CH431917A - Extendable mast installation - Google Patents

Extendable mast installation

Info

Publication number
CH431917A
CH431917A CH303566A CH303566A CH431917A CH 431917 A CH431917 A CH 431917A CH 303566 A CH303566 A CH 303566A CH 303566 A CH303566 A CH 303566A CH 431917 A CH431917 A CH 431917A
Authority
CH
Switzerland
Prior art keywords
mast
elements
tubular
plate
jack
Prior art date
Application number
CH303566A
Other languages
French (fr)
Inventor
Rubeli Jean
Original Assignee
Rubeli Jean
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Rubeli Jean filed Critical Rubeli Jean
Priority to CH303566A priority Critical patent/CH431917A/en
Publication of CH431917A publication Critical patent/CH431917A/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • E04H12/18Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures movable or with movable sections, e.g. rotatable or telescopic
    • E04H12/185Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures movable or with movable sections, e.g. rotatable or telescopic with identical elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Description

  

      Installation   <B>de mât extensible</B>    La présente     invention    a pour objet une     installation     de mât extensible, notamment pour supporter des pro  jecteurs d'éclairage sur un     terrain    de sport, comportant  une     série    d'éléments tubulaires s'emboîtant les uns dans  les autres, un magasin pour ces éléments et des     moyens     pour extraire les éléments du     magasin,    les emboîter les  uns     dans    les autres et     les    déplacer vers le haut pour       former    le mât.  



  Dans les     installations    connues de     ce    type, le déve  loppement ou l'extension du mât     nécessite    un     appareil-          lage        spécial    pour le déroulement synchronisé des     câbles     de     haubanage,        ce    qui complique et rend coûteuse     l'ins-          tallation.    Jusqu'ici il n'a     pas    été proposé de solution  valable pour réaliser des mâts     extensibles    de hauteur       importante,    par exemple 15 mètres et plus,

       sans        utiliser     de haubans.  



  La présente invention donne une solution à ce pro  blème et     l'installation    qui en fait l'objet se distingue par  le fait qu'elle comprend un support mobile sur     lequel     sont     disposés        verticalement        côte    à côte les éléments tubu  laires, un     vérin    pour soulever un     plateau        disposé    en  un     point    du parcours du support mobile,

   ce     plateau     étant     destiné    à porter     successivement    les éléments     tubu-          laires    à partir du support, un     mécanisme    actionné par  le vérin pour     faire        avancer        ce    support chaque fois que  le     vérin    est revenu     dans    sa position de départ après avoir       soulevé    ledit     plateau    portant un élément, un dispositif  de     retenue    de l'élément dans sa position soulevée,

   ce       dispositif    agissant sur des bossages de l'élément jusqu'à       ce    que l'élément suivant soit emboîté et     soulève    l'élément       précédent    hors de     prise    avec le     dispositif    de retenue et       inversement    lors de     la        descente    des     éléments,        des        moyens     de guidage des     éléments    tubulaires,

   et un     extracteur     commandé     par    le plateau du     vérin    et coopérant avec  un     bossage    de l'élément     tubulaire    pour déboîter cet  élément du     précédent    lors de     l'abaissement    du mât.    Le     dessin    annexé représente, à titre d'exemple, une  forme d'exécution     ainsi    qu'une variante de     l'installation     faisant l'objet de la présente invention.  



  La     fig.    1 est une vue en élévation, partiellement  en coupe, de     cette        installation    avec le mât développé.  La     fig.    2 est une vue     semblable    à la     fig.    1 dans la       position        escamotée    du mât.  



  La     fig.    3 est une vue à plus grande échelle d'un       détail    de la     fig.    2.  



  La     fig.    4     esit    une vue en plan de     la        fig.    3.  



  La     fig.    5 est une vue en élévation partiellement en  coupe et à plus grande     échelle    d'un élément     tubulaire     du mât.  



  La     fig.    6 est une vue en coupe de l'installation en  cours d'érection du mât.  



  La     fig.    7     est    une vue en élévation latérale d'un  détail à plus grande échelle de     la.        fig.    6.  



  La     fig.    8     est    une vue en plan de la     fig.    7.  



  Les     fig.    9 et 10 sont des vues en élévation et en       plan    à plus grande échelle d'un autre     détail    de     la        fig.    6.  La     fig.    11 est une vue de profil .d'un     détail    de la       fig.    9.  



  Les     fig.    12 et 13 sont des vues en élévation sem  blables aux     fig.    1 et 2     mais    d'une     variante.     



  Les     fig.    14 et 15 sont     ries    vues en élévation et en  plan à plus grande     échelle    d'un détail de cette variante.       L'installation    de mât     extensible    représentée aux     fig.     



  1 et 2 est utilisée     notamment    pour supporter des pro  jecteurs     d'éclairage    sur un terrain de sport ou tout  autre endroit où il     est    désirable de pouvoir     escamoter     le mât dans le sol.

   A cet     effet,        l'installation    est montée  dans une fosse 1 creusée dans le sol dont le     niveau    est       indiqué    en 2.     Elle    comprend une série     d'éléments        tubu-          laires    3 s'emboîtant les     uns    dans les autres pour former      le mât comme représenté à la     fig.    1,

   l'élément 3' du  sommet du mât     étant        solidaire    d'un     support    de lampe  4     formant    en même     temps    un couvercle     s'adaptant    dans  l'ouverture de la fosse 1 dans la position escamotée de  la     fig.    2. Chaque élément 3 comporte des connexions  électriques (non représentées) destinées à venir en prise  avec les connexions de l'élément suivant ou précédent  pour l'amenée du courant électrique au sommet du mât.  



