000060A Active CN101250880B (en) 2007-12-19 2007-12-19 Method for embedding and fixing steel tube concrete pile and steel tube pile anchor

Country Status (1)

Country Link
CN (1) CN101250880B (en)

Families Citing this family (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102086645B (en) * 2009-12-07 2012-05-23 中交第三航务工程勘察设计院有限公司 Socketed pile and construction method thereof
CN102605781A (en) * 2012-04-10 2012-07-25 中交二公局第三工程有限公司 Rocky bed steel pipe pile sinking construction process
CN102943466B (en) * 2012-11-14 2014-07-16 中铁十二局集团有限公司 Construction method for miniature steel pipe concrete pile to penetrate through roadbed layer for reinforcing soft foundation construction
CN102966111B (en) * 2012-12-13 2016-01-27 中铁上海工程局集团第二工程有限公司 A kind of steel pipe pile anchoring construction method in deep water torrent intectate steep bare rock
CN103485340B (en) * 2013-09-18 2016-03-30 中交二航局第四工程有限公司 A kind of antinode plate fore shaft steel pile casting device and construction method thereof
CN104563111B (en) * 2014-12-01 2016-06-22 浙江省岩土基础公司 A kind of construction method of taper pile anchor rock
CN105239566B (en) * 2015-08-12 2017-01-25 河海大学 Multi-head stirring type large-diameter cast-in-situ pipe pile device and application thereof
CN105926593B (en) * 2016-04-22 2018-11-13 东通岩土科技(杭州)有限公司 A kind of column pile construction method in boulder bed
CN105908773A (en) * 2016-06-12 2016-08-31 上海勘测设计研究院有限公司 Two-stage socketed pile wind turbine foundation for shallow covering stratum foundation of offshore wind plant and construction method
CN106400832B (en) * 2016-11-29 2018-08-10 湖南送变电勘察设计咨询有限公司 A kind of construction method of environment-friendly type assembled grouting behind shaft or drift lining steel cylinder pile foundation
CN106677169B (en) * 2017-01-17 2019-05-31 陕西隆极机械设备有限公司 It is adapted to the squeezed screw thread pile construction method that spins of severe cold weather
CN107059908A (en) * 2017-05-23 2017-08-18 安徽工程大学 Large diameter steel pipe concrete-pile
CN112376552B (en) * 2020-11-24 2021-07-30 武汉盛士瑞建设工程有限公司 Energy-saving pile foundation and construction method thereof
CN112538852A (en) * 2020-11-30 2021-03-23 湖北工建基础设施建设有限公司 Construction method of deepwater bored pile for thin covering layer
CN113006085A (en) * 2021-03-12 2021-06-22 河北工业大学 Supporting-first-excavating foundation pit supporting system for inclined prefabricated steel piles and construction method of supporting-second-excavating foundation pit supporting system
CN113373915B (en) * 2021-06-30 2023-05-12 中国十九冶集团有限公司 Method for reinforcing steel column pile structure
CN115217100A (en) * 2021-12-15 2022-10-21 高永光 Construction method of ocean engineering cast-in-place pile

Also Published As

Publication number Publication date
CN101250880A (en) 2008-08-27

Similar Documents

Publication Publication Date Title
CN101250880B (en) Method for embedding and fixing steel tube concrete pile and steel tube pile anchor
CN104846810B (en) Self-circulating posterior grouting bored pile construction method
CN102767173B (en) High polymer material slurry filled discrete material pile composite foundation and construction method thereof
CN100572683C (en) The large-diameter ultra-deep rock borehole bottom-expanding filling pile job practices
KR101194594B1 (en) Construction method of the concrete filled steel tube column
CN106930277B (en) A kind of construction of manual-excavation cast-in-place pile method
CN104452829B (en) A kind of pile-raft foundation float Structure and construction method
CN105507340B (en) Construction method of bridge pile foundation in mountainous area
CN108118698A (en) The construction method of stake and special Static pressure pile driver
CN100532733C (en) Diving casting cast-in-place pile construction method for constructing in scree layer and sand layer
CN108547641A (en) The bottom stab ilization system and its construction method in rich water soft stratum heavy haul railway tunnel
CN108166483A (en) Bored pile construction method
CN102733378A (en) Construction method of concrete pile
CN102011399A (en) PHC pile-based multiple high jet pedestal pile construction method
CN103510510A (en) Reinforced long spiral drilling concrete grouting pile and construction method thereof
CN101255692B (en) Heterotype squeezing-close bottom-enlarging filling pile construction method
CN110042844A (en) A kind of construction method of cast-in-place major diameter foundation pit support pipe pile
JP3927842B2 (en) Construction method of double pipe digging small diameter pile
KR101135163B1 (en) Grout injection and replacement device and the soft ground foundation concrete pile using the same method
CN103938637A (en) Construction method for rigid pile and flexible pile combination foundation pit supporting for hard-interlayer soft soil geology
CN107740427A (en) A kind of construction method of interpolation concrete prefabricated square stake foundation pit enclosure structure
KR20120030493A (en) Method of reinforcing existing concrete footing structure using micropile and structure thereof
CN101603315B (en) Method for constructing seepage prevention system of secondary cofferdam for immersed tube tunnel
CN203594023U (en) Enhanced type long auger drilling pressure-grouting concrete pile
CN102704478B (en) Building anchor rod construction technology

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant