WO2024092998A1 - Processus de construction par compactage vibrant à l'eau saturée pour des pierres concassées calibrées - Google Patents

Processus de construction par compactage vibrant à l'eau saturée pour des pierres concassées calibrées Download PDF

Info

Publication number
WO2024092998A1
WO2024092998A1 PCT/CN2022/142583 CN2022142583W WO2024092998A1 WO 2024092998 A1 WO2024092998 A1 WO 2024092998A1 CN 2022142583 W CN2022142583 W CN 2022142583W WO 2024092998 A1 WO2024092998 A1 WO 2024092998A1
Authority
WO
WIPO (PCT)
Prior art keywords
crushed stone
graded
paving
raw materials
compaction
Prior art date
Application number
PCT/CN2022/142583
Other languages
English (en)
Chinese (zh)
Inventor
白银战
Original Assignee
中国港湾工程有限责任公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 中国港湾工程有限责任公司 filed Critical 中国港湾工程有限责任公司
Publication of WO2024092998A1 publication Critical patent/WO2024092998A1/fr

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C23/00Auxiliary devices or arrangements for constructing, repairing, reconditioning, or taking-up road or like surfaces
    • E01C23/01Devices or auxiliary means for setting-out or checking the configuration of new surfacing, e.g. templates, screed or reference line supports; Applications of apparatus for measuring, indicating, or recording the surface configuration of existing surfacing, e.g. profilographs
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C7/00Coherent pavings made in situ
    • E01C7/02Coherent pavings made in situ made of road-metal without binders
    • E01C7/04Coherent pavings made in situ made of road-metal without binders of broken stones, gravel, or like materials

