CN113152200A - Method for preventing and controlling cracks of road water-stable gravel base layer in reclamation area - Google Patents

Method for preventing and controlling cracks of road water-stable gravel base layer in reclamation area Download PDF

Info

Publication number
CN113152200A
CN113152200A CN202110303446.1A CN202110303446A CN113152200A CN 113152200 A CN113152200 A CN 113152200A CN 202110303446 A CN202110303446 A CN 202110303446A CN 113152200 A CN113152200 A CN 113152200A
Authority
CN
China
Prior art keywords
aggregate
paving
base layer
road
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110303446.1A
Other languages
Chinese (zh)
Inventor
高智
郭晓军
于照海
闫斌
姚文江
马勇
周俊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xinjiang Corps Survey And Design Institute Group Co ltd
Original Assignee
Xinjiang Corps Survey And Design Institute Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xinjiang Corps Survey And Design Institute Group Co ltd filed Critical Xinjiang Corps Survey And Design Institute Group Co ltd
Priority to CN202110303446.1A priority Critical patent/CN113152200A/en
Publication of CN113152200A publication Critical patent/CN113152200A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C11/00Details of pavings
    • E01C11/005Methods or materials for repairing pavings

Abstract

The invention relates to the technical field of gap filling materials, and discloses a method for preventing and controlling cracks of a water-stable gravel base layer of a road in a reclamation area, which comprises the following steps of S1, measuring a pavement crack area; s2, stirring the mixture for use; s3, performing temperature shrinkage tests of an electrical measurement method under five different states of a water saturation state, an optimal water content state, a semi-air-drying state, an air-drying state and a drying state; s4, constructing by using an inverted structure; s5, cutting a seam and then paving a geogrid; s6, carrying out process construction and maintenance, wherein the main research results in the invention are as follows: a complete set of technology suitable for preventing and treating water-stable natural gravel semi-rigid base pavement cracking of roads in Xinjiang reclamation areas is provided from the aspects of raw material control, pavement structure, material grading design, construction process and the like. The reasonable cement dosage range and the optimal cement adding process of the water-stable natural gravel mixture in the Xinjiang reclamation area are researched. Solves the problems of proper cement dosage range and construction procedures, the cracking mechanism and the cracking interval of cement stabilized gravel layers and the like.

Description

Method for preventing and controlling cracks of road water-stable gravel base layer in reclamation area
Technical Field
The invention relates to the technical field of gap filling materials, in particular to a method for preventing and controlling cracks of a water-stable gravel base layer of a highway in a reclamation area.
Background
By the end of 2009, the total road mileage in China already exceeds 200 kilometers, and the highway traffic mileage breaks through 6 kilometers. China has completed the development course of three or forty years in developed countries in a short time of more than ten years. Particularly, after the 21 st century, the nation carries out the great strategy of western major development, high-grade highways in western and middle areas are rapidly developed, and the highway industry all over the country presents a splendid scene by the construction of access projects of rural and rural oil communication paths. Meanwhile, the demand for highway construction is also developing towards high-grade and high-standard directions, vehicles are required to be driven on roads safely, comfortably and economically at a certain speed, and the demand for road performance is also increasing. With the increase of traffic volume and the increase of automobile load, higher requirements are put on the overall strength and the flatness of the road surface. In order to meet the ever-increasing requirements of heavy traffic and heavy load on roads, China largely adopts semi-rigid base asphalt pavements with inorganic binder stabilized aggregates as a base and asphalt concrete as a surface.
As the cement stabilized macadam or gravel mixture is used in large quantity in China, the existing problems are slowly revealed, and as the cement stabilized macadam or gravel is brittle and is sensitive to the change of temperature and humidity, shrinkage cracking is easily caused by the change of temperature or humidity during the construction and use processes. Therefore, a reclamation area highway water-stable gravel base layer crack control method is provided.
Disclosure of Invention
Technical problem to be solved
Aiming at the defects of the prior art, the invention provides a method for preventing and controlling cracks of a water-stable gravel base layer of a road in a reclamation area, and solves the problems.
(II) technical scheme
In order to achieve the above purpose, the invention provides the following technical scheme: the method for preventing and controlling the cracks of the water-stable gravel base layer of the road in the reclamation area comprises the following steps:
s1, measuring a pavement crack area;
s2, stirring the mixture for use;
s3, performing temperature shrinkage tests of an electrical measurement method under five different states of a water saturation state, an optimal water content state, a semi-air-drying state (1/2 optimal water content), an air-drying state (1/5 optimal water content) and a drying state;
s4, constructing by using an inverted structure;
s5, cutting a seam and then paving a geogrid;
and S6, carrying out process construction and maintenance.
Preferably, the road surface sealing measurement in S1 specifically includes the following steps: step 1, calculating a crushing and filling range according to the distribution range of the cracks, wherein the length of the crushing range is larger than the length of the cracks by 1.5cm, and the width of the crushing range is larger than the width of the cracks by 1 cm.
Preferably, the mixture mixing procedure in S2 specifically includes the following steps:
a) drying the aggregate;
b) the raw materials are prepared according to the design grading (the natural grading is directly weighed according to the total weight). In the experiment of adding the fly ash instead of the experiment, the fly ash is added into the aggregate and mixed evenly);
c) adding a predetermined amount of water;
d) placing into a plastic bag, and soaking and stewing the materials;
e) after 4h, cement is added and uniformly mixed, and subsequent tests are carried out.
Preferably, the compression test in S3 tests the following test results: the cement stabilizing material base layer is doped with aggregate, so that the temperature shrinkage of the mixture can be obviously reduced; the temperature shrinkage of cement stabilized aggregates is smaller than that of lime fly ash stabilized aggregates and also smaller than that of lime stabilized aggregates.
Preferably, the construction method of the flip-chip structure in S4 includes the following specific construction methods and measures:
1) 20cm of the finished sub-base layer pavement is dug, the width of the original base layer is 10.4m of the designed width of the original shoulder, and the inner edge of the shoulder is straightened according to the designed width through manual cooperation with a grader. Ensuring the width of the subbase pavement;
2) and after the excavation is finished, leveling by a grader, watering and rolling the original pavement, and detecting the compactness, the flatness and the deflection of the pavement according to the detection requirement of the subbase layer. The lower bearing layer is ensured to be flat, compact and free from loosening, slurry turning and the like;
3) and after the pavement detection meets the design requirements, performing center line lofting and edge elevation sampling and hanging steel strand control. The paving and rolling processes are the same as those of the base layers of other test sections. The road section has a height difference at joints at two sides, and is in two-layer step lap joint by adopting a length of 15cm and a height of 10 cm;
4) after the layer of the gravel is cured, constructing base-layer graded gravel, wherein the construction method is carried out according to the construction process of the subbase layer;
preferably, the specific construction method for laying the geogrid by slitting in the step S5 is as follows:
1) after paving the cement stabilization base layer, watering for natural curing, and after curing, cutting one cutting seam every 10 meters along the direction of the transverse axis of the route by using a cutting machine;
2) after the joint cutting is finished, manually lapping the prepared geogrid with the length of 50cm and the width meeting the base layer pavement along each edge of the joint cutting by 25 cm;
3) after the geogrid is lapped, the geogrid is fixed by an iron sheet, so that the geogrid is prevented from being displaced by wheels when the vehicle sprays emulsified asphalt;
preferably, the construction process and maintenance measures in S6 specifically include the following steps:
1) preparing; preparing a lower bearing layer, checking the flatness, compactness and deflection value of the layer, and taking measures to treat unqualified positions, weak positions and low-lying pot holes to ensure that the surface of the lower bearing layer is compact and flat without any loose or weak positions;
2) construction lofting; and recovering the center line, determining the plane position of each 10 m section to accurately control the accuracy of the elevation of the section, and preparing each construction technology before paving aggregate. The elevation of the aggregate paving edge is controlled by hanging steel strands, and the error between each steel chisel point and each point of the steel strands is measured again before the aggregate paving. So as to avoid the unqualified flatness of the paver after the paving is finished. Marking the starting point and the ending point of each section of 200 meters by the display board according to the different sections divided by the centerline distance. So as to identify the position of each road section, and is beneficial to the collection of various construction data and parameters;
3) production and transportation of aggregates;
4) spreading;
5) and rolling.
Preferably, in step 3) of S6, the production and transportation of the aggregate are specifically as follows:
1) trial preparation is carried out before the mass production of the aggregates, the mass production can be carried out after the accuracy of the aggregate cement content is stable and the mass production is ensured, a cement dose spot check test is carried out during the production period so as to ensure that the accuracy of the cement content is changed, and the allowable deviation value of the cement content is +/-0.2;
2) in the aggregate trial preparation, the water content test of the aggregate is carried out, and the water content of the aggregate is preferably adjusted to be slightly more than 0.3-0.6 of the optimal water content according to the test result so as to prevent the water loss of the aggregate in the transportation and paving processes. The weather with too high temperature can be adjusted according to the field test condition. The moisture content of the aggregate during rolling is in principle at an optimum moisture content;
3) the vehicles need to be in place in time during aggregate transportation, the aggregate transportation vehicles can conveniently enter the construction section along the road junction according to the surrounding traffic environment of the road section, the situation that the material trucks roll back and forth on the lower bearing to damage the lower bearing layer is avoided to the greatest extent, and the specific vehicle transportation route is detailed in a test section construction plan.
Preferably, in step 4) of S6, the paving operation is as follows:
1) after the aggregate is transported to the site, the aggregate is quickly paved by manually matching with a paver, the paving speed is uniform, the phenomenon of stopping and waiting for the aggregate is strictly reduced when the paver is paved, and stable, efficient and ordered connection is formed between a transport vehicle and the paver;
2) before paving, various preparation works need to be prepared, the elevation needs to be strictly controlled, the discharging bottom plate of the paver can be lifted and adjusted to the road arch required by design through controlling the road arch, a straight line is pulled down on the bottom plate by a construction line, the height difference between measuring plates and lines is used in the road middle distance from the bottom plate, and the adjustment can be carried out if the road arch required by design cannot be achieved. The reasonable loose paving coefficient is grasped according to the primary trial paving, namely, the left, middle and right three-point elevations of each section of every 10 m are taken in the paving operation before the paving, the effective loose paving coefficient is converted by three-time height difference comparison after the paving and the rolling are finished and measured once each time;
3) after the aggregates are paved, the place where the coarse and fine particles are separated and the coarse aggregate nest are manually removed in time, the new mixture is used for filling, and the road roller is tightly pressed by the paver for one time so as to keep the moisture.
Preferably, in step 5) of S6, the rolling process includes the following steps: after paving, every 30-50 m of aggregate is a rolling section, and any vehicle is strictly forbidden to pass through in the rolling process. According to the rolling principle, the road shoulder is rolled into the road on the straight line section of the road with light weight, heavy weight, outer side and inner side, and the curve section is rolled from the inner side of the curve to the outer side. The rear wheels overlap 2/1 the wheel width during rolling. And the exposed unevenness is inspected at any time by a guiding rule manually in the rolling process, and the roller is leveled manually and quickly. Static pressure and micro vibration of the road roller with 18 tons of rolling passes are planned once, and static recovery of strong vibration is planned once for 3-4 times, and the concrete passes can be adjusted through a field test compaction result. The initial setting time of the cement is not easily exceeded for 3-4 hours from the production of the aggregate to the completion of the rolling detection, and the initial pressure of the rolling speed is preferably 2.0-2.5 km/h after 1.5-1.7 km/h.
(III) advantageous effects
Compared with the prior art, the invention provides a method for preventing and controlling the cracks of the water-stable gravel base layer of the road in the reclamation area, which has the following beneficial effects:
the research researches the prevention and control technology of cracks of the cement stabilized gravel base layer of the road in the reclamation area by performing indoor tests on the performances of the water stabilized gravel mixtures with different grades and different cement dosages and combining theoretical analysis, and provides a scheme for engineering application. The main research results are as follows: a complete set of technology suitable for preventing and treating water-stable natural gravel semi-rigid base pavement cracking of roads in Xinjiang reclamation areas is provided from the aspects of raw material control, pavement structure, material grading design, construction process and the like. The reasonable cement dosage range and the optimal cement adding process of the water-stable natural gravel mixture in the Xinjiang reclamation area are researched. The cracking distance of the natural gravel water-stable base layer of the road in the reclamation area is estimated theoretically and basically consistent with an actual measurement value, so that the problems of proper cement dosage range and construction procedures, the cracking mechanism and the cracking distance of the cement-stable gravel layer and the like are solved.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Example (b): the method for preventing and controlling the cracks of the water-stable gravel base layer of the road in the reclamation area comprises the following steps:
s1, measuring a pavement crack area;
s2, stirring the mixture for use;
s3, performing temperature shrinkage tests of an electrical measurement method under five different states of a water saturation state, an optimal water content state, a semi-air-drying state (1/2 optimal water content), an air-drying state (1/5 optimal water content) and a drying state;
s4, constructing by using an inverted structure;
s5, cutting a seam and then paving a geogrid;
and S6, carrying out process construction and maintenance.
The road surface locking measurement in the S1 specifically comprises the following steps: step 1, calculating a crushing and filling range according to the distribution range of the cracks, wherein the length of the crushing range is larger than the length of the cracks by 1.5cm, and the width of the crushing range is larger than the width of the cracks by 1 cm.
The mixture mixing procedure in the S2 specifically comprises the following steps:
a) drying the aggregate;
b) the raw materials are prepared according to the design grading (the natural grading is directly weighed according to the total weight). In the experiment of adding the fly ash instead of the experiment, the fly ash is added into the aggregate and mixed evenly);
c) adding a predetermined amount of water;
d) placing into a plastic bag, and soaking and stewing the materials;
e) after 4h, cement is added and uniformly mixed, and subsequent tests are carried out.
The compression test in S3 tests the following test results: the cement stabilizing material base layer is doped with aggregate, so that the temperature shrinkage of the mixture can be obviously reduced; the temperature shrinkage of cement stabilized aggregates is smaller than that of lime fly ash stabilized aggregates and also smaller than that of lime stabilized aggregates.
The construction method of the inverted structure in the S4 comprises the following specific construction methods and measures:
1) 20cm of the finished sub-base layer pavement is dug, the width of the original base layer is 10.4m of the designed width of the original shoulder, and the inner edge of the shoulder is straightened according to the designed width through manual cooperation with a grader. Ensuring the width of the subbase pavement;
2) and after the excavation is finished, leveling by a grader, watering and rolling the original pavement, and detecting the compactness, the flatness and the deflection of the pavement according to the detection requirement of the subbase layer. The lower bearing layer is ensured to be flat, compact and free from loosening, slurry turning and the like;
3) and after the pavement detection meets the design requirements, performing center line lofting and edge elevation sampling and hanging steel strand control. The paving and rolling processes are the same as those of the base layers of other test sections. The road section has a height difference at joints at two sides, and is in two-layer step lap joint by adopting a length of 15cm and a height of 10 cm;
4) and after the layer is cured, constructing the base layer graded gravel, wherein the construction method is carried out according to the base layer construction process.
The specific construction method for laying the geogrid by cutting the seams in the S5 comprises the following steps:
1) after paving the cement stabilization base layer, watering for natural curing, and after curing, cutting one cutting seam every 10 meters along the direction of the transverse axis of the route by using a cutting machine;
2) after the joint cutting is finished, manually lapping the prepared geogrid with the length of 50cm and the width meeting the base layer pavement along each edge of the joint cutting by 25 cm;
