CN109534189A - Hoisting construction method for cast-in-situ core tube structure of assembled integral frame - Google Patents
Hoisting construction method for cast-in-situ core tube structure of assembled integral frame Download PDFInfo
- Publication number
- CN109534189A CN109534189A CN201811354101.3A CN201811354101A CN109534189A CN 109534189 A CN109534189 A CN 109534189A CN 201811354101 A CN201811354101 A CN 201811354101A CN 109534189 A CN109534189 A CN 109534189A
- Authority
- CN
- China
- Prior art keywords
- tower crane
- grouting
- construction method
- construction
- tower
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 62
- 238000011065 in-situ storage Methods 0.000 title description 2
- 239000011229 interlayer Substances 0.000 claims description 17
- 239000008267 milk Substances 0.000 claims description 8
- 210000004080 milk Anatomy 0.000 claims description 8
- 235000013336 milk Nutrition 0.000 claims description 8
- 239000010410 layer Substances 0.000 claims description 7
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 7
- 241001310793 Podium Species 0.000 claims description 5
- 238000012795 verification Methods 0.000 claims description 3
- 230000008901 benefit Effects 0.000 abstract description 10
- 238000000034 method Methods 0.000 abstract description 8
- 230000008569 process Effects 0.000 abstract description 3
- 238000009434 installation Methods 0.000 description 8
- 238000010586 diagram Methods 0.000 description 5
- 230000003014 reinforcing effect Effects 0.000 description 4
- 238000009416 shuttering Methods 0.000 description 4
- 239000004035 construction material Substances 0.000 description 3
- 239000002131 composite material Substances 0.000 description 2
- 239000000839 emulsion Substances 0.000 description 2
- 238000012986 modification Methods 0.000 description 2
- 230000004048 modification Effects 0.000 description 2
- 239000000178 monomer Substances 0.000 description 2
- 238000005457 optimization Methods 0.000 description 2
- 238000004873 anchoring Methods 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000009435 building construction Methods 0.000 description 1
- 230000009194 climbing Effects 0.000 description 1
- 230000015271 coagulation Effects 0.000 description 1
- 238000005345 coagulation Methods 0.000 description 1
- 238000012937 correction Methods 0.000 description 1
- 230000001186 cumulative effect Effects 0.000 description 1
- 238000013461 design Methods 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 230000010354 integration Effects 0.000 description 1
- 238000012544 monitoring process Methods 0.000 description 1
- 230000008439 repair process Effects 0.000 description 1
- 238000011160 research Methods 0.000 description 1
- 230000009466 transformation Effects 0.000 description 1
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C23/00—Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
- B66C23/62—Constructional features or details
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C13/00—Other constructional features or details
- B66C13/04—Auxiliary devices for controlling movements of suspended loads, or preventing cable slack
- B66C13/08—Auxiliary devices for controlling movements of suspended loads, or preventing cable slack for depositing loads in desired attitudes or positions
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The invention relates to the technical field of construction of an assembled integral frame, and discloses a hoisting construction method for a cast-in-place core tube structure of the assembled integral frame, which comprises the following steps: determining the number and the type of the tower cranes according to the weight and the position of the heaviest prefabricated part and the initial position of the tower crane; determining the final position of the tower crane according to the building plan, the building structure type and the basement structure; comparing and checking performance parameters of the tower crane according to the maximum weight of the prefabricated part and the maximum weight appearing in construction; arranging a tower crane; determining the attachment form of the tower crane, wherein the attachment form comprises that the tower crane is attached to a structural column, the tower crane is attached to the side of a frame beam, and the tower crane is attached to the top of the frame beam; the comprehensive consideration such as the operation radius, the maximum prefabricated part lifting capacity, the tower crane position and the attachment form is combined in the model selection process, and the method has the advantages of high tower crane efficiency and high balance degree between hoisting operation areas.
Description
Technical field
The present invention relates to assembled general frame technical field of construction, more specifically, it relates to which a kind of assembled is whole
Frame cast-in-place core wall structure lifting construction method.
Background technique
With the propulsion that construction industry modernizes, traditional architecture mode is gradually no longer complies with the growth requirement in epoch, assembled
Building is becoming a new emphasis of construction industry Transformation Development.Medium-and-large-sized prefabricated components and the installation Mission Day of equipment are cumulative
It is more, construction site tower crane using extremely widespread.Since tower crane has, construction efficiency is high, boundary of works area is wide, effective lifting height
The advantages that big, the construction and installation for building its assembly concrete provide great convenience.
But need the operating radius in view of tower crane using tower crane in the construction process, maximum prefabricated components lifting capacity with
And it is some between group's tower, if disregarding calculation above-mentioned factor, will limit tower crane service efficiency and lifting operation region it
Between equilibrium degree.
Summary of the invention
Problem in view of the prior art, the present invention provide a kind of cast-in-place core wall structure heavy dressing of assembled general frame
Work method has the advantages that tower crane is high-efficient, the equilibrium degree between lifting operation region is high.
To achieve the above object, the present invention provides the following technical scheme that
A kind of assembled general frame cast-in-place core wall structure lifting construction method, includes the following steps:
Step S1: the rough location of the most heavy prefabricated components weight of lifting, position and tower crane as needed determines the number of tower crane
Amount and type;
Step S2: the final position of tower crane is determined according to architectural plan, building structure pattern and basement structure;
Step S3: joined according to the performance of the maximum weight comparison verification tower crane occurred in the maximum weight and construction of prefabricated components
Number retains performance parameter the surplus of setting;
Step S4: arrangement tower crane, every main building configure two tower cranes, and the working range of tower crane is made to cover main building and podium;
Step S5: determining the attached form of tower crane, attached form include tower crane attachment in structural column, tower crane attachment in Vierendeel girder
Side and tower crane attachment are in frame back.
Through the above technical solutions, combining operating radius, maximum prefabricated components lifting capacity, tower crane position during type selecting
And attached form etc. comprehensively considers, to overcome the inefficiency of simple-arranged tower crane, lifting operation region in the prior art
Between it is unbalanced the problems such as, have the advantages that tower crane is high-efficient, the equilibrium degree between lifting operation region is high.
Further, step S4 further include: main building is divided into two flowing water sections by two tower cranes, wherein a tower crane lifts structure
Part, another tower crane lifting template and laminated floor slab.
Through the above technical solutions, a tower crane is responsible for flowing water section lifting component, another tower crane is responsible for shuttering supporting and is taken
It constructs if being bound with laminated floor slab reinforcing bar, avoids work holdup phenomenon.
Further, step S5 further include:
Step S51: determine that grouting form, grouting form include when layer grouting and interlayer grouting;
Step S52: matching grouting form and attached form, then the grouting form being in the milk using interlayer and tower crane attachment are matched in frame
It sets a roof beam in place the attached form on top.
Through the above technical solutions, interlayer grouting is as progress key node but can be interspersed in main structure construction,
Do not influence the whole duration, and there is no crossings on different level to construct, tower crane attachment adhere in the attached form of frame back stress by
Entire Core Walls Structure floor system undertakes, and prefabricated post and framed bent are subjected only to minimum part power.
Further, further include step S6: setting circumferential highway, the circumferential highway for road in the field of construction area
Surround annex.
Through the above technical solutions, making annex two sides respectively has a road, the shape to block up when a large amount of components are marched into the arena is avoided
Condition.
Further, the gradient of the circumferential highway is less than the road grade set, the turning half of the circumferential highway
Diameter is less than the road radius set.
Through the above technical solutions, avoiding the case where appearance of separate unit tower crane can not unload.
Further, stockyard is provided with by the circumferential highway, the work for around main building and being located at tower crane is arranged in stockyard
In region.
Through the above technical solutions, tower crane is avoided to there is lifting blind area.
Further, the stockyard is located at by the tower crane, and close to the tower crane.
Through the above technical solutions, lifting covering is able to satisfy the direct lifting nothing of most heavy prefabricated components and all kinds of construction materials
The demand that need to be transported.
Compared with prior art, the beneficial effects of the present invention are: combining operating radius, maximum prefabricated structure during type selecting
Part lifting capacity, tower crane position and attached form etc. comprehensively consider, and match grouting form and attached form, then match using interlayer
The grouting form and tower crane attachment of grouting are in the attached form of frame back.
Interlayer grouting is as progress key node but can be interspersed in main structure construction, does not influence the whole duration, and
There is no crossings on different level construction, tower crane attachment adheres to stress by entire Core Walls Structure floor system in the attached form of frame back
It undertakes, prefabricated post and framed bent are subjected only to minimum part power.Overcome the inefficiency of simple-arranged tower crane, lifting in the prior art
The problems such as unbalanced between operating area, has the advantages that tower crane is high-efficient, the equilibrium degree between lifting operation region is high.
Detailed description of the invention
Fig. 1 is the method flow diagram of step of embodiment of the present invention S1 to step S6;
Fig. 2 is the method flow diagram of step of embodiment of the present invention S51 to step S52;
Fig. 3 is the prefabricated components information table of the embodiment of the present invention;
Fig. 4 is the prefabricated post floor plan of the embodiment of the present invention;
Fig. 5 is the precast beam floor plan of the embodiment of the present invention;
Fig. 6 is the tower crane model table of the embodiment of the present invention;
Fig. 7 is the plane layout of tower crane schematic diagram of the embodiment of the present invention;
Fig. 8 is the tower crane attachment schematic diagram of the embodiment of the present invention;
Fig. 9 is the interlayer grouting schematic diagram of the embodiment of the present invention.
Specific embodiment
With reference to the accompanying drawings and examples, the present invention will be described in detail.
Embodiment
A kind of assembled general frame cast-in-place core wall structure lifting construction method, as shown in Figure 1, including following step
It is rapid:
Step S1: the rough location of the most heavy prefabricated components weight of lifting, position and tower crane as needed determines the number of tower crane
Amount and type;
Step S2: the final position of tower crane is determined according to architectural plan, building structure pattern and basement structure;
Step S3: joined according to the performance of the maximum weight comparison verification tower crane occurred in the maximum weight and construction of prefabricated components
Number retains performance parameter the surplus of setting;
Step S4: arrangement tower crane, every main building configure two tower cranes, and the working range of tower crane is made to cover main building and podium.Step
Rapid S4 further include: main building is divided into two flowing water sections by two tower cranes, wherein a tower crane lifting components, another tower crane lifts mould
Plate and laminated floor slab.One tower crane is responsible for flowing water section lifting component, and another tower crane is responsible for shuttering supporting and is set up and laminated floor slab
Reinforcing bar binding construction, avoids work holdup phenomenon.
Step S5: determining the attached form of tower crane, attached form include tower crane attachment in structural column, tower crane attachment in frame
Beam side and tower crane attachment are in frame back.Operating radius, maximum prefabricated components lifting capacity, tower crane are combined during type selecting
Position and attached form etc. comprehensively consider, to overcome the inefficiency of simple-arranged tower crane, lifting operation in the prior art
The problems such as unbalanced between region, has the advantages that tower crane is high-efficient, the equilibrium degree between lifting operation region is high.Such as Fig. 2 institute
Show, step S5 further includes step S51 and step S52.Step S51: determining grouting form, grouting form include when layer grouting and
Interlayer grouting.Step S52: matching grouting form and attached form, then match attached using the grouting form and tower crane of interlayer grouting
In the attached form of frame back.Interlayer grouting is as progress key node but can be interspersed in main structure construction, no
The whole duration is influenced, and there is no crossings on different level to construct, tower crane attachment adheres to stress by whole in the attached form of frame back
A Core Walls Structure floor system undertakes, and prefabricated post and framed bent are subjected only to minimum part power.
Step S6: circumferential highway is set by road in the field of construction area, circumferential highway surrounds annex.Make annex two sides
Respectively there is a road, avoids the situation to block up when a large amount of components are marched into the arena.The gradient of circumferential highway is less than the road slope set
Degree, the turning radius of circumferential highway are less than the road radius set.Avoid the case where appearance of separate unit tower crane can not unload.Ring
Stockyard is provided with by shape road, stockyard is arranged in around main building and is located in the working region of tower crane.Tower crane is avoided to there is lifting
Blind area.Stockyard is located at by tower crane, and close to tower crane.Lifting covering is able to satisfy the direct of most heavy prefabricated components and all kinds of construction materials
Demand of the lifting without transhipment.
In the present embodiment by taking the second general headquarters, China Electronics Scientific Research Building as an example, which is located in listing Pudong New District Zhangjiang
Area mainly includes two layers of underground garage, the building 1#, the building 2#, the building 3#.The building 1# totally 11 floor, 48.25 meters of building height, monomer pre-emulsion rate
It is 39.16%;The building 2# totally 12 floor, building height is 48.45 meters high, and monomer pre-emulsion rate is 41.36%, and two main buildings are that assembly is whole
Formula frame-cast-in-place core wall structure;The building 3# totally 2 floor, 10.5 meters of building height, be cast-in-place framework.1# prefabricated components information,
2# prefabricated components information is as shown in Figure 3.