Definitions

  • the present invention relates to the technical field of road base construction, and more specifically to a graded crushed stone saturated water-tight vibration construction process.
  • the base of pavement structures such as roads, airport runways, and storage yards usually have graded crushed stone, cement stabilized crushed stone, cement stabilized soil, etc.
  • cement stabilized crushed stone is usually used as the pavement structure base in China.
  • the graded crushed stone base has a lower cost and is not limited by the initial setting of cement during construction. The difficulty of rolling and surface preparation is much lower than that of cement stabilized crushed stone base, so it is still used in many places.
  • the graded crushed stone base layer is compacted according to the conventional moisture content control and layered compaction method, its compaction degree is difficult to approach or reach 100%, and quality problems such as unqualified compaction degree, loose surface, peeling, etc. often occur during the construction of graded crushed stone.
  • the loose surface has a great influence on the subsequent sweeping and oil penetration construction, and it is difficult to meet the design requirements of the airport runway under heavy load.
  • An object of the present invention is to solve at least the above problems and to provide at least the advantages which will be described hereinafter.
  • Another object of the present invention is to provide a construction process for saturated water-tight vibration of graded crushed stone, which can enable the graded crushed stone to be applied to the airport pavement base with a compaction degree of 100%.
  • the surface of the airport pavement base is flat and dense without looseness or segregation.
  • a saturated water-tight vibration construction process for graded crushed stone which comprises:
  • the mixture is spread on the surface of the underlying layer and then compacted.
  • the compaction method includes: static pressing first, repairing and leveling, and then vibration rolling. The compacted mixture is then fully watered until saturated, and then the rolling is repeated until the water flows out of the gaps and the graded gravel layer reaches the compaction requirement.
  • the mixing ratio of the crushed stone raw materials is: when the sieve hole size is 50 mm, the crushed stone passing rate is 100wt%, when the sieve hole size is 37 mm, the crushed stone passing rate is 95-100wt%, when the sieve hole size is 25 mm, the crushed stone passing rate is 70-95wt%, when the sieve hole size is 19 mm, the crushed stone passing rate is 55-85wt%, when the sieve hole size is 4.75 mm, the crushed stone passing rate is 30-60wt%, when the sieve hole size is 0.6 mm, the crushed stone passing rate is 12-30wt%, and when the sieve hole size is 0.075 mm, the crushed stone passing rate is 0-8wt%;
  • the weight proportion of crushed stone raw materials passing through the 0.075mm sieve hole in the crushed stone raw materials passing through the 0.6mm sieve hole does not exceed 60%; the weight proportion of needle-shaped and flaky crushed stone raw materials in the crushed stone raw materials with a particle size greater than 4.75mm does not exceed 15%, and the needle-shaped and flaky crushed stone raw materials are defined in the test method in ASTM D 693 standard; the abrasion value of the crushed stone raw materials is tested in accordance with the ASTM C131 test procedure, and the result is not greater than 35%; the sodium sulfate firmness of the crushed stone raw materials is tested in accordance with the ASTM C 88 test procedure, and after 5 test cycles, the loss value is less than 5%.
  • the process of mixing the crushed stone raw materials to obtain the mixture specifically includes: placing the crushed stone raw materials in a mixing station, using the mixing station to forcibly mix the mixture, and adding water during mixing according to the optimal moisture content of the crushed stone raw materials that meet the grading requirements ⁇ 2%, and the optimal moisture content of the crushed stone raw materials that meet the grading requirements is determined by a heavy compaction test.
  • the surface of the underlying layer is first wetted by sprinkling water.
  • the surface of the truck bed of the transport vehicle is first wetted by spraying water.
  • the graded crushed stone layer reaches the compaction requirement, it is also repaired and jointed, and finally accepted.
  • the compaction degree of the graded crushed stone layer is measured by a sand filling method.
  • static compaction is first performed once, followed by repair and leveling, and then vibration rolling is performed four times.
  • the present invention includes at least the following beneficial effects: when graded crushed stone is applied to the airport pavement base, the compaction degree should reach 100%. If it is constructed according to the conventional layered compaction method, its compaction degree is difficult to reach 100%.
  • the saturated water-tight vibration compaction process provided by the present application successfully solves this technical problem. At the same time, since the graded crushed stone is saturated with water during the compaction process, there is no need to consider the quality problems such as looseness and peeling of the base surface caused by excessive surface water loss of the graded crushed stone base during the compaction process.
  • FIG1 is a flow chart of a saturated water-tight vibration process for graded crushed stone according to an embodiment of the present invention
  • FIG2 is a perspective schematic diagram of the pavement of the Hambantota Airport in Sri Lanka according to an embodiment of the present invention
  • FIG3 is a close-up schematic diagram of the pavement of the Hambantota Airport in Sri Lanka according to an embodiment of the present invention.
  • the pavement design of Hambantota Airport in Sri Lanka is based on the AC150/5320-6E specification of the Federal Aviation Administration of the United States "Airport Pavement Design and Evaluation". According to the requirements of the specification, graded crushed stone is used in the airport pavement base, and the compaction degree should reach 100%, and the CBR value should not be less than 100%.
