WO2021124671A1 - 作業機械の作業補助装置および作業現場における施工面認識方法 - Google Patents

作業機械の作業補助装置および作業現場における施工面認識方法 Download PDF

Info

Publication number
WO2021124671A1
WO2021124671A1 PCT/JP2020/039417 JP2020039417W WO2021124671A1 WO 2021124671 A1 WO2021124671 A1 WO 2021124671A1 JP 2020039417 W JP2020039417 W JP 2020039417W WO 2021124671 A1 WO2021124671 A1 WO 2021124671A1
Authority
WO
WIPO (PCT)
Prior art keywords
work
construction surface
information
unit
ground reference
Prior art date
Application number
PCT/JP2020/039417
Other languages
English (en)
French (fr)
Inventor
小川 徹也
宏明 河合
俊宏 野木
佑介 上村
大輔 野田
Original Assignee
株式会社神戸製鋼所
コベルコ建機株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 株式会社神戸製鋼所, コベルコ建機株式会社 filed Critical 株式会社神戸製鋼所
Priority to CN202080086367.3A priority Critical patent/CN114787456A/zh
Priority to US17/785,841 priority patent/US20230019245A1/en
Priority to EP20901313.5A priority patent/EP4060127A1/en
Publication of WO2021124671A1 publication Critical patent/WO2021124671A1/ja

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F3/00Dredgers; Soil-shifting machines
    • E02F3/04Dredgers; Soil-shifting machines mechanically-driven
    • E02F3/96Dredgers; Soil-shifting machines mechanically-driven with arrangements for alternate or simultaneous use of different digging elements
    • E02F3/963Arrangements on backhoes for alternate use of different tools
    • E02F3/964Arrangements on backhoes for alternate use of different tools of several tools mounted on one machine
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F9/00Component parts of dredgers or soil-shifting machines, not restricted to one of the kinds covered by groups E02F3/00 - E02F7/00
    • E02F9/26Indicating devices
    • E02F9/261Surveying the work-site to be treated
    • E02F9/262Surveying the work-site to be treated with follow-up actions to control the work tool, e.g. controller
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F3/00Dredgers; Soil-shifting machines
    • E02F3/04Dredgers; Soil-shifting machines mechanically-driven
    • E02F3/76Graders, bulldozers, or the like with scraper plates or ploughshare-like elements; Levelling scarifying devices
    • E02F3/7609Scraper blade mounted forwardly of the tractor on a pair of pivoting arms which are linked to the sides of the tractor, e.g. bulldozers
    • E02F3/7613Scraper blade mounted forwardly of the tractor on a pair of pivoting arms which are linked to the sides of the tractor, e.g. bulldozers with the scraper blade adjustable relative to the pivoting arms about a vertical axis, e.g. angle dozers
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F3/00Dredgers; Soil-shifting machines
    • E02F3/04Dredgers; Soil-shifting machines mechanically-driven
    • E02F3/76Graders, bulldozers, or the like with scraper plates or ploughshare-like elements; Levelling scarifying devices
    • E02F3/7609Scraper blade mounted forwardly of the tractor on a pair of pivoting arms which are linked to the sides of the tractor, e.g. bulldozers
    • E02F3/7618Scraper blade mounted forwardly of the tractor on a pair of pivoting arms which are linked to the sides of the tractor, e.g. bulldozers with the scraper blade adjustable relative to the pivoting arms about a horizontal axis
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F3/00Dredgers; Soil-shifting machines
    • E02F3/04Dredgers; Soil-shifting machines mechanically-driven
    • E02F3/76Graders, bulldozers, or the like with scraper plates or ploughshare-like elements; Levelling scarifying devices
    • E02F3/80Component parts
    • E02F3/84Drives or control devices therefor, e.g. hydraulic drive systems
    • E02F3/841Devices for controlling and guiding the whole machine, e.g. by feeler elements and reference lines placed exteriorly of the machine
    • E02F3/842Devices for controlling and guiding the whole machine, e.g. by feeler elements and reference lines placed exteriorly of the machine using electromagnetic, optical or photoelectric beams, e.g. laser beams
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F3/00Dredgers; Soil-shifting machines
    • E02F3/04Dredgers; Soil-shifting machines mechanically-driven
    • E02F3/76Graders, bulldozers, or the like with scraper plates or ploughshare-like elements; Levelling scarifying devices
    • E02F3/80Component parts
    • E02F3/84Drives or control devices therefor, e.g. hydraulic drive systems
    • E02F3/844Drives or control devices therefor, e.g. hydraulic drive systems for positioning the blade, e.g. hydraulically
    • E02F3/847Drives or control devices therefor, e.g. hydraulic drive systems for positioning the blade, e.g. hydraulically using electromagnetic, optical or acoustic beams to determine the blade position, e.g. laser beams
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F9/00Component parts of dredgers or soil-shifting machines, not restricted to one of the kinds covered by groups E02F3/00 - E02F7/00
    • E02F9/26Indicating devices
    • E02F9/261Surveying the work-site to be treated
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F9/00Component parts of dredgers or soil-shifting machines, not restricted to one of the kinds covered by groups E02F3/00 - E02F7/00
    • E02F9/26Indicating devices
    • E02F9/264Sensors and their calibration for indicating the position of the work tool
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F9/00Component parts of dredgers or soil-shifting machines, not restricted to one of the kinds covered by groups E02F3/00 - E02F7/00
    • E02F9/26Indicating devices
    • E02F9/267Diagnosing or detecting failure of vehicles

Definitions

  • the present invention relates to a work assisting device of a work machine capable of assisting work using a work machine and a method of recognizing a construction surface at a work site.
  • a work machine having a machine body and a work member supported by the machine body so as to be relatively movable with respect to the machine body
  • the working member is, for example, an attachment including a soil removal plate or a bucket capable of performing excavation work or leveling work.
  • Patent Document 1 describes a target work surface setting device (work assist device) that enables a worker of a work machine to easily grasp the position of a target work surface (construction surface) virtually set in the ground. )
  • the target work surface setting device includes a work machine side computer provided in the work machine and an office side computer arranged in an office away from the work site.
  • the setting switch of the work machine side computer is turned on, the work site-specific 3D data including the plan view and the cross-sectional view is transmitted from the office side computer to the work machine side computer via the transmitter / receiver.
  • the work machine side computer calculates the position information of the target work surface based on the received 3D data.
  • the work machine side computer is three-dimensional of the work machine at the work site based on the position information received from the GPS antenna device provided in the work machine and the correction information received from the GPS reference station provided at the work site. Calculate the position information. Further, the computer on the work machine side compares the calculated position information of the target work surface with the three-dimensional position information of the work machine to see if the work machine is located within a range in which the work member can reach the target work surface. It is determined whether or not it is present, and the determination result is notified to the operator. Since the worker can grasp the relative positional relationship between the work member and the target work surface from the notification information, it is possible to efficiently perform excavation work and ground leveling work at the work site.
  • Patent Document 1 in order to set the construction surface (target work surface), a communication mechanism that enables communication between the work machine side computer and the office side computer is required, and a communication mechanism is required.
  • the work machine side computer needs to have a large-capacity storage unit for storing 3D data according to the work site. For this reason, the configuration of the work assist device for assisting the work of the work machine is complicated and the cost is increased, so that there is a problem that it is difficult for some installers to introduce such a work assist device.
  • An object of the present invention is a work assisting device and work of a work machine that enables a worker to easily recognize a construction surface without requiring reception of 3D data according to a work site from the outside or storage in advance. It is to provide a method of recognizing the construction surface at the site.
  • the work assisting device of the work machine is capable of moving relative to the machine body including the traveling portion capable of traveling on the ground and the machine body. It is a work assisting device of a work machine capable of assisting the work of forming a predetermined construction surface at a work site by using a work machine having a work member supported by the machine body and capable of excavating the ground. ..
  • the work assisting device includes a main body coordinate information acquisition unit capable of acquiring main body coordinate information which is information on absolute coordinates of the main body reference point provided in the machine main body in advance at the work site, and the main body reference point.
  • the main body posture information acquisition unit that can acquire the main body posture information that is information on the posture of the machine main body as a reference, and the working member position information that is information on the relative position of the working member with respect to the machine main body.
  • the specific part coordinate calculation unit capable of calculating and outputting the absolute coordinates of the specific part of the work member at the work site is associated with the construction surface.
  • An arrangement information receiving unit capable of receiving arrangement information which is information indicating that the specific portion of the working member is arranged at at least three ground reference points according to the traveling of the traveling unit, and the above-mentioned
  • the absolute coordinates of the specific part calculated by the specific part coordinate calculation unit in response to the arrangement information receiving unit receiving the arrangement information at each of the at least three ground reference points are set to the absolute coordinates of the specific part of the at least three ground reference points. It is possible to accept input of at least three distance information, which is information regarding the distance in the vertical direction from each of the storage unit and the at least three ground reference points to the construction surface, which are stored as absolute coordinates at the work site.
  • the work site It includes a construction surface calculation unit that calculates the equation of the construction surface in the absolute coordinate system, and a construction surface information output unit that outputs information about the equation of the construction surface calculated by the construction surface calculation unit.
  • the construction surface recognition method at a work site excavates the ground supported by the machine body so as to be relatively movable with respect to the machine body including a traveling portion capable of traveling on the ground.
  • Each of the work machine having the work member capable of performing the work and the work assist device of the work machine are prepared, and at least the at least 3 associated with the construction surface is associated with the running of the traveling portion.
  • the specific parts of the work member are arranged in order at one ground reference point, and the absolute coordinates of the specific part calculated by the specific part coordinate calculation unit corresponding to each ground reference point are used as absolute coordinates of each ground reference point.
  • Each is stored in the storage unit, and at least three distance information, which is information on the distance in the vertical direction from each of the at least three ground reference points to the construction surface, is input to the distance information input unit. And, from the absolute coordinates of the at least three ground reference points stored in the storage unit and the at least three distance information input to the distance information input unit, the construction in the absolute coordinate system of the work site. To calculate the surface equation, output the information about the calculated construction surface equation, and make the operator recognize the position of the construction surface at the work site based on the output information. To be equipped.
  • the construction surface recognition method at the work site is supported by the machine body so as to be relatively movable with respect to the machine body including the traveling portion capable of traveling on the ground and the ground.
  • the work machine having the work member capable of excavating the work machine and the work assist device of the work machine are prepared, and the work auxiliary device associated with the construction surface is associated with at least according to the running of the traveling portion.
  • the specific parts of the work member are sequentially arranged at at least three ground reference points, and the absolute coordinates of the specific part calculated by the specific part coordinate calculation unit corresponding to each ground reference point are set to the absolute coordinates of each ground reference point.
  • At least three distance information which are stored in the storage unit as coordinates and information on the distance in the vertical direction from each of the at least three ground reference points to the construction surface, are input to the distance information input unit.
  • the absolute coordinates of the at least three ground reference points stored in the storage unit and the at least three distance information input to the distance information input unit in the absolute coordinate system of the work site.
  • To calculate the equation of the construction surface output the information about the calculated equation of the construction surface, and make the worker recognize the position of the construction surface at the work site based on the output information.
  • a confirmation reference member including a straight line portion parallel to the construction surface and orthogonal to the traveling direction of the traveling portion of the working machine in a plan view is arranged at the work site, and the working machine is operated.
  • the lower end of the soil removal plate extending in the left-right direction is aligned with the straight portion of the confirmation reference member, and the distances between the left and right ends of the lower end of the soil removal plate and the construction surface are compared with each other. This includes confirming whether or not the calculated construction surface equation is included in the predetermined allowable range.
  • FIG. 1 is a schematic side sectional view for explaining the structure of the excavator 100 (working machine) including the construction surface setting device 1 (work assisting device) (FIG. 2) according to the present embodiment.
  • FIG. 2 is a block diagram of the excavator 100 including the construction surface setting device 1 according to the present embodiment.
  • FIG. 3 is a side view for explaining the coordinate information of the construction surface setting device 1 and the excavator 100 according to the present embodiment, and FIG. 4 is a plan view of the same.
  • the construction surface setting device 1 is provided on the hydraulic excavator 100.
  • the excavator 100 includes a machine body 10, an attachment 30, and a dozer portion 40.
  • the machine body 10 has a lower body 11 and an upper swivel body 20.
  • Crawler units 12 (running portions) capable of traveling on the ground are arranged on both the left and right sides of the lower main body 11.
  • the upper swivel body 20 is arranged behind the swivel frame 21, a swivel frame 21 that is rotatably supported around a swivel center axis extending in the vertical direction on the lower body 11, a cab 22 that allows an operator to board, and a cab 22. It has an engine room 23, an engine 24, a first hydraulic pump 25, a second hydraulic pump 26, and a support portion 27.
  • the engine 24 is arranged in the engine room 23.
  • the first hydraulic pump 25 and the second hydraulic pump 26 are driven by the engine 24 and discharge hydraulic oil to a hydraulic circuit (not shown) for driving the attachment 30 and the dozer portion 40, respectively.
  • the support portion 27 is arranged on the swivel frame 21 on the right side of the cab 22 (on the back side of the paper surface in FIG. 1), and supports the attachment 30 in an undulating manner.
  • the attachment 30 includes a swingable boom, an arm, and a bucket, respectively, and performs predetermined excavation work and the like.
  • the dozer portion 40 (working member) is arranged on the front side portion of the lower main body 11.
  • the dozer portion 40 is supported by the machine body 10 so that it can move relative to the machine body 10, and the ground can be excavated.
  • the dozer portion 40 has a soil removal plate 41 and a support frame 42 (soil removal plate support portion) that supports the soil removal plate 41.
  • the excavator 100 has a lift cylinder 43, a pair of left and right angle cylinders 44, and a tilt cylinder 45.
  • the support frame 42 is supported by the lower body 11 of the machine body 10 so as to swing around the lift rotation center axis F1 extending in the left-right direction, and supplies hydraulic oil to the lift cylinder 43 from the second hydraulic pump 26.
  • the support frame 42 swings around the lift rotation shaft F1 by expanding and contracting according to the discharge.
  • the soil removal plate 41 swings in the lift direction D1 of FIG. 1, and the lift angle of the soil removal plate 41 (dozer portion 40) changes.
  • the pair of left and right angle cylinders 44 expand and contract according to the supply and discharge of hydraulic oil received from the second hydraulic pump 26, so that the soil discharge plate 41 swings around the angle rotation shaft F2.
  • the soil removal plate 41 swings in the angle direction D2 of FIG. 1, and the angle angle of the soil removal plate 41 (dozer portion 40) changes.
  • the soil removal plate 41 is supported by the tip end portion of the support frame 42 so as to swing around the tilt rotation axis F3 extending in the left-right direction. Then, the tilt cylinder 45 expands and contracts according to the supply and discharge of the hydraulic oil received from the second hydraulic pump 26, so that the soil discharge plate 41 swings around the tilt rotation axis F3 in the tilt direction D3 of FIG.
  • the tilt angle of the plate 41 (dozer portion 40) changes.
  • the construction surface setting device 1 (work assist device of the work machine) provided in the excavator 100 includes a control unit 50, an operation unit 51, an input unit 52, a main body coordinate detection unit 53, and the main body coordinate detection unit 53. It has a main body angle detection unit 54, a soil removal plate angle detection unit 55, a drive unit 56, a display unit 57, and a notification unit 58.
  • the construction surface setting device 1 can assist the work of forming a predetermined construction surface TS (see FIGS. 8 and 10) at the work site.
  • the operation unit 51 is arranged in the cab 22 and receives operation commands related to the traveling operation of the crawler unit 12, the turning operation of the upper swing body 20, the attachment 30 and the driving of the dozer unit 40 by the operator.
  • the input unit 52 (arrangement information reception unit, distance information input unit) is arranged in the cab 22 and accepts input of various information by the operator.
  • at least three ground reference points associated with the construction surface TS of the work site, and the specific parts of the soil removal plate 41 can be sequentially arranged on the ground.
  • the input unit 52 sequentially receives the arrangement information, which is information indicating that the specific portion of the soil removal plate 41 is arranged at least at least three ground reference points arranged above according to the traveling of the crawler unit 12. Is possible.
  • the input unit 52 is capable of receiving input of at least three distance information, which is information on the distance in the vertical direction from each of the at least three ground reference points to the construction surface TS.
  • the main body coordinate detection unit 53 can acquire main body coordinate information which is information on absolute coordinates at the work site of the main body reference point provided in advance on the machine main body 10.
  • the main body coordinate detection unit 53 includes a GNSS (Global Navigation Satellite System) reference station 61 and a GNSS mobile station 62. Further, the main body reference point is arranged on the upper surface portion of the cab 22.
  • the GNSS reference station 61 is a reference station located at the work site or located at the position closest to the work site, and has three axes of x0 axis, y0 axis, and z0 axis with respect to the origin G0 as shown in FIG. The absolute coordinates are determined.
  • the GNSS mobile station 62 is arranged on the upper surface of the cab 22 corresponding to the main body reference point.
  • GNSS in addition to the known GPS (Global Positioning System), GLONASS (Global Navigation Satellite System), Galileo, Quasi-Zenith Satellite (QZSS: Quasi-Zenith Satellite System) and other satellites may be adopted.
  • the main body angle detection unit 54 can acquire main body posture information which is information on the posture of the machine main body 10 with the main body reference point as a reference.
  • the main body angle detection unit 54 is an angle sensor (main body angle sensor) arranged on the upper surface portion of the cab 22 corresponding to the main body reference point.
  • the main body angle detection unit 54 detects rotations around the x1 axis, the y1 axis, and the z1 axis with reference to the mobile station origin G1 in FIGS. 3 and 4, respectively, and is a known IMU (Inertial Measurement Unit) inertial measurement unit. ) Is used. That is, the main body angle detection unit 54 detects and outputs the lift angle, pitch angle, and yaw angle of the machine main body 10 with respect to the main body reference point as the main body posture information, respectively.
  • IMU Inertial Measurement Unit
  • the soil removal plate angle detection unit 55 can acquire work member position information which is information on the relative position of the dozer unit 40 (soil removal plate 41) with respect to the machine body 10.
  • the soil removal plate angle detection unit 55 is an angle sensor (soil removal plate angle sensor) arranged on the soil removal plate 41.
  • the soil removal plate angle detection unit 55 detects rotations around the x3 axis, y3 axis, and z3 axis with reference to the soil removal plate origin G3 in FIGS. 3 and 4, respectively, and in the present embodiment, the main body angle detection unit 55. IMU is used as in 54. That is, the soil removal plate angle detection unit 55 detects and outputs the lift angle, the angle angle, and the tilt angle of the soil removal plate 41 as the work member position information, respectively.
  • the drive unit 56 includes the engine 24, the first hydraulic pump 25, and the second hydraulic pump 26 described above, and further has a drive transmission mechanism such as other hydraulic circuits and gears.
  • the drive unit 56 receives a control signal from the drive control unit 501 of the control unit 50 and drives the crawler unit 12, the swivel frame 21, the attachment 30, and the dozer unit 40.
  • the display unit 57 is arranged in the cab 22 and displays various information related to the operation of the excavator 100.
  • the display unit 57 can display the position information (information about the construction surface TS) of the construction surface TS based on the equation of the construction surface TS output from the output unit 506 described later. Further, the display unit 57 can further display information on the relative position between the construction surface TS and the specific portion based on the absolute coordinates of the specific portion output from the soil removal plate coordinate calculation unit 502. is there.
  • the notification unit 58 is arranged inside the cab 22 or outside the excavator 100, and notifies the operator of various types of information.
  • the notification unit 58 includes a speaker, a buzzer, a light, and the like.
  • the control unit 50 is composed of a CPU (Central Processing Unit), a ROM (Read Only Memory) for storing a control program, a RAM (Random Access Memory) used as a work area of the CPU, and the like. Further, the control unit 50 is connected to an operation unit 51, an input unit 52, a main body coordinate detection unit 53, a main body angle detection unit 54, a soil removal plate angle detection unit 55, a drive unit 56, a display unit 57, a notification unit 58, and the like. Has been done.
  • a CPU Central Processing Unit
  • ROM Read Only Memory
  • RAM Random Access Memory
  • the control unit 50 When the CPU executes a control program stored in the ROM, the control unit 50 includes a drive control unit 501, a soil removal plate coordinate calculation unit 502, a construction surface calculation unit 503, a determination unit 504, a storage unit 505, and an output unit. It functions to include the 506.
  • the drive control unit 501 controls the drive unit 56 so as to drive the crawler unit 12, the swivel frame 21, the attachment 30, and the dozer unit 40 in response to a command signal input to the operation unit 51.
  • the soil removal plate coordinate calculation unit 502 calculates the absolute coordinates of the specific part of the soil removal plate 41 at the work site. Specifically, the soil removal plate coordinate calculation unit 502 uses the main body coordinate information acquired by the main body coordinate detection unit 53, the main body posture information acquired by the main body angle detection unit 54, and the soil removal plate angle detection unit 55. Based on the acquired work member position information, it is possible to calculate and output the absolute coordinates of a specific portion of the soil removal plate 41 at the work site.
  • the construction surface calculation unit 503 uses the absolute coordinates of the at least three ground reference points stored in the storage unit 505 and the at least three distance information input to the input unit 52 in the absolute coordinate system of the work site. Calculate the equation of the construction surface TS. More specifically, the construction surface calculation unit 503 uses at least three virtual references arranged below the at least three ground reference points from the absolute coordinates of the at least three ground reference points and the at least three distance information. The absolute coordinates of the points are calculated, and the equation of the construction surface TS is calculated based on the calculated at least three virtual reference points. The calculation method of the construction surface TS will be described in detail later.
  • the determination unit 504 executes various determination operations in the flow of the construction surface TS setting process. Further, the determination unit 504 executes a predetermined determination process at the time of confirming the equation of the construction surface TS calculated and determined by the construction surface calculation unit 503.
  • the storage unit 505 stores various information referred to in the flow of the construction surface TS setting process. Further, the storage unit 505 stores various threshold information and the like in advance. Further, the storage unit 505 sets the absolute coordinates of the specific portion calculated by the soil removal plate coordinate calculation unit 502 in response to the input unit 52 receiving the arrangement information at the at least three ground reference points. Each of the three ground reference points is stored as absolute coordinates at the work site.
  • the output unit 506 (construction surface information output unit) outputs information related to the equation of the construction surface TS calculated and determined by the construction surface calculation unit 503.
  • FIG. 5 is a flowchart of the construction surface setting process in the construction surface setting device 1 according to the present embodiment.
  • 6 and 7 are flowcharts showing a part of the construction surface setting process of FIG.
  • FIG. 8 is a perspective view of the work site of the excavator 100 including the construction surface setting device 1 according to the present embodiment.
  • FIG. 9 is a schematic view for explaining how the construction surface TS is calculated by the construction surface setting device 1 according to the present embodiment.
  • the soil removal plate 41 of the excavator 100 has a lower end portion 41S extending in the left-right direction. Further, the left and right end portions of the lower end portion 41S of the soil removal plate 41 are defined as the soil removal plate left end portion 41L and the soil removal plate right end portion 41R, respectively.
  • the left end portion 41L of the soil removal plate 41 functions as a specific part in order to acquire the position information (equation of a plane) of the construction surface TS in the absolute coordinate system of the work site.
  • the ground GL is provided with three chopsticks. That is, the first horizontal plate K1 is fixed to the first vertical plate J1 inserted into the ground GL, the second horizontal plate K2 is fixed to the second vertical plate J2, and the third horizontal plate K2 is fixed to the third vertical plate J3.
  • the plate K3 is fixed.
  • the first vertical plate J1, the second vertical plate J2, and the third vertical plate J3 are arranged so as to extend in the vertical direction, and the first horizontal plate K1, the second horizontal plate K2, and the third horizontal plate K3 extend horizontally. It is arranged in.
