CN215858940U - Novel detachable combined type steel structure aerial work moving operation platform - Google Patents

Novel detachable combined type steel structure aerial work moving operation platform Download PDF

Info

Publication number
CN215858940U
CN215858940U CN202122033244.8U CN202122033244U CN215858940U CN 215858940 U CN215858940 U CN 215858940U CN 202122033244 U CN202122033244 U CN 202122033244U CN 215858940 U CN215858940 U CN 215858940U
Authority
CN
China
Prior art keywords
connecting frame
upper connecting
lower connecting
steel structure
platform
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202122033244.8U
Other languages
Chinese (zh)
Inventor
刘伟
吴星
董效杰
史俊彦
董贺
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Second Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Original Assignee
Second Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Second Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd filed Critical Second Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Priority to CN202122033244.8U priority Critical patent/CN215858940U/en
Application granted granted Critical
Publication of CN215858940U publication Critical patent/CN215858940U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Forklifts And Lifting Vehicles (AREA)

Abstract

本实用新型涉及拆卸组合式钢结构高空作业移动操作平台领域,具体为一种新型的可拆卸组合式钢结构高空作业移动操作平台,包括上连接架和下连接架,上连接架设置在导轨的上方,下连接架设置在导轨的下方,且下连接架的左右两侧外套于上连接架的左右外侧,有益效果是:本实用新型通过加入滑轮的结构,通过电机带动滑轮在导轨内进行转动,使其可以控制该装置进行水平移动,通过螺柱和螺纹套筒的结构,通过螺柱的转动带动升降平台的上升或者下降,避免传统缆绳吊篮两人作业的要求,利用本平台操作大大减少了操作人员上下移动,提别是悬空操作,可以明显提高施工效率和保证施工安全,缩短工期,具有良好的经济效益和社会效益。

Figure 202122033244

The utility model relates to the field of dismantling combined steel structure high-altitude operation mobile operation platforms, in particular to a novel dismountable combined steel structure high-altitude operation mobile operation platform, which comprises an upper connecting frame and a lower connecting frame, and the upper connecting frame is arranged on a guide rail. Above, the lower connecting frame is arranged below the guide rail, and the left and right sides of the lower connecting frame are sheathed on the left and right outer sides of the upper connecting frame. , so that it can control the device to move horizontally. Through the structure of the stud and the threaded sleeve, the rotation of the stud drives the lifting or lowering of the lifting platform, avoiding the requirement of two-person operation of the traditional cable hanging basket, and using this platform to operate greatly It reduces the up and down movement of the operator, especially the suspended operation, which can significantly improve the construction efficiency, ensure the construction safety, shorten the construction period, and have good economic and social benefits.