  • graded gravel base is constructed according to the conventional layered compaction method, its compaction degree is difficult to reach 100%. This is the technical difficulty of this construction. After many experiments and demonstrations, the technical research team of the project department finally came up with the saturated watertight compaction method and successfully solved this technical problem.
  • the saturated water-tight vibration construction process of graded crushed stone specifically includes the following steps:
  • Construction commencement report Submit the "Graded gravel base construction commencement report" to the owner. The gravel base construction can only be carried out after approval.
  • the source of aggregates must be approved by the engineer and must be clean, solid, durable crushed stone particles that are roughly the same as the sample. Pebbles and crushed pebbles are not allowed;
  • Aggregates can be mixed with fine sand, stone powder, or other similar binders or fillers approved by other suppliers. The mixture should be uniform and meet the requirements of the technical specifications;
  • the mixture must be capable of being compacted into a dense and stable base and must not contain vegetable matter, clay lumps, easily decomposable or breakable or other harmful matter.
  • the stockpile yard is selected near the mixing station, and a temporary stockpile silo is set up at the mixing station.
  • Raw materials of various specifications in the stockpile silo are separated by isolation walls.
  • a WCB-500 graded gravel mixing station is installed at the mixing site. After the equipment arrives at the site, it is installed and debugged, and calibrated by the measurement department. It can only be used after inspection that all indicators meet the requirements.
  • a loader is configured in the mixing station silo for loading and preparing materials;
  • Transportation equipment 15 dump trucks with a load capacity of more than 15 tons will be equipped according to the mixing capacity and transportation road conditions. The number will be adjusted according to the construction progress and on-site needs;
  • Paving equipment The model of the paving machine brought to the site is DTU95 produced by Sany Heavy Industry;
  • Rolling equipment One 26T single-wheel vibratory roller and one 22T single-wheel vibratory roller, and one small tamping machine are used for construction;
  • a batch of small tools such as shovels, wheelbarrows, wire ropes, etc.
  • Laboratory construction is divided into three aspects, namely: establishment of quality management system for construction site laboratories, laboratory hardware construction, and rational allocation and quality education of personnel.
  • Laboratory quality system including the organizational structure, responsibilities, procedures, processes and resources for implementing quality management.
  • Laboratory technical staff 1 technical supervisor and 8 operators are equipped to ensure the basic needs of grassroots construction and on-site testing.
  • the lower bearing layer to be accepted must meet the specified requirements, and its longitudinal and transverse slopes, flatness, compaction, longitudinal elevation, etc. must meet the assessment requirements, otherwise the lower bearing layer must be reprocessed before the base construction.
  • the surface of the underlying layer Before paving the base layer, the surface of the underlying layer can be appropriately sprinkled with water to moisten the surface according to the site conditions.
  • test section with an area of not less than 300 square meters shall be paved on site approved by the owner's engineer.
  • the shoulder section (between two navigation lights) between runway 2200 and 3000 shall be selected to pave the test section first;
  • the following parameters are determined through the construction of the test section: whether the construction mix ratio of materials is reasonable; the loose paving coefficient of materials; standard construction method; paving speed; method for controlling the moisture content of the mixture; combination of compaction machinery, rolling method and compaction sequence as well as speed and number of passes; coordination and cooperation of mixing, transportation, paving and rolling machinery; inspection method after compaction; length of the daily working section; standardized management and optimized construction organization.
  • the owner's engineer shall be notified 48 hours before the construction of the test area. If the preparation work cannot be completed in time due to bad weather and equipment failure, the owner's engineer shall be notified verbally or in writing to obtain consent.
  • a pile is set up every 10m for leveling measurement, and the guide control line bracket is driven into the paving edge line 50cm away.
  • the position of the guide control line bracket corresponds to the center line pile number.
  • the spacing between the guide control line brackets is 10m.
  • the height of the cross bar of the guide control line bracket is adjusted and set to the elevation of the guide control line during paving.
  • the elevation of the guide control line the top surface elevation of the underlying layer + the loose laying coefficient ⁇ the designed compacted thickness of the graded gravel layer + the fixed value.
  • the fixed value is the height difference between the conductor and the ironing plate of the paving equipment.
  • the materials should be well graded from coarse to fine, and the design batching specifications required in the above table should be strictly followed, and the deviation should be controlled within the allowable range;
  • the percentage of material passing the 0.075 mm sieve must not exceed 60% of the percentage passing the 0.60 mm sieve;
  • the content of needle and flake crushed stone with a particle size greater than 4.75 mm shall not exceed 15% by weight.
  • the test method for distinguishing needle and flake crushed stone shall comply with the definition of ASTM D 693;
  • the loss value should be less than 5% after 5 test cycles;