  • each horizontal plate On the upper surface of each horizontal plate, a first reference point P1, a second reference point P2, and a third reference point P3 (all ground reference points) corresponding to the construction surface TS to be formed by excavation and leveling work are previously provided. It is set. Further, the distances in the vertical direction from the first reference point P1, the second reference point P2 and the third reference point P3 to the construction surface TS, that is, the first depth L1, the second depth L2 and the third depth L3 ( In each case, the distance information) is a value known in advance at the work site. These distances are indicated, for example, on the side surfaces of the first horizontal plate K1, the second horizontal plate K2, and the third horizontal plate K3, respectively.
  • the points located below the first reference point P1, the second reference point P2, and the third reference point P3 by the first depth L1, the second depth L2, and the third horizontal plate K3, respectively, are the first points. It is defined as 1 virtual point Q1, 2nd virtual point Q2, and 3rd virtual point Q3 (all are virtual reference points). It is assumed that the first reference point P1, the second reference point P2, and the third reference point P3 are not arranged in a straight line.
  • step S1 when the worker starts the construction surface TS setting processing flow at the work site, the construction surface calculation step is first performed (step S1 in FIG. 5).
  • step S1 will be described in detail later.
  • the determination unit 504 of the control unit 50 confirms the construction surface calculation completion flag (step S02).
  • the construction surface calculation completion flag is a flag for determining whether or not the construction surface calculation step in step S01 has been completed, and can be switched between ON and OFF, and is stored and updated in the storage unit 505. .
  • the construction surface calculation completion flag is ON in step S02 (YES in step S02)
  • the determination unit 504 proceeds to step S03.
  • step S03 the determination unit 504 confirms the correction mode switch.
  • the switch is provided in the cab 22 and is provided to determine whether or not to correct the equation of the construction surface TS calculated in step S01 by a predetermined correction flow, which is required by the operator. It switches ON / OFF accordingly.
  • the construction surface calculation unit 503 executes the correction calculation of the construction surface TS. The correction calculation will also be described in detail later.
  • the determination unit 504 confirms whether or not the MC start switch is ON (step S05).
  • the switch is an automatic MC (machine control), that is, a switch for determining whether or not the excavator 100 automatically performs the construction of the construction surface TS, and is provided in the cab 22.
  • automatic MC is executed based on the calculated construction surface TS (step S06).
  • step S05 when the MC start switch is OFF (NO in step S05), it is determined that the operator has the intention to carry out the construction of the construction surface TS by himself / herself, the processing flow returns to step S01, and the previous step S01
  • the equation of the construction surface TS calculated and determined in the above, the position information, and the like are displayed on the display unit 57. By confirming the displayed information, the worker can perform the work by himself / herself while recognizing the position of the construction surface TS.
  • the soil removal plate coordinate calculation unit 502 executes the cutting edge coordinate calculation (step S11).
  • the soil removal plate coordinate calculation unit 502 uses the detection results of the main body coordinate detection unit 53 (GNSS reference station 61, GNSS mobile station 62), the main body angle detection unit 54, and the soil removal plate angle detection unit 55 to indicate the cutting edge, that is, soil removal.
  • the absolute coordinates (global coordinates) at the work site of the left end 41L of the soil removal plate of the plate 41 are calculated.
  • the calculation is executed in substantially real time at predetermined time intervals (for example, 1 second) while the construction surface calculation step S01 is being executed.
  • the soil removal plate coordinate calculation unit 502 acquires the known coordinates of the GNSS reference station 61 and the coordinate vector of the GNSS mobile station 62 from the GNSS. Further, the vectors from the GNSS mobile station 62 (mobile station origin G1) to the frame origin G2 located at the base end of the support frame 42 of the dozer portion 40 and the soil removal plate origin G3 of the soil removal plate 41 are vectorized by the machine body 10. Introduction Calculated from the length and the angle of rotation detected by each angle sensor. As a result, the soil removal plate coordinate calculation unit 502 can calculate the absolute coordinates of the left end portion 41L of the soil removal plate 41 of the soil removal plate 41, so that the coordinates of each reference point at the time of subsequent reference point input can be acquired. Is possible.
  • the reference information reception step is started (step S12 in FIG. 6).
  • an input request for the reference point number N is displayed on the display unit 57, and the operator inputs the value of the reference point number N through the input unit 52 (step S21).
  • the reference point N corresponds to the number of reference points (ground reference points) set on the ground.
  • N 3 is input.
  • a setting instruction for storing the absolute coordinates of the first reference point P1 is received by the input unit 52 (step S22), and the coordinates of the first reference point P1 are stored in the storage unit 505.
  • the absolute coordinates of the left end portion 41L of the soil removal plate calculated by the soil removal plate coordinate calculation unit 502 are stored in the storage unit 505 as the absolute coordinates of the first reference point P1 (step S23).
  • the depth information (first depth L1) of the first virtual point Q1 is stored in the storage unit 505 (step S25).
  • step S26 when n ⁇ N, that is, n ⁇ N (NO in step S26), 1 is added to the current n (step S27), and the steps after step S22 are repeated.
  • the absolute coordinates of the first reference point P1, the second reference point P2, and the third reference point P3 at the work site, and the first depth L1, the second depth L2, and the third depth L3 The values are stored in the storage unit 505, respectively.
  • step S13 of FIG. 6 the determination unit 504 determines whether the storage unit 505 stores the absolute coordinates and depth information of each reference point as described above.
  • the construction surface calculation unit 503 calculates the position of the target construction surface (equation of a plane). (Step S14). If the absolute coordinates and depth information of the N sets of reference points are not stored in step S13 (NO in step S13), the construction surface calculation unit 503 sets the construction surface calculation completion flag stored in the storage unit 505. It is updated to OFF, and step S11 and subsequent steps are repeated.
  • the construction surface calculation unit 503 includes the absolute coordinates of the first reference point P1, the second reference point P2, and the third reference point P3 (three specific ground reference points), the first depth L1, and the second depth. From the L2 and the third depth L3 (three specific distance information), the first virtual point Q1, the second virtual point Q2, and the third virtual point Q3 (3) arranged below the three specific ground reference points, respectively. Calculate the absolute coordinates of one specific virtual reference point). At this time, the absolute coordinates of the corresponding virtual points are calculated by subtracting the corresponding depth information from the Z coordinates of the absolute coordinates of each reference point. Then, the construction surface calculation unit 503 calculates the equation of the plane passing through the three calculated specific virtual reference points as the equation of the construction surface TS.
  • the construction surface calculation unit 503 calculates the equation of the construction surface TS based on the first virtual point Q1, the second virtual point Q2, and the third virtual point Q3 in step S14 of FIG. explain.
  • N 3
  • the equation of the construction surface TS corresponds to the equation of a plane passing through all of the first virtual point Q1, the second virtual point Q2, and the third virtual point Q3.
  • A, B, C and D become known, and the equation of the construction surface TS can be obtained.
  • the calculation of the equation of the construction surface TS is not limited to the above, and other known solution methods such as the solution method by simultaneous equations can be used.
  • step S14 of FIG. 6 when the construction surface calculation unit 503 calculates and determines the equation of the construction surface TS, the soil removal plate coordinate calculation unit 502 calculates the absolute coordinates of the left end portion 41L of the soil removal plate 41 of the current soil removal plate 41. Calculate (step S15). In other words, the soil removal plate coordinate calculation unit 502 calculates the relative position of the soil removal plate left end portion 41L (cutting edge) with respect to the construction surface TS. Then, the construction surface calculation unit 503 updates the construction surface calculation completion flag of the storage unit 505 to ON (step S16). After that, the process proceeds to step S02 of FIG. 5, and steps S03 to S06 are executed as described above.
  • step S04 of FIG. 5 The operator confirms whether or not the position information (equation of a plane) of the construction surface TS calculated in step S01 is correct, in other words, whether the calculated construction surface TS is included in the predetermined error range. be able to.
  • the horizontal plate of the chopstick for confirmation is provided with a fourth reference point (ground reference point for confirmation) associated with the construction surface TS, and the construction surface is provided from the fourth reference point.
  • the depth information (distance in the vertical direction) to the TS is indicated on the horizontal plate as a known value.
  • the absolute coordinates of the confirmation ground reference point and the depth information are stored in the storage unit 505 by the same flow as in FIG.
  • the construction surface calculation unit 503 calculates the absolute coordinates of the confirmation virtual reference point arranged below the confirmation ground reference point from this information.
  • the determination unit 504 determines the equation of the construction surface TS based on the absolute coordinates of the calculated confirmation virtual reference point and the equation of the construction surface TS calculated by the construction surface calculation unit 503 in step S01. It is determined whether or not the product is within a predetermined allowable range.
  • the determination unit 504 determines that the equation of the construction surface TS is within a predetermined allowable range when the distance between the virtual reference point for confirmation and the construction surface TS is smaller than the preset threshold value. Then, when the distance between the virtual reference point for confirmation and the construction surface TS is larger than the preset threshold value, it is determined that the equation of the construction surface TS is not included in the predetermined allowable range. In the latter case, the output unit 506 may notify the operator of the notification information indicating that the equation of the construction surface TS is abnormal by using the display unit 57 or the notification unit 58.
  • the equation of the construction surface TS is corrected by a predetermined calculation.
  • the equation of the construction surface TS is again calculated based on four virtual points obtained by adding the above-mentioned virtual reference point for confirmation to the first virtual point Q1, the second virtual point Q2, and the third virtual point Q3. It is calculated.
  • the construction surface calculation unit 503 obtains a known mean square plane based on the absolute coordinates of the four virtual points, and uses it as the corrected construction surface TS.
  • the equation of the construction surface TS is calculated so that the sum of squares of the distances from each of the four virtual points to the construction surface TS is minimized.
  • the coefficients of X, Y, and Z in the equation showing the construction surface TS are A, B, and C, respectively, as described above, these A so that the sum of squares of the distances from each of the four virtual points is minimized.
  • B, C parameter values are calculated.
  • F ⁇ (Li) 2.
  • A, B, and C can be obtained.
  • LU decomposition by a known matrix, Lagrange's undetermined constant method, or the like can be adopted.
  • the method of determining the equation of the construction surface TS based on the above four virtual points is not limited to the correction calculation step, and may be adopted in the construction surface calculation step of step S01. That is, in step S01, the construction surface TS is not limited to the one calculated and determined based on the three ground reference points and the distance information, but the construction is performed based on four or more ground reference points and the distance information.
  • the surface TS may be calculated and determined. In this case, by increasing the reference point, it is possible to cancel a delicate setting error when setting the cutting edge.
  • FIG. 10 is a side sectional view of a work site of the excavator 100 including the construction surface setting device 1 according to the present embodiment.
  • FIG. 11 is a perspective view of a work site of the excavator 100 including the construction surface setting device 1 according to the present embodiment.
  • a confirmation chopstick is arranged on the rear end side (front side) of the excavator 100 in the traveling direction at the work site.
  • the chopsticks are a fourth vertical plate J4 and a fifth vertical plate J5 arranged vertically at intervals in the front-rear direction, and a fourth horizontal plate K4 and a fourth horizontal plate K4 arranged so as to straddle the two vertical plates. It has a swash plate K5 and.
  • the fourth horizontal plate K4 is arranged horizontally, and the swash plate K5 is arranged so as to be inclined toward the rear end portion of the construction surface TS.
  • the fourth depth L4 which is the distance from the fourth horizontal plate K4 to the construction surface TS in the vertical direction, is known and is indicated on the side surface of the fourth horizontal plate K4, for example.
  • Such a chopstick has been conventionally arranged at the work site.
  • Excavation work is carried out on the construction surface TS with the inclination of the worker and the swash plate K5 as a guide. As described above, in the conventional work site to which the present invention is not applied, the worker does not recognize the position of the construction surface TS.
  • a plurality of construction surface virtual threads FL (confirmation reference members) are arranged between the plurality of standing plates J arranged so as to surround the construction surface TS at the work site. Will be set up.
  • the construction surface virtual thread FL is arranged in parallel with the construction surface TS, unlike the conventional horizontally arranged water thread, and the distance from the construction surface TS is set to a known fifth depth L5. ing.
  • the construction surface virtual thread FL arranged on the rear end side of the construction surface virtual thread FL shown in FIG. 11 is arranged so as to be orthogonal to the traveling direction DS of the excavator 100 in a plan view.
  • the chopstick shown in FIG. 10 corresponds to a chopstick located at the rear end on the right side of the work site in FIG.
  • the operator operates the excavator 100 and discharges soil to the construction surface virtual thread FL on the front side of the traveling direction DS as shown in FIG. Match the lower end 41S of the plate 41. That is, the left end 41L of the soil removal plate 41 and the right end 41R of the soil removal plate 41 are arranged on the construction surface virtual thread FL.
  • the determination unit 504 becomes the soil removal plate 41 at the left end portion 41L and the soil removal plate right end portion 41R.
  • Each distance to the construction surface TS is calculated, and the magnitude relationship between the calculated distances is compared.
  • the positional relationship between the construction surface TS calculated in the previous flow and the soil removal plate 41 is correctly set, and from the state shown in FIG.
  • the operator operates the excavator 100 and allows the soil removal plate 41 to enter the ground, the excavation work can be accurately performed toward the construction surface TS.
  • the difference between the distances compared above is larger than the threshold value, there is a problem in the arrangement of the soil removal plate 41 or the position (equation) of the construction surface TS, and the output unit 506 outputs the information.
  • the operator is notified through the display unit 57 and the notification unit 58. Therefore, it is possible to check the traveling direction of the machine body 10 and offset processing of each angle sensor error by detecting the horizontal.
  • the construction surface TS of the soil removal plate 41 When the operator operates the excavator 100 from the state shown in FIG. 11 and performs the excavation work by the soil removal plate 41, in the present embodiment, as shown in FIG. 10, the construction surface TS of the soil removal plate 41 The excavation angle ⁇ with respect to the above is calculated and displayed on the display unit 57.
  • the absolute coordinates (equation of a plane) of the construction surface TS are known, and the soil removal plate coordinate calculation unit 502 determines the absolute coordinates of the soil removal plate right end 41R and the soil removal plate left end 41L of the soil removal plate 41. Since the calculation can be performed, the excavation angle ⁇ in FIG. 10 can be calculated based on the positional relationship between the two.
  • the soil removal plate coordinate calculation unit 502 acquires the coordinate information (main body coordinate information) of the machine main body 10 acquired by the main body coordinate detection unit 53 and the main body angle detection unit 54. Based on the attitude information of the machine body 10 (main body attitude information) and the position information of the soil removal plate 41 (work member position information) acquired by the soil removal plate angle detection unit 55, the soil removal plate at the work site. The absolute coordinates of the left end portion 41L (specific part) of the soil removal plate 41 can be calculated and output.
  • the left end portion 41L of the earth removal plate is arranged in order at each ground reference point, and when the input unit 52 receives the arrangement information, the storage unit 505 calculates the earth removal plate left end portion 41L by the earth removal plate coordinate calculation unit 502.
  • the absolute coordinates of can be stored as the absolute coordinates of each ground reference point.
  • the input unit 52 receives depth information (distance information) with respect to the construction surface TS of each ground reference point.
  • the construction surface calculation unit 503 can calculate the equation of the construction surface TS in the absolute coordinate system of the work site from the absolute coordinates of each ground reference point and the distance information corresponding thereto.
  • the worker sets each ground reference point by using the chopsticks and water threads that have been conventionally provided at the work site, and arranges the left end portion 41L of the soil removal plate of the excavator 100 in order at the ground reference point.
  • the equation of the construction surface TS at the work site can be easily obtained by simply inputting the distance information from the ground reference point to the construction surface TS into the input unit 52, and the output unit 506 outputs the equation. Based on the information, the position of the construction surface TS can be easily recognized.
  • the construction surface calculation unit 503 calculates the absolute coordinates of the virtual reference points arranged below the ground reference points from the absolute coordinates of the ground reference points and the distance information, and the calculation is performed.
  • the equation of the construction surface TS is calculated based on the virtual reference point. According to such a configuration, the construction surface calculation unit 503 easily calculates the equation of the construction surface TS from the absolute coordinates of the virtual reference point virtually set in the ground based on the calculation method of the equation of a plane. be able to.
  • the construction surface calculation unit 503 calculates the absolute coordinates of the three virtual reference points (specific virtual reference points) arranged below the three ground reference points (specific ground reference points).
  • the equation of the plane passing through the three calculated virtual reference points is calculated as the equation of the construction surface TS. Therefore, the equation of the construction surface TS can be calculated easily and in a short time based on the three virtual reference points.
  • the construction surface calculation unit 503 calculates the absolute coordinates of the four virtual reference points (specific virtual reference points), and constructs the equation of the least squares plane based on the calculated four virtual reference points. It may be calculated as an equation of a plane TS. According to such a configuration, the equation of the construction surface TS can be calculated with higher accuracy based on the four virtual reference points.
  • the position information (equation of a plane) of the construction surface TS may be calculated and determined based on five or more ground reference points (virtual reference points).
  • the construction surface calculation unit is arranged below at least one confirmation ground reference point from the absolute coordinates of at least one confirmation ground reference point and at least one confirmation distance information. It is possible to calculate the absolute coordinates of at least one confirmation virtual reference point. Further, the determination unit 504 sets the equation of the construction surface TS within a predetermined allowable range based on the absolute coordinates of the calculated virtual reference point for confirmation and the equation of the construction surface TS calculated by the construction surface calculation unit 503. Determine if it is included in. According to such a configuration, the operator simply arranges the left end portion 41L of the soil removal plate of the excavator 100 at the ground reference point for confirmation and inputs the confirmation distance information to the input unit 52, and the determination unit 504 can perform the determination unit 504.
  • the accuracy of the equation of the construction surface TS can be determined based on the previously calculated equation of the construction surface TS and the absolute coordinates of the virtual reference point for confirmation. Therefore, it is possible to prevent mistakes in excavation and leveling work from occurring at the work site based on the equation of the construction surface TS calculated erroneously. In addition, the worker can start the on-site work after sufficiently confirming the accuracy of the calculated equation of the construction surface.
  • the main body angle detection unit 54 detects and outputs the lift angle, pitch angle, and yaw angle of the machine main body 10 with respect to the main body reference point on the cab 22 as posture information of the machine main body 10, respectively. Includes body angle sensor. Further, the main body coordinate detection unit 53 acquires the coordinate information of the machine main body 10 based on the global positioning satellite system. According to such a configuration, it is possible to detect the position information and the posture information of the machine body 10 even in an environment where there is a shield around the excavator 100.
  • the operator can easily recognize the position of the construction surface TS by the information displayed on the display unit 57, and the construction surface TS and the soil removal plate are generated by the information displayed on the display unit.
