WO2021000443A1 - Hosting method for heavy apparatus close to unsealed building - Google Patents
Hosting method for heavy apparatus close to unsealed building Download PDFInfo
- Publication number
- WO2021000443A1 WO2021000443A1 PCT/CN2019/110663 CN2019110663W WO2021000443A1 WO 2021000443 A1 WO2021000443 A1 WO 2021000443A1 CN 2019110663 W CN2019110663 W CN 2019110663W WO 2021000443 A1 WO2021000443 A1 WO 2021000443A1
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- steel
- building
- unclosed
- equipment
- steel pipe
- Prior art date
Links
Images
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C23/00—Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
- B66C23/18—Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes
- B66C23/26—Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes for use on building sites; constructed, e.g. with separable parts, to facilitate rapid assembly or dismantling, for operation at successively higher levels, for transport by road or rail
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C23/00—Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
- B66C23/18—Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes
- B66C23/36—Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes mounted on road or rail vehicles; Manually-movable jib-cranes for use in workshops; Floating cranes
Definitions
- the invention relates to the technical field of equipment hoisting, in particular to a method for hoisting heavy equipment adjacent to an unclosed building.
- the hoisting of heavy equipment is mostly carried out after the main structure of the building is completed. It is rarely used to first hoist the heavy equipment and then construct the main structure of the building. Underground buildings such as subway stations are hoisted in the foundation pit before they are closed. Heavy equipment such as a shield machine has a relatively large mass.
- large lifting equipment is mainly used For hoisting, the requirements for lifting tonnage of lifting equipment are relatively high.
- the surrounding environment of most subway stations is complicated, and sufficient space cannot be increased for larger lifting equipment, and higher lifting equipment rental costs It is also relatively high. In urban environments, there are also situations where it cannot be rented.
- Such a construction environment brings greater difficulties to hoisting, and the hoisting radius of the lifting equipment is limited, and it is not a mechanism that can extend indefinitely. , It is further impossible to directly hoist the equipment from the deeper underground buildings.
- the hoisting of heavy equipment must not only ensure the safety of the main structure of the building that does not form a closed whole, but also ensure that the foundation bearing capacity of the crane in the foundation pit meets the requirements of hoisting safety. At the same time, it is also necessary to consider the load of the crane in the foundation pit to form a closed whole. Adverse effects of buildings. When heavy equipment is hoisted in the foundation pit of a nearby building that does not form a closed whole, the crane load in the foundation pit generates lateral pressure on the ground. If the lateral pressure on the ground is too large, it will seriously affect the safety of the building that does not form a closed whole, and even cause Bring catastrophic consequences.
- the present invention provides a method for hoisting heavy equipment adjacent to unclosed buildings, which can realize the hoisting of heavy equipment step by step.
- the hoisting is reliable and has little impact on unclosed buildings, and the impact on unclosed buildings is reduced accordingly.
- Equipment requirements are provided.
- a method for hoisting heavy equipment for nearby unclosed buildings including:
- the first-level lifting equipment never closes the inside of the building to hoist heavy equipment to the temporary platform, and then use the second-level lifting equipment to hoist the heavy equipment from the temporary platform to the outside of the building.
- the above-mentioned hoisting method can be used for hoisting heavy equipment in buildings that are not completely enclosed (partially closed and partly unclosed).
- the first-level lifting equipment is located on the top of the unenclosed building and will The heavy equipment is hoisted to the temporary platform, and then hoisted by the second-level hoisting equipment.
- the setting facilitates the entry and exit of the lifting equipment, and correspondingly reduces the lateral pressure of the lifting equipment on the building.
- the rated lifting loads of the first-level lifting equipment and the second-level lifting equipment are the same or similar, and both meet the lifting safety requirements, which The elevation of the station area is different.
- the first-level lifting equipment is a crawler crane.
- the two crawlers of the crawler crane are located at the top of the middle of the two end wells of the unclosed building, and the center distance of the crawlers is consistent with the center distance of the longitudinal beams at the top of the middle of the end well In this way, a certain space is provided for the temporary storage platform, and it is also convenient for the first-level lifting equipment to be hoisted.
- the crawler crane can be assembled and is convenient for installation on the top of the building.
- the top of the unenclosed building is supported by a steel box to support the first-level lifting equipment.
- the arrangement of the steel box can buffer and evenly distribute the stress generated by the first-level lifting equipment on the top of the building.
- the backfilled soil body is vertically provided with a number of steel pipe lattice column structures.
- the steel pipe lattice column structure Through the arrangement of the steel pipe lattice column structure, they are used as vertical force transmission members to reduce the stress of the second-level lifting equipment on the backfilled soil.
- the steel pipe lattice column is transmitted to the rock layer under the foundation pit, thus effectively avoiding the lateral pressure generated by the lifting equipment on the building structure during the hoisting process.
- each of the steel tube lattice column structure includes at least one steel tube, the steel tube is filled with concrete, the bottom of the steel tube lattice column structure is provided with a first steel plate, the top of the steel tube lattice column structure is provided with a second steel plate, and each The two adjacent steel pipes in the steel-tube lattice column structure are connected by connecting pieces. There are multiple rows of connecting pieces between the two adjacent steel pipes.
- the steel pipes are filled with concrete, and the adjacent steel pipes in the steel pipe lattice column structure pass through sleeves.
- the valve grouting pipe injects cement slurry, which is beneficial to improve the rigidity of the steel pipe lattice column structure and ensure the reliability of vertical force transmission.
- steps of setting backfill soil on the side of the unclosed building are as follows:
- the two rows of steel sheet piles are connected by setting steel wire ropes, and the steel wires are arranged in layers. During the layered arrangement of the steel wire ropes, soil is gradually backfilled between the two rows of steel sheet piles;
- the steel wire rope will go around the end of the I-beam and fasten it with a buckle.
- the steel wire ropes are cut to recover the steel sheet piles on both sides of the backfill soil.
- the height of the backfilled soil is to be the minimum value under the premise of meeting the requirements of the second-level lifting equipment, so as to reduce the amount of backfilled soil, reduce the construction cost and minimize the side pressure zone of the backfilled soil.
- the coming series has adverse effects.
- the present invention uses two-stage lifting equipment to hoist heavy equipment in unenclosed buildings, which reduces the requirements for lifting equipment and correspondingly reduces the strength requirements of the lifting equipment on the foundation structure. Through step-by-step transport, The lateral pressure of the lifting equipment on the building is also correspondingly reduced to avoid adverse effects on the building.
- the present invention not only facilitates the entry and departure of two-level lifting equipment through the setting of backfilling soil, especially the entry and departure of two-level lifting equipment.
- the second-level lifting equipment can not only facilitate heavy equipment
- the hoisting is also convenient for hoisting the first-level lifting equipment through the second-level lifting equipment.
- steel sheet piles are set on both sides of the backfilled soil and tightened by steel wire ropes, which can act as a retaining wall for the backfilled soil and improve the stability of the backfilled soil as the foundation of the second-level lifting equipment Strong, can avoid the lateral pressure of the hoisting load on the building, and ensure the safety of unclosed buildings.
- the present invention can transmit the lifting load to the supporting rock layer at the bottom of the foundation pit by installing steel sheet piles in the backfill soil body, thereby further avoiding the lateral pressure of the lifting load on the building and improving the vertical stability of the foundation structure.
- Figure 1 A schematic plan view of the main structure of the station in the embodiment of the present invention
- Figure 2 is a cross-sectional view of the main structure of the station in the embodiment of the present invention.
- Figure 3 is a schematic longitudinal view of the main structure of the station in the embodiment of the present invention.
- Figure 4 is a schematic cross-sectional view of the backfilled soil in the embodiment of the present invention.
- Fig. 5 is a schematic diagram of the occupation of two cranes for hoisting shield components in the embodiment of the present invention.
- Figure 6 is a schematic diagram of the layout of monitoring points in the embodiment of the present invention.
- Fig. 7 is a schematic diagram of the horizontal plane of foundation treatment of the crane in the embodiment of the present invention.
- Figure 8 is a schematic cross-sectional view of the connection between the steel sheet pile and the steel wire rope in the embodiment of the present invention.
- Figure 9 is a horizontal schematic diagram of the connection between the steel sheet pile and the steel wire rope in the embodiment of the present invention.
- Figure 10 is a schematic plan view of the steel pipe lattice column structure in the embodiment of the present invention.
- Figure 11 is a schematic side view of the steel pipe lattice column structure in the embodiment of the present invention.
- Figure 12 is a top view of the car crane in the embodiment of the present invention.
- the present invention proposes a method for hoisting heavy equipment in nearby unenclosed buildings.
- a method for hoisting heavy equipment in a nearby unclosed building includes:
- the first-level lifting equipment hoists the heavy equipment from the unclosed building to the temporary platform 4, and then the second-level lifting equipment lifts the lifting equipment from the temporary platform to the outside of the building.
- This hoisting method can be applied to the construction where the main subway station is not completely enclosed.
- the maximum mass of a shield machine for a rail transit project is 130t for the front shield and 120t for the middle shield. Hoisting is required.
- the main structure of the receiving end is only completed for about 30m without forming a closed overall structure.
- the depth of the foundation pit is 20m.
- the surrounding side of the main structure of the station is a foundation pit, and there is no building or foundation structure to support.
- the rated lifting loads of the first-level lifting equipment and the second-level lifting equipment are the same or similar, and both meet the lifting safety requirements, the elevation of the station area different.
- the first-level lifting equipment located on the top of the unclosed station uses a crawler crane, and the two crawlers of the crawler crane are located at the two ends of the unclosed building At the top of the well, the track center distance is consistent with the center distance of the longitudinal beams at the top of the end well.
- the crawler crane can be assembled and is convenient for The installation on the top of the building avoids the drawback that the complete lifting equipment cannot reach the station area in a self-propelled manner.
- the top of the unenclosed building is supported by a steel box to support the first-level lifting equipment, and the arrangement of the steel box can buffer and evenly distribute the stress generated by the first-level lifting equipment on the top of the building.
- the second-level lifting equipment is a self-propelled wheeled crane, preferably a 500t truck crane, which not only facilitates the entry of the truck crane and its required lifting accessories, but also facilitates the assembly of the crawler crane; there are 4 truck cranes
- the legs 21 and the four legs 21 are all supported by the square box 18.
- the advantage of the preferred 500 truck crane is that the four outriggers 21 of the truck crane are transmitted in a concentrated load pattern, which facilitates the setting of the force transmission structure and the avoidance of lateral pressure generated by the hoisting load.
- the first-level lifting equipment is preferably a 350t crawler crane 5.
- the two crawlers of the crawler crane 5 are located on the top of the middle of the two end wells of the unclosed building.
- the center distance of the crawler is consistent with the center distance of the longitudinal beams on the top of the station.
- the platform 4 is arranged close to the second-level lifting equipment, so as to provide a certain space for the temporary storage platform and also facilitate the hoisting of the first-level lifting equipment.
- the crawler crane 5 can be assembled and installed on the top of the building.
- the top of the unclosed building is supported by a steel box to support the first-level lifting equipment.
- the installation of the steel box can cushion the stress generated by the first-level lifting equipment on the top of the building.
- the steel box 20 is also a square box. It is located above the longitudinal beams of the main station structure 6 as shown in FIG. 5.
- the steel pipe lattice column structure is used as a vertical force transmission member to reduce the stress of the second-level lifting equipment on the backfill soil through the steel pipe
- the lattice column structure is transferred to the rock below the foundation pit, thereby effectively avoiding the lateral pressure generated by the lifting equipment on the building structure during the hoisting process.
- Each of the steel tube lattice column structure includes at least one steel tube 8, filled with concrete 14, the bottom of the steel tube lattice column structure is provided with a first steel plate 16, and the top of the steel tube lattice column structure is provided with a second steel plate 17, and
- the two adjacent steel pipes 8 in each steel pipe lattice column structure are connected by a connecting piece, and the connecting piece is the second I-beam 15, as shown in Figure 10, there are multiple rows between two adjacent steel pipes 8
- the connecting piece, the steel pipe 8 is filled with concrete, and the cement slurry is injected between the adjacent steel pipes in the steel pipe lattice column structure through the sleeve valve grouting pipe, which is beneficial to improve the strong rigidity of the steel pipe lattice column structure and ensure the reliability of vertical force transmission.
- the steps for setting backfill soil on the side of the unclosed building are as follows:
- a number of first steel plates 16 are set on the bottom of the foundation pit.
- the size of the first steel plate 16 is 1000 ⁇ 1000 ⁇ 20mm.
- Three steel pipes 8 of steel pipe lattice column structure are welded on the surface of the first steel plate 16, adjacent steel pipe grids
- the column structure interval is set according to the set distance;
- the backfilled soil body 2 needs to be rolled after layering.
- the steel pipe lattice column needs to be prevented from being hit during the soil rolling process.
- the displacement of the sandbags near the main structure of the station shall be monitored.
- the position of the station and the force of the hoisting load should be lightly pressed at 6 places close to the main structure of the station to ensure that the main structure of the station 6 is not affected by the side pressure of the backfilled soil; the inner 1m range of the steel sheet piles on both sides should be rolled according to the design requirements.
- a second steel plate 17 is installed on the top of the steel pipe.
- the size of the second steel plate 17 is 1000 ⁇ 1000 ⁇ 20mm, and the second steel plate 17 has a ⁇ 200 concrete pouring hole.
- the steel sheet pile 7 includes a number of Lassen plates interlocked with each other.
- the cross-section of the Lassen plates is U-shaped.
- the interlocked Lassen plates are beneficial to improve the bending rigidity of the steel sheet pile 7.
- Columns connect the Larsen boards on both sides.
- the steel pipe lattice column structure at each location includes three steel pipes 8, which are arranged at three points of an equilateral triangle.
- the three steel pipes 8 are arranged in an equilateral triangle with a center distance of 1.5m.
- the steel pipe lattice column structure includes at least four places.
- the four steel pipe lattice column structures form four rectangular points to be arranged, so that they correspond to the four legs of the lifting equipment such as the car crane 3, which can effectively connect the car crane legs to the foundation. The stress is transferred downward, and the lateral force generated by the lifting equipment is dispersed and transmitted to the rock formation at the bottom of the foundation pit.
- the settlement is monitored in real time during the whole process of hoisting. It is mainly arranged on both sides of the truck crane 3, the two sides of the backfill earthwork 12 and the top of the building, so that the settlement of the main structure 6 of the station can be monitored. Horizontal and horizontal displacement are monitored; Figure 6 shows the schematic diagram of the monitoring point layout. The initial value of the monitoring point is obtained before hoisting, and real-time monitoring is performed during the hoisting process to ensure the safety of hoisting.
- the concrete reinforcement layer 1 After the concrete reinforcement layer 1 is poured, it is maintained according to the technical requirements.
- static pressure grouting is performed through the embedded sleeve grouting valve pipe to improve the compactness of the soil between the lattice steel pipe lattice columns
- the grouting pressure should not be higher than 4bar.
- the shield equipment hoisting starts.
- the 500t truck crane enters the site according to the requirements of the station, installs the counterweight, checks the spreaders and locks, and completes the acceptance work.
- a 350t crawler crane enters the site, and a 500t truck crane will lift it to the top of the station according to its parts for assembly, installation of counterweights, inspection of spreaders and locks, and completion of the acceptance work.
- the 350t crawler crane 5 will hoist and turn over the shield machine parts from the shield hoisting hole 19, and place it on the temporary platform.
- the top of the station is hoisted, the main boom of the crane is rotated, and the shield components are placed on the transfer flatbed to complete the hoisting operation. Repeat the above steps to complete all lifting operations.
- the setting method of the wire rope 10 is as follows:
- the hoisting method provided in this embodiment can be used for hoisting heavy equipment in a building that is not completely enclosed.
- the first-level lifting equipment hoists the heavy equipment to the temporary platform from the inside of the unclosed building, and then the second-level The lifting equipment is hoisted, so there is no need to rely only on a larger lifting equipment for lifting, which reduces the tonnage requirements of the lifting equipment.
- the setting of backfill soil facilitates the entry and departure of the lifting equipment.
- the arrangement of the column structure transmits the hoisting load of the second hoisting equipment to the rock layer at the bottom of the foundation pit, avoiding the adverse effects of the hoisting equipment and the hoisting load on the building's lateral pressure.
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Structural Engineering (AREA)
- Transportation (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
Description
Claims (10)
- 一种近邻未封闭建筑物的重型设备吊装方法,其特征在于,包括:A method for hoisting heavy equipment for nearby unclosed buildings, which is characterized in that it comprises:在未封闭建筑物顶部设置第一级起重设备,未封闭建筑物顶部第一级起重设备一侧设置暂放平台;Install the first-level lifting equipment on the top of the unenclosed building, and set up a temporary platform on the side of the first-level lifting device on the top of the unenclosed building;在未封闭建筑物一侧设置回填土体,在回填土体的顶部设置第二级起重设备,暂放平台设于第一级起重设备与第二级起重设备之间;Set up the backfilled soil on the side of the unclosed building, set the second-level lifting equipment on the top of the backfilled soil, and set the temporary platform between the first-level lifting equipment and the second-level lifting equipment;第一级起重设备从未封闭建筑物内部吊装重型设备至暂放平台,然后通过第二级起重设备将需吊装的重型设备从暂放平台吊装至建筑物外侧。The first-level lifting equipment never closes the inside of the building to hoist heavy equipment to the temporary platform, and then use the second-level lifting equipment to hoist the heavy equipment from the temporary platform to the outside of the building.
- 根据权利要求1所述的一种近邻未封闭建筑物的重型设备吊装方法,其特征在于,所述第一级起重设备与所述第二级起重设备的额定起重荷载相同或相近,且皆满足吊装安全要求,其站位区域标高不同。The method for hoisting heavy equipment near an unenclosed building according to claim 1, wherein the rated lifting loads of the first-level lifting equipment and the second-level lifting equipment are the same or similar, And they all meet the lifting safety requirements, and the elevation of the station area is different.
- 根据权利要求1所述的一种近邻未封闭建筑物的重型设备吊装方法,其特征在于,所述第一级起重设备为履带吊,履带吊的两条履带位于未封闭建筑物两个端头井中间的顶部。The method for hoisting heavy equipment adjacent to an unclosed building according to claim 1, wherein the first-level lifting equipment is a crawler crane, and two crawlers of the crawler crane are located at two ends of the unclosed building. The top of the head in the middle of the well.
- 根据权利要求1所述的一种近邻未封闭建筑物的重型设备吊装方法,其特征在于,所述未封闭建筑物顶部通过钢箱以支撑所述的第一级起重设备。The method for hoisting heavy equipment adjacent to an unclosed building according to claim 1, wherein the top of the unclosed building is supported by a steel box to support the first-level lifting equipment.
- 根据权利要求1所述的一种近邻未封闭建筑物的重型设备吊装方法,其特征在于,所述回填土体内竖向设有若干处钢管格构柱结构。The method for hoisting heavy equipment near an unclosed building according to claim 1, wherein a plurality of steel pipe lattice column structures are vertically arranged in the backfilled soil body.
- 根据权利要求5所述的一种近邻未封闭建筑物的重型设备吊装方法,其特征在于,每一处所述钢管格构柱结构包括至少一根钢管,钢管内填充有混凝土,钢管格构柱结构底部设置第一钢板,钢管格构柱结构顶部设置第二钢板,且每一处钢管格构柱结构中相邻的两根钢管通过连接件连接,相邻的两根钢管之间设有多排连接件。The method for hoisting heavy equipment for nearby unclosed buildings according to claim 5, wherein each of the steel pipe lattice column structure includes at least one steel pipe, the steel pipe is filled with concrete, and the steel pipe lattice column structure The first steel plate is set at the bottom of the structure, the second steel plate is set on the top of the steel pipe lattice column structure, and the two adjacent steel pipes in each steel pipe lattice column structure are connected by connecting pieces, and there are multiple steel pipes between the adjacent two steel pipes.排连接件。 Row connectors.
- 根据权利要求1所述的一种近邻未封闭建筑物的重型设备吊装方法,其特征在于,所述在未封闭建筑物一侧设置回填土体的步骤如下:The method for hoisting heavy equipment adjacent to an unclosed building according to claim 1, wherein the step of setting backfill soil on one side of the unclosed building is as follows:在基坑底面竖向设置钢管格构柱结构的钢管,相邻的钢管格构柱结构间隔按设定距离设置;Vertically install steel pipes of steel pipe lattice column structure on the bottom surface of the foundation pit, and set the interval between adjacent steel pipe lattice columns according to the set distance;在基坑内未封闭建筑物侧壁的两侧各设置一排钢板桩,两排钢板桩间隔按设定距离设置;Set up a row of steel sheet piles on both sides of the side wall of the unclosed building in the foundation pit, and set the interval between the two rows of steel sheet piles according to the set distance;两排钢板桩之间通过设置钢丝绳进行连接,钢丝绳分层设置,在钢丝绳分层 设置的过程中,逐渐在两排钢板桩之间回填土体;The two rows of steel sheet piles are connected by setting steel wire ropes, and the steel wires are arranged in layers. During the layered installation of the steel wire ropes, soil is gradually backfilled between the two rows of steel sheet piles;土体回填至钢管顶部标高一致时,在钢管顶部设置第二钢板,在第二钢板及回填土体顶部铺设钢板网并浇筑混凝土加固层,同时向钢管格构柱的钢管内灌注混凝土。When the soil is backfilled to the same elevation on the top of the steel pipe, a second steel plate is installed on the top of the steel pipe, expanded steel mesh is laid on the top of the second steel plate and the backfilled soil, and a concrete reinforcement layer is poured, while concrete is poured into the steel pipe of the steel pipe lattice column.
- 根据权利要求7所述的一种近邻未封闭建筑物的重型设备吊装方法,其特征在于,所述钢丝绳设置方法如下:The method for hoisting heavy equipment for nearby unclosed buildings according to claim 7, wherein the method for setting the steel wire rope is as follows:在一排钢板桩的外侧安放工字钢,钢丝绳绕过该工字钢的端部用卡扣固定,钢丝绳穿过钢板桩后到另一排钢板桩外侧的工字钢;Place the I-beam on the outer side of a row of steel sheet piles, the steel wire rope will go around the end of the I-beam and fasten it with a buckle.通过紧绳器拉紧钢丝绳后再用卡扣固定钢丝绳的另一端部。After the wire rope is tightened by the rope tightener, the other end of the wire rope is fixed with a buckle.
- 根据权利要求7所述的一种近邻未封闭建筑物的重型设备吊装方法,其特征在于,吊装施工完成后剪断钢丝绳,对回填土体两侧的钢板桩进行回收。The method for hoisting heavy equipment for nearby unclosed buildings according to claim 7, characterized in that the steel wire ropes are cut after the hoisting construction is completed, and the steel sheet piles on both sides of the backfilled soil are recovered.
- 根据权利要求1所述的一种近邻未封闭建筑物的重型设备吊装方法,其特征在于,所述回填土体的高度在满足第二级起重设备工作要求的前提下取最小值。The method for hoisting heavy equipment of a nearby unclosed building according to claim 1, wherein the height of the backfilled soil is taken to the minimum value on the premise that the working requirements of the second-level lifting equipment are met.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
AU2019453220A AU2019453220B2 (en) | 2019-07-01 | 2019-10-11 | Hosting method for heavy apparatus close to unsealed building |
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910585294.1A CN110329925B (en) | 2019-07-01 | 2019-07-01 | Heavy equipment hoisting method for neighboring unsealed building |
CN201910585294.1 | 2019-07-01 |
Publications (1)
Publication Number | Publication Date |
---|---|
WO2021000443A1 true WO2021000443A1 (en) | 2021-01-07 |
Family
ID=68144772
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
PCT/CN2019/110663 WO2021000443A1 (en) | 2019-07-01 | 2019-10-11 | Hosting method for heavy apparatus close to unsealed building |
Country Status (3)
Country | Link |
---|---|
CN (1) | CN110329925B (en) |
AU (1) | AU2019453220B2 (en) |
WO (1) | WO2021000443A1 (en) |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2000257266A (en) * | 1999-03-05 | 2000-09-19 | Taisei Corp | Building skeleton constructing method |
CN101363224A (en) * | 2008-09-05 | 2009-02-11 | 上海隧道工程股份有限公司 | Movable foundation pit support system and construction method |
CN105967075A (en) * | 2016-05-30 | 2016-09-28 | 中建五局第三建设有限公司 | Construction method of vertical transportation system at hundred-meter deep mining pit large-drop steep cliff |
CN108978644A (en) * | 2018-07-28 | 2018-12-11 | 江苏地基工程有限公司 | Energy saving and environment friendly bored pile construction method |
US10202734B2 (en) * | 2016-12-21 | 2019-02-12 | John Rene Spronken | Prefabricated resuable concrete pedestal element |
CN109534189A (en) * | 2018-11-14 | 2019-03-29 | 中建局集团第建筑有限公司 | A kind of assembled general frame cast-in-place core wall structure lifting construction method |
CN109723062A (en) * | 2019-01-18 | 2019-05-07 | 济南轨道交通集团有限公司 | Heave-load device hanging apparatus and hanging method based on proximity deep foundation pit construction environment |
Family Cites Families (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE2931421C2 (en) * | 1979-08-02 | 1981-11-26 | Reich Maschinen GmbH, 7911 Nersingen | Jib tower crane with extendable trolley jib |
-
2019
- 2019-07-01 CN CN201910585294.1A patent/CN110329925B/en active Active
- 2019-10-11 AU AU2019453220A patent/AU2019453220B2/en active Active
- 2019-10-11 WO PCT/CN2019/110663 patent/WO2021000443A1/en active Application Filing
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2000257266A (en) * | 1999-03-05 | 2000-09-19 | Taisei Corp | Building skeleton constructing method |
CN101363224A (en) * | 2008-09-05 | 2009-02-11 | 上海隧道工程股份有限公司 | Movable foundation pit support system and construction method |
CN105967075A (en) * | 2016-05-30 | 2016-09-28 | 中建五局第三建设有限公司 | Construction method of vertical transportation system at hundred-meter deep mining pit large-drop steep cliff |
US10202734B2 (en) * | 2016-12-21 | 2019-02-12 | John Rene Spronken | Prefabricated resuable concrete pedestal element |
CN108978644A (en) * | 2018-07-28 | 2018-12-11 | 江苏地基工程有限公司 | Energy saving and environment friendly bored pile construction method |
CN109534189A (en) * | 2018-11-14 | 2019-03-29 | 中建局集团第建筑有限公司 | A kind of assembled general frame cast-in-place core wall structure lifting construction method |
CN109723062A (en) * | 2019-01-18 | 2019-05-07 | 济南轨道交通集团有限公司 | Heave-load device hanging apparatus and hanging method based on proximity deep foundation pit construction environment |
Also Published As
Publication number | Publication date |
---|---|
AU2019453220A1 (en) | 2021-09-09 |
CN110329925B (en) | 2020-07-24 |
CN110329925A (en) | 2019-10-15 |
AU2019453220B2 (en) | 2023-02-02 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110306524B (en) | Foundation reinforcing structure and method for hoisting heavy equipment close to unsealed building | |
CN105155558A (en) | Combined retaining structure and construction method thereof | |
WO2022016720A1 (en) | Temporary passage construction method employing support structure in deep foundation pit | |
CN107806101B (en) | Construction method for strip foundation pit cast-in-place concrete diagonal bracing prefabricated connecting beam | |
CN104294769A (en) | Built abutment structure reinforced through combination of pile supplementing and abutment cap enlarging and construction method | |
CN112854228A (en) | Confined space foundation pit earth excavation construction method | |
CN209585054U (en) | One kind is quickly met an urgent need diagonal brace for salvage of foundation pits | |
CN108330963A (en) | A kind of constructing device for inside soil body existing pile foundation pile extension | |
CN110241863B (en) | Soft soil foundation pit excavation process pipe gallery deformation control device and control method thereof | |
CN111997043A (en) | Segmented reinforcement cage and diaphragm wall construction method under low-clearance high-voltage line | |
CN111218938A (en) | Excavation construction method for foundation pit above existing tunnel | |
WO2021000443A1 (en) | Hosting method for heavy apparatus close to unsealed building | |
CN111305182A (en) | Soft foundation reinforcement construction method | |
CN206616602U (en) | A kind of outdoor construction elevator strengthening of foundation device | |
CN114525808B (en) | Deep foundation pit edge gantry crane ground beam construction method | |
CN114319432B (en) | Construction process of semi-underground subway station and semi-underground subway station | |
CN109555129A (en) | One kind is quickly met an urgent need diagonal brace and construction method for salvage of foundation pits | |
CN114991165A (en) | Construction method for subway deep foundation pit adjacent to railway business line | |
CN204940310U (en) | A kind of combination retaining structure | |
CN212656218U (en) | Heavy pile machine load underpinning structure | |
CN106836325A (en) | A kind of outdoor construction elevator strengthening of foundation device | |
CN211621667U (en) | Tubular pile cushion cap girder steel rail mounted tower machine walking foundation structure | |
CN113090066A (en) | Construction method for newly added entrances and exits of existing buildings and elevator shaft | |
CN112323816A (en) | Unloading type combined retaining structure and construction method thereof | |
CN219862862U (en) | Tower crane foundation construction structure suitable for geological conditions of silt layer |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
121 | Ep: the epo has been informed by wipo that ep was designated in this application |
Ref document number: 19936097 Country of ref document: EP Kind code of ref document: A1 |
|
ENP | Entry into the national phase |
Ref document number: 2019453220 Country of ref document: AU Date of ref document: 20191011 Kind code of ref document: A |
|
NENP | Non-entry into the national phase |
Ref country code: DE |
|
122 | Ep: pct application non-entry in european phase |
Ref document number: 19936097 Country of ref document: EP Kind code of ref document: A1 |
|
122 | Ep: pct application non-entry in european phase |
Ref document number: 19936097 Country of ref document: EP Kind code of ref document: A1 |
|
32PN | Ep: public notification in the ep bulletin as address of the adressee cannot be established |
Free format text: NOTING OF LOSS OF RIGHTS PURSUANT TO RULE 112(1) EPC (EPO FORM 1205 DATED 12.10.22) |
|
122 | Ep: pct application non-entry in european phase |
Ref document number: 19936097 Country of ref document: EP Kind code of ref document: A1 |