  • the liquid limit of fine aggregate with a particle size less than 0.42 mm should be no greater than 25 and the plastic limit should be no greater than 4; according to ASTM 2419 test of the sand equivalent value of this particle size level, the test result should be greater than 35%;
  • test sample is a construction mix ratio sample
  • the needle and flake content should be less than 30%.
  • the mixing of graded crushed stone base material adopts the centralized factory mixing method.
  • the mixer is a set of WCB-500 graded crushed stone mixer, with an average output of 500t per hour.
  • the equipment should be fully debugged before mixing.
  • the debugging of the mixing equipment is divided into two steps: the first step is to debug the aggregate gradation, that is, without adding water, determine the mixing ratio of various crushed stones; the second step is to debug the mixture, that is, add water to the crushed stone and adjust the water content to meet the requirements of the design mix ratio.
  • the test personnel Before mixing, the test personnel shall measure the aggregate gradation and aggregate moisture content. If the construction is carried out in the rainy season, the frequency of moisture content measurement shall be increased, and the construction mix ratio and the actual amount of water added during mixing shall be calculated. Considering that the moisture content will be lost during mixing, transportation, paving, shaping, rolling and other processes, the amount of water used for mixing can be appropriately increased according to the weather, transportation distance and construction progress, so that the moisture content of the mixed material after mixing is slightly greater than the optimal moisture content by 0.5-1% (determined by the test). In the morning, when the temperature is low, there is no wind and the transportation distance is short, the moisture content of the mixed material is close to the optimal moisture content.
  • the moisture content of the mixed material should be higher than the optimal moisture content.
  • the materials When mixing the graded crushed stone base mixture, the materials shall be loaded in strict accordance with the mix ratio design requirements approved by the owner's engineer. The materials shall be sent from the silo to the mixing silo via a belt conveyor. At the same time, water shall be added according to the mix ratio requirements. After mixing, the materials shall be sent to the storage silo by a belt conveyor to wait for loading.
  • the mixing quality shall be jointly controlled by the laboratory attendant and the machine operator. The person in charge of each control shall strictly select the aggregate specifications and quantity of each silo according to the mix ratio notice provided by the laboratory.
  • the amount of various aggregates and water used during mixing shall be accurate to ensure that the gradation of the mixture meets the design requirements and that the materials discharged are uniform and there is no separation of coarse and fine materials.
  • the materials When loading the graded crushed stone base mixture, in order to reduce segregation, the materials shall be loaded three times: front, back and middle, and a special person shall be arranged to be responsible for the command.
  • the water content is slightly greater than the optimum water content
  • the graded crushed stone mixture is transported by dump trucks of 15 tons or more. When the transportation distance is long, there is wind or the temperature is high at noon, the mixture on the material truck is covered with tarpaulin to prevent water loss.
  • the transportation capacity is adjusted in time according to the mixer capacity, transportation distance, paving capacity, etc.
  • the transportation vehicles must ensure that there are three vehicles waiting to unload in front of the paver, and no less than three vehicles waiting to load at the mixing station.
  • the number of vehicles, drivers, and driving routes are uniformly implemented the day before paving. According to the production quantity required by the construction section of the front field, sufficient transportation vehicles are equipped to ensure continuous operation of the construction section.
  • the compaction method includes: first static compaction once, repairing and leveling, then vibration rolling 4 times, and then fully watering the rolled mixture until saturation, and then repeating the rolling until the water flows out of the gaps and the graded gravel layer reaches the compaction requirement.
  • the mixture was spread using a DTU95 paver produced by Sany Heavy Industry.
  • the sensor used a steel wire rope to control the elevation and thickness.
  • the surface of the underlying layer was properly sprinkled with water and moistened, and the operation of each part of the paver was checked every day to see if it was normal.
  • the ironing plate was padded with wooden boards so that the elevation of the ironing plate was the loose elevation of the paving layer. To reduce the deformation of the ironing plate, each paver ironing plate must be padded at least three places.
  • the speed of the paver is determined according to the mixing capacity and transportation capacity. It is strictly forbidden to stop the paver to wait for materials, so as to maintain the continuity of paving and improve the flatness.
  • the paving speed of the paver is 1.5-2m/min. When paving the mixture, the minimum paving speed should be 1.5m/min to reduce the phenomenon of stopping to wait for materials.
  • a dedicated person will direct the transport vehicle to stop 20 to 30 cm in front of the paver to prevent collision with the paver.
  • the paver will push the unloading vehicle forward and unload while moving forward.
  • the vehicle cannot brake during unloading.
  • the unloading speed should be coordinated with the paving speed.
  • a dedicated person will direct the unloading.
  • a dedicated person After the paver spreads, a dedicated person shall be assigned to eliminate the segregation of coarse and fine aggregates, promptly remove local coarse aggregate "nests", and fill them with newly mixed materials. If there is too much coarse aggregate, a dedicated person shall be assigned to fill the gaps with newly mixed fine aggregates in a timely manner.
