CH244432A - Method for regulating the performance of gas turbine plants. - Google Patents

Method for regulating the performance of gas turbine plants.

Info

Publication number
CH244432A
CH244432A CH244432DA CH244432A CH 244432 A CH244432 A CH 244432A CH 244432D A CH244432D A CH 244432DA CH 244432 A CH244432 A CH 244432A
Authority
CH
Switzerland
Prior art keywords
load
turbine
compressor
expansion stage
switched
Prior art date
Application number
Other languages
German (de)
Inventor
Oerlikon Maschinenfabrik
Original Assignee
Oerlikon Maschf
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Oerlikon Maschf filed Critical Oerlikon Maschf
Publication of CH244432A publication Critical patent/CH244432A/en

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F02COMBUSTION ENGINES; HOT-GAS OR COMBUSTION-PRODUCT ENGINE PLANTS
    • F02CGAS-TURBINE PLANTS; AIR INTAKES FOR JET-PROPULSION PLANTS; CONTROLLING FUEL SUPPLY IN AIR-BREATHING JET-PROPULSION PLANTS
    • F02C9/00Controlling gas-turbine plants; Controlling fuel supply in air- breathing jet-propulsion plants
    • F02C9/16Control of working fluid flow
    • F02C9/18Control of working fluid flow by bleeding, bypassing or acting on variable working fluid interconnections between turbines or compressors or their stages

Description

  

  Verfahren zur Regelung der Leistung von     Gasturbinenanlagen.       Eine     Gasturbinenanlage    für ein beliebiges  Gas (auch Heissluft) als Arbeitsmittel weist  bekanntlich mindestens einen Kompressor,  einen     Brennraum    und eine     Turbine    auf.  



  Will man nun bei     Teillast    die Drehzahlen  der Maschinen wenigstens angenähert kon  stant halten und dafür die Fördermengen  reduzieren, so muss der vom Kompressor er  zeugte Druck (der mit sinkender Förder  menge eher ansteigt) dem Druck vor der Tur  bine (der mit sinkender Fördermenge rasch  fällt) angepasst werden. Dies kann am ein  fachsten durch eine Drosselung mittels einer       Querschnittsverengung    auf der Saugseite oder  auf der     Druckseite    des Kompressors erfolgen.  Jede Drosselung ist aber eine Energiever  nichtung und setzt den Wirkungsgrad herab.  



  Die vorliegende Erfindung bezweckt, bei       Gasturbinenanlagen,    deren     Kompressor    und  Turbine bei     allen    Lasten mit mindestens an  genähert konstanter Drehzahl laufen, eine       Teillastmengenregelung    zu, schaffen, bei wel  cher diese     Energievernichtung    vermindert  wird.

   Das Verfahren nach der Erfindung be-    steht darin, dass bei Teillast mindestens eine       Expansionsstufe    zur     Ausnützung    des bei       kleiner    Fördermenge zu hohen Druckgefälles  eingeschaltet wird, derart,     dass    bei minimaler  Last mindestens angenähert die gesamte     Ar-          beitsmittelmenge    der Anlage durch diese Ex  pansionsstufe strömt, während bei maximaler  Last mindestens angenähert .die gesamte Ar  beitsmittelmenge über eine     By-pass-Leitung     um diese     Expansionsstufe    herumgeführt wird.  



  An Hand der beiliegenden Zeichnung,  welche schematisch einige Ausführungsbei  spiele der ebenfalls Gegenstand -der Erfin  dung bildenden Einrichtung zur Durchfüh  rung des Verfahrens zeigt, wird das Verfah  ren nach der Erfindung beispielsweise erläu  tert.  



       Fig.    1 zeigt eine übliche Gasturbinen  anlage offener     Schaltungsart.    1 ist der Kom  pressor, 2 der     Brennraum    und 3 die Turbine.  Die Luft wird vom     Kompressor    1 angesaugt,  auf Druck gebracht und dem Brennraum 2  zugeführt. Die Heissgase strömen zur Tur  bine 3, wo sie z. B. auf Atmosphärendruck      expandieren. Die Abgase können weiter aus  genutzt werden, z. B. zur     Vorwärmung    der       Kompressorluft    usw.  



