WO2023010644A1 - 一种小间距多桥并行段箱梁同步运架施工方法 - Google Patents

一种小间距多桥并行段箱梁同步运架施工方法 Download PDF

Info

Publication number
WO2023010644A1
WO2023010644A1 PCT/CN2021/116670 CN2021116670W WO2023010644A1 WO 2023010644 A1 WO2023010644 A1 WO 2023010644A1 CN 2021116670 W CN2021116670 W CN 2021116670W WO 2023010644 A1 WO2023010644 A1 WO 2023010644A1
Authority
WO
WIPO (PCT)
Prior art keywords
bridge
double
line
erection
erecting machine
Prior art date
Application number
PCT/CN2021/116670
Other languages
English (en)
French (fr)
Inventor
林福生
王黎
李泽鹏
李�昊
王剑
王建超
田晓旺
Original Assignee
中铁上海工程局集团有限公司
中铁上海工程局集团第四工程有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 中铁上海工程局集团有限公司, 中铁上海工程局集团第四工程有限公司 filed Critical 中铁上海工程局集团有限公司
Publication of WO2023010644A1 publication Critical patent/WO2023010644A1/zh

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Definitions

  • the invention relates to a construction method for erecting multi-bridges, in particular to a construction method for synchronous frame transport of box girders in parallel sections of multi-bridges with small spacing.
  • the technical problem to be solved by the present invention is to provide a construction method for synchronous transport of box girders with small spacing and multi-bridge parallel sections.
  • the box girder erection scheme is optimized according to the order of girder erection.
  • the equipment adjustment operation is simple during cross operations, and the construction efficiency is fast and the safety is high.
  • a construction method for synchronously transporting frame of box girder of multi-bridge parallel section with small spacing is characterized in that, comprises the following steps:
  • the bridge erecting machine moves to the right to erect the second double-wire bridge, and transports the girder through the first double-wire bridge;
  • the bridge erecting machine moves to the left to erect the second single-wire bridge, and transports the girder through the first double-wire bridge;
  • the bridge erecting machine moves to the right to erect the third single-line bridge extended from the second double-line bridge, and transports the girder through the first double-line bridge;
  • the bridge erecting machine moves to the right to erect the fourth single-line bridge extended from the second double-line bridge, and transports the girder through the first double-line bridge;
  • the bridge erecting machine moves to the left to erect the first single-line bridge, and transports the girder through the first double-line bridge.
  • the beneficial effects of the present invention are: in the erection of multiple bridges with small spacing, because the distance between parallel bridges is too small, two or more bridge erecting machines cannot be accommodated at the same time, and the erection scheme of the box girder is optimized according to the bridge erection sequence. operation, and use the completed line bridge to transport beams and erect construction synchronously, which not only has high construction efficiency, but also has high safety.
  • the present invention can also be improved as follows.
  • the two ends of the line bridge are respectively provided with a beam field and a beam lifting machine traversing zone, and the beam lifting machine traversing zone is equipped with a beam lifting machine;
  • the bridge erecting machine When the bridge erecting machine moves left or right, it returns to the beam field and turns around or realizes the left or right movement through the beam lifting machine.
  • the beneficial effect of adopting the above-mentioned further scheme is that the traverse area of the girder lifting machine is located within a small span area of the parallel section, and the bridge erecting machine can perform the next bridging operation after turning around in the girder field or the traverse area of the girder lifting machine according to the actual situation. High efficiency and save time.
  • step 1) to step 6 when erecting the bridge, erect it in the direction of small mileage first, and then in the direction of large mileage.
  • the beneficial effect of adopting the above-mentioned further solution is that the bridge erecting machine needs to return to the beam field or make a U-turn through the traverse area of the beam lifting machine, and the beam transport vehicle performs return transport in two directions, thereby facilitating the left or right movement of the bridge erecting machine.