  L'extrémité inférieure de l'élément 3     (fig.    5) est  usinée conique     intérieurement    en 5 pour     faciliter    l'em  boîtement avec     l'élément        suivant.    Deux bossages 6 dia  métralement opposés sont soudés sur l'élément 3 ou  venus de fabrication avec celui-ci à proximité de son       extrémité        inférieure,    c'est-à-dire environ au tiers de sa  hauteur effective désignée en H.

   L'extrémité supérieure  d'emboîtement de l'élément 3 présente une partie  conique 7 pour faciliter l'emboîtement     avec    l'élément  précédent, une portée     cylindrique    8 usinée avec préci  sion pour venir s'ajuster dans l'élément     précédent,    une  partie 9 de diamètre réduit et une seconde portée 10       également    usinée avec précision pour venir s'ajuster dans  l'élément précédent, 11 désignant un épaulement sur  lequel vient reposer ledit élément précédent. Cette extré  mité d'emboîtement h s'étend sur une hauteur h égale  à environ     lia    de     la    hauteur effective H de l'élément.

    Cet élément est de     préférence    en acier coulé mais     peut     être en aluminium ou autre métal ou     alliage.     



  Les éléments 3 sont disposés     verticalement    côte à  côte sur     un    support     mobile    12     constitué    par deux     bandes     cylindriques concentriques     reliées    entre elles par des       entretoises    13 et montées sur des galets 14 portés par  des axes radiaux 15 supportés par deux     anneaux    concen  triques 16 et 17     fixés    au fond de la fosse 1.  



  Des     saillies    de centrage 12' sont     fixées    à     intervalles          réguliers    sur le support 12 et servent à     contrer    les       éléments        tubulaires    3 en les espaçant     également    sur ledit       support.     



  Un vérin     hydraulique    18 muni d'un     plateau    19 est       agencé    de telle     manière    au fond de la fosse 1 que le       plateau    19 soit     placé    en un     point    du parcours circulaire  du support 12 pour     porter        successivement    les éléments       tubulaires    3 à     partir    de ce support 12 comme il sera  décrit en     détail    plus loin.  



  Pour faire avancer le     support    12,     l'installation    com  porte un     mécanisme    actionné     pair    le     vérin    18 et com  prenant deux crochets 20 et 21,     pivotant    sur des axes  20' et 21'     respectivement    et venant s'accrocher sélecti  vement à des chevilles 22     solidaires    du support 12 sur  lequel elles sont également réparties.     Les    axes d'articu  lation 20', 21' sont reliés à des tiges     coulissantes    23,  24 par     l'intermédiaire    de     tringles    25, 26.

   Ces tiges     cou-          lissantes    23 et 24 portent des bras 27, 28 respectivement       destinés    à venir     sélectivement    en     prise        avec    le     plateau     19 selon qu'un élément 3 doit être     extrait    du support 12  (extension du mât) ou au     contraire    ramené sur celui-ci       (escamotage    du mât). La sélection est opérée à     partir     d'un levier inverseur 29 venant en prise avec un     élément     3 se trouvant au droit du     plateau    19.

   Ce levier 29 agit  sur les tiges     coulissantes    23, 24 par une     tringlerie    vue  en plan à     la        fig.    8 et une barre d'appui 30, 30'     fixée     sur chacune     des    tiges 23, 24 présente une     extrémité     31     respectivement    32     coopérant        avec    les     crochets    20, 21       respectivement    pour les soulever ou les libérer sélec  tivement.

           Lorsqu'un    élément 3 est sur le plateau 19     (fig.    6),       il    s'étend verticalement jusqu'à un châssis inférieur 33  portant des     galets    34 de guidage     disposés    autour de et  en contact avec l'élément     précédent    représenté en     trait          mixte.    Le châssis 33 porte un     dispositif    de retenue de  l'élément 3 dans sa position soulevée (non représentée)       correspondant    à la course maximum du     vérin    18,

       c'est-          à-dire    lorsque le     plateau    19     arrive    adjacent aux galets  34. Ce     dispositif    de retenue     comprend    deux cliquets 35  diamétralement opposés destinés à retenir l'élément 3  en. venant se placer sous les bossages 6     (fig.    9). Chaque       cliquet    35 porte une     cheville    36 destinée à être actionnée  par un levier 37 pour     écarter    les cliquets 35 du passage  des bossages 6 lorsqu'un élément 3 doit redescendre.

   A  cet effet, le levier 37 est commandé par un mécanisme  de déclenchement comportant un organe     d'accrochage     38 articulé sur une tige verticale 39     coulissant    dans un  tube 40 et     sollicité    par des ressorts de traction 41 soit       dans    une position     inopérante    comme représenté à la       fig.    11, c'est-à-dire     rabattu    à l'extérieur du tube 40,

   soit  dans une position     verticale    dans     .laquelle    la tige 39 com  prime un ressort 42 disposé dans le tube 40 entre     la          tige    39 et un axe 43     solidaire    du levier 37. La     tige    39  porte un ergot 44 destiné à coopérer avec le plateau 19  du vérin.

      L'installation décrite comprend en     outre    un extrac  teur 45     (fig.    6)     commandé    par le plateau 19 du vérin  et coopérant avec     un    des bossages 6 de l'élément 3 pour  déboîter cet élément du     précédent    lors de     l'abaissement     du mât.     Cet        extracteur    comprend une     rampe        fixe    46  présentant un tronçon     vertical    et deux tronçons 46' et  46"     inclinés    en s'écartant de l'axe     vertical    du vérin.

   Un  équipage mobile 47 est monté sur la rampe 46 et est  muni d'un doigt inférieur 48 destiné à venir en prise  avec le plateau 19 lors de la     descente    et un doigt supé  rieur 49 destiné à venir en prise avec un des bossages  6 de l'élément 3 pour exercer sur lui une traction vers  le     bas    et le déboîter de l'élément     supérieur.    L'équipage  mobile 47 est retenu sur la rampe 46 par des galets 50  et 51 roulant sur le côté intérieur de     cette    rampe.

   Le  galet 51 est maintenu     élastiquement    par un     ressort    52  accroché à l'axe du doigt 49 pour lui permettre de suivre  le tronçon     incliné    53 à l'intérieur de     la.    rampe 46.  



  Un châssis supérieur 54 est monté au niveau du sol  2 et porte une seconde série de galets 55     pour    le guidage  des éléments tubulaires     sortant    de la fosse 1.  



  Le fonctionnement de     l'installation    décrite est le       suivant     Supposons que le mât doit être dressé. Les éléments  3 sont tous sur le     support    12     comme    représenté aux       fig.    3 et 4. Un de     ces        éléments    se     trouve    juste     au-dessus     du plateau 19 du vérin 18 et le levier 29 s'appuie contre  cet élément.

      Le vérin fait monter le     plateau    19 portant l'élément  3 dont le bossage 6 de gauche     (fig.    6) vient en prise       avec    le doigt 49 de     l'extracteur    et le déplace     vers    le haut  avec l'équipage mobile 47.

   Arrivé sur la     rampe        inclinée     46', -le doigt 49     s'écarte    du bossage 6 et l'élément 3  continue de monter jusqu'à ce qu'il arrive dans la posi  tion représentée à la     fig.    9.     Dans    cette position, les       cliquets    35 retiennent     l'élément    3 par ses bossages 6  et le plateau 19 est redescendu.

   Arrivé dans     le    support  12, il actionne le     bras    28 se trouvant sur sa trajectoire,  ce qui a pour effet de tirer le crochet 21 accroché à une      cheville 22 et dégagé de la came 32 (par le     coulissement     de la tige 24) vers la gauche à la     fig.    7 en entraînant  avec lui le support 12.

   La course du crochet 21 est  limitée et pour     compléter    le     déplacement    du support 12       indépendamment    du mécanisme d'avancement décrit  (29-32), on prévoit la disposition suivante  Le support 12 est muni à l'intérieur d'une     rampe     ondulée 56     contre    laquelle vient s'appuyer un galet 57       soumis    à l'action d'un ressort 58. Lorsque le support  12 tourne d'un cran, il amène le galet 57 sur le sommet  d'une ondulation de la rampe 56 contre l'action du res  sort 58. La poussée du galet a pour effet de faire avan  cer le support 12 jusqu'à     ce    que ledit galet 57 se trouve  de nouveau dans un creux.

   L'élément tubulaire 3 suivant  peut ainsi être amené au-dessus du plateau 19 prêt à  être soulevé par ce dernier pour être emboîté dans l'élé  ment     précédent.    Le vérin soulève alors les deux éléments  emboîtés jusqu'à ce que l'élément inférieur s'accroche  par ses bossages 6 aux     cliquets    35 et ainsi de suite jus  qu'au dernier     élément    du support 12.  



  Pour descendre le mât, le vérin soulève le plateau  19     (fig.    9)     avec    l'élément inférieur du mât jusqu'à ce  que ce plateau vienne en     prise        avec    l'ergot 44 de la  tige 39 du     mécanisme    de déclenchement. Cet ergot 44  fait pivoter l'organe     d'accrochage    38 contre l'action des  ressorts 41 jusqu'à ce qu'il se mette dans le prolongement  de la tige 39. Les ressorts 41 tirent alors vers le haut  l'organe d'accrochage 38 avec     la    tige 39 qui comprime  le     ressort    42 dans le tube 40.

   L'axe 43 est soulevé par  le ressort 42, amenant ainsi le levier 37 dans la posi  tion en     mixte    de la     fig.    9. Dans     cette    position, le levier  37 maintient écartés les     cliquets    35 par     l'intermédiaire     des     chevilles    36. L'élément     inférieur    3 peut descendre,  ses bossages 6 étant     libérés    des     cliquets    35.

   Le plateau  19     redescend    donc et vient en prise avec l'organe  d'accrochage 38 qu'il     abaisse    et amène de nouveau dans  sa position     représentée    à la     fig.    11. Pendant     l'abaisse-          ment    de l'organe 38, le levier 37 revient dans sa posi  tion en trait plein de même que les cliquets 35 qui sont  alors prêts à retenir l'élément 3 suivant.  



  En continuant à descendre, le     plateau    19 vient accro  cher le doigt 48 de l'extracteur et ramène celui-ci dans  la position de la     fig.    6. Le doigt 49 vient alors en prise  avec le bossage 6 de gauche de l'élément 3 inférieur  et en continuant à     descendre    le     plateau    19 entraîne       l'extracteur    vers le bas jusqu'à ce que cet élément se  déboîte de celui qui est retenu par les cliquets 35. Le  plateau 19 arrive ainsi dans le support 12 avec l'élément  3 libre.

   Le levier 29 est     déplacé    en     venant    sur la paroi  extérieure de     cet    élément,     il    amène le bras 27 dans     la     trajectoire du     plateau    19 et abaisse le crochet 20 au  moyen de la     came    3.

   En     continuant    à :descendre, le pla  teau 19     fait    basculer le bras 27 qui     actionne    le crochet  20     lequel,    en     prise    avec une     cheville    22,     déplace    le sup  port 12 dans le sens de     la    flèche B et le cycle recom  mence, jusqu'au dernier élément du mât.  



  L'installation décrite permet de développer des mâts       jusqu'à    environ 15 m de hauteur.  



  De bons résultats ont été obtenus en     utilisant    des  éléments     tubulaires    tels que     décrits    et présentant     une     section d'emboîtement dont le diamètre est la hauteur       dans    le rapport de     i/2.    Cet emboîtement est suffi  sant pour     empêcher    un déboîtement qui serait dû à une  force     résultante    verticale lors d'une poussée latérale sur  l'élément supérieur.

      La variante de     l'installation    représentée aux     figures     12 à 15     permet    de     réaliser    des mâts de 30 à 40 m de  hauteur. Dans     cette    variante, les éléments tubulaires 3a  sont légèrement coniques de sorte que     la    partie supé  rieure du mât est plus légère. A part cette     conicité,    les  éléments sont     semblables    à ceux de la forme d'exécution       précédente    et     seuls    les moyens de guidage de ces élé  ments diffèrent de     ceux        décrits    plus haut.  



  La     fig.    12 est semblable à     la.        fig.    1 et montre le mât  conique en position dressée alors qu'à la     fig.    13 le mât  est     escamoté    dans la fosse 1 et les éléments 3a sont  tous sur le     support        rotatif    12.  



  Les     moyens    de guidage représentés aux     fig.    14 et  15 comprennent deux séries de     galets    59 montés de  façon     déplaçable    sur un châssis     inférieur    60 et respec  tivement un châssis supérieur 61. Ces galets 59 sont       portés    par des     consoles    62     pivotant        autour        d'axes,    63  solidaires du châssis 60 respectivement 61.

   Derrière cha  que galet est montée une     poulie        horizontale    64 tournant  autour d'un axe     vertical    fixé entre deux flasques     soli-          daires    de     la,    console 62     correspondante.    Un câble 65  ancré à une extrémité en un point fixe 66 de l'instal  lation passe sur ces     poulies    64 et est fixé à son autre       extrémité    à un     vérin    67.  



  Le câble 65 est toujours sous tension de sorte que  les galets 59 sont     maintenus    appliqués contre les élé  ments     tubulaires    3 indépendamment de leur diamètre.  



  Cette solution de guidage des éléments du mât     peut          également    être appliquée au mât     cylindrique    des     fig.    1  à 11. Au lieu de galets 34, 55 ou 59, on pourrait uti  liser des patins en     matière    plastique ou autre venant  s'appliquer     contre    les     éléments    tubulaires.  



       L'installation    décrite présente l'avantage     important     de     permettre    l'érection de     mâts    de grande     hauteur    sans  nécessiter de câbles de haubanage. D'autre part, le méca  nisme d'avancement et de mise en     place    des éléments       tubulaires    est particulièrement simple puisqu'il ne pré  voit pas de moteur d'entraînement et qu'un seul vérin  suffit     pour    commander ce     mécanisme.  



      <B> Extensible mast installation </B> The present invention relates to an extendable mast installation, in particular for supporting lighting projectors on a sports field, comprising a series of tubular elements fitting together. in the others, a store for these elements and means for extracting the elements from the store, fitting them into each other and moving them upwards to form the mast.



  In known installations of this type, the development or extension of the mast requires special equipment for the synchronized unwinding of the stay cables, which complicates and makes the installation expensive. Until now, no valid solution has been proposed for making extendable masts of great height, for example 15 meters and more,

       without using shrouds.



  The present invention provides a solution to this problem and the installation which is the subject thereof is distinguished by the fact that it comprises a movable support on which the tubular elements are arranged vertically side by side, a jack for lifting a plate arranged at a point along the path of the mobile support,

   this plate being intended to successively carry the tubular elements from the support, a mechanism actuated by the jack to advance this support each time the jack has returned to its starting position after having raised said plate carrying an element, a element retaining device in its raised position,

   this device acting on bosses of the element until the next element is nested and lifts the previous element out of engagement with the retaining device and vice versa during the descent of the elements, means for guiding the elements tubular,

   and an extractor controlled by the cylinder plate and cooperating with a boss of the tubular element to disengage this element from the previous one when the mast is lowered. The appended drawing represents, by way of example, an embodiment as well as a variant of the installation which is the subject of the present invention.



  Fig. 1 is an elevational view, partially in section, of this installation with the mast developed. Fig. 2 is a view similar to FIG. 1 in the retracted position of the mast.



  Fig. 3 is a view on a larger scale of a detail of FIG. 2.



  Fig. 4 is a plan view of FIG. 3.



  Fig. 5 is an elevational view partially in section and on a larger scale of a tubular element of the mast.



  Fig. 6 is a sectional view of the installation during erection of the mast.



  Fig. 7 is a side elevational view of an enlarged detail of the. fig. 6.



  Fig. 8 is a plan view of FIG. 7.



  Figs. 9 and 10 are elevation and plan views on a larger scale of another detail of FIG. 6. FIG. 11 is a side view of a detail of FIG. 9.



  Figs. 12 and 13 are views in elevation similar to FIGS. 1 and 2 but of a variant.



  Figs. 14 and 15 are views in elevation and in plan on a larger scale of a detail of this variant. The extensible mast installation shown in fig.



  1 and 2 is used in particular to support lighting projectors on a sports field or any other place where it is desirable to be able to retract the mast into the ground.

   For this purpose, the installation is mounted in a pit 1 dug in the ground, the level of which is indicated at 2. It comprises a series of tubular elements 3 which fit into each other to form the mast as shown. in fig. 1,

   the element 3 'of the top of the mast being integral with a lamp support 4 forming at the same time a cover fitting into the opening of the pit 1 in the retracted position of FIG. 2. Each element 3 has electrical connections (not shown) intended to engage with the connections of the next or previous element for supplying electric current to the top of the mast.



  The lower end of element 3 (fig. 5) is tapered internally at 5 to facilitate fitting with the next element. Two diametrically opposed bosses 6 are welded to the element 3 or manufactured with the latter near its lower end, that is to say approximately one third of its effective height designated at H.

   The upper engagement end of the element 3 has a conical part 7 to facilitate engagement with the preceding element, a cylindrical bearing surface 8 machined with precision to fit into the preceding element, a part 9 of reduced diameter and a second bearing surface 10 also machined with precision to fit into the previous element, 11 designating a shoulder on which said previous element rests. This interlocking end h extends over a height h equal to approximately 11a of the effective height H of the element.

    This element is preferably made of cast steel but may be of aluminum or other metal or alloy.



  The elements 3 are arranged vertically side by side on a movable support 12 formed by two concentric cylindrical bands connected to each other by spacers 13 and mounted on rollers 14 carried by radial axes 15 supported by two concen tric rings 16 and 17 fixed to the bottom of pit 1.



  Centering projections 12 'are fixed at regular intervals on the support 12 and serve to counter the tubular elements 3 by also spacing them on said support.



  A hydraulic cylinder 18 provided with a plate 19 is arranged in such a way at the bottom of the pit 1 that the plate 19 is placed at a point of the circular path of the support 12 to successively carry the tubular elements 3 from this support 12 as it will be described in detail later.



  To advance the support 12, the installation comprises a mechanism actuated by the jack 18 and comprising two hooks 20 and 21, pivoting on axes 20 'and 21' respectively and coming to hook selectively to integral pins 22. of the support 12 on which they are equally distributed. The articulation axes 20 ', 21' are connected to sliding rods 23, 24 by means of rods 25, 26.

   These sliding rods 23 and 24 carry arms 27, 28 respectively intended to come into engagement selectively with the plate 19 depending on whether an element 3 is to be extracted from the support 12 (extension of the mast) or, on the contrary, brought back onto the latter. (retracting the mast). The selection is made from a reversing lever 29 engaging an element 3 located to the right of the plate 19.

   This lever 29 acts on the sliding rods 23, 24 by a linkage seen in plan in FIG. 8 and a support bar 30, 30 'fixed on each of the rods 23, 24 has an end 31 respectively 32 cooperating with the hooks 20, 21 respectively to lift them or release them selectively.

           When an element 3 is on the plate 19 (FIG. 6), it extends vertically to a lower frame 33 carrying guide rollers 34 arranged around and in contact with the preceding element shown in phantom. The frame 33 carries a device for retaining the element 3 in its raised position (not shown) corresponding to the maximum stroke of the cylinder 18,

       that is to say when the plate 19 arrives adjacent to the rollers 34. This retaining device comprises two diametrically opposed pawls 35 intended to retain the element 3 in. coming to be placed under the bosses 6 (fig. 9). Each pawl 35 carries a pin 36 intended to be actuated by a lever 37 to move the pawls 35 away from the passage of the bosses 6 when an element 3 has to come down.

   To this end, the lever 37 is controlled by a trigger mechanism comprising a hooking member 38 articulated on a vertical rod 39 sliding in a tube 40 and urged by tension springs 41 either in an inoperative position as shown in FIG. . 11, that is to say folded back outside the tube 40,

   either in a vertical position in .laquelle the rod 39 com prime a spring 42 disposed in the tube 40 between the rod 39 and a pin 43 integral with the lever 37. The rod 39 carries a lug 44 intended to cooperate with the plate 19 of the cylinder .

      The installation described further comprises an extractor 45 (FIG. 6) controlled by the plate 19 of the jack and cooperating with one of the bosses 6 of the element 3 to disengage this element from the preceding one when the mast is lowered. This extractor comprises a fixed ramp 46 having a vertical section and two sections 46 'and 46 "inclined away from the vertical axis of the jack.

   A mobile unit 47 is mounted on the ramp 46 and is provided with a lower finger 48 intended to engage with the plate 19 during the descent and an upper finger 49 intended to engage with one of the bosses 6 of the 'element 3 to exert a downward pull on it and disengage it from the upper element. The mobile unit 47 is retained on the ramp 46 by rollers 50 and 51 rolling on the inner side of this ramp.

   The roller 51 is resiliently held by a spring 52 hooked to the axis of the finger 49 to allow it to follow the inclined section 53 inside the. ramp 46.



  An upper frame 54 is mounted at ground level 2 and carries a second series of rollers 55 for guiding the tubular elements emerging from the pit 1.



  The operation of the installation described is as follows Suppose that the mast is to be raised. The elements 3 are all on the support 12 as shown in FIGS. 3 and 4. One of these elements is located just above the plate 19 of the cylinder 18 and the lever 29 rests against this element.

      The jack raises the plate 19 carrying the element 3, the left-hand boss 6 of which (FIG. 6) engages with the finger 49 of the extractor and moves it upwards with the movable assembly 47.

   Arrived on the inclined ramp 46 ', the finger 49 moves away from the boss 6 and the element 3 continues to rise until it arrives in the position shown in FIG. 9. In this position, the pawls 35 retain the element 3 by its bosses 6 and the plate 19 is lowered.

   Arrived in the support 12, it actuates the arm 28 located on its path, which has the effect of pulling the hook 21 hooked to a pin 22 and released from the cam 32 (by sliding the rod 24) to the left in fig. 7 by taking the support 12 with it.

   The travel of the hook 21 is limited and to complete the movement of the support 12 independently of the advancement mechanism described (29-32), the following arrangement is provided. The support 12 is provided inside with a corrugated ramp 56 against which comes to rest a roller 57 subjected to the action of a spring 58. When the support 12 rotates by a notch, it brings the roller 57 on the top of an undulation of the ramp 56 against the action of the res out 58. The thrust of the roller has the effect of advancing the support 12 until said roller 57 is again in a hollow.

   The following tubular element 3 can thus be brought above the plate 19 ready to be lifted by the latter to be fitted into the preceding element. The jack then lifts the two nested elements until the lower element hooks by its bosses 6 to the pawls 35 and so on until the last element of the support 12.



  To lower the mast, the jack raises the plate 19 (FIG. 9) with the lower element of the mast until this plate engages with the lug 44 of the rod 39 of the trigger mechanism. This lug 44 causes the hooking member 38 to pivot against the action of the springs 41 until it is placed in the extension of the rod 39. The springs 41 then pull the hooking member upwards. 38 with the rod 39 which compresses the spring 42 in the tube 40.

   The pin 43 is lifted by the spring 42, thus bringing the lever 37 into the mixed position of FIG. 9. In this position, the lever 37 keeps the pawls 35 apart through the pins 36. The lower element 3 can descend, its bosses 6 being released from the pawls 35.

   The plate 19 therefore descends and engages with the fastening member 38 which it lowers and brings again to its position shown in FIG. 11. During the lowering of the member 38, the lever 37 returns to its position in solid lines as do the pawls 35 which are then ready to retain the next member 3.



  By continuing to descend, the plate 19 hooks dearly to the finger 48 of the extractor and brings the latter back to the position of FIG. 6. The finger 49 then engages with the left boss 6 of the lower element 3 and by continuing to lower the plate 19 drives the extractor downwards until this element disengages from the one which is retained. by the pawls 35. The plate 19 thus arrives in the support 12 with the element 3 free.

   The lever 29 is moved by coming on the outer wall of this element, it brings the arm 27 in the path of the plate 19 and lowers the hook 20 by means of the cam 3.

   Continuing to: descend, the plate 19 swings the arm 27 which actuates the hook 20 which, in engagement with a pin 22, moves the support 12 in the direction of arrow B and the cycle starts again, until last element of the mast.



  The installation described makes it possible to develop masts up to about 15 m in height.



  Good results have been obtained using tubular elements as described and having a fitting section whose diameter is the height in the ratio of i / 2. This interlocking is sufficient to prevent dislocation which would be due to a resulting vertical force during a lateral thrust on the upper element.

      The variant of the installation shown in Figures 12 to 15 makes it possible to produce masts 30 to 40 m in height. In this variant, the tubular elements 3a are slightly conical so that the upper part of the mast is lighter. Apart from this taper, the elements are similar to those of the previous embodiment and only the guiding means of these elements differ from those described above.



  Fig. 12 is similar to. fig. 1 and shows the conical mast in the upright position while in fig. 13 the mast is retracted into the pit 1 and the elements 3a are all on the rotating support 12.



  The guide means shown in FIGS. 14 and 15 comprise two series of rollers 59 mounted in a movable manner on a lower frame 60 and respectively an upper frame 61. These rollers 59 are carried by consoles 62 pivoting about axes, 63 integral with the frame 60 respectively 61.

   Behind each roller is mounted a horizontal pulley 64 rotating about a vertical axis fixed between two solid flanges of the corresponding console 62. A cable 65 anchored at one end at a fixed point 66 of the installation passes over these pulleys 64 and is fixed at its other end to a jack 67.



  The cable 65 is always under tension so that the rollers 59 are kept pressed against the tubular elements 3 regardless of their diameter.



  This solution for guiding the elements of the mast can also be applied to the cylindrical mast of FIGS. 1 to 11. Instead of rollers 34, 55 or 59, one could use pads made of plastic or the like which are applied against the tubular elements.



       The installation described has the important advantage of allowing the erection of tall masts without requiring guy cables. On the other hand, the mechanism for advancing and positioning the tubular elements is particularly simple since it does not provide for a drive motor and only one cylinder is sufficient to control this mechanism.

 

Claims (1)

REVENDICATION Installation de mât extensible, notamment pour sup porter des projecteurs d'éclairage sur un terrain de sport, comportant une série d'éléments tubulaires s'emboîtant les uns dans les autres, un magasin pour ces éléments et des moyens pour extraire les éléments du magasin, les emboîter les uns dans les autres et les déplacer vers le haut pour former le mât, caractérisée par le fait qu'elle comprend un support mobile sur lequel sont disposés verticalement côte à côte les éléments tubulaires, CLAIM Installation of an extendable pole, in particular for supporting lighting projectors on a sports field, comprising a series of tubular elements fitting into each other, a store for these elements and means for extracting the elements from the store, fit them into each other and move them upwards to form the mast, characterized in that it comprises a movable support on which the tubular elements are arranged vertically side by side, un vérin pour soulever un plateau disposé en un point du parcours du support mobile, ce plateau étant destiné à porter successivement les éléments tubulaires à partir du support, un mécanisme actionné par le vérin pour faire avancer ce support chaque fois que le vérin est revenu dans sa. position de départ après avoir soulevé ledit plateau portant un élément, a jack for lifting a plate disposed at a point along the path of the mobile support, this plate being intended to successively carry the tubular elements from the support, a mechanism actuated by the jack to advance this support each time the jack has returned to her. starting position after lifting said plate carrying an element, un dispositif de retenue de l'élément dans sa position soulevée, ce dispositif agis sant sur des bossages de l'élément jusqu'à ce que l'élé ment suivant soit emboîté et soulève l'élément précé dent hors de prise avec le dispositif de retenue et inver sement lors de la descente des éléments, des moyens de guidage des éléments tubulaires, a device for retaining the element in its raised position, this device acting on bosses of the element until the next element is nested and lifts the preceding element out of engagement with the device. retained and inverted during the descent of the elements, the means for guiding the tubular elements, et un extracteur com mandé par le plateau du vérin et coopérant avec un bos sage de l'élément tubulaire pour déboîter cet élément du précédent lors de l'abaissement du mât. and an extractor controlled by the plate of the jack and cooperating with a bos sage of the tubular element to disengage this element from the previous one when the mast is lowered. SOUS-REVENDICATIONS 1. Installation selon la revendication, caractérisée par le fait que chaque élément comporte des connexions électriques destinées à venir en prise avec les connexions de l'élément suivant ou précédent pour l'amenée de cou- rant .électrique au sommet du mât. SUB-CLAIMS 1. Installation according to claim, characterized in that each element comprises electrical connections intended to engage with the connections of the next or previous element for the supply of electric current to the top of the mast. . 2. Installation selon la revendication, caractérisée par le fait que ledit mécanisme pour faire avancer le support des éléments tubulaires comprend deux crochets de transport destinés à venir alternativement en prise avec des saillies solidaires dudit support mobile pour faire tourner celui-ci <RTI 2. Installation according to claim, characterized in that said mechanism for advancing the support of the tubular elements comprises two transport hooks intended to come into engagement alternately with projections integral with said movable support to rotate the latter <RTI ID="0004.0033"> dans un sens ou dans l'autre, cha que crochet étant actionné par un doigt commandé par un levier changeur de direction pour venir ou non sur la trajectoire du plateau porté par le vérin en vue d'âtre basculé ou non par ce plateau selon qu'in porte ou non un élément tubulaire, ID = "0004.0033"> in one direction or the other, each hook being actuated by a finger controlled by a direction-changing lever to come or not on the path of the plate carried by the jack with a view to tilted hearth or not by this plate depending on whether or not it carries a tubular element, par le fait que l'extracteur com- prend une rampe fixe présentant un tronçon vertical et deux tronçons d'extrémités inclinés en s'éloignant de l'axe vertical du vérin, by the fact that the extractor comprises a fixed ramp having a vertical section and two end sections inclined away from the vertical axis of the jack, un équipage mobile monté sur ladite rampe et muni d'un doigt inférieur destiné à venir en prise avec le plateau du vérin lors de sa descente et un doigt supérieur destiné à venir en prise avec un bossage de l'élément tubulaire pour exercer sur celui-ci une traction vers a movable unit mounted on said ramp and provided with a lower finger intended to engage with the plate of the cylinder during its descent and an upper finger intended to engage with a boss of the tubular element to exert on it here a pull towards le bas et le déboîter de l'élément supé- rieur, ledit doigt supérieur mobile étant escamoté par l'une des rampes inclinées lors de la, montée d'un élé ment tubulaire en cours d'érection du mât, the bottom and disengage it from the upper element, said movable upper finger being retracted by one of the inclined ramps during the ascent of a tubular element during erection of the mast, et par le fait que le dispositif de retenue de l'élément tubulaire com- prend des cliquets diamétralement opposés, destinés à retenir un élément tubulaire en venant se placer sous les bossages de cet élément, and by the fact that the device for retaining the tubular element comprises diametrically opposed pawls intended to retain a tubular element by coming to be placed under the bosses of this element, ces cliquets étant écartés du passage des bossages par des leviers commandés par un mécanisme de déclenchement actionné par le vérin. 3. Installation selon la revendication, caractérisée par le fait que tous les éléments tubulaires sont cylin- driques et de même diamètre de façon à former un mât de section constante. 4. these pawls being spaced from the passage of the bosses by levers controlled by a trigger mechanism actuated by the jack. 3. Installation according to claim, characterized in that all the tubular elements are cylindrical and of the same diameter so as to form a mast of constant section. 4. Installation selon la revendication, caractérisée par le fait que la section transversale des éléments tubu laires va en diminuant des éléments inférieurs aux élé ments supérieurs de façon à former un mât de forme générale conique. Installation according to Claim, characterized in that the cross section of the tubular elements decreases from the lower elements to the upper elements so as to form a mast of generally conical shape. 5. Installation selon la revendication, caractérisée par le faut qu'elle comprend des moyens de guidage du mât s'adaptant à la. section transversale des éléments, 5. Installation according to claim, characterized in that it comprises means for guiding the mast adapting to the. cross section of the elements, ces moyens comportant d'une part au moins une série de galets ou patins disposés dans un même plan autour du mât à une hauteur déterminée et déplaçables radia- lement, et d'autre part, these means comprising on the one hand at least a series of rollers or pads arranged in the same plane around the mast at a determined height and radially displaceable, and on the other hand, un câble passant sur les supports des galets autour du mât en formant une boucle dont une extrémité est fixe et l'autre mobile de façon à serrer constamment la. boucle pour .maintenir les galets en contact avec les éléments tubulaires du mât. a cable passing over the supports of the rollers around the mast, forming a loop, one end of which is fixed and the other movable so as to constantly tighten the. loop to keep the rollers in contact with the tubular elements of the mast.
CH303566A 1966-03-03 1966-03-03 Extendable mast installation CH431917A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CH303566A CH431917A (en) 1966-03-03 1966-03-03 Extendable mast installation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CH303566A CH431917A (en) 1966-03-03 1966-03-03 Extendable mast installation

Publications (1)

Publication Number Publication Date
CH431917A true CH431917A (en) 1967-03-15

Family

ID=4247156

Family Applications (1)

Application Number Title Priority Date Filing Date
CH303566A CH431917A (en) 1966-03-03 1966-03-03 Extendable mast installation

Country Status (1)

Country Link
CH (1) CH431917A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO1980002576A1 (en) * 1979-05-23 1980-11-27 Steinmanns Erben A Barrier with retractable post
DE4119466A1 (en) * 1990-08-02 1992-02-06 Zuse Konrad Prof Dr Ing E H Dr Extensible and retractable tower structure

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO1980002576A1 (en) * 1979-05-23 1980-11-27 Steinmanns Erben A Barrier with retractable post
DE4119466A1 (en) * 1990-08-02 1992-02-06 Zuse Konrad Prof Dr Ing E H Dr Extensible and retractable tower structure
US5249396A (en) * 1990-08-02 1993-10-05 Konrad Zuse Extensible and contractible mast

Similar Documents

Publication Publication Date Title
EP0006097B1 (en) Cable conveyor
CH431917A (en) Extendable mast installation
CH497336A (en) Gripper device for handling metal scrap blocks
CH411006A (en) Process for welding wires on condenser coils, and machine for its implementation
EP0340076B1 (en) Device for retaining and loading lengthy objects, such as ladders, onto the roof of a vehicle
EP0051241B1 (en) Process and apparatus for handling elongated large objects
FR2625888A1 (en) DEVICE FOR DISPENSING STACKED CUPS
FR2684341A1 (en) Device for raising or withdrawing a ladder or the like onto or from a roof rack of a vehicle
FR2681893A1 (en) Two-level car park - has lower pallets displaceable sideways and upper pallets suspended vertically with powered pulley chains at each corner
FR2673612A1 (en) Device for destacking and automatic dispensing of trays
EP0249568B1 (en) Yarn package handler for hydro-extractors
EP0114143A2 (en) Automatic goods lift
FR2574773A1 (en) Carriage for receiving and transporting a knitting article for circular knitting machines
FR2511990A1 (en) TOP-LOADING DEVICE FOR CONTINUOUSLY UNWINDING A WIRE
CH202006A (en) Apparatus for supplying ingots to a melting furnace.
FR2943888A1 (en) DEVICE FOR THE INSTALLATION OF A TUBULAR SHEATH.
FR2680713A1 (en) METHOD AND DEVICE FOR AUTOMATICALLY PLACING TWO HALF CONES IN THE CONICAL HOLLOW OF A CUP.
CH590151A5 (en) Packaging bag production machine - uses hose net material with guide element in upper and lower sections
EP3063087B1 (en) Facility for the weight filling of containers resting on a conveyor
CH202621A (en) Lifting device for vehicles.
FR2661164A1 (en) Device for destacking buckets with handles
FR2501082A1 (en) Cleaning rake for grille - has rake between side plates hinging on trucks working in vertical guides
FR2574771A2 (en) Improvements made to the unreeling of metal wire packaged in the form of reels
FR2716875A1 (en) Pallet stacking and unstacking installation
BE493317A (en)