  Bei Teillast wird durch das Ventil 4 die  Luftmenge zum Kompressor so weit gedros  selt, dass der     Druck    nach dem Kompressor 1  dem Druck entspricht, der sich entsprechend  der kleineren Fördermenge in der Turbine 3  einstellt. Durch Schliessen des Ventils 4 sinkt  der Druck vor dem Kompressor 1. Das da  durch     entstehende    Druckgefälle zwischen der  Atmosphäre und dem Kompressor 1     wird     durch Drosselung vernichtet und geht ver  loren; zudem     bewirkt    die Drosselung eine dem  tieferen Druck entsprechend zu hohe Tem  peratur,     wa.s    den Kraftbedarf erhöht.  



       Fig.    2 zeigt das erste     Ausführungsbei-          spiel,der    Erfindung. Bei Normallast wird die  Luft vom Kompressor 1 durch Leitungen 5  und 6 angesaugt. Das Ventil 4' ist offen  und somit arbeitet die Anlage wie diejenige  nach     Fig.    1. Bei Teillast wird das Ventil 4'  nach und nach geschlossen, und die Luft.  strömt ganz oder teilweise durch eine Leitung  7 zur Turbine 8 und von dieser zum Kom  pressor 1.

   Vor dem Kompressor muss der  Druck bei Teillast entsprechend der kleineren  Fördermenge sinken; je kleiner die Teillast,  je kleiner ist der Ansaugdruck des     Kompres-          sors.    Die     Teillastturbine    8 nützt nun das  Druckgefälle zwischen der Atmosphäre und  dem Druck vor dem Kompressor 1 aus. Da  der Kompressor immer das gleiche Volumen  ansaugt, der Druck vor dem Kompressor aber  abhängig ist von der Grösse der Teillast, wer  den zweckmässig die     Durchtrittsquerschnitte     der Turbine 8 mit Änderung der Teillast ver  ändert, was durch eine     'Querschnittsregelung     gut möglich ist.

   Es     könnte    auch das Ventil  4' zur Drosselung mitbenutzt werden; aber  die damit     abgedrosselte    Luftmenge leistet  keine Arbeit, und zudem wird durch Dros  selung die Temperatur vor dem Kompressor  erhöht und damit die Kraftaufnahme. Der  Kompressor -wird im allgemeinen mehrstufig  sein, und es ist daher möglich, dass insbeson  dere die letzten Stufen bei der Drucksenkung  vor dem Kompressor nicht mehr zu den ersten    Stufen passen und dass "Pumpen" eintritt.  Um dies zu vermeiden, können die Quer  schnitte nach den Laufrädern des Kompres  sors und abhängig von der Belastung ver  ändern werden, oder es kann eine     "Pump-          verhütungs"-Einrichtung    angeordnet     -werden.     



       Fig.    3 zeigt eine andere Ausführung des  Erfindungsgegenstandes.. Bei Normallast     wird     die Luft vom     Kompressor    1 durch den     Brenn-          raum    2 und Leitungen 18 und 19 zur Turbine  3 gedrückt. Das Ventil 10 ist offen. Bei Teil  last muss die Fördermenge verkleinert wer  den.

   Es erfolgt dies auf einfache Weise mit  tels der Turbine 11; diese wird bei Teillast  infolge Schliessens des Ventils 10     beauf-          schla.gt.    Um bei allen Teillasten günstig zu  arbeiten, kann die Turbine 11, ähnlich     wie     die Turbine 8 in     Fig.    2,     Querschnittsregelung     erhalten.  



  Auch bei dieser Ausführung wird der im  allgemeinen mehrstufige Kompressor mit Ab  nahme der Fördermenge ins     "Pumpen"    kom  men; es werden also auch hier die Quer  schnitte nach den Laufrädern des     Kompres-          sors    den durchströmenden -Mengen angepasst.  



  Die Turbine 11 kann auch zwischen zwei  Expansionsstufen der Hauptturbine 3 ange  ordnet werden, oder,     -wenn    die     Hauptturbine    3  in mehrere     Teilturbinen    unterteilt ist, zwi  schen zwei derselben. Die Turbine 11 kann  auch nach der Turbine 3 geschaltet sein, wie  das Beispiel     Fig.    4 zeigt. Bei Normallast  bleibt das Ventil 10 offen und bei Teillast  ganz oder teilweise geschlossen. Der Druck  nach der Turbine 3 entspricht bei Normallast  ungefähr dem Atmosphärendruck. Bei Teil  last steigt der Druck nach der Turbine 3 um  so mehr, je kleiner die Teillast ist. Die Tur  bine 11 nützt das Druckgefälle zwischen Tur  bine 3 (Austritt) und dem Atmosphärendruck  aus.  