  • the width of the bridge erecting machine can be shortened by rotating the 2# outrigger of the bridge erecting machine to avoid avoidance, so as to ensure that both the beam transporting vehicle and the bridge erecting machine can pass smoothly, and then It can meet the simultaneous construction of multiple lines in the closely parallel area of the bridge without affecting each other.
  • the height of the bridge erecting machine can be adjusted as a whole by extending the legs of the bridge erecting machine, so that the bridge erecting machine can pass through the existing portal piers.
  • the width of the main outrigger of the bridge erecting machine protruding from the bridge deck is less than 2.4m.
  • the beneficial effect of adopting the above-mentioned further scheme is that the distance between the line bridges in the parallel section is overloaded, the main legs of the bridge erecting machine protrude from the bridge deck too long, and the beam transport vehicle and the bridge erection machine cannot be staggered when driving.
  • the beam transporting vehicle transports the beams
  • the beam transporting vehicle is a separated beam transporting vehicle.
  • the beneficial effect of adopting the above-mentioned further scheme is that the separated beam transport vehicle is more flexible in walking, and is suitable for beam transport on small-radius lines.
  • the beam transport vehicle can assist the bridge erecting machine to complete the U-turn in the small space of the site.
  • the girder field is provided with a girder upper bridge area
  • the girder upper bridge area includes at least one girder lifting machine spanning four bridges and six lines and at least one single-double shared shipping platform.
  • the beneficial effect of adopting the above-mentioned further solution is that the girder is lifted onto the bridge to move the box girder from the girder field to the beam transporting vehicle, and is transported to a designated position by sending the pedestal and the beam transporting vehicle, which is simple and fast.
  • At least one beam lifting machine spanning four bridges and six lines is provided in the traverse area of the beam lifting machine.
  • the beneficial effect of adopting the above further solution is that the beam lifting machine is used for lifting the beam, and it is also convenient for the bridge erecting machine to turn around.
  • step 6) also includes support grouting, and the grouting material formwork is removed after the grouting material strength reaches 20Mpa.
  • Fig. 1 is the erection structural diagram of a specific embodiment of the present invention.
  • Fig. 2 is an erection structure diagram of Embodiment 1 of the present invention.
  • plural means at least two, such as two, three, etc., unless otherwise specifically defined.
  • a construction method for synchronous frame transport of box girders with small spacing and multi-bridge parallel sections including the following steps:
  • the bridge erecting machine can return to the girder field and move right, and the bridge erecting machine moves right to erect the second double-line bridge 2, and transport the girder through the first double-line bridge 1, and the bridge erecting machine
  • the width of the main outriggers extending out of the bridge deck is less than 2.4m. Since the box girder flange plate of the first double-line bridge 1 interferes with the girder truck or bridge erecting machine on the adjacent line bridge, the main support legs of the bridge erecting machine The width protruding from the bridge deck cannot be too large.
  • the bridge erecting machine moves to the left to erect the second single-line bridge 3, and transports the girder through the first double-line bridge 1. car.
  • the separated beam transport vehicle is more flexible and suitable for beam transport on small-radius lines.
  • the beam transport vehicle can assist the bridge erecting machine to complete the U-turn in the small space of the site.
  • the bridge erecting machine moves to the right to erect the third single-line bridge 4 extended from the second double-line bridge 2, and transports the girder through the first double-line bridge 1.
  • the width of the bridge erecting machine can be shortened by rotating the 2# outrigger of the bridge erecting machine to avoid avoidance, so as to ensure that both the beam transporting vehicle and the bridge erecting machine can pass smoothly, and then It can meet the simultaneous construction of multiple lines in the closely parallel area of the bridge without affecting each other.
  • the height of the bridge erecting machine can be adjusted as a whole by extending the legs of the bridge erecting machine, so that the bridge erecting machine can pass through the existing portal piers.