3) and after the overlapping of the geogrids is finished, the geogrids are fixed by using iron sheets, so that the geogrids are prevented from being displaced by wheels when the vehicle sprays emulsified asphalt.
The construction process and maintenance measures in the step S6 specifically comprise the following steps:
1) preparing; preparing a lower bearing layer, checking the flatness, compactness and deflection value of the layer, and taking measures to treat unqualified positions, weak positions and low-lying pot holes to ensure that the surface of the lower bearing layer is compact and flat without any loose or weak positions;
2) construction lofting; and recovering the center line, determining the plane position of each 10 m section to accurately control the accuracy of the elevation of the section, and preparing each construction technology before paving aggregate. The elevation of the aggregate paving edge is controlled by hanging steel strands, and the error between each steel chisel point and each point of the steel strands is measured again before the aggregate paving. So as to avoid the unqualified flatness of the paver after the paving is finished. Marking the starting point and the ending point of each section of 200 meters by the display board according to the different sections divided by the centerline distance. So as to identify the position of each road section, and is beneficial to the collection of various construction data and parameters;
3) production and transportation of aggregates;
4) spreading;
5) and rolling.
In the step 3) of S6, the production and transportation of the aggregate are specifically as follows:
1) trial preparation is carried out before the mass production of the aggregates, the mass production can be carried out after the accuracy of the aggregate cement content is stable and the mass production is ensured, a cement dose spot check test is carried out during the production period so as to ensure that the accuracy of the cement content is changed, and the allowable deviation value of the cement content is +/-0.2;
2) in the aggregate trial preparation, the water content test of the aggregate is carried out, and the water content of the aggregate is preferably adjusted to be slightly more than 0.3-0.6 of the optimal water content according to the test result so as to prevent the water loss of the aggregate in the transportation and paving processes. The weather with too high temperature can be adjusted according to the field test condition. The moisture content of the aggregate during rolling is in principle at an optimum moisture content;
3) the vehicles need to be in place in time during aggregate transportation, the aggregate transportation vehicles can conveniently enter the construction section along the road junction according to the surrounding traffic environment of the road section, the situation that the material trucks roll back and forth on the lower bearing to damage the lower bearing layer is avoided to the greatest extent, and the specific vehicle transportation route is detailed in a test section construction plan.
In the step 4) of S6, the paving operation is as follows:
1) after the aggregate is transported to the site, the aggregate is quickly paved by manually matching with a paver, the paving speed is uniform, the phenomenon of stopping and waiting for the aggregate is strictly reduced when the paver is paved, and stable, efficient and ordered connection is formed between a transport vehicle and the paver;
2) before paving, various preparation works need to be prepared, the elevation needs to be strictly controlled, the discharging bottom plate of the paver can be lifted and adjusted to the road arch required by design through controlling the road arch, a straight line is pulled down on the bottom plate by a construction line, the height difference between measuring plates and lines is used in the road middle distance from the bottom plate, and the adjustment can be carried out if the road arch required by design cannot be achieved. The reasonable loose paving coefficient is grasped according to the primary trial paving, namely, the left, middle and right three-point elevations of each section of every 10 m are taken in the paving operation before the paving, the effective loose paving coefficient is converted by three-time height difference comparison after the paving and the rolling are finished and measured once each time;
3) after the aggregates are paved, the place where the coarse and fine particles are separated and the coarse aggregate nest are manually removed in time, the new mixture is used for filling, and the road roller is tightly pressed by the paver for one time so as to keep the moisture.
In the step 5) of S6, the rolling operation is specifically as follows: after paving, every 30-50 m of aggregate is a rolling section, and any vehicle is strictly forbidden to pass through in the rolling process. According to the rolling principle, the road shoulder is rolled into the road on the straight line section of the road with light weight, heavy weight, outer side and inner side, and the curve section is rolled from the inner side of the curve to the outer side. The rear wheels overlap 2/1 the wheel width during rolling. And the exposed unevenness is inspected at any time by a guiding rule manually in the rolling process, and the roller is leveled manually and quickly. Static pressure and micro vibration of the road roller with 18 tons of rolling passes are planned once, and static recovery of strong vibration is planned once for 3-4 times, and the concrete passes can be adjusted through a field test compaction result. The initial setting time of the cement is not easily exceeded for 3-4 hours from the production of the aggregate to the completion of the rolling detection, and the initial pressure of the rolling speed is preferably 2.0-2.5 km/h after 1.5-1.7 km/h.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (10)

