WO2024092998A1 - Saturated-water vibrating compaction construction process for graded crushed stone - Google Patents

Saturated-water vibrating compaction construction process for graded crushed stone Download PDF

Info

Publication number
WO2024092998A1
WO2024092998A1 PCT/CN2022/142583 CN2022142583W WO2024092998A1 WO 2024092998 A1 WO2024092998 A1 WO 2024092998A1 CN 2022142583 W CN2022142583 W CN 2022142583W WO 2024092998 A1 WO2024092998 A1 WO 2024092998A1
Authority
WO
WIPO (PCT)
Prior art keywords
crushed stone
graded
paving
raw materials
compaction
Prior art date
Application number
PCT/CN2022/142583
Other languages
French (fr)
Chinese (zh)
Inventor
白银战
Original Assignee
中国港湾工程有限责任公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 中国港湾工程有限责任公司 filed Critical 中国港湾工程有限责任公司
Publication of WO2024092998A1 publication Critical patent/WO2024092998A1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C23/00Auxiliary devices or arrangements for constructing, repairing, reconditioning, or taking-up road or like surfaces
    • E01C23/01Devices or auxiliary means for setting-out or checking the configuration of new surfacing, e.g. templates, screed or reference line supports; Applications of apparatus for measuring, indicating, or recording the surface configuration of existing surfacing, e.g. profilographs
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C7/00Coherent pavings made in situ
    • E01C7/02Coherent pavings made in situ made of road-metal without binders
    • E01C7/04Coherent pavings made in situ made of road-metal without binders of broken stones, gravel, or like materials

Definitions

  • the present invention relates to the technical field of road base construction, and more specifically to a graded crushed stone saturated water-tight vibration construction process.
  • the base of pavement structures such as roads, airport runways, and storage yards usually have graded crushed stone, cement stabilized crushed stone, cement stabilized soil, etc.
  • cement stabilized crushed stone is usually used as the pavement structure base in China.
  • the graded crushed stone base has a lower cost and is not limited by the initial setting of cement during construction. The difficulty of rolling and surface preparation is much lower than that of cement stabilized crushed stone base, so it is still used in many places.
  • the graded crushed stone base layer is compacted according to the conventional moisture content control and layered compaction method, its compaction degree is difficult to approach or reach 100%, and quality problems such as unqualified compaction degree, loose surface, peeling, etc. often occur during the construction of graded crushed stone.
  • the loose surface has a great influence on the subsequent sweeping and oil penetration construction, and it is difficult to meet the design requirements of the airport runway under heavy load.
  • An object of the present invention is to solve at least the above problems and to provide at least the advantages which will be described hereinafter.
  • Another object of the present invention is to provide a construction process for saturated water-tight vibration of graded crushed stone, which can enable the graded crushed stone to be applied to the airport pavement base with a compaction degree of 100%.
  • the surface of the airport pavement base is flat and dense without looseness or segregation.
  • a saturated water-tight vibration construction process for graded crushed stone which comprises:
  • the mixture is spread on the surface of the underlying layer and then compacted.
  • the compaction method includes: static pressing first, repairing and leveling, and then vibration rolling. The compacted mixture is then fully watered until saturated, and then the rolling is repeated until the water flows out of the gaps and the graded gravel layer reaches the compaction requirement.
  • the mixing ratio of the crushed stone raw materials is: when the sieve hole size is 50 mm, the crushed stone passing rate is 100wt%, when the sieve hole size is 37 mm, the crushed stone passing rate is 95-100wt%, when the sieve hole size is 25 mm, the crushed stone passing rate is 70-95wt%, when the sieve hole size is 19 mm, the crushed stone passing rate is 55-85wt%, when the sieve hole size is 4.75 mm, the crushed stone passing rate is 30-60wt%, when the sieve hole size is 0.6 mm, the crushed stone passing rate is 12-30wt%, and when the sieve hole size is 0.075 mm, the crushed stone passing rate is 0-8wt%;
  • the weight proportion of crushed stone raw materials passing through the 0.075mm sieve hole in the crushed stone raw materials passing through the 0.6mm sieve hole does not exceed 60%; the weight proportion of needle-shaped and flaky crushed stone raw materials in the crushed stone raw materials with a particle size greater than 4.75mm does not exceed 15%, and the needle-shaped and flaky crushed stone raw materials are defined in the test method in ASTM D 693 standard; the abrasion value of the crushed stone raw materials is tested in accordance with the ASTM C131 test procedure, and the result is not greater than 35%; the sodium sulfate firmness of the crushed stone raw materials is tested in accordance with the ASTM C 88 test procedure, and after 5 test cycles, the loss value is less than 5%.
  • the process of mixing the crushed stone raw materials to obtain the mixture specifically includes: placing the crushed stone raw materials in a mixing station, using the mixing station to forcibly mix the mixture, and adding water during mixing according to the optimal moisture content of the crushed stone raw materials that meet the grading requirements ⁇ 2%, and the optimal moisture content of the crushed stone raw materials that meet the grading requirements is determined by a heavy compaction test.
  • the surface of the underlying layer is first wetted by sprinkling water.
  • the surface of the truck bed of the transport vehicle is first wetted by spraying water.
  • the graded crushed stone layer reaches the compaction requirement, it is also repaired and jointed, and finally accepted.
  • the compaction degree of the graded crushed stone layer is measured by a sand filling method.
  • static compaction is first performed once, followed by repair and leveling, and then vibration rolling is performed four times.
  • the present invention includes at least the following beneficial effects: when graded crushed stone is applied to the airport pavement base, the compaction degree should reach 100%. If it is constructed according to the conventional layered compaction method, its compaction degree is difficult to reach 100%.
  • the saturated water-tight vibration compaction process provided by the present application successfully solves this technical problem. At the same time, since the graded crushed stone is saturated with water during the compaction process, there is no need to consider the quality problems such as looseness and peeling of the base surface caused by excessive surface water loss of the graded crushed stone base during the compaction process.
  • FIG1 is a flow chart of a saturated water-tight vibration process for graded crushed stone according to an embodiment of the present invention
  • FIG2 is a perspective schematic diagram of the pavement of the Hambantota Airport in Sri Lanka according to an embodiment of the present invention
  • FIG3 is a close-up schematic diagram of the pavement of the Hambantota Airport in Sri Lanka according to an embodiment of the present invention.
  • the pavement design of Hambantota Airport in Sri Lanka is based on the AC150/5320-6E specification of the Federal Aviation Administration of the United States "Airport Pavement Design and Evaluation". According to the requirements of the specification, graded crushed stone is used in the airport pavement base, and the compaction degree should reach 100%, and the CBR value should not be less than 100%.
  • graded gravel base is constructed according to the conventional layered compaction method, its compaction degree is difficult to reach 100%. This is the technical difficulty of this construction. After many experiments and demonstrations, the technical research team of the project department finally came up with the saturated watertight compaction method and successfully solved this technical problem.
  • the saturated water-tight vibration construction process of graded crushed stone specifically includes the following steps:
  • Construction commencement report Submit the "Graded gravel base construction commencement report" to the owner. The gravel base construction can only be carried out after approval.
  • the source of aggregates must be approved by the engineer and must be clean, solid, durable crushed stone particles that are roughly the same as the sample. Pebbles and crushed pebbles are not allowed;
  • Aggregates can be mixed with fine sand, stone powder, or other similar binders or fillers approved by other suppliers. The mixture should be uniform and meet the requirements of the technical specifications;
  • the mixture must be capable of being compacted into a dense and stable base and must not contain vegetable matter, clay lumps, easily decomposable or breakable or other harmful matter.
  • the stockpile yard is selected near the mixing station, and a temporary stockpile silo is set up at the mixing station.
  • Raw materials of various specifications in the stockpile silo are separated by isolation walls.
  • a WCB-500 graded gravel mixing station is installed at the mixing site. After the equipment arrives at the site, it is installed and debugged, and calibrated by the measurement department. It can only be used after inspection that all indicators meet the requirements.
  • a loader is configured in the mixing station silo for loading and preparing materials;
  • Transportation equipment 15 dump trucks with a load capacity of more than 15 tons will be equipped according to the mixing capacity and transportation road conditions. The number will be adjusted according to the construction progress and on-site needs;
  • Paving equipment The model of the paving machine brought to the site is DTU95 produced by Sany Heavy Industry;
  • Rolling equipment One 26T single-wheel vibratory roller and one 22T single-wheel vibratory roller, and one small tamping machine are used for construction;
  • a batch of small tools such as shovels, wheelbarrows, wire ropes, etc.
  • Laboratory construction is divided into three aspects, namely: establishment of quality management system for construction site laboratories, laboratory hardware construction, and rational allocation and quality education of personnel.
  • Laboratory quality system including the organizational structure, responsibilities, procedures, processes and resources for implementing quality management.
  • Laboratory technical staff 1 technical supervisor and 8 operators are equipped to ensure the basic needs of grassroots construction and on-site testing.
  • the lower bearing layer to be accepted must meet the specified requirements, and its longitudinal and transverse slopes, flatness, compaction, longitudinal elevation, etc. must meet the assessment requirements, otherwise the lower bearing layer must be reprocessed before the base construction.
  • the surface of the underlying layer Before paving the base layer, the surface of the underlying layer can be appropriately sprinkled with water to moisten the surface according to the site conditions.
  • test section with an area of not less than 300 square meters shall be paved on site approved by the owner's engineer.
  • the shoulder section (between two navigation lights) between runway 2200 and 3000 shall be selected to pave the test section first;
  • the following parameters are determined through the construction of the test section: whether the construction mix ratio of materials is reasonable; the loose paving coefficient of materials; standard construction method; paving speed; method for controlling the moisture content of the mixture; combination of compaction machinery, rolling method and compaction sequence as well as speed and number of passes; coordination and cooperation of mixing, transportation, paving and rolling machinery; inspection method after compaction; length of the daily working section; standardized management and optimized construction organization.
  • the owner's engineer shall be notified 48 hours before the construction of the test area. If the preparation work cannot be completed in time due to bad weather and equipment failure, the owner's engineer shall be notified verbally or in writing to obtain consent.
  • a pile is set up every 10m for leveling measurement, and the guide control line bracket is driven into the paving edge line 50cm away.
  • the position of the guide control line bracket corresponds to the center line pile number.
  • the spacing between the guide control line brackets is 10m.
  • the height of the cross bar of the guide control line bracket is adjusted and set to the elevation of the guide control line during paving.
  • the elevation of the guide control line the top surface elevation of the underlying layer + the loose laying coefficient ⁇ the designed compacted thickness of the graded gravel layer + the fixed value.
  • the fixed value is the height difference between the conductor and the ironing plate of the paving equipment.
  • the materials should be well graded from coarse to fine, and the design batching specifications required in the above table should be strictly followed, and the deviation should be controlled within the allowable range;
  • the percentage of material passing the 0.075 mm sieve must not exceed 60% of the percentage passing the 0.60 mm sieve;
  • the content of needle and flake crushed stone with a particle size greater than 4.75 mm shall not exceed 15% by weight.
  • the test method for distinguishing needle and flake crushed stone shall comply with the definition of ASTM D 693;
  • the loss value should be less than 5% after 5 test cycles;
  • the liquid limit of fine aggregate with a particle size less than 0.42 mm should be no greater than 25 and the plastic limit should be no greater than 4; according to ASTM 2419 test of the sand equivalent value of this particle size level, the test result should be greater than 35%;
  • test sample is a construction mix ratio sample
  • the needle and flake content should be less than 30%.
  • the mixing of graded crushed stone base material adopts the centralized factory mixing method.
  • the mixer is a set of WCB-500 graded crushed stone mixer, with an average output of 500t per hour.
  • the equipment should be fully debugged before mixing.
  • the debugging of the mixing equipment is divided into two steps: the first step is to debug the aggregate gradation, that is, without adding water, determine the mixing ratio of various crushed stones; the second step is to debug the mixture, that is, add water to the crushed stone and adjust the water content to meet the requirements of the design mix ratio.
  • the test personnel Before mixing, the test personnel shall measure the aggregate gradation and aggregate moisture content. If the construction is carried out in the rainy season, the frequency of moisture content measurement shall be increased, and the construction mix ratio and the actual amount of water added during mixing shall be calculated. Considering that the moisture content will be lost during mixing, transportation, paving, shaping, rolling and other processes, the amount of water used for mixing can be appropriately increased according to the weather, transportation distance and construction progress, so that the moisture content of the mixed material after mixing is slightly greater than the optimal moisture content by 0.5-1% (determined by the test). In the morning, when the temperature is low, there is no wind and the transportation distance is short, the moisture content of the mixed material is close to the optimal moisture content.
  • the moisture content of the mixed material should be higher than the optimal moisture content.
  • the materials When mixing the graded crushed stone base mixture, the materials shall be loaded in strict accordance with the mix ratio design requirements approved by the owner's engineer. The materials shall be sent from the silo to the mixing silo via a belt conveyor. At the same time, water shall be added according to the mix ratio requirements. After mixing, the materials shall be sent to the storage silo by a belt conveyor to wait for loading.
  • the mixing quality shall be jointly controlled by the laboratory attendant and the machine operator. The person in charge of each control shall strictly select the aggregate specifications and quantity of each silo according to the mix ratio notice provided by the laboratory.
  • the amount of various aggregates and water used during mixing shall be accurate to ensure that the gradation of the mixture meets the design requirements and that the materials discharged are uniform and there is no separation of coarse and fine materials.
  • the materials When loading the graded crushed stone base mixture, in order to reduce segregation, the materials shall be loaded three times: front, back and middle, and a special person shall be arranged to be responsible for the command.
  • the water content is slightly greater than the optimum water content
  • the graded crushed stone mixture is transported by dump trucks of 15 tons or more. When the transportation distance is long, there is wind or the temperature is high at noon, the mixture on the material truck is covered with tarpaulin to prevent water loss.
  • the transportation capacity is adjusted in time according to the mixer capacity, transportation distance, paving capacity, etc.
  • the transportation vehicles must ensure that there are three vehicles waiting to unload in front of the paver, and no less than three vehicles waiting to load at the mixing station.
  • the number of vehicles, drivers, and driving routes are uniformly implemented the day before paving. According to the production quantity required by the construction section of the front field, sufficient transportation vehicles are equipped to ensure continuous operation of the construction section.
  • the compaction method includes: first static compaction once, repairing and leveling, then vibration rolling 4 times, and then fully watering the rolled mixture until saturation, and then repeating the rolling until the water flows out of the gaps and the graded gravel layer reaches the compaction requirement.
  • the mixture was spread using a DTU95 paver produced by Sany Heavy Industry.
  • the sensor used a steel wire rope to control the elevation and thickness.
  • the surface of the underlying layer was properly sprinkled with water and moistened, and the operation of each part of the paver was checked every day to see if it was normal.
  • the ironing plate was padded with wooden boards so that the elevation of the ironing plate was the loose elevation of the paving layer. To reduce the deformation of the ironing plate, each paver ironing plate must be padded at least three places.
  • the speed of the paver is determined according to the mixing capacity and transportation capacity. It is strictly forbidden to stop the paver to wait for materials, so as to maintain the continuity of paving and improve the flatness.
  • the paving speed of the paver is 1.5-2m/min. When paving the mixture, the minimum paving speed should be 1.5m/min to reduce the phenomenon of stopping to wait for materials.
  • a dedicated person will direct the transport vehicle to stop 20 to 30 cm in front of the paver to prevent collision with the paver.
  • the paver will push the unloading vehicle forward and unload while moving forward.
  • the vehicle cannot brake during unloading.
  • the unloading speed should be coordinated with the paving speed.
  • a dedicated person will direct the unloading.
  • a dedicated person After the paver spreads, a dedicated person shall be assigned to eliminate the segregation of coarse and fine aggregates, promptly remove local coarse aggregate "nests", and fill them with newly mixed materials. If there is too much coarse aggregate, a dedicated person shall be assigned to fill the gaps with newly mixed fine aggregates in a timely manner.
  • the edges of the road surface should be trimmed and shaped, and compacted with relevant tools (such as a shovel) to ensure that the edges are straight, smooth and dense.
  • the joints of the upper and lower layers should be staggered by no less than 3m.
  • the compaction and rolling of the mixture will be carried out by a 26T single steel wheel vibratory roller and a 22T single steel wheel vibratory roller.
  • the rolling length should be 50 to 80 meters.
  • the rolling sections should be clearly layered, with obvious boundary marks and continuous rolling.
  • the principle of static pressure should be followed for both initial and final pressure to reduce deformation and improve surface density and flatness.
  • the rolling sequence is to use a 22T grade roller for static rolling once, weak vibration rolling twice, and strong vibration rolling twice. Then use a sprinkler truck to fully sprinkle water on the compacted mixture until it is saturated. Then use a 26T grade roller to repeat strong vibration rolling until the water flows out of the gaps and the graded gravel layer reaches the compaction requirement. Finally, use a 26T grade roller for static rolling once to make the surface dense and free of wheel marks.
  • Rolling method After paving and forming, the roller is used for rolling.
  • the rolling direction is parallel to the center line of the road.
  • rolling is carried out from the shoulder to the center.
  • rolling is carried out from the inside to the outside, so that the longitudinal extension and the cross slope meet the design requirements.
  • the roller rolls in a step-like manner. At the joint of the two rolling sections, the roller rolls at a 45-degree angle.
  • the wheel tracks overlap by 1/2 of the wheel width.
  • the rear wheel must exceed the joint of the two sections. When the rear wheel rolls the full width of the road surface, it is considered one pass. Rolling is carried out until the required compaction degree and no wheel tracks are left.
  • the rolling speed of the roller is preferably 1st gear for the first two passes, and 2nd gear can be used afterwards. High-speed rolling is absolutely not allowed.
  • Rolling procedure static pressure ⁇ weak vibration ⁇ strong vibration ⁇ static pressure. Record the number of rolling times on site. Both sides of the road surface should be rolled 1 to 2 more times. The speed of the roller should be 1.5 to 1.7 km/h during steady pressure, 1.8 to 2.2 km/h during vibration pressure, and 1.5 to 1.7 km/h during final pressure.
  • transverse joint treatment the graded crushed stone base mixture that is not compacted on the day of the paver can be rolled together with the mixture to be paved the next day, but attention should be paid to the moisture content of this part of the mixture.
  • the moisture content is low, appropriate watering should be added to make its moisture content meet the specified requirements.
  • Longitudinal joint treatment When rolling the longitudinal joint, leave about 20cm unrolled as the control elevation surface for the next paver to move. At the same time, the joint should overlap about 5cm. When the paver has paved the entire designed width of the working surface, the next rolling surface can be rolled. If the machine is shut down due to special circumstances, the entire paving surface should be rolled (including the reserved 20cm). When paving is restarted, the uncompacted and loose materials at the longitudinal joint should be shoveled away first, and the longitudinal joint should be shoveled into a vertical section. Then, water should be sprinkled to moisten the joint before new paving, leveling, and rolling work.
  • Treatment of the interface When paving at the interface, first spread 20cm more on one surface. After leveling and compacting, scrape off the excess material on the interface and shovel the interface into a vertical section. Then sprinkle water to moisten the interface before paving, leveling and rolling the other surface.
  • the compaction degree of the graded crushed stone base of the pavement of Sri Lanka's Hambantota Airport reached 100%, and the CBR value reached 120%.
  • the surface of the base was flat and dense, without looseness or segregation, fully meeting the requirements of the US Federal Aviation Administration's "Airport Pavement Design and Evaluation" AC 150/5320-6E specification.
  • graded crushed stone Because graded crushed stone has micro-permeability, on the one hand, it can continuously discharge the infiltrated water within a certain period of time, so that it will not accumulate on the interface of the structural layer, and maintain the intact connection between the graded crushed stone base and the asphalt layer of the airport pavement above it; on the other hand, graded crushed stone will not have strong water permeability, so it will not cause a large amount of water to quickly infiltrate the roadbed, causing the roadbed soil to quickly reach supersaturation and soften, and quickly reduce the bearing capacity of the airport runway.
  • the shrinkage coefficient of graded crushed stone is extremely small, almost zero, which can avoid the reflection cracks of the asphalt surface layer caused by the shrinkage of the semi-rigid base.
  • graded crushed stone is a granular body, which does not transmit stress and displacement by itself. Therefore, it can dissipate and absorb the high stress and strain at the crack tip caused by changes in environmental factors, especially load and temperature changes, and completely absorb the strain energy at the crack tip under the action of external loads, eliminating the possibility of crack expansion in the asphalt surface layer.
  • graded crushed stone has sufficient compressive and shear strength, meeting the requirements of being a pavement load-bearing layer.
  • the mixture consistent with the above embodiment was used for conventional moisture content control and layered compaction construction, that is, layered paving and rolling, and the mixture was controlled at the optimal moisture content during each layer rolling.
  • the final graded crushed stone base compaction degree can only reach 98% at most, which is difficult to meet the requirements of the Federal Aviation Administration's "Airport Pavement Design and Evaluation" AC 150/5320-6E specification.

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Road Paving Structures (AREA)

Abstract

A saturated-water vibrating compaction construction process for graded crushed stone, comprising: carrying out checking and accepting and finishing on a base course; carrying out mixing proportion design and tests on graded crushed stone so as to determine a mixing proportion, the coefficient of loose paving and a paving method; performing survey and setting out on the base course which has been qualified in checking and accepting; preparing crushed-stone raw materials according to the mixing proportion determined by the tests, adding the crushed-stone raw materials to a mixing machine and mixing same to obtain a mixture; and paving the mixture on the surface of the base course according to the coefficient of loose paving and the paving method which are determined by the tests, and compacting same, wherein a compacting method comprises first carrying out static compaction, repairing and leveling, then carrying out vibration rolling, fully sprinkling water to the rolled mixture until saturation, and repeatedly rolling same until the water flows away from gaps and said graded crushed-stone layer satisfies the requirement of the degree of compaction. Therefore, the process can enable graded crushed stone to be applied to airport road surface courses, the degree of compaction reaching 100%, and the airport road surface courses having flat and compact surfaces and being free of loosening and segregation.

Description

级配碎石饱和水密振实施工工艺Construction technology of graded crushed stone saturated watertight vibration 技术领域Technical Field
本发明涉及道路基层施工技术领域。更具体地说,本发明涉及一种级配碎石饱和水密振实施工工艺。The present invention relates to the technical field of road base construction, and more specifically to a graded crushed stone saturated water-tight vibration construction process.
背景技术Background technique
道路、机场跑道、堆场等道面结构的基层通常有级配碎石、水泥稳定碎石、水泥稳定土等形式。目前,针对机场跑道,在国内通常使用水泥稳定碎石作为道面结构基层,而级配碎石基层相比于水泥稳定碎石基层,其造价更低,且施工时不存在水泥初凝的限制,其碾压和做面的难度都远低于水泥稳定碎石基层,因此仍然在较多地方应用。The base of pavement structures such as roads, airport runways, and storage yards usually have graded crushed stone, cement stabilized crushed stone, cement stabilized soil, etc. At present, for airport runways, cement stabilized crushed stone is usually used as the pavement structure base in China. Compared with the cement stabilized crushed stone base, the graded crushed stone base has a lower cost and is not limited by the initial setting of cement during construction. The difficulty of rolling and surface preparation is much lower than that of cement stabilized crushed stone base, so it is still used in many places.
但是,目前级配碎石基层压实施工时如果按照常规的含水量控制、分层压实法施工,其压实度很难接近或达到100%,且在级配碎石施工当中经常出现压实度不合格、表面松散、脱皮等质量问题,而松散的表面对后期的扫面和透油施工影响较大,难以满足重载作用下机场跑道的设计要求。However, if the graded crushed stone base layer is compacted according to the conventional moisture content control and layered compaction method, its compaction degree is difficult to approach or reach 100%, and quality problems such as unqualified compaction degree, loose surface, peeling, etc. often occur during the construction of graded crushed stone. The loose surface has a great influence on the subsequent sweeping and oil penetration construction, and it is difficult to meet the design requirements of the airport runway under heavy load.
发明内容Summary of the invention
本发明的一个目的是解决至少上述问题,并提供至少后面将说明的优点。An object of the present invention is to solve at least the above problems and to provide at least the advantages which will be described hereinafter.
本发明还有一个目的是提供一种级配碎石饱和水密振实施工工艺,能使级配碎石应用于机场道面基层,压实度达到100%,同时机场道面基层表面平整密实,无松散,无离析。Another object of the present invention is to provide a construction process for saturated water-tight vibration of graded crushed stone, which can enable the graded crushed stone to be applied to the airport pavement base with a compaction degree of 100%. At the same time, the surface of the airport pavement base is flat and dense without looseness or segregation.
为了实现根据本发明的这些目的和其它优点,提供了一种级配碎石饱和水密振实施工工艺,其包括:In order to achieve these purposes and other advantages according to the present invention, a saturated water-tight vibration construction process for graded crushed stone is provided, which comprises:
下承层验收、修整;Acceptance and repair of the underlying layer;
对级配碎石进行配合比设计和试验,以确定配合比、松铺系数、摊铺方法;Carry out mix design and testing of graded crushed stone to determine mix ratio, loose paving coefficient and paving method;
在验收合格的下承层上测量放样;Measure and set out on the qualified underlying layer;
按试验确定的配合比准备碎石原料,将碎石原料置于拌和机械中进行拌和得到混合料;Prepare crushed stone raw materials according to the mix ratio determined by the test, and place the crushed stone raw materials in a mixing machine for mixing to obtain a mixed material;
按试验确定的松铺系数和摊铺方法,将混合料摊铺在下承层表面,再压实,其中,压实方法包括:先静压,修补找平,再振动碾压,然后对碾压后的混合料充分洒水至饱和,再重复碾压直到水分从空隙中流走,且级配碎石层达到压实度要求。According to the loose paving coefficient and paving method determined by the test, the mixture is spread on the surface of the underlying layer and then compacted. The compaction method includes: static pressing first, repairing and leveling, and then vibration rolling. The compacted mixture is then fully watered until saturated, and then the rolling is repeated until the water flows out of the gaps and the graded gravel layer reaches the compaction requirement.
优选的是,所述级配碎石层应用于机场道面基层时,碎石原料的配合比为:筛孔大小为50mm时碎石通过率为100wt%,筛孔大小为37mm时碎石通过率为95~100wt%,筛孔大小为25mm时碎石通过率为70~95wt%,筛孔大小为19mm时碎石通过率为55~85wt%,筛孔大小为4.75mm时碎石通过率为30~60wt%,筛孔大小为0.6mm时碎石通过率为12~30wt%,筛孔大小为0.075mm时碎石通过率为0~8wt%;Preferably, when the graded crushed stone layer is applied to the airport pavement base, the mixing ratio of the crushed stone raw materials is: when the sieve hole size is 50 mm, the crushed stone passing rate is 100wt%, when the sieve hole size is 37 mm, the crushed stone passing rate is 95-100wt%, when the sieve hole size is 25 mm, the crushed stone passing rate is 70-95wt%, when the sieve hole size is 19 mm, the crushed stone passing rate is 55-85wt%, when the sieve hole size is 4.75 mm, the crushed stone passing rate is 30-60wt%, when the sieve hole size is 0.6 mm, the crushed stone passing rate is 12-30wt%, and when the sieve hole size is 0.075 mm, the crushed stone passing rate is 0-8wt%;
其中,通过0.075mm筛孔的碎石原料在通过0.6mm筛孔的碎石原料中的重量占比不超过60%;粒径大于4.75mm的碎石原料中针状和片状碎石原料的重量占比不超过15%,针状和片状碎石原料按ASTM D 693标准中的试验方法定义;按照ASTM C131试验规程测试碎石原料的磨耗值,其结果不大于35%;按照ASTM C 88试验规程测试碎石原料的硫酸钠坚固性,经过5个试验循环后,其损失值小于5%。Among them, the weight proportion of crushed stone raw materials passing through the 0.075mm sieve hole in the crushed stone raw materials passing through the 0.6mm sieve hole does not exceed 60%; the weight proportion of needle-shaped and flaky crushed stone raw materials in the crushed stone raw materials with a particle size greater than 4.75mm does not exceed 15%, and the needle-shaped and flaky crushed stone raw materials are defined in the test method in ASTM D 693 standard; the abrasion value of the crushed stone raw materials is tested in accordance with the ASTM C131 test procedure, and the result is not greater than 35%; the sodium sulfate firmness of the crushed stone raw materials is tested in accordance with the ASTM C 88 test procedure, and after 5 test cycles, the loss value is less than 5%.
优选的是,将碎石原料拌和得到混合料的过程具体包括:将碎石原料置于搅拌站中,采用搅拌站强制拌合混合料,拌和时按照满足所述级配要求的碎石原料的最佳含水量±2%加水,满足所述级配要求的碎石原料的最佳含水量采用重型击实实验进行确定。Preferably, the process of mixing the crushed stone raw materials to obtain the mixture specifically includes: placing the crushed stone raw materials in a mixing station, using the mixing station to forcibly mix the mixture, and adding water during mixing according to the optimal moisture content of the crushed stone raw materials that meet the grading requirements ±2%, and the optimal moisture content of the crushed stone raw materials that meet the grading requirements is determined by a heavy compaction test.
优选的是,将混合料摊铺在下承层表面前,先对下承层表面洒水进行湿润。Preferably, before spreading the mixture on the surface of the underlying layer, the surface of the underlying layer is first wetted by sprinkling water.
优选的是,将混合料由搅拌站运输至摊铺施工现场前,先对运输车辆车斗表面洒水进行湿润。Preferably, before the mixed material is transported from the mixing station to the paving construction site, the surface of the truck bed of the transport vehicle is first wetted by spraying water.
优选的是,在验收合格的下承层上测量放样的过程包括:每隔10m设一桩,进行水准测量,在铺筑边线外50cm处打入导向控制线支架,导向控制线支架位置对应中线桩号,导向控制线支架间距为10m,根据下承层顶面标高、设计厚度、试验得出的松铺系数及固定值,调整导向控制线支架横杆高度,设定为铺筑时导向控制线标高,导向控制线标高=下承层顶面高程+松铺系数×级配碎石层设计压实厚度+固定值,固定值为导线与摊铺设备的熨平板高差。Preferably, the process of measurement and layout on the qualified underlying layer includes: setting a pile every 10m, conducting leveling measurement, driving a guide control line bracket 50cm outside the paving edge line, the position of the guide control line bracket corresponds to the center line pile number, the spacing between the guide control line brackets is 10m, and adjusting the height of the cross bar of the guide control line bracket according to the elevation of the top surface of the underlying layer, the design thickness, the loose laying coefficient obtained from the test and the fixed value, and setting it to the elevation of the guide control line during paving, the elevation of the guide control line = elevation of the top surface of the underlying layer + loose laying coefficient × designed compacted thickness of the graded gravel layer + fixed value, and the fixed value is the height difference between the conductor and the ironing plate of the paving equipment.
优选的是,级配碎石层达到压实度要求后还进行修补和接缝处理,最后验收。Preferably, after the graded crushed stone layer reaches the compaction requirement, it is also repaired and jointed, and finally accepted.
优选的是,级配碎石层的压实度采用灌砂法测量得到。Preferably, the compaction degree of the graded crushed stone layer is measured by a sand filling method.
优选的是,所述压实的方法中,先静压1遍,修补找平,再振动碾压4遍。Preferably, in the compaction method, static compaction is first performed once, followed by repair and leveling, and then vibration rolling is performed four times.
本发明至少包括以下有益效果:级配碎石应用于机场道面基层时,压实度应当达到100%,如果按照常规分层压实法施工,其压实度很难达到100%,而本申请提供的饱和水密振实工艺,成功解决了这一技术难题,同时由于在压实过程中,级配碎石中含水饱和, 因此无需考虑级配碎石基层在压实过程中表面失水过多而导致基层表面松散、脱皮等质量问题。The present invention includes at least the following beneficial effects: when graded crushed stone is applied to the airport pavement base, the compaction degree should reach 100%. If it is constructed according to the conventional layered compaction method, its compaction degree is difficult to reach 100%. The saturated water-tight vibration compaction process provided by the present application successfully solves this technical problem. At the same time, since the graded crushed stone is saturated with water during the compaction process, there is no need to consider the quality problems such as looseness and peeling of the base surface caused by excessive surface water loss of the graded crushed stone base during the compaction process.
本发明的其它优点、目标和特征将部分通过下面的说明体现,部分还将通过对本发明的研究和实践而为本领域的技术人员所理解。Other advantages, objectives and features of the present invention will be embodied in part through the following description, and in part will be understood by those skilled in the art through study and practice of the present invention.
附图说明BRIEF DESCRIPTION OF THE DRAWINGS
图1为本发明实施例所述级配碎石饱和水密振实施工工艺的流程图;FIG1 is a flow chart of a saturated water-tight vibration process for graded crushed stone according to an embodiment of the present invention;
图2为本发明实施例所述斯里兰卡汉班托塔机场道面的远景示意图;FIG2 is a perspective schematic diagram of the pavement of the Hambantota Airport in Sri Lanka according to an embodiment of the present invention;
图3为本发明实施例所述斯里兰卡汉班托塔机场道面的近景示意图。FIG3 is a close-up schematic diagram of the pavement of the Hambantota Airport in Sri Lanka according to an embodiment of the present invention.
具体实施方式Detailed ways
下面结合附图对本发明做进一步的详细说明,以令本领域技术人员参照说明书文字能够据以实施。The present invention will be further described in detail below in conjunction with the accompanying drawings so that those skilled in the art can implement the invention with reference to the description.
需要说明的是,下述实施方案中所述实验方法,如无特殊说明,均为常规方法,所述试剂和材料,如无特殊说明,均可从商业途径获得;在本发明的描述中,术语“横向”、“纵向”、“上”、“下”、“前”、“后”、“左”、“右”、“竖直”、“水平”、“顶”、“底”、“内”、“外”等指示的方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述本发明和简化描述,并不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本发明的限制。It should be noted that the experimental methods described in the following embodiments are conventional methods unless otherwise specified, and the reagents and materials are commercially available unless otherwise specified; in the description of the present invention, the terms "lateral", "longitudinal", "upper", "lower", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", etc., indicating directions or positional relationships, are based on the directions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore cannot be understood as a limitation on the present invention.
下面以斯里兰卡汉班托塔机场道面基层为例来说明所述级配碎石饱和水密振实施工工艺,斯里兰卡汉班托塔机场道面设计依据美国联邦航空局《机场道面设计与评价》AC150/5320-6E规范,根据规范要求,级配碎石应用于机场道面基层,压实度应达到100%,同时CBR值不应小于100%。The following takes the pavement base of Hambantota Airport in Sri Lanka as an example to illustrate the graded crushed stone saturated watertight vibration construction process. The pavement design of Hambantota Airport in Sri Lanka is based on the AC150/5320-6E specification of the Federal Aviation Administration of the United States "Airport Pavement Design and Evaluation". According to the requirements of the specification, graded crushed stone is used in the airport pavement base, and the compaction degree should reach 100%, and the CBR value should not be less than 100%.
级配碎石基层如果按照常规分层压实法施工,其压实度很难达到100%,这是该项施工的技术难点,项目部技术研究小组经过多次试验论证,终于得出了饱和水密压实法,成功解决了这一技术难题。If the graded gravel base is constructed according to the conventional layered compaction method, its compaction degree is difficult to reach 100%. This is the technical difficulty of this construction. After many experiments and demonstrations, the technical research team of the project department finally came up with the saturated watertight compaction method and successfully solved this technical problem.
如图1所示,所述级配碎石饱和水密振实施工工艺,具体包括以下步骤:As shown in FIG1 , the saturated water-tight vibration construction process of graded crushed stone specifically includes the following steps:
S1、施工准备;S1. Construction preparation;
具体包括:Specifically include:
1、技术及资料准备;1. Technical and data preparation;
(1)编制施工方案并获业主审批;(1) Prepare a construction plan and obtain approval from the owner;
(2)组织人员进行详细的培训交底;(2) Organize personnel to conduct detailed training and briefing;
(3)开工报告:向业主报送《级配碎石基层开工报告》,经同意后方可进行碎石基层施工。(3) Construction commencement report: Submit the "Graded gravel base construction commencement report" to the owner. The gravel base construction can only be carried out after approval.
2、设备及物资准备;2. Preparation of equipment and materials;
(2.1)材料试验准备;(2.1) Material test preparation;
(一)熟悉设计要求及验收标准和施工规范,组织全体施工人员进行工艺操作和质量标准的技术交底,调试和熟悉前台和后台的各种机械操作。(1) Be familiar with design requirements, acceptance standards and construction specifications, organize all construction personnel to conduct technical briefings on process operations and quality standards, and debug and familiarize themselves with various mechanical operations at the front and back ends.
(二)按照设计和规范要求选择合格的碎石并及时取样做规定的试验和向业主报验,具体要求如下:(II) Select qualified crushed stone in accordance with the design and specification requirements, take samples in time for the required tests and report to the owner for inspection. The specific requirements are as follows:
a骨料的来源要经得工程师审核统一,含料要为干净,坚固,耐用的轧碎石块颗粒,且跟样品大致相同.不允许使用卵石和轧碎卵石;a. The source of aggregates must be approved by the engineer and must be clean, solid, durable crushed stone particles that are roughly the same as the sample. Pebbles and crushed pebbles are not allowed;
b骨料可以和细沙,石粉,或和其他来料经得批准的类似的粘结料或填料混合.混料要均匀且符合技术规格书的要求;b. Aggregates can be mixed with fine sand, stone powder, or other similar binders or fillers approved by other suppliers. The mixture should be uniform and meet the requirements of the technical specifications;
c混合料要能够被压实成密实稳定的基层,且不能含有植物质,粘土结块,易分解或破碎或其他有害物质。c. The mixture must be capable of being compacted into a dense and stable base and must not contain vegetable matter, clay lumps, easily decomposable or breakable or other harmful matter.
(2.2)堆料场地准备;(2.2) Preparation of stockpile site;
堆料场选择在拌和站附近,拌和站设立临时堆料仓,堆料仓内各种规格的原材料均采用隔离墙隔开。The stockpile yard is selected near the mixing station, and a temporary stockpile silo is set up at the mixing station. Raw materials of various specifications in the stockpile silo are separated by isolation walls.
(2.3)机械设备准备;(2.3) Preparation of mechanical equipment;
(一)大型设备;(1) Large equipment;
1)拌和设备:在拌合场地安装一台型号为WCB-500的级配碎石拌和站,设备进场后组织安装、调试,并经计量部门进行了标定,经检验各项指标能符合要求方可使用。在拌和站料仓配置一台装载机上料和备料用;1) Mixing equipment: A WCB-500 graded gravel mixing station is installed at the mixing site. After the equipment arrives at the site, it is installed and debugged, and calibrated by the measurement department. It can only be used after inspection that all indicators meet the requirements. A loader is configured in the mixing station silo for loading and preparing materials;
2)运输设备:根据拌和能力及运输道路路况配备载重在15t以上的自卸车15辆,其数量将根据施工进度及现场需求进行调整;2) Transportation equipment: 15 dump trucks with a load capacity of more than 15 tons will be equipped according to the mixing capacity and transportation road conditions. The number will be adjusted according to the construction progress and on-site needs;
3)摊铺设备:进场三一重工产的型号为DTU95摊铺机一台;3) Paving equipment: The model of the paving machine brought to the site is DTU95 produced by Sany Heavy Industry;
4)碾压设备:施工采用一台26T级单钢轮振动压路机和一台22T级单钢轮振动压路机,小型打夯机一台;4) Rolling equipment: One 26T single-wheel vibratory roller and one 22T single-wheel vibratory roller, and one small tamping machine are used for construction;
5)洒水设备:两台洒水车,根据情况需要时再增加;5) Sprinkler equipment: two sprinkler trucks, with more to be added as needed;
6)其他机械设备:平地机一台,主要进行下承层修补作业。发电机一台,搅拌站备用发电设备;6) Other mechanical equipment: one land grader, mainly used for repairing the underlying layer. One generator, backup power generation equipment for the mixing station;
以上机械操作人员均持有有效操作证,并对各自机械、车辆的工作性能做到心中有数。混合料试拌前,出具相关证书,经业主工程师对拌和楼及机械设备的工作性能进行调试验证确认,确保混合料的集料级配、含水量准确性符合技术规范的要求,使所有工序处于受控状态。The above machine operators all hold valid operation certificates and are fully aware of the working performance of their own machines and vehicles. Before the trial mixing of the mixture, relevant certificates are issued, and the owner's engineer will debug and verify the working performance of the mixing plant and mechanical equipment to ensure that the aggregate gradation and moisture content of the mixture meet the requirements of the technical specifications, so that all processes are under control.
(二)小型设备;(ii) small equipment;
铁锹、手推车、钢丝绳等小型机具一批。A batch of small tools such as shovels, wheelbarrows, wire ropes, etc.
(2.3)工地实验室准备;(2.3) Site laboratory preparation;
试验室建设分三个内容,即:工地试验室质量管理体系建立、试验室硬件建设及人员的合理配备与素质教育。Laboratory construction is divided into three aspects, namely: establishment of quality management system for construction site laboratories, laboratory hardware construction, and rational allocation and quality education of personnel.
1)试验室质量体系:包括实施质量管理的组织机构、职责、程序、过程和资源。1) Laboratory quality system: including the organizational structure, responsibilities, procedures, processes and resources for implementing quality management.
2)试验室硬件建设:包括试验仪器配备精良程度、设备仪器的数量及质量。2) Laboratory hardware construction: including the degree of sophistication of test instruments, the quantity and quality of equipment and instruments.
3)试验室技术人员的配备:配备1名技术主管,8名操作工,以确保基层施工及现场检测工作的基本需要。3) Laboratory technical staff: 1 technical supervisor and 8 operators are equipped to ensure the basic needs of grassroots construction and on-site testing.
(2.4)测量准备;(2.4) Measurement preparation;
1)认真对照图纸,再实行放样工作;1) Carefully check the drawings before carrying out the layout work;
2)测量人员要持证上岗,仪器要事先标定,放样前再次检校仪器的工作性能;2) Surveyors must be certified, instruments must be calibrated in advance, and the working performance of the instruments must be recalibrated before setting out;
3)对测量控制网进行联测,并将复测成果上报业主工程师认可;3) Conduct joint testing of the measurement and control network and submit the retest results to the owner’s engineer for approval;
4)对路中线及路边线进行放样,放样后必须再次复核测量成果,所测的测量成果要保证准确无误;这些点作为以后基层的控制点;4) Stake out the road centerline and roadside line. After staking out, the measurement results must be reviewed again to ensure that the measurement results are accurate; these points will serve as control points for the base layer in the future;
5)在最后一层碎石摊铺前应再做一次联合测量。5) Another joint measurement should be made before the last layer of gravel is laid.
(2.5)现场准备工作;(2.5) Site preparation;
(一)下承层的准备;(1) Preparation of underlying strata;
积极做好下承层的验收、修整工作,为基层施工提供良好的现场空间,同时注意以下几点。Actively carry out the acceptance and repair work of the underlying layer to provide a good on-site space for the base construction, and pay attention to the following points.
1)验收的下承层必须符合规定要求,其纵、横坡度、平整度、压实度、纵断高程等满足评定要求,否则基层施工前必须对下承层重新处理。1) The lower bearing layer to be accepted must meet the specified requirements, and its longitudinal and transverse slopes, flatness, compaction, longitudinal elevation, etc. must meet the assessment requirements, otherwise the lower bearing layer must be reprocessed before the base construction.
2)级配碎石混合料上路前,对下承层做最后一次检查,将现场工作面存在的浮土、杂物清除干净,并保持平整。2) Before the graded gravel mixture is put on the road, make a final inspection of the underlying layer, remove all loose soil and debris on the on-site working surface, and keep it flat.
3)对出现有坑洞的下承层,先用相同的材料仔细填补和压实,松散处应耙松并补添相同材料拌和、整形洒水并重新压实,使之达到压实度要求。3) For the underlying layer with holes, first fill and compact it carefully with the same material. The loose areas should be loosened and supplemented with the same material, mixed, shaped and watered, and re-compacted to meet the compaction requirements.
4)在基层摊铺前,根据现场情况可对下承层表面适当洒水,使其表面润湿。4) Before paving the base layer, the surface of the underlying layer can be appropriately sprinkled with water to moisten the surface according to the site conditions.
5)在道面施工时,高填方路堤可能发生沉降,必须对下承层做好沉降观测工作。5) During road surface construction, high fill embankments may undergo settlement, and settlement observations must be made on the underlying layers.
(二)临时道路;(2) Temporary roads;
做好临时道路修整及日常维护。Carry out temporary road repairs and daily maintenance.
(三)临时排水系统;(3) Temporary drainage system;
做好临时排水沟等排水设施,完善临时排水系统。防止雨水浸泡级配碎石工作面。Make good temporary drainage ditch and other drainage facilities, improve the temporary drainage system, and prevent rainwater from soaking the graded gravel working surface.
S2、试验段施工;S2, construction of test section;
1)试验段位置;1) Test section location;
级配碎石基层正式施工10天前,在业主工程师批准的现场试铺一段面积不小于300平方米的试验段。在跑道2200~3000之间选择道肩部分(两个助航灯之间)先铺筑试验段;10 days before the formal construction of the graded crushed stone base, a test section with an area of not less than 300 square meters shall be paved on site approved by the owner's engineer. The shoulder section (between two navigation lights) between runway 2200 and 3000 shall be selected to pave the test section first;
2)碾压试验;2) rolling test;
先按照层厚20cm,松铺系数1.25进行试验,可在试验中再进行优化调整,用灌砂法进行压实度检测,并记录各项原始数据,直到压实度满足相应压实标准。First, test with layer thickness of 20cm and loose laying coefficient of 1.25. Optimization and adjustment can be made during the test. Compactness test can be carried out by sand injection method, and various original data can be recorded until the compaction meets the corresponding compaction standard.
3)试验成果;3) Experimental results;
通过试验段的施工确定如下参数:材料的施工配合比例是否合理;材料的松铺系数;标准的施工方法;摊铺速度;混合料含水率的控制方法;压实机械的组合方式、碾压方法和压实顺序以及速度和遍数;拌和、运输、摊铺和碾压机具的协调和配合;压实后的检验方法;每天作业段的长度;标准化管理和优化施工组织。The following parameters are determined through the construction of the test section: whether the construction mix ratio of materials is reasonable; the loose paving coefficient of materials; standard construction method; paving speed; method for controlling the moisture content of the mixture; combination of compaction machinery, rolling method and compaction sequence as well as speed and number of passes; coordination and cooperation of mixing, transportation, paving and rolling machinery; inspection method after compaction; length of the daily working section; standardized management and optimized construction organization.
4)试验时间;4) Test time;
试验区施工前48小时通知业主工程师。如遇到不良天气和设备故障,准备工作无法及时完成,应口头或书面通知业主工程,征得同意。The owner's engineer shall be notified 48 hours before the construction of the test area. If the preparation work cannot be completed in time due to bad weather and equipment failure, the owner's engineer shall be notified verbally or in writing to obtain consent.
S3、在验收合格的下承层上测量放样;S3. Measure and set out on the qualified underlying layer;
每隔10m设一桩,进行水准测量,在铺筑边线外50cm处打入导向控制线支架,导向控制线支架位置对应中线桩号,导向控制线支架间距为10m,根据下承层顶面标高、设计厚度、试验得出的松铺系数及固定值(10cm),调整导向控制线支架横杆高度,设定为铺筑时导向控制线标高,导向控制线标高=下承层顶面高程+松铺系数×级配碎石层设计压实厚度+固定值,固定值为导线与摊铺设备的熨平板高差。A pile is set up every 10m for leveling measurement, and the guide control line bracket is driven into the paving edge line 50cm away. The position of the guide control line bracket corresponds to the center line pile number. The spacing between the guide control line brackets is 10m. According to the top surface elevation of the underlying layer, the design thickness, the loose laying coefficient obtained from the test and the fixed value (10cm), the height of the cross bar of the guide control line bracket is adjusted and set to the elevation of the guide control line during paving. The elevation of the guide control line = the top surface elevation of the underlying layer + the loose laying coefficient × the designed compacted thickness of the graded gravel layer + the fixed value. The fixed value is the height difference between the conductor and the ironing plate of the paving equipment.
S4、按试验确定的配合比准备碎石原料,将碎石原料置于拌和机械中进行拌和得到混合料;S4. Prepare crushed stone raw materials according to the mix ratio determined by the test, and place the crushed stone raw materials in a mixing machine for mixing to obtain a mixed material;
(1)碎石基层级配要求如下表所示:(1) The requirements for the gradation of the crushed stone base are shown in the following table:
Figure PCTCN2022142583-appb-000001
Figure PCTCN2022142583-appb-000001
材料从粗到细要分级良好,严格按照上表要求的设计配料规格来实施,偏差控制在允许的范围之内;The materials should be well graded from coarse to fine, and the design batching specifications required in the above table should be strictly followed, and the deviation should be controlled within the allowable range;
通过0.075毫米筛的材料百分比不能超过通过0.60毫米筛百分比的60%;The percentage of material passing the 0.075 mm sieve must not exceed 60% of the percentage passing the 0.60 mm sieve;
碎石粒径大于4.75mm级别的碎石针、片状含量不得超过重量的15%。针、片状的区别试验方法应遵守ASTM D 693的定义;The content of needle and flake crushed stone with a particle size greater than 4.75 mm shall not exceed 15% by weight. The test method for distinguishing needle and flake crushed stone shall comply with the definition of ASTM D 693;
如按照ASTM C131试验规程测试碎石磨耗值,其结果不得大于35%;If the gravel abrasion value is tested according to the ASTM C131 test procedure, the result shall not be greater than 35%;
如按照ASTM C 88试验规程测试碎石硫酸钠坚固性,经过5个试验循环后,其损失 值应该小于5%;If the sodium sulfate strength of crushed stone is tested according to ASTM C 88 test procedure, the loss value should be less than 5% after 5 test cycles;
如按照ASTM D 4318试验规程测试,粒径小于0.42mm的细集料液限应该不大于25和塑限不大于4;根据ASTM的2419测试该粒径级别的砂当量值,试验结果应该大于35%;If tested according to ASTM D 4318 test procedure, the liquid limit of fine aggregate with a particle size less than 0.42 mm should be no greater than 25 and the plastic limit should be no greater than 4; according to ASTM 2419 test of the sand equivalent value of this particle size level, the test result should be greater than 35%;
根据试验规程ASTM 1833,测试4天饱水试验样本的CBR值,结果不小于100%。试验样本为施工配合比样本;According to the test procedure ASTM 1833, the CBR value of the 4-day saturated test sample is tested, and the result is not less than 100%. The test sample is a construction mix ratio sample;
根据试验规程ASTM D 4791试验要求,针、片状含量应小于30%。According to the test requirements of ASTM D 4791, the needle and flake content should be less than 30%.
(2)拌和(2) Mixing
(一)级配碎石基层混合料的拌和采用集中厂拌法,拌和机为一套WCB-500型级配碎石拌和机,平均每小时出料分别为500t。拌和前应对设备进行充分调试,拌和设备的调试分两步:第一步是对集料级配的调试,即不加入水,确定各种碎石的配合比例;第二步是混合料的调试,即在碎石中加入水,调整含水量,达到设计配合比的要求。(I) The mixing of graded crushed stone base material adopts the centralized factory mixing method. The mixer is a set of WCB-500 graded crushed stone mixer, with an average output of 500t per hour. The equipment should be fully debugged before mixing. The debugging of the mixing equipment is divided into two steps: the first step is to debug the aggregate gradation, that is, without adding water, determine the mixing ratio of various crushed stones; the second step is to debug the mixture, that is, add water to the crushed stone and adjust the water content to meet the requirements of the design mix ratio.
拌和前试验人员测定集料的级配和集料含水量,若在雨季施工,要增加含水量的测定频率,计算施工配合比和拌和时实际的加水量,考虑到拌和、运输、摊铺、整形、碾压等过程含水量会损失,故在拌和时,可根据天气、运距及施工进度适当提高拌和用水量,使拌和后混合料含水量略大于最佳含水量0.5~1%(具体由试验确定)。早上气温较低、无风、运距近的情况下,混合料含水量接近最佳含水量。中午气温高、有风、运距远的情况下,混合料的含水量要高于最佳含水量。实施拌和时要做到,后场各项准备工作和前场的各项准备工作就绪后,才可以开始拌和生产。Before mixing, the test personnel shall measure the aggregate gradation and aggregate moisture content. If the construction is carried out in the rainy season, the frequency of moisture content measurement shall be increased, and the construction mix ratio and the actual amount of water added during mixing shall be calculated. Considering that the moisture content will be lost during mixing, transportation, paving, shaping, rolling and other processes, the amount of water used for mixing can be appropriately increased according to the weather, transportation distance and construction progress, so that the moisture content of the mixed material after mixing is slightly greater than the optimal moisture content by 0.5-1% (determined by the test). In the morning, when the temperature is low, there is no wind and the transportation distance is short, the moisture content of the mixed material is close to the optimal moisture content. At noon, when the temperature is high, there is wind and the transportation distance is long, the moisture content of the mixed material should be higher than the optimal moisture content. When implementing mixing, it is necessary to ensure that all preparations in the back field and the front field are ready before starting mixing production.
(二)级配碎石基层混合料在拌和时,严格按照业主工程师批准的配合比设计要求进行上料,由料仓经皮带输送机送入搅拌仓内,同时按照配合比要求,添加水,经搅拌后由皮带输送机送入储料仓等待装料。拌和质量由试验室值班员和机械操作手共同控制,各控制负责人严格按照试验室提供的配合比通知单选用各料仓集料规格和数量,拌和时各种集料、用水量要准确,以保证混合料的级配符合设计要求,保证出场的料均匀一致,无粗细料分离现象。级配碎石基层混合料装车时,为减轻离析现象,装车时分前、后、中三次装料,并安排有专人负责指挥。(II) When mixing the graded crushed stone base mixture, the materials shall be loaded in strict accordance with the mix ratio design requirements approved by the owner's engineer. The materials shall be sent from the silo to the mixing silo via a belt conveyor. At the same time, water shall be added according to the mix ratio requirements. After mixing, the materials shall be sent to the storage silo by a belt conveyor to wait for loading. The mixing quality shall be jointly controlled by the laboratory attendant and the machine operator. The person in charge of each control shall strictly select the aggregate specifications and quantity of each silo according to the mix ratio notice provided by the laboratory. The amount of various aggregates and water used during mixing shall be accurate to ensure that the gradation of the mixture meets the design requirements and that the materials discharged are uniform and there is no separation of coarse and fine materials. When loading the graded crushed stone base mixture, in order to reduce segregation, the materials shall be loaded three times: front, back and middle, and a special person shall be arranged to be responsible for the command.
(三)每天出料检测:(III) Daily discharge inspection:
(1)含水量;(1) Water content;
(2)集料级配;(2) Aggregate gradation;
(3)混合料离析现象。(3) Mixture segregation phenomenon.
(四)拌和注意事项:(IV) Mixing precautions:
(1)、配料准确;(1) Accurate ingredients;
(2)、含水量略大于最佳含水量;(2) The water content is slightly greater than the optimum water content;
(3)、拌和均匀;(3) Mix evenly;
(4)、混合料检测及时。(4) The mixture is tested in a timely manner.
(五)拌和过程中人员安排:每个拌和楼操作人员2人,负责拌和站的操作;拌和站巡检4人,负责拌和站各料仓的检查;检测混合料级配含水量1人;指挥装料1人。(V) Personnel arrangement during mixing process: 2 operators in each mixing plant, responsible for the operation of the mixing station; 4 inspectors at the mixing station, responsible for the inspection of each silo at the mixing station; 1 person to test the moisture content of the mixture gradation; 1 person to direct the loading.
(六)运输(VI) Transportation
级配碎石混合料运输采用15T以上自卸车,当运距较长,有风或中午气温高,用蓬布将料车上的混合料进行覆盖,以防止水分散失,运输能力根据拌和机能力、运距、摊铺能力等及时调整。运输车辆要保证在摊铺机前面等待卸料的车辆有三辆,拌和站等待装料的车辆不少于三辆。车辆数量、驾驶员、行驶路线在摊铺前一天进行统一落实,根据前场的施工路段所需的生产数量,配备足够的运输车辆,确保施工段落连续作业。The graded crushed stone mixture is transported by dump trucks of 15 tons or more. When the transportation distance is long, there is wind or the temperature is high at noon, the mixture on the material truck is covered with tarpaulin to prevent water loss. The transportation capacity is adjusted in time according to the mixer capacity, transportation distance, paving capacity, etc. The transportation vehicles must ensure that there are three vehicles waiting to unload in front of the paver, and no less than three vehicles waiting to load at the mixing station. The number of vehicles, drivers, and driving routes are uniformly implemented the day before paving. According to the production quantity required by the construction section of the front field, sufficient transportation vehicles are equipped to ensure continuous operation of the construction section.
将混合料由搅拌站运输至摊铺施工现场前,先对运输车辆车斗表面洒水进行湿润,运输车辆车况必须良好,保证混合料在最佳含水量运输。Before transporting the mixture from the mixing station to the paving construction site, sprinkle water on the surface of the transport vehicle's bed to moisten it. The transport vehicle must be in good condition to ensure that the mixture is transported at the optimal moisture content.
对运输道路经常维护,保证道路平稳通畅,防止混合料在运输期间离析。Regularly maintain the transportation roads to ensure that the roads are smooth and unobstructed and to prevent the mixture from segregating during transportation.
S5、按试验确定的松铺系数和摊铺方法,将混合料摊铺在下承层表面,再压实,其中,压实方法包括:先静压1遍,修补找平,再振动碾压4遍,然后对碾压后的混合料充分洒水至饱和,再重复碾压直到水分从空隙中流走,且级配碎石层达到压实度要求。S5. According to the loose paving coefficient and paving method determined by the test, the mixture is spread on the surface of the underlying layer and then compacted. The compaction method includes: first static compaction once, repairing and leveling, then vibration rolling 4 times, and then fully watering the rolled mixture until saturation, and then repeating the rolling until the water flows out of the gaps and the graded gravel layer reaches the compaction requirement.
具体的,混合料的摊铺,采用三一重工产的型号为DTU95摊铺机进行摊铺。摊铺时,传感器采用钢丝绳来控制标高及厚度,摊铺前对下承层表面进行适当洒水润湿,并坚持每天检查摊铺机各部分部件运转情况是否正常。摊铺机起步前,用木板垫起熨平板,使熨平板的标高为摊铺层的松铺标高,为减少熨平板的变形,每个摊铺机熨平板至少要垫起三处。Specifically, the mixture was spread using a DTU95 paver produced by Sany Heavy Industry. During paving, the sensor used a steel wire rope to control the elevation and thickness. Before paving, the surface of the underlying layer was properly sprinkled with water and moistened, and the operation of each part of the paver was checked every day to see if it was normal. Before the paver started, the ironing plate was padded with wooden boards so that the elevation of the ironing plate was the loose elevation of the paving layer. To reduce the deformation of the ironing plate, each paver ironing plate must be padded at least three places.
摊铺作业时根据拌和能力和运输能力,确定摊铺机速度,严禁出现摊铺机停机待料的情况,保持摊铺的连续性,提高平整度。摊铺机摊铺速度为1.5~2m/min,摊铺混合料时速度宜采用最小摊铺速度为1.5m/min,以减少停机待料的现象。During paving operations, the speed of the paver is determined according to the mixing capacity and transportation capacity. It is strictly forbidden to stop the paver to wait for materials, so as to maintain the continuity of paving and improve the flatness. The paving speed of the paver is 1.5-2m/min. When paving the mixture, the minimum paving speed should be 1.5m/min to reduce the phenomenon of stopping to wait for materials.
摊铺过程中有专人指挥运输车辆在摊铺机前方20~30cm处停车,防止碰撞摊铺机,由摊铺机迎上去推动卸料车,一边前进一边卸料,卸料时料车不能踩刹车,卸料速度应与摊铺速度相协调,卸料时由专人指挥卸料。运输车辆在下承层上调头时,要在指定地方进行,以减少对下承层的损坏,同时注意不能碰撞导向控制线钢丝,以免影响摊铺层的标高精度控制。During the paving process, a dedicated person will direct the transport vehicle to stop 20 to 30 cm in front of the paver to prevent collision with the paver. The paver will push the unloading vehicle forward and unload while moving forward. The vehicle cannot brake during unloading. The unloading speed should be coordinated with the paving speed. A dedicated person will direct the unloading. When the transport vehicle turns around on the underlying layer, it must be done at the designated place to reduce damage to the underlying layer. At the same time, be careful not to collide with the guide control wire to avoid affecting the elevation accuracy control of the paving layer.
摊铺作业时,指定现场技术人员对已摊铺的基层进行标高和厚度跟踪控制,根据检测结果对摊铺机传感器进行微调,以保证符合设计及规范要求,确保施工质量。During paving operations, designated on-site technicians will track and control the elevation and thickness of the paved base layer, and fine-tune the paver sensors based on the test results to ensure compliance with design and specification requirements and to ensure construction quality.
摊铺机摊铺后,安排专人消除粗细集料离析现象,及时挖除局部的粗集料“窝”,并用新拌和料填补。出现粗集料偏多的情况,要及时安排专人用新拌和混合细料嵌隙填补。After the paver spreads, a dedicated person shall be assigned to eliminate the segregation of coarse and fine aggregates, promptly remove local coarse aggregate "nests", and fill them with newly mixed materials. If there is too much coarse aggregate, a dedicated person shall be assigned to fill the gaps with newly mixed fine aggregates in a timely manner.
混合料摊铺后,路面边缘做好修边、整形,并用相关工具(如铁锹)把边拍实,以保证边缘直顺密实。After the mixture is spread, the edges of the road surface should be trimmed and shaped, and compacted with relevant tools (such as a shovel) to ensure that the edges are straight, smooth and dense.
摊铺时上下层接头应错开不小于3m。When paving, the joints of the upper and lower layers should be staggered by no less than 3m.
具体的,混合料的压实,碾压将采用一台26T级单钢轮振动压路机、一台22T级单钢轮振动压路机进行联合碾压。Specifically, the compaction and rolling of the mixture will be carried out by a 26T single steel wheel vibratory roller and a 22T single steel wheel vibratory roller.
混合料经摊铺、整形后,立即进行碾压,碾压长度以50~80m为宜,碾压段落层次分明,设有明显的分界标志并形成连续碾压,坚持遵循初压和终压均采用静压的原则,以减小变形和提高表层密实度、平整度。After the mixture is spread and shaped, it is rolled immediately. The rolling length should be 50 to 80 meters. The rolling sections should be clearly layered, with obvious boundary marks and continuous rolling. The principle of static pressure should be followed for both initial and final pressure to reduce deformation and improve surface density and flatness.
碾压顺序采用22T级压路机静压1遍,弱振碾压2遍,强振碾压2遍,然后对碾压后的混合料用洒水车充分洒水至饱和,再用26T级压路机重复强振碾压直到水分从空隙中流走,且级配碎石层达到压实度要求,最后再用26T级压路机静压1遍使表面密实无轮迹。The rolling sequence is to use a 22T grade roller for static rolling once, weak vibration rolling twice, and strong vibration rolling twice. Then use a sprinkler truck to fully sprinkle water on the compacted mixture until it is saturated. Then use a 26T grade roller to repeat strong vibration rolling until the water flows out of the gaps and the graded gravel layer reaches the compaction requirement. Finally, use a 26T grade roller for static rolling once to make the surface dense and free of wheel marks.
碾压方法:摊铺成型后压路机进行碾压,碾压方向与路中心线平行,直线段,由路肩向中心碾压,在超高路段上,由内侧向外侧进行碾压,使纵向顺延,横坡符合设计要求。压路机碾压时成阶梯状碾压,两碾压段的接头处,采用压路机成45度角斜碾,正常碾压时轮迹重叠1/2轮宽,后轮必须超过两段的接缝处,后轮压完路面全宽时为一遍,碾压至要求的压实度并无轮迹为止。压路机的碾压速度,前两遍以采用1档为宜,以后可采用2档,绝不可高速碾压。碾压程序:静压~弱振~强振~静压。现场记录碾压遍数,道面的两侧要多压1~2遍,压路机稳压时1.5~1.7km/h,振动压时1.8~2.2km/h,终压1.5—1.7km/h。Rolling method: After paving and forming, the roller is used for rolling. The rolling direction is parallel to the center line of the road. For straight sections, rolling is carried out from the shoulder to the center. For super-high sections, rolling is carried out from the inside to the outside, so that the longitudinal extension and the cross slope meet the design requirements. The roller rolls in a step-like manner. At the joint of the two rolling sections, the roller rolls at a 45-degree angle. During normal rolling, the wheel tracks overlap by 1/2 of the wheel width. The rear wheel must exceed the joint of the two sections. When the rear wheel rolls the full width of the road surface, it is considered one pass. Rolling is carried out until the required compaction degree and no wheel tracks are left. The rolling speed of the roller is preferably 1st gear for the first two passes, and 2nd gear can be used afterwards. High-speed rolling is absolutely not allowed. Rolling procedure: static pressure ~ weak vibration ~ strong vibration ~ static pressure. Record the number of rolling times on site. Both sides of the road surface should be rolled 1 to 2 more times. The speed of the roller should be 1.5 to 1.7 km/h during steady pressure, 1.8 to 2.2 km/h during vibration pressure, and 1.5 to 1.7 km/h during final pressure.
压路机严禁在已完成的或正在碾压的路段上“调头”和急刹车,保证级配碎石基层表 面不受破坏。It is strictly forbidden for the roller to "turn around" or brake suddenly on the completed or rolling road section to ensure that the surface of the graded gravel base is not damaged.
死角处处理:在转角等压路机无法碾压的部位,将采用小型夯机夯实,局部小的地方采用人工夯实。Treatment of blind corners: In corners and other places where rollers cannot compact, small tamping machines will be used for compaction, and manual compaction will be used in small areas.
平整度控制:施工过程中采用人工铲除接头处的拥包,同时用4.8米直尺检查平整度,不符合要求的立即进行处理,消除碾压段之间的不平整。整平应仔细进行,目的是将凸出部分刮除并用人工及时扫出工作面外,局部低凹的部分不得用刮除料作为找平层,即“只准铲高,不得补凹”。个别严重的,凹坑需要找平时,应用人工挖成方形成矩形面(深度不少于10cm),填补相同的混合料,人工补平并夯实再统一碾压成型。Flatness control: During the construction process, the bumps at the joints are manually shoveled away, and the flatness is checked with a 4.8-meter ruler. Those that do not meet the requirements are immediately processed to eliminate the unevenness between the rolling sections. The leveling should be done carefully, with the purpose of scraping off the protruding parts and manually sweeping them out of the working surface in time. The scraped materials should not be used as the leveling layer for the local concave parts, that is, "only shoveling is allowed, not filling the concave". In some serious cases, when the pits need to be leveled, they should be manually dug into a rectangular surface (depth of not less than 10cm), filled with the same mixture, manually leveled and compacted, and then uniformly rolled to form.
S6、级配碎石层达到压实度要求后还进行修补和接缝处理,最后验收。S6. After the graded gravel layer reaches the compaction requirement, it will be repaired and the joints will be treated before final acceptance.
具体的,横向接缝处理:靠近摊铺机当天未压实的级配碎石基层混合料,可与第二天摊铺的混合料一起碾压,但应注意此部分混合料的含水量。当含水量较低时,应适当补充洒水,使其含水量达到规定的要求。Specifically, transverse joint treatment: the graded crushed stone base mixture that is not compacted on the day of the paver can be rolled together with the mixture to be paved the next day, but attention should be paid to the moisture content of this part of the mixture. When the moisture content is low, appropriate watering should be added to make its moisture content meet the specified requirements.
纵向接缝处理:纵向接缝碾压时先留20cm左右不碾压,作为下一次摊铺机行走时的控制高程面,同时接缝应搭接5cm左右,当摊铺机摊铺完整个工作面设计宽度时,再进行下个碾压面碾压。如遇特殊情况停机时,应把整个摊铺面碾压完(包括预留的20cm),重新开始摊铺时,应先把纵向接缝处未压实松散的料铲掉,并把纵向接缝铲成垂直断面,然后适当洒水湿润接缝再进行新的摊铺、整平、碾压工作。Longitudinal joint treatment: When rolling the longitudinal joint, leave about 20cm unrolled as the control elevation surface for the next paver to move. At the same time, the joint should overlap about 5cm. When the paver has paved the entire designed width of the working surface, the next rolling surface can be rolled. If the machine is shut down due to special circumstances, the entire paving surface should be rolled (including the reserved 20cm). When paving is restarted, the uncompacted and loose materials at the longitudinal joint should be shoveled away first, and the longitudinal joint should be shoveled into a vertical section. Then, water should be sprinkled to moisten the joint before new paving, leveling, and rolling work.
交接面处理:在交接面处摊铺时,先在一个面上多摊铺20cm,整平压实后,对交接面上多余的料铲掉,并把交接面铲成垂直断面,然后适当洒水湿润交接面再进行另外一个面摊铺、整平、碾压工作。Treatment of the interface: When paving at the interface, first spread 20cm more on one surface. After leveling and compacting, scrape off the excess material on the interface and shovel the interface into a vertical section. Then sprinkle water to moisten the interface before paving, leveling and rolling the other surface.
养生:每一段工作面碾压完成并用灌砂法检验压实度合格后,进行交验,同时及时进行上层透层施工。如不能连续施工上层时,设专人进行养护,同时要采取交通管制,除洒水车外,其它车辆禁止通行。Maintenance: After each section of the working surface is rolled and the compaction degree is tested by the sand filling method, it will be inspected and the upper layer will be constructed in time. If the upper layer cannot be constructed continuously, a special person will be assigned to perform maintenance. At the same time, traffic control will be implemented. Except for sprinkler trucks, other vehicles are prohibited from passing.
经上述施工工艺,斯里兰卡汉班托塔机场道面级配碎石基层压实度达到100%,同时CBR值达到了120%,且基层表面平整密实、无松散、无离析,完全达到美国联邦航空局《机场道面设计与评价》AC 150/5320-6E规范要求。Through the above construction technology, the compaction degree of the graded crushed stone base of the pavement of Sri Lanka's Hambantota Airport reached 100%, and the CBR value reached 120%. The surface of the base was flat and dense, without looseness or segregation, fully meeting the requirements of the US Federal Aviation Administration's "Airport Pavement Design and Evaluation" AC 150/5320-6E specification.
由于级配碎石具有微渗水性能,一方面能够在一定时间内将下渗的水不断地排出,不至于积聚在结构层的交界面上,保持级配碎石基层与其上的机场道面沥青层之间的完好连 接;另一方面级配碎石也不会强渗水,因此不会导致大量的水很快下渗到路基,使路基土很快达到过饱水软化而迅速降低机场跑道承载能力。且级配碎石收缩系数极小,几乎为零,可以避免半刚性基层因收缩而引起的沥青面层反射裂缝。又级配碎石属于散粒体,本身并不传递应力和位移,因此它能消散、吸收单纯由环境因素变化,尤其是荷载、温度骤变情况下裂纹尖端的高应力及应变,完全吸收了外荷作用下裂缝尖端的应变能,消除了沥青面层裂缝扩展的可能性。另外,级配碎石具有足够的抗压、抗剪切强度,满足了作为道面承重层的要求。Because graded crushed stone has micro-permeability, on the one hand, it can continuously discharge the infiltrated water within a certain period of time, so that it will not accumulate on the interface of the structural layer, and maintain the intact connection between the graded crushed stone base and the asphalt layer of the airport pavement above it; on the other hand, graded crushed stone will not have strong water permeability, so it will not cause a large amount of water to quickly infiltrate the roadbed, causing the roadbed soil to quickly reach supersaturation and soften, and quickly reduce the bearing capacity of the airport runway. In addition, the shrinkage coefficient of graded crushed stone is extremely small, almost zero, which can avoid the reflection cracks of the asphalt surface layer caused by the shrinkage of the semi-rigid base. In addition, graded crushed stone is a granular body, which does not transmit stress and displacement by itself. Therefore, it can dissipate and absorb the high stress and strain at the crack tip caused by changes in environmental factors, especially load and temperature changes, and completely absorb the strain energy at the crack tip under the action of external loads, eliminating the possibility of crack expansion in the asphalt surface layer. In addition, graded crushed stone has sufficient compressive and shear strength, meeting the requirements of being a pavement load-bearing layer.
2013年3月18日,斯里兰卡汉班托塔国际机场正式通航,截至今天,运营将近两年时间,跑道道面使用状况良好(如图2~3所示),经过设计回访,没有发现早期病害的出现,达到了设计效果。相比半刚性基层,级配碎石基层为整个项目节省水泥约3万吨,节省直接工程成本1980万元。On March 18, 2013, Sri Lanka's Hambantota International Airport was officially opened to traffic. As of today, it has been in operation for nearly two years, and the runway pavement is in good condition (as shown in Figures 2 and 3). After a design review, no early disease was found, and the design effect was achieved. Compared with the semi-rigid base, the graded crushed stone base saves about 30,000 tons of cement for the entire project and saves 19.8 million yuan in direct engineering costs.
对比例:Comparative Example:
在试验段施工时,曾使用上述实施例中一致的混合料进行常规的含水量控制、分层压实法施工,即分层摊铺、碾压,每层碾压时混合料控制在最佳含水量。然而最终得到的级配碎石基层压实度最高仅能达到98%,难以满足美国联邦航空局《机场道面设计与评价》AC 150/5320-6E规范要求。During the construction of the test section, the mixture consistent with the above embodiment was used for conventional moisture content control and layered compaction construction, that is, layered paving and rolling, and the mixture was controlled at the optimal moisture content during each layer rolling. However, the final graded crushed stone base compaction degree can only reach 98% at most, which is difficult to meet the requirements of the Federal Aviation Administration's "Airport Pavement Design and Evaluation" AC 150/5320-6E specification.
尽管本发明的实施方案已公开如上,但其并不仅仅限于说明书和实施方式中所列运用,它完全可以被适用于各种适合本发明的领域,对于熟悉本领域的人员而言,可容易地实现另外的修改,因此在不背离权利要求及等同范围所限定的一般概念下,本发明并不限于特定的细节和这里示出与描述的图例。Although the embodiments of the present invention have been disclosed as above, they are not limited to the applications listed in the specification and the implementation modes, and they can be fully applied to various fields suitable for the present invention. For those familiar with the art, additional modifications can be easily implemented. Therefore, without departing from the general concept defined by the claims and the scope of equivalents, the present invention is not limited to the specific details and the illustrations shown and described herein.

Claims (9)

  1. 一种级配碎石饱和水密振实施工工艺,其特征在于,包括:A graded crushed stone saturated watertight vibration construction process, characterized by comprising:
    下承层验收、修整;Acceptance and repair of the underlying layer;
    对级配碎石进行配合比设计和试验,以确定配合比、松铺系数、摊铺方法;Carry out mix design and testing of graded crushed stone to determine mix ratio, loose paving coefficient and paving method;
    在验收合格的下承层上测量放样;Measure and set out on the qualified underlying layer;
    按试验确定的配合比准备碎石原料,将碎石原料拌和得到混合料;Prepare crushed stone raw materials according to the mix ratio determined by the test, and mix the crushed stone raw materials to obtain a mixed material;
    按试验确定的松铺系数和摊铺方法,将混合料摊铺在下承层表面,再压实,其中,压实方法包括:先静压,修补找平,再振动碾压,然后对碾压后的混合料充分洒水至饱和,再重复碾压直到水分从空隙中流走,且级配碎石层达到压实度要求。According to the loose paving coefficient and paving method determined by the test, the mixture is spread on the surface of the underlying layer and then compacted. The compaction method includes: static pressing first, repairing and leveling, and then vibration rolling. The compacted mixture is then fully watered until saturated, and then the rolling is repeated until the water flows out of the gaps and the graded gravel layer reaches the compaction requirement.
  2. 如权利要求1所述的级配碎石饱和水密振实施工工艺,其特征在于,所述级配碎石层应用于机场道面基层时,碎石原料的配合比为:筛孔大小为50mm时碎石通过率为100wt%,筛孔大小为37mm时碎石通过率为95~100wt%,筛孔大小为25mm时碎石通过率为70~95wt%,筛孔大小为19mm时碎石通过率为55~85wt%,筛孔大小为4.75mm时碎石通过率为30~60wt%,筛孔大小为0.6mm时碎石通过率为12~30wt%,筛孔大小为0.075mm时碎石通过率为0~8wt%;The construction process of graded crushed stone saturated watertight vibration as claimed in claim 1 is characterized in that when the graded crushed stone layer is applied to the airport pavement base, the mixing ratio of the crushed stone raw materials is: when the sieve hole size is 50mm, the crushed stone passing rate is 100wt%, when the sieve hole size is 37mm, the crushed stone passing rate is 95-100wt%, when the sieve hole size is 25mm, the crushed stone passing rate is 70-95wt%, when the sieve hole size is 19mm, the crushed stone passing rate is 55-85wt%, when the sieve hole size is 4.75mm, the crushed stone passing rate is 30-60wt%, when the sieve hole size is 0.6mm, the crushed stone passing rate is 12-30wt%, and when the sieve hole size is 0.075mm, the crushed stone passing rate is 0-8wt%;
    其中,通过0.075mm筛孔的碎石原料在通过0.6mm筛孔的碎石原料中的重量占比不超过60%;粒径大于4.75mm的碎石原料中针状和片状碎石原料的重量占比不超过15%,针状和片状碎石原料按ASTM D 693标准中的试验方法定义;按照ASTM C131试验规程测试碎石原料的磨耗值,其结果不大于35%;按照ASTM C 88试验规程测试碎石原料的硫酸钠坚固性,经过5个试验循环后,其损失值小于5%。Among them, the weight proportion of crushed stone raw materials passing through the 0.075mm sieve hole in the crushed stone raw materials passing through the 0.6mm sieve hole does not exceed 60%; the weight proportion of needle-shaped and flaky crushed stone raw materials in the crushed stone raw materials with a particle size greater than 4.75mm does not exceed 15%, and the needle-shaped and flaky crushed stone raw materials are defined in the test method in ASTM D 693 standard; the abrasion value of the crushed stone raw materials is tested in accordance with the ASTM C131 test procedure, and the result is not greater than 35%; the sodium sulfate firmness of the crushed stone raw materials is tested in accordance with the ASTM C 88 test procedure, and after 5 test cycles, the loss value is less than 5%.
  3. 如权利要求2所述的级配碎石饱和水密振实施工工艺,其特征在于,将碎石原料拌和得到混合料的过程具体包括:将碎石原料置于搅拌站中,采用搅拌站强制拌合混合料,拌和时按照满足所述级配要求的碎石原料的最佳含水量±2%加水,满足所述级配要求的碎石原料的最佳含水量采用重型击实实验进行确定。The graded crushed stone saturated watertight vibration construction process as described in claim 2 is characterized in that the process of mixing the crushed stone raw materials to obtain a mixture specifically includes: placing the crushed stone raw materials in a mixing station, using the mixing station to forcibly mix the mixture, and adding water during mixing according to the optimal water content ±2% of the crushed stone raw materials that meet the grading requirements, and the optimal water content of the crushed stone raw materials that meet the grading requirements is determined by a heavy compaction test.
  4. 如权利要求1所述的级配碎石饱和水密振实施工工艺,其特征在于,将混合料摊铺在下承层表面前,先对下承层表面洒水进行湿润。The construction process of graded crushed stone saturated watertight vibration as described in claim 1 is characterized in that before the mixture is spread on the surface of the underlying layer, the surface of the underlying layer is first sprinkled with water to moisten it.
  5. 如权利要求3所述的级配碎石饱和水密振实施工工艺,其特征在于,将混合料由 搅拌站运输至摊铺施工现场前,先对运输车辆车斗表面洒水进行湿润。The construction process for saturated watertight vibration of graded crushed stone as described in claim 3 is characterized in that before the mixed material is transported from the mixing station to the paving construction site, the surface of the truck bed of the transport vehicle is first sprinkled with water to moisten it.
  6. 如权利要求1所述的级配碎石饱和水密振实施工工艺,其特征在于,在验收合格的下承层上测量放样的过程包括:每隔10m设一桩,进行水准测量,在铺筑边线外50cm处打入导向控制线支架,导向控制线支架位置对应中线桩号,导向控制线支架间距为10m,根据下承层顶面标高、设计厚度、试验得出的松铺系数及固定值,调整导向控制线支架横杆高度,设定为铺筑时导向控制线标高,导向控制线标高=下承层顶面高程+松铺系数×级配碎石层设计压实厚度+固定值,固定值为导线与摊铺设备的熨平板高差。The construction process of graded crushed stone saturated watertight vibration as described in claim 1 is characterized in that the process of measuring and setting out on the qualified lower bearing layer includes: setting a pile every 10m, conducting leveling measurement, driving a guide control line bracket 50cm outside the paving edge line, the position of the guide control line bracket corresponds to the center line pile number, the spacing between the guide control line brackets is 10m, and adjusting the height of the cross bar of the guide control line bracket according to the elevation of the top surface of the lower bearing layer, the design thickness, the loose laying coefficient obtained from the test and the fixed value, and setting it to the elevation of the guide control line during paving, the elevation of the guide control line = the elevation of the top surface of the lower bearing layer + the loose laying coefficient × the designed compacted thickness of the graded crushed stone layer + the fixed value, and the fixed value is the height difference between the conductor and the ironing plate of the paving equipment.
  7. 如权利要求1所述的级配碎石饱和水密振实施工工艺,其特征在于,级配碎石层达到压实度要求后还进行修补和接缝处理,最后验收。The construction process of graded crushed stone saturated watertight vibration as described in claim 1 is characterized in that after the graded crushed stone layer reaches the compaction requirement, it is also repaired and jointed, and finally accepted.
  8. 如权利要求1所述的级配碎石饱和水密振实施工工艺,其特征在于,级配碎石层的压实度采用灌砂法测量得到。The construction process for graded crushed stone saturated watertight vibration as described in claim 1 is characterized in that the compaction degree of the graded crushed stone layer is measured by a sand filling method.
  9. 如权利要求1所述的级配碎石饱和水密振实施工工艺,其特征在于,所述压实的方法中,先静压1遍,修补找平,再振动碾压4遍。The construction process of graded crushed stone saturated watertight vibration as described in claim 1 is characterized in that in the compaction method, static compaction is first performed once, repair and leveling are performed, and then vibration rolling is performed four times.
PCT/CN2022/142583 2022-11-01 2022-12-28 Saturated-water vibrating compaction construction process for graded crushed stone WO2024092998A1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN202211354290.0A CN115787386A (en) 2022-11-01 2022-11-01 Saturated watertight compaction construction process for graded broken stones
CN202211354290.0 2022-11-01

Publications (1)

Publication Number Publication Date
WO2024092998A1 true WO2024092998A1 (en) 2024-05-10

Family

ID=85434762

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2022/142583 WO2024092998A1 (en) 2022-11-01 2022-12-28 Saturated-water vibrating compaction construction process for graded crushed stone

Country Status (2)

Country Link
CN (1) CN115787386A (en)
WO (1) WO2024092998A1 (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102477710A (en) * 2010-11-22 2012-05-30 中国十七冶集团有限公司 Construction method for subbase layer of natural graded pebble road surface
CN103161109A (en) * 2011-12-13 2013-06-19 中国二十冶集团有限公司 Method for subgrade filling of peat soil subgrade by sea sand
CN105714653A (en) * 2016-02-02 2016-06-29 上海建工集团股份有限公司 Combined rolling technology for graded broken stone base construction
CN107604785A (en) * 2017-07-19 2018-01-19 甘肃路桥建设集团养护科技有限责任公司 Wide cut thick Construction of semi-rigid base technique entirely is mixed and stirred in vibration
CN113718604A (en) * 2021-07-15 2021-11-30 兰州交通大学 Wind-accumulated sand filler filling method for desert abdominal highway
CN114381981A (en) * 2022-01-28 2022-04-22 中电建路桥集团有限公司 Construction method for double-layer combined paving test section of guide way
US20220205188A1 (en) * 2020-12-30 2022-06-30 Shandong Provincial Communications Planning And Design Institute Group Co., Ltd Full-depth ultra-thin long-life pavement structure and construction method thereof

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6781669B2 (en) * 2017-06-14 2020-11-04 鹿島建設株式会社 Compaction method and compaction management system
CN108004864A (en) * 2017-12-01 2018-05-08 江苏中路工程技术研究院有限公司 With construction method of the improvement collapsible loess as roadbed filling
CN112982058A (en) * 2019-12-14 2021-06-18 浙江建腾建设有限公司 Vibration mixing construction method for cement stabilized macadam
CN111893827A (en) * 2020-08-05 2020-11-06 中交上海航道局有限公司 Construction process of urban trunk road

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102477710A (en) * 2010-11-22 2012-05-30 中国十七冶集团有限公司 Construction method for subbase layer of natural graded pebble road surface
CN103161109A (en) * 2011-12-13 2013-06-19 中国二十冶集团有限公司 Method for subgrade filling of peat soil subgrade by sea sand
CN105714653A (en) * 2016-02-02 2016-06-29 上海建工集团股份有限公司 Combined rolling technology for graded broken stone base construction
CN107604785A (en) * 2017-07-19 2018-01-19 甘肃路桥建设集团养护科技有限责任公司 Wide cut thick Construction of semi-rigid base technique entirely is mixed and stirred in vibration
US20220205188A1 (en) * 2020-12-30 2022-06-30 Shandong Provincial Communications Planning And Design Institute Group Co., Ltd Full-depth ultra-thin long-life pavement structure and construction method thereof
CN113718604A (en) * 2021-07-15 2021-11-30 兰州交通大学 Wind-accumulated sand filler filling method for desert abdominal highway
CN114381981A (en) * 2022-01-28 2022-04-22 中电建路桥集团有限公司 Construction method for double-layer combined paving test section of guide way

Also Published As

Publication number Publication date
CN115787386A (en) 2023-03-14

Similar Documents

Publication Publication Date Title
CN107338686A (en) A kind of Subgrade Filled Soil in High Speed Railway construction method
CN108978389A (en) A kind of construction method of bituminous pavement
CN111021174A (en) Construction method of urban road
CN114381981A (en) Construction method for double-layer combined paving test section of guide way
CN106522073A (en) Construction method of high-added water-stable milled waste base
CN114232649B (en) Construction method for filling earthwork of ballastless track roadbed
CN211472012U (en) Signal lamp crossing filling type composite pavement
CN113929378A (en) Oil shale semicoke and application of modified material thereof
CN111827033A (en) Construction method for widening and filling solidified soil of expressway intercommunicating ramp roadbed
CN112982058A (en) Vibration mixing construction method for cement stabilized macadam
WO2024092998A1 (en) Saturated-water vibrating compaction construction process for graded crushed stone
CN111719371A (en) Road base layer component and road paving method
CN113152200A (en) Method for preventing and controlling cracks of road water-stable gravel base layer in reclamation area
Pittman Construction of roller-compacted concrete pavements
Sharp Concrete in Highway Engineering: International Series of Monographs in Civil Engineering
CN111979865A (en) Composite asphalt pavement construction method
CN113529575A (en) Construction process for backfilling construction waste of abutment back of high-grade highway bridge and culvert
Mallick et al. Construction of Asphalt Pavements
CN111576125B (en) Construction method for transverse automatic feeding base layer
Li et al. Control Points of the Compaction Technology for Subgrades and Pavements in Municipal Road Engineering
CN113584981A (en) Assembled cement concrete pavement slab and construction method
CN113174793A (en) Construction method for widening roadbed by improving filling material solidified soil
Wu et al. Louisiana Transportation Research Center
CN112176815A (en) Highway water-stable structure subsection step type continuous paving construction process
CN116356797A (en) Filling construction method for improving soil by utilizing waste soil as resource

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 22964292

Country of ref document: EP

Kind code of ref document: A1