In tower crane type selecting, for assembled coagulation construction, the type selecting of vertical transport equipment tower crane is a Xiang Zhiguan
Important work, reasonable tower crane type selecting can effectively ensure that prefabricated components construction and installation efficiency.Therefore, it should be tied during type selecting
It closes engineering project actual conditions, operating radius, maximum prefabricated components lifting capacity, economical etc. to comprehensively consider, to realize tower crane
Optimal selection.
More than two three floor of main building of this engineering be the cast-in-place core wall structure of prefabricated integral frame-, mainly have prefabricated post,
Composite beam, superimposed sheet, wherein between 7 ~ 9 tons, most heavy component reaches 9.25 tons for prefabricated post, composite beam average weight.Cause
This, tower crane type selecting and arrangement also need to consider following factor: (1) substantially according to most heavy prefabricated components weight, position and tower crane
Installation site carries out tower crane type selecting, and model should be able to meet the most lifting requirements of reconstruct part and the lifting at amplitude peak and want
It asks;(2) according to the places situations such as architectural plan, building structure pattern, basement structure, the transit route of component and construction
Deployment scenario finally determines the installation site of tower crane.Tower crane installation site should be able to cover whole construction sites, and lean on as far as possible
The nearly big region of lifting capacity;In view of group towers work influences, tower crane correlation and brachium should be limited, and undertake each tower crane
Lifting operation region it is substantially balanced;(3) because there are the plane transportations of a large amount of prefabricated components, it is necessary to supply line in field of making rational planning for
Road controls haul road grade and turning radius;(4) according to lifting possible in the maximum weight of each component, construction
Maximum weight and position and the comparison of tower crane lifting performance verify, and there are suitable surpluses, to prevent appearing in conceptual design not
The exception of consideration.
Below by taking the building this engineering 1# as an example, prefabricated components are briefly statisticallyd analyze:
As shown in figure 4, the building 1# prefabricated post average weight is 7 ~ 9 tons, most heavy prefabricated post reaches 9.25 tons at 3 ~ 6 layers, in 7,8,
13,14 axis, 9,10,11,12 axis prefabricated post average weights are 7 ~ 8 tons.As shown in figure 5, most heavy precast main beam be distributed in A, D, 7,
14 axis, average weight are 8 ~ 9 tons, are most weighed to 9.15 tons;Secondary beam average weight is 6 tons.Superimposed sheet average weight is 2.2 tons.
In conclusion integration project actual demand and tower crane Type Selection Principle, this engineering tower crane model are as shown in Figure 6.
The arrangement of tower crane should be according to construction site construction environment and the comprehensive determination of economic condition, under normal circumstances, assembled
The arrangement principle of construction site tower crane should follow following basic principle: (1) meeting the needs for itself climbing and adhering to;(2)
Lifting covering should be able to meet the lifting demand of most heavy prefabricated components and all kinds of construction materials, and should be ensured that tower crane and stack pre-
The place of component processed is close to each other;(3) avoid the presence of lifting blind area;(4) comprehensively consider tower crane demolishing process, while should not influence
The construction of proximity structure avoids each engineering construction installation progress from interacting.
This engineering tower crane plan view is as shown in Figure 7.By Fig. 7 it can be seen that every main building is configured with Liang Taita
It hangs, podium is whole all in tower crane lifting range, can carry out podium construction while ensure that high building construction.According to this engineering
Main building is divided into two flowing water sections by fabricated construction deployment, two tower cranes, i.e. a tower crane is responsible for left side flowing water section component and is hung
Dress, the shuttering supporting that another tower crane is responsible for right side are set up to bind with laminated floor slab reinforcing bar and construct, and work holdup phenomenon is avoided.Together
When, road arrangement is circumferential highway in field, and stockyard is arranged near main building, while in tower crane covering surface.It both avoids in this way
The situation that a large amount of components block up when marching into the arena also avoids the case where appearance of separate unit tower crane can not unload.
The comparison of tower crane attachment anchoring and scheme are selected.The attached form of tower crane is as shown in Figure 8, comprising: tower crane attachment in
Structural column, tower crane attachment are in Vierendeel girder side and tower crane attachment in frame back.