  • the work can be performed accurately while recognizing the relative positional relationship with 41.
  • the soil removal plate 41 of the dozer portion 40 of the excavator 100 is used as a reference for calculating the absolute coordinates of each ground reference point.
  • the operator can easily recognize the equation and the position information of the construction surface TS by operating the excavator 100 and arranging the soil removal plate 41 at each ground reference point.
  • the ground reference point (such as a chopstick) arranged at the work site can also be arranged at a lower position. Therefore, the height of the member arranged to set the ground reference point can be suppressed.
  • the soil removal plate angle detection unit 55 detects and outputs the lift angle around the lift rotation axis F1 of the soil removal plate 41 as the position information (work member position information) of the soil removal plate 41.
  • a soil removal plate angle sensor capable of According to such a configuration, the operator can easily arrange the soil removal plate 41 of the excavator 100 at each ground reference point by adjusting the lift angle of the soil removal plate 41 in addition to the running of the crawler unit 12. Can be done.
  • the above-mentioned soil removal plate angle sensor can further detect and output the tilt angle around the tilt rotation axis F3 of the soil removal plate 41 as the position information of the soil removal plate 41.
  • the soil removal plate angle sensor can detect the tilt angle of the soil removal plate 41, the operator can adjust the traveling and lift angles of the crawler unit 12 and the soil removal plate 41. By adjusting the tilt angle, the soil removal plate 41 of the excavator 100 can be easily arranged at the ground reference point. Since the soil removal plate angle sensor can detect and output the angle angle around the angle rotation axis F2 of the soil removal plate 41, the operator can tilt the soil removal plate 41 in the horizontal direction. Therefore, as shown in FIG. 11, it is also possible to arrange the soil removal plate 41 along the construction surface virtual thread FL which is inclined on the ground and perform the confirmation work of the construction surface TS.
  • the operator can recognize the position of the construction surface TS at the work site by the flow as described above. That is, the construction surface recognition method at the work site according to the present embodiment is the construction surface recognition method at the work site, and is movable relative to the machine body including the traveling portion capable of traveling on the ground and the machine body.
  • Each of the work machine having the work member supported by the machine body and capable of excavating the ground and the work assist device of the work machine according to any one of the above are prepared, and at least the traveling The specific parts of the work member are sequentially arranged at at least three ground reference points associated with the construction surface according to the traveling of the unit, and the specific part coordinate calculation unit calculates in accordance with each ground reference point.
  • At least three distance information is input to the distance information input unit, the absolute coordinates of the at least three ground reference points stored in the storage unit, and at least three input to the distance information input unit. From the two distance information, the equation of the construction surface in the absolute coordinate system of the work site is calculated, and the information about the equation of the construction surface calculated by the construction surface calculation unit is output, and the output information is output. Based on the above, the operator is made to recognize the position of the construction surface at the work site.
  • the worker sets each ground reference point by using the chopsticks and water threads that have been conventionally provided at the work site, and sets a specific part of the work machine as the ground reference point.
  • the equation of the construction surface at the work site can be easily obtained, and the construction surface information output unit can be used.
  • the position information of the construction surface can be easily recognized based on the output information.
  • the construction surface recognition method at the work site is a construction surface recognition method at the work site, and is movable relative to the machine body including the traveling portion capable of traveling on the ground and the machine body.
  • Each of the work machine having the work member supported by the machine body and capable of excavating the ground and the work assist device of the work machine according to any one of the above are prepared, and at least the traveling
  • the specific parts of the work member are sequentially arranged at at least three ground reference points associated with the construction surface according to the traveling of the unit, and the specific part coordinate calculation unit calculates in accordance with each ground reference point.
  • At least three distance information is input to the distance information input unit, the absolute coordinates of the at least three ground reference points stored in the storage unit, and at least three input to the distance information input unit. From the two distance information, the equation of the construction surface in the absolute coordinate system of the work site is calculated, and the information about the equation of the construction surface calculated by the construction surface calculation unit is output, and the output information is output.
  • the construction surface setting device 1 according to the present invention, the shovel 100 provided with the construction surface setting device 1, and the construction surface recognition method at the work site have been described above, but the present invention is not limited to this, and the following modifications are made. Is possible.
  • the left end 41L of the soil removal plate 41 is designated as a specific portion, but the specific portion may be the right end 41R of the soil removal plate 41 or the central portion of the soil removal plate 41. You may. Further, instead of the soil removal plate 41, the absolute coordinates of each reference point may be calculated based on a specific portion of the attachment 30 (for example, a part of the bucket at the tip).
  • the operator may directly input the coordinates from the input unit 52 with the GNSS mobile station 62 arranged at the position to be stored. .. In this case, the operator may press the storage instruction switch (not shown) arranged in the cab 22, and the coordinates of the GNSS mobile station 62 at that time may be transmitted to the control unit 50.
  • the place where the ground reference point is set is the top of the standing plate of the chopstick, the upper surface of the horizontal plate, the lower surface of the horizontal plate, the reference line drawn on the horizontal plate, and the drawing between the chopsticks.
  • the height from the construction surface TS (virtual reference point) is known at the work site, such as spilled water thread, and the operator adjusts the specific part of the soil removal plate 41 to the ground reference point.
  • the ground reference point be arranged at a position easily visible to the operator in the cab 22.
  • the ground reference point is not limited to the upper periphery of the construction surface TS, and may be arranged outside the construction area.
  • the same chopsticks as before are used. It is possible to calculate and determine the construction surface TS only by itself, and a huge amount of three-dimensional shape data indicating the topography of the work site is unnecessary.
  • the main body coordinate detection unit 53 has the GNSS reference station 61 and the GNSS mobile station 62, but the main body coordinate detection unit 53 uses the total station.
  • the main body coordinate information which is information on the absolute coordinates of the main body reference point provided in the machine main body 10 in advance at the work site, may be acquired.
  • a master unit equipped with a camera capable of measuring distance and angle is installed at the work site, while instead of the GNSS mobile station 62, a child including a prism photographed by the camera.
  • the machine is mounted on the excavator 100. According to such a configuration, the main body coordinate information can be detected with high accuracy, and the main body coordinate information can be detected even in a work site where the sky is shielded such as in a tunnel.
  • a relay point based on the origin G2, x2 axis, y2 axis, and z2 axis is set at the base end portion of the dozer portion 40, and the dozer portion 40 (soil removal plate 41) is set via the relay point.
  • the work member position information which is information on the relative position of the machine body 10 with respect to the machine body 10, may be acquired. Further, the GNSS mobile station 62 may be directly arranged at the base end portion of the dozer portion 40.
  • the work assist device of the work machine is capable of moving relative to the machine body including the traveling portion capable of traveling on the ground and the machine body. It is a work assist device of a work machine capable of assisting the work of forming a predetermined construction surface at a work site by using a work machine having a work member supported by the machine body and capable of excavating the ground.
  • the main body coordinate information acquisition unit capable of acquiring the main body coordinate information which is the information on the absolute coordinates of the main body reference point provided in the machine main body in advance at the work site, and the main body reference point as a reference.
  • the main body posture information acquisition unit that can acquire the main body posture information that is information about the posture of the machine main body and the working member position information that is information about the relative position of the working member with respect to the machine main body.
  • a specific part coordinate calculation unit capable of calculating and outputting the absolute coordinates of a specific part of the work member at the work site based on the work member position information, and at least three associated with the construction surface.
  • An arrangement information receiving unit capable of receiving arrangement information which is information indicating that the specific portion of the working member is arranged at least according to the traveling of the traveling unit at the ground reference point, and at least three grounds.
  • the absolute coordinates of the specific part calculated by the specific part coordinate calculation unit in response to the arrangement information receiving unit receiving the arrangement information at each of the reference points are set at the work site of the at least three ground reference points.
  • Distance information capable of accepting input of at least three distance information, which is information on the storage unit and the distance from each of the at least three ground reference points in the vertical direction to the construction surface, which are stored as absolute coordinates, respectively.
  • the absolute coordinates of the at least three ground reference points stored in the storage unit, and the at least three distance information input to the distance information input unit, in the absolute coordinate system of the work site includes a construction surface calculation unit that calculates the equation of the construction surface, and a construction surface information output unit that outputs information about the equation of the construction surface calculated by the construction surface calculation unit.
  • the construction surface calculation unit can calculate the equation of the construction surface in the absolute coordinate system of the work site from the absolute coordinates of each ground reference point and the corresponding distance information. Therefore, the worker sets each ground reference point, operates the work machine, arranges the specific part in order at the ground reference point, and inputs the distance information from the ground reference point to the construction surface to the distance information input unit.
  • the equation of the construction surface at the work site can be easily obtained only by inputting each, and the position of the construction surface can be easily recognized based on the information output by the construction surface information output unit.
  • the worker may set the ground reference point by using a chopstick or a water thread that has been conventionally provided at the work site.
  • the construction surface calculation unit is arranged below at least three ground reference points based on the absolute coordinates of the at least three ground reference points and the at least three distance information. It is desirable to calculate the absolute coordinates of the virtual reference point and calculate the equation of the construction surface based on the calculated at least three virtual reference points.
  • the construction surface calculation unit easily calculates the equation of the construction surface from the absolute coordinates of three or more virtual reference points virtually set in the ground based on the calculation method of the equation of a plane. be able to.
  • the at least three ground reference points include three specific ground reference points
  • the distance information input unit relates to the distance in the vertical direction from each of the three specific ground reference points to the construction surface.
  • the construction surface calculation unit uses the absolute coordinates of the three specific ground reference points and the three specific distance information to obtain the three specific ground reference points. It is desirable to calculate the absolute coordinates of the three specific virtual reference points arranged below, and to calculate the equation of a plane passing through the calculated three specific virtual reference points as the equation of the construction surface.
  • the equation of construction surface can be calculated easily and in a short time based on three specific virtual reference points.
  • the at least three ground reference points include at least four specific ground reference points
  • the distance information input unit is in the vertical direction from each of the at least four specific ground reference points to the construction surface.
  • the construction surface calculation unit Upon receiving input of at least four specific distance information, which is information on a distance, the construction surface calculation unit receives at least four of the absolute coordinates of the at least four specific ground reference points and the at least four specific distance information.
  • the absolute coordinates of at least four specific virtual reference points arranged below each specific ground reference point are calculated, and the equation of the minimum squared plane based on the calculated at least four specific virtual reference points is calculated as the equation of the construction surface. It may be calculated as.
  • the equation of the construction surface can be calculated with higher accuracy based on four or more specific virtual reference points.
  • the arrangement information receiving unit is a confirmation arrangement indicating that the specific portion is arranged at at least one confirmation ground reference point associated with the construction surface according to the traveling of the traveling unit. It is further possible to receive information, and the storage unit obtains at least one absolute coordinate of the specific part calculated by the specific part coordinate calculation unit in response to receiving the confirmation arrangement information. It is possible to store the confirmation ground reference point as the absolute coordinates at the work site, and the distance information input unit is information on the distance in the vertical direction from at least one confirmation ground reference point to the construction surface. , It is possible to accept input of at least one confirmation distance information, and the construction surface calculation unit is based on the absolute coordinates of the at least one confirmation ground reference point and the at least one confirmation distance information.
  • the operator simply places a specific part of the work machine at the ground reference point for confirmation and inputs the confirmation distance information to the distance information input unit, and the judgment unit is calculated in advance.
  • the accuracy of the equation of construction surface can be determined based on the equation of a plane and the absolute coordinates of the virtual reference point for confirmation. Therefore, the operator can start the on-site work after sufficiently confirming the accuracy of the calculated equation of the construction surface.
  • the main body posture information acquisition unit includes a main body angle sensor that detects and outputs the lift angle, pitch angle, and yaw angle of the machine main body with respect to the main body reference point as the main body posture information, respectively. Is desirable. Further, it is desirable that the main body coordinate information acquisition unit acquires the main body coordinate information based on the global positioning satellite system or the total station.
  • a display unit capable of displaying information related to the equation of the construction surface output from the construction surface information output unit.
  • the operator can easily recognize the position of the construction surface by the information displayed on the display unit.
  • the display unit can further display information on the relative position between the construction surface and the specific portion based on the absolute coordinates of the specific portion output from the specific portion coordinate calculation unit. Is desirable.
  • the operator can perform the work accurately while recognizing the relative positional relationship between the construction surface and the work member based on the information displayed on the display unit.
  • the work member of the work machine supports the soil removal plate and the soil removal plate, and is supported by the machine body so as to swing around the center axis of the lift rotation extending in the left-right direction. It has a soil plate support portion, and the specific part coordinate calculation unit can calculate and output the absolute coordinates of the specific part of the soil removal plate as a specific part of the work member at the work site. Is desirable.
  • the operator can easily recognize the position of the construction surface by operating the work machine and arranging the soil removal plate at each ground reference point.
  • the work member position information acquisition unit uses the soil removal plate angle sensor capable of detecting and outputting the lift angle around the lift rotation center axis of the soil removal plate as the work member position information. It is desirable to include it.
  • the work member position information acquisition unit has a soil removal plate angle sensor, the operator can remove the work machine by adjusting the lift angle of the soil removal plate in addition to the traveling of the traveling unit.
  • the soil plate can be easily placed at the ground reference point.
  • the soil removal plate of the working member is supported by the soil removal plate support portion so as to swing around the tilt rotation center axis extending in the left-right direction, and the soil removal plate angle sensor is supported by the soil removal plate angle sensor. It is desirable that the tilt angle around the tilt rotation center axis of the soil removal plate can be further detected and output as the work member position information.
  • the soil removal plate angle sensor can detect the tilt angle of the soil removal plate, the operator adjusts the tilt angle of the soil removal plate in addition to adjusting the traveling and lift angles of the traveling portion. As a result, the soil removal plate of the work machine can be easily placed at the ground reference point.
  • the construction surface recognition method at the work site is the construction surface recognition method at the work site, and is movable relative to the machine body including the traveling portion capable of traveling on the ground and the machine body.
  • Each of the work machine having the work member supported by the machine body and capable of excavating the ground and the work assist device of the work machine according to any one of the above are prepared, and at least the traveling
  • the specific parts of the work member are sequentially arranged at at least three ground reference points associated with the construction surface according to the traveling of the unit, and the specific part coordinate calculation unit calculates in accordance with each ground reference point.
  • At least three distance information is input to the distance information input unit, the absolute coordinates of the at least three ground reference points stored in the storage unit, and at least the at least three distance information input to the distance information input unit. From the three distance information, the equation of the construction surface in the absolute coordinate system of the work site is calculated, and the information regarding the calculated equation of the construction surface is output, and based on the output information, the said It is provided to make the operator recognize the position of the construction surface at the work site.
  • the worker sets each ground reference point, arranges specific parts of the work machine in order at the ground reference point, and inputs the distance information from the ground reference point to the construction surface to the distance information input unit.
  • the equation of the construction surface at the work site can be easily obtained only by inputting each, and the position information of the construction surface can be easily recognized based on the information output by the construction surface information output unit.
  • it is not necessary to receive information including a huge amount of data from the outside like 3D data at a work site or to store the information in a storage unit in advance, which can suppress the complexity and cost increase of the work assist device. it can.
  • the construction surface recognition method at the work site is the construction surface recognition method at the work site, and moves relative to the machine body including the traveling portion capable of traveling on the ground and the machine body.
  • Each of a work machine having a work member supported by the machine body and capable of excavating the ground and a work assist device of the work machine according to any one of the above can be prepared, and at least The specific parts of the work member are sequentially arranged at at least three ground reference points associated with the construction surface according to the running of the traveling unit, and the specific part coordinate calculation unit corresponds to each ground reference point.
  • At least three distance information is input to the distance information input unit, the absolute coordinates of the at least three ground reference points stored in the storage unit, and the distance information input unit are input to the absolute coordinates. From the at least three distance information, the equation of the construction surface in the absolute coordinate system of the work site is calculated, and the information regarding the calculated equation of the construction surface is output, and based on the output information.
  • the operator can confirm the accuracy of the equation of the construction surface from the relative positional relationship between the soil removal plate and the construction surface only by aligning the soil removal plate with the confirmation reference member.
  • the distance between the left and right ends of the soil removal plate and the construction surface is equal to each other within a predetermined error range, the soil removal plate is allowed to enter the ground as it is to stabilize excavation to the construction surface. It can be carried out.
  • a work assisting device and work of a work machine that enable a worker to easily recognize a construction surface without requiring reception of 3D data according to a work site from the outside or storage in advance.
  • a method of recognizing the construction surface at the site is provided.