  Beim Beispiel     Fig.    5 wird eine     einstufige          Teillastturbine    verwendet. 12 bedeutet ein  dem Laufrad 13     vorgeschaltetes        Leitrad.    Die       Zuströmung    der Luft erfolgt durch den Stut  zen 14, die     Abströmung    durch den Stutzen  15.     Fig.    6 zeigt hierzu die Anordnung der       112engenregelungsventile.    Bei Normallast sind      alle Ventile 16, 17 und 18 offen. Die Luft  strömt durch das offene Ventil 4'     (Fig.    2)  entsprechend dem kleinsten Widerstand un  mittelbar zum     Kompressor    1.

   Bei Übergang  auf Teillast beginnt zunächst das Ventil 4'  zu schliessen     und    ist z. B. bei 3/4 Last ge  schlossen. Hierauf beginnt das Ventil 17 zu  schliessen, das bei 1/ Last geschlossen ist.  Unter 1/2 Last bis 1/4 Last schliesst das Ventil  16; das     Ventil    18 .schliesst     unterhalb    1/4 Last.  Durch diese Anordnung kann das Druck  gefälle zwischen Atmosphäre und     Kompres-          soreintrittsdruck    ausgenützt werden, wodurch  der Wirkungsgrad bei Teillast wesentlich ge  hoben wird. Ähnlich ist die Gasturbine 11  der Beispiele     Fig.    3 und 4 gebaut.  



  Um bei mehrstufigen Kompressoren bei  abnehmender Luftmenge das "Pumpen" zu  vermeiden,     kann.    in einzelnen oder allen Stu  fen eine Anpassung der     Leitquerschnitte    nach  den Laufrädern an die Fördermenge nach be  kannten Anordnungen erfolgen.  



  Kompressor, Turbinen und Brennräume  können beliebiger Bauart .sein. Auch können  beliebige     Wärmeanstauscher,    je nachdem es       das        System    verlangt, vorhanden sein.  



  In jedem Falle wird bei Teillast die Ar  beitsmittelmenge herabgesetzt durch eine       Querschnittsverminderung    vor oder nach dem  Kompressor, und es wird mindestens eine Ex  pansionsstufe zur Ausnützung des bei klei  nerer Fördermenge zu hohen Druckgefälles  eingeschaltet. Die     Querschnittsverminderung     kann in der     Teillastturbine    selber erfolgen  oder zusätzlich noch an einer andern Stelle,       insbesondere    am     Kompressorgehäuse.     



  Die Atmosphäre kann auch durch einen  höheren oder tieferen Druck ersetzt sein, je  nach System und Zuleitung.



  Method for regulating the performance of gas turbine plants. A gas turbine system for any gas (including hot air) as the working medium is known to have at least one compressor, a combustion chamber and a turbine.



  If you want to keep the speed of the machines at least approximately constant at part load and to reduce the delivery rate, the pressure generated by the compressor (which tends to increase with decreasing delivery rate) must match the pressure in front of the turbine (which falls rapidly as delivery rate decreases ) be adjusted. This can be done most easily by throttling by means of a cross-sectional constriction on the suction side or on the pressure side of the compressor. However, every throttling is an energy destruction and reduces the efficiency.



  The purpose of the present invention is to create a partial load control in gas turbine systems, the compressor and turbine of which run at all loads at at least an approximately constant speed, in which this energy loss is reduced.

   The method according to the invention consists in that at part load at least one expansion stage is switched on to utilize the pressure gradient which is too high with a small delivery rate, in such a way that at minimum load at least approximately the entire amount of working fluid in the system flows through this expansion stage during at maximum load at least approximately .the entire amount of work equipment is routed around this expansion stage via a bypass line.



  With reference to the accompanying drawing, which shows schematically some Ausführungsbei games of the also subject -der inven tion forming device for imple mentation of the method, the method according to the invention is tert erläu, for example.



       Fig. 1 shows a conventional gas turbine system of open circuit type. 1 is the compressor, 2 is the combustion chamber and 3 is the turbine. The air is sucked in by the compressor 1, pressurized and fed to the combustion chamber 2. The hot gases flow to the turbine 3, where they z. B. expand to atmospheric pressure. The exhaust gases can be further used from, e.g. B. to preheat the compressor air etc.