Figure 202122033244

Description

Novel detachable combined type steel structure aerial work moving operation platform
Technical Field
The utility model relates to the field of detachable combined type steel structure aerial work moving operation platforms, in particular to a novel detachable combined type steel structure aerial work moving operation platform.
Background
All adopt the ground installation to low latitude small-span steel construction at present, but accomplish the back to the whole vestibule hoist and mount of the large-scale steel construction of narrow and small space high altitude large-span, there are a large amount of high altitude construction projects, and the steel vestibule component is many, the interval is big from top to bottom, the component is bulky, the welding workman removes the difficult scheduling problem and leads to the construction operation cycle length, high altitude construction utilizes the safe risk that traditional operation platform can't guarantee the high-frequency removal, especially to the edge position, because the impetus is few, constructor operating space is little, so utilize this novel combination formula steel construction operation platform of dismantling to just very necessary.
SUMMERY OF THE UTILITY MODEL
The utility model aims to provide a novel detachable combined type steel structure aerial work mobile operation platform to solve the problems in the background technology.
In order to achieve the purpose, the utility model provides the following technical scheme: the utility model provides a novel can dismantle combination formula steel construction high altitude construction removes operation platform, including last link and lower link, it sets up the top at the guide rail to go up the link, the link sets up the below at the guide rail down, and the left and right sides overcoat of lower link is in the outside about last link, go up the link and pass through fixing bolt fixed connection with lower link, the inboard of going up the link is rotated and is connected with the pulley that drives the link horizontal direction and remove, the below middle part of lower link is rotated and is connected with the double-screw bolt, double-screw bolt and lift platform's middle part top spiro union, and the below both sides fixedly connected with of lower link carries out spacing wall built-up to lift platform's rising and decline.
Preferably, the middle part of the lower part of the upper connecting frame is provided with an empty groove and is erected above the guide rail through the empty groove, the upper connecting frame is horizontally connected with the upper part of the guide rail in a sliding manner, and pulleys are arranged on the left side and the right side of the inner part of the empty groove.
Preferably, the pulley is installed at the medial extremity of dead lever, and the pulley rotates with the dead lever to be connected, and the outside end of dead lever and the left and right sides inner wall middle part fixed connection of last link, the pulley drive through external motor.
Preferably, the upper middle part of the lower connecting frame is provided with an empty groove, the width of the empty groove of the lower connecting frame is larger than that of the outer wall of the upper connecting frame, the upper connecting frame is vertically inserted into the empty groove of the lower connecting frame, and the upper connecting frame is fixedly connected with the left side and the right side of the lower connecting frame through four fixing bolts.
Preferably, the middle part of the lower connecting frame is fixedly connected with the top of the rotary bearing, the lower part of the rotary bearing is rotatably connected with the top of the stud, the bottom of the stud is driven by the motor, and the lower parts of the left side and the right side of the lower connecting frame are fixedly connected with the top of the wall.
Preferably, sliding connection has a lift platform on the double-screw bolt, and lift platform includes threaded sleeve, hanging flower basket and spout, lift platform's top middle part fixedly connected with threaded sleeve, threaded sleeve's inboard and double-screw bolt spiro union.
Preferably, a hanging basket is fixedly connected to the upper portion of the outer side of the lifting platform, sliding grooves are vertically formed in the left side and the right side of the lifting platform, and the sliding grooves are connected with a wall in a sliding mode.
Compared with the prior art, the utility model has the beneficial effects that: the utility model can control the device to horizontally move by adding a pulley structure and driving the pulley to rotate in the guide rail through the motor, and can avoid the requirement of two-person operation of the traditional cable hanging basket by driving the lifting platform to ascend or descend through the rotation of the stud and the structure of the threaded sleeve.
Drawings
FIG. 1 is a top three-dimensional view of the present invention;
FIG. 2 is a front view of the structure of the present invention;
FIG. 3 is a bottom three-dimensional view of the present invention;
fig. 4 is a side view of the present invention.