The comparison of tower crane attachment form is as follows: (1) the first tower crane attachment in structural column form is made in cast-in-place structural
With a kind of attached form the most universal.(2) second of tower crane attachment are the optimization based on the first in Vierendeel girder side form, excellent
Point has cantilevered structure in structural column, but this engineering main building outermost in avoiding drawknot, this attached form need to be in overhanging secondary beam
Upper indwelling construction joint has certain influence to cantilevered structure, at the same the later period need to spend it is more manually and the time is to constructing herein
Seam is repaired.(3) the third tower crane attachment is the optimization based on second in frame back, advantage in avoiding drawknot in
Structural column, while the problem of avoid the indwelling construction joint at cantilevered structure.
The ratio choosing of tower crane attachment form and grouting form are close not in fabricated construction in the work of tower crane attachment formal character
It can divide, i.e., live grouting form determines tower crane attachment anchor type.
Grouting is divided into following two kinds of forms in the selection work of grouting form: when layer grouting is in the milk with interlayer.When layer is in the milk
It is in the milk immediately after the completion of prefabricated post lifts, the advantages of such mode is that structural column is connect with floor plates and more may be used
It leans on, certain upper load can be carried.Disadvantage is that grouting construction is the key of progress monitoring during main structure construction
Node exists simultaneously interchange operation, there is some potential safety problems.Interlayer grouting is i.e. to pre- before shuttering supporting framed bent is removed
Cylinder processed carries out grouting construction, as shown in Figure 9.The advantages of such mode, is, although grouting construction is as progress key node
But it can be interspersed in main structure construction, as two-level node even three-level node, not influence the whole duration, and there is no vertical
Body crossed construction;The disadvantage is that, reinforcing bar and cushion block are only leaned in the connection of column and substructure before grouting construction, top is most of
Load is supported by supporting row frame.The construction of final choice interlayer grouting.
The grouting form based on interlayer grouting is again to three kinds of attached forms of tower crane in the selection work of tower crane attachment form
It carries out than choosing.The first attached form, when carrying out tower crane attachment, in-situ precast column is not in the milk, therefore, tower crane attachment
In there are biggish security risks in the prefabricated post not being in the milk;Second of attached form, need to overhanging secondary beam on indwelling construction joint,
There is certain influence to cantilevered structure, while the later period needs to spend and more manually repair with the time to construction joint herein;The
Three kinds of attached forms, attachment stress are undertaken by entire Core Walls Structure floor system, and prefabricated post and framed bent are subjected only to minimum part power,
The security risk for avoiding the first attached form has also evaded influence of second of attached form to cantilevered structure.Therefore,
In conjunction with this project actual conditions, final choice tower crane attachment is in the construction of frame back.
Tower crane plays an important role during prefabricated concrete structure prefabricated part hanging, and prefabricated components are main
Lifting, installation, correction rely on tower crane completion, therefore, the type selecting of tower crane, arrangement and adhere to the selection of anchor type and directly affect
The construction deployment and construction speed of entire project.Operating radius, maximum prefabricated components lifting capacity, tower are combined during type selecting
It hangs position and attached form etc. to comprehensively consider, matches grouting form and attached form, then match the grouting being in the milk using interlayer
Form and tower crane attachment are in the attached form of frame back.Interlayer grouting is as progress key node but can be interspersed in main body knot
In structure construction, the whole duration is not influenced, and there is no crossings on different level to construct, tower crane attachment is attached in the attached form of frame back
Stress undertaken by entire Core Walls Structure floor system, prefabricated post and framed bent are subjected only to minimum part power.Overcome in the prior art
The problems such as unbalanced between the inefficiency of simple-arranged tower crane, lifting operation region, have that tower crane is high-efficient, lifting operation area
The high advantage of equilibrium degree between domain.
The above is only a preferred embodiment of the present invention, protection scope of the present invention is not limited merely to above-mentioned implementation
Example, all technical solutions belonged under thinking of the present invention all belong to the scope of protection of the present invention.It should be pointed out that for the art
Those of ordinary skill for, several improvements and modifications without departing from the principles of the present invention, these improvements and modifications
It should be regarded as protection scope of the present invention.
Claims (7)
1. a kind of assembled general frame cast-in-place core wall structure lifting construction method, which comprises the steps of:
Step S1: the rough location of the most heavy prefabricated components weight of lifting, position and tower crane as needed determines the number of tower crane
Amount and type;
Step S2: the final position of tower crane is determined according to architectural plan, building structure pattern and basement structure;
Step S3: joined according to the performance of the maximum weight comparison verification tower crane occurred in the maximum weight and construction of prefabricated components
Number retains performance parameter the surplus of setting;
Step S4: arrangement tower crane, every main building configure two tower cranes, and the working range of tower crane is made to cover main building and podium;
Step S5: determining the attached form of tower crane, attached form include tower crane attachment in structural column, tower crane attachment in Vierendeel girder
Side and tower crane attachment are in frame back.