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Optics & Photonics (AREA)
  • Acoustics & Sound (AREA)
  • Component Parts Of Construction Machinery (AREA)
  • Operation Control Of Excavators (AREA)

Abstract

作業現場に応じた3Dデータの外部からの受け取りや前もっての記憶を要することなく、作業者が施工面を容易に認識することを可能とする。作業補助装置(1)は、本体座標情報取得部(53)と、本体姿勢情報取得部(54)と、作業部材位置情報取得部(55)と、特定部位座標演算部(502)と、配置情報受付部および距離情報入力部(52)と、施工面演算部(503)と、記憶部(505)と、施工情報出力部(506)と、を有する。特定部位座標演算部(502)は、各取得部の取得情報から作業部材(41)の特定部位の絶対座標を演算することができる。施工面演算部(503)は、前記特定部位が順に配置される3つの地上基準点の絶対座標と、地上基準点と施工面(TS)との距離を示す3つの距離情報とから、作業現場の絶対座標系における施工面(TS)の方程式を演算し、決定する。

Description

作業機械の作業補助装置および作業現場における施工面認識方法
 本発明は、作業機械を用いた作業を補助することが可能な作業機械の作業補助装置および作業現場における施工面認識方法に関する。
 従来から、機械本体と前記機械本体に対して相対移動可能なように前記機械本体に支持された作業部材とを有する作業機械が知られている。前記作業部材は、たとえば掘削作業や均し作業を行うことが可能な排土板やバケットを含むアタッチメントなどである。
 特許文献1には、作業機械の作業者が、地中に仮想的に設定された目標作業面(施工面)の位置を容易に把握することを可能とする目標作業面設定装置(作業補助装置)が開示されている。当該目標作業面設定装置は、作業機械に備えられた作業機械側コンピュータと、作業現場から離れた事務所に配置される事務所側コンピュータとを備える。作業機械側コンピュータの設定スイッチがオンされると、平面図および断面図などを含む作業現場固有の3Dデータが事務所側コンピュータから送受信機を介して作業機械側コンピュータに送信される。作業機械側コンピュータは、受信した3Dデータをもとに目標作業面の位置情報を演算する。
 更に、作業機械側コンピュータは、作業機械に設けられたGPSアンテナ装置から受信する位置情報と、作業現場に設けられたGPS基準局から受信する補正情報とに基づいて、作業現場における作業機械の3次元位置情報を算出する。更に、作業機械側コンピュータは、演算された目標作業面の位置情報と作業機械の3次元位置情報とを比較することで、作業部材が目標作業面に到達できる範囲に作業機械が位置しているか否かを判定し、その判定結果を作業者に報知する。作業者は当該報知情報によって作業部材と目標作業面との相対的な位置関係を把握することができるため、作業現場での掘削作業や整地作業を効率的に行うことが可能となる。
特開2006-265954号公報
 特許文献1に記載された技術では、施工面(目標作業面)の設定のために、作業機械側コンピュータと事務所側コンピュータとの間での通信を可能とする通信機構が必要となるとともに、作業機械側コンピュータが、作業現場に応じた3Dデータを記憶するための大容量記憶部を有する必要がある。このため、作業機械の作業を補助するための作業補助装置の構成が複雑化するとともに、そのコストが増加するため、施工者によってはこのような作業補助装置の導入が難しいという問題があった。
 本発明の目的は、作業現場に応じた3Dデータの外部からの受け取りや前もっての記憶を要することなく、作業者が施工面を容易に認識することを可能とする作業機械の作業補助装置および作業現場における施工面認識方法を提供することである。
 上記の点を踏まえて導き出された、本発明の一の局面に係る作業機械の作業補助装置は、地上を走行可能な走行部を含む機械本体と前記機械本体に対して相対移動可能なように前記機械本体に支持され地面を掘削することが可能な作業部材とを有する作業機械を用いて作業現場において所定の施工面を形成する作業を補助することが可能な作業機械の作業補助装置である。当該作業補助装置は、予め前記機械本体に設けられた本体基準点の前記作業現場における絶対座標に関する情報である本体座標情報を取得することが可能な本体座標情報取得部と、前記本体基準点を基準とする前記機械本体の姿勢に関する情報である本体姿勢情報を取得することが可能な本体姿勢情報取得部と、前記作業部材の前記機械本体に対する相対位置に関する情報である作業部材位置情報を取得することが可能な作業部材位置情報取得部と、前記本体座標情報取得部によって取得された前記本体座標情報と、前記本体姿勢情報取得部によって取得された前記本体姿勢情報と、前記作業部材位置情報取得部によって取得された前記作業部材位置情報とに基づいて、前記作業現場における前記作業部材の特定部位の絶対座標を演算および出力することが可能な特定部位座標演算部と、前記施工面に関連付けられた少なくとも3つの地上基準点に少なくとも前記走行部の走行に応じて前記作業部材の前記特定部位が配置されたことを示す情報である配置情報をそれぞれ受け付けることが可能な配置情報受付部と、前記少なくとも3つの地上基準点のそれぞれにおいて前記配置情報受付部が前記配置情報を受け付けることに対応して前記特定部位座標演算部が演算する前記特定部位の絶対座標を、前記少なくとも3つの地上基準点の前記作業現場における絶対座標としてそれぞれ記憶する、記憶部と、前記少なくとも3つの地上基準点のそれぞれから前記施工面までの上下方向における距離に関する情報である、少なくとも3つの距離情報の入力を受け付けることが可能な距離情報入力部と、前記記憶部に記憶された前記少なくとも3つの地上基準点の前記絶対座標と、前記距離情報入力部に入力された前記少なくとも3つの距離情報とから、前記作業現場の絶対座標系における前記施工面の方程式を演算する施工面演算部と、前記施工面演算部によって演算された前記施工面の方程式に関する情報を出力する施工面情報出力部と、を備える。
 本発明の他の局面に係る作業現場における施工面認識方法は、地上を走行可能な走行部を含む機械本体と前記機械本体に対して相対移動可能なように前記機械本体に支持され地面を掘削することが可能な作業部材とを有する作業機械と、上記の作業機械の作業補助装置とをそれぞれ準備することと、少なくとも前記走行部の走行に応じて、前記施工面に関連付けられた前記少なくとも3つの地上基準点に前記作業部材の前記特定部位を順に配置し、各地上基準点に対応して前記特定部位座標演算部が演算する前記特定部位の絶対座標を、各地上基準点の絶対座標として前記記憶部にそれぞれ記憶することと、前記少なくとも3つの地上基準点のそれぞれから前記施工面までの上下方向における距離に関する情報である、少なくとも3つの距離情報を前記距離情報入力部にそれぞれ入力することと、前記記憶部に記憶された前記少なくとも3つの地上基準点の前記絶対座標と、前記距離情報入力部に入力された前記少なくとも3つの距離情報とから、前記作業現場の絶対座標系における前記施工面の方程式を演算することと、前記演算した前記施工面の方程式に関する情報を出力し、当該出力された情報に基づいて、前記作業現場における前記施工面の位置を作業者に認識させることと、を備える。
 また、本発明の他の局面に係る作業現場における施工面認識方法は、地上を走行可能な走行部を含む機械本体と前記機械本体に対して相対移動可能なように前記機械本体に支持され地面を掘削することが可能な作業部材とを有する作業機械と、上記の作業機械の作業補助装置とをそれぞれ準備することと、少なくとも前記走行部の走行に応じて、前記施工面に関連付けられた前記少なくとも3つの地上基準点に前記作業部材の前記特定部位を順に配置し、各地上基準点に対応して前記特定部位座標演算部が演算する前記特定部位の絶対座標を、各地上基準点の絶対座標として前記記憶部にそれぞれ記憶することと、前記少なくとも3つの地上基準点のそれぞれから前記施工面までの上下方向における距離に関する情報である、少なくとも3つの距離情報を前記距離情報入力部にそれぞれ入力することと、前記記憶部に記憶された前記少なくとも3つの地上基準点の前記絶対座標と、前記距離情報入力部に入力された前記少なくとも3つの距離情報とから、前記作業現場の絶対座標系における前記施工面の方程式を演算することと、前記演算した前記施工面の方程式に関する情報を出力し、当該出力された情報に基づいて、作業者に前記作業現場における前記施工面の位置を認識させることと、前記施工面と平行かつ平面視で前記作業機械の前記走行部の走行方向と直交する直線部分を含む確認用基準部材を前記作業現場に配設することと、前記作業機械を操作し、前記排土板のうち左右方向に延びる下端部を前記確認用基準部材の前記直線部分に揃えることと、前記排土板の前記下端部の左右両端部と前記施工面との距離を互いに比較することで、前記演算された施工面の方程式が所定の許容範囲に含まれているか否かを確認することと、を備える。
本発明の一実施形態に係る作業補助装置を含む作業機械の構造を説明するための模式的な側断面図である。 本発明の一実施形態に係る作業補助装置を含む作業機械のブロック図である。 本発明の一実施形態に係る作業補助装置および作業機械の座標情報を説明するための側面図である。 本発明の一実施形態に係る作業補助装置および作業機械の座標情報を説明するための平面図である。 本発明の一実施形態に係る作業補助装置における施工面設定処理のフローチャートである。 本発明の一実施形態に係る作業補助装置における施工面設定処理の一部を示すフローチャートである。 本発明の一実施形態に係る作業補助装置における施工面設定処理の一部を示すフローチャートである。 本発明の一実施形態に係る作業補助装置を含む作業機械の作業現場の斜視図である。 本発明の一実施形態に係る作業補助装置によって施工面が演算される様子を説明するための模式図である。 本発明の一実施形態に係る作業補助装置を含む作業機械の作業現場の側断面図である。 本発明の一実施形態に係る作業補助装置を含む作業機械の作業現場の斜視図である。
 以下、添付図面を参照しながら、本発明の一実施形態について詳述する。図1は、本実施形態に係る施工面設定装置1(作業補助装置)(図2)を含むショベル100(作業機械)の構造を説明するための模式的な側断面図である。図2は、本実施形態に係る施工面設定装置1を含むショベル100のブロック図である。図3は、本実施形態に係る施工面設定装置1およびショベル100の座標情報を説明するための側面図であり、図4は、同平面図である。
 本実施形態では、作業機械の一例として、油圧式のショベル100に施工面設定装置1が設けられている。ショベル100は、機械本体10と、アタッチメント30と、ドーザ部40と、を備える。機械本体10は、下部本体11と、上部旋回体20と、を有する。下部本体11の左右両側には、地上を走行可能なクローラユニット12(走行部)が配設されている。上部旋回体20は、下部本体11に上下方向に延びる旋回中心軸周りに旋回可能に支持された旋回フレーム21と、作業者が搭乗することを許容するキャブ22と、キャブ22の後方に配置されたエンジンルーム23と、エンジン24と、第1油圧ポンプ25と、第2油圧ポンプ26と、支持部27と、を有する。
 エンジン24はエンジンルーム23に配置される。第1油圧ポンプ25および第2油圧ポンプ26は、エンジン24によって駆動され、アタッチメント30およびドーザ部40を駆動するための不図示の油圧回路に作動油をそれぞれ吐出する。支持部27は、旋回フレーム21上であってキャブ22の右方(図1の紙面奥側)に配置され、アタッチメント30を起伏可能に支持する。アタッチメント30は、それぞれ揺動可能な不図示のブーム、アームおよびバケットを含み、所定の掘削作業などを行う。
 ドーザ部40(作業部材)は、下部本体11の前側部分に配置される。ドーザ部40は、機械本体10に対して相対移動可能なように機械本体10に支持され地面を掘削することが可能とされている。ドーザ部40は、排土板41と当該排土板を41支持する支持フレーム42(排土板支持部)と、を有する。更に、ショベル100は、リフトシリンダ43と、左右一対のアングルシリンダ44と、チルトシリンダ45と、を有する。支持フレーム42は、左右方向に延びるリフト回転中心軸F1回りに揺動可能なように機械本体10の下部本体11に支持されており、リフトシリンダ43が第2油圧ポンプ26から受ける作動油の給排に応じて伸縮することで、支持フレーム42がリフト回転軸F1周りに揺動する。この結果、排土板41が、図1のリフト方向D1に揺動し、排土板41(ドーザ部40)のリフト角が変化する。また、左右一対のアングルシリンダ44が、第2油圧ポンプ26から受ける作動油の給排に応じてそれぞれ伸長および収縮することで、排土板41がアングル回転軸F2周りに揺動する。この結果、排土板41が、図1のアングル方向D2に揺動し、排土板41(ドーザ部40)のアングル角が変化する。また、排土板41は、左右方向に延びるチルト回転軸F3回りに揺動可能なように支持フレーム42の先端部に支持されている。そして、チルトシリンダ45が第2油圧ポンプ26から受ける作動油の給排に応じて伸縮することで、排土板41がチルト回転軸F3周りに図1のチルト方向D3に揺動し、排土板41(ドーザ部40)のチルト角が変化する。
 図2に示すように、ショベル100に設けられた施工面設定装置1(作業機械の作業補助装置)は、制御部50と、操作部51と、入力部52と、本体座標検出部53と、本体角度検出部54と、排土板角度検出部55と、駆動部56と、表示部57と、報知部58と、を有する。施工面設定装置1は、作業現場において所定の施工面TS(図8、図10参照)を形成する作業を補助することが可能とされている。
 操作部51は、キャブ22内に配置され、作業者によってクローラユニット12の走行動作、上部旋回体20の旋回動作、アタッチメント30およびドーザ部40の駆動に関する操作指令を受け付ける。
 入力部52(配置情報受付部、距離情報入力部)は、キャブ22内に配置され、作業者によって各種の情報の入力を受け付ける。特に、本実施形態では、作業現場の施工面TSに関連付けられた少なくとも3つの地上基準点であって地上において排土板41の特定部位が順に配置されることが可能なように施工面TSの上方に配置された少なくとも3つの地上基準点に、少なくともクローラユニット12の走行に応じて排土板41の前記特定部位が配置されたことを示す情報である配置情報を入力部52が順に受け付けることが可能とされている。更に、入力部52は、前記少なくとも3つの地上基準点のそれぞれから前記施工面TSまでの上下方向における距離に関する情報である、少なくとも3つの距離情報の入力をそれぞれ受け付けることが可能とされている。
 本体座標検出部53(本体座標情報取得部)は、予め機械本体10に設けられた本体基準点の作業現場における絶対座標に関する情報である本体座標情報を取得することが可能である。本体座標検出部53は、GNSS(Global Navigation Satellite System/全球測位衛星システム)基準局61と、GNSS移動局62と、を有する。また、上記の本体基準点は、キャブ22の上面部に配置されている。GNSS基準局61は、作業現場に配置された、または、作業現場に最も近い位置に配置された基準局であり、図3のように原点G0を基準としてx0軸、y0軸、z0軸の3軸で前記絶対座標を決定する。GNSS移動局62は、上記の本体基準点に対応してキャブ22の上面部に配置されている。なお、GNSSとして、公知のGPS(Global Positioning System)に加え、GLONASS(Global Navigation Satellite System)、Galileo、準天頂衛星(QZSS:Quasi-Zenith Satellite System)等の衛星測位システムが採用されてもよい。
 本体角度検出部54(本体姿勢情報取得部)は、前記本体基準点を基準とする機械本体10の姿勢に関する情報である本体姿勢情報を取得することが可能である。本実施形態では、本体角度検出部54は、前記本体基準点に対応してキャブ22の上面部に配置された角度センサ(本体角度センサ)である。本体角度検出部54は、図3、図4において移動局原点G1を基準としてx1軸、y1軸、z1軸回りの回転をそれぞれ検知するものであり、公知のIMU(Inertial Measurement Unit:慣性計測装置)が用いられている。すなわち、本体角度検出部54は、前記本体基準点を基準とする機械本体10のリフト角、ピッチ角およびヨー角を前記本体姿勢情報としてそれぞれ検出および出力する。
 排土板角度検出部55(作業部材位置情報取得部)は、ドーザ部40(排土板41)の機械本体10に対する相対位置に関する情報である作業部材位置情報を取得することが可能である。本実施形態では、排土板角度検出部55は、排土板41に配置された角度センサ(排土板角度センサ)である。排土板角度検出部55は、図3、図4において排土板原点G3を基準としてx3軸、y3軸、z3軸回りの回転をそれぞれ検知するものであり、本実施形態では本体角度検出部54と同様にIMUが用いられている。すなわち、排土板角度検出部55は、前記作業部材位置情報として、排土板41の前記リフト角、アングル角およびチルト角をそれぞれ検出および出力する。
 駆動部56は、前述のエンジン24、第1油圧ポンプ25および第2油圧ポンプ26を含み、その他の油圧回路、ギヤなどの駆動伝達機構を更に有している。駆動部56は、制御部50の駆動制御部501からの制御信号を受けて、クローラユニット12、旋回フレーム21、アタッチメント30およびドーザ部40を駆動する。
 表示部57は、キャブ22内に配置され、ショベル100の動作に関する各種の情報を表示する。特に、表示部57は、後記の出力部506から出力された施工面TSの方程式に基づく施工面TSの位置情報(施工面TSに関する情報)を表示することが可能とされている。また、表示部57は、排土板座標演算部502から出力された前記特定部位の絶対座標に基づいて、前記施工面TSと前記特定部位との相対位置に関する情報を更に表示することが可能である。
 報知部58は、キャブ22内またはショベル100の外部に配置され、作業者に対して各種の情報を報知する。一例として、報知部58は、スピーカ、ブザー、ライトなどからなる。
 制御部50は、CPU(Central Processing Unit)、制御プログラムを記憶するROM(Read Only Memory)、CPUの作業領域として使用されるRAM(Random Access Memory)等から構成されている。また、制御部50には、操作部51、入力部52、本体座標検出部53、本体角度検出部54、排土板角度検出部55、駆動部56、表示部57および報知部58などが接続されている。制御部50は、前記CPUがROMに記憶された制御プログラムを実行することにより、駆動制御部501、排土板座標演算部502、施工面演算部503、判定部504、記憶部505、出力部506を備えるように機能する。
 駆動制御部501は、操作部51に入力される指令信号に応じてクローラユニット12、旋回フレーム21、アタッチメント30およびドーザ部40を駆動するように駆動部56を制御する。
 排土板座標演算部502(特定部位座標演算部)は、作業現場における排土板41の特定部位の絶対座標を演算する。詳しくは、排土板座標演算部502は、本体座標検出部53によって取得された前記本体座標情報と、本体角度検出部54によって取得された前記本体姿勢情報と、排土板角度検出部55によって取得された前記作業部材位置情報とに基づいて、作業現場における排土板41の特定部位の絶対座標を演算および出力することが可能とされている。
 施工面演算部503は、記憶部505に記憶された前記少なくとも3つの地上基準点の前記絶対座標と、入力部52に入力された前記少なくとも3つの距離情報とから、作業現場の絶対座標系における施工面TSの方程式を演算する。より詳しくは、施工面演算部503は、前記少なくとも3つの地上基準点の絶対座標と前記少なくとも3つの距離情報とから、前記少なくとも3つの地上基準点の下方にそれぞれ配置される少なくとも3つの仮想基準点の絶対座標を演算し、当該演算された少なくとも3つの仮想基準点に基づいて前記施工面TSの方程式を演算する。当該施工面TSの演算方法については後記で詳述する。
 判定部504は、施工面TSの設定処理のフローにおいて、各種の判定動作を実行する。また、判定部504は、施工面演算部503によって演算、決定された施工面TSの方程式の確認作業時に、所定の判定処理を実施する。
 記憶部505は、施工面TSの設定処理のフローにおいて参照される各種の情報を記憶する。また、記憶部505は、あらかじめ各種の閾値情報などを記憶している。更に、記憶部505は、前記少なくとも3つの地上基準点において入力部52が前記配置情報を受け付けることにそれぞれ対応して排土板座標演算部502が演算する前記特定部位の絶対座標を、前記少なくとも3つの地上基準点の作業現場における絶対座標としてそれぞれ記憶する。
 出力部506(施工面情報出力部)は、施工面演算部503によって演算、決定された施工面TSの方程式に関する情報を出力する。
 図5は、本実施形態に係る施工面設定装置1における施工面設定処理のフローチャートである。図6および図7は、図5の施工面設定処理の一部を示すフローチャートである。図8は、本実施形態に係る施工面設定装置1を含むショベル100の作業現場の斜視図である。図9は、本実施形態に係る施工面設定装置1によって施工面TSが演算される様子を説明するための模式図である。
 図4に示すように、ショベル100の排土板41は、左右方向に延びる下端部41Sを有する。また、排土板41の下端部41Sの左右両端部がそれぞれ排土板左端部41Lおよび排土板右端部41Rと定義される。本実施形態では、作業現場の絶対座標系における施工面TSの位置情報(平面の方程式)を取得するために、排土板41の排土板左端部41Lが特定部位として機能する。
 図8に示すように、作業現場の一例として、地面GLには3つの丁張りが設けられている。すなわち、地面GLに挿入された第1立板J1に第1横板K1が固定され、同様に、第2立板J2に第2横板K2が固定され、第3立板J3に第3横板K3が固定されている。第1立板J1、第2立板J2および第3立板J3は鉛直方向に延びるように配設され、第1横板K1、第2横板K2および第3横板K3は水平に延びるように配設されている。
 各横板の上面部には、掘削、整地作業によって形成される予定の施工面TSに対応した第1基準点P1、第2基準点P2および第3基準点P3(すべて地上基準点)が予め設定されている。また、第1基準点P1、第2基準点P2および第3基準点P3から施工面TSまでの上下方向における距離である、第1深さL1、第2深さL2および第3深さL3(いずれも距離情報)は作業現場においてあらかじめ既知の値とされている。これらの距離は、たとえば第1横板K1、第2横板K2および第3横板K3の側面にそれぞれ表記されている。なお、第1基準点P1、第2基準点P2および第3基準点P3から、それぞれ第1深さL1、第2深さL2および第3横板K3だけ下方に位置する点が、それぞれ、第1仮想点Q1、第2仮想点Q2および第3仮想点Q3(いずれも仮想基準点)と定義される。なお、第1基準点P1、第2基準点P2および第3基準点P3は一直線上に配置されないことが前提とされる。
 図5に示すように、作業現場において作業者が施工面TSの設定処理フローを開始すると、まず、施工面演算ステップが行われる(図5のステップS1)。なお、当該ステップS1については、後記で詳述する。施工面の演算ステップが終了すると、制御部50の判定部504が施工面演算完了フラグを確認する(ステップS02)。当該施工面演算完了フラグは、ステップS01の施工面演算ステップが完了したか否かを判定するためのフラグであり、ONおよびOFFの間で切り換え可能とされ、記憶部505に記憶、更新される。判定部504は、ステップS02において施工面演算完了フラグがONの場合(ステップS02でYES)、ステップS03に進む。一方、ステップS02において施工面演算完了フラグがOFFの場合(ステップS02でNO)、ステップS01に戻る。ステップS03では、判定部504が補正モードスイッチを確認する。当該スイッチは、キャブ22内に設けられており、ステップS01において演算された施工面TSの方程式を所定の補正フローによって補正するか否かを決定するために設けられており、作業者が必要に応じてON/OFFを切換える。ステップS03において補正モードスイッチがONである場合、施工面演算部503によって施工面TSの補正演算が実行される。なお、当該補正演算についても後記で詳述する。ステップS03において補正モードスイッチがOFFの場合、または、ステップS04において補正演算が完了した場合、判定部504はMC開始スイッチがONか否かを確認する(ステップS05)。当該スイッチは、自動MC(マシンコントロール)、すなわち施工面TSの施工をショベル100が自動で行うか否かを決定するためのスイッチでありキャブ22内に設けられている。MC開始スイッチがONの場合(ステップS05でYES)、演算された施工面TSに基づいて自動MCが実行される(ステップS06)。一方、MC開始スイッチがOFFの場合(ステップS05でNO)、作業者は自ら施工面TSの施工を実施する意思を持っていると判断され、ステップS01に処理フローは戻るとともに、先のステップS01において演算、決定された施工面TSの方程式、位置情報などが表示部57に表示される。作業者は当該表示情報を確認することで、施工面TSの位置を認識しながら自ら作業を行うことができる。
 図6を参照して、図5のステップS01の施工面演算ステップについて更に詳述する。施工面演算ステップS01が開始されると、排土板座標演算部502が刃先座標演算(ステップS11)を実行する。ここでは、排土板座標演算部502が、本体座標検出部53(GNSS基準局61、GNSS移動局62)、本体角度検出部54および排土板角度検出部55の検出結果から、刃先すなわち排土板41の排土板左端部41Lの作業現場における絶対座標(グローバル座標)を演算する。なお、当該演算は、施工面演算ステップS01が実行されている間、所定の時間刻み(たとえば1秒)間隔で、ほぼリアルタイムで実行される。この際、排土板座標演算部502は、既知となっているGNSS基準局61の座標とGNSSからGNSS移動局62の座標ベクトルを取得する。更に、GNSS移動局62(移動局原点G1)からドーザ部40の支持フレーム42の基端部に位置するフレーム原点G2および排土板41の排土板原点G3までのベクトルを、機械本体10の緒言長さと各角度センサによって検出される回転角とから演算する。この結果、排土板座標演算部502は、排土板41の排土板左端部41Lの絶対座標を演算することができるため、以後の基準点入力時の各基準点の座標を取得することが可能となる。
 排土板座標演算部502によって排土板41の排土板左端部41Lの絶対座標が演算可能になると、基準情報の受付ステップが開始される(図6のステップS12)。図7を参照して、当該ステップが開始されると、表示部57に基準点数Nの入力要求が表示され、作業者が入力部52を通じて基準点数Nの値を入力する(ステップS21)。当該基準点数Nとは、地上に設定された基準点(地上基準点)の数に相当する。図8では、第1基準点P1、第2基準点P2および第3基準点P3が準備されているため、N=3が入力される。
 次に、表示部57に第1基準点P1(n=1)の設定指示要求が表示される。そこで、作業者は、ショベル100のクローラユニット12およびドーザ部40を操作することによって、排土板41の排土板左端部41Lを図8の第1基準点P1に一致するように配置する。すなわち、排土板41の排土板左端部41L(刃先)が第1基準点P1(n=1)に移動する。ここで、作業者は、入力部52に設けられた不図示の設定指示スイッチを押圧する。この結果、第1基準点P1の絶対座標を記憶するための設定指示が入力部52によって受け付けられ(ステップS22)、第1基準点P1の座標が記憶部505に記憶される。この際、排土板座標演算部502が演算する排土板左端部41Lの絶対座標が、第1基準点P1の絶対座標として記憶部505に記憶される(ステップS23)。次に、表示部57に第1仮想点Q1(n=1)の深さ情報(距離情報)の入力要求が表示される。そこで、作業者は、第1基準点P1近傍のたとえば第1横板K1に表示される第1深さL1を確認し、入力部52から第1深さL1の値を入力する(ステップS24)。この結果、第1仮想点Q1の深さ情報(第1深さL1)が記憶部505に記憶される(ステップS25)。次に、判定部504は、現在のn(=1)とステップS21で受け付けた基準点数Nとの一致性を確認する(ステップS26)。ステップS26において、n<N、すなわちn≠Nの場合(ステップS26でNO)、現在のnに1が追加され(ステップS27)、ステップS22以降のステップが繰り返される。
 すなわち、表示部57には第2基準点P2(n=2)の設定指示要求が表示される。そこで、作業者は、ショベル100のクローラユニット12およびドーザ部40を操作することによって、排土板41の排土板左端部41Lを図8の第2基準点P2に一致するように配置する。すなわち、排土板41の排土板左端部41L(刃先)が第2基準点P2(n=2)に移動する。以下の流れは、n=1の場合と同様である。
 やがて、n=3の場合に、ステップS26においてn=Nが成立すると(ステップS26でYES)、図6のステップS13に進む。上記のような流れによって、第1基準点P1、第2基準点P2および第3基準点P3の作業現場における絶対座標と、第1深さL1、第2深さL2および第3深さL3の値が、それぞれ記憶部505に記憶される。
 図6のステップS13では、判定部504が、記憶部505に上記のような各基準点の絶対座標および深さ情報が格納されているかを判定する。ここで、N組の基準点の絶対座標および深さ情報がそれぞれ格納されている場合(ステップS13でYES)、施工面演算部503が目標となる施工面の位置(平面の方程式)を演算する(ステップS14)。なお、ステップS13においてN組の基準点の絶対座標および深さ情報が格納されていない場合(ステップS13でNO)、施工面演算部503は記憶部505に記憶されている施工面演算完了フラグをOFFに更新し、ステップS11以下を繰り返す。
 ステップS14において、施工面演算部503は、第1基準点P1、第2基準点P2および第3基準点P3(3つの特定地上基準点)の絶対座標と、第1深さL1、第2深さL2および第3深さL3(3つの特定距離情報)とから、3つの特定地上基準点の下方にそれぞれ配置される第1仮想点Q1、第2仮想点Q2および第3仮想点Q3(3つの特定仮想基準点)の絶対座標を演算する。この際、各基準点の絶対座標のZ座標から、対応する深さ情報を減算することで、対応する仮想点の絶対座標が演算される。そして、施工面演算部503は、当該演算された3つの特定仮想基準点を通る平面の方程式を施工面TSの方程式として演算する。
 図6のステップS14において施工面演算部503が、第1仮想点Q1、第2仮想点Q2および第3仮想点Q3に基づいて、施工面TSの方程式を演算する過程を図9を参照して説明する。なお、N=3の場合、施工面TSの方程式は、第1仮想点Q1、第2仮想点Q2および第3仮想点Q3のすべてを通る平面の方程式に相当する。
 図9に示すように、Q1、Q2およびQ3を通る施工面TSを想定すると、ベクトルQ1・Q2およびベクトルQ1・Q3という2つのベクトルの外積をとることで、当該2つのベクトルにそれぞれ直交する法線ベクトル(α、β、γ)が得られる。ここで、施工面TSの方程式をAX+BY+CZ+D=0とすると、上記のα、β、γは、それぞれA、B、Cに相当する。したがって、α、β、γを施工面TSの方程式のA、B、Cにそれぞれ代入するとともに、Q1、Q2およびQ3のうちの一の座標をX、Y、Zに代入すると、係数Dを得ることができる。この結果、A、B、CおよびDが既知となり、施工面TSの方程式を得ることができる。なお、施工面TSの方程式の演算は上記に限定されるものではなく、連立方程式による解法などその他の公知の解法を用いることができる。
 図6のステップS14において、施工面演算部503が施工面TSの方程式を演算、決定すると、排土板座標演算部502は、現在の排土板41の排土板左端部41Lの絶対座標を演算する(ステップS15)。換言すれば、排土板座標演算部502は、施工面TSに対する排土板左端部41L(刃先)の相対位置を演算する。そして、施工面演算部503は、記憶部505の施工面演算完了フラグをONに更新する(ステップS16)。その後、図5のステップS02に進み、前述のようにステップS03~S06が実行される。
 次に、図5のステップS04において実行される補正演算処理について説明する。作業者は、ステップS01において演算された施工面TSの位置情報(平面の方程式)が正しいか否かを、換言すれば演算された施工面TSが所定の誤差範囲に含まれているかを確認することができる。一例として、図8に示されるような丁張が、確認用として更にもう1つ作業現場に設定されていると仮定する。この場合、確認用の丁張の横板には、施工面TSに関連付けられた4つ目の基準点(確認用地上基準点)が設けられており、当該4つ目の基準点から施工面TSまでの深さ情報(上下方向における距離)は既知の値として、前記横板に表記されている。
 ここで、図7と同様のフローによって、確認用地上基準点の絶対座標と、深さ情報(距離情報)とが記憶部505にそれぞれ記憶される。そして、施工面演算部503は、これらの情報から、確認用地上基準点の下方に配置される確認用仮想基準点の絶対座標を演算する。そして、判定部504は、前記演算された確認用仮想基準点の絶対座標と、ステップS01において施工面演算部503によって演算された前記施工面TSの方程式とに基づいて、施工面TSの方程式が所定の許容範囲内に含まれているか否かを判定する。この際、判定部504は、確認用仮想基準点と施工面TSとの距離が予め設定された閾値よりも小さい場合には施工面TSの方程式が所定の許容範囲内に含まれていると判定し、確認用仮想基準点と施工面TSとの距離が予め設定された前記閾値よりも大きい場合には施工面TSの方程式が所定の許容範囲内に含まれていないと判定する。後者の場合、出力部506が施工面TSの方程式に異常があることを示す報知情報を表示部57や報知部58を用いて作業者に報知してもよい。なお、確認用仮想基準点の座標が(XP、YP、ZP)とすると、施工面TSと確認用仮想基準点との距離ΔLは、ΔL=(A×XP+B×YP+C×ZP+D)/√(A+B+C)で算出される。
 なお、施工面TSの方程式が所定の許容範囲内に含まれていると判定されると、施工面TSの方程式の補正は不要であるため、図5のステップS04からステップS05に進めばよい。一方、施工面TSの方程式が所定の許容範囲内に含まれていないと判定されると、施工面TSの方程式が所定の演算によって補正される。一例として、ここでは、第1仮想点Q1、第2仮想点Q2、第3仮想点Q3に、上記の確認用仮想基準点を加えた4つの仮想点に基づいて、施工面TSの方程式が再度演算される。ここで、施工面演算部503は、4つの仮想点の絶対座標に基づいて公知の平均二乗平面を求め、補正後の施工面TSとする。
 上記の平均二乗平面の算出方法としては、一例として以下のような方法をあげることができる。すなわち、4つの仮想点のそれぞれから施工面TSまでの距離の2乗和が最小になるように施工面TSの方程式を演算する。前述のように施工面TSを示す方程式におけるX、Y、Zの係数がそれぞれA、B、Cと仮定すると、4つの仮想点のそれぞれからの距離の2乗和が最小になるようにこれらA、B、Cのパラメータ値を計算する。ここで、4つの仮想点のそれぞれからの距離Liの2乗和をFと定義すると、F=Σ(Li)で表される。そして、当該Fの両辺を偏微分すると3次元連立方程式が導出され、A、B、Cを求めることができる。なお、A、B、Cのそれぞれを単位ベクトルとするためには、A+B+C=1を前提条件とすればよい。上記の方程式の解法には、公知の行列によるLU分解、ラグランジェの未定定数法などを採用することができる。
 なお、上記の4点の仮想点に基づく施工面TSの方程式の決定方法は、補正演算ステップに限定されるものではなく、ステップS01の施工面演算ステップにおいて採用されてもよい。すなわち、ステップS01では、3つの地上基準点および距離情報に基づいて、施工面TSが演算、決定されるものに限定されるものではなく、4つ以上の地上基準点および距離情報に基づいて施工面TSが演算、決定されるものでもよい。この場合、基準点を増加させることで刃先セット時の微妙な設定ミスを打ち消すことが可能となる。
 また、本実施形態では、施工面TSが演算、決定されたのち、作業者がショベル100の排土板41によって地面を掘削する前に、施工面TSと排土板41との位置関係を確認することができる。図10は、本実施形態に係る施工面設定装置1を含むショベル100の作業現場の側断面図である。図11は、本実施形態に係る施工面設定装置1を含むショベル100の作業現場の斜視図である。
 図10に示すように、一例として、作業現場においてショベル100の進行方向後端側(手前側)に、確認用の丁張が配設される。当該丁張は、前後方向に間隔をおいて鉛直方向に配置された第4立板J4および第5立板J5と、当該2つの立板に跨るように配設される第4横板K4および斜板K5と、を有する。第4横板K4は水平に配設されており、斜板K5は施工面TSの後端部に向かって傾斜するように配設されている。なお、第4横板K4から施工面TSまでの上下方向における距離である第4深さL4は既知であり、たとえば第4横板K4の側面に表記される。このような丁張は従来から作業現場に配設されているものである。作業者や斜板K5の傾斜を目安として施工面TSへの掘削作業を実施する。なお、前述のように、本発明が適用されていない従来の作業現場では、作業者は施工面TSの位置を認識していない。
 更に、本実施形態では、図11に示すように、作業現場において施工面TSを囲むように配設された複数の立板J間に複数の施工面仮想糸FL(確認用基準部材)が配設される。当該施工面仮想糸FLは、従来の水平に配設される水糸と異なり、施工面TSと平行に配設されており、施工面TSとの距離は既知の第5深さL5に設定されている。また、図11に示される施工面仮想糸FLのうち後端側に配設された施工面仮想糸FLは、平面視でショベル100の進行方向DSと直交するように配設されている。なお、図10に示される丁張は、図11において作業現場の右側の後端部に位置する丁張に相当する。
 前述のフローに基づいて予め施工面TSが演算、決定された状態で、作業者は、ショベル100を操作し、図11に示すように進行方向DSの手前側において施工面仮想糸FLに排土板41の下端部41Sを一致させる。すなわち、排土板41の排土板左端部41Lおよび排土板右端部41Rが施工面仮想糸FL上に配置される。この状態で、作業者がキャブ22内に配置された不図示の施工面TS確認用スイッチを押圧すると、判定部504は排土板41の排土板左端部41Lおよび排土板右端部41Rと施工面TSとのそれぞれの距離を演算するとともに、当該演算された距離同士の大小関係を比較する。そして、両者の差が予め設定された閾値以下の場合には、先のフローにおいて演算された施工面TSと排土板41との位置関係が正しく設定されており、図11に示される状態から作業者がショベル100を操作し、排土板41を地中に進入させることで、施工面TSに向かって掘削作業を正確に行うことができる。一方、上記で比較される距離同士の差が前記閾値よりも大きい場合には、排土板41の配置または施工面TSの位置(方程式)に問題があるため、出力部506が当該情報を出力し表示部57および報知部58を通じて作業者に報知する。したがって、機械本体10の走行方向の確認、水平を検出することによる各角度センサ誤差のオフセット処理が可能となる。
 なお、図11に示される状態から作業者がショベル100を操作し、排土板41による掘削作業を実施する場合、本実施形態では、図10に示すように、排土板41の施工面TSに対する掘削角度θが演算され、表示部57に表示される。ステップS01において施工面TSの絶対座標(平面の方程式)が既知であるとともに、排土板座標演算部502が排土板41の排土板右端部41Rおよび排土板左端部41Lの絶対座標を演算することができるため、両者の位置関係に基づいて、図10の掘削角度θを演算することができる。なお、上記のような排土板41の排土板左端部41Lおよび排土板右端部41Rを施工面仮想糸FLに沿って配設することによって、ドリフトが乗りやすいヨー角の補正方法として使用することも可能である。
 以上のように、本実施形態によれば、排土板座標演算部502は、本体座標検出部53によって取得された機械本体10の座標情報(本体座標情報)と、本体角度検出部54によって取得された機械本体10の姿勢情報(本体姿勢情報)と、排土板角度検出部55によって取得された排土板41の位置情報(作業部材位置情報)とに基づいて、作業現場における排土板41の排土板左端部41L(特定部位)の絶対座標を演算および出力することができる。そして、排土板左端部41Lが各地上基準点に順に配置され、入力部52がその配置情報を受け付けると、記憶部505は排土板座標演算部502によって演算される排土板左端部41Lの絶対座標を各地上基準点の絶対座標として記憶することができる。更に、入力部52(距離情報入力部)は、各地上基準点の施工面TSに対する深さ情報(距離情報)を受け付ける。この結果、施工面演算部503は、各地上基準点の絶対座標とこれに対応する距離情報とから作業現場の絶対座標系における施工面TSの方程式を演算することができる。したがって、作業者は、従来から作業現場に設けられていた丁張や水糸などを利用して各地上基準点を設定し、ショベル100の排土板左端部41Lを当該地上基準点に順に配置するとともに、当該地上基準点から施工面TSまでの距離情報を入力部52にそれぞれ入力するだけで、作業現場における施工面TSの方程式を容易に得ることができるとともに、出力部506によって出力される情報に基づいて、施工面TSの位置を容易に認識することができる。また、作業現場の3Dデータのように膨大なデータ量を含む情報を外部から受け取ることや前記情報をあらかじめ記憶部505に記憶する必要がなく、施工面設定装置1の複雑化やコストアップを抑制することができる。
 更に、本実施形態では、施工面演算部503は、地上基準点の絶対座標と距離情報とから、地上基準点の下方にそれぞれ配置される仮想基準点の絶対座標を演算し、当該演算された仮想基準点に基づいて施工面TSの方程式を演算する。このような構成によれば、施工面演算部503は、地中に仮想的に設定される仮想基準点の絶対座標から平面の方程式の演算手法に基づいて施工面TSの方程式を容易に演算することができる。
 また、本実施形態では、施工面演算部503は、3つの地上基準点(特定地上基準点)の下方にそれぞれ配置される3つの仮想基準点(特定仮想基準点)の絶対座標を演算し、当該演算された3つの仮想基準点を通る平面の方程式を施工面TSの方程式として演算する。したがって、3つの仮想基準点に基づいて、施工面TSの方程式を容易かつ短時間で演算することができる。
 一方、前述のように、施工面演算部503は、4つの仮想基準点(特定仮想基準点)の絶対座標を演算し、当該演算された4つの仮想基準点に基づく最小二乗平面の方程式を施工面TSの方程式として演算するものでもよい。このような構成によれば、4つの仮想基準点に基づいて、施工面TSの方程式をより高い精度で演算することができる。なお、5つ以上の地上基準点(仮想基準点)に基づいて、施工面TSの位置情報(平面の方程式)が演算、決定されるものでもよい。
 更に、本実施形態では、前記施工面演算部は、少なくとも1つの確認用地上基準点の絶対座標と少なくとも1つの確認用距離情報とから、少なくとも1つの確認用地上基準点の下方に配置される少なくとも1つの確認用仮想基準点の絶対座標を演算することが可能である。また、判定部504は、当該演算された確認用仮想基準点の絶対座標と施工面演算部503によって演算された施工面TSの方程式とに基づいて、施工面TSの方程式が所定の許容範囲内に含まれているか否かを判定する。このような構成によれば、作業者がショベル100の排土板左端部41Lを確認用地上基準点に配置するとともに、確認用距離情報を入力部52に入力するだけで、判定部504が、先に演算された施工面TSの方程式と確認用仮想基準点の絶対座標とに基づいて施工面TSの方程式の精度を判定することができる。したがって、誤って演算された施工面TSの方程式に基づいて、作業現場において掘削および整地作業のミスが発生することを防止することができる。また、作業者は、演算された施工面の方程式の精度を充分に確認した上で、現場作業に着手することができる。
 また、本実施形態では、本体角度検出部54は、キャブ22上の本体基準点を基準とする機械本体10のリフト角、ピッチ角およびヨー角を、機械本体10の姿勢情報としてそれぞれ検出および出力する本体角度センサを含む。また、本体座標検出部53は、全球測位衛星システムに基づいて機械本体10の座標情報を取得する。このような構成によれば、ショベル100の周囲に遮蔽物がある環境においても、機械本体10の位置情報および姿勢情報を検出することが可能となる。
 また、本実施形態では、表示部57に表示される情報によって、作業者が施工面TSの位置を容易に認識することができるとともに、表示部に表示される情報によって施工面TSと排土板41との相対位置関係を認識しながら作業を精度よく行うことができる。
