CN109534189A - Hoisting construction method for cast-in-situ core tube structure of assembled integral frame - Google Patents

Hoisting construction method for cast-in-situ core tube structure of assembled integral frame Download PDF

Info

Publication number
CN109534189A
CN109534189A CN201811354101.3A CN201811354101A CN109534189A CN 109534189 A CN109534189 A CN 109534189A CN 201811354101 A CN201811354101 A CN 201811354101A CN 109534189 A CN109534189 A CN 109534189A
Authority
CN
China
Prior art keywords
tower crane
grouting
construction method
construction
tower
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811354101.3A
Other languages
Chinese (zh)
Inventor
姜红平
石梦琪
唐翔
曾德龙
崔玉建
侯亮亮
沈礼鹏
严海鹏
王东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction First Group Corp Ltd
First Construction Co Ltd of China Construction First Group Corp Ltd
Original Assignee
China Construction First Group Corp Ltd
First Construction Co Ltd of China Construction First Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction First Group Corp Ltd, First Construction Co Ltd of China Construction First Group Corp Ltd filed Critical China Construction First Group Corp Ltd
Priority to CN201811354101.3A priority Critical patent/CN109534189A/en
Publication of CN109534189A publication Critical patent/CN109534189A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C23/00Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
    • B66C23/62Constructional features or details
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C13/00Other constructional features or details
    • B66C13/04Auxiliary devices for controlling movements of suspended loads, or preventing cable slack
    • B66C13/08Auxiliary devices for controlling movements of suspended loads, or preventing cable slack for depositing loads in desired attitudes or positions
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention relates to the technical field of construction of an assembled integral frame, and discloses a hoisting construction method for a cast-in-place core tube structure of the assembled integral frame, which comprises the following steps: determining the number and the type of the tower cranes according to the weight and the position of the heaviest prefabricated part and the initial position of the tower crane; determining the final position of the tower crane according to the building plan, the building structure type and the basement structure; comparing and checking performance parameters of the tower crane according to the maximum weight of the prefabricated part and the maximum weight appearing in construction; arranging a tower crane; determining the attachment form of the tower crane, wherein the attachment form comprises that the tower crane is attached to a structural column, the tower crane is attached to the side of a frame beam, and the tower crane is attached to the top of the frame beam; the comprehensive consideration such as the operation radius, the maximum prefabricated part lifting capacity, the tower crane position and the attachment form is combined in the model selection process, and the method has the advantages of high tower crane efficiency and high balance degree between hoisting operation areas.

Description

A kind of assembled general frame cast-in-place core wall structure lifting construction method
Technical field
The present invention relates to assembled general frame technical field of construction, more specifically, it relates to which a kind of assembled is whole Frame cast-in-place core wall structure lifting construction method.
Background technique
With the propulsion that construction industry modernizes, traditional architecture mode is gradually no longer complies with the growth requirement in epoch, assembled Building is becoming a new emphasis of construction industry Transformation Development.Medium-and-large-sized prefabricated components and the installation Mission Day of equipment are cumulative It is more, construction site tower crane using extremely widespread.Since tower crane has, construction efficiency is high, boundary of works area is wide, effective lifting height The advantages that big, the construction and installation for building its assembly concrete provide great convenience.
But need the operating radius in view of tower crane using tower crane in the construction process, maximum prefabricated components lifting capacity with And it is some between group's tower, if disregarding calculation above-mentioned factor, will limit tower crane service efficiency and lifting operation region it Between equilibrium degree.
Summary of the invention
Problem in view of the prior art, the present invention provide a kind of cast-in-place core wall structure heavy dressing of assembled general frame Work method has the advantages that tower crane is high-efficient, the equilibrium degree between lifting operation region is high.
To achieve the above object, the present invention provides the following technical scheme that
A kind of assembled general frame cast-in-place core wall structure lifting construction method, includes the following steps:
Step S1: the rough location of the most heavy prefabricated components weight of lifting, position and tower crane as needed determines the number of tower crane Amount and type;
Step S2: the final position of tower crane is determined according to architectural plan, building structure pattern and basement structure;
Step S3: joined according to the performance of the maximum weight comparison verification tower crane occurred in the maximum weight and construction of prefabricated components Number retains performance parameter the surplus of setting;
Step S4: arrangement tower crane, every main building configure two tower cranes, and the working range of tower crane is made to cover main building and podium;
Step S5: determining the attached form of tower crane, attached form include tower crane attachment in structural column, tower crane attachment in Vierendeel girder Side and tower crane attachment are in frame back.
Through the above technical solutions, combining operating radius, maximum prefabricated components lifting capacity, tower crane position during type selecting And attached form etc. comprehensively considers, to overcome the inefficiency of simple-arranged tower crane, lifting operation region in the prior art Between it is unbalanced the problems such as, have the advantages that tower crane is high-efficient, the equilibrium degree between lifting operation region is high.
Further, step S4 further include: main building is divided into two flowing water sections by two tower cranes, wherein a tower crane lifts structure Part, another tower crane lifting template and laminated floor slab.
Through the above technical solutions, a tower crane is responsible for flowing water section lifting component, another tower crane is responsible for shuttering supporting and is taken It constructs if being bound with laminated floor slab reinforcing bar, avoids work holdup phenomenon.
Further, step S5 further include:
Step S51: determine that grouting form, grouting form include when layer grouting and interlayer grouting;
Step S52: matching grouting form and attached form, then the grouting form being in the milk using interlayer and tower crane attachment are matched in frame It sets a roof beam in place the attached form on top.
Through the above technical solutions, interlayer grouting is as progress key node but can be interspersed in main structure construction, Do not influence the whole duration, and there is no crossings on different level to construct, tower crane attachment adhere in the attached form of frame back stress by Entire Core Walls Structure floor system undertakes, and prefabricated post and framed bent are subjected only to minimum part power.
Further, further include step S6: setting circumferential highway, the circumferential highway for road in the field of construction area Surround annex.
Through the above technical solutions, making annex two sides respectively has a road, the shape to block up when a large amount of components are marched into the arena is avoided Condition.
Further, the gradient of the circumferential highway is less than the road grade set, the turning half of the circumferential highway Diameter is less than the road radius set.
Through the above technical solutions, avoiding the case where appearance of separate unit tower crane can not unload.
Further, stockyard is provided with by the circumferential highway, the work for around main building and being located at tower crane is arranged in stockyard In region.
Through the above technical solutions, tower crane is avoided to there is lifting blind area.
Further, the stockyard is located at by the tower crane, and close to the tower crane.
Through the above technical solutions, lifting covering is able to satisfy the direct lifting nothing of most heavy prefabricated components and all kinds of construction materials The demand that need to be transported.
Compared with prior art, the beneficial effects of the present invention are: combining operating radius, maximum prefabricated structure during type selecting Part lifting capacity, tower crane position and attached form etc. comprehensively consider, and match grouting form and attached form, then match using interlayer The grouting form and tower crane attachment of grouting are in the attached form of frame back.
Interlayer grouting is as progress key node but can be interspersed in main structure construction, does not influence the whole duration, and There is no crossings on different level construction, tower crane attachment adheres to stress by entire Core Walls Structure floor system in the attached form of frame back It undertakes, prefabricated post and framed bent are subjected only to minimum part power.Overcome the inefficiency of simple-arranged tower crane, lifting in the prior art The problems such as unbalanced between operating area, has the advantages that tower crane is high-efficient, the equilibrium degree between lifting operation region is high.
Detailed description of the invention
Fig. 1 is the method flow diagram of step of embodiment of the present invention S1 to step S6;
Fig. 2 is the method flow diagram of step of embodiment of the present invention S51 to step S52;
Fig. 3 is the prefabricated components information table of the embodiment of the present invention;
Fig. 4 is the prefabricated post floor plan of the embodiment of the present invention;
Fig. 5 is the precast beam floor plan of the embodiment of the present invention;
Fig. 6 is the tower crane model table of the embodiment of the present invention;
Fig. 7 is the plane layout of tower crane schematic diagram of the embodiment of the present invention;
Fig. 8 is the tower crane attachment schematic diagram of the embodiment of the present invention;