2. assembled general frame cast-in-place core wall structure lifting construction method according to claim 1, feature exist
In step S4 further include: main building is divided into two flowing water sections by two tower cranes, wherein a tower crane lifting components, another tower crane
Lift template and laminated floor slab.
3. assembled general frame cast-in-place core wall structure lifting construction method according to claim 1, feature exist
In step S5 further include:
Step S51: determine that grouting form, grouting form include when layer grouting and interlayer grouting;
Step S52: matching grouting form and attached form, then the grouting form being in the milk using interlayer and tower crane attachment are matched in frame
It sets a roof beam in place the attached form on top.
4. assembled general frame cast-in-place core wall structure lifting construction method according to claim 1, feature exist
In further including step S6: road is set as circumferential highway in the field by construction area, and the circumferential highway surrounds annex.
5. assembled general frame cast-in-place core wall structure lifting construction method according to claim 4, feature exist
In the gradient of, the circumferential highway it is less than the road grade set, the turning radius of the circumferential highway, which is less than, to be set
Road radius.
6. assembled general frame cast-in-place core wall structure lifting construction method according to claim 5, feature exist
In being provided with stockyard by the circumferential highway, stockyard is arranged in around main building and is located in the working region of tower crane.
7. assembled general frame cast-in-place core wall structure lifting construction method according to claim 6, feature exist
In the stockyard is located at by the tower crane, and close to the tower crane.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811354101.3A CN109534189A (en) | 2018-11-14 | 2018-11-14 | Hoisting construction method for cast-in-situ core tube structure of assembled integral frame |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811354101.3A CN109534189A (en) | 2018-11-14 | 2018-11-14 | Hoisting construction method for cast-in-situ core tube structure of assembled integral frame |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109534189A true CN109534189A (en) | 2019-03-29 |
Family
ID=65847387
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811354101.3A Pending CN109534189A (en) | 2018-11-14 | 2018-11-14 | Hoisting construction method for cast-in-situ core tube structure of assembled integral frame |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109534189A (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110407104A (en) * | 2019-07-26 | 2019-11-05 | 五冶集团上海有限公司 | The accurate merogenesis hanging method of steel column based on BIM |
WO2021000443A1 (en) * | 2019-07-01 | 2021-01-07 | 济南轨道交通集团有限公司 | Hosting method for heavy apparatus close to unsealed building |
CN112561487A (en) * | 2020-12-21 | 2021-03-26 | 广联达科技股份有限公司 | Method, device and equipment for calculating construction progress and readable storage medium |
CN113445741A (en) * | 2021-07-08 | 2021-09-28 | 江苏沪宁钢机股份有限公司 | Half-floor tower suspended ceiling construction method |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104746884A (en) * | 2015-04-10 | 2015-07-01 | 华东建筑设计研究院有限公司 | Method for hoisting prefabricated parts of assembled building |
CN206267309U (en) * | 2016-12-15 | 2017-06-20 | 北京智慧云建科技有限公司 | A kind of assembled steel concrete frame core wall structure system |
CN106986275A (en) * | 2017-03-13 | 2017-07-28 | 同济大学 | A kind of assembled architecture plane layout of tower crane and selection method based on BIM |
CN107165421A (en) * | 2017-06-12 | 2017-09-15 | 江苏建科建设监理有限公司 | A kind of construction method of concrete assembled building |
CN107386660A (en) * | 2017-08-02 | 2017-11-24 | 中国十七冶集团有限公司 | Tower crane system in prefabricated concrete structure construction based on BIM technology |
CN107476583A (en) * | 2017-08-18 | 2017-12-15 | 国网上海市电力公司 | A kind of concrete assembled building builds construction method |
-
2018
- 2018-11-14 CN CN201811354101.3A patent/CN109534189A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104746884A (en) * | 2015-04-10 | 2015-07-01 | 华东建筑设计研究院有限公司 | Method for hoisting prefabricated parts of assembled building |
CN206267309U (en) * | 2016-12-15 | 2017-06-20 | 北京智慧云建科技有限公司 | A kind of assembled steel concrete frame core wall structure system |