  • Step 6) also includes support grouting, after the strength of the grouting material reaches 20Mpa, the grouting material formwork is removed.
  • step 6 when erecting the bridge, it is first erected in the direction of small mileage, and then erected in the direction of long mileage. Turn back and transport in one direction, so as to facilitate the left or right movement of the bridge erecting machine.
  • the two ends of the line bridge are respectively provided with a beam field 7 and a beam lifting machine traversing area 8, and the beam lifting machine traversing area 8 is equipped with a beam lifting machine.
  • the beam lifting machine traversing area 8 is equipped with a beam lifting machine.
  • at least one beam lifting machine spanning four bridges and six lines is provided in the beam lifting machine traversing area 8 .
  • the bridge erecting machine moves left or right, it returns to the beam field 7 and turns around or realizes the left or right movement by the beam lifting machine, and the beam field 7 is also used for prefabricated line girders.
  • the beam field 7 is provided with the upper bridge area 9 of the beam, and the upper bridge area 9 of the beam includes at least one beam lifting machine across four bridges and six lines and at least one single and double shared delivery platform.
  • the Xiong’an Station of the Beijing-Xiong Intercity Railway is an elevated station that gathers multiple lines such as Xiongshang, Shixiong Intercity, and bullet train lines.
  • On the south side of Xiong’an Station there is a newly built south-north embankment flood diversion road (about 1.4km wide) and bullet trains Place.
  • the interlaced bridges cross each other from the original four bridges and six lines to five bridges and six lines. Due to the requirement of the construction period, the bridges of each line need to be constructed at the same time.
  • the beam yard is chosen to set up the beam yard at the intersection of the Xiongshang double-track bridge and the single-track bridge on the left line of the bullet train, so as to meet the requirements of single- and double-line prefabricated beams. At the same time, carry out the construction requirements of the beam transport on the bridge.
  • the bridge erecting machine needs to shuttle through the portal pier construction when the box girder is erected, and the bridge crane legs need to avoid obstacles such as the continuous beam under construction on the side side when passing the continuous beam.
  • the spacing does not meet the construction requirements of a parallel double-track bridge where one bridge erects the girder and the other bridge transports the girder.
  • the parallel line segments are Shixiong left line (single line), EMU left line (single line), Xiongshang line (double lines), EMU right line & Shixiong right line (double first, then single),
  • the line spacing is 14m, 5m, 5m, 5m respectively, five bridges and six line sections (about 1km long).
  • the bridge erecting machine When the erection of the Xiongshang double line is completed, the bridge erecting machine is transferred to the right line of Shixiong & the right line of the EMU to erect the right line of Shixiong & the right line of the EMU, and the beam transport vehicle passes through the Xiongshang line to transport the beams.
  • the beam flange plate is interfered by the 2# outrigger of the bridge erecting machine, so the beam transport vehicle cannot pass normally.
  • the bridge erecting machine can rotate the 2# outrigger horizontally to 70° in the non-beam erecting state, so that the width of the 2# outrigger is narrowed from 14.4m to 7.6m, shortening the width of the bridge erecting machine, and ensuring The beam transport vehicle can pass smoothly.
  • the bridge erecting machine can rotate the 2# outrigger to the beam erecting state by itself, and complete the passage of the bridge erecting machine.
  • the bridge erecting machine When the upper part of the erection line meets the portal pier, the bridge erecting machine is limited by the clearance and width of the portal pier, and the height and width of the 2# outrigger of the bridge erecting machine in normal beam erection state are generally limited and cannot pass normally. Now take the minimum clearance height as an example.
  • the bridge erecting machine passes through the portal pier, the three outriggers of the bridge erecting machine can shrink. After shrinking, the maximum height changes from 11.14m to 7.6m, and can pass through the portal with a minimum clearance of 8.049m. piers to meet the on-site beam erection construction.