In the figure: the device comprises an upper connecting frame 1, a lower connecting frame 2, a rotary bearing 21, a fixing bolt 3, a pulley 4, a fixing rod 41, a stud 5, a wall hanging 6, a lifting platform 7, a threaded sleeve 71, a hanging basket 72 and a sliding groove 73.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Referring to fig. 1 to 4, the present invention provides a technical solution: the utility model provides a novel can dismantle combination formula steel construction high altitude construction and remove operation platform, includes link 1 and lower link 2, goes up link 1 and sets up in the top of guide rail, and lower link 2 sets up in the below of guide rail.
The left side and the right side of the lower connecting frame 2 are sleeved outside the left side and the right side of the upper connecting frame 1, and the upper connecting frame 1 and the lower connecting frame 2 are fixedly connected through a fixing bolt 3.
The inner side of the upper connecting frame 1 is rotatably connected with a pulley 4 which drives the upper connecting frame 1 to move in the horizontal direction, and the middle part below the lower connecting frame 2 is rotatably connected with a stud 5.
The stud 5 is in threaded connection with the upper portion of the middle of the lifting platform 7, and the two sides of the lower portion of the lower connecting frame 2 are fixedly connected with wall hanging bodies 6 which limit the ascending and descending of the lifting platform 7.
The middle part of the lower part of the upper connecting frame 1 is provided with an empty groove and is erected above the guide rail through the empty groove, the upper connecting frame 1 is horizontally connected with the upper part of the guide rail in a sliding manner, and pulleys 4 are arranged on the left side and the right side of the inner part of the empty groove.
The pulley 4 is installed at the inboard end of dead lever 41, and the pulley 4 rotates with dead lever 41 and is connected, and the outside end of dead lever 41 and the left and right sides inner wall middle part fixed connection of last link 1, the pulley 4 drive through external motor.
The upper middle part of the lower connecting frame 2 is provided with an empty groove, the width of the empty groove of the lower connecting frame 2 is larger than that of the outer wall of the upper connecting frame 1, the upper connecting frame 1 is vertically inserted into the empty groove of the lower connecting frame 2, and the upper connecting frame 1 and the left side and the right side of the lower connecting frame 2 are fixedly connected through four fixing bolts 3.
The middle part of the lower connecting frame 2 is fixedly connected with the top of the rotating bearing 21, the lower part of the rotating bearing 21 is rotatably connected with the top of the stud 5, the bottom of the stud 5 is driven by a motor, and the lower parts of the left side and the right side of the lower connecting frame 2 are fixedly connected with the top of the wall hanging 6.
The stud 5 is connected with a lifting platform 7 in a sliding mode, the lifting platform 7 comprises a threaded sleeve 71, a hanging basket 72 and a sliding groove 73, the threaded sleeve 71 is fixedly connected to the middle of the upper portion of the lifting platform 7, and the inner side of the threaded sleeve 71 is in threaded connection with the stud 5.
A hanging basket 72 is fixedly connected to the upper portion of the outer side of the lifting platform 7, sliding grooves 73 are vertically formed in the left side and the right side of the lifting platform 7, and the sliding grooves 73 are vertically and slidably connected with the wall hanging 6.
The working principle is as follows: after the guide rail is laid at the required high-altitude action position, the upper connecting frame 1 is moved to the position above the guide rail through the hoisting equipment.
After the upper connecting frame 1 is arranged on the guide rail, the inner side empty groove below the upper connecting frame is attached to the guide rail, and the pulley 4 extends into the guide rail.
The lower link 2 is moved to a position just below the upper link 1 and the lower link 2 is lifted up so that the upper link 1 is completely inserted into the upper middle hollow of the lower link 2.
After the upper connecting frame 1 and the lower connecting frame 2 are fixed through the fixing bolts 3, the installation of the device is completed.
When the electric vehicle is used, the wall at the bottom of the lower connecting frame 2 is grounded, and the motor passing through the bottom of the stud 5 is installed on the ground.
The stud 5 is driven by the motor to rotate anticlockwise, and the lifting platform 7 is limited by the wall built-up 6 due to the fact that the stud 5 is in threaded connection with the threaded sleeve 71.
At this point, the lifting platform 7 slides vertically down the stud 5 until it moves to the bottom of the stud 5, and the operator stands on the lifting platform 7 and is protected by the basket 72.
And the stud 5 is rotated clockwise, so that the lifting platform 7 moves vertically upwards, and constructors are lifted to a place where construction is required.
And the pulley 4 is driven to rotate by an external motor, so that a constructor can horizontally move when standing in the hanging basket 72, and the construction area of the constructor is increased.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the utility model, the scope of which is defined in the appended claims and their equivalents.