  • the edges of the road surface should be trimmed and shaped, and compacted with relevant tools (such as a shovel) to ensure that the edges are straight, smooth and dense.
  • the joints of the upper and lower layers should be staggered by no less than 3m.
  • the compaction and rolling of the mixture will be carried out by a 26T single steel wheel vibratory roller and a 22T single steel wheel vibratory roller.
  • the rolling length should be 50 to 80 meters.
  • the rolling sections should be clearly layered, with obvious boundary marks and continuous rolling.
  • the principle of static pressure should be followed for both initial and final pressure to reduce deformation and improve surface density and flatness.
  • the rolling sequence is to use a 22T grade roller for static rolling once, weak vibration rolling twice, and strong vibration rolling twice. Then use a sprinkler truck to fully sprinkle water on the compacted mixture until it is saturated. Then use a 26T grade roller to repeat strong vibration rolling until the water flows out of the gaps and the graded gravel layer reaches the compaction requirement. Finally, use a 26T grade roller for static rolling once to make the surface dense and free of wheel marks.
  • Rolling method After paving and forming, the roller is used for rolling.
  • the rolling direction is parallel to the center line of the road.
  • rolling is carried out from the shoulder to the center.
  • rolling is carried out from the inside to the outside, so that the longitudinal extension and the cross slope meet the design requirements.
  • the roller rolls in a step-like manner. At the joint of the two rolling sections, the roller rolls at a 45-degree angle.
  • the wheel tracks overlap by 1/2 of the wheel width.
  • the rear wheel must exceed the joint of the two sections. When the rear wheel rolls the full width of the road surface, it is considered one pass. Rolling is carried out until the required compaction degree and no wheel tracks are left.
  • the rolling speed of the roller is preferably 1st gear for the first two passes, and 2nd gear can be used afterwards. High-speed rolling is absolutely not allowed.
  • Rolling procedure static pressure ⁇ weak vibration ⁇ strong vibration ⁇ static pressure. Record the number of rolling times on site. Both sides of the road surface should be rolled 1 to 2 more times. The speed of the roller should be 1.5 to 1.7 km/h during steady pressure, 1.8 to 2.2 km/h during vibration pressure, and 1.5 to 1.7 km/h during final pressure.
  • transverse joint treatment the graded crushed stone base mixture that is not compacted on the day of the paver can be rolled together with the mixture to be paved the next day, but attention should be paid to the moisture content of this part of the mixture.
  • the moisture content is low, appropriate watering should be added to make its moisture content meet the specified requirements.
  • Longitudinal joint treatment When rolling the longitudinal joint, leave about 20cm unrolled as the control elevation surface for the next paver to move. At the same time, the joint should overlap about 5cm. When the paver has paved the entire designed width of the working surface, the next rolling surface can be rolled. If the machine is shut down due to special circumstances, the entire paving surface should be rolled (including the reserved 20cm). When paving is restarted, the uncompacted and loose materials at the longitudinal joint should be shoveled away first, and the longitudinal joint should be shoveled into a vertical section. Then, water should be sprinkled to moisten the joint before new paving, leveling, and rolling work.
  • Treatment of the interface When paving at the interface, first spread 20cm more on one surface. After leveling and compacting, scrape off the excess material on the interface and shovel the interface into a vertical section. Then sprinkle water to moisten the interface before paving, leveling and rolling the other surface.
  • the compaction degree of the graded crushed stone base of the pavement of Sri Lanka's Hambantota Airport reached 100%, and the CBR value reached 120%.
  • the surface of the base was flat and dense, without looseness or segregation, fully meeting the requirements of the US Federal Aviation Administration's "Airport Pavement Design and Evaluation" AC 150/5320-6E specification.
  • graded crushed stone Because graded crushed stone has micro-permeability, on the one hand, it can continuously discharge the infiltrated water within a certain period of time, so that it will not accumulate on the interface of the structural layer, and maintain the intact connection between the graded crushed stone base and the asphalt layer of the airport pavement above it; on the other hand, graded crushed stone will not have strong water permeability, so it will not cause a large amount of water to quickly infiltrate the roadbed, causing the roadbed soil to quickly reach supersaturation and soften, and quickly reduce the bearing capacity of the airport runway.
  • the shrinkage coefficient of graded crushed stone is extremely small, almost zero, which can avoid the reflection cracks of the asphalt surface layer caused by the shrinkage of the semi-rigid base.
  • graded crushed stone is a granular body, which does not transmit stress and displacement by itself. Therefore, it can dissipate and absorb the high stress and strain at the crack tip caused by changes in environmental factors, especially load and temperature changes, and completely absorb the strain energy at the crack tip under the action of external loads, eliminating the possibility of crack expansion in the asphalt surface layer.
  • graded crushed stone has sufficient compressive and shear strength, meeting the requirements of being a pavement load-bearing layer.
  • the mixture consistent with the above embodiment was used for conventional moisture content control and layered compaction construction, that is, layered paving and rolling, and the mixture was controlled at the optimal moisture content during each layer rolling.
  • the final graded crushed stone base compaction degree can only reach 98% at most, which is difficult to meet the requirements of the Federal Aviation Administration's "Airport Pavement Design and Evaluation" AC 150/5320-6E specification.