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

一种小间距多桥并行段箱梁同步运架施工方法,包括以下步骤:架设第一双线桥(1);所述第一双线桥(1)架设完成后,架桥机右移架设第二双线桥(2),并通过所述第一双线桥(1)运梁;所述第二双线桥(2)架设完成后,所述架桥机左移架设第二单线桥(3),并通过所述第一双线桥(1)运梁;所述第二单线桥(3)架设完成后,所述架桥机右移架设所述第二双线桥(2)延长出来的第三单线桥(4),并通过所述第一双线桥(1)运梁;所述第三单线桥(4)架设完成后,所述架桥机右移架设所述第二双线桥(2)延长出来的第四单线桥(5),并通过所述第一双线桥(1)运梁;所述第四单线桥(5)架设完成后,所述架桥机左移架设第一单线桥(6),并通过所述第一双线桥(1)运梁。

Description

一种小间距多桥并行段箱梁同步运架施工方法 技术领域
本发明涉及多桥架设的施工方法,尤其是涉及一种小间距多桥并行段箱梁同步运架施工方法。
背景技术
目前铁路桥梁多桥梁共建、多桥并行线同步施工情况日益增多,桥梁与桥梁之间间距过于狭小,无法满足两台架桥机同步架梁的施工要求。同时,在架梁过程中还需穿越既有桥梁及其构筑物,对架梁过程中的运梁工作造成阻碍,影响架梁施工进度。
发明内容
本发明所要解决的技术问题是提供一种小间距多桥并行段箱梁同步运架施工方法,根据架梁顺序优化箱梁架设方案,交叉作业时设备调整操作简单,施工效率快安全性高。
本发明解决上述技术问题的技术方案如下:1.一种小间距多桥并行段箱梁同步运架施工方法,其特征在于,包括以下步骤:
1)架设第一双线桥;
2)所述第一双线桥架设完成后,架桥机右移架设第二双线桥,并通过所述第一双线桥运梁;
3)所述第二双线桥架设完成后,所述架桥机左移架设第二单线桥,并通过所述第一双线桥运梁;
4)所述第二单线桥架设完成后,所述架桥机右移架设所述第二双线桥延长出来的第三单线桥,并通过所述第一双线桥运梁;
5)所述第三单线桥架设完成后,所述架桥机右移架设所述第二双线桥延长出来的第四单线桥,并通过所述第一双线桥运梁;
6)所述第四单线桥架设完成后,所述架桥机左移架设第一单线桥,并通过所述第一双线桥运梁。
本发明的有益效果是:小间距多桥架设中,由于并行的桥梁与桥梁之间间距过小,不能同时容纳两台或多台架桥机,根据架桥顺序优化箱梁的架设方案,交叉作业,并利用已完成的线路桥进行运梁,同步架设施工,不但施工效率高,且安全性高。
在上述技术方案的基础上,本发明还可以做如下改进。
进一步,线桥两端分别设置有梁场和提梁机横移区,所述提梁机横移区安装有提梁机;
所述架桥机左移或右移时,返回所述梁场掉头或通过所述提梁机实现左移或右移。
采用上述进一步方案的有益效果是提梁机横移区位于并行段跨区域较小范围内,架桥机可根据实际情况在梁场或者提梁机横移区进行掉头后,进行下一次架桥操作,效率高,节约时间。
进一步,步骤1)至步骤6)中,架桥时先小里程方向架设,再大里程方向架设。
采用上述进一步方案的有益效果是架桥机需要返回梁场或者通过提梁机横移区进行掉头,运梁车在两个方向进行折返运输,从而利于架桥机进行左移或者右移。
当运梁车运梁过程中与架桥机相互干扰时,可通过旋转架桥机2#支腿缩短架桥机的宽度进行避让,从而保证运梁车和架桥机均能顺利通过,进而能够满足在桥梁紧密并行区多条线路同时进行架梁施工而互不影响。当架桥机需穿越即有既有门式墩时,可通过伸缩架桥机的各个支腿,整体调整架桥机 高度,实现架桥机穿越既有门式墩。
进一步,所述架桥机的主支腿伸出桥面的宽度小于2.4m。
采用上述进一步方案的有益效果是平行段的线桥间距过载,架桥机的主支腿伸出桥面过长,运梁车与架桥机会车时无法错开。
进一步,运梁车运梁时,所述运梁车为分离式运梁车。