CN106986275A (en) * | 2017-03-13 | 2017-07-28 | 同济大学 | A kind of assembled architecture plane layout of tower crane and selection method based on BIM |
CN107165421A (en) * | 2017-06-12 | 2017-09-15 | 江苏建科建设监理有限公司 | A kind of construction method of concrete assembled building |
CN107386660A (en) * | 2017-08-02 | 2017-11-24 | 中国十七冶集团有限公司 | Tower crane system in prefabricated concrete structure construction based on BIM technology |
CN107476583A (en) * | 2017-08-18 | 2017-12-15 | 国网上海市电力公司 | A kind of concrete assembled building builds construction method |
Non-Patent Citations (1)
Title |
---|
唐翔等: "塔式起重机在装配整体式框架-现浇核心筒结构施工中的应用", 《建筑施工》 * |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2021000443A1 (en) * | 2019-07-01 | 2021-01-07 | 济南轨道交通集团有限公司 | Hosting method for heavy apparatus close to unsealed building |
CN110407104A (en) * | 2019-07-26 | 2019-11-05 | 五冶集团上海有限公司 | The accurate merogenesis hanging method of steel column based on BIM |
CN112561487A (en) * | 2020-12-21 | 2021-03-26 | 广联达科技股份有限公司 | Method, device and equipment for calculating construction progress and readable storage medium |
CN112561487B (en) * | 2020-12-21 | 2024-01-23 | 广联达科技股份有限公司 | Method, device and equipment for calculating construction progress and readable storage medium |
CN113445741A (en) * | 2021-07-08 | 2021-09-28 | 江苏沪宁钢机股份有限公司 | Half-floor tower suspended ceiling construction method |
CN113445741B (en) * | 2021-07-08 | 2023-02-28 | 江苏沪宁钢机股份有限公司 | Half-floor tower suspended ceiling construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109534189A (en) | Hoisting construction method for cast-in-situ core tube structure of assembled integral frame | |
CN106894639B (en) | The hanging reverse construction method of installation of steel construction under a kind of | |
CN112900692B (en) | Large-span special-shaped steel structure building, supporting device thereof and construction method | |
CN102535845A (en) | Construction method of bearing frame of corridor structure | |
CN103291076A (en) | Multilayer steel truss fragmented reverse hoisting construction method in arc-shaped frame | |
CN114232805B (en) | Construction method of ultrahigh-height large-span steel concrete beam hanging structure | |
CN102444203A (en) | High-altitude long-span overhanging corridor type reinforced concrete structure and construction method | |
CN106760110B (en) | Based on BIM profiled sheet-armored concrete hollow sandwich floor construction engineering method | |
CN107700648A (en) | Prefabricated component and cast-in-place post assembled integral concrete frame structure construction | |
CN112502714B (en) | Assembled shaft barrel structure and design and construction method | |
CN105421632A (en) | Quick and saving floor system and construction method thereof | |
CN107269085A (en) | A kind of construction method of large-diameter concrete silo top conical shell structure | |
CN107245953A (en) | The bent device and crossed construction method of a kind of multilayer bridge structure | |
CN207277541U (en) | Prefabricated component and cast-in-place column assembled integral concrete frame structure | |
CN104831928B (en) | High-altitude long-span concrete conjoined structure shuttering supporting steel platform construction method | |
Abdelrazaq | Design and construction planning of the Burj Khalifa, Dubai, UAE | |
CN116357143A (en) | Tank room dome construction method based on BIM | |
CN106193621A (en) | Fabricated construction superimposed sheet string hangs construction method | |
CN105386447A (en) | Construction method for replacement support of post-cast strip in construction site | |
CN114892813A (en) | Large-span building main body supporting steel structure and construction method | |
CN115324104A (en) | Permanent and temporary combined assembly type station and construction method thereof | |
CN107165038A (en) | The complete prefabricated substructure and construction method of a kind of bridge | |
KR20210141194A (en) | Construction Method and Device of Wall and Floor Structure in Elevator's Machine Room in Apartment Building and Office Using Hanging Structural Method by Steel and Deck Plate in Top-down Structure | |
Abdelrazaq et al. | Brief on the Construction Planning of the Burj Dubai Project, Dubai, UAE | |
CN115559351B (en) | Reverse construction method for multi-layer basement of all-steel structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190329 |
|
RJ01 | Rejection of invention patent application after publication |