  At partial load, the amount of air to the compressor is throttled so far through the valve 4 that the pressure after the compressor 1 corresponds to the pressure that is set in the turbine 3 according to the smaller flow rate. By closing the valve 4, the pressure in front of the compressor 1 drops. The pressure gradient that arises between the atmosphere and the compressor 1 is destroyed by throttling and is lost; In addition, the throttling causes the temperature to be too high, corresponding to the lower pressure, which increases the power requirement.



       2 shows the first embodiment, the invention. At normal load, the air is sucked in by the compressor 1 through lines 5 and 6. The valve 4 'is open and thus the system works like that of FIG. 1. At part load, the valve 4' is gradually closed, and the air. flows completely or partially through a line 7 to the turbine 8 and from there to the compressor 1.

   Upstream of the compressor, the pressure at part load must decrease in accordance with the smaller delivery rate; the lower the partial load, the lower the intake pressure of the compressor. The part-load turbine 8 now uses the pressure gradient between the atmosphere and the pressure upstream of the compressor 1. Since the compressor always draws in the same volume, but the pressure upstream of the compressor depends on the size of the partial load, whoever appropriately changes the flow cross-sections of the turbine 8 with a change in the partial load, which is easily possible through a cross-section control.

   The valve 4 'could also be used for throttling; but the amount of air that is throttled off does no work, and throttling also increases the temperature in front of the compressor and thus the power consumption. The compressor will generally be multi-stage, and it is therefore possible that in particular the last stages in the pressure reduction before the compressor no longer match the first stages and that "pumping" occurs. To avoid this, the cross-sections can be changed according to the compressor impellers and depending on the load, or a "surge prevention" device can be arranged.



       3 shows another embodiment of the subject matter of the invention. At normal load, the air is pressed from the compressor 1 through the combustion chamber 2 and lines 18 and 19 to the turbine 3. The valve 10 is open. The delivery rate must be reduced at part load.

   This is done in a simple manner with means of the turbine 11; this is acted upon at partial load as a result of valve 10 closing. In order to work favorably with all partial loads, the turbine 11, similar to the turbine 8 in FIG. 2, can have cross-sectional control.



  In this version, too, the generally multi-stage compressor will come into "pumping" when the flow rate decreases; the cross-sections after the compressor impellers are therefore also adapted to the flow rates.



  The turbine 11 can also be arranged between two expansion stages of the main turbine 3, or -if the main turbine 3 is divided into several sub-turbines, between two of the same. The turbine 11 can also be connected after the turbine 3, as the example in FIG. 4 shows. At normal load, the valve 10 remains open and at part load it remains fully or partially closed. The pressure after the turbine 3 corresponds approximately to the atmospheric pressure under normal load. At part load, the pressure after the turbine 3 increases the more the lower the part load is. The turbine 11 uses the pressure gradient between turbine 3 (outlet) and the atmospheric pressure.



  In the example of FIG. 5, a single-stage part-load turbine is used. 12 means a stator connected upstream of the impeller 13. The inflow of air takes place through the nozzle 14 and the outflow through the nozzle 15. FIG. 6 shows the arrangement of the flow control valves. At normal load, all valves 16, 17 and 18 are open. The air flows through the open valve 4 '(FIG. 2) directly to the compressor 1 according to the smallest resistance.

   When switching to part load, the valve 4 'begins to close and is z. B. closed at 3/4 load. The valve 17 then begins to close, which is closed at 1 / load. The valve 16 closes under 1/2 load to 1/4 load; the valve 18 closes below 1/4 load. This arrangement allows the pressure drop between the atmosphere and the compressor inlet pressure to be used, which significantly increases the efficiency at part load. The gas turbine 11 of the examples in FIGS. 3 and 4 is constructed in a similar manner.



  In order to avoid "pumping" with decreasing air volume in multi-stage compressors, you can. in individual or all stages an adaptation of the guide cross-sections after the impellers to the flow rate according to known arrangements.



  Compressors, turbines and combustion chambers can be of any type. Any desired heat exchangers, as required by the system, can also be present.



  In any case, the work medium amount is reduced at part load by a cross-sectional reduction before or after the compressor, and at least one expansion stage is switched on to take advantage of the pressure gradient that is too high when the delivery rate is smaller. The cross-section reduction can take place in the part-load turbine itself or additionally at another point, in particular on the compressor housing.



  The atmosphere can also be replaced by a higher or lower pressure, depending on the system and supply line.