采用上述进一步方案的有益效果是分离式运梁车行走较为灵活,适应小半径线路运梁,同时运梁车可协助架桥机在场地较小的空间完成场内掉头等。
进一步,所述梁场设置有提梁上桥区,且所述提梁上桥区包括至少一台横跨四桥六线的提梁机和至少一台单双共用的发运台座。
采用上述进一步方案的有益效果是提梁上桥去用于将箱梁从梁场移动至运梁车上,通过发送台座和运梁车运送至指定位置,简单快速。
进一步,所述提梁机横移区设置有至少一台横跨四桥六线的提梁机。
采用上述进一步方案的有益效果是提梁机用于提梁,同时也便于架桥机掉头。
进一步,步骤6)后还包括支座灌浆,待灌浆料的强度达到20Mpa后,拆除灌浆料模板。
采用上述进一步方案的有益效果是支座灌浆后将各线桥段连接稳固,便于后续进一步架设。
附图说明
图1为本发明一具体实施例的架设结构图;
图2为本发明实施例一的架设结构图。
附图中,各标号所代表的部件列表如下:
1、第一双线桥;2、第二双线桥;3、第二单线桥;4、第三单线桥;5、 第四单线桥;6、第一单线桥;7、梁场;8、提梁机横移区;9、提梁上桥区。
具体实施方式
以下结合附图对本发明的原理和特征进行描述,所举实例只用于解释本发明,并非用于限定本发明的范围。
在本发明的描述中,需要理解的是,术语“中心”、“长度”、“上”、“下”、“前”、“后”、“左”、“右”、“竖直”、“水平”、“顶”、“内”、“外”、“周侧”、“周向”等指示的方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述本发明和简化描述,而不是指示或暗示所指的系统或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本发明的限制。
在本发明的描述中,“多个”的含义是至少两个,例如两个,三个等,除非另有明确具体的限定。
在本发明中,除非另有明确的规定和限定,术语“安装”、“相连”、“连接”、“固定”等术语应做广义理解,例如,可以是固定连接,也可以是可拆卸连接,或成一体;可以是机械连接,也可以是电连接;可以是直接相连,也可以通过中间媒介间接相连,可以是两个元件内部的连通或两个元件的相互作用关系,除非另有明确的限定。对于本领域的普通技术人员而言,可以根据具体情况理解上述术语在本发明中的具体含义。
如图1所示,一种小间距多桥并行段箱梁同步运架施工方法,包括以下步骤:
1)架设第一双线桥1;通过架桥机以及后续运梁车的配合,完成第一双线桥的架设。
2)第一双线桥1架设完成后,架桥机可返回梁场掉头右移,架桥机右移架设第二双线桥2,并通过第一双线桥1运梁,架桥机的主支腿伸出桥面 的宽度小于2.4m,由于第一双线桥1的箱梁翼缘板相邻线桥上的运梁车或者架桥机发生干涉,因此,架桥机的主支撑腿伸出桥面的宽度不能过大。
3)第二双线桥2架设完成后,架桥机左移架设第二单线桥3,并通过第一双线桥1运梁,运梁车运梁时,运梁车为分离式运梁车。分离式运梁车行走较为灵活,适应小半径线路运梁,同时运梁车可协助架桥机在场地较小的空间完成场内掉头等。
4)第二单线桥3架设完成后,架桥机右移架设第二双线桥2延长出来的第三单线桥4,并通过第一双线桥1运梁。
当运梁车运梁过程中与架桥机相互干扰时,可通过旋转架桥机2#支腿缩短架桥机的宽度进行避让,从而保证运梁车和架桥机均能顺利通过,进而能够满足在桥梁紧密并行区多条线路同时进行架梁施工而互不影响。当架桥机需穿越即有既有门式墩时,可通过伸缩架桥机的各个支腿,整体调整架桥机高度,实现架桥机穿越既有门式墩。
5)第三单线桥4架设完成后,架桥机右移架设第二双线桥2延长出来的第四单线桥5,并通过第一双线桥1运梁。6)第四单线桥5架设完成后,架桥机左移架设第一单线桥6,并通过第一双线桥1运梁。步骤6)后还包括支座灌浆,待灌浆料的强度达到20Mpa后,拆除灌浆料模板。步骤1)至步骤6)中,架桥时均采用的是先小里程方向架设,再大里程方向架设,架桥机需要返回梁场或者通过提梁机横移区进行掉头,运梁车在两个方向进行折返运输,从而利于架桥机进行左移或者右移。