1. Reclamation district highway water stable gravel base course crack control method, its characterized in that: the method comprises the following steps:
s1, measuring a pavement crack area;
s2, stirring the mixture for use;
s3, performing temperature shrinkage tests of an electrical measurement method under five different states of a water saturation state, an optimal water content state, a semi-air-drying state (1/2 optimal water content), an air-drying state (1/5 optimal water content) and a drying state;
s4, constructing by using an inverted structure;
s5, cutting a seam and then paving a geogrid;
and S6, carrying out process construction and maintenance.
2. The reclamation area highway unstable gravel base layer crack control method of claim 1, characterized in that: the road surface locking measurement in the S1 specifically comprises the following steps: step 1, calculating a crushing and filling range according to the distribution range of the cracks, wherein the length of the crushing range is larger than the length of the cracks by 1.5cm, and the width of the crushing range is larger than the width of the cracks by 1 cm.
3. The reclamation area highway unstable gravel base layer crack control method of claim 1, characterized in that: the mixture mixing procedure in the S2 specifically comprises the following steps:
a) drying the aggregate;
b) the natural grading is prepared step by step (the natural grading is directly weighed according to the total weight, the fly ash is added into the aggregate in the experiment, and the fly ash is mixed and stirred uniformly);
c) adding a predetermined amount of water;
d) placing into a plastic bag, and soaking and stewing the materials;
e) after 4h, cement is added and uniformly mixed, and subsequent tests are carried out.
4. The reclamation area highway unstable gravel base layer crack control method of claim 1, characterized in that: the compression test in S3 tests the following test results: the cement stabilizing material base layer is doped with aggregate, so that the temperature shrinkage of the mixture can be obviously reduced; the temperature shrinkage of cement stabilized aggregates is smaller than that of lime fly ash stabilized aggregates and also smaller than that of lime stabilized aggregates.
5. The reclamation area highway unstable gravel base layer crack control method of claim 1, characterized in that: the construction method of the inverted structure in the S4 comprises the following specific construction methods and measures:
1) digging 20cm of the finished subbase pavement, reserving an original shoulder with the width of 10.4m designed for the original base course, and straightening the inner edge of the shoulder according to the designed width by manually matching with a grader to ensure the width of the subbase pavement;
2) after the excavation is finished, leveling by a grader, spraying water on the original pavement for rolling, detecting the compaction degree, the leveling degree and the deflection of the pavement according to the detection requirements of the subbase layer, and ensuring that the lower bearing layer is smooth, compact and free of loosening, grout turnover and other phenomena;
3) after the pavement detection meets the design requirements, performing center line lofting, adopting hanging steel stranded wires at the side elevation for control, paving and rolling the same as the base layer process of other test sections, wherein the height difference exists at joints at two sides of the section, and adopting the length of 15cm and the height of 10cm for carrying out two-layer step lap joint;
4) and after the layer is cured, constructing the base layer graded gravel, wherein the construction method is carried out according to the base layer construction process.
6. The reclamation area highway unstable gravel base layer crack control method of claim 1, characterized in that: the specific construction method for laying the geogrid by cutting the seams in the S5 comprises the following steps:
1) after paving the cement stabilization base layer, watering for natural curing, and after curing, cutting one cutting seam every 10 meters along the direction of the transverse axis of the route by using a cutting machine;
2) after the joint cutting is finished, manually lapping the prepared geogrid with the length of 50cm and the width meeting the base layer pavement along each edge of the joint cutting by 25 cm;
3) and after the overlapping of the geogrids is finished, the geogrids are fixed by using iron sheets, so that the geogrids are prevented from being displaced by wheels when the vehicle sprays emulsified asphalt.
7. The reclamation area highway unstable gravel base layer crack control method of claim 1, characterized in that: the construction process and maintenance measures in the step S6 specifically comprise the following steps:
1) preparing; preparing a lower bearing layer, checking the flatness, compactness and deflection value of the layer, and taking measures to treat unqualified positions, weak positions and low-lying pot holes to ensure that the surface of the lower bearing layer is compact and flat without any loose or weak positions;
