CN101148945A - Building exterior wall finishing automatic lifting workbench - Google Patents
Building exterior wall finishing automatic lifting workbench Download PDFInfo
- Publication number
- CN101148945A CN101148945A CNA2007100201871A CN200710020187A CN101148945A CN 101148945 A CN101148945 A CN 101148945A CN A2007100201871 A CNA2007100201871 A CN A2007100201871A CN 200710020187 A CN200710020187 A CN 200710020187A CN 101148945 A CN101148945 A CN 101148945A
- Authority
- CN
- China
- Prior art keywords
- workbench
- column
- building
- exterior wall
- wall finishing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Abstract
The automatically lifting workbench for finishing outer wall of building consists of one well type frame connected to the building, one workbench, and one workbench lifting mechanism. The workbench lifting mechanism has one motor, one driving wheel connected to the rotation shaft of the motor and one vertical driving belt inside the well type frame and meshed to the driving wheel; and the workbench is embedded inside the well type frame and is raised or lowered by means of the forward or backward rotation of the motor. The automatically lifting workbench may reach different heights of the outer wall of building easily, and has simple operation, high work efficiency, capacity of lowering finishing cost, and high safety.
Description
Technical field
The present invention relates to the architecture construction technology, but specifically a kind of workbench that is used for the building exterior wall finishing automatic lifting.
Background technology
After the building main body construction is finished, the task of next stage is that skin is fitted up.At present, building exterior wall finishing still continue to use traditional scaffold layer by layer bed board as the finishing working platform.This working platform, just not saying building when main body construction, build the danger of bringing in traditional scaffold and the later unloading process, consumption and holding time with regard to its built material are also quite long, and change layer construction and need constantly to alternate and lay workbench, not only labour intensive, whole operating efficiency are also lower.The applicant is in the patent of having applied for " outside shelf for building construction " on the same day to State Intellectual Property Office, this be a kind of building main body construction with layer outrigger, can no longer need to build traditional scaffold, so just exist building exterior wall finishing, the particularly problem of high-rise building outer wall finishing of how solving.
Summary of the invention
The present invention is directed to the problems referred to above, proposed a kind of building exterior wall finishing automatic lifting workbench, purpose is to increase work efficiency, strengthens security performance, reduces the building operations cost.
Technical solution of the present invention
The present invention mainly is made up of the elevating mechanism of the column that is connected with the building main body, workbench and control workbench.To be the drive that connected by the machine shaft that is located at workbench be meshed with the upright driving-belt that is provided with in the well formula column described elevating mechanism, drives workbench and operate.Column is a well formula column, embeddedly is connected with workbench, and elevating mechanism is provided with two synchronous motors and can connects and in gear and the well formula column upright tooth bar is set and is meshed, and also can be to connect in sprocket wheel and the well formula column upright chain to be set and to be meshed.Workbench embeds the vertical of well formula column and slides to two masts of the guide rail that is provided with along well formula column, and forward and reverse rotation of motor realizes the liter of workbench integral body and falls.
Beneficial effect of the present invention:
(1) the present invention needs only just commentaries on classics, the counter-rotating of control motor shaft as the building exterior wall finishing platform, can rise to drop to reach different aspects, and is easy to operate, can obviously increase work efficiency.
(2) the present invention has saved the raw material of a large amount of structure exterior wall finishing platforms, goes back saving of work and time, and the exterior wall finishing cost is reduced significantly.
(3) the present invention has changed the working method of traditional architecture beyond the region of objective existence wall finishing, with the constructor build, the dismantling operation platform and need constantly more lay-up row's scaffold floor and up and down danger such as climbing work and finish by machinery, make the unsafe factor in the construction drop to minimum point.
(4) the present invention when middle-high building is constructed, alternative hoist at present commonly used, from and can save the lease expenses of hoist.
Description of drawings
Fig. 1 is the attached status architecture schematic diagram of looking of the present invention's (two upright post type) and building annexation.
Fig. 2 is the attached status architecture schematic diagram of looking of the present invention's (single upright post type) and building annexation.
Fig. 3 is that the master of the present invention's (two upright post type) and building annexation looks the status architecture schematic diagram.
Fig. 4 is the attached status architecture schematic diagram of looking of the present invention's (single upright post type) and building annexation.
Fig. 5 is the side-looking status architecture schematic diagram of the present invention and building annexation.
The specific embodiment
As shown in Figure 1, 2, workbench 1 of the present invention is embedded in and connects well formula column 2, wherein: well formula column 2 can embed as two of Fig. 1, as the single connection of Fig. 2, also can be that a plurality of embeddings connect; Workbench 1 can be fitted up the shape extension of building facade as required and build, and make the trend and the identical (not shown) of building 3 facades trend of workbench 1: well formula column 2 is connected on the building 3.
Shown in Fig. 3,4, workbench 1 of the present invention is the frame type steel work, comprises stull 11, directly supports 12, diagonal brace 13, lays laminate on the work top, and the workbench surrounding is perpendicular railing 14, and is with safety net.Motor 4 is installed in the below that well formula column 2 embeds operating positions, and is provided with synchronous two, to prevent perfectly safe when in running order.The tooth bar with well formula column of establishing travelling gear on the motor shaft is meshed; The chain with well formula column of establishing drive sprocket on the motor shaft is meshed.Well formula column also is provided with spacing button 21 with the rocking of restriction tooth bar (chain) 41, and can guarantee the optimal engagement of itself and drive.
As shown in Figure 5, well formula column 2 promptly is connected with building 3 with rod member 22 every a floor, and vertical dual-side guide rail 23 is to utilize on two root posts of well formula column the place ahead to slide on the workbench of motor installation place.In addition: the table top of workbench 1 is provided with bed board, and periphery is provided with railing 14 and safety net.
The present invention is through mechanical calculation, the also equal compliant requirement of do practice checking.To sum up, the present invention can reach the expection goal of the invention.
Claims (8)
1. building exterior wall finishing automatic lifting workbench, it is characterized in that: it mainly is made up of the elevating mechanism of the column that is connected with the building main body, workbench and control workbench, described elevating mechanism be the drive that connects by the machine shaft that is located at workbench, with column in upright driving-belt be set be meshed, drive workbench and realize rising and falling.
2. building exterior wall finishing automatic lifting workbench according to claim 1 is characterized in that: the axle of the motor of described elevating mechanism (4) connects the upright tooth bar that is provided with in gear and the column and is meshed; Or connecting the upright chain that is provided with in sprocket wheel and the column is meshed.
3. building exterior wall finishing automatic lifting workbench according to claim 1, it is characterized in that: described column is a well formula column (2), be two columns or single column or a plurality of column, embeddedly be connected with workbench, the vertical dual-side in motor installation place that workbench embeds well formula column is provided with guide rail 23 along sliding on two root posts of well formula column the place ahead.
4. building exterior wall finishing automatic lifting workbench according to claim 1 and 2 is characterized in that: the motor of described elevating mechanism (4) is two synchronous motors.
5. building exterior wall finishing automatic lifting workbench according to claim 1 is characterized in that: workbench (1) can be fitted up the shape extension of building facade as required and build, and the trend of workbench and building (3) facade trend are coincide.
6. building exterior wall finishing automatic lifting workbench according to claim 1 or 5, it is characterized in that: workbench (1) is the frame type steel work, comprise stull (11), straight support (12), diagonal brace (13), work top is provided with bed board, and the workbench surrounding is with railing (14) and safety net.
7. according to claim 1 or 3 described building exterior wall finishing automatic lifting workbench, it is characterized in that: the tooth bar of well formula column (2) or sprocket wheel (41) also are provided with spacing button (21).
8. according to claim 1 or 3 described building exterior wall finishing automatic lifting workbench, it is characterized in that: well formula column (2) promptly is connected with building (3) with rod member (22) every a floor.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNA2007100201871A CN101148945A (en) | 2007-03-02 | 2007-03-02 | Building exterior wall finishing automatic lifting workbench |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNA2007100201871A CN101148945A (en) | 2007-03-02 | 2007-03-02 | Building exterior wall finishing automatic lifting workbench |
Publications (1)
Publication Number | Publication Date |
---|---|
CN101148945A true CN101148945A (en) | 2008-03-26 |
Family
ID=39249629
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CNA2007100201871A Pending CN101148945A (en) | 2007-03-02 | 2007-03-02 | Building exterior wall finishing automatic lifting workbench |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101148945A (en) |
Cited By (14)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105460735A (en) * | 2015-12-28 | 2016-04-06 | 广州市京龙工程机械有限公司 | Lift mast section module with platform component |
CN105587114A (en) * | 2015-12-28 | 2016-05-18 | 广州市京龙工程机械有限公司 | Improved construction ascending and descending platform |
CN105672641A (en) * | 2016-03-11 | 2016-06-15 | 上海建工集团股份有限公司 | Double-guide-frame multi-stage synchronous lifting working platform and construction method thereof |
CN105672640A (en) * | 2016-03-11 | 2016-06-15 | 上海建工集团股份有限公司 | Single-guide-frame multi-stage lifting work platform and construction method thereof |
CN105672642A (en) * | 2016-03-11 | 2016-06-15 | 上海建工集团股份有限公司 | Dual-guide-frame multistage lifting working platform with adjustable gaps and construction method thereof |
CN105715031A (en) * | 2016-03-11 | 2016-06-29 | 上海建工集团股份有限公司 | Double-guide-frame multi-stage lifting working platform with adjustable spacing and length and construction method for double-guide-frame multi-stage lifting working platform |
CN105715030A (en) * | 2016-03-11 | 2016-06-29 | 上海建工集团股份有限公司 | Single-guide-frame multi-stage lifting working platform with adjustable spacing and length and construction method for single-guide-frame multi-stage lifting working platform |
CN105781091A (en) * | 2016-03-11 | 2016-07-20 | 上海建工集团股份有限公司 | Adjustable-length single-guide-frame multilevel synchronous lifting working platform and construction method thereof |
CN105781092A (en) * | 2016-03-11 | 2016-07-20 | 上海建工集团股份有限公司 | Single-guide-frame and multi-stage lifting working platform with adjustable interval and construction method thereof |
CN105804383A (en) * | 2016-03-11 | 2016-07-27 | 上海建工集团股份有限公司 | Length-adjustable double-guide-frame multistage synchronous lifting working platform and construction method thereof |
CN106276549A (en) * | 2015-06-01 | 2017-01-04 | 江苏京龙工程机械有限公司 | Two-stage two-layer single-column lifting working platform |
CN108529458A (en) * | 2018-04-20 | 2018-09-14 | 哈尔滨共阳科技咨询有限公司 | Hanging method outside a kind of panel material room |
CN111515909A (en) * | 2020-04-29 | 2020-08-11 | 南宁学院 | Quick overhaul device of electrical control equipment |
CN114876178A (en) * | 2022-05-13 | 2022-08-09 | 中交四公局第一工程有限公司 | Climbing frame clamping mechanism for building construction |
-
2007
- 2007-03-02 CN CNA2007100201871A patent/CN101148945A/en active Pending
Cited By (15)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106276549A (en) * | 2015-06-01 | 2017-01-04 | 江苏京龙工程机械有限公司 | Two-stage two-layer single-column lifting working platform |
CN105460735A (en) * | 2015-12-28 | 2016-04-06 | 广州市京龙工程机械有限公司 | Lift mast section module with platform component |
CN105587114A (en) * | 2015-12-28 | 2016-05-18 | 广州市京龙工程机械有限公司 | Improved construction ascending and descending platform |
CN105715030A (en) * | 2016-03-11 | 2016-06-29 | 上海建工集团股份有限公司 | Single-guide-frame multi-stage lifting working platform with adjustable spacing and length and construction method for single-guide-frame multi-stage lifting working platform |
CN105672642A (en) * | 2016-03-11 | 2016-06-15 | 上海建工集团股份有限公司 | Dual-guide-frame multistage lifting working platform with adjustable gaps and construction method thereof |
CN105715031A (en) * | 2016-03-11 | 2016-06-29 | 上海建工集团股份有限公司 | Double-guide-frame multi-stage lifting working platform with adjustable spacing and length and construction method for double-guide-frame multi-stage lifting working platform |
CN105672640A (en) * | 2016-03-11 | 2016-06-15 | 上海建工集团股份有限公司 | Single-guide-frame multi-stage lifting work platform and construction method thereof |
CN105781091A (en) * | 2016-03-11 | 2016-07-20 | 上海建工集团股份有限公司 | Adjustable-length single-guide-frame multilevel synchronous lifting working platform and construction method thereof |
CN105781092A (en) * | 2016-03-11 | 2016-07-20 | 上海建工集团股份有限公司 | Single-guide-frame and multi-stage lifting working platform with adjustable interval and construction method thereof |
CN105804383A (en) * | 2016-03-11 | 2016-07-27 | 上海建工集团股份有限公司 | Length-adjustable double-guide-frame multistage synchronous lifting working platform and construction method thereof |
CN105672641A (en) * | 2016-03-11 | 2016-06-15 | 上海建工集团股份有限公司 | Double-guide-frame multi-stage synchronous lifting working platform and construction method thereof |
CN108529458A (en) * | 2018-04-20 | 2018-09-14 | 哈尔滨共阳科技咨询有限公司 | Hanging method outside a kind of panel material room |
CN111515909A (en) * | 2020-04-29 | 2020-08-11 | 南宁学院 | Quick overhaul device of electrical control equipment |
CN114876178A (en) * | 2022-05-13 | 2022-08-09 | 中交四公局第一工程有限公司 | Climbing frame clamping mechanism for building construction |
CN114876178B (en) * | 2022-05-13 | 2024-03-01 | 中交四公局第一工程有限公司 | Climbing frame clamping mechanism for building construction |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101148945A (en) | Building exterior wall finishing automatic lifting workbench | |
JP5688493B2 (en) | Compound lifting stage | |
CN102505845B (en) | Quick construction method for high-rise buildings | |
CN200975099Y (en) | automatic up-down workstation for buildings exterior wall decoration | |
CN103359626B (en) | A kind of Marine riser crane | |
CN100526581C (en) | Reciprocating self-climbing type climbing form system and its climbing form method | |
CN105672642A (en) | Dual-guide-frame multistage lifting working platform with adjustable gaps and construction method thereof | |
CN107059609A (en) | Bridge maintenance system span formula steel structure platform | |
CN109025234A (en) | A kind of building high-altitude vacantly construct with can level, vertically the track crane ship that walk | |
JP2007205043A (en) | Construction method and dismantling method of scaffolding for high-rise building | |
CN105672641A (en) | Double-guide-frame multi-stage synchronous lifting working platform and construction method thereof | |
CN212002447U (en) | Supporting frame of assembled building board of encorbelmenting | |
CN105625780B (en) | Elevator is equipped with the tower type parking building of single side outlet | |
CN207582922U (en) | Exterior wall finishing lifting type workbench | |
CN105064750B (en) | Elevator is provided with the tower type parking building that bilateral is exported | |
CN106437126B (en) | A kind of console mode hydraulic lifting scaffold guiding bearing and method for dismounting | |
CN1145973A (en) | Multi-stacking parking system | |
CN205713036U (en) | High pier over-form construction platform | |
CN215858940U (en) | Novel detachable combined type steel structure aerial work moving operation platform | |
CN105019657A (en) | Building construction system | |
CN206529691U (en) | Bridge maintenance system steel construction inspection platform | |
CN205653119U (en) | Ladder is used in building site construction convenient to go up and down | |
CN204876579U (en) | Building construction system | |
CN210048454U (en) | Adjustable lifting platform | |
CN105178602A (en) | Building construction system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C02 | Deemed withdrawal of patent application after publication (patent law 2001) | ||
WD01 | Invention patent application deemed withdrawn after publication |