 

Claims (1)

PATENTANSPRUCH I: Verfahren zur Regelung der Leistung von Gasturbinenanlagen mit mindestens einem Kompressor und mindestens einer Turbine, deren Drehzahlen bei allen Lasten mindestens angenähert konstant bleiben, dadurch gekenn zeichnet, dass bei Teillast mindestens eine Expansionsstufe zur Ausnützung des bei kleiner Fördermenge zu' hohen Druckgefälles eingeschaltet wird, derart, dass bei minimaler Last mindestens angenähert die gesamte Ar beitsmittelmenge der Anlage durch diese Expansionsstufe strömt, PATENT CLAIM I: Method for regulating the performance of gas turbine systems with at least one compressor and at least one turbine, the speeds of which remain at least approximately constant under all loads, characterized in that at part load at least one expansion stage is switched on to utilize the pressure gradient which is too high when the delivery rate is small is in such a way that at minimum load at least approximately the entire amount of working fluid in the system flows through this expansion stage, während bei maxi maler Last mindestens angenähert die ge samte Arbeitsmittelmenge über eine By-pass- Leitung um diese Expansionsstufe herumge führt wird. UNTERANSPRü CHE 1. Verfahren nach Patentanspruch I, da durch gekennzeichnet, dass bei Teillast eine auf der Saugseite des Kompressors angeord nete Expansionsstufe eingeschaltet wird. 2. while at maximum load at least approximately the entire amount of working fluid is led around this expansion stage via a bypass line. SUBClaims 1. The method according to claim I, characterized in that at part load an expansion stage angeord designated on the suction side of the compressor is switched on. 2. Verfahren nach Patentanspruch I, da durch gekennzeichnet, dass bei Teillast eine zwischen Kompressor und. Hauptturbine an geordnete Expansionsstufe eingeschaltet wird. 3. Verfahren nach Patentanspruch I, da durch gekennzeichnet, dass bei Teillast eine zwischen zwei Stufen der Hauptturbine an geordnete Expansionsstufe eingeschaltet wird. 4. Verfahren nach Patentanspruch I, da durch gekennzeichnet, dass bei Teillast eine nach der Hauptturbine angeordnete Expan sionsstufe eingeschaltet wird. 5. Method according to claim I, characterized in that at part load one between the compressor and. Main turbine is switched on at an ordered expansion stage. 3. The method according to claim I, characterized in that at part load, an expansion stage arranged between two stages of the main turbine is switched on. 4. The method according to claim I, characterized in that an expansion stage arranged after the main turbine is switched on at partial load. 5. Verfahren nach Patentanspruch I, da durch .gekennzeichnet, dass die Mengenrege lungsventile einer als Teillastturbine vorge sehenen Expansionsstufe mit abnehmender Belastung geschlossen, mit zunehmender Be lastung geöffnet werden. 6. Verfahren nach Patentanspruch I, da durch gekennzeichnet, dass bei Normallast eine als Teillastturbine vorgesehene Expan sionsstufe ausgeschaltet wird. 7. Method according to patent claim I, characterized by the fact that the volume control valves of an expansion stage provided as a part-load turbine are closed with decreasing load and opened with increasing load. 6. The method according to claim I, characterized in that an expansion stage provided as a part-load turbine is switched off at normal load. 7th Verfahren nach Patentanspruch I, da durch gekennzeichnet, dass bei Teillast die nach den Laufrädern liegenden Leitkanäle des Kompressors in ihrem Querschnitt zwecks Anpassung an die Fördermenge verändert werden. B. Verfahren nach Patentanspruch I, da durch gekennzeichnet, dass eine zusätzliche Mengenregelung durch Verkleinerung von Querschnitten erfolgt. Method according to patent claim I, characterized in that, at partial load, the cross-section of the guide channels of the compressor located after the impellers are changed in order to adapt to the delivery rate. B. The method according to claim I, characterized in that an additional amount control takes place by reducing cross-sections. .9. Verfahren nach Patentanspruch I, da durch gekennzeichnet, dass bei kleinen För- dermengen am Kompressor eine "Pumpver- hütungs"-Einriehtung eingeschaltet wird. 1Ö. Verfahren nach Patentanspruch I, da durch gekennzeichnet, dass bei Teillast eine Expansionsstufe eingeschaltet wird, die für Mengenregelung gebaut ist. .9. Method according to patent claim 1, characterized in that a "anti-pumping" device is switched on in the case of small delivery quantities at the compressor. 1Ö. Method according to patent claim I, characterized in that at partial load an expansion stage is switched on which is built for volume control. PATENTANSPRUCH II: Einrichtung zur Durchführung des Ver fahrens nach Patentanspruch I, dadurch ge kennzeichnet, dass sie mindestens eine Tur binenstufe und mindestens eine By-pa.ss-Lei- tung zur Umgehung derselben sowie Absperr organe zur Beschickung der Turbinenstufe oder der By-pass-Leitung mit Arbeitsmittel aufweist. PATENT CLAIM II: Device for carrying out the method according to claim I, characterized in that it has at least one turbine stage and at least one By-pa.ss line to bypass the same as well as shut-off devices for charging the turbine stage or the bypass - Has line with work equipment.
CH244432D 1945-01-27 1945-01-27 Method for regulating the performance of gas turbine plants. CH244432A (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CH244432T 1945-01-27