线桥两端分别设置有梁场7和提梁机横移区8,提梁机横移区8安装有提梁机。一具体实施例中,提梁机横移区8设置有至少一台横跨四桥六线的提梁机。
架桥机左移或右移时,返回梁场7掉头或通过提梁机实现左移或右移,梁场7还用于预制线梁。梁场7设置有提梁上桥区9,且提梁上桥区9包括 至少一台横跨四桥六线的提梁机和至少一台单双共用的发运台座。
实施例一
京雄城际铁路雄安车站汇集雄商、石雄城际、动车走行线等多条线的高架车站,雄安站南侧有新盖房南北堤分洪道(宽约1.4km)同时设有动车所。线路出雄安设有四桥六线,在新盖房南、北堤处分别采用最大跨80米的并行4联连续梁(两双两单)跨越泄洪大堤。过新盖房南堤后线路交错桥梁相互跨越由原四桥六线变为五桥六线。因工期要求需要各个线路桥梁同时进行施工,为满足预制梁施工及架设工期要求梁场选择在雄商双线桥与动车走行左线单线桥交错的位置设置梁场,满足单、双线预制梁同时进行桥上运梁架设施工的要求。因桥梁上下交错又相互并行,箱梁架设时架桥机需穿梭于门式墩施工、过连续梁时桥机支腿需躲避旁边一侧正在施工的连续梁等障碍,同时需解决平行桥梁线间距不满足并行双线桥一桥架梁另一桥运梁的施工要求。
并行线段(四桥六线长约1.4km)分别为石雄左线(单线)、动车左线(单线)、雄商线(双线)、动车右线&石雄右线(先双后单),线间距分别为14m、5m、5m、5m,五桥六线段(长约1km)。桥群过新盖房南堤后石雄左单线桥标高逐步升高上跨雄商双线桥与动车走行左线单线桥两座桥梁,动车走行左线单线桥标高逐步下降下穿雄商双线桥,跨越的墩柱均采用门式墩其中门式墩最小净空8.4m。
并行段具体施工过程中,1)先架设雄商线,雄商线并行段架设完成后,2)架桥机右移架设动车右线&石雄右线的共线段,并通过雄商线运梁;3)动车右线&石雄右线的共线段架设完成后,架设动车左线,并通过雄商线运梁;4)动车左线架设完毕之后架设动车右线,架设动车右线时通过雄商线运梁;5)动车右线架设完毕后,架设石雄右线;6)石雄右线架设完毕后,最后架设石雄左线,同样通过雄商线运梁。
当雄商双线架设完毕,架桥机转移至石雄右线&动车右线上架设石雄右线&动车右线时,运梁车通过雄商线运梁。当运梁车与架桥机交汇时因梁翼缘板被架桥机2#支腿干扰,运梁车无法正常通过。此时,架桥机在非架梁的状态下可将2#支腿水平旋转至70°,使得2#支腿宽度由14.4m收窄至7.6m,缩短了架桥机的宽度,进而保证运梁车能够顺利通过。待运梁车通过2#支腿后,架桥机可以自行将2#支腿旋转至架梁状态,完成架桥机的过孔。
当架设线路线路上部遇门式墩时,架桥机会受到门式墩净空及净宽限制,正常架梁状态架桥机2#支腿高宽受限一般无法正常通过。现以最低净空高为例说明,架桥机过门式墩时,架桥机三个支腿可进行收缩,收缩后最高度由11.14m变为为7.6m,能够通过最小净空8.049m的门式墩,满足现场架梁施工。
在本说明书的描述中,参考术语“一个实施例”、“一些实施例”、“示例”、“具体示例”、或“一些示例”等的描述意指结合该实施例或示例描述的具体特征、结构、材料或者特点包含于本发明的至少一个实施例或示例中。在本说明书中,对上述术语的示意性表述不必须针对的是相同的实施例或示例。而且,描述的具体特征、结构、材料或者特点可以在任一个或多个实施例或示例中以合适的方式结合。此外,在不相互矛盾的情况下,本领域的技术人员可以将本说明书中描述的不同实施例或示例以及不同实施例或示例的特征进行结合和组合。
以上所述仅为本发明的较佳实施例,并不用以限制本发明,凡在本发明的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。

