CN100500507C - 船舶机舱底层舾装件的安装方法 - Google Patents
船舶机舱底层舾装件的安装方法 Download PDFInfo
- Publication number
- CN100500507C CN100500507C CNB2007100392366A CN200710039236A CN100500507C CN 100500507 C CN100500507 C CN 100500507C CN B2007100392366 A CNB2007100392366 A CN B2007100392366A CN 200710039236 A CN200710039236 A CN 200710039236A CN 100500507 C CN100500507 C CN 100500507C
- Authority
- CN
- China
- Prior art keywords
- equipment
- line
- grid
- ship
- installation method
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Jib Cranes (AREA)
Abstract
本发明公开了一种船舶机舱底层舾装件的安装方法,其包括步骤:以肋位和距舯的纵骨线作为基准线,在内场地上画出船舯线、肋位线和纵骨线和内底板边线,在墙上或立柱上设置高度线,以确定格栅高度和基座高度;树立格栅框架的立柱,在地面上拼装格栅平面,并与立柱焊接;在格栅上定位设备基座、维修平台;安装设备至上述基座和维修平台上;安装管子支架;安装管子、阀件和附件;将安装好的机舱底层舾装件整体或分为一个以上的单元吊运上船。该方法有效地缩短船坞内的作业时间,提高工作效率,实现舾装作业前移、船坞作业内场化,改善了作业环境,提高了作业的安全性,并降低了造船成本。
Description
技术领域
本发明涉及一种船舶制造,特别涉及一种船舶机舱底层舾装件的安装方法。
背景技术
长期以来,机舱底层的管路安装,要在船体机舱总段在船坞内定位以后,再采用若干个管束单元和盆舾装的安装方法。这样做不仅延长了在船坞内的作业时间,同时施工的环境也不理想。
发明内容
本发明要解决的技术问题是提供一种可以实现船坞作业内场化,舾装作业前移的船舶机舱底层舾装件的安装方法。
本发明的目的是通过以下技术方案实现的:
一种船舶机舱底层舾装件的安装方法,其包括步骤:
S1、以肋位和距舯的纵骨线作为基准线,在内场地上画出船舯线、肋位线和纵骨线和内底板边线,在墙上或立柱上设置高度线,以确定格栅高度和基座高度;
S2、树立格栅框架的立柱,在地面上拼装格栅平面,并与立柱焊接;
S3、在格栅上定位设备基座、维修平台;
S4、安装设备至上述基座和维修平台上;
S5、安装管子支架;
S6、安装管子、阀件和附件;
S7、将安装好的机舱底层舾装件整体或分为一个以上的单元吊运上船。
其中,在S5中利用格栅和基座的立柱作为管子的支架,或将格栅的支柱兼作箱柜基座的支柱。
其中,S1中使用激光经纬仪设定该格栅高度和基座高度。
其中,S2中连接处的格栅角钢作点焊处理。
其中,S3中相邻的设备采用公共基座,自重不大的非动力设备的基座只对面板进行定位。
其中,S4中按设备的外形和接口尺寸制作临时模型来代替设备进行定位。
其中,各单元的接口位置尽可能平直,上下接口叉开,两相邻单元连接管的法兰布置要呈阶梯状。
本发明的积极进步效果在于:
一种船舶机舱底层舾装件的安装方法,其能有效地缩短船坞内的作业时间,提高工作效率,实现舾装作业前移、船坞作业内场化,改善了作业环境,提高了作业的安全性,并降低了造船成本。
具体实施方式
下面给出本发明较佳实施例,以详细说明本发明的技术方案。
一种船舶机舱底层舾装件的安装方法,其包括以下几个步骤:
1、首先以肋位和距舯的纵骨线作为基准线,在内场地上画出船舯线、肋位线和纵骨线和内底板边线,在墙上或立柱上设置高度线,以确定格栅高度和基座高度,最好用激光经纬仪打出高度点,其中格栅为现有技术,即用来固定各个装置的钢板,在此不再赘述;
2、树立格栅框架的立柱,在地面上拼装格栅平面,将格栅平面翻身后吊运到立柱上端并与立柱焊接,注意两个单元(根据内场的起吊能力将整个机舱底层组装好的部件划分为若干单元)连接处的格栅角钢作点焊处理;
3、在格栅上定位设备基座、维修平台,一般动力设备的基座必须带有足够强度的支撑,而非动力设备的基座(自重又不大的设备)可以只做面板,同时利用格栅的立柱来作为支撑,基座与格栅框架连成一个整体,相邻的设备考虑采用公共基座;
4、安装设备至上述基座和维修平台上,如某些设备、阀件暂时没有到货时,可以先按设备的外形和接口尺寸做一个临时模型来代替,同时要注意考虑到单元在船上的位置,要预留安装及维护操作的空间;
5、安装管子支架,并尽量利用格栅和基座的立柱作为管子的支架,也可以将格栅的支柱兼作箱柜基座的支柱,最大限度地节省材料,避免重复设置,并且各小单元的接口位置尽可能平直,上下接口叉开,尽量方便与单元外管子的连接,两相邻单元连接管的法兰布置要呈阶梯状;
6、安装管子、阀件和附件,注意管路的阀件、附件安装时必须与系统介质流向一致,如阀件有编号的应对号入座,管子法兰连接及与机械设备的连接时,两法兰面的中心偏移、平面歪斜和间隙须符合公司的相关质量要求,安装时不允许强拉硬撬。
7、在内场按吊装顺序将各单元拆开,分别吊运上船。(如起吊能力允许,也可以整体吊运上船。)
Claims (7)
1、一种船舶机舱底层舾装件的安装方法,其包括步骤:
S1、以肋位和距舯的纵骨线作为基准线,在内场地上画出船舯线、肋位线和纵骨线和内底板边线,在墙上或立柱上设置高度线,以确定格栅高度和基座高度;
S2、树立格栅框架的立柱,在地面上拼装格栅平面,并与立柱焊接;
S3、在格栅上定位设备基座、维修平台;
S4、安装设备至上述基座和维修平台上;
S5、安装管子支架;
S6、安装管子、阀件和附件;
S7、将安装好的机舱底层舾装件整体或分为一个以上的单元吊运上船。
2、根据权利要求1所述的船舶机舱底层舾装件的安装方法,其特征为,在S5中利用格栅和基座的立柱作为管子的支架,或将格栅的支柱兼作箱柜基座的支柱。
3、根据权利要求1或2所述的船舶机舱底层舾装件的安装方法,其特征为,S1中使用激光经纬仪设定该格栅高度和基座高度。
4、根据权利要求1或2所述的船舶机舱底层舾装件的安装方法,其特征为,S2中连接处的格栅角钢作点焊处理。
5、根据权利要求1或2所述的船舶机舱底层舾装件的安装方法,其特征为,S3中相邻的设备采用公共基座,自重不大的非动力设备的基座只对面板进行定位。
6、根据权利要求1或2所述的船舶机舱底层舾装件的安装方法,其特征为,S4中按设备的外形和接口尺寸制作临时模型来代替设备进行定位。
7、根据权利要求1或2所述的船舶机舱底层舾装件的安装方法,其特征为,各单元的接口位置尽可能平直,上下接口叉开,两相邻单元连接管的法兰布置要呈阶梯状。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNB2007100392366A CN100500507C (zh) | 2007-04-06 | 2007-04-06 | 船舶机舱底层舾装件的安装方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNB2007100392366A CN100500507C (zh) | 2007-04-06 | 2007-04-06 | 船舶机舱底层舾装件的安装方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN101032995A CN101032995A (zh) | 2007-09-12 |
CN100500507C true CN100500507C (zh) | 2009-06-17 |
Family
ID=38729777
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CNB2007100392366A Expired - Fee Related CN100500507C (zh) | 2007-04-06 | 2007-04-06 | 船舶机舱底层舾装件的安装方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN100500507C (zh) |
Families Citing this family (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101628610B (zh) * | 2008-07-18 | 2012-08-22 | 上海船厂船舶有限公司 | 船坞天桥的定位方法 |
CN103204225B (zh) * | 2012-01-12 | 2015-12-16 | 江苏新世纪造船有限公司 | 船舶机舱出入工艺孔的分段建造阶段安装方法 |
CN103204222A (zh) * | 2012-01-12 | 2013-07-17 | 江苏新世纪造船有限公司 | 机舱集控室模块化制造 |
CN102556282B (zh) * | 2012-01-17 | 2014-08-13 | 广州广船国际股份有限公司 | 一种船舶集控室的建造工艺 |
CN102874378B (zh) * | 2012-10-29 | 2015-02-25 | 南通润邦海洋工程装备有限公司 | 机舱盆舾装工艺 |
CN103661802B (zh) * | 2013-12-05 | 2016-01-20 | 江苏新时代造船有限公司 | 舾装件的安装作业方法 |
CN110282077B (zh) * | 2018-03-19 | 2022-04-01 | 江苏现代造船技术有限公司 | 一种造船过程中绑扎桥分段的建造方法 |
CN112224357B (zh) * | 2020-10-20 | 2021-11-09 | 广州黄船海洋工程有限公司 | 一种饱和潜水压力舱室安装方法 |
CN112528404B (zh) * | 2020-12-04 | 2023-04-14 | 江南造船(集团)有限责任公司 | 适用于船舶舾装平台的格栅设计方法、装置、介质及终端 |
CN114633851B (zh) * | 2022-03-23 | 2023-03-17 | 江南造船(集团)有限责任公司 | 一种船舶格栅区域装配方法 |
-
2007
- 2007-04-06 CN CNB2007100392366A patent/CN100500507C/zh not_active Expired - Fee Related
Non-Patent Citations (8)
Title |
---|
单元组装是提高预舾装水平的有效手段. 章祖岐.造船技术,第5期. 1996 |
单元组装是提高预舾装水平的有效手段. 章祖岐.造船技术,第5期. 1996 * |
船体建造工艺学. 冯运檀,47-57,72-82,90-108,哈尔滨船舶工程学院出版社. 1990 |
船体建造工艺学. 冯运檀,47-57,72-82,90-108,哈尔滨船舶工程学院出版社. 1990 * |
船舶舾装及其发展趋势. 朱国英,朱珉虎.江苏船舶,第11卷第2期. 1994 |
船舶舾装及其发展趋势. 朱国英,朱珉虎.江苏船舶,第11卷第2期. 1994 * |
船舶舾装工作前移的探讨. 程古林,李天生.造船技术,第4期. 2005 |
船舶舾装工作前移的探讨. 程古林,李天生.造船技术,第4期. 2005 * |
Also Published As
Publication number | Publication date |
---|---|
CN101032995A (zh) | 2007-09-12 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN100500507C (zh) | 船舶机舱底层舾装件的安装方法 | |
CN101306717A (zh) | 一种船舶建造中轴系照光方法 | |
CN102184747B (zh) | 一种模块化钢制安全壳环吊梁及其组装方法 | |
CN206394828U (zh) | 舱室模块化卫生单元 | |
JP5732527B2 (ja) | 円筒型タンクの構築方法 | |
CN201856883U (zh) | 在车间内场制作成的船舶管系单元 | |
CN103243926A (zh) | 高层建筑工程管井立管吊装的施工方法 | |
CN204916044U (zh) | 一种船用可拆式木甲板固定装置 | |
CN202337344U (zh) | 一种散货船货舱内脚手架结构 | |
CN208036543U (zh) | 一种船舶机舱可拆式活动地板系统 | |
CN105292378A (zh) | 液化气船单元管架无余量对接的建造方法 | |
CN202225997U (zh) | 一种挂舵臂 | |
CN110053735B (zh) | 一种用于大型lng船舭部压载舱区域的脚手架搭设方法 | |
KR101706207B1 (ko) | 선박 또는 해양 플랜트용 의장 설치 방법 | |
CN101591917A (zh) | 钢吊箱施工工艺 | |
CN103523173B (zh) | 一种滚轮闸刀掣链器的制造安装工艺 | |
CN116290809A (zh) | 超高层管井立管模块化施工方法 | |
CN104259808B (zh) | 海上井架拼装及整吊上船方法 | |
CN101693389A (zh) | 预铸混凝土模板方法 | |
CN101571003B (zh) | 大型球罐施工平台搭建装置及其搭建方法 | |
CN113404304A (zh) | 超大型fpso管廊模块建造的工艺 | |
CN201391222Y (zh) | 一种用于船舶分段搁置建造中的简易爬梯 | |
CN114590368B (zh) | 一种双燃料船舶燃气设备间的布置方法 | |
CN205804601U (zh) | 可重复利用的活动屋架与立柱的连接节点 | |
CN102152046A (zh) | 船用柴油机上轴承进油管制作的辅助装置及制作方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20090617 Termination date: 20170406 |
|