2) construction lofting; recovering a central line, determining the plane position of each 10 m section to accurately control the accuracy of the section elevation, preparing various construction technology preparations before aggregate paving, controlling the elevation of an aggregate paving edge by hanging steel strands, and repeatedly measuring the errors between steel drill points and between steel drill points of the steel strands before the aggregate paving so as to avoid unqualified flatness after the paving of a paver;
3) production and transportation of aggregates;
4) spreading;
5) and rolling.
8. The reclamation area highway unstable gravel base layer crack control method of claim 7, characterized in that: in the step 3) of S6, the production and transportation of the aggregate are specifically as follows:
1) trial preparation is carried out before the mass production of the aggregates, the mass production can be carried out after the accuracy of the aggregate cement content is stable and the mass production is ensured, a cement dose spot check test is carried out during the production period so as to ensure that the accuracy of the cement content is changed, and the allowable deviation value of the cement content is +/-0.2;
2) in the aggregate trial preparation, the water content of the aggregate is tested, and the water content of the aggregate is adjusted to be slightly more than 0.3-0.6 of the optimal water content according to the test result so as to prevent the water loss of the aggregate in the transportation and paving processes, and the weather with too high temperature is adjusted according to the field test condition so that the water content of the aggregate in the rolling process is in the optimal water content in principle;
3) the vehicles need to be in place in time during aggregate transportation, the aggregate transportation vehicles can conveniently enter the construction section along the road junction according to the surrounding traffic environment of the road section, the situation that the material trucks roll back and forth on the lower bearing to damage the lower bearing layer is avoided to the greatest extent, and the specific vehicle transportation route is detailed in a test section construction plan.
9. The reclamation area highway unstable gravel base layer crack control method of claim 7, characterized in that: in the step 4) of S6, the paving operation is as follows:
1) after the aggregate is transported to the site, the aggregate is quickly paved by manually matching with a paver, the paving speed is uniform, the phenomenon of stopping and waiting for the aggregate is strictly reduced when the paver is paved, and stable, efficient and ordered connection is formed between a transport vehicle and the paver;
2) before paving, various preparation works need to be prepared, the elevation needs to be strictly controlled, the control of an arch can lift and adjust a discharging bottom plate of a paver to the arch of the road required by design, a construction line is used for pulling down a straight line on the bottom plate, the height difference between a measuring tape measuring plate and the line is used in the road middle distance bottom plate, if the arch of the road required by the design cannot be met, the adjustment can be carried out, the reasonable loose coefficient needs to be mastered according to the primary trial paving, namely, the left, middle and right three-point elevations of each section of every 10 meters are taken in the paving operation before paving, the paving and rolling are measured once after being finished, and the effective loose coefficient is converted through the three-time height difference comparison;
3) after the aggregates are paved, the place where the coarse and fine particles are separated and the coarse aggregate nest are manually removed in time, the new mixture is used for filling, and the road roller is tightly pressed by the paver for one time so as to keep the moisture.
10. The reclamation area highway unstable gravel base layer crack control method of claim 7, characterized in that: in the step 5) of S6, the rolling operation is specifically as follows: after paving aggregate, every 30-50 m is a rolling section, in the rolling process, any vehicle is strictly forbidden to pass, the rolling principle is that firstly, the weight is light, then the weight is heavy, then the road is rolled from the road shoulder to the road on the straight line section, the curve section is rolled from the inner side of the curve to the outer side, in the rolling process, the rear wheel is overlapped 2/1 wheels wide and exceeds the seams at the two ends, in the rolling process, a guiding rule is manually used for checking exposed unevenness at any time, manual rapid leveling is performed, 18 tons of road rollers are planned to perform static pressure once, micro vibration once and strong shock once for 3-4 times, the specific number of times can be adjusted through a field test compaction degree result, 3-4 hours which does not exceed the initial setting time of cement easily are performed when the production of the aggregate is rolled and the rolling detection is completed, and 2.0-2.5 km/h is preferably adopted after the initial pressing speed is 1.5-1.7 km/h.
CN202110303446.1A 2021-03-22 2021-03-22 Method for preventing and controlling cracks of road water-stable gravel base layer in reclamation area Pending CN113152200A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110303446.1A CN113152200A (en) 2021-03-22 2021-03-22 Method for preventing and controlling cracks of road water-stable gravel base layer in reclamation area

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110303446.1A CN113152200A (en) 2021-03-22 2021-03-22 Method for preventing and controlling cracks of road water-stable gravel base layer in reclamation area

Publications (1)

Publication Number Publication Date
CN113152200A true CN113152200A (en) 2021-07-23

Family

ID=76888166

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110303446.1A Pending CN113152200A (en) 2021-03-22 2021-03-22 Method for preventing and controlling cracks of road water-stable gravel base layer in reclamation area

Country Status (1)

Country Link
CN (1) CN113152200A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114214895A (en) * 2021-12-03 2022-03-22 中交一公局西北工程有限公司 Construction process of water-stable base course in large-temperature-difference area

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114214895A (en) * 2021-12-03 2022-03-22 中交一公局西北工程有限公司 Construction process of water-stable base course in large-temperature-difference area

Similar Documents

Publication Publication Date Title
CN103922645B (en) A kind of asphalt and preparation method thereof
Bocci et al. Recycling techniques and environmental issues relating to the widening of an high traffic volume Italian motorway
CN108894085A (en) Bituminous pavement tunneling boring once paves molding construction engineering method
CN111485468B (en) Premixed foam asphalt base layer and subbase layer in-situ cold regeneration construction method
CN107338686A (en) A kind of Subgrade Filled Soil in High Speed Railway construction method
CN111021174A (en) Construction method of urban road
CN106522073A (en) Construction method of high-added water-stable milled waste base
CN111155401A (en) One-step paving and forming construction method for water-stable base layer
CN113152200A (en) Method for preventing and controlling cracks of road water-stable gravel base layer in reclamation area
CN108517734B (en) Construction method for synchronously paving smooth and rough asphalt pavement
CN114163187A (en) Emulsified asphalt plant-mixed cold-recycling mixture and construction process thereof
CN111455762B (en) Construction method of basin-shaped curved surface of asphalt concrete in test field
CN211472012U (en) Signal lamp crossing filling type composite pavement
CN112195707A (en) Large-thickness wide-width water-stabilized layer paving construction method
CN107151961A (en) A kind of construction method of town road
CN112982058A (en) Vibration mixing construction method for cement stabilized macadam
CN111719371A (en) Road base layer component and road paving method
CN113417182A (en) Asphalt pavement paving method capable of reducing air bubbles for highway engineering
CN112575686A (en) UHPC bridge deck transverse bridge unequal-thickness asphalt paving construction process
CN113089410A (en) Asphalt pavement structure for permanent structure conversion of highway precast beam field pavement
Cable et al. Thin bonded overlay evaluation
CN114808586B (en) Construction method for asphalt pavement anti-cracking in severe cold region
CN211446437U (en) Hot recycled asphalt road structure of plantmix
CN115787386A (en) Saturated watertight compaction construction process for graded broken stones
CN112982054A (en) Reinforcing treatment construction method for specific geological rainflower stone gravel layer roadbed in Nanjing area

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: No.36 Jianshe Road, Tianshan District, Urumqi, Xinjiang Uygur Autonomous Region 830000

Applicant after: Xinjiang Corps Survey and Design Institute Group Co.,Ltd.

Address before: No.36 Jianshe Road, Tianshan District, Urumqi, Xinjiang Uygur Autonomous Region 830000

Applicant before: Xinjiang Corps Survey and Design Institute (Group) Co.,Ltd.

CB02 Change of applicant information