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Road Paving Structures (AREA)

Abstract

La présente invention concerne un processus de construction par compactage vibrant à l'eau saturée pour des pierres concassées calibrées, consistant à : réaliser la vérification ainsi que l'acceptation et la finition sur une couche de base ; effectuer la conception et les essais de proportion de mélange sur des pierres concassées calibrées afin de déterminer une proportion de mélange, le coefficient de pose en vrac et une méthode de pose ; effectuer le relevé et la mise en place sur la couche de base qui a été qualifiée lors de la vérification et de l'acceptation ; préparer des matières premières de pierres concassées selon la proportion de mélange déterminée par les essais, ajouter les matières premières de pierres concassées dans une machine de mélange et les mélanger afin d'obtenir un mélange ; et poser le mélange sur la surface de la couche de base selon le coefficient de pose en vrac et la méthode de pose qui sont déterminés par les essais, et le compacter, une méthode de compactage consistant à effectuer d'abord un compactage statique, à réparer et à niveler, puis à effectuer un roulage par vibration, à arroser complètement le mélange roulé d'eau jusqu'à saturation et à le rouler à plusieurs reprises jusqu'à ce que l'eau s'écoule des interstices et que ladite couche de pierres concassées calibrées satisfasse les exigences du degré de compactage. Par conséquent, le processus peut permettre d'appliquer des pierres concassées calibrées aux couches de roulement des routes d'aéroport, le degré de compactage atteignant 100 %, et les couches de roulement des routes d'aéroport ayant des surfaces planes et compactes et étant exemptes d'ameublissement et de ségrégation.
PCT/CN2022/142583 2022-11-01 2022-12-28 Processus de construction par compactage vibrant à l'eau saturée pour des pierres concassées calibrées WO2024092998A1 (fr)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN202211354290.0A CN115787386A (zh) 2022-11-01 2022-11-01 级配碎石饱和水密振实施工工艺
CN202211354290.0 2022-11-01

Publications (1)

Publication Number Publication Date
WO2024092998A1 true WO2024092998A1 (fr) 2024-05-10

Family

ID=85434762

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2022/142583 WO2024092998A1 (fr) 2022-11-01 2022-12-28 Processus de construction par compactage vibrant à l'eau saturée pour des pierres concassées calibrées

Country Status (2)

Country Link
CN (1) CN115787386A (fr)
WO (1) WO2024092998A1 (fr)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102477710A (zh) * 2010-11-22 2012-05-30 中国十七冶集团有限公司 一种天然级配卵石路面底基层的施工方法
CN103161109A (zh) * 2011-12-13 2013-06-19 中国二十冶集团有限公司 采用海砂对泥炭土地基进行路基填筑的方法
CN105714653A (zh) * 2016-02-02 2016-06-29 上海建工集团股份有限公司 级配碎石基层施工组合碾压工艺
CN107604785A (zh) * 2017-07-19 2018-01-19 甘肃路桥建设集团养护科技有限责任公司 振动拌和宽幅全厚半刚性基层施工工艺
CN113718604A (zh) * 2021-07-15 2021-11-30 兰州交通大学 一种沙漠腹地高速公路风积沙填料填筑方法
CN114381981A (zh) * 2022-01-28 2022-04-22 中电建路桥集团有限公司 导行路双层联铺试验段施工方法
US20220205188A1 (en) * 2020-12-30 2022-06-30 Shandong Provincial Communications Planning And Design Institute Group Co., Ltd Full-depth ultra-thin long-life pavement structure and construction method thereof