 更に、本実施形態では、各地上基準点の絶対座標を演算するための基準として、ショベル100のドーザ部40の排土板41が用いられている。このような構成によれば、作業者は、ショベル100を操作して排土板41を各地上基準点に配置することで、施工面TSの方程式、位置情報を容易に認識することができる。特に、アタッチメント30と比較して予め低い位置に配置されたドーザ部40の排土板41を用いる場合、作業現場に配設する地上基準点(丁張など)も低い位置に配置することが可能であるため、地上基準点を設定するために配設する部材の高さを抑えることができる。
 更に、本実施形態では、排土板角度検出部55は、排土板41の位置情報(作業部材位置情報)として、排土板41のリフト回転軸F1回りのリフト角を検出および出力することが可能な排土板角度センサを含む。このような構成によれば、作業者はクローラユニット12の走行に加え、排土板41のリフト角を調整することで、ショベル100の排土板41を各地上基準点に容易に配置することができる。
 また、本実施形態では、上記の排土板角度センサは、排土板41の位置情報として、排土板41のチルト回転軸F3回りのチルト角を更に検出および出力することが可能である。このような構成によれば、排土板角度センサが排土板41のチルト角を検出することができるため、作業者はクローラユニット12の走行およびリフト角の調整に加え、排土板41のチルト角を調整することで、ショベル100の排土板41を地上基準点に容易に配置することができる。なお、排土板角度センサは、排土板41のアングル回転軸F2回りのアングル角を検出および出力可能であるため、作業者は排土板41を水平方向に対して傾斜させることができる。したがって、図11のように、地上において傾斜して配置された施工面仮想糸FLに沿って排土板41を配置し、施工面TSの確認作業を行うことも可能である。
 なお、本実施形態では、前述のようなフローによって、作業現場において作業者は施工面TSの位置を認識することができる。すなわち、本実施形態に係る、作業現場における施工面認識方法は、作業現場における施工面認識方法であって、地上を走行可能な走行部を含む機械本体と前記機械本体に対して相対移動可能なように前記機械本体に支持され地面を掘削することが可能な作業部材とを有する作業機械と、上記の何れか1に記載の作業機械の作業補助装置とをそれぞれ準備することと、少なくとも前記走行部の走行に応じて、前記施工面に関連付けられた前記少なくとも3つの地上基準点に前記作業部材の前記特定部位を順に配置し、各地上基準点に対応して前記特定部位座標演算部が演算する前記特定部位の絶対座標を、各地上基準点の絶対座標として前記記憶部にそれぞれ記憶することと、前記少なくとも3つの地上基準点のそれぞれから前記施工面までの上下方向における距離に関する情報である、少なくとも3つの距離情報を前記距離情報入力部に入力することと、前記記憶部に記憶された前記少なくとも3つの地上基準点の前記絶対座標と、前記距離情報入力部に入力された前記少なくとも3つの距離情報とから、前記作業現場の絶対座標系における前記施工面の方程式を演算することと、前記施工面演算部によって演算された前記施工面の方程式に関する情報を出力し、当該出力された情報に基づいて、前記作業現場における前記施工面の位置を作業者に認識させることと、を備える。
 このような方法によれば、作業者は、従来から作業現場に設けられていた丁張や水糸などを利用して各地上基準点を設定し、作業機械の特定部位を当該地上基準点に順に配置するとともに、当該地上基準点から施工面までの距離情報を距離情報入力部にそれぞれ入力するだけで、作業現場における施工面の方程式を容易に得ることができるとともに、施工面情報出力部によって出力される情報に基づいて施工面の位置情報を容易に認識することができる。また、作業現場の3Dデータのように膨大なデータ量を含む情報を外部から受け取ることや前記情報をあらかじめ記憶部に記憶する必要がなく、作業補助装置の複雑化やコストアップを抑制することができる。
 また、本実施形態に係る、作業現場における施工面認識方法は、作業現場における施工面認識方法であって、地上を走行可能な走行部を含む機械本体と前記機械本体に対して相対移動可能なように前記機械本体に支持され地面を掘削することが可能な作業部材とを有する作業機械と、上記の何れか1に記載の作業機械の作業補助装置とをそれぞれ準備することと、少なくとも前記走行部の走行に応じて、前記施工面に関連付けられた前記少なくとも3つの地上基準点に前記作業部材の前記特定部位を順に配置し、各地上基準点に対応して前記特定部位座標演算部が演算する前記特定部位の絶対座標を、各地上基準点の絶対座標として前記記憶部にそれぞれ記憶することと、前記少なくとも3つの地上基準点のそれぞれから前記施工面までの上下方向における距離に関する情報である、少なくとも3つの距離情報を前記距離情報入力部に入力することと、前記記憶部に記憶された前記少なくとも3つの地上基準点の前記絶対座標と、前記距離情報入力部に入力された前記少なくとも3つの距離情報とから、前記作業現場の絶対座標系における前記施工面の方程式を演算することと、前記施工面演算部によって演算された前記施工面の方程式に関する情報を出力し、当該出力された情報に基づいて、作業者に前記作業現場における前記施工面の位置を認識させることと、前記施工面と平行かつ平面視で前記作業機械の前記走行部の走行方向と直交する直線部分を含む確認用基準部材を前記作業現場に配設することと、前記作業機械を操作し、前記排土板のうち左右方向に延びる下端部を前記確認用基準部材の前記直線部分に揃えることと、前記排土板の前記下端部の左右両端部と前記施工面との距離を互いに比較することで、前記施工面の方程式が所定の許容範囲に含まれているか否かを確認することと、を備える。
 このような方法によれば、作業者が排土板を確認用基準部材に揃えた上で、排土板の左右両端部と施工面との距離が所定の誤差範囲内で互いに等しい場合には、排土板と施工面とが互いに平行に配置されているため、そのまま排土板を地中に進入させることで、施工面までの掘削を安定して行うことができる。
 以上、本発明に係る施工面設定装置1およびこれを備えたショベル100、ならびに作業現場における施工面認識方法について説明したが、本発明はこれに限定されるものではなく、下記のような変形例が可能である。
 (1)上記の実施形態では、排土板41の排土板左端部41Lを特定部位としたが、特定部位は、排土板右端部41Rでもよいし、排土板41の中央部であってもよい。また、排土板41の代わりに、アタッチメント30の特定部位(たとえば先端のバケットの一部)に基づいて、各基準点の絶対座標が演算されてもよい。
 (2)また、機械本体10の特定部位による地上基準位置の指定に代えて、GNSS移動局62を記憶したい位置に配置した状態で、作業者が入力部52から直接座標を入力するものでもよい。この場合、作業者がキャブ22内に配置された不図示の記憶指示スイッチを押し、その時のGNSS移動局62の座標が制御部50に送信されればよい。
 (3)また、地上基準点が設定される場所は、丁張りの立板の頂部、横板の上面部、横板の下面部、横板上に描かれた基準線、丁張り間に引かれた水糸など、作業現場において施工面TS(仮想基準点)からの高さが既知であるものであればよく、作業者が当該地上基準点に排土板41の特定部位を合わせることにより、より分かりやすい位置指定を行うことが可能となる。特に、地上基準点は、キャブ22内の作業者から見えやすい位置に配置されることが望ましい。
 (4)また、地上基準点は施工面TSの上方周辺に限られず、施工領域外に配置されてもよい、施工領域外に設置した丁張りを基準点とすることで従来と同様の丁張りのみで施工面TSを演算、決定することが可能となり、作業現場の地形などを示す膨大な3次元形状データが不要となる。
 (5)また、上記の実施形態では、本体座標検出部53が、GNSS基準局61と、GNSS移動局62と、を有する態様にて説明したが、本体座標検出部53は、トータルステーションを利用して、予め機械本体10に設けられた本体基準点の作業現場における絶対座標に関する情報である本体座標情報を取得する態様でもよい。一例として、GNSS基準局61の代わりに、距離および角度を測定可能なカメラを備えた親機が作業現場に設置される一方、GNSS移動局62の代わりに、前記カメラによって撮影されるプリズムを含む子機がショベル100に装着される。このような構成によれば、本体座標情報を精度よく検出することができるとともに、トンネル内などのように上空が遮蔽された作業現場においても、本体座標情報を検出することができる。
 (6)更に、上記の実施形態では、図3に示すように、GNSS移動局62によって設定される原点G1、x1軸、y1軸、z1軸を基準とした機械本体10の座標に対して、排土板角度検出部55によって検出される原点G3、x3軸、y3軸、z3軸に基づく排土板41の相対的な位置情報によって、ドーザ部40(排土板41)の機械本体10に対する相対位置に関する情報である作業部材位置情報が取得される態様にて説明したが、本発明はこれに限定されるものではない。図3に示すように、ドーザ部40の基端部に原点G2、x2軸、y2軸、z2軸に基づく中継点が設定され、当該中継点を介して、ドーザ部40(排土板41)の機械本体10に対する相対位置に関する情報である作業部材位置情報が取得される態様でもよい。また、前記ドーザ部40の基端部にGNSS移動局62が直接配置されてもよい。
 上記の点を踏まえて導き出された、本発明の一の局面に係る作業機械の作業補助装置は、地上を走行可能な走行部を含む機械本体と前記機械本体に対して相対移動可能なように前記機械本体に支持され地面を掘削することが可能な作業部材とを有する作業機械を用いて作業現場において所定の施工面を形成する作業を補助することが可能な作業機械の作業補助装置であって、予め前記機械本体に設けられた本体基準点の前記作業現場における絶対座標に関する情報である本体座標情報を取得することが可能な本体座標情報取得部と、前記本体基準点を基準とする前記機械本体の姿勢に関する情報である本体姿勢情報を取得することが可能な本体姿勢情報取得部と、前記作業部材の前記機械本体に対する相対位置に関する情報である作業部材位置情報を取得することが可能な作業部材位置情報取得部と、前記本体座標情報取得部によって取得された前記本体座標情報と、前記本体姿勢情報取得部によって取得された前記本体姿勢情報と、前記作業部材位置情報取得部によって取得された前記作業部材位置情報とに基づいて、前記作業現場における前記作業部材の特定部位の絶対座標を演算および出力することが可能な特定部位座標演算部と、前記施工面に関連付けられた少なくとも3つの地上基準点に少なくとも前記走行部の走行に応じて前記作業部材の前記特定部位が配置されたことを示す情報である配置情報をそれぞれ受け付けることが可能な配置情報受付部と、前記少なくとも3つの地上基準点のそれぞれにおいて前記配置情報受付部が前記配置情報を受け付けることに対応して前記特定部位座標演算部が演算する前記特定部位の絶対座標を、前記少なくとも3つの地上基準点の前記作業現場における絶対座標としてそれぞれ記憶する、記憶部と、前記少なくとも3つの地上基準点のそれぞれから前記施工面までの上下方向における距離に関する情報である、少なくとも3つの距離情報の入力を受け付けることが可能な距離情報入力部と、前記記憶部に記憶された前記少なくとも3つの地上基準点の前記絶対座標と、前記距離情報入力部に入力された前記少なくとも3つの距離情報とから、前記作業現場の絶対座標系における前記施工面の方程式を演算する施工面演算部と、前記施工面演算部によって演算された前記施工面の方程式に関する情報を出力する施工面情報出力部と、を備える。
 本構成によれば、施工面演算部が、各地上基準点の絶対座標とこれに対応する距離情報とから作業現場の絶対座標系における施工面の方程式を演算することができる。したがって、作業者は、各地上基準点を設定し作業機械を操作してその特定部位を当該地上基準点に順に配置するとともに、当該地上基準点から施工面までの距離情報を距離情報入力部にそれぞれ入力するだけで、作業現場における施工面の方程式を容易に得ることができるとともに、施工面情報出力部によって出力される情報に基づいて施工面の位置を容易に認識することができる。また、作業現場の3Dデータのように膨大なデータ量を含む情報を外部から受け取ることや前記情報をあらかじめ記憶部に記憶する必要がなく、作業補助装置の複雑化やコストアップを抑制することができる。なお、作業者は、従来から作業現場に設けられていた丁張や水糸などを利用して地上基準点を設定してもよい。
 上記の構成において、前記施工面演算部は、前記少なくとも3つの地上基準点の前記絶対座標と前記少なくとも3つの距離情報とから、前記少なくとも3つの地上基準点の下方にそれぞれ配置される少なくとも3つの仮想基準点の絶対座標を演算し、当該演算された少なくとも3つの仮想基準点に基づいて前記施工面の方程式を演算することが望ましい。
 本構成によれば、施工面演算部は、地中に仮想的に設定される3つ以上の仮想基準点の絶対座標から平面の方程式の演算手法に基づいて施工面の方程式を容易に演算することができる。
 上記の構成において、前記少なくとも3つの地上基準点は、3つの特定地上基準点を含み、前記距離情報入力部は、前記3つの特定地上基準点のそれぞれから前記施工面までの上下方向における距離に関する情報である、3つの特定距離情報の入力を受け付け、前記施工面演算部は、前記3つの特定地上基準点の前記絶対座標と前記3つの特定距離情報とから、前記3つの特定地上基準点の下方にそれぞれ配置される3つの特定仮想基準点の絶対座標を演算し、当該演算された3つの特定仮想基準点を通る平面の方程式を前記施工面の方程式として演算することが望ましい。
 本構成によれば、3つの特定仮想基準点に基づいて、施工面の方程式を容易かつ短時間で演算することができる。
 上記の構成において、前記少なくとも3つの地上基準点は、少なくとも4つの特定地上基準点を含み、前記距離情報入力部は、前記少なくとも4つの特定地上基準点のそれぞれから前記施工面までの上下方向における距離に関する情報である、少なくとも4つの特定距離情報の入力を受け付け、前記施工面演算部は、前記少なくとも4つの特定地上基準点の前記絶対座標と前記少なくとも4つの特定距離情報とから、前記少なくとも4つの特定地上基準点の下方にそれぞれ配置される少なくとも4つの特定仮想基準点の絶対座標を演算し、当該演算された少なくとも4つの特定仮想基準点に基づく最小二乗平面の方程式を前記施工面の方程式として演算するものでもよい。
 本構成によれば、4つ以上の特定仮想基準点に基づいて、施工面の方程式をより高い精度で演算することができる。
 上記の構成において、前記配置情報受付部は、前記施工面に関連付けられた少なくとも1つの確認用地上基準点に少なくとも前記走行部の走行に応じて前記特定部位が配置されたことを示す確認用配置情報を受け付けることが更に可能であり、前記記憶部は、前記確認用配置情報を受け付けることに対応して、前記特定部位座標演算部によって演算される前記特定部位の絶対座標を、前記少なくとも1つの確認用地上基準点の前記作業現場における絶対座標として記憶することが可能であり、距離情報入力部は、前記少なくとも1つの確認用地上基準点から前記施工面までの上下方向における距離に関する情報である、少なくとも1つの確認用距離情報の入力を受け付けることが可能であり、前記施工面演算部は、前記少なくとも1つの確認用地上基準点の前記絶対座標と前記少なくとも1つの確認用距離情報とから、前記少なくとも1つの確認用地上基準点の下方に配置される少なくとも1つの確認用仮想基準点の絶対座標を演算することが可能であり、当該演算された確認用仮想基準点の絶対座標と予め前記施工面演算部によって演算された前記施工面の方程式とに基づいて、前記施工面の方程式が所定の許容範囲内に含まれているか否かを判定する判定部を更に備えることが望ましい。
 本構成によれば、作業者が作業機械の特定部位を確認用地上基準点に配置するとともに、確認用距離情報を距離情報入力部に入力するだけで、判定部が、先に演算された施工面の方程式と確認用仮想基準点の絶対座標とに基づいて施工面の方程式の精度を判定することができる。このため、作業者は、演算された施工面の方程式の精度を充分に確認した上で、現場作業に着手することができる。
 上記の構成において、前記本体姿勢情報取得部は、前記本体基準点を基準とする前記機械本体のリフト角、ピッチ角およびヨー角を前記本体姿勢情報としてそれぞれ検出および出力する本体角度センサを含むことが望ましい。また、前記本体座標情報取得部は、全球測位衛星システムまたはトータルステーションに基づいて前記本体座標情報を取得することが望ましい。
 また、上記の構成において、前記施工面情報出力部から出力された前記施工面の方程式に関する情報を表示することが可能な表示部を更に備えることが望ましい。
 本構成によれば、表示部に表示される情報によって、作業者が施工面の位置を容易に認識することができる。
 上記の構成において、前記表示部は、前記特定部位座標演算部から出力された前記特定部位の絶対座標に基づいて、前記施工面と前記特定部位との相対位置に関する情報を更に表示することが可能であることが望ましい。
 本構成によれば、作業者は、表示部に表示される情報によって施工面と作業部材との相対位置関係を認識しながら、作業を精度よく行うことができる。
 上記の構成において、前記作業機械の前記作業部材は、排土板と当該排土板を支持するとともに左右方向に延びるリフト回転中心軸回りに揺動可能なように前記機械本体に支持された排土板支持部と、を有し、前記特定部位座標演算部は、前記作業現場における前記作業部材の特定部位として、前記排土板の特定部位の絶対座標を演算および出力することが可能であることが望ましい。
 本構成によれば、作業者は、作業機械を操作して排土板を各地上基準点に配置することで、施工面の位置を容易に認識することができる。
 上記の構成において、前記作業部材位置情報取得部は、前記作業部材位置情報として、前記排土板の前記リフト回転中心軸回りのリフト角を検出および出力することが可能な排土板角度センサを含むことが望ましい。
 本構成によれば、作業部材位置情報取得部が排土板角度センサを有しているため、作業者は走行部の走行に加え、排土板のリフト角を調整することで作業機械の排土板を地上基準点に容易に配置することができる。
 上記の構成において、前記作業部材の前記排土板は、左右方向に延びるチルト回転中心軸周りに揺動可能なように前記排土板支持部に支持されており、前記排土板角度センサは、前記作業部材位置情報として、前記排土板の前記チルト回転中心軸回りのチルト角を更に検出および出力することが可能であることが望ましい。
 本構成によれば、排土板角度センサが排土板のチルト角を検出することができるため、作業者は走行部の走行およびリフト角の調整に加え、排土板のチルト角を調整することで、作業機械の排土板を地上基準点に容易に配置することができる。
 本発明の他の局面に係る作業現場における施工面認識方法は、作業現場における施工面認識方法であって、地上を走行可能な走行部を含む機械本体と前記機械本体に対して相対移動可能なように前記機械本体に支持され地面を掘削することが可能な作業部材とを有する作業機械と、上記の何れか1に記載の作業機械の作業補助装置とをそれぞれ準備することと、少なくとも前記走行部の走行に応じて、前記施工面に関連付けられた前記少なくとも3つの地上基準点に前記作業部材の前記特定部位を順に配置し、各地上基準点に対応して前記特定部位座標演算部が演算する前記特定部位の絶対座標を、各地上基準点の絶対座標として前記記憶部にそれぞれ記憶することと、前記少なくとも3つの地上基準点のそれぞれから前記施工面までの上下方向における距離に関する情報である、少なくとも3つの距離情報を前記距離情報入力部にそれぞれ入力することと、前記記憶部に記憶された前記少なくとも3つの地上基準点の前記絶対座標と、前記距離情報入力部に入力された前記少なくとも3つの距離情報とから、前記作業現場の絶対座標系における前記施工面の方程式を演算することと、前記演算した前記施工面の方程式に関する情報を出力し、当該出力された情報に基づいて、前記作業現場における前記施工面の位置を作業者に認識させることと、を備える。
 本方法によれば、作業者は、各地上基準点を設定し作業機械の特定部位を当該地上基準点に順に配置するとともに、当該地上基準点から施工面までの距離情報を距離情報入力部にそれぞれ入力するだけで、作業現場における施工面の方程式を容易に得ることができるとともに、施工面情報出力部によって出力される情報に基づいて施工面の位置情報を容易に認識することができる。また、作業現場の3Dデータのように膨大なデータ量を含む情報を外部から受け取ることや前記情報をあらかじめ記憶部に記憶する必要がなく、作業補助装置の複雑化やコストアップを抑制することができる。
 また、本発明の他の局面に係る作業現場における施工面認識方法は、作業現場における施工面認識方法であって、地上を走行可能な走行部を含む機械本体と前記機械本体に対して相対移動可能なように前記機械本体に支持され地面を掘削することが可能な作業部材とを有する作業機械と、上記の何れか1に記載の作業機械の作業補助装置とをそれぞれ準備することと、少なくとも前記走行部の走行に応じて、前記施工面に関連付けられた前記少なくとも3つの地上基準点に前記作業部材の前記特定部位を順に配置し、各地上基準点に対応して前記特定部位座標演算部が演算する前記特定部位の絶対座標を、各地上基準点の絶対座標として前記記憶部にそれぞれ記憶することと、前記少なくとも3つの地上基準点のそれぞれから前記施工面までの上下方向における距離に関する情報である、少なくとも3つの距離情報を前記距離情報入力部にそれぞれ入力することと、前記記憶部に記憶された前記少なくとも3つの地上基準点の前記絶対座標と、前記距離情報入力部に入力された前記少なくとも3つの距離情報とから、前記作業現場の絶対座標系における前記施工面の方程式を演算することと、前記演算した前記施工面の方程式に関する情報を出力し、当該出力された情報に基づいて、作業者に前記作業現場における前記施工面の位置を認識させることと、前記施工面と平行かつ平面視で前記作業機械の前記走行部の走行方向と直交する直線部分を含む確認用基準部材を前記作業現場に配設することと、前記作業機械を操作し、前記排土板のうち左右方向に延びる下端部を前記確認用基準部材の前記直線部分に揃えることと、前記排土板の前記下端部の左右両端部と前記施工面との距離を互いに比較することで、前記演算された施工面の方程式が所定の許容範囲に含まれているか否かを確認することと、を備える。
 本方法によれば、作業者が排土板を確認用基準部材に揃えるだけで、排土板と施工面との相対位置関係から施工面の方程式の精度を確認することができる。そして、排土板の左右両端部と施工面との距離が所定の誤差範囲内で互いに等しい場合には、そのまま排土板を地中に進入させることで、施工面までの掘削を安定して行うことができる。
 本発明によれば、作業現場に応じた3Dデータの外部からの受け取りや前もっての記憶を要することなく、作業者が施工面を容易に認識することを可能とする作業機械の作業補助装置および作業現場における施工面認識方法が提供される。

Claims (14)

  1.  地上を走行可能な走行部を含む機械本体と前記機械本体に対して相対移動可能なように前記機械本体に支持され地面を掘削することが可能な作業部材とを有する作業機械を用いて作業現場において所定の施工面を形成する作業を補助することが可能な作業機械の作業補助装置であって、
     予め前記機械本体に設けられた本体基準点の前記作業現場における絶対座標に関する情報である本体座標情報を取得することが可能な本体座標情報取得部と、
     前記本体基準点を基準とする前記機械本体の姿勢に関する情報である本体姿勢情報を取得することが可能な本体姿勢情報取得部と、
     前記作業部材の前記機械本体に対する相対位置に関する情報である作業部材位置情報を取得することが可能な作業部材位置情報取得部と、
     前記本体座標情報取得部によって取得された前記本体座標情報と、前記本体姿勢情報取得部によって取得された前記本体姿勢情報と、前記作業部材位置情報取得部によって取得された前記作業部材位置情報とに基づいて、前記作業現場における前記作業部材の特定部位の絶対座標を演算および出力することが可能な特定部位座標演算部と、
     前記施工面に関連付けられた少なくとも3つの地上基準点に少なくとも前記走行部の走行に応じて前記作業部材の前記特定部位が配置されたことを示す情報である配置情報をそれぞれ受け付けることが可能な配置情報受付部と、
     前記少なくとも3つの地上基準点のそれぞれにおいて前記配置情報受付部が前記配置情報を受け付けることに対応して前記特定部位座標演算部が演算する前記特定部位の絶対座標を、前記少なくとも3つの地上基準点の前記作業現場における絶対座標としてそれぞれ記憶する、記憶部と、
     前記少なくとも3つの地上基準点のそれぞれから前記施工面までの上下方向における距離に関する情報である、少なくとも3つの距離情報の入力を受け付けることが可能な距離情報入力部と、
     前記記憶部に記憶された前記少なくとも3つの地上基準点の前記絶対座標と、前記距離情報入力部に入力された前記少なくとも3つの距離情報とから、前記作業現場の絶対座標系における前記施工面の方程式を演算する施工面演算部と、
     前記施工面演算部によって演算された前記施工面の方程式に関する情報を出力する施工面情報出力部と、
     を備える、作業機械の作業補助装置。
  2. 請求項1に記載の作業機械の作業補助装置であって、
     前記施工面演算部は、前記少なくとも3つの地上基準点の前記絶対座標と前記少なくとも3つの距離情報とから前記少なくとも3つの地上基準点の下方にそれぞれ配置される少なくとも3つの仮想基準点の絶対座標を演算し、当該演算された少なくとも3つの仮想基準点に基づいて前記施工面の方程式を演算する、作業機械の作業補助装置。
  3. 請求項2に記載の作業機械の作業補助装置であって、
     前記少なくとも3つの地上基準点は、3つの特定地上基準点を含み、
     前記距離情報入力部は、前記3つの特定地上基準点のそれぞれから前記施工面までの上下方向における距離に関する情報である、3つの特定距離情報の入力を受け付け、
     前記施工面演算部は、前記3つの特定地上基準点の前記絶対座標と前記3つの特定距離情報とから、前記3つの特定地上基準点の下方にそれぞれ配置される3つの特定仮想基準点の絶対座標を演算し、当該演算された3つの特定仮想基準点を通る平面の方程式を前記施工面の方程式として演算する、作業機械の作業補助装置。
  4. 請求項2に記載の作業機械の作業補助装置であって、
     前記少なくとも3つの地上基準点は、少なくとも4つの特定地上基準点を含み、
     前記距離情報入力部は、前記少なくとも4つの特定地上基準点のそれぞれから前記施工面までの上下方向における距離に関する情報である、少なくとも4つの特定距離情報の入力を受け付け、
     前記施工面演算部は、前記少なくとも4つの特定地上基準点の前記絶対座標と前記少なくとも4つの特定距離情報とから、前記少なくとも4つの特定地上基準点の下方にそれぞれ配置される少なくとも4つの特定仮想基準点の絶対座標を演算し、当該演算された少なくとも4つの特定仮想基準点に基づく最小二乗平面の方程式を前記施工面の方程式として演算する、作業機械の作業補助装置。
  5. 請求項1乃至4の何れか1項に記載の作業機械の作業補助装置であって、
     前記配置情報受付部は、前記施工面に関連付けられた少なくとも1つの確認用地上基準点に少なくとも前記走行部の走行に応じて前記特定部位が配置されたことを示す確認用配置情報を受け付けることが更に可能であり、
     前記記憶部は、前記配置情報受付部が前記確認用配置情報を受け付けることに対応して、前記特定部位座標演算部によって演算される前記特定部位の絶対座標を前記少なくとも1つの確認用地上基準点の前記作業現場における絶対座標として記憶することが可能であり、
     距離情報入力部は、前記少なくとも1つの確認用地上基準点から前記施工面までの上下方向における距離に関する情報である、少なくとも1つの確認用距離情報の入力を受け付けることが可能であり、
     前記施工面演算部は、前記少なくとも1つの確認用地上基準点の前記絶対座標と前記少なくとも1つの確認用距離情報とから、前記少なくとも1つの確認用地上基準点の下方に配置される少なくとも1つの確認用仮想基準点の絶対座標を演算することが可能であり、
     前記演算された確認用仮想基準点の絶対座標と予め前記施工面演算部によって演算された前記施工面の方程式とに基づいて、前記施工面の方程式が所定の許容範囲内に含まれているか否かを判定する判定部を更に備える、作業機械の作業補助装置。
  6. 請求項1に記載の作業機械の作業補助装置であって、
     前記本体姿勢情報取得部は、前記本体基準点を基準とする前記機械本体のリフト角、ピッチ角およびヨー角を前記本体姿勢情報としてそれぞれ検出および出力する本体角度センサを含む、作業機械の作業補助装置。
  7. 請求項1に記載の作業機械の作業補助装置であって、
     前記本体座標情報取得部は、全球測位衛星システムまたはトータルステーションに基づいて前記本体座標情報を取得する、作業機械の作業補助装置。
  8. 請求項1に記載の作業機械の作業補助装置であって、
     前記施工面情報出力部から出力された前記施工面の方程式に関する情報を表示することが可能な表示部を更に備える、作業機械の作業補助装置。
  9. 請求項8に記載の作業機械の作業補助装置であって、
     前記表示部は、前記特定部位座標演算部から出力された前記特定部位の絶対座標に基づいて前記施工面と前記特定部位との相対位置に関する情報を更に表示することが可能である、作業機械の作業補助装置。
  10. 請求項1に記載の作業機械の作業補助装置であって、
     前記作業機械の前記作業部材は、排土板と当該排土板を支持するとともに左右方向に延びるリフト回転中心軸回りに揺動可能なように前記機械本体に支持された排土板支持部と、を有し、
     前記特定部位座標演算部は、前記作業現場における前記作業部材の特定部位として前記排土板の特定部位の絶対座標を演算および出力することが可能である、作業機械の作業補助装置。
  11. 請求項10に記載の作業機械の作業補助装置であって、
     前記作業部材位置情報取得部は、前記作業部材位置情報として前記排土板の前記リフト回転中心軸回りのリフト角を検出および出力することが可能な排土板角度センサを含む、作業機械の作業補助装置。
  12. 請求項11に記載の作業機械の作業補助装置であって、
     前記作業部材の前記排土板は、左右方向に延びるチルト回転中心軸周りに揺動可能なように前記排土板支持部に支持されており、
     前記排土板角度センサは、前記作業部材位置情報として前記排土板の前記チルト回転中心軸回りのチルト角を更に検出および出力することが可能である、作業機械の作業補助装置。
  13.  作業現場における施工面認識方法であって、
     地上を走行可能な走行部を含む機械本体と前記機械本体に対して相対移動可能なように前記機械本体に支持され地面を掘削することが可能な作業部材とを有する作業機械と、請求項1乃至12の何れか1項に記載の作業機械の作業補助装置とをそれぞれ準備することと、
     少なくとも前記走行部の走行に応じて、前記施工面に関連付けられた前記少なくとも3つの地上基準点に前記作業部材の前記特定部位を順に配置し、各地上基準点に対応して前記特定部位座標演算部が演算する前記特定部位の絶対座標を各地上基準点の絶対座標として前記記憶部にそれぞれ記憶することと、
     前記少なくとも3つの地上基準点のそれぞれから前記施工面までの上下方向における距離に関する情報である、少なくとも3つの距離情報を前記距離情報入力部にそれぞれ入力することと、
     前記記憶部に記憶された前記少なくとも3つの地上基準点の前記絶対座標と、前記距離情報入力部に入力された前記少なくとも3つの距離情報とから、前記作業現場の絶対座標系における前記施工面の方程式を演算することと、
     前記演算した前記施工面の方程式に関する情報を出力し、当該出力された情報に基づいて前記作業現場における前記施工面の位置を作業者に認識させることと、
     を備える、作業現場における施工面認識方法。
  14.  作業現場における施工面認識方法であって、
     地上を走行可能な走行部を含む機械本体と前記機械本体に対して相対移動可能なように前記機械本体に支持され地面を掘削することが可能な作業部材とを有する作業機械と、請求項10乃至12の何れか1項に記載の作業機械の作業補助装置とをそれぞれ準備することと、
     少なくとも前記走行部の走行に応じて、前記施工面に関連付けられた前記少なくとも3つの地上基準点に前記作業部材の前記特定部位を順に配置し、各地上基準点に対応して前記特定部位座標演算部が演算する前記特定部位の絶対座標を各地上基準点の絶対座標として前記記憶部にそれぞれ記憶することと、
     前記少なくとも3つの地上基準点のそれぞれから前記施工面までの上下方向における距離に関する情報である、少なくとも3つの距離情報を前記距離情報入力部にそれぞれ入力することと、
     前記記憶部に記憶された前記少なくとも3つの地上基準点の前記絶対座標と、前記距離情報入力部に入力された前記少なくとも3つの距離情報とから、前記作業現場の絶対座標系における前記施工面の方程式を演算することと、
     前記演算した前記施工面の方程式に関する情報を出力し、当該出力された情報に基づいて、作業者に前記作業現場における前記施工面の位置を認識させることと、
     前記施工面と平行かつ平面視で前記作業機械の前記走行部の走行方向と直交する直線部分を含む確認用基準部材を前記作業現場に配設することと、
     前記作業機械を操作し前記排土板のうち左右方向に延びる下端部を前記確認用基準部材の前記直線部分に揃えることと、
     前記排土板の前記下端部の左右両端部と前記施工面との距離を互いに比較することで、前記演算された施工面の方程式が所定の許容範囲に含まれているか否かを確認することと、
     を備える、作業現場における施工面認識方法。
     
PCT/JP2020/039417 2019-12-18 2020-10-20 作業機械の作業補助装置および作業現場における施工面認識方法 WO2021124671A1 (ja)

Priority Applications (3)

Application Number Priority Date Filing Date Title
CN202080086367.3A CN114787456A (zh) 2019-12-18 2020-10-20 工程机械的作业辅助装置及作业现场的施工面识别方法
US17/785,841 US20230019245A1 (en) 2019-12-18 2020-10-20 Work assist device for work machine and method for recognizing construction surface at work site
EP20901313.5A EP4060127A1 (en) 2019-12-18 2020-10-20 Work assist device for work machine and method for recognizing construction surface at work site

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
JP2019228329A JP2021095775A (ja) 2019-12-18 2019-12-18 作業機械の作業補助装置および作業現場における施工面認識方法
JP2019-228329 2019-12-18

Publications (1)

Publication Number Publication Date
WO2021124671A1 true WO2021124671A1 (ja) 2021-06-24

Family

ID=76430882

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/JP2020/039417 WO2021124671A1 (ja) 2019-12-18 2020-10-20 作業機械の作業補助装置および作業現場における施工面認識方法

Country Status (5)

Country Link
US (1) US20230019245A1 (ja)
EP (1) EP4060127A1 (ja)
JP (1) JP2021095775A (ja)
CN (1) CN114787456A (ja)
WO (1) WO2021124671A1 (ja)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2023204197A1 (ja) * 2022-04-19 2023-10-26 日本精機株式会社 作業支援システム
WO2023243580A1 (ja) * 2022-06-13 2023-12-21 日本精機株式会社 作業支援システム

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH03295935A (ja) * 1990-04-13 1991-12-26 Shimizu Corp 管埋設施工法及び施工装置
JP2002340556A (ja) * 2001-05-18 2002-11-27 Hitachi Constr Mach Co Ltd 走行式建設機械の位置計測システム、位置計測コンピュータ及び位置計測プログラム
JP2006265954A (ja) 2005-03-24 2006-10-05 Hitachi Constr Mach Co Ltd 作業機械の目標作業面設定装置
JP2010117230A (ja) * 2008-11-12 2010-05-27 Topcon Corp 建設機械
JP2017003448A (ja) * 2015-06-11 2017-01-05 株式会社岩崎 地盤測量装置、地盤測量システム、地盤測量プログラムおよび地盤測量方法
JP2017071916A (ja) * 2015-10-05 2017-04-13 株式会社小松製作所 施工管理システム及び施工管理方法
JP2017180712A (ja) * 2016-03-31 2017-10-05 日立建機株式会社 建設機械
US9783955B1 (en) * 2016-11-09 2017-10-10 Caterpillar Inc. System and method for moving material
JP2018155027A (ja) * 2017-03-17 2018-10-04 日立建機株式会社 建設機械
JP2019039208A (ja) * 2017-08-24 2019-03-14 日立建機株式会社 油圧式作業機械

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108549771A (zh) * 2018-04-13 2018-09-18 山东天星北斗信息科技有限公司 一种挖掘机辅助施工系统及方法

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH03295935A (ja) * 1990-04-13 1991-12-26 Shimizu Corp 管埋設施工法及び施工装置
JP2002340556A (ja) * 2001-05-18 2002-11-27 Hitachi Constr Mach Co Ltd 走行式建設機械の位置計測システム、位置計測コンピュータ及び位置計測プログラム
JP2006265954A (ja) 2005-03-24 2006-10-05 Hitachi Constr Mach Co Ltd 作業機械の目標作業面設定装置
JP2010117230A (ja) * 2008-11-12 2010-05-27 Topcon Corp 建設機械
JP2017003448A (ja) * 2015-06-11 2017-01-05 株式会社岩崎 地盤測量装置、地盤測量システム、地盤測量プログラムおよび地盤測量方法
JP2017071916A (ja) * 2015-10-05 2017-04-13 株式会社小松製作所 施工管理システム及び施工管理方法
JP2017180712A (ja) * 2016-03-31 2017-10-05 日立建機株式会社 建設機械
US9783955B1 (en) * 2016-11-09 2017-10-10 Caterpillar Inc. System and method for moving material
JP2018155027A (ja) * 2017-03-17 2018-10-04 日立建機株式会社 建設機械
JP2019039208A (ja) * 2017-08-24 2019-03-14 日立建機株式会社 油圧式作業機械

Also Published As

Publication number Publication date
CN114787456A (zh) 2022-07-22
JP2021095775A (ja) 2021-06-24
US20230019245A1 (en) 2023-01-19
EP4060127A1 (en) 2022-09-21

Similar Documents

Publication Publication Date Title
EP1541772B1 (en) Excavation teaching apparatus for construction machine
JP6925816B2 (ja) 位置計測システム、作業機械、及び位置計測方法
JP5823046B1 (ja) 油圧ショベルの較正システム及び較正方法
CN105339759B (zh) 作业机械的控制系统以及作业机械的控制方法
US7831362B2 (en) Position measuring system for working machine
KR20170108124A (ko) 표시 시스템 및 건설 기계
CN110799708B (zh) 作业机械
WO2021124671A1 (ja) 作業機械の作業補助装置および作業現場における施工面認識方法
JP6918716B2 (ja) 建設機械
US11585073B2 (en) Construction system and construction method
KR20100122389A (ko) 스테레오 비전 기술을 이용한 굴삭작업 지원 시스템
JP6949727B2 (ja) 作業機械の較正方法、較正装置および作業機械の較正システム
KR20190110590A (ko) 굴삭 기계의 표시 시스템, 굴삭 기계, 및 굴삭 기계의 표시 방법
JP6878051B2 (ja) 排土板の位置補正量取得方法
JP2689250B2 (ja) トンネル用掘進機の姿勢制御装置
WO2023204197A1 (ja) 作業支援システム
JP7065002B2 (ja) 作業機械
WO2023282204A1 (ja) 作業機械の制御システム、作業機械、及び作業機械の制御方法
WO2023282203A1 (ja) 作業機械の制御システム、作業機械、及び作業機械の制御方法
WO2023063038A1 (ja) バケット情報取得装置およびこれを備えた建設機械
KR20150102445A (ko) 지형 정보를 이용한 건설기계의 작업 제어 장치 및 그 방법

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 20901313

Country of ref document: EP

Kind code of ref document: A1

ENP Entry into the national phase

Ref document number: 2020901313

Country of ref document: EP

Effective date: 20220614

NENP Non-entry into the national phase

Ref country code: DE