Claims (7)

1.一种新型的可拆卸组合式钢结构高空作业移动操作平台,包括上连接架(1)和下连接架(2),其特征在于:所述上连接架(1)设置在导轨的上方,所述下连接架(2)设置在导轨的下方,且下连接架(2)的左右两侧外套于上连接架(1)的左右外侧,上连接架(1)和下连接架(2)通过固定螺栓(3)固定连接,上连接架(1)的内侧转动连接有带动上连接架(1)水平方向移动的滑轮(4),下连接架(2)的下方中部转动连接有螺柱(5),螺柱(5)与升降平台(7)的中部上方螺接,且下连接架(2)的下方两侧固定连接有对升降平台(7)的上升和下降进行限位的挂壁(6)。1. A novel detachable combined steel structure mobile operation platform for aerial work, comprising an upper connecting frame (1) and a lower connecting frame (2), characterized in that: the upper connecting frame (1) is arranged above the guide rail , the lower connecting frame (2) is arranged below the guide rail, and the left and right sides of the lower connecting frame (2) are covered on the left and right outer sides of the upper connecting frame (1), and the upper connecting frame (1) and the lower connecting frame (2) ) is fixedly connected by fixing bolts (3), the inner side of the upper connecting frame (1) is rotatably connected with a pulley (4) that drives the upper connecting frame (1) to move in the horizontal direction, and the lower middle of the lower connecting frame (2) is rotatably connected with a screw. The column (5) and the stud (5) are screwed to the upper part of the middle of the lifting platform (7), and the lower two sides of the lower connecting frame (2) are fixedly connected with a limiter for the lifting and lowering of the lifting platform (7). Wall mounted (6). 2.根据权利要求1所述的一种新型的可拆卸组合式钢结构高空作业移动操作平台,其特征在于:所述上连接架(1)的下方中部设置有空槽且通过空槽架设在导轨的上方,上连接架(1)与导轨上方水平滑动连接,空槽内部左右两侧设置有滑轮(4)。2. A novel detachable combined steel structure mobile operating platform for aerial work according to claim 1, characterized in that: the lower middle of the upper connecting frame (1) is provided with an empty slot and is erected on the upper connecting frame (1) through the empty slot. Above the guide rail, the upper connecting frame (1) is horizontally slidably connected with the upper part of the guide rail, and pulleys (4) are arranged on the left and right sides inside the hollow groove. 3.根据权利要求2所述的一种新型的可拆卸组合式钢结构高空作业移动操作平台,其特征在于:所述滑轮(4)安装在固定杆(41)的内侧端部,滑轮(4)与固定杆(41)转动连接,固定杆(41)的外侧端部与上连接架(1)的左右两侧内壁中部固定连接,滑轮(4)的通过外置电机带动。3. A novel detachable combined steel structure aerial work mobile operation platform according to claim 2, characterized in that: the pulley (4) is installed on the inner end of the fixed rod (41), and the pulley (4) ) is rotatably connected with the fixing rod (41), the outer end of the fixing rod (41) is fixedly connected with the middle part of the left and right inner walls of the upper connecting frame (1), and the pulley (4) is driven by an external motor. 4.根据权利要求1所述的一种新型的可拆卸组合式钢结构高空作业移动操作平台,其特征在于:所述下连接架(2)的上方中部设置有空槽,下连接架(2)的空槽宽度大于上连接架(1)的外壁宽度,上连接架(1)竖直插入下连接架(2)的空槽中,且通过四个固定螺栓(3)将上连接架(1)和下连接架(2)的左右两侧固定连接。4. A novel detachable combined steel structure mobile operating platform for aerial work according to claim 1, characterized in that: an upper middle part of the lower connecting frame (2) is provided with an empty groove, and the lower connecting frame (2) is provided with an empty groove. ) is larger than the width of the outer wall of the upper connecting frame (1), the upper connecting frame (1) is vertically inserted into the empty slot of the lower connecting frame (2), and the upper connecting frame ( 1) and the left and right sides of the lower connecting frame (2) are fixedly connected. 5.根据权利要求4所述的一种新型的可拆卸组合式钢结构高空作业移动操作平台,其特征在于:所述下连接架(2)的下方中部与旋转轴承(21)的顶部固定连接,旋转轴承(21)的下方与螺柱(5)的顶部转动连接,螺柱(5)的底部通过电机带动,下连接架(2)的左右两侧下方与挂壁(6)的顶部固定连接。5. A novel detachable combined steel structure mobile operation platform for aerial work according to claim 4, characterized in that: the lower middle part of the lower connecting frame (2) is fixedly connected to the top of the rotating bearing (21) , the bottom of the rotary bearing (21) is rotatably connected with the top of the stud (5), the bottom of the stud (5) is driven by the motor, and the bottom of the left and right sides of the lower connecting frame (2) is fixed with the top of the wall (6) connect. 6.根据权利要求5所述的一种新型的可拆卸组合式钢结构高空作业移动操作平台,其特征在于:所述螺柱(5)上滑动连接有升降平台(7),升降平台(7)包括螺纹套筒(71)、吊篮(72)和滑槽(73),升降平台(7)的上方中部固定连接有螺纹套筒(71),螺纹套筒(71)的内侧与螺柱(5)螺接。6. A novel detachable combined steel structure mobile operation platform for aerial work according to claim 5, characterized in that: a lifting platform (7) is slidably connected to the stud (5), and the lifting platform (7) ) includes a threaded sleeve (71), a hanging basket (72) and a chute (73), the upper middle of the lifting platform (7) is fixedly connected with a threaded sleeve (71), and the inner side of the threaded sleeve (71) is connected to the stud (5) Screw connection. 7.根据权利要求6所述的一种新型的可拆卸组合式钢结构高空作业移动操作平台,其特征在于:所述升降平台(7)的外侧上方固定连接有吊篮(72),升降平台(7)的左右两侧内竖直设置有滑槽(73),滑槽(73)与挂壁(6)竖直滑动连接。7. A novel detachable combined steel structure mobile operation platform for aerial work according to claim 6, characterized in that: a hanging basket (72) is fixedly connected above the outer side of the lifting platform (7), and the lifting platform The left and right sides of (7) are vertically provided with chute (73), and the chute (73) is vertically slidably connected with the hanging wall (6).
CN202122033244.8U 2021-08-27 2021-08-27 Novel detachable combined type steel structure aerial work moving operation platform Active CN215858940U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202122033244.8U CN215858940U (en) 2021-08-27 2021-08-27 Novel detachable combined type steel structure aerial work moving operation platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202122033244.8U CN215858940U (en) 2021-08-27 2021-08-27 Novel detachable combined type steel structure aerial work moving operation platform

Publications (1)

Publication Number Publication Date
CN215858940U true CN215858940U (en) 2022-02-18

Family

ID=80242973

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202122033244.8U Active CN215858940U (en) 2021-08-27 2021-08-27 Novel detachable combined type steel structure aerial work moving operation platform

Country Status (1)

Country Link
CN (1) CN215858940U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114457999A (en) * 2022-03-10 2022-05-10 安徽伟宏钢结构集团股份有限公司 A mobile operating platform for frame steel structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114457999A (en) * 2022-03-10 2022-05-10 安徽伟宏钢结构集团股份有限公司 A mobile operating platform for frame steel structure

Similar Documents

Publication Publication Date Title
CN206655129U (en) A kind of nacelle device of bridge construction
CN107522125A (en) A kind of portable device for lifting of power engineering
CN112900825B (en) A hoistway self-climbing operation platform
CN110015624A (en) It is a kind of for removing the mobile work platform of high-rise buildings
CN215558710U (en) Adjustable track traction erection device for bridge construction
CN215858940U (en) Novel detachable combined type steel structure aerial work moving operation platform
CN206359150U (en) A kind of hanging basket system
CN102730518A (en) Cement truck lifter
CN211596364U (en) A multifunctional anti-collision wall construction trolley
CN210341634U (en) Viaduct outer wall painting crane
CN221856149U (en) Guide rope type hanging basket
CN209091151U (en) A telescopic arm type window cleaner
CN218292712U (en) But height-adjusting's scaffold frame for house construction
CN214531843U (en) Lifting device for climbing frame
CN110577153A (en) An upper module gantry component unit for an escalator
CN213475352U (en) An electric lift type aerial work platform
CN204402107U (en) One machine one plate back boom multi-storied garage
CN212248943U (en) Support tool for construction of green building energy-saving roof
CN203555689U (en) Electric hanging basket for vertical shaft
CN211255177U (en) Municipal works electromechanical device's salvagees device
CN210366899U (en) a lift platform
CN205709737U (en) A kind of high-lift operation hanging cradle
CN223227023U (en) Intelligent safety early warning hanging basket
CN218061309U (en) Multistage safe lifting construction platform
CN208532052U (en) A kind of material lift device of the building safety with anti-collision effect

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant