CN101131000A - 一种控制建筑物不均匀沉降的施工方法 - Google Patents

一种控制建筑物不均匀沉降的施工方法 Download PDF

Info

Publication number
CN101131000A
CN101131000A CNA2006100154289A CN200610015428A CN101131000A CN 101131000 A CN101131000 A CN 101131000A CN A2006100154289 A CNA2006100154289 A CN A2006100154289A CN 200610015428 A CN200610015428 A CN 200610015428A CN 101131000 A CN101131000 A CN 101131000A
Authority
CN
China
Prior art keywords
foundation
building
settlement
buildings
ground
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CNA2006100154289A
Other languages
English (en)
Inventor
张新旺
王桂云
王文华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
TIANJIN SENYU CONSTRUCTION TECHNIQUES LEGAL ADVICE Ltd
Original Assignee
TIANJIN SENYU CONSTRUCTION TECHNIQUES LEGAL ADVICE Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by TIANJIN SENYU CONSTRUCTION TECHNIQUES LEGAL ADVICE Ltd filed Critical TIANJIN SENYU CONSTRUCTION TECHNIQUES LEGAL ADVICE Ltd
Priority to CNA2006100154289A priority Critical patent/CN101131000A/zh
Publication of CN101131000A publication Critical patent/CN101131000A/zh
Pending legal-status Critical Current

Links

Landscapes

  • Foundations (AREA)

Abstract

一种控制建筑物不均匀沉降的施工方法,其特征在于,它包括以下步骤:(1)设置沉降缝;(2)增强承重结构整体刚度;(3)地基处理。本发明的优越性在于:1.设置合理的沉降缝,是减少由于地基不均匀变形对建筑物造成危害的有效方法之一;2.上部结构和基础自重约占总荷载的40%~70%,其中民用建筑的比例较大,约占60%~70%,因此,地基处理和减轻结构自重是减少建筑物沉降的有效措施。

Description

一种控制建筑物不均匀沉降的施工方法
(一)技术领域:
本发明涉及一种建筑施工方法,特别是一种控制建筑物不均匀沉降的施工方法。
(二)背景技术:
目前,由于建筑物是由多道纵横墙及楼盖、屋盖等组成,并且由建筑物的平面形状,体型的复杂多变,其空间刚度难以定量计算和表达,再加上建筑物的荷载分布不均匀,以及地基土的压缩性各不相同,迄今还无法通过理论计算来解决上部结构与地基共同工作的问题。但是,除从建筑物体型合理设计上给予充分考虑外,根据工程实践可从施工工艺加以解决。
(三)发明内容:
本发明的目的在于设计一种控制建筑物不均匀沉降的施工方法,它从结构措施及地基处理两方面综合考虑,是一种有效控制建筑物不均匀沉降的施工方法。
本发明的技术方案:一种控制建筑物不均匀沉降的施工方法,其特征在于,它包括以下步骤:
(1)设置沉降缝:
在下列部位设置沉降缝:
i.地基土的压缩性有显著差异处;
ii.地基基础形式不同处;
iii.平面复杂的建筑物转折部位;
iv.建筑物高度或荷载差异处;
v建筑结构类型不同处;
vi.局部地下室的边缘处;
vii.分期建造房屋的分界处;
(2)增强承重结构整体刚度:
i.控制建筑物的长高比;
ii.设置圈梁,在建筑物的墙体内设置钢筋砼圈梁;
(3)地基处理:
i.根据地基上的软弱程度和上部结构不同情况,采取钢筋混凝土十字交叉条形基础、筏片基础、箱型基础或做成钢筋混凝土基础墙的形式;
ii.减轻结构自重;
iii.设置地下室和半地下室。
上述所说的地基处理中的筏片基础做成肋梁式。
上述所说的地基处理中的减轻结构自重,采取选用钢结构或轻质墙体材料。
本发明的优越性在于:1、设置合理的沉降缝,是减少由于地基不均匀变形对建筑物造成危害的有效方法之一;2、上部结构和基础自重约占总荷载的40%~70%,其中民用建筑的比例较大,约占60%~70%,因此,地基处理和减轻结构自重是减少建筑物沉降的有效措施。
(四)具体实施方式:
实施例:一“工”字形建筑物,在其纵横单元相交处,基础密集。采取本案控制建筑物不均匀沉降的施工方法,其特征在于,它包括以下步骤:
(1)设置沉降缝:
在下列部位设置沉降缝:
i.地基土的压缩性有显著差异处;
ii.地基基础形式不同处;
iii.平面复杂的建筑物转折部位;
iv.建筑物高度或荷载差异处;
v建筑结构类型不同处;
vi.局部地下室的边缘处;
vii.分期建造房屋的分界处;
(2)增强承重结构整体刚度:
i.控制建筑物的长高比;
ii.设置圈梁,在建筑物的墙体内设置钢筋砼圈梁;
(3)地基处理:
i.根据地基上的软弱程度和上部结构情况,采取钢筋混凝土十字交叉条形基础或筏片基础做成钢筋混凝土基础墙的形式,地基处理中的筏片基础做成肋梁式;
ii.减轻结构自重,采取选用轻质墙体材料;
iii.设置地下室。

Claims (3)

1.一种控制建筑物不均匀沉降的施工方法,其特征在于,它包括以下步骤:
(1)设置沉降缝:
在下列部位设置沉降缝:
i.地基土的压缩性有显著差异处;
ii.地基基础形式不同处;
iii.平面复杂的建筑物转折部位;
iv.建筑物高度或荷载差异处;
v建筑结构类型不同处;
vi.局部地下室的边缘处;
vii.分期建造房屋的分界处;
(2)增强承重结构整体刚度:
i.控制建筑物的长高比;
ii.设置圈梁,在建筑物的墙体内设置钢筋砼圈梁;
(3)地基处理:
i.根据地基上的软弱程度和上部结构不同情况,采取钢筋混凝土十字交叉条形基础、筏片基础、箱形基础或做成钢筋混凝土基础墙的形式;
ii.减轻结构自重;
iii.设置地下室和半地下室。
2.根据权利要求1所说的一种控制建筑物不均匀沉降的施工方法,其特征在于所说的地基处理中的筏片基础做成肋梁式。
3.根据权利要求1所说的一种控制建筑物不均匀沉降的施工方法,其特征在于所说的地基处理中的减轻结构自重,采取选用钢结构或轻质墙体材料。
CNA2006100154289A 2006-08-23 2006-08-23 一种控制建筑物不均匀沉降的施工方法 Pending CN101131000A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNA2006100154289A CN101131000A (zh) 2006-08-23 2006-08-23 一种控制建筑物不均匀沉降的施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNA2006100154289A CN101131000A (zh) 2006-08-23 2006-08-23 一种控制建筑物不均匀沉降的施工方法

Publications (1)

Publication Number Publication Date
CN101131000A true CN101131000A (zh) 2008-02-27

Family

ID=39128396

Family Applications (1)

Application Number Title Priority Date Filing Date
CNA2006100154289A Pending CN101131000A (zh) 2006-08-23 2006-08-23 一种控制建筑物不均匀沉降的施工方法

Country Status (1)

Country Link
CN (1) CN101131000A (zh)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102808423A (zh) * 2012-08-23 2012-12-05 天津市津美园林工程有限公司 消除地面与建筑物外墙交接处沉降裂缝的方法
CN105274979A (zh) * 2015-10-12 2016-01-27 上海市基础工程集团有限公司 在既有结构上开孔对下部土体进行地基处理的施工方法
US11384501B2 (en) 2020-05-06 2022-07-12 Qingdao Tianyuan Weiye Thermal Insulation And Waterproof Engineering Co., Ltd. Method for sealing post-cast strip in foundation with no gap

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102808423A (zh) * 2012-08-23 2012-12-05 天津市津美园林工程有限公司 消除地面与建筑物外墙交接处沉降裂缝的方法
CN105274979A (zh) * 2015-10-12 2016-01-27 上海市基础工程集团有限公司 在既有结构上开孔对下部土体进行地基处理的施工方法
US11384501B2 (en) 2020-05-06 2022-07-12 Qingdao Tianyuan Weiye Thermal Insulation And Waterproof Engineering Co., Ltd. Method for sealing post-cast strip in foundation with no gap

Similar Documents

Publication Publication Date Title
CN204040464U (zh) 一种楼板模板支承结构
CN102926504A (zh) 一种用于钢混叠合粱结合部的连接钢构件及施工方法
CN108756196A (zh) 一种装配式建筑主体防护装置及其施工方法
CN102777037B (zh) 一种简单实用的大跨度钢梁吊装施工方法
CN101131000A (zh) 一种控制建筑物不均匀沉降的施工方法
CN204098314U (zh) 钢板组合楼板
CN203922362U (zh) 装配式模块化钢结构电梯井道
CN202577331U (zh) 施工现场彩钢板活动房装配式混凝土基础
CN204059906U (zh) 电梯井道整体提升型钢脚手架
CN104669434A (zh) 大型钢筋混凝土预制柱、梁吊装辅助预埋件施工方法
CN103112766A (zh) 悬置于房屋建筑地下室顶板上方的施工电梯及其施工方法
CN205348214U (zh) 一种柱状式钢筋混凝土与型钢混合式龙门吊基础
CN205475849U (zh) 一种钢结构建筑装配式预制混凝土剪力墙
CN102817467A (zh) 钢结构高空安装操作平台
CN208396338U (zh) 承重墙地下施工托换支撑体系
CN208137272U (zh) 一种自承重砌体隔墙支撑刚架
CN209293173U (zh) 模块式钢结构栈桥外部走廊
CN206846097U (zh) 一种门刚与框架分装式管道支架结构
CN202081512U (zh) 高低连体建筑无障碍装修结构
CN207260377U (zh) 一种楼层组合
CN206599994U (zh) 一种免洞穿式模板支撑体系支顶件
CN205172031U (zh) 一种能节省空间的建筑夹层结构
CN206737358U (zh) 一种预制装配式钢混框架电梯井结构
CN205907879U (zh) 一种增强双向传力性能的叠合板
CN208533564U (zh) 管廊

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Open date: 20080227