Claims (8)

  1. 一种小间距多桥并行段箱梁同步运架施工方法,其特征在于,包括以下步骤:
    1)架设第一双线桥(1);
    2)所述第一双线桥(1)架设完成后,架桥机右移架设第二双线桥(2),并通过所述第一双线桥(1)运梁;
    3)所述第二双线桥(2)架设完成后,所述架桥机左移架设第二单线桥(3),并通过所述第一双线桥(1)运梁;
    4)所述第二单线桥(3)架设完成后,所述架桥机右移架设所述第二双线桥(2)延长出来的第三单线桥(4),并通过所述第一双线桥(1)运梁;
    5)所述第三单线桥(4)架设完成后,所述架桥机右移架设所述第二双线桥(2)延长出来的第四单线桥(5),并通过所述第一双线桥(1)运梁;
    6)所述第四单线桥(5)架设完成后,所述架桥机左移架设第一单线桥(6),并通过所述第一双线桥(1)运梁。
  2. 根据权利要求1所述的小间距多桥并行段箱梁同步运架施工方法,其特征在于:线桥两端分别设置有梁场(7)和提梁机横移区(8),所述提梁机横移区(8)安装有提梁机;
    所述架桥机左移或右移时,返回所述梁场(7)掉头或通过所述提梁机实现左移或右移。
  3. 根据权利要求1所述的小间距多桥并行段箱梁同步运架施工方法,其特征在于:步骤1)至步骤6)中,架桥时先小里程方向架设,再大里程方向架设。
  4. 根据权利要求1所述的小间距多桥并行段箱梁同步运架施工方法,其特征在于:所述架桥机的主支腿伸出桥面的宽度小于2.4m。
  5. 根据权利要求1至4任一项所述的小间距多桥并行段箱梁同步运架施工方法,其特征在于:运梁车运梁时,所述运梁车为分离式运梁车。
  6. 根据权利要求2所述的小间距多桥并行段箱梁同步运架施工方法,其特征在于:所述梁场(7)设置有提梁上桥区(9),且所述提梁上桥区(9)包括至少一台横跨四桥六线的提梁机和至少一台单双共用的发运台座。
  7. 根据权利要求6所述的小间距多桥并行段箱梁同步运架施工方法,其特征在于:所述提梁机横移区(8)设置有至少一台横跨四桥六线的提梁机。
  8. 根据权利要求1所述的小间距多桥并行段箱梁同步运架施工方法,其特征在于:步骤6)后还包括支座灌浆,待灌浆料的强度达到20Mpa后,拆除灌浆料模板。
PCT/CN2021/116670 2021-08-04 2021-09-06 一种小间距多桥并行段箱梁同步运架施工方法 WO2023010644A1 (zh)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN202110891333.8 2021-08-04
CN202110891333.8A CN113756190B (zh) 2021-08-04 2021-08-04 一种小间距多桥并行段箱梁同步运架施工方法

Publications (1)

Publication Number Publication Date
WO2023010644A1 true WO2023010644A1 (zh) 2023-02-09

Family

ID=78788550

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2021/116670 WO2023010644A1 (zh) 2021-08-04 2021-09-06 一种小间距多桥并行段箱梁同步运架施工方法

Country Status (3)

Country Link
CN (1) CN113756190B (zh)
LU (1) LU502495B1 (zh)
WO (1) WO2023010644A1 (zh)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007321389A (ja) * 2006-05-31 2007-12-13 Nippon Sharyo Seizo Kaisha Ltd 橋梁架設工法
CN106567342A (zh) * 2016-11-10 2017-04-19 上海市基础工程集团有限公司 局促空间超宽桥面高低腿门吊架设预制梁方法
CN107165055A (zh) * 2017-07-07 2017-09-15 中铁二局集团有限公司 一种大吨位、非对称、分幅预制箱梁梁上运梁及整孔架设施工方法
CN107165051A (zh) * 2017-05-15 2017-09-15 中铁三局集团线桥工程有限公司 高架站单双线箱梁架设施工方法
CN107675630A (zh) * 2017-09-09 2018-02-09 中建八局第三建设有限公司 一种轻轨高架预制箱梁架设施工装置及其施工方法
CN208501523U (zh) * 2018-05-30 2019-02-15 郑州市华中建机有限公司 一种新型用于架设拼宽梁的架桥机
CN110055902A (zh) * 2019-05-23 2019-07-26 中铁二局集团有限公司 一种大吨位箱梁正位提梁上桥施工方法及其架设方法

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5203662B2 (ja) * 2007-09-26 2013-06-05 株式会社エム・テック 架設桁による橋梁主桁の架設方法および架設桁の横取り機構
CN106758861A (zh) * 2017-03-17 2017-05-31 王燏斌 一种造桥装置及其施工法
CN208104910U (zh) * 2018-03-30 2018-11-16 中铁二局第四工程有限公司 一种中低速磁悬浮低置线路路基结构
CN110230261B (zh) * 2019-05-21 2021-08-17 宁波市政工程建设集团股份有限公司 一种双层同步梁上架梁的安装施工方法

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007321389A (ja) * 2006-05-31 2007-12-13 Nippon Sharyo Seizo Kaisha Ltd 橋梁架設工法
CN106567342A (zh) * 2016-11-10 2017-04-19 上海市基础工程集团有限公司 局促空间超宽桥面高低腿门吊架设预制梁方法
CN107165051A (zh) * 2017-05-15 2017-09-15 中铁三局集团线桥工程有限公司 高架站单双线箱梁架设施工方法
CN107165055A (zh) * 2017-07-07 2017-09-15 中铁二局集团有限公司 一种大吨位、非对称、分幅预制箱梁梁上运梁及整孔架设施工方法
CN107675630A (zh) * 2017-09-09 2018-02-09 中建八局第三建设有限公司 一种轻轨高架预制箱梁架设施工装置及其施工方法
CN208501523U (zh) * 2018-05-30 2019-02-15 郑州市华中建机有限公司 一种新型用于架设拼宽梁的架桥机
CN110055902A (zh) * 2019-05-23 2019-07-26 中铁二局集团有限公司 一种大吨位箱梁正位提梁上桥施工方法及其架设方法

Also Published As

Publication number Publication date
LU502495B1 (en) 2023-01-12
CN113756190A (zh) 2021-12-07
CN113756190B (zh) 2023-01-24

Similar Documents

Publication Publication Date Title
US11391004B1 (en) Construction method for upright lifting of large-tonnage box girder to bridge, and erection method for large-tonnage box girder
CN102182147B (zh) 一种钢箱梁架设方法
CN111852521B (zh) 大断面盾构隧道内部结构施工用口字件拼装台车及同步施工方法
CN107740350A (zh) 全预制桥梁架桥机的桥墩柱施工方法及其过孔方法
CN110847062A (zh) 80米跨宽幅钢箱梁厂内整孔拼装双幅架设施工方法
CN206538672U (zh) 新型装配式桁架钢栈桥
CN104727227A (zh) 一种中承式钢箱系杆拱桥敞口格构式钢梁整节段架设方法
CN209652741U (zh) 一种跨铁路站场大跨度高架桥
WO2023010644A1 (zh) 一种小间距多桥并行段箱梁同步运架施工方法
JP5184248B2 (ja) 立体交差の施工方法
CN112681135B (zh) 一种几字形跨海临时钢栈桥的施工方法
BR112020024195B1 (pt) Estrutura de barra composta por concreto e aço adequada para uma ferrovia de transporte pesado
CN217810564U (zh) 一种预制箱梁多节段悬臂非对称拼接系统
CN107091105A (zh) 用于实现叠交隧道连续施工的空中钢平台及其施工方法
WO2023000921A1 (zh) 一种轨桥一体捷运系统及翻坝运输系统
CN113944106A (zh) 一种陆地矮墩桥梁上桥用钢栈桥通道及其施工方法
CN114790687A (zh) 大跨度钢箱连拱桥施工方法
CN109629454B (zh) 一种单侧提升节段梁的架桥设备和架桥方法
CN201459609U (zh) 一种斜交箱梁架桥机
CN111676972A (zh) 一种在基坑上施工用的安全操作平台
CN219044795U (zh) 一种龙门吊90°转向多轴走行轮
CN110331693A (zh) 一种全装配式钢码头结构及其施工方法
CN216212364U (zh) 用于双层安全壳核电厂的设备运输平台及核电厂安全壳系统
CN210684482U (zh) 一种上承式拱桥施工用钢拱架分段移送装置
US11732428B2 (en) System for construction of double u and single u steel concrete composite structure for bridges

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 21952513

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE