CN114381981A - Construction method of double-layer combined paving test section of guide road - Google Patents
Construction method of double-layer combined paving test section of guide road Download PDFInfo
- Publication number
- CN114381981A CN114381981A CN202210109238.2A CN202210109238A CN114381981A CN 114381981 A CN114381981 A CN 114381981A CN 202210109238 A CN202210109238 A CN 202210109238A CN 114381981 A CN114381981 A CN 114381981A
- Authority
- CN
- China
- Prior art keywords
- mixture
- paving
- cement
- construction
- paver
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 78
- 238000012360 testing method Methods 0.000 title claims abstract description 53
- 239000000203 mixture Substances 0.000 claims abstract description 129
- 238000005096 rolling process Methods 0.000 claims abstract description 60
- 238000002156 mixing Methods 0.000 claims abstract description 56
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims abstract description 49
- 238000013461 design Methods 0.000 claims abstract description 40
- 230000036541 health Effects 0.000 claims abstract description 11
- 238000007689 inspection Methods 0.000 claims abstract description 11
- 239000004568 cement Substances 0.000 claims description 71
- 239000000463 material Substances 0.000 claims description 39
- 238000000034 method Methods 0.000 claims description 36
- 238000005056 compaction Methods 0.000 claims description 31
- 238000005204 segregation Methods 0.000 claims description 23
- 229910000831 Steel Inorganic materials 0.000 claims description 22
- 230000008569 process Effects 0.000 claims description 22
- 239000010959 steel Substances 0.000 claims description 22
- 239000004575 stone Substances 0.000 claims description 20
- 238000004519 manufacturing process Methods 0.000 claims description 15
- 238000002360 preparation method Methods 0.000 claims description 11
- 238000001514 detection method Methods 0.000 claims description 10
- 229910052500 inorganic mineral Inorganic materials 0.000 claims description 10
- 239000011707 mineral Substances 0.000 claims description 10
- 239000002245 particle Substances 0.000 claims description 9
- 238000004321 preservation Methods 0.000 claims description 8
- 239000002994 raw material Substances 0.000 claims description 7
- 239000004576 sand Substances 0.000 claims description 7
- 239000002023 wood Substances 0.000 claims description 6
- RBTBFTRPCNLSDE-UHFFFAOYSA-N 3,7-bis(dimethylamino)phenothiazin-5-ium Chemical compound C1=CC(N(C)C)=CC2=[S+]C3=CC(N(C)C)=CC=C3N=C21 RBTBFTRPCNLSDE-UHFFFAOYSA-N 0.000 claims description 4
- 238000004364 calculation method Methods 0.000 claims description 4
- 238000009415 formwork Methods 0.000 claims description 4
- 229960000907 methylthioninium chloride Drugs 0.000 claims description 4
- 238000000465 moulding Methods 0.000 claims description 4
- 239000011398 Portland cement Substances 0.000 claims description 3
- 238000011049 filling Methods 0.000 claims description 3
- 239000004746 geotextile Substances 0.000 claims description 3
- 238000012216 screening Methods 0.000 claims description 3
- 230000002087 whitening effect Effects 0.000 claims description 3
- 238000003756 stirring Methods 0.000 claims 1
- 239000002689 soil Substances 0.000 abstract description 7
- 238000003825 pressing Methods 0.000 abstract description 4
- 239000010410 layer Substances 0.000 description 39
- 238000011068 loading method Methods 0.000 description 5
- 230000006641 stabilisation Effects 0.000 description 4
- 238000011105 stabilization Methods 0.000 description 4
- 239000004744 fabric Substances 0.000 description 3
- 239000003673 groundwater Substances 0.000 description 3
- 239000008188 pellet Substances 0.000 description 3
- 238000001556 precipitation Methods 0.000 description 3
- 239000002344 surface layer Substances 0.000 description 3
- 230000002159 abnormal effect Effects 0.000 description 2
- 238000009825 accumulation Methods 0.000 description 2
- 230000008859 change Effects 0.000 description 2
- 238000004891 communication Methods 0.000 description 2
- 238000007906 compression Methods 0.000 description 2
- 238000011161 development Methods 0.000 description 2
- 239000000428 dust Substances 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- 230000003203 everyday effect Effects 0.000 description 2
- 238000005259 measurement Methods 0.000 description 2
- 239000000843 powder Substances 0.000 description 2
- 238000000275 quality assurance Methods 0.000 description 2
- 239000002699 waste material Substances 0.000 description 2
- QAOWNCQODCNURD-UHFFFAOYSA-L Sulfate Chemical compound [O-]S([O-])(=O)=O QAOWNCQODCNURD-UHFFFAOYSA-L 0.000 description 1
- 230000005856 abnormality Effects 0.000 description 1
- 239000004927 clay Substances 0.000 description 1
- 238000005520 cutting process Methods 0.000 description 1
- 238000007599 discharging Methods 0.000 description 1
- 238000009826 distribution Methods 0.000 description 1
- 239000003651 drinking water Substances 0.000 description 1
- 235000020188 drinking water Nutrition 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000001704 evaporation Methods 0.000 description 1
- 230000008020 evaporation Effects 0.000 description 1
- 238000002474 experimental method Methods 0.000 description 1
- 230000008014 freezing Effects 0.000 description 1
- 238000007710 freezing Methods 0.000 description 1
- 239000011440 grout Substances 0.000 description 1
- 238000007654 immersion Methods 0.000 description 1
- 238000012423 maintenance Methods 0.000 description 1
- 230000007935 neutral effect Effects 0.000 description 1
- 230000008520 organization Effects 0.000 description 1
- 238000005192 partition Methods 0.000 description 1
- 239000002985 plastic film Substances 0.000 description 1
- 229920006255 plastic film Polymers 0.000 description 1
- 230000008092 positive effect Effects 0.000 description 1
- 230000002265 prevention Effects 0.000 description 1
- 238000012545 processing Methods 0.000 description 1
- 238000004537 pulping Methods 0.000 description 1
- 238000003908 quality control method Methods 0.000 description 1
- 230000033764 rhythmic process Effects 0.000 description 1
- 238000007790 scraping Methods 0.000 description 1
- 230000035945 sensitivity Effects 0.000 description 1
- 238000000926 separation method Methods 0.000 description 1
- 239000002002 slurry Substances 0.000 description 1
- 239000007787 solid Substances 0.000 description 1
- 238000003860 storage Methods 0.000 description 1
- 238000012795 verification Methods 0.000 description 1
- 238000005303 weighing Methods 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
- E01C7/00—Coherent pavings made in situ
- E01C7/08—Coherent pavings made in situ made of road-metal and binders
- E01C7/10—Coherent pavings made in situ made of road-metal and binders of road-metal and cement or like binders
- E01C7/14—Concrete paving
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
- E01C19/00—Machines, tools or auxiliary devices for preparing or distributing paving materials, for working the placed materials, or for forming, consolidating, or finishing the paving
- E01C19/48—Machines, tools or auxiliary devices for preparing or distributing paving materials, for working the placed materials, or for forming, consolidating, or finishing the paving for laying-down the materials and consolidating them, or finishing the surface, e.g. slip forms therefor, forming kerbs or gutters in a continuous operation in situ
- E01C19/4806—Machines, tools or auxiliary devices for preparing or distributing paving materials, for working the placed materials, or for forming, consolidating, or finishing the paving for laying-down the materials and consolidating them, or finishing the surface, e.g. slip forms therefor, forming kerbs or gutters in a continuous operation in situ with solely rollers for consolidating or finishing
- E01C19/4826—Machines, tools or auxiliary devices for preparing or distributing paving materials, for working the placed materials, or for forming, consolidating, or finishing the paving for laying-down the materials and consolidating them, or finishing the surface, e.g. slip forms therefor, forming kerbs or gutters in a continuous operation in situ with solely rollers for consolidating or finishing the materials being aggregate mixed with binders
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
- E01C23/00—Auxiliary devices or arrangements for constructing, repairing, reconditioning, or taking-up road or like surfaces
- E01C23/01—Devices or auxiliary means for setting-out or checking the configuration of new surfacing, e.g. templates, screed or reference line supports; Applications of apparatus for measuring, indicating, or recording the surface configuration of existing surfacing, e.g. profilographs
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
- E01C23/00—Auxiliary devices or arrangements for constructing, repairing, reconditioning, or taking-up road or like surfaces
- E01C23/03—Arrangements for curing paving; Devices for applying curing means; Devices for laying prefabricated underlay, e.g. sheets, membranes; Protecting paving under construction or while curing, e.g. use of tents
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
- E01C7/00—Coherent pavings made in situ
- E01C7/08—Coherent pavings made in situ made of road-metal and binders
- E01C7/10—Coherent pavings made in situ made of road-metal and binders of road-metal and cement or like binders
- E01C7/14—Concrete paving
- E01C7/142—Mixtures or their components, e.g. aggregate
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Road Paving Structures (AREA)
Abstract
本发明提供了导行路双层联铺试验段施工方法,属于市政工程领域,包括以下步骤,S1、下承层准备;S2、测量放样,放样出中桩、边桩,确定摊铺的宽度,便于路肩培土,在两侧打设基准点,控制高程;S3、混合料的拌和与运输;S4、混合料的摊铺,采用两台摊铺机梯形作业,正常摊铺时,连续、均匀地摊铺;S5、混合料的碾压,碾压过程为初压‑复压‑终压,初压使摊铺好的混合料经初压成稳定状态,复压进行路面密实,终压进行收面;S6、接缝处理,避免纵向接缝,横向施工缝用人工把含水量合适的混合料补齐;S7、养生和质量检验,质量符合设计和施工规范要求。本发明施工质量稳定可靠,效率高。
The invention provides a construction method for a double-layer combined paving test section of a guide road, which belongs to the field of municipal engineering. It is convenient to cultivate soil on the road shoulder, set reference points on both sides to control the elevation; S3, mixing and transportation of the mixture; S4, the paving of the mixture, using two paver trapezoid operations, during normal paving, continuous and uniform Paving; S5. Rolling of the mixture. The rolling process is initial pressure-re-compression-final pressure. The initial pressure makes the paved mixture into a stable state after initial pressing, and the re-pressing is used to compact the road surface, and the final pressure is used to close the pavement. Surface; S6, joint treatment, avoid longitudinal joints, and manually fill the horizontal construction joints with the mixture with appropriate water content; S7, health care and quality inspection, the quality meets the requirements of design and construction specifications. The invention has stable and reliable construction quality and high efficiency.
Description
技术领域technical field
本发明属于市政工程领域,涉及导行路水泥稳定碎石施工,尤其涉及导行路双层联铺试验段施工方法。The invention belongs to the field of municipal engineering, relates to the cement-stabilized gravel construction of a guide road, and in particular relates to a construction method for a double-layer combined paving test section of a guide road.
背景技术Background technique
市政道路工程是城市建设工作的一个重要组成部分,是为城市居民和企业,事业单位的生活和生产提供服务的基础工程,因此,道路工程施工质量,直接影响城市的各项经济建设。Municipal road engineering is an important part of urban construction work, and it is a basic project that provides services for the life and production of urban residents, enterprises and institutions. Therefore, the quality of road engineering construction directly affects the economic construction of the city.
在实际工作生活中,经常会遇到高速公路某某路段因为天气、事故或者道路施工需要封闭道路中断交通的情况,此时候需要修筑导行路,执行标准按照高速公路标准进行,保证通行的顺畅性。In actual work and life, it is often encountered that a certain section of the expressway needs to be closed due to weather, accidents or road construction to interrupt traffic. At this time, it is necessary to build a guide road, and the implementation standard shall be carried out in accordance with the expressway standard to ensure the smoothness of traffic. .
为了确定压路机型号以及小型夯机等机械的使用最佳配合经济必选;确定松铺厚度和压实厚度以及其他参数,需要设置试验段,以保证后续整个工程的施工质量,所以试验段的施工至关重要。In order to determine the model of the road roller and the use of small rammers and other machinery to best match the economical choice; to determine the thickness of loose paving, compaction thickness and other parameters, it is necessary to set up a test section to ensure the construction quality of the entire subsequent project, so the construction of the test section critical.
发明内容SUMMARY OF THE INVENTION
本发明要解决的问题是在于提供导行路双层联铺试验段施工方法,解决了以上背景技术中存在的问题,施工质量稳定可靠,效率高。The problem to be solved by the present invention is to provide a construction method for the double-layer joint paving test section of the guide road, which solves the problems existing in the above background technology, and has stable and reliable construction quality and high efficiency.
为解决上述技术问题,本发明采用的技术方案是:导行路双层联铺试验段施工方法,包括以下步骤,In order to solve the above-mentioned technical problems, the technical scheme adopted in the present invention is: the construction method of the double-layer paving test section of the guide road comprises the following steps:
S1、下承层准备,底基层施工前下承层检查验收合格,在下承层内侧支设钢模板,然后对下承层进行彻底清扫;S1. Preparation of the lower bearing layer. Before the construction of the sub-base, the lower bearing layer is checked and accepted, and the steel formwork is supported on the inner side of the lower bearing layer, and then the lower bearing layer is thoroughly cleaned;
S2、测量放样,放样出中桩、边桩,确定摊铺的宽度,便于路肩培土,在两侧打设基准点,控制高程;S2. Measure and set out, set out the middle pile and side pile, determine the width of the paving, which is convenient for road shoulder cultivation, and set reference points on both sides to control the elevation;
S3、混合料的拌和与运输;混合料拌合均匀,使混合料运至现场摊铺时的含水率不小于最佳含水率,运输上料时,出料口距车厢槽帮最高点距离不得大于50cm,卸料时,让混合料自然卸到摊铺机料斗中,卸料速度与摊铺速度相协调,避免运输车撞击摊铺机以及将混合料卸在摊铺机外面;S3. Mixing and transportation of the mixture; the mixture is mixed evenly, so that the moisture content of the mixture when it is transported to the site for paving is not less than the optimum moisture content. If it is larger than 50cm, when unloading, let the mixed material unload into the paver hopper naturally, and the unloading speed should be coordinated with the paving speed to avoid the transport vehicle hitting the paver and unloading the mixed material outside the paver;
S4、混合料的摊铺,采用两台摊铺机梯形作业,在摊铺起点,将摊铺机熨平板升起,按照虚铺厚度将已加工好的枕木放在下面,放置平衡,满足虚铺厚度要求,然后落下熨平板,正常摊铺时,连续、均匀地摊铺;S4. For the paving of the mixed material, two pavers are used for trapezoidal operation. At the starting point of the paving, the paver screed is raised, and the processed sleepers are placed below according to the thickness of the virtual paving. Pave thickness requirements, and then drop the screed, and pave continuously and evenly during normal paving;
S5、混合料的碾压,驱动轮朝向摊铺机方向,由路边向路中、先轻后重、先慢后快、低速行驶碾压,避免出现推移、起皮和漏压的现象,严禁压路机在碾压成型或正在碾压路段调头或急刹车;碾压过程为初压-复压-终压,初压使摊铺好的混合料经初压成稳定状态,复压进行路面密实,终压进行收面;S5. For the rolling of the mixture, the driving wheel faces the direction of the paver, from the side of the road to the middle of the road, first light and then heavy, first slow and then fast, and rolling at low speed to avoid the phenomenon of shifting, peeling and leakage. It is strictly forbidden for the road roller to turn around or brake suddenly during the rolling process or the rolling road section; the rolling process is initial pressure-recompression-final pressure. , the final pressure is used to close the surface;
S6、接缝处理,避免纵向接缝,横向施工缝用人工把含水量合适的混合料补齐,垂直于路中心线放置方木,方木高度同压实层厚度相等,碾压密实;S6. Joint treatment, avoid longitudinal joints, manually fill the horizontal construction joints with the mixture with appropriate water content, place square wood perpendicular to the road centerline, the height of the square wood is equal to the thickness of the compaction layer, and the rolling is compact;
S7、养生和质量检验,水泥稳定碎石混合料碾压完成,检测合格后及时覆盖透水式土工布洒水进行养生,两幅间应相互搭接20cm以上,保证表面湿润,养生期不少于7天,质量符合设计和施工规范要求。S7. Health preservation and quality inspection. The cement stabilized gravel mixture is rolled and compacted. After the test is passed, the permeable geotextile is covered with water in time for health preservation. The two pieces should overlap each other by more than 20cm to ensure that the surface is moist. The quality meets the design and construction specification requirements.
进一步的,在步骤S2中,用φ20mm的钢钎在两侧打设基准点,基准点高程为设计高程加20cm,基准点设立时,直线段每10米一个钢钎,曲线段每5米一个钢钎,挂钢丝绳拉紧,保证基准线水平,基准线采用φ5mm的钢丝固定在钢钎上,每段长度应小于200m,用紧线器拉紧,其拉力不小于1000N。Further, in step S2, use φ20mm steel drill to set reference points on both sides, the reference point elevation is the design elevation plus 20cm, when the reference point is established, a steel drill is used for every 10 meters in the straight line, and a steel drill is used for every 5 meters in the curved segment. Steel drill, hang the wire rope and tighten it to ensure the level of the reference line. The reference line is fixed on the steel drill with φ5mm steel wire. The length of each section should be less than 200m, and the tension is not less than 1000N.
进一步的,在步骤S4中,采用两台摊铺机梯形作业,外侧摊铺机在前,内侧摊铺机在后,前面摊铺机外侧采用标高基准线控制,路中采用6m长导梁控制;后面摊铺机外侧采用标高基准线控制;前后摊铺机相距不超过10m,横向搭接宽度30cm,异型路段人工铺筑时,采用挂线控制标高,摊铺速度要均匀,控制在1.5m-2.0m/min,中途不得变速,摊铺不停顿、间断。Further, in step S4, two pavers are used for trapezoidal operation, the outer paver is in front, the inner paver is behind, the outer side of the front paver is controlled by the elevation reference line, and the road is controlled by a 6m long guide beam. ;The outer side of the rear paver is controlled by the elevation reference line; the distance between the front and rear paver is not more than 10m, and the horizontal overlap width is 30cm. When artificially paving the special-shaped road section, use the hanging line to control the elevation, and the paving speed should be uniform and controlled at 1.5m -2.0m/min, no speed change is allowed in the middle, and the paving is not stopped or interrupted.
进一步的,在步骤S5中,用灌砂法检测压实度是否合格,若不合格应增加碾压遍数,压实度检测频率每200m每车道2处,压路机停车要错开,相隔间距不小于3m,停在已碾压好的路段上,复压完成后对碾压隆起部位人工处理,设专人用6m直尺进行平整度检测,每车道检测。Further, in step S5, the sand filling method is used to check whether the compaction degree is qualified. If it is unqualified, the number of rolling passes should be increased. The compaction degree detection frequency should be 2 points per 200m per lane. 3m, stop on the road section that has been rolled, and after the recompression is completed, the rolling bulge will be manually processed, and a special person will use a 6m ruler to test the flatness, and each lane will be tested.
进一步的,在步骤S1之前先进行混合料原料的准备,包括水泥、粗集料、细集料,混合料采用振动成型法进行配合比设计,调配矿质混合料级配,配制不同水泥剂量,水泥剂量在4%-6%。Further, before step S1, the raw materials of the mixture are prepared, including cement, coarse aggregate, and fine aggregate, the mixture is designed by the vibration molding method, the gradation of the mineral mixture is prepared, and different cement dosages are prepared. The dose is 4%-6%.
进一步的,水泥采用32.5普通硅酸盐水泥,细集料选用级配良好的石屑,细集料中小于0.075mm的颗粒含量应不大于15%,塑性指数不大于8%,并且集料的亚甲蓝值不大于10g/Kg,砂当量不小于50%。Further, 32.5 ordinary Portland cement is used as the cement, and stone chips with good gradation are selected as the fine aggregate. The methylene blue value is not more than 10g/Kg, and the sand equivalent is not less than 50%.
进一步的,当拌合设备调试完毕,材料组成设计完成后,进行施工配合比调试,包括第一阶段试生产:按设定的施工参数,不掺加水泥和水,在皮带上取料筛分,验证级配是否符合设计要求,必要时调整生产参数并做好相关的记录;Further, when the commissioning of the mixing equipment is completed and the design of the material composition is completed, the commissioning of the construction mix ratio is carried out, including the first stage of trial production: according to the set construction parameters, no cement and water are added, and the material is reclaimed and screened on the belt. , verify whether the gradation meets the design requirements, adjust the production parameters if necessary and make relevant records;
第二阶段试生产:先按设计配合比掺加水泥和水,然后按标准剂量的±1%调整剂量掺加水泥和水,分别取样进行含水量测定、水泥剂量测定、标准密度及无侧限抗压强度试验确定施工配合比指导施工。The second stage of trial production: first add cement and water according to the design mix ratio, then add cement and water according to ±1% of the standard dose, and take samples for water content determination, cement dose determination, standard density and unconfined The compressive strength test determines the construction mix ratio to guide the construction.
进一步的,正式拌合前,做集料筛分试验,检验碎石混合料级配是否满足要求,如有问题及时调整,严格控制19mm,9.5mm,4.75mm关键筛孔的通过率,当集料的颗粒级配发生变化时,应重新调整配合比,保证混合料级配符合设计要求,拌合时,水泥剂量比设计增加0.5%,每半天进行一次混合料筛分,保证矿料级配准确,级配发生变化时,计算进行调整,混合料拌合均匀,严禁出现花白料及离析现象,含水率1.0%-2.0%。Further, before the formal mixing, do the aggregate screening test to check whether the gradation of the crushed stone mixture meets the requirements. If there is any problem, adjust it in time. When the particle gradation of the material changes, the mixing ratio should be re-adjusted to ensure that the mixture gradation meets the design requirements. When mixing, the cement dosage should be increased by 0.5% compared with the design, and the mixture should be screened every half a day to ensure the mineral material gradation. Accurate, when the gradation changes, the calculation is adjusted, the mixture is mixed evenly, the phenomenon of whitening and segregation is strictly prohibited, and the moisture content is 1.0%-2.0%.
进一步的,搅拌过程中,减少混合料的离析,水稳混合料在搅拌站输出时,降低出料高度,成品仓应间歇放料,成品仓放料口距运料车厢的垂直距离不宜大于0.5m;摊铺过程中,摊铺机的螺旋布料器有三分之二埋入混合料中,使螺旋布料器均匀地运转。Further, during the mixing process, the segregation of the mixture should be reduced. When the water-stabilized mixture is output in the mixing station, the discharge height should be reduced. The finished product warehouse should be discharged intermittently. m; During the paving process, two-thirds of the auger of the paver is buried in the mixture, so that the auger runs evenly.
与现有技术相比,本发明具有的优点和积极效果如下。Compared with the prior art, the present invention has the following advantages and positive effects.
1、本发明严格控制混合料拌合质量,拌合过程当中时时检测,并调整设备性能,保证水泥剂量,拌合时,水泥剂量宜比设计增加0.5%,每半天进行一次混合料筛分,保证矿料级配准确,级配发生变化时,计算进行调整,从原料上进行预防和准备,保证厚度的施工质量;1. The present invention strictly controls the mixing quality of the mixture, checks the mixing process from time to time, and adjusts the performance of the equipment to ensure the cement dosage. During mixing, the cement dosage should be increased by 0.5% compared with the design, and the mixture is screened every half a day. Ensure that the grading of mineral materials is accurate. When the grading changes, the calculation is adjusted, and prevention and preparation are carried out from the raw materials to ensure the construction quality of the thickness;
2、本发明在运输和摊铺的过程中,设置上料和下料的注意事项,尽可能减少混合料的离析,保证均匀装料,连续摊铺和卸料,速度平稳,摊铺机后面应设专人消除细集料离析现象,同时摊铺设备布料螺栓加反向叶片,并调整好角度,防止离析,稳定可靠,效率高;2. In the process of transportation and paving, the present invention sets the precautions for loading and unloading, reduces the segregation of the mixture as much as possible, and ensures uniform loading, continuous paving and unloading, and stable speed. A special person should be set up to eliminate the segregation of fine aggregates, and at the same time, the cloth bolts and reverse blades of the paving equipment should be adjusted, and the angle should be adjusted to prevent segregation, which is stable and reliable, and has high efficiency;
3、本发明可保证水稳层平整度,碾压在水泥初凝前及试验确定的延迟时间内完成,并达到要求压实度,摊铺机铺装过程中,保证连续均匀地摊铺,保证压实度。3. The invention can ensure the flatness of the water stable layer, and the rolling is completed before the initial setting of the cement and the delay time determined by the test, and reaches the required compaction degree. During the paving process of the paver, the continuous and uniform paving is ensured. Guaranteed compaction.
附图说明Description of drawings
构成本发明的一部分的附图用来提供对本发明的进一步理解,本发明的示意性实施例及其说明用于解释本发明,并不构成对本发明的不当限定。在附图中:The accompanying drawings constituting a part of the present invention are used to provide further understanding of the present invention, and the exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute an improper limitation of the present invention. In the attached image:
图1是本发明导行路双层联铺试验段施工方法实施例的导向路横断面图;Fig. 1 is the cross-sectional view of the guide road of the construction method embodiment of the double-layer paving test section of the guide road of the present invention;
图2是本发明导行路双层联铺试验段施工方法的流程图;Fig. 2 is the flow chart of the construction method of the double-layer paving test section of the guide road of the present invention;
图3是本发明水泥稳定类基层检测标准表。Fig. 3 is a standard table for the detection of cement-stabilized base layers of the present invention.
具体实施方式Detailed ways
需要说明的是,在不冲突的情况下,本发明中的实施例及实施例中的特征可以相互组合。It should be noted that the embodiments of the present invention and the features of the embodiments may be combined with each other under the condition of no conflict.
在本发明的描述中,需要理解的是,术语“中心”、“纵向”、“横向”、“上”、“下”、“前”、“后”、“左”、“右”、“竖直”、“水平”、“顶”、“底”、“内”、“外”等指示的方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述本发明和简化描述,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本发明的限制。此外,术语“第一”、“第二”等仅用于描述目的,而不能理解为指示或暗示相对重要性或者隐含指明所指示的技术特征的数量。由此,限定有“第一”、“第二”等的特征可以明示或者隐含地包括一个或者更多个该特征。在本发明的描述中,除非另有说明,“多个”的含义是两个或两个以上。In the description of the present invention, it should be understood that the terms "center", "portrait", "horizontal", "top", "bottom", "front", "rear", "left", "right", " The orientation or positional relationship indicated by vertical, horizontal, top, bottom, inner, outer, etc. is based on the orientation or positional relationship shown in the drawings, and is only for the convenience of describing the present invention and The description is simplified rather than indicating or implying that the device or element referred to must have a particular orientation, be constructed and operate in a particular orientation, and therefore should not be construed as limiting the invention. In addition, the terms "first", "second", etc. are used for descriptive purposes only, and should not be construed as indicating or implying relative importance or implying the number of indicated technical features. Thus, a feature defined as "first", "second", etc., may expressly or implicitly include one or more of that feature. In the description of the present invention, unless otherwise specified, "plurality" means two or more.
在本发明的描述中,需要说明的是,除非另有明确的规定和限定,术语“安装”、“相连”、“连接”应做广义理解,例如,可以是固定连接,也可以是可拆卸连接,或一体地连接;可以是机械连接,也可以是电连接;可以是直接相连,也可以通过中间媒介间接相连,可以是两个元件内部的连通。对于本领域的普通技术人员而言,可以通过具体情况理解上述术语在本发明中的具体含义。In the description of the present invention, it should be noted that the terms "installed", "connected" and "connected" should be understood in a broad sense, unless otherwise expressly specified and limited, for example, it may be a fixed connection or a detachable connection Connection, or integral connection; can be mechanical connection, can also be electrical connection; can be directly connected, can also be indirectly connected through an intermediate medium, can be internal communication between two elements. For those of ordinary skill in the art, the specific meanings of the above terms in the present invention can be understood through specific situations.
下面结合附图对本发明的具体实施例做详细说明。The specific embodiments of the present invention will be described in detail below with reference to the accompanying drawings.
如图1-图3所示,导行路桩号范围为DXK0+222.425-DXK1+200.120,全长977.695m,全线采用双向四车道高速公路标准,设计速度采用80Km/h,路基标准宽度21.5m,行车道宽度采用为4*3.75m,中央分隔带为1m,路缘带为2*1.5m,硬路肩为2*1.5m,土路肩为2*0.75m,如图1所示,为导行路横断面图。As shown in Fig. 1-Fig. 3, the guide road station number range is DXK0+222.425-DXK1+200.120, the total length is 977.695m, the whole line adopts the standard of two-way four-lane expressway, the design speed adopts 80Km/h, and the standard width of the roadbed is 21.5m. The width of the carriageway is 4*3.75m, the central dividing belt is 1m, the curb belt is 2*1.5m, the hard shoulder is 2*1.5m, and the dirt shoulder is 2*0.75m, as shown in Figure 1, it is a guide road Cross-sectional view.
导行路水泥稳定碎石试验段选在DXK0+427.591-DXK0+994.954,总长567.363m,压实厚度为0.18m,试验段水泥稳定碎石分为两层,分别为底基层3.0Mpa/7d以及基层4.0Mpa/7d,摊铺方式采用双层联铺,强度按照基层4.0Mpa/7d执行,此段落作为水泥稳定碎石双层联铺试验段。The test section of the cement-stabilized gravel of the guide road is selected at DXK0+427.591-DXK0+994.954, with a total length of 567.363m and a compaction thickness of 0.18m. The cement-stabilized gravel in the test section is divided into two layers, which are the sub-base 3.0Mpa/7d and the base. 4.0Mpa/7d, the paving method adopts double-layer joint paving, and the strength is implemented according to the base layer 4.0Mpa/7d. This section is used as the test section of cement-stabilized gravel double-layer joint paving.
本工程所处区域属暖温带季风型大陆性半湿润干旱气候,春旱少雨,夏湿多雨,秋凉干燥,冬寒少雪。多年平均气温12.4℃,极端最高气温41.2℃,极端最低气温-22.2℃。多年平均降水量495.1毫米,极端最大年降水量931.8毫米,极端最小降水量207.3毫米。全年以偏北风最多,年平均风速2.1米/秒。历史极端最大风速为20米/秒。The area where the project is located has a warm temperate monsoon continental semi-humid arid climate, with little rain in spring, wet and rainy summer, cool and dry autumn, and cold winter with little snow. The annual average temperature is 12.4°C, the extreme maximum temperature is 41.2°C, and the extreme minimum temperature is -22.2°C. The annual average precipitation is 495.1 mm, the extreme maximum annual precipitation is 931.8 mm, and the extreme minimum precipitation is 207.3 mm. The northerly wind is the most throughout the year, with an annual average wind speed of 2.1 m/s. The extreme maximum wind speed in history is 20 m/s.
本项目所在场地地基基本稳定,地下水水位对工程建设影响较小,基本不存在软弱土、可液化土等问题,地面沉降问题发育程度弱。该场地15米深度范围内分布有第四系冲洪积堆积物,在垂向上具有明显的沉积韵律,水平方向上分布厚度较稳定。场地土主要划分为粉质黏土、粉土、粉砂、中砂等。场地地下水位埋深12.74-13.41米,场地非液化土层厚度和地下水位深度符合dw>d0+db-3,场地可不考虑液化影响,且本区标准冻深为0.6米。The foundation of the site where the project is located is basically stable, the groundwater level has little impact on the construction of the project, there are basically no problems such as soft soil and liquefiable soil, and the development of land subsidence is weak. The Quaternary alluvial deposits are distributed within 15 meters of the site, with obvious sedimentary rhythm in the vertical direction, and the distribution thickness in the horizontal direction is relatively stable. The site soil is mainly divided into silty clay, silt, silt, medium sand, etc. The groundwater level of the site is buried at a depth of 12.74-13.41 meters. The thickness of the non-liquefied soil layer and the depth of the groundwater table are in line with dw>d0+db-3. The site may not consider the impact of liquefaction, and the standard freezing depth in this area is 0.6 meters.
导行路双层联铺试验段施工方法,包括以下步骤。The construction method of the double-layer joint paving test section of the guide road includes the following steps.
一、在进行施工前,先按照以下步骤进行施工准备。1. Before construction, follow the steps below to prepare for construction.
1、场站准备1. Station preparation
(1)水泥稳定碎石采用商品拌合站成品料运至现场,商品拌合站位置在河北省廊坊市霸州市开发区大何庄村,运距为23.5公里,需要45分钟运至施工现场,商品站采用WCB-800型(800T/H)稳定土拌合设备,设备采用双拌缸,拌缸长度不小于5m,冷料仓5个,配备水流量计和水泥重量计,并能在操作室显示加水量和水泥用量,拌合设备计量准确,并经质量技术监督所检定合格,拌合楼电脑能随时记录分时段的生产配合比及产量以及总量累计,并可以储存或导出,并且拌合站安装监控。(1) The cement stabilized crushed stone is transported to the site by the finished material of the commercial mixing station. The commercial mixing station is located in Dahezhuang Village, Bazhou City Development Zone, Langfang City, Hebei Province. The transportation distance is 23.5 kilometers, and it takes 45 minutes to transport to the construction site. , Commodity station adopts WCB-800 (800T/H) stabilized soil mixing equipment, the equipment adopts double mixing cylinder, the length of mixing cylinder is not less than 5m, 5 cold silos, equipped with water flow meter and cement weight meter, and can be used in The operation room displays the amount of water added and the amount of cement. The mixing equipment is accurately measured and qualified by the quality and technical supervision institute. The computer of the mixing building can record the production mix ratio, output and total amount by time period at any time, and can store or export. And the mixing station is installed and monitored.
(2)料斗上方加设10cm×10cm的直径不小于φ16的钢筋方格网,筛除超出粒径规格的集料和杂物,料斗间设置挡板,高度不小于80cm。(2) Add a 10cm×10cm steel grid with a diameter of not less than φ16 above the hopper to screen out the aggregates and sundries that exceed the particle size specification, and set up baffles between the hoppers with a height of not less than 80cm.
(3)废料集中堆放,特别是运料车上未清空的废料。(3) Centralized stacking of waste, especially the waste that has not been emptied on the material transporter.
(4)拌合场地应干净、整洁,集料堆下不积水,设备停放有序。(4) The mixing site should be clean and tidy, there should be no water accumulation under the aggregate pile, and the equipment should be parked in an orderly manner.
(5)试验段方案经监理单位审批后,对作业班组进行技术和安全交底后,才可进行试验段施工。(5) After the plan of the test section is approved by the supervision unit, the construction of the test section can be carried out only after the technical and safety disclosures are made to the operation team.
2、原材准备2. Raw material preparation
由于水泥稳定碎石采用外购成品料运至施工现场,故施工单位进行过程材料与配合比的把控工作。Since the cement stabilized crushed stone is transported to the construction site by the purchased finished materials, the construction unit shall control the process materials and the mixing ratio.
(1)水泥(1) Cement
根据室内配合比设计验证,采用32.5普通硅酸盐水泥,进场水泥经试验室取样检测,各项技术指标要符合国家技术标准的要求。According to the design and verification of indoor mix ratio, 32.5 ordinary Portland cement is used, and the cement entering the site is sampled and tested by the laboratory, and various technical indicators must meet the requirements of national technical standards.
表1泥技术指标Table 1 Mud technical indicators
(2)粗集料:粗集料级配符合下表要求。(2) Coarse aggregate: The gradation of coarse aggregate meets the requirements of the following table.
表2粗集料技术指标Table 2 Technical Specifications of Coarse Aggregate
(3)细集料:细集料选用级配良好的石屑,细集料中小于0.075mm的颗粒含量应不大于15%,塑性指数不大于8%,并且集料的亚甲蓝值不大于10g/Kg,砂当量不小于50%。(3) Fine aggregates: fine aggregates are selected from stone chips with good gradation. The content of particles smaller than 0.075mm in the fine aggregates should not exceed 15%, the plasticity index should not exceed 8%, and the methylene blue value of the aggregates should not exceed 10%. More than 10g/Kg, the sand equivalent is not less than 50%.
表3细集料技术指标Table 3 Technical Specifications of Fine Aggregate
3、混合料组成设计3. Design of the composition of the mixture
混合料采用振动成型法进行配合比设计,调配矿质混合料级配,配制不同水泥剂量,水泥剂量配置2种,分别为4%、5%,4%水泥剂量现场实际检测结果为4.1,5%水泥剂量现场实际检测结果为5.4,5%水泥剂量符合设计图纸7d/4.0Mpa的要求,经过试验的理论配比以及其他指标如下:The mixture adopts the vibration molding method to design the mix ratio, mixes the mineral mixture gradation, and prepares different cement dosages. The cement dosage configuration is 2 kinds, respectively 4% and 5%. The actual test results of the 4% cement dosage are 4.1 and 5%. The actual test result of the cement dosage on site is 5.4, and the 5% cement dosage meets the requirements of the design drawing 7d/4.0Mpa. The tested theoretical ratio and other indicators are as follows:
表4混合料设计Table 4 Mixture Design
水泥稳定碎石7d浸水抗压强度应符合《公路路面基层施工技术规范》相关要求。The 7d water immersion compressive strength of cement-stabilized crushed stone should meet the relevant requirements of "Technical Specification for Construction of Highway Pavement Base".
为减少底基层裂缝,在满足设计强度的基础上控制水泥用量,水泥剂量控制在4%,最大不超过6%。在减少水泥量的同时,限制细集料、粉料用量;根据施工气候条件调整用水量。In order to reduce cracks in the sub-base, the cement dosage should be controlled on the basis of satisfying the design strength, and the cement dosage should be controlled at 4%, and the maximum should not exceed 6%. While reducing the amount of cement, limit the amount of fine aggregate and powder; adjust the water consumption according to the construction climatic conditions.
4、矿料级配4. Mineral grading
水泥稳定碎石的组成设计包括原材料质量检验,矿质混合料级配组成设计,确定必需的水泥剂量和混合料的最佳含水量等。拌合厂开始生产前,应根据现场集料进行设计配合比复验,复验合格的配合比作为标准配合比控制生产。The composition design of cement-stabilized crushed stone includes raw material quality inspection, mineral mixture gradation composition design, determination of necessary cement dosage and optimal water content of mixture, etc. Before the mixing plant starts production, the design mix ratio should be re-examined according to the on-site aggregate, and the re-examined mix ratio will be used as the standard mix ratio to control production.
表5水泥稳定碎石级配范围Table 5 Gradation range of cement stabilized crushed stone
5、底基层的生产配合比调试5. Debugging of the production mix ratio of the sub-base
当拌合设备调试完毕,材料组成设计完成后,应进行施工配合比调试。When the mixing equipment is debugged and the material composition design is completed, the construction mix ratio should be debugged.
第一阶段试生产:按设定的施工参数,不掺加水泥和水,在皮带上取料筛分,验证级配是否符合设计要求,必要时调整生产参数并做好相关的记录。The first stage of trial production: According to the set construction parameters, without adding cement and water, take and screen the material on the belt to verify whether the gradation meets the design requirements, adjust the production parameters if necessary, and make relevant records.
第二阶段试生产:先按设计配合比掺加水泥和水,然后按标准剂量的±1%调整剂量掺加水泥和水。分别取样进行含水量测定、水泥剂量测定、标准密度及无侧限抗压强度试验确定施工配合比指导施工。The second stage of trial production: firstly add cement and water according to the designed mix ratio, and then add cement and water according to ±1% of the standard dosage. Samples were taken for moisture content determination, cement dosage determination, standard density and unconfined compressive strength tests to determine the construction mix ratio to guide construction.
6、施工现场准备6. Construction site preparation
(1)路基交验:路基交验由总监办、施工单位方共同参与实现。(1) Subgrade inspection: Subgrade inspection shall be realized jointly by the superintendent's office and the construction unit.
(2)路基质量检查:应检查路基施工质量(高程、中线偏位、宽度、横坡度、平整度、压实度、反射裂缝、弯沉等)。(2) Subgrade quality inspection: The subgrade construction quality (elevation, midline offset, width, transverse slope, flatness, compaction, reflection cracks, deflection, etc.) should be checked.
(3)在水泥稳定碎石(4.0Mpa/7d)施工前应无过干、过湿现象,表面平整、无积水、无松散现象。(3) Before the cement stabilized gravel (4.0Mpa/7d) is applied, there should be no over-dry or over-wet phenomenon, and the surface should be smooth, without water accumulation and looseness.
二、导行路双层联铺试验段施工工艺流程如下2. The construction process of the double-layer combined paving test section of the guide road is as follows
工艺流程:如图2所示,下承层准备→测量放样→混合料拌合→混合料运输→混合料摊铺→混合料碾压→压实度检测→养生→成品验收→下一道工序。Process flow: As shown in Figure 2, lower bearing layer preparation → measurement and lofting → mixture mixing → mixture transportation → mixture paving → mixture rolling → compaction detection → preservation → finished product acceptance → next process.
1、下承层准备1. Preparation of the lower bearing layer
(1)底基层施工前下承层检查验收合格。包括高程、中线偏位、宽度、横坡度、平整度、反射裂缝、弯沉等。下承层表面应平整、坚实,具有合适的路拱和横坡,没有任何松散、软弱部位,边沿顺直,路肩平顺、整齐。(1) The inspection and acceptance of the lower bearing layer before the construction of the sub-base layer is qualified. Including elevation, midline offset, width, cross slope, flatness, reflection crack, deflection, etc. The surface of the lower bearing layer should be flat and solid, with suitable road crowns and cross slopes, without any loose and weak parts, with straight edges and smooth and tidy shoulders.
(2)在下承层内侧支设高180mm钢模板,钢模板支立牢固线条要顺直;在外侧先培土路肩,用小型压实机压实,达到规定的压实度后切边与底面垂直,再铺设塑料薄膜以防止水稳碎石边缘水份损失,摊铺宽度保证上层设计宽度要求。(2) A steel formwork with a height of 180mm is set up on the inner side of the lower bearing layer, and the firm line of the steel formwork should be straight and straight; on the outside, the road shoulder is first built, and compacted with a small compactor, and the cut edge is perpendicular to the bottom surface after reaching the specified degree of compaction , and then lay plastic film to prevent water loss at the edge of the water stabilized gravel, and the paving width ensures the design width of the upper layer.
(3)对下承层进行彻底清扫,并适量洒水,在施工过程当中,保持下承层表面湿润,以保证上下层之间的结合。(3) Thoroughly clean the lower bearing layer and sprinkle appropriate amount of water. During the construction process, keep the surface of the lower bearing layer moist to ensure the combination between the upper and lower layers.
2、测量放样2. Measure and stake out
(1)下承层经监理工程师检查验收合格后,采用GPS准确放样出中桩、边桩,确定摊铺的宽度,便于路肩培土。(1) After the lower bearing layer is checked and accepted by the supervision engineer, GPS is used to accurately set out the middle piles and side piles, and the width of the paving is determined to facilitate the road shoulder cultivation.
(2)用φ20mm的钢钎在两侧打设基准点,以此来严格控制高程,基准点高程为设计高程加20cm,基准点设立时,直线段每10米一个钢钎,曲线段每5米一个钢钎,挂钢丝绳要拉紧,保证基准线水平。(2) Use φ20mm steel drills to set datum points on both sides to strictly control the elevation. The elevation of the datum point is the design elevation plus 20cm. When the datum point is established, a steel drill is used for every 10 meters in the straight line segment, and every 5 meters in the curved segment. Meter a steel drill, the hanging wire rope should be tightened to ensure the level of the reference line.
(3)基准线采用φ5mm的钢丝固定在钢钎上,每段长度应小于200m,用紧线器拉紧,其拉力不小于1000N。(3) The reference line is fixed on the steel wire with φ5mm steel wire, the length of each section should be less than 200m, and the tension is not less than 1000N.
3、混合料的拌和3. Mixing of the mixture
(1)水泥稳定碎石混合料采用WCB800t/h的稳定土拌合设备进行拌合,拌合前对拌合设备进行反复检验调整,使拌合设备计量准确,并经质量技术监督所检定合格。(1) The cement stabilized crushed stone mixture is mixed with WCB800t/h stabilized soil mixing equipment. Before mixing, the mixing equipment is repeatedly inspected and adjusted, so that the mixing equipment is accurately measured and qualified by the Quality and Technical Supervision Institute. .
(2)采用3台ZL-50装载机给料斗上料,开工前对机手进行培训,铲料符合要求,减少上料时的离析现象的发生,供料均匀,不宜过满,料斗间用隔板分隔,避免串料现象发生。上料前试验人员应测定集料的含水率,避免集料含水率变化频繁,影响混合料的含水率。(2) Three sets of ZL-50 loaders are used to feed the hopper, and the operator is trained before the start of construction. The shovel meets the requirements, and the occurrence of segregation during feeding is reduced. The feeding is uniform and should not be overfilled. The partition is separated to avoid the phenomenon of stringing. Before feeding, the tester should measure the moisture content of the aggregate to avoid frequent changes in the moisture content of the aggregate and affect the moisture content of the mixture.
(3)开始正式拌合前,做集料筛分试验,检验碎石混合料级配是否满足要求,如有问题及时调整,严格控制19mm,9.5mm,4.75mm关键筛孔的通过率。当集料的颗粒级配发生变化时,应重新调整配合比,保证混合料级配符合设计要求。(3) Before starting the formal mixing, do the aggregate screening test to check whether the gradation of the crushed stone mixture meets the requirements. If there is any problem, adjust it in time, and strictly control the pass rate of the key sieve holes of 19mm, 9.5mm and 4.75mm. When the particle gradation of the aggregate changes, the mix ratio should be readjusted to ensure that the mix gradation meets the design requirements.
(4)混合料拌合要均匀,严禁出现花白料及离析现象,根据天气温度的变化及时调整含水率,一般控制在大于最佳含水率1.0%-2.0%左右,使混合料运至现场摊铺时的含水率不小于最佳含水率。(4) The mixture should be evenly mixed, and the phenomenon of whitening and segregation is strictly prohibited. The moisture content should be adjusted in time according to the change of weather and temperature. Generally, the moisture content should be controlled at about 1.0%-2.0% greater than the optimum moisture content, so that the mixture can be transported to the site for paving. The moisture content is not less than the optimum moisture content.
(5)拌合站现场试验员,检测拌合时混合料的水泥剂量、含水率和各种集料的配合比,并做好记录,发现异常时及时调整或停止生产。(5) The on-site tester of the mixing station shall detect the cement dosage, moisture content and the mixing ratio of various aggregates of the mixture during mixing, and make a record, and adjust or stop the production in time when any abnormality is found.
(6)各料斗配备1-2名工作人员及时清理料仓口超粒径石块及杂物,时刻监视下料情况,保证不出现卡堵现象,确保机械设备正常运转。(6) Each hopper is equipped with 1-2 staff members to clean the super-sized stones and sundries at the entrance of the hopper in time, and monitor the feeding situation at all times to ensure that there is no jamming phenomenon, and to ensure the normal operation of the mechanical equipment.
4、混合料的运输4. Transportation of mixed materials
(1)根据拌合能力(800t/h)、运输距离(约23.5Km)及摊铺速度(1.5m-2.0m/min),拟采用20辆载重50t以上大吨位自卸车运输,自卸车车厢应清理干净,不得有剩余料或水积聚在车厢底部。(1) According to the mixing capacity (800t/h), transportation distance (about 23.5Km) and paving speed (1.5m-2.0m/min), 20 large-tonnage dump trucks with a load of more than 50t are planned to be transported. It should be cleaned up and no residual material or water should accumulate on the bottom of the carriage.
(2)从拌和楼向运料车上放料时,出料口距车厢槽帮最高点距离不得大于50cm,采取三次卸料法,以减少粗细集料的离析现象。(2) When discharging materials from the mixing building to the material transporter, the distance between the discharge port and the highest point of the trough of the carriage shall not be greater than 50cm, and the three-time discharge method shall be adopted to reduce the segregation of coarse and fine aggregates.
(3)自卸车装料后,采用不透水篷布覆盖,篷布下缘到达槽帮的2/3(由上至下计算)并绑扎牢固,避免水份损失,以免影响压实及成型效果。(3) After the dump truck is loaded, it is covered with an impermeable tarpaulin. The lower edge of the tarpaulin reaches 2/3 of the groove (calculated from top to bottom) and is tied firmly to avoid water loss and affect the compaction and forming effect.
(4)运输车辆出场时,过磅、开具出场单,标明吨位、出场时间、车数编号一式四份,存根磅房留存,混合料到现场后,施工人员查看出场单及目测混合料的质量,对于时间过长的混合料予以废除,摊铺后签收出场单,并写明摊铺时间。(4) When the transport vehicle comes out, weigh and issue an out-of-field order, indicating the tonnage, appearance time, and number of vehicles in quadruplicate, and keep the stub in the weighing room. For the mixture that is too long, it will be abolished. After paving, sign and receive the exit list, and indicate the paving time.
(5)运输车由专人进行负责指挥,装有联络通讯工具,及简单的维修工具,车辆出现问题能够及时沟通处理,保证车辆出现故障后,能够及时抢修,能在最短的时间内恢复运转。(5) The transport vehicle is commanded by a special person, equipped with liaison communication tools and simple maintenance tools. The vehicle can be communicated and dealt with in a timely manner to ensure that after the vehicle fails, it can be repaired in time and can resume operation in the shortest time.
(6)运输车卸料时,设专人指挥,使运输车在摊铺机前方30cm左右停车,挂空挡,摊铺机前进碰到运输车,由工人敲开运输车后挡门栓,运输车料斗分三次起升,让混合料自然卸到摊铺机料斗中,避免自卸车起升过快,粗集料滚落集中造成局部离析,运输车司机与摊铺机操作手密切配合,边前进边卸料,卸料速度与摊铺速度相协调,避免运输车撞击摊铺机以及将混合料卸在摊铺机外面。(6) When the transporter is unloading, a special person shall be set up to direct the transporter to stop the transporter about 30cm in front of the paver and put it in neutral gear. The hopper is lifted in three times, so that the mixed material is naturally unloaded into the paver hopper, to avoid the dump truck lifting too fast, and the coarse aggregate rolling down concentratedly causing partial segregation. The transporter driver and the paver operator closely cooperate to move forward Side unloading, the unloading speed is coordinated with the paving speed, to avoid the transporter hitting the paver and unloading the mixture outside the paver.
5、混合料的摊铺5. Paving of the mixture
摊铺前下承层清扫干净,无杂物,并洒水湿润,洒水量不宜过大或过小,以不流淌为准;摊铺时保持下承层处于湿润状态,随洒随铺,洒水不宜过量。Before paving, the lower bearing layer should be cleaned, free of debris, and sprinkled with water. excess.
(1)摊铺机型号:两台徐工摊铺机,型号分别为:903、953T(1) Paver model: two XCMG paver models: 903, 953T
水泥稳定碎石4.0Mpa/7d分上下基层,一般路段下基层设计摊铺宽度为10.81,基层设计摊铺宽度为10.48;两台摊铺机组装宽度分别为6.5m和4.50m。Cement-stabilized gravel 4.0Mpa/7d is divided into upper and lower bases. In general, the designed paving width of the lower base is 10.81, and the design paving width of the base is 10.48; the assembly widths of the two paver are 6.5m and 4.50m respectively.
松铺系数分两段验证分别为:The loose paving coefficient is verified in two stages:
①DXK0+427.591-DXK0+677.591段松铺系数拟采用1.25,松铺厚度=18cm×1.25=22.5cm,施工时按22.5cm松铺厚度控制。①The loose laying coefficient of DXK0+427.591-DXK0+677.591 section is planned to be 1.25, the loose laying thickness=18cm×1.25=22.5cm, and the loose laying thickness of 22.5cm shall be controlled during construction.
②DXK0+677.591-DXK0+994.954段松铺系数拟采用1.30,松铺厚度=18cm×1.30=23.4cm,施工时按23.5cm松铺厚度控制,根据压实后的厚度检测及时调整。②The loose laying coefficient of DXK0+677.591-DXK0+994.954 section is planned to be 1.30, the loose laying thickness=18cm×1.30=23.4cm, the loose laying thickness of 23.5cm shall be controlled during construction, and the thickness shall be adjusted in time according to the thickness detection after compaction.
(2)采用两台摊铺机梯形作业(外侧摊铺机在前,内侧摊铺机在后)。前面摊铺机外侧采用标高基准线控制,路中采用6m长导梁控制;后面摊铺机外侧采用标高基准线控制;前后摊铺机相距不超过10m,横向搭接宽度30cm。异型路段人工铺筑时,采用挂线控制标高。摊铺机就位具体做法如下:在摊铺起点,将摊铺机熨平板升起,按照虚铺厚度将已加工好的枕木放在下面,放置平衡,满足虚铺厚度要求,然后落下熨平板,检查螺旋送料器的运转情况和传感器的灵敏度,保证机械能够正常运转。(2) Trapezoidal operation with two pavers (outside paver is in front and inner paver is behind). The outer side of the front paver is controlled by the elevation reference line, and the road is controlled by a 6m long guide beam; the outer side of the rear paver is controlled by the elevation reference line; the distance between the front and rear paver is not more than 10m, and the horizontal lap width is 30cm. When artificially paving special-shaped sections, use hanging lines to control the elevation. The specific method of placing the paver in place is as follows: at the starting point of paving, raise the paver screed, place the processed sleepers below according to the thickness of the virtual paving, place it in a balanced manner to meet the requirements of the thickness of the virtual paving, and then lower the screed. , Check the operation of the screw feeder and the sensitivity of the sensor to ensure the normal operation of the machine.
(3)正常摊铺时,每台摊铺机前有2~3辆运输车在等待卸料,以保证连续、均匀地摊铺。卸料时运输车起斗角度应尽量大些,使混合料整体塌落,以避免卸料时产生离析。摊铺时,螺旋送料器要匀速送料,杜绝高速运转,避免粗骨料集中滚落造成底部混合料离析;摊铺速度要均匀,控制在1.5m-2.0m/min,中途不得变速,摊铺不停顿、间断,运料车倒车、卸料尽量连续,不能造成摊铺停机待料;要保持储料室内料位稳定,并使摊铺机的螺旋布料器均衡向两侧供料,螺旋布料器料位略高于螺旋布料器,满埋螺旋低速输料,使熨平板挡板前混合料在全宽范围内保持一致,避免摊铺层出现离析现象。(3) During normal paving, there are 2 to 3 transport vehicles waiting for unloading in front of each paver to ensure continuous and even paving. When unloading, the bucket angle of the transport truck should be as large as possible, so that the mixture will collapse as a whole, so as to avoid segregation during unloading. When paving, the screw feeder should feed at a uniform speed to prevent high-speed operation, and avoid the separation of the bottom mixture caused by the concentrated rolling of the coarse aggregate; the paving speed should be uniform and controlled at 1.5m-2.0m/min. Do not stop or interrupt, and the material transporter should be reversed and unloaded as continuously as possible, so as not to cause the paving to stop and wait for materials; to keep the material level in the storage room stable, and to make the paver auger evenly supply material to both sides, spiral material The material level of the auger is slightly higher than that of the auger, and the auger is fully buried and the material is conveyed at a low speed, so that the mixture before the screed baffle is consistent in the full width, and the segregation of the paving layer is avoided.
(4)摊铺时,摊铺机两侧设专人看管传感器,保证基准线不被扰动。同时采用拉线,随时检测下返高度,以便发现问题及时与摊铺机操作手沟通,进行调整,确保摊铺厚度,避免出现波浪式表面。摊铺过程中及时检测松铺厚度。(4) When paving, there are special personnel on both sides of the paver to take care of the sensors to ensure that the baseline is not disturbed. At the same time, the pull line is used to detect the lower return height at any time, so as to find the problem and communicate with the paver operator in time to make adjustments to ensure the thickness of the paving and avoid wavy surfaces. The loose thickness is detected in time during the paving process.
(5)每台摊铺机前要有2人清理履带前的粒料。每台摊铺机后设1名工人对摊铺后的表面进行检查,对异常混合料及时换填,并通知前场负责人,便于及时分析异常混合料产生原因,与试验负责人、拌和负责人沟通解决;对粗细集料离析现象,特别是局部粗集料窝要铲除,并用筛子筛细混合料人工找补。(5) Before each paver, two people should clean the pellets before the track. A worker is set behind each paver to check the surface after paving, replace the abnormal mixture in time, and notify the person in charge of the front field, so as to analyze the cause of the abnormal mixture in time, and communicate with the person in charge of the test and the person in charge of mixing. The problem of segregation of coarse and fine aggregates, especially the local coarse aggregate nests, should be eliminated, and the fine mixture should be sieved with a sieve to make up for it manually.
(6)摊铺机操作手应时时观察混合料的状态,如发现含水量过小、混合料颜色差异性大(水泥含量小)、拌合不均匀等情况,应立即停止摊铺并通知现场技术人员处理。(6) The paver operator should observe the state of the mixture from time to time. If it is found that the water content is too small, the color difference of the mixture is large (small cement content), and the mixing is uneven, etc., they should immediately stop paving and notify the scene. Technicians handle.
(7)运输车离开时撒在地上的混合料,立即铲除,避免摊铺机履带压在上面而影响摊铺面平整度。设专人用6m直尺纵、横向量测,对平整度差的部位用人工铲除找平。(7) The mixture that is scattered on the ground when the transport vehicle leaves should be removed immediately to prevent the paver track from pressing on it and affecting the smoothness of the paving surface. Set up a special person to measure vertically and horizontally with a 6m ruler, and manually remove and level the parts with poor flatness.
6、混合料的碾压6. Rolling of the mixture
(1)水泥稳定碎石混合料在摊铺30~50m长度后,压路机即可在全宽范围内进行碾压。碾压时,驱动轮朝向摊铺机方向,由路边向路中、先轻后重、先慢后快、低速行驶碾压的原则,避免出现推移、起皮和漏压的现象。严禁压路机在碾压成型或正在碾压路段调头或急刹车。(1) After the cement-stabilized gravel mixture is paved with a length of 30-50m, the road roller can be rolled over the full width. When rolling, the driving wheel should face the direction of the paver, from the roadside to the middle of the road. It is strictly forbidden for the roller to make a U-turn or brake suddenly in the rolling or rolling section.
(2)碾压工艺:(2) Rolling process:
碾压机械:2台22t轮胎式振动压路机、1台30t胶轮压路机和1台13t双钢轮压路机。为确定水稳碎石底基层试验段压实效果,拟采用两种碾压方式(选择一种最佳碾压组合):Rolling machinery: 2 sets of 22t tire vibratory road rollers, 1 set of 30t rubber tire road rollers and 1 set of 13t double drum road rollers. In order to determine the compaction effect of the water-stabilized gravel subbase test section, two rolling methods are proposed (choose an optimal rolling combination):
DXK0+427.591-DXK0+677.591段采用碾压方式一:DXK0+427.591-DXK0+677.591 segment adopts rolling method 1:
初压:(稳压)采用胶轮轮压路机,外侧留30cm不碾压(防止溜肩),压路机以2.5km/h行走速度碾压一遍,停机接头形成45度梯形碾压一遍,使摊铺好的混合料经初压成稳定状态。Preliminary pressure: (pressure stabilization) A rubber wheel roller is used, leaving 30cm on the outside without rolling (to prevent shoulder slipping), the road roller is rolled once at a walking speed of 2.5km/h, and the stop joint is rolled once in a 45-degree trapezoid to make the paving A good mixture is initially pressed into a stable state.
复压:(密实)采用22吨振动压路机错1/2轮,轻振一遍、重振三遍,碾压速度控制在2.0km/h。Re-compression: (compacting) 22-ton vibratory rollers are used to stagger 1/2 round, vibrate once and revive three times, and control the rolling speed at 2.0km/h.
终压:采用30t胶轮压路机碾压两遍收面。Final pressure: Use a 30t rubber wheel roller to roll twice to close the surface.
DXK0+677.591-DXK0+994.954段采用碾压方式二:DXK0+677.591-DXK0+994.954 segment adopts rolling method 2:
初压:(稳压)采用钢轮压路机,压路机以2.5km/h行走速度碾压一遍,停机接头形成45度梯形碾压一遍,使摊铺好的混合料经初压成稳定状态。Initial pressure: (pressure stabilization) Drum roller is used, the roller is rolled once at a walking speed of 2.5km/h, and the stop joint forms a 45-degree trapezoidal rolling once, so that the paved mixture is initially pressed into a stable state.
复压:(密实)采用22吨振动压路机错1/2轮,轻振一遍、重振两遍、轻振一遍,碾压速度控制在2.0km/h。Re-compression: (compacting) 22-ton vibratory rollers are used to stagger 1/2 round, vibrate once, reinvigorate twice, and vibrate once, and control the rolling speed at 2.0km/h.
终压:采用胶轮压路机碾压两遍,再用钢轮压路机碾压一遍收面。Final pressing: Roll the surface twice with a rubber wheel roller, and then roll it once with a steel wheel roller to close the surface.
单钢轮振动压路机重振两遍后,用灌砂法检测压实度是否合格,若不合格应增加碾压遍数,压实度检测频率每200m每车道2处(试验段检测频率加倍)。After the single-drum vibratory roller is revitalized twice, use the sand filling method to test whether the compaction degree is qualified. If it is unqualified, the number of times of rolling should be increased. The compaction degree detection frequency is 2 points per 200m per lane (the detection frequency of the test section is doubled) .
(3)压路机倒车应自然停车,无特殊情况,不许刹车;换挡要轻且平顺,不要拉动基层。在第一遍初步稳压时,倒车后应原路返回,换挡位置应在已压好的段落上,在未碾压的一头换挡倒车位置错开,要成齿状,出现个别翻浆、起皮时,应进行铲平处理。(3) The roller should stop naturally when reversing, and no brakes are allowed unless there are special circumstances; the gear shift should be light and smooth, and do not pull the grassroots. During the first preliminary voltage stabilization, return to the original road after reversing, the shifting position should be on the already pressed section, and the shifting and reversing position on the unrolled end should be staggered, and it should be tooth-shaped, and there will be individual pulping, starting When peeling, it should be leveled.
(4)压路机停车要错开,相隔间距不小于3m,应停在已碾压好的路段上。严禁压路机在刚完成的或正在碾压的路段上调头和急刹车。碾压宜在水泥初凝前及试验确定的延迟时间内完成,达到要求的压实度,同时没有明显的轮迹。(4) The rollers should be parked in a staggered manner, with an interval of not less than 3m, and should be parked on the road section that has been rolled. It is strictly forbidden for the roller to turn around and brake suddenly on the road that has just been completed or is being rolled. The rolling compaction should be completed before the initial setting of the cement and within the delay time determined by the test to achieve the required degree of compaction without obvious wheel tracks.
(5)混合料加水拌合至碾压成型时间,不得超过水泥初凝时间。(5) The mixture is mixed with water until the time of rolling and molding, which shall not exceed the initial setting time of the cement.
(6)平整度检测及处理:复压完成后对碾压隆起部位人工处理,设专人用6m直尺进行平整度检测,每车道检测。(6) Flatness detection and treatment: After the recompression is completed, the rolling bulge is manually processed, and a special person is assigned to use a 6m ruler to test the flatness, and each lane is tested.
7、接缝处理7. Seam processing
(1)横向接缝(1) Transverse seam
混合料摊铺时不宜中断,如因故中断超过2小时或每天施工结束后应设横向施工缝。将摊铺机驶离混合料末端,用人工把含水量合适的混合料补齐。垂直于路中心线放置方木,方木高度同压实层厚度相等,碾压密实。用6m直尺检测平整度,确定切割范围并划线,沿线将平整度不合格的混合料铲除。重新铺筑混合料之前将下承层清理干净,接缝处涂刷水泥浆。It is not advisable to interrupt the paving of the mixture. If it is interrupted for more than 2 hours or after the construction every day, horizontal construction joints should be set up. Drive the paver away from the end of the mix, and manually make up the mix with the proper moisture content. Place square wood perpendicular to the road centerline, the height of the square wood is equal to the thickness of the compaction layer, and the rolling is dense. Use a 6m ruler to test the flatness, determine the cutting range and draw a line, and remove the mixture with unqualified flatness along the line. Before re-laying the mix, clean the underlayer and apply grout to the joints.
(2)纵向接缝(2) Longitudinal seams
避免纵向接缝,在必须分两幅施工时,纵缝必须垂直相等,不允许斜接。Avoid longitudinal joints. When construction must be divided into two pieces, the longitudinal joints must be vertically equal, and miter joints are not allowed.
8、养生8. Health
(1)水泥稳定碎石混合料碾压完成,检测合格后及时覆盖透水式土工布洒水进行养生,两幅间应相互搭接20cm以上,保证表面湿润。(1) The cement-stabilized crushed stone mixture is rolled and compacted. After passing the test, it should be covered with permeable geotextiles and sprinkled with water in time. The two sheets should overlap each other by more than 20cm to ensure that the surface is moist.
(2)养生期内,除洒水车外任何车辆禁止通行,采用高度1.5m的标识栏杆进行横向全幅布设并设置“禁止通行”标识牌,设专人进行看管。(2) During the health preservation period, all vehicles except the sprinkler are prohibited from passing through. The sign railings with a height of 1.5m are used for horizontal full-width layout, and a "No Pass" sign is set up, and a special person is assigned to take care of it.
(3)养生期不少于7天,每天完成段设置养生天数标识牌,前三天洒水次数每天至少6次以上,之后以保持表面湿润为度,每个作业面设专人负责养生工作。(3) The health preservation period is not less than 7 days, and the number of health care days signs will be set up in the completed section every day. The number of waterings for the first three days should be at least 6 times a day. After that, the surface should be kept moist, and each working surface should be assigned a special person to be responsible for the health preservation work.
9、质量检验9. Quality inspection
(1)粒料应符合设计和施工规范要求,并应根据当地料源选择质坚干净粒料。(1) The pellets should meet the requirements of design and construction specifications, and the firm and clean pellets should be selected according to the local source.
(2)水泥用量和矿料级配应按设计控制准确。(2) The amount of cement and mineral grading should be controlled accurately according to the design.
(3)摊铺时应注意消除离析现象,尤其是带状离析和窝状离析。(3) When paving, attention should be paid to eliminate segregation, especially band segregation and nest segregation.
(4)混合料应处于最佳含水量状况下,用压路机碾压至要求的压实度。从加水拌合到碾压终了的时间不应超过水泥初凝时间。(4) The mixture should be in the best moisture content condition, and it should be rolled with a road roller to the required degree of compaction. The time from mixing with water to the end of rolling should not exceed the initial setting time of cement.
(5)碾压检查合格后应立即覆盖或洒水养生,养生期应符合规范要求。(5) After the rolling inspection is passed, it should be covered or sprinkled with water immediately, and the curing period should meet the requirements of the specification.
(6)表面平整密实、边线整齐、无松散、坑洼、软弹现象,施工接茬平顺。(6) The surface is flat and dense, the edges are neat, there is no looseness, potholes, and soft elastic phenomena, and the construction is smooth.
实测项目如图3所示。The measured items are shown in Figure 3.
10、外观要求10. Appearance requirements
(1)表面平整密实、无坑洼、无明显离析。(1) The surface is smooth and compact, without potholes and obvious segregation.
(2)施工接茬平整、稳定。(2) The construction stubble is smooth and stable.
三、保障措施3. Safeguard measures
1、混合料拌合质量(含水量、水泥剂量、矿料级配)1. Mixing quality of the mixture (water content, cement dosage, mineral gradation)
含水量是水稳碎石碾压的关键,当实际含水量W接近最佳含水量(W0)时,压实度才能保证,当W>W0时,水分过大碾压时容易“弹簧”,且在振动碾压时,容易将水泥浆集聚在表面。这样在取芯检查时,试件下部易出现松散或强度不够,当W<W0,水稳层容易松散,碾压不密实,造成强度不足。为保证含水量合适,应设专人检测含水量,并根据气候情况及时调整拌合含水量。Moisture content is the key to water-stabilized crushed stone rolling. When the actual water content W is close to the optimal water content (W0), the degree of compaction can be guaranteed. And during vibrating rolling, it is easy to accumulate cement slurry on the surface. In this way, when the core is checked, the lower part of the specimen is prone to loosening or insufficient strength. When W<W0, the water stable layer is prone to loosening, and the rolling is not compact, resulting in insufficient strength. In order to ensure that the water content is appropriate, a special person should be set up to detect the water content and adjust the mixing water content in time according to the weather conditions.
水泥剂量是水泥稳定碎石强度是否合格的关键,拌合过程当中必须时时检测,并调整设备性能,保证水泥剂量。为保证水泥剂量,拌合时,水泥剂量宜比设计增加0.5%。每半天进行一次混合料筛分,保证矿料级配准确,级配发生变化时,计算进行调整。The cement dosage is the key to whether the strength of the cement stabilized crushed stone is qualified. During the mixing process, it must be checked from time to time, and the performance of the equipment should be adjusted to ensure the cement dosage. In order to ensure the cement dosage, the cement dosage should be increased by 0.5% compared with the design during mixing. The mixture is screened every half a day to ensure the accurate grading of the ore. When the grading changes, the calculation is adjusted.
2、混合料的离析2. Segregation of the mixture
为尽可能减少混合料的离析,要求做到以下几点要求:In order to minimize the segregation of the mixture, the following requirements are required:
(1)水稳混合料在搅拌站输出时,应尽量降低出料高度,成品仓应间歇放料。(1) When the water-stabilized mixture is output in the mixing station, the discharge height should be reduced as much as possible, and the finished product warehouse should be discharged intermittently.
(2)成品仓放料口距运料车厢的垂直距离不宜大于0.5m,运料车应及时移动前后位置,保证均匀装料,以降低每次装料的堆体高度。(2) The vertical distance between the discharge port of the finished product warehouse and the material transport carriage should not be greater than 0.5m. The material transporter should move the front and rear positions in time to ensure uniform loading and reduce the stack height of each loading.
(3)运料车辆在运输过程中,应匀速行驶,起步刹车要平稳,路况差时应慢行,避免强烈的颠簸振动。(3) During the transportation process, the material transport vehicle should drive at a uniform speed, and the starting brake should be stable. When the road conditions are poor, it should drive slowly to avoid strong bumps and vibrations.
(4)运料车辆在向摊铺机受料斗卸料时,应缓慢均匀地提升车厢,切忌速度太快。(4) When the material transport vehicle is unloading to the paver hopper, it should lift the carriage slowly and evenly, and avoid the speed too fast.
(5)摊铺过程中,摊铺机的螺旋布料器应有三分之二埋入混合料中,应使螺旋布料器均匀地运转,切忌或快或慢。在摊铺机后面应设专人消除细集料离析现象,特别应该铲除局部粗集料“窝”,并用新拌混合料填补。(5) During the paving process, two-thirds of the auger of the paver should be buried in the mixture, and the auger should be run evenly, and should not be fast or slow. A special person should be set up behind the paver to eliminate the segregation of fine aggregates, especially the local "nests" of coarse aggregates should be removed and filled with freshly mixed materials.
(6)人工找平时,应扣锹布料,切忌扬锹远抛,同时,刮爬拖动次数不大于2次。(6) When leveling manually, the shovel fabric should be buckled, and the shovel should not be thrown far away. At the same time, the number of scraping and dragging should not be more than 2 times.
(7)摊铺设备布料螺栓加反向叶片,并调整好角度,防止离析。(7) Paving equipment cloth bolts and reverse blades, and adjust the angle to prevent segregation.
(8)适当减少摊铺机收斗次数,尽量不收斗。(8) Appropriately reduce the number of times the paver is retracted, and try not to retract the bucket.
(9)适当降低熨平板高度。(9) Appropriately reduce the height of the screed.
(10)摊铺机螺旋布料器后加橡胶垫,防止大料向后滚落造成上下离析。(10) Add a rubber pad to the rear of the paver auger to prevent the large material from rolling backwards and causing upper and lower segregation.
3、平整度3. Flatness
水稳基层的平整度事关面层施工质量,如果控制不好,一方面会影响面层的平整度,另一方面会造成面层的厚度难以控制。为保证水稳层平整度,做到以下几点:The flatness of the water stabilization base is related to the construction quality of the surface layer. If the control is not good, on the one hand, it will affect the flatness of the surface layer, and on the other hand, the thickness of the surface layer will be difficult to control. In order to ensure the smoothness of the water stable layer, do the following:
(1)水稳基层的下承层必须达到规定的平整度要求后,才能进行水稳基层的摊铺,若下承层表面是平整度很差的波浪状,则势必会反射至基层表面,而造成基层表面的平整度难以控制。(1) The lower bearing layer of the water-stabilized base must meet the specified flatness requirements before the water-stabilized base can be paved. If the surface of the lower bearing is wavy with poor flatness, it will inevitably reflect to the surface of the base. As a result, the flatness of the base surface is difficult to control.
(2)碾压宜在水泥初凝前及试验确定的延迟时间内完成,并达到要求压实度,同时没有明显的轮迹。严格按照施工方案碾压工艺进行碾压,防止出现波浪,影响平整度。(2) The rolling compaction should be completed before the initial setting of the cement and the delay time determined by the test, and the required compaction degree should be achieved, and there is no obvious wheel track. Rolling is carried out in strict accordance with the rolling process of the construction plan to prevent waves and affect the flatness.
(3)人工找平时,应选用经验丰富、责任心强的人员负责找平,同时要配备6m左右的直尺辅助检查不平整处。(3) For manual leveling, experienced and responsible personnel should be selected to be responsible for leveling, and at the same time, a ruler of about 6m should be equipped to assist in checking the unevenness.
(4)摊铺机铺装过程中,应保证连续均匀地摊铺,摊铺机前方应有运料车辆在等候卸料,否则摊铺机经常停顿会影响平整度。(4) During the paving process of the paver, it should be ensured that the paving is continuous and even, and there should be a transport vehicle in front of the paver waiting to unload, otherwise the frequent stop of the paver will affect the flatness.
(5)碾压完毕立即做压实度试验,若试验结果达不到标准重新进行碾压。(5) Do the compaction test immediately after the rolling is completed. If the test result fails to meet the standard, carry out the rolling again.
(6)严格控制混合料的用水量,避免含水率过大或过小。(6) Strictly control the water consumption of the mixture to avoid too large or too small moisture content.
4、碾压质量4. Rolling quality
为保证水泥稳定碎石基层的压实度,压实机械是关键,对压实设备能力要求较高。施工过程中必须严格按照试验段确定的碾压组合,配备压路机,保证压实度。质量保证措施In order to ensure the compaction of the cement-stabilized gravel base, compaction machinery is the key, and the capacity of compaction equipment is relatively high. During the construction process, the rolling combination determined in the test section must be strictly followed, and a road roller must be equipped to ensure the degree of compaction. Quality Assurance Measures
5、建立“横向到边、纵向到底、控制有效”的质量检验体系。项目经理部组织严密完善的职能管理机构,按照质量保证体系正常运转的要求,依据分工负责,相互协调的管理原则,层层落实职能、责任、风险和利益,保证在整个工程施工过程中,质量保证体系的正常动作及发挥保障作用。5. Establish a quality inspection system of "horizontal to edge, vertical to the end, and effective control". The project management department organizes a well-organized and perfect functional management organization, in accordance with the requirements of the normal operation of the quality assurance system, according to the management principle of division of labor and mutual coordination, and implements functions, responsibilities, risks and interests layer by layer to ensure that in the entire project construction process, quality, quality To ensure the normal operation of the system and play a role in safeguarding.
6、施工过程质量控制6. Quality control during construction
6.1、原材料6.1. Raw materials
(1)水泥、碎石等材料必须经监理工程师批准,未经批准的不允许使用。(1) Materials such as cement and crushed stone must be approved by the supervising engineer, and those without approval are not allowed to be used.
(2)水泥:选用终凝时间较长(宜在6小时以上)的水泥,宜用32.5水泥。快硬水泥、早强水泥以及受潮变质的水泥严禁使用。(2) Cement: Cement with a longer final setting time (preferably more than 6 hours) should be used, and 32.5 cement should be used. Fast-hardening cement, early-strength cement and cement that has been deteriorated by moisture are strictly prohibited.
(3)碎石:要求其压碎值不超过26%,最大粒径不大于31.5mm;碎石的颗粒组成应符合规范级配要求。小于0.075mm的颗粒含量应小于20%的要求。(3) Crushed stone: the crushing value is required not to exceed 26%, and the maximum particle size is not greater than 31.5mm; the particle composition of the crushed stone should meet the specification gradation requirements. The content of particles less than 0.075mm should be less than the requirement of 20%.
(4)水:采用饮用水。(4) Water: use drinking water.
6.2、混合料的组成设计6.2. Composition design of mixture
(1)组成设计原则:粉料含量不宜过多;在达到强度的前提下,采用最佳水泥剂量;改善集料级配,减少水泥用量。(1) Composition design principle: the powder content should not be too much; on the premise of reaching the strength, the optimal cement dosage should be adopted; the aggregate gradation should be improved and the cement dosage should be reduced.
(2)不断优化施工配合比,使其强度、压实度达到最优。(2) Continuously optimize the construction mix ratio to optimize its strength and compaction.
6.3、水泥稳定基层混合料的拌合6.3. Mixing of cement stabilized base mix
拌和站配制混合料,灰剂量、含水量、级配都要符合设计值。由于机器运行误差、气候等因素的影响,混合料各种指标偏离设计值。试验检测人员应及时监测、调整,使之保持在设计值内。When the mixing station prepares the mixture, the amount of ash, water content and gradation must conform to the design values. Due to the influence of factors such as machine operating error and climate, various indicators of the mixture deviate from the design values. Test personnel should monitor and adjust in time to keep it within the design value.
6.4、控制混合料含水量6.4. Control the water content of the mixture
拌和站从出料含水量应高于最佳含水率1%左右,到摊铺碾压前,混合料含水量平均损失1%左右。The moisture content of the mixing station should be about 1% higher than the optimal moisture content from the discharge, and the average moisture loss of the mixture is about 1% before the paving and rolling.
6.5、水泥稳定基层混合料的运输6.5. Transportation of cement stabilized base mix
运料车必须有篷布覆盖,装料后立即覆盖,直至卸料时方可取下覆盖篷布,防止水分蒸发影响摊铺、碾压质量。The truck must be covered with a tarpaulin, which should be covered immediately after loading, and the tarpaulin may not be removed until unloading to prevent water evaporation from affecting the quality of paving and rolling.
6.6、水泥稳定基层混合料的摊铺6.6. Paving of cement stabilized base mix
混合料从出拌和站到摊铺地点,应尽量缩短时间,在水泥的初凝时间内完成拌和、运输、摊铺、碾压等。From the mixing station to the paving site, the time should be shortened as much as possible, and the mixing, transportation, paving, rolling, etc. should be completed within the initial setting time of the cement.
6.7、水泥稳定基层混合料的碾压6.7. Rolling of cement stabilized base mix
碾压时应遵循碾压原则,设专人检测平整度。When rolling, the rolling principle should be followed, and a special person should be set up to check the flatness.
严格按照以上步骤进行,从原料的准备,混料到运输进行严格控制,按照以下工艺进行,下承层准备→测量放样→混合料拌合→混合料运输→混合料摊铺→混合料碾压→压实度检测→养生→成品验收→下一道工序,减少了返工过程,提升了试验段施工的质量和效率。Strictly follow the above steps, and strictly control from the preparation of raw materials, mixing to transportation, and carry out the following process: preparation of the lower bearing layer → measurement and lofting → mixing of the mixture → transportation of the mixture → paving of the mixture → rolling of the mixture →Compact degree detection →Health care →Finished product acceptance →The next process reduces the rework process and improves the quality and efficiency of the construction of the test section.
以上对本发明的一个实施例进行了详细说明,但所述内容仅为本发明的较佳实施例,不能被认为用于限定本发明的实施范围。凡依本发明申请范围所作的均等变化与改进等,均应仍归属于本发明的专利涵盖范围之内。An embodiment of the present invention has been described in detail above, but the content is only a preferred embodiment of the present invention, and cannot be considered to limit the scope of the present invention. All equivalent changes and improvements made according to the scope of the application of the present invention should still belong to the scope of the patent of the present invention.
Claims (9)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202210109238.2A CN114381981A (en) | 2022-01-28 | 2022-01-28 | Construction method of double-layer combined paving test section of guide road |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202210109238.2A CN114381981A (en) | 2022-01-28 | 2022-01-28 | Construction method of double-layer combined paving test section of guide road |
Publications (1)
Publication Number | Publication Date |
---|---|
CN114381981A true CN114381981A (en) | 2022-04-22 |
Family
ID=81204464
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202210109238.2A Pending CN114381981A (en) | 2022-01-28 | 2022-01-28 | Construction method of double-layer combined paving test section of guide road |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN114381981A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115125800A (en) * | 2022-05-31 | 2022-09-30 | 北京市首发天人生态景观有限公司 | Multifunctional plant material concrete paving equipment |
CN115450090A (en) * | 2022-10-20 | 2022-12-09 | 中电建路桥集团有限公司 | Digital autonomous double-layer paving device and method |
WO2024092998A1 (en) * | 2022-11-01 | 2024-05-10 | 中国港湾工程有限责任公司 | Saturated-water vibrating compaction construction process for graded crushed stone |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
RU2135671C1 (en) * | 1998-08-31 | 1999-08-27 | Селиванов Николай Павлович | Motor road and method of its operation together with repair and reconstruction |
CN112982058A (en) * | 2019-12-14 | 2021-06-18 | 浙江建腾建设有限公司 | Vibration mixing construction method for cement stabilized macadam |
CN113123197A (en) * | 2021-04-21 | 2021-07-16 | 鹏图建设有限公司 | Method and process for stabilizing macadam base with cement |
CN113403914A (en) * | 2021-05-31 | 2021-09-17 | 广州市土木金建筑工程有限公司 | Municipal road asphalt concrete pavement construction detection method |
-
2022
- 2022-01-28 CN CN202210109238.2A patent/CN114381981A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
RU2135671C1 (en) * | 1998-08-31 | 1999-08-27 | Селиванов Николай Павлович | Motor road and method of its operation together with repair and reconstruction |
CN112982058A (en) * | 2019-12-14 | 2021-06-18 | 浙江建腾建设有限公司 | Vibration mixing construction method for cement stabilized macadam |
CN113123197A (en) * | 2021-04-21 | 2021-07-16 | 鹏图建设有限公司 | Method and process for stabilizing macadam base with cement |
CN113403914A (en) * | 2021-05-31 | 2021-09-17 | 广州市土木金建筑工程有限公司 | Municipal road asphalt concrete pavement construction detection method |
Non-Patent Citations (2)
Title |
---|
刘卫: "水稳碎石基层双层连铺施工关键技术", 山西建筑, no. 17, pages 108 - 109 * |
季香钦: "水稳碎石基层两层连铺施工技术分析探讨", 科技资讯, no. 1, pages 91 - 92 * |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115125800A (en) * | 2022-05-31 | 2022-09-30 | 北京市首发天人生态景观有限公司 | Multifunctional plant material concrete paving equipment |
CN115125800B (en) * | 2022-05-31 | 2024-04-19 | 北京市首发天人生态景观有限公司 | Multifunctional plant material concrete paving equipment |
CN115450090A (en) * | 2022-10-20 | 2022-12-09 | 中电建路桥集团有限公司 | Digital autonomous double-layer paving device and method |
CN115450090B (en) * | 2022-10-20 | 2023-09-01 | 中电建路桥集团有限公司 | Digital autonomous double-layer paving device and paving method |
WO2024092998A1 (en) * | 2022-11-01 | 2024-05-10 | 中国港湾工程有限责任公司 | Saturated-water vibrating compaction construction process for graded crushed stone |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN114381981A (en) | Construction method of double-layer combined paving test section of guide road | |
CN104762862B (en) | SMA asphaltic road-mix surface course construction methods | |
CN104631261B (en) | A kind of cement stabilized macadam underlayment, go to a grassroots level and the construction method of three layers of upper basic unit even paving | |
CN106894308A (en) | A kind of crack resistance construction of cement stable macadam base method | |
CN104652238B (en) | A kind of urban road accessible base layer construction method | |
CN111021174A (en) | Construction method of urban road | |
WO2023020630A1 (en) | Construction method for upper surface course made of steel slag-asphalt mixture | |
CN106522073A (en) | Construction method of high-added water-stable milled waste base | |
CN104631260A (en) | Upper-layer and lower-layer joined-paving construction method of cement stabilized macadam | |
CN112982058A (en) | Vibration mixing construction method for cement stabilized macadam | |
CN105064163A (en) | Cement stabilization macadam base layer ultrahigh reverse slope section one-time molding construction method | |
CN111719371A (en) | Road base layer component and road paving method | |
CN211472012U (en) | Signal lamp crossing filling type composite pavement | |
CN114908630A (en) | Factory road structure and secondary permanent-temporary combined layered construction method | |
CN111455762B (en) | Construction Method of Asphalt Concrete Pot Surface in Test Site | |
CN106868968B (en) | A kind of non-flexible foundation bituminous pavement entirety thick plate structure construction method | |
CN220057515U (en) | Road pavement structure | |
CN211171471U (en) | High-performance steel slag pavement | |
WO2024092998A1 (en) | Saturated-water vibrating compaction construction process for graded crushed stone | |
CN113584981A (en) | Assembled cement concrete pavement slab and construction method | |
Sharp | Concrete in Highway Engineering: International Series of Monographs in Civil Engineering | |
CN113152200A (en) | Method for preventing and controlling cracks of road water-stable gravel base layer in reclamation area | |
Mallick et al. | Construction of Asphalt Pavements | |
CN114032732B (en) | Bend brake test pavement and construction method thereof | |
Mohney | Fabric Retaining Wall-Olympic NF |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20220422 |