CH434335A - Method of construction of a passage under track and installation for the implementation of this method - Google Patents

Method of construction of a passage under track and installation for the implementation of this method

Info

Publication number
CH434335A
CH434335A CH508066A CH508066A CH434335A CH 434335 A CH434335 A CH 434335A CH 508066 A CH508066 A CH 508066A CH 508066 A CH508066 A CH 508066A CH 434335 A CH434335 A CH 434335A
Authority
CH
Switzerland
Prior art keywords
abutments
abutment
track
slab
passage
Prior art date
Application number
CH508066A
Other languages
French (fr)
Inventor
Reymond Fritz
Original Assignee
Reymond Fritz
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Reymond Fritz filed Critical Reymond Fritz
Priority to CH508066A priority Critical patent/CH434335A/en
Publication of CH434335A publication Critical patent/CH434335A/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/005Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries by forcing prefabricated elements through the ground, e.g. by pushing lining from an access pit

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Bridges Or Land Bridges (AREA)

Description

  

  . Procédé de     construction    d'un passage sous voie et     installation    pour la mise en     aeuvre    de ce procédé    La présente invention a pour objet un procédé de       construction    d'un passage sous voie comportant au  moins deux culées sur     lesquelles    repose au moins une       dalle    en béton     armé,        précontraint    ou non, dans lequel on  pose préalablement un faux pont pour supporter tempo  rairement la voie.  



  L'invention comprend également une     installation     pour la mise en oeuvre du procédé     ci-dessus.     



  Dans les     ouvrages    de     génie    civil de ce genre, le pro  cédé traditionnel consiste à établir tout d'abord un faux  pont pour     soutenir    la ou les voies ferrées avant d'entre  prendre la construction des culées destinées à supporter  la dalle     définitive    de     (ouvrage.    On creuse ensuite les  tranchées dans lesquelles seront construites les     culées,     ce qui nécessite l'étayage des parois de chaque tranchée.

    Cet étayage est rendu d'autant plus compliqué qu'il doit  permettre     l'établissement    du coffrage de la culée depuis  la semelle qui a     approximativement    la largeur de la  tranchée jusqu'à sommet au fur et à mesure de son érec  tion.  



  Une fois les culées     terminées,    on construit ou on ripe  la ou les     dalles    s'appuyant sur ces culées et sur     lesquelles     reposeront les voies ferrées après     élimination    du faux  pont.  



  Ce mode .d'exécution des travaux est long et     coûteux.     La présente invention vise à remédier à ces inconvé  nients et le procédé     qui    en fait l'objet se     distingue    par le  fait qu'on établit d'un côté de la voie à un niveau infé  rieur, des appuis     provisoires    orientés dans la direction  déterminée des culées sur une     semelle    s'étendent au pied  de ces appuis pour permettre la construction en au moins  un élément de chaque culée avec un     front    d'attaque pré  sentant des redans lui donnant     l'inclinaison    générale cor  respondant à l'angle de glissement du terrain,

   ces redans  étant munis d'un blindage formé de couteaux destinés à  s'enfoncer dans le     terrain,    on déplace la     culée    formée d'au  moins un élément dans le terrain au moyen de     vérins    s'ap  puyant contre l'appui provisoire correspondant, et on  élimine le matériau de déblai par-dessus ou     par    l'inté  rieur de la     construction,

      on     construit    au     moins    une     dalle       en béton armé sur des     fausses        culées    et on ripe-     cette          dalle        sur    les     culées    après     avoir    dégagé les matériaux  restant entre le niveau     supérieur    des     culées    et les faux  pont.  



  L'installation pour la mise en.     oeuvre    du procédé  selon l'invention comprend une batterie de vérins com  mandés à     partir    d'un poste central, ces vérins venant       s'appuyer    contre la face frontale de l'appui     provisoire     correspondant, par     l'intermédiaire    de moyens de calage       et        .contre    la face arrière de la     culée    construite sur place  en: au moins un élément, et     des    moyens. pour     déplacer    la  dalle en béton armé et l'amener sur les     culées.     



  Le dessin annexé illustre, à titre d'exemple, une       forme    d'exécution -du procédé faisant l'objet de la pré  sente invention et montre schématiquement un exemple  de     l'ins.tallation        pour    la     mise    en     oeuvre    de ce procédé.  



  La     ù-.    1 est une vue     schématique    en coupe     montrant     les     travaux    en cours.     d'exécution..     



  La     fg.    2 est une coupe par la     ligne    2-2 de la     fig.    1.  La     fig.    3 est une vue en plan     @de    la     fig.    1.  



  La     fig.    4 est une coupe parla ligne 4-4 de la     fig.    3.  La     fig.    5 est une coupe     partielle    par la ligne 5-5 de       l'a-fig.    4.  



  Le procédé     illustré    sert à la     construction        d'un    pas  sage sous voie     comportant    deux     culées        sur        lesquelles     repose une     dalle    en béton armé. Dans ce procédé, on  pose préalablement par mesure de sécurité un faux pont  1     pour        supporter        -temporairement    la ou les voies repré  sentées en 2 et 3.

   On établit d'un côté     des.    voies en con  trebas, deux appuis provisoires 4 et 5 dont la base pré  sente des décrochements     destinés.    à assurer un ancrage  efficace de ces appuis     dans    le terrain. Une semelle 6 se  prolonge en     avant    de chaque appui provisoire 4, 5,  c'est-à-dire à partir de l'extrémité de celui-ci regardant  les voies. Cette semelle 6 se trouve au-dessous du niveau  de la chaussée du passage sous voie.  



  On     construit    sur la     semelle    6 un élément de culée 7  évidé comme représenté à la     fig.    4. Cet élément     çom-          porte    deux     flancs        inclinés.    8 et 9 se terminant à la- base  par une semelle 10 et au     sommet        par    une partie épaisse      ou membrure supérieure 11     destinée    à recevoir la dalle  D et présentant un canal 12 en forme de U.

   Le     flanc    8       est    plus     incliné    que le     flanc    9 et     sert    à retenir     le        terrain..          Il    est     terminé    à sa     partie        supérieure    par un' muret 13       vertical    prolongeant un des     côtés    du canal 12.

   Le     flanc    9  de l'élément 7 forme le mur latéral du passage sous voie  une fois l'ouvrage     terminé,    le trottoir 14 s'étendant le  long de     ce    mur comme représenté à la     fig.    4.  



  Des     cloisons    m servent à renforcer intérieurement  l'élément de     culée    7 à sa base, ces     cloisons        formant    des  canaux     longitudinaux    qui peuvent être utilisés par la  suite par exemple pour     l'écoulement    des eaux     usées    ou  pour le passage de conduites     électriques    ou autres.

   Des       évidements    15 sont ménagés tous les mètres dans la  cloison     horizontale    et au-dessus de     celle-ci    sont formés  des sommiers 16     formant    des entretoises espacées     régu-          lièrement.     



  L'élément de culée 7 présente un front d'attaque  avec deux     redans    17, 18 donnant à ce front d'attaque       l'inclinaison    générale correspondant à     l'angle    a de glis  sement du terrain. Ces redans sont munis d'un     blindage     frontal 17' et 18' formant ,des couteaux verticaux vus de  profil mais qui ont l'inclinaison des     parois    de l'élément  de culée 7 vus en bout.  



  Les dimensions des     éléments.    de culée 7 sont, par  exemple, de 5     .m    de largeur à la base sur 10 m de lon  gueur et 6 m de hauteur,     c'est-à-dire    jusqu'au sommet du  muret 11. Les redans 17 et 18 ont dans     ce    cas 1 m de  décrochement. La partie     inférieure    du front d'attaque est  également munie d'un     blindage    19. Ces dimensions sont  telles que des hommes peuvent se     tenir    à l'intérieur de  l'élément 7 pour y travailler comme il sera décrit plus       loin.     



  Une fois l'élément de culée 7 terminé, on le déplace       horizontalement        dans    le     terrain    au moyen de     vérins    20  s'appuyant     contre    l'appui     provisoire    4 correspondant,  c'est-à-dire celui se trouvant dans     l'alignement    de l'élé  ment 7.

   Les     vérins    20 sont     commandés    en synchronisme  à     partir    d'une station     centrale    prévue à cet effet et dont       l'utilisation    est     déja        connue    dans     d'autres        applications.     Au     fur    et à mesure de l'avancement de l'élément 7, le  terrain découpé par les     couteaux    17', 18' et 19 et creusé  par     les        hommes    se trouvant     dans    l'élément,

   est     éliminé     par l'intérieur de celui-ci à l'aide d'un transporteur à  ruban par exemple. Lorsque l'élément 7 a été amené  dans la position indiquée en trait mixte à la     fig.    1, on  construit sur la semelle 6 un second élément semblable  mais ne     présentant    pas -de front     d',attaque    à redans et on  le pousse     contre    le premier élément de façon à amener  sa face frontale     généralement    verticale, en     contact        jointif     avec la face arrière dudit premier élément.

   On cons  truira autant d'éléments de culée     qu'il    en faudra     pour     établir la culée     définitive.     



       Conjointement    à la     construction    sur place     des    élé  ments de culée, on prépare la     dalle    de     couverture    D en  béton armé sur les culées     provisoires    comme représenté  aux fi-. 1 et 2.

   Dans une variante, on pourrait pré  voir une charge de     ballast    sur les appuis     provisoires     pour améliorer     l'ancrage    de ces     appuis    et construire la       dalle    de béton armé sur le terrain naturel dans l'aligne  ment des appuis     provisoires.    La     ,dalle    D     est    ensuite ripée  à l'aide de vérins sur     les        -culées    après     .avoir    dégagé les  matériaux restant entre le niveau supérieur de ces culées  et le faux pont.

   On     utilise    à cet effet des fers profilés     liés     à l'arrière des     culées    formant un chemin de     glissement          rectiligne    dans     l'alignement    de fers de réception     disposés     sur les culées. La     surface    ide frottement .de     ces    fers est    enduite d'un     lubrifiant    spécial puis la     dalle    est posée sur  ces fers et ripée     dans    la position représentée à la     fig.    1  en trait     mixte.     



  On pourrait bien entendu riper la     dalle    de façon  connue au moyen de rouleaux.  



  Bien que dans le procédé décrit, chaque     culée    soit  formée ,de plusieurs éléments,     construits    successivement,  cette culée pourrait être construite     en    un seul     élément.     



  Le procédé décrit a l'avantage de réduire     considé-          rablement    la durée des travaux et de permettre .d'éviter  la mise hors service des voies     pendant    un temps pro  longé. D'autre part, la hauteur des voies     n'est    pas modi  fiée au cours des opérations du procédé .décrit, ce qui  permet la circulation des trains.  



  On pourrait bien entendu appliquer le procédé décrit  à tout autre passage     souterrain,    notamment à un passage  sous voie routière.



  . Method of construction of a passage under track and installation for the implementation of this method The present invention relates to a method of construction of a passage under track comprising at least two abutments on which rests at least one reinforced concrete slab. , prestressed or not, in which a false bridge is installed beforehand to temporarily support the track.



  The invention also comprises an installation for implementing the above method.



  In civil engineering works of this kind, the traditional process consists in first establishing a false bridge to support the railway track (s) before starting the construction of the abutments intended to support the final slab (work. The trenches in which the abutments will be built are then dug, which requires the shoring of the walls of each trench.

    This shoring is made all the more complicated as it must allow the establishment of the formwork of the abutment from the sole which has approximately the width of the trench to the top as it is erected.



  Once the abutments are completed, the slab (s) resting on these abutments and on which the railway tracks will rest after elimination of the false bridge is built or ripped.



  This method of carrying out the work is long and expensive. The present invention aims to remedy these drawbacks and the method which is the subject thereof is distinguished by the fact that one establishes on one side of the track at a lower level, provisional supports oriented in the determined direction of the abutments on a sole extend at the foot of these supports to allow the construction of at least one element of each abutment with a leading face having steps giving it the general inclination corresponding to the angle of the land slip ,

   these steps being provided with a shield formed by knives intended to sink into the ground, the abutment formed of at least one element is moved in the ground by means of jacks leaning against the corresponding provisional support, and the excavated material is removed from above or from inside the construction,

      at least one reinforced concrete slab is built on false abutments and this slab is ripped over the abutments after having cleared the materials remaining between the upper level of the abutments and the false bridges.



  The installation for the setting. Implementation of the method according to the invention comprises a battery of jacks controlled from a central station, these jacks coming to rest against the front face of the corresponding provisional support, by means of wedging means and against. the rear face of the abutment built on site in: at least one element, and means. to move the reinforced concrete slab and bring it to the abutments.



  The appended drawing illustrates, by way of example, an embodiment of the method forming the subject of the present invention and schematically shows an example of the installation for the implementation of this method.



  The ù-. 1 is a schematic sectional view showing the work in progress. execution ..



  The fg. 2 is a section taken along line 2-2 of FIG. 1. FIG. 3 is a plan view @de FIG. 1.



  Fig. 4 is a section through line 4-4 of FIG. 3. Fig. 5 is a partial section taken on line 5-5 of a-fig. 4.



  The illustrated process is used for the construction of a step under track comprising two abutments on which rests a reinforced concrete slab. In this process, a false bridge 1 is installed beforehand as a safety measure to temporarily support the path (s) shown in 2 and 3.

   We establish on one side of the. lanes below, two provisional supports 4 and 5, the base of which has intended setbacks. to ensure an effective anchoring of these supports in the ground. A sole 6 extends in front of each provisional support 4, 5, that is to say from the end of the latter looking at the tracks. This sole 6 is located below the level of the roadway of the passage under the track.



  A hollow abutment element 7 is built on the sole 6 as shown in FIG. 4. This element has two inclined sides. 8 and 9 ending at the base with a sole 10 and at the top with a thick part or upper chord 11 intended to receive the slab D and having a U-shaped channel 12.

   The side 8 is more inclined than the side 9 and serves to hold back the ground. It is terminated at its upper part by a vertical wall 13 extending one side of the channel 12.

   The side 9 of the element 7 forms the side wall of the passage under the track once the work is finished, the sidewalk 14 extending along this wall as shown in FIG. 4.



  Partitions m serve to internally reinforce the abutment element 7 at its base, these partitions forming longitudinal channels which can be used subsequently for example for the flow of waste water or for the passage of electrical or other conduits.

   Recesses 15 are made every meter in the horizontal partition and above the latter are formed springs 16 forming regularly spaced spacers.



  The abutment element 7 has a leading edge with two steps 17, 18 giving this leading edge the general inclination corresponding to the angle α of landslide. These steps are provided with a frontal armor 17 'and 18' forming vertical knives seen in profile but which have the inclination of the walls of the abutment element 7 seen at the end.



  The dimensions of the elements. of abutment 7 are, for example, 5 m wide at the base by 10 m long and 6 m high, that is to say up to the top of the wall 11. Steps 17 and 18 have in this case 1 m of step. The lower part of the attack front is also provided with armor 19. These dimensions are such that men can stand inside the element 7 to work there, as will be described later.



  Once the abutment element 7 is completed, it is moved horizontally in the ground by means of jacks 20 resting against the corresponding provisional support 4, that is to say that located in alignment with the item 7.

   The jacks 20 are controlled in synchronism from a central station provided for this purpose and the use of which is already known in other applications. As element 7 advances, the ground cut by knives 17 ', 18' and 19 and dug by men in the element,

   is removed from inside it using a tape conveyor for example. When the element 7 has been brought into the position indicated in phantom in FIG. 1, a second similar element is built on the sole 6 but does not have a stepped attack front and it is pushed against the first element so as to bring its generally vertical front face, in full contact with the rear face of said first element.

   As many abutment elements will be constructed as necessary to establish the final abutment.



       In conjunction with the on-site construction of the abutment elements, the reinforced concrete cover slab D is prepared on the temporary abutments as shown in fi-. 1 and 2.

   In a variant, a ballast load could be provided on the provisional supports to improve the anchoring of these supports and to build the reinforced concrete slab on the natural ground in line with the provisional supports. The, slab D is then ripped using jacks on the -culées after having cleared the materials remaining between the upper level of these abutments and the false bridge.

   For this purpose, profiled irons linked to the rear of the abutments forming a rectilinear sliding path are used in alignment with the receiving irons arranged on the abutments. The surface ide friction .de these irons is coated with a special lubricant then the slab is placed on these irons and ripped in the position shown in fig. 1 in phantom.



  The slab could of course be ripped in a known manner by means of rollers.



  Although in the method described, each abutment is formed of several elements, built successively, this abutment could be built in a single element.



  The method described has the advantage of considerably reducing the duration of the work and of making it possible to prevent the tracks from being taken out of service for a long time. On the other hand, the height of the tracks is not changed during the operations of the described method, which allows the movement of trains.



  The method described could of course be applied to any other underground passage, in particular to a passage under a roadway.

 

Claims (1)

REVENDICATIONS I. Procédé de construction d'un passage sous voie comportant au moins deux culées sur lesquelles -repose au moins une dalle en béton armé, dans lequel on pose préalablement un faux pont pour supporter temporaire ment la voie, CLAIMS I. A method of constructing a passage under a track comprising at least two abutments on which rests at least one reinforced concrete slab, in which a false bridge is first laid to temporarily support the track, caractérisé par le fait qu'on établit d'un côté .de la voie à un niveau inférieur des appuis provi soires orientés dans la direction déterminée des culées sur une semelle s'étendant au pied de ces appuis pour permettre la construction en au moins un élément de chaque culée avec un front d'attaque présentant des redans lui donnant l'inclinaison générale correspondant à l'angle de glissement .du terrain, ces redans étant munis d'un blindage formé de couteaux destinés à s'enfoncer dans le terrain, on déplace la culée formée d'au moins un élément dans le terrain au moyen de vérins s'ap puyant contre l'appui provisoire correspondant, characterized by the fact that one establishes on one side of the track at a lower level provisional supports oriented in the determined direction of the abutments on a sole extending at the foot of these supports to allow construction in at least one element of each abutment with an attack front having steps giving it the general inclination corresponding to the sliding angle of the land, these steps being provided with armor formed by knives intended to sink into the terrain, the abutment formed of at least one element is moved in the ground by means of jacks leaning against the corresponding provisional support, et on élimine le matériau de déblai par-dessus ou par l'inté rieur de la construction, on construit au moins une dalle en béton armé sur de fausses culées et on ripe cette dalle sur les culées après avoir dégagé les matériaux restant entre le niveau supérieur des culées et le faux pont. II. and the excavated material is removed from above or from inside the construction, at least one reinforced concrete slab is constructed on false abutments and this slab is ripped on the abutments after having cleared the materials remaining between the level upper abutments and false bridge. II. Installation pour la mise en oeuvre du procédé selon la revendication I, caractérisée par le fait qu'elle comprend une batterie de vérins commandés à partir d'un poste central, ces vérins venant s'appuyer contre la face frontale de l'appui provisoire correspondant par l'intermédiaire de moyens de calage et contre la face arrière de la culée construite sur place en au moins un élément, et des moyens pour déplacer la dalle en béton armé et l'amener sur les culées. III. Passage sous voie obtenu par le procédé selon la revendication I. Installation for implementing the method according to Claim I, characterized in that it comprises a battery of jacks controlled from a central station, these jacks coming to rest against the front face of the corresponding temporary support by means of wedging means and against the rear face of the abutment built on site in at least one element, and means for moving the reinforced concrete slab and bringing it onto the abutments. III. Passage under track obtained by the process according to claim I. SOUS-REVENDICATIONS 1. Procédé selon la revendication I, caractérisé par le fait qu'on construit chaque culée en plusieurs élé ments, chaque élément étant formé ou amené successi vement sur la semelle et présentant une face verticale destinée à venir s'appuyer contre la face arrière corres pondante de l'élément précédent, le premier élément étant muni du front d'attaque. 2. SUB-CLAIMS 1. Method according to claim I, characterized in that each abutment is constructed in several elements, each element being formed or brought successively onto the sole and having a vertical face intended to come to rest against the base. corresponding rear face of the preceding element, the first element being provided with the leading edge. 2. Passage sous voie selon la revendication III, caractérisé par le fait qu'il comprend plusieurs éléments de culée évidés présentant chacun deux flancs inclinés destinés l'un à retenir le terrain et l'autre à former le mur intérieur latéral du passage terminé, ces deux flancs étant reliés à la base par une semelle et au sommet par une membrure recevant la dalle, des cloisons intérieures renforçant ledit élément à la base, ces cloisons formant ,des canaux longitudinaux. 3. Under-track passage according to Claim III, characterized in that it comprises several hollowed-out abutment elements each having two inclined sides, one intended to retain the ground and the other to form the lateral interior wall of the completed passage, these two sides being connected to the base by a sole and to the top by a frame receiving the slab, internal partitions reinforcing said element at the base, these partitions forming longitudinal channels. 3. Passage sous voie selon la revendication III et la sous-revendication 2, caractérisé par le fait que le flanc servant à retenir le terrain est plus incliné par rapport à la verticale que l'autre et se termine au sommet par un muret vertical. Underground passage according to claim III and sub-claim 2, characterized in that the side serving to retain the ground is more inclined relative to the vertical than the other and ends at the top with a vertical wall.
CH508066A 1966-04-06 1966-04-06 Method of construction of a passage under track and installation for the implementation of this method CH434335A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CH508066A CH434335A (en) 1966-04-06 1966-04-06 Method of construction of a passage under track and installation for the implementation of this method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CH508066A CH434335A (en) 1966-04-06 1966-04-06 Method of construction of a passage under track and installation for the implementation of this method

Publications (1)

Publication Number Publication Date
CH434335A true CH434335A (en) 1967-04-30

Family

ID=4287593

Family Applications (1)

Application Number Title Priority Date Filing Date
CH508066A CH434335A (en) 1966-04-06 1966-04-06 Method of construction of a passage under track and installation for the implementation of this method

Country Status (1)

Country Link
CH (1) CH434335A (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3833960A (en) * 1972-08-23 1974-09-10 W Herth Process for the construction of underpasses and an abutment for use therein
FR2574831A1 (en) * 1984-12-13 1986-06-20 Miomandre Jean Pierre Method eliminating earthworks and thereby embankment fills during the installation of prefabricated railway or road bridges
EP0192004A1 (en) * 1984-12-13 1986-08-27 Jean-Pierre Miomandre Process and apparatus for installing a structure such as a prefabricated bridge
FR2586045A2 (en) * 1985-08-07 1987-02-13 Miomandre Jean Pierre Method and device for installing a prefabricated bridge
FR2591275A2 (en) * 1986-05-09 1987-06-12 Beauthier Jean Marie Method for the construction of structures under railways in service and device for the implementation of this method
FR2591276A2 (en) * 1986-05-09 1987-06-12 Beauthier Jean Marie Method for the construction of structures under railways in operation and device for the implementation of this method
EP0245155A1 (en) * 1986-05-09 1987-11-11 Jean Marie Beauthier Process for carrying out works under railway tracks in operation
FR2628144A2 (en) * 1986-05-09 1989-09-08 Beauthier Jean Marie Construction method below railway tracks - uses small auxiliary plates below rails to support track during construction

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3833960A (en) * 1972-08-23 1974-09-10 W Herth Process for the construction of underpasses and an abutment for use therein
FR2574831A1 (en) * 1984-12-13 1986-06-20 Miomandre Jean Pierre Method eliminating earthworks and thereby embankment fills during the installation of prefabricated railway or road bridges
EP0192004A1 (en) * 1984-12-13 1986-08-27 Jean-Pierre Miomandre Process and apparatus for installing a structure such as a prefabricated bridge
FR2586045A2 (en) * 1985-08-07 1987-02-13 Miomandre Jean Pierre Method and device for installing a prefabricated bridge
FR2591275A2 (en) * 1986-05-09 1987-06-12 Beauthier Jean Marie Method for the construction of structures under railways in service and device for the implementation of this method
FR2591276A2 (en) * 1986-05-09 1987-06-12 Beauthier Jean Marie Method for the construction of structures under railways in operation and device for the implementation of this method
EP0245155A1 (en) * 1986-05-09 1987-11-11 Jean Marie Beauthier Process for carrying out works under railway tracks in operation
FR2628144A2 (en) * 1986-05-09 1989-09-08 Beauthier Jean Marie Construction method below railway tracks - uses small auxiliary plates below rails to support track during construction

Similar Documents

Publication Publication Date Title
CA1217349A (en) Engineering of reinforced concrete structures, such as tunnels, underpasses and the like, and precast concrete elements used in said engineering processes
EP0166656B1 (en) Prefabricated retaining elements for protecting, reinforcing and/or lining excavations, anchoring and connecting devices, and method for using these elements and devices
FR2487405A1 (en) WALL MODULE FOR THE CONSTRUCTION OF CONCRETE STRUCTURES AND METHOD FOR CONSTRUCTING A CONCRETE CAST CONCRETE STRUCTURE
WO1986000358A1 (en) Method and equipement for making a rigid slab enabling to carry a building
EP0295175B2 (en) Hollow structure with flat base plate
EP0065486B1 (en) A constant cross-sectional elongated piece of work and a method of constructing this piece of work
CH434335A (en) Method of construction of a passage under track and installation for the implementation of this method
FR2531733A1 (en) METHOD AND DEVICE FOR EXTRACTING A FORMWORK IN THE CONTEXT OF PRODUCING A MOLDED WALL IN THE GROUND
FR2523627A1 (en) METHOD FOR CONFORTING ARCHES OR SIMILAR CONSTRUCTIONS
EP0245155B1 (en) Process for carrying out works under railway tracks in operation
FR2749329A1 (en) Temporary or permanent safety barrier for roads and motorways
FR2620153A1 (en) CONSTRUCTION PANEL, ESPECIALLY CLADDING PANEL, WITH INTEGRATED THERMAL INSULATION
EP0197021B1 (en) Method for driving a tunnel
FR2642109A1 (en) Elongate hollow structure and method for manufacturing it
FR2825728A1 (en) Method ensuring continuity in highway separation walls in which interruptions are made comprises positioning end pieces in which truss frames are housed, pouring concrete and placing cover above interruption between end pieces
EP0242497B1 (en) Tunnel construction process
FR2672937A1 (en) UNDERGROUND TUBULAR STRUCTURE AND ITS MANUFACTURING METHOD.
BE1001360A3 (en) Deck semi-prefabricated.
FR2749331A1 (en) Prefabricated concrete frame forming underpass beneath roads or railways
FR2727447A1 (en) Construction of tunnel under embankment in soft soils or areas prone to flooding
FR2824851A1 (en) PREFABRICATED BRIDGE SUPPORT
WO1996000867A1 (en) Fluid circulation pipe
FR2488302A1 (en) SET OF CONSTRUCTION ELEMENTS FOR BUILDING RETAINING WALLS
FR2704582A1 (en) Protection and reinforcement system for the bottom of partitions in industrial buildings.
EP0004998A2 (en) Construction frame