Publications (1)

Publication Number Publication Date
CH244432A true CH244432A (en) 1946-09-15

Family

ID=4464265

Family Applications (1)

Application Number Title Priority Date Filing Date
CH244432D CH244432A (en) 1945-01-27 1945-01-27 Method for regulating the performance of gas turbine plants.

Country Status (1)

Country Link
CH (1) CH244432A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
NL7713255A (en) * 1976-12-02 1978-06-06 Bbc Brown Boveri & Cie PROCEDURE FOR CONTROLLING A POWER INSTALLATION WITH A GAS TURBINE GROUP AND DEVICE FOR PERFORMING THE PROCEDURE.
EP2982833A1 (en) * 2014-08-08 2016-02-10 Rolls-Royce plc Gas turbine engine

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
NL7713255A (en) * 1976-12-02 1978-06-06 Bbc Brown Boveri & Cie PROCEDURE FOR CONTROLLING A POWER INSTALLATION WITH A GAS TURBINE GROUP AND DEVICE FOR PERFORMING THE PROCEDURE.
EP2982833A1 (en) * 2014-08-08 2016-02-10 Rolls-Royce plc Gas turbine engine
US10590856B2 (en) 2014-08-08 2020-03-17 Rolls-Royce Plc Gas turbine engine having an annular core bleed

Similar Documents

Publication Publication Date Title
EP3146184B1 (en) Method of providing a cooling flow from a compressor to a turbine in a gas turbine engine
EP2000649B1 (en) Jet engine with compressor air circulation and method for operating the same
EP2639429A1 (en) Aircraft engine
DE2909825A1 (en) CONTROL SYSTEM FOR A MULTI-STAGE AXIAL FLOW COMPRESSOR OF A GAS TURBINE ENGINE
DE60307662T2 (en) COMPRESSOR WITH POWER CONTROL
DE1964758A1 (en) Control of a furnace system for the thermal treatment of metals
DE102015110044A1 (en) Connected Gas Turbine Auxiliary Systems
DD153718A1 (en) WORKING PROCEDURE FOR A SELF-BRAKING INTERNAL COMBUSTION ENGINE
CH244432A (en) Method for regulating the performance of gas turbine plants.
EP1600630B1 (en) Multistage gas compressor and its control method
EP3167197B1 (en) Method for pressure and temperature control of a fluid in a series of cryogenic compressors
DE809913C (en) Two or multi-stage refrigeration machine
DE1428106B2 (en) ADJUSTMENT DEVICE FOR JOINT ADJUSTMENT OF THE GUIDE BLADES OF THE AXIAL STAGES OF A MULTISTAGE CENTRIFUGAL COMPRESSOR
WO2020074300A1 (en) Air compression system for an air separation process
DE585967C (en) Power control of a gas turbine
DE890117C (en) Multi-stage centrifugal compressor
JPS61197793A (en) Cooling method in multi-stage root type vacuum pump
DE1926395A1 (en) Ventilation device for exhaust steam condensers of steam turbines
CH188402A (en) Internal combustion engine with turbine for utilizing the energy contained in the exhaust gases of the internal combustion engine.
CH347296A (en) Device to improve the partial load operation of a turbo compressor system
DE815425C (en) Method for improving the partial load efficiency in an open gas turbine process
CH208050A (en) Gas turbine plant.
DE913342C (en) Procedure for changing the degree of cooling when the compressor load on a dynamic compressor and associated compressor changes
DE102005040802A1 (en) Operation of a turbo compressor, with a turbine, measures the pressures at two different points for a rapid detection of an overload to trigger counter measures
CH220292A (en) Method for increasing the readiness for sudden loads on gas turbine systems.