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6781669B2 (ja) * 2017-06-14 2020-11-04 鹿島建設株式会社 締固め方法、及び、締固め管理システム
CN108004864A (zh) * 2017-12-01 2018-05-08 江苏中路工程技术研究院有限公司 运用改良湿陷性黄土作为路基填料的施工方法
CN112982058A (zh) * 2019-12-14 2021-06-18 浙江建腾建设有限公司 一种水泥稳定碎石振动拌和施工工法
CN111893827A (zh) * 2020-08-05 2020-11-06 中交上海航道局有限公司 一种城市主干道路的施工工艺

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102477710A (zh) * 2010-11-22 2012-05-30 中国十七冶集团有限公司 一种天然级配卵石路面底基层的施工方法
CN103161109A (zh) * 2011-12-13 2013-06-19 中国二十冶集团有限公司 采用海砂对泥炭土地基进行路基填筑的方法
CN105714653A (zh) * 2016-02-02 2016-06-29 上海建工集团股份有限公司 级配碎石基层施工组合碾压工艺
CN107604785A (zh) * 2017-07-19 2018-01-19 甘肃路桥建设集团养护科技有限责任公司 振动拌和宽幅全厚半刚性基层施工工艺
US20220205188A1 (en) * 2020-12-30 2022-06-30 Shandong Provincial Communications Planning And Design Institute Group Co., Ltd Full-depth ultra-thin long-life pavement structure and construction method thereof
CN113718604A (zh) * 2021-07-15 2021-11-30 兰州交通大学 一种沙漠腹地高速公路风积沙填料填筑方法
CN114381981A (zh) * 2022-01-28 2022-04-22 中电建路桥集团有限公司 导行路双层联铺试验段施工方法

Also Published As

Publication number Publication date
CN115787386A (zh) 2023-03-14

Similar Documents

Publication Publication Date Title
CN107338686A (zh) 一种高速铁路路基填料施工方法
CN108978389A (zh) 一种沥青路面的施工方法
CN111021174A (zh) 一种城市道路的施工方法
CN114381981A (zh) 导行路双层联铺试验段施工方法
CN106522073A (zh) 一种高掺量水稳铣刨旧料基层施工方法
CN114232649B (zh) 无砟轨道路基土方填筑的施工方法
CN211472012U (zh) 一种信号灯路口灌入式复合路面
CN113929378A (zh) 一种油页岩半焦及其改性材料的应用
CN111827033A (zh) 一种高速公路互通匝道路基加宽填筑固化土施工方法
CN112982058A (zh) 一种水泥稳定碎石振动拌和施工工法
WO2024092998A1 (fr) Processus de construction par compactage vibrant à l'eau saturée pour des pierres concassées calibrées
CN111719371A (zh) 一种道路基层组分以及道路铺设方法
CN113152200A (zh) 垦区公路水稳砂砾基层裂缝防治方法
Pittman Construction of roller-compacted concrete pavements
Sharp Concrete in Highway Engineering: International Series of Monographs in Civil Engineering
CN111979865A (zh) 一种复合式沥青路面施工方法
CN113529575A (zh) 高等级公路桥涵台背回填建筑废弃物施工工艺
Mallick et al. Construction of Asphalt Pavements
CN111576125B (zh) 一种横向自动给料基层施工方法
Li et al. Control Points of the Compaction Technology for Subgrades and Pavements in Municipal Road Engineering
CN113584981A (zh) 一种装配式水泥混凝土路面板及施工方法
CN113174793A (zh) 一种通过改良填筑材料固化土加宽路基的施工方法
Wu et al. Louisiana Transportation Research Center
CN112176815A (zh) 公路水稳结构分段阶梯式连铺施工工艺
CN116356797A (zh) 一种弃土资源化利用改良土的填筑施工方法

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 22964292

Country of ref document: EP

Kind code of ref document: A1