Fig. 9 is the interlayer grouting schematic diagram of the embodiment of the present invention.
Specific embodiment
With reference to the accompanying drawings and examples, the present invention will be described in detail.
Embodiment
A kind of assembled general frame cast-in-place core wall structure lifting construction method, as shown in Figure 1, including following step It is rapid:
Step S1: the rough location of the most heavy prefabricated components weight of lifting, position and tower crane as needed determines the number of tower crane Amount and type;
Step S2: the final position of tower crane is determined according to architectural plan, building structure pattern and basement structure;
Step S3: joined according to the performance of the maximum weight comparison verification tower crane occurred in the maximum weight and construction of prefabricated components Number retains performance parameter the surplus of setting;
Step S4: arrangement tower crane, every main building configure two tower cranes, and the working range of tower crane is made to cover main building and podium.Step Rapid S4 further include: main building is divided into two flowing water sections by two tower cranes, wherein a tower crane lifting components, another tower crane lifts mould Plate and laminated floor slab.One tower crane is responsible for flowing water section lifting component, and another tower crane is responsible for shuttering supporting and is set up and laminated floor slab Reinforcing bar binding construction, avoids work holdup phenomenon.
Step S5: determining the attached form of tower crane, attached form include tower crane attachment in structural column, tower crane attachment in frame Beam side and tower crane attachment are in frame back.Operating radius, maximum prefabricated components lifting capacity, tower crane are combined during type selecting Position and attached form etc. comprehensively consider, to overcome the inefficiency of simple-arranged tower crane, lifting operation in the prior art The problems such as unbalanced between region, has the advantages that tower crane is high-efficient, the equilibrium degree between lifting operation region is high.Such as Fig. 2 institute Show, step S5 further includes step S51 and step S52.Step S51: determining grouting form, grouting form include when layer grouting and Interlayer grouting.Step S52: matching grouting form and attached form, then match attached using the grouting form and tower crane of interlayer grouting In the attached form of frame back.Interlayer grouting is as progress key node but can be interspersed in main structure construction, no The whole duration is influenced, and there is no crossings on different level to construct, tower crane attachment adheres to stress by whole in the attached form of frame back A Core Walls Structure floor system undertakes, and prefabricated post and framed bent are subjected only to minimum part power.
Step S6: circumferential highway is set by road in the field of construction area, circumferential highway surrounds annex.Make annex two sides Respectively there is a road, avoids the situation to block up when a large amount of components are marched into the arena.The gradient of circumferential highway is less than the road slope set Degree, the turning radius of circumferential highway are less than the road radius set.Avoid the case where appearance of separate unit tower crane can not unload.Ring Stockyard is provided with by shape road, stockyard is arranged in around main building and is located in the working region of tower crane.Tower crane is avoided to there is lifting Blind area.Stockyard is located at by tower crane, and close to tower crane.Lifting covering is able to satisfy the direct of most heavy prefabricated components and all kinds of construction materials Demand of the lifting without transhipment.
In the present embodiment by taking the second general headquarters, China Electronics Scientific Research Building as an example, which is located in listing Pudong New District Zhangjiang Area mainly includes two layers of underground garage, the building 1#, the building 2#, the building 3#.The building 1# totally 11 floor, 48.25 meters of building height, monomer pre-emulsion rate It is 39.16%;The building 2# totally 12 floor, building height is 48.45 meters high, and monomer pre-emulsion rate is 41.36%, and two main buildings are that assembly is whole Formula frame-cast-in-place core wall structure;The building 3# totally 2 floor, 10.5 meters of building height, be cast-in-place framework.1# prefabricated components information, 2# prefabricated components information is as shown in Figure 3.
In tower crane type selecting, for assembled coagulation construction, the type selecting of vertical transport equipment tower crane is a Xiang Zhiguan Important work, reasonable tower crane type selecting can effectively ensure that prefabricated components construction and installation efficiency.Therefore, it should be tied during type selecting It closes engineering project actual conditions, operating radius, maximum prefabricated components lifting capacity, economical etc. to comprehensively consider, to realize tower crane Optimal selection.
More than two three floor of main building of this engineering be the cast-in-place core wall structure of prefabricated integral frame-, mainly have prefabricated post, Composite beam, superimposed sheet, wherein between 7 ~ 9 tons, most heavy component reaches 9.25 tons for prefabricated post, composite beam average weight.Cause This, tower crane type selecting and arrangement also need to consider following factor: (1) substantially according to most heavy prefabricated components weight, position and tower crane Installation site carries out tower crane type selecting, and model should be able to meet the most lifting requirements of reconstruct part and the lifting at amplitude peak and want It asks;(2) according to the places situations such as architectural plan, building structure pattern, basement structure, the transit route of component and construction Deployment scenario finally determines the installation site of tower crane.Tower crane installation site should be able to cover whole construction sites, and lean on as far as possible The nearly big region of lifting capacity;In view of group towers work influences, tower crane correlation and brachium should be limited, and undertake each tower crane Lifting operation region it is substantially balanced;(3) because there are the plane transportations of a large amount of prefabricated components, it is necessary to supply line in field of making rational planning for Road controls haul road grade and turning radius;(4) according to lifting possible in the maximum weight of each component, construction Maximum weight and position and the comparison of tower crane lifting performance verify, and there are suitable surpluses, to prevent appearing in conceptual design not The exception of consideration.
Below by taking the building this engineering 1# as an example, prefabricated components are briefly statisticallyd analyze:
As shown in figure 4, the building 1# prefabricated post average weight is 7 ~ 9 tons, most heavy prefabricated post reaches 9.25 tons at 3 ~ 6 layers, in 7,8, 13,14 axis, 9,10,11,12 axis prefabricated post average weights are 7 ~ 8 tons.As shown in figure 5, most heavy precast main beam be distributed in A, D, 7, 14 axis, average weight are 8 ~ 9 tons, are most weighed to 9.15 tons;Secondary beam average weight is 6 tons.Superimposed sheet average weight is 2.2 tons. In conclusion integration project actual demand and tower crane Type Selection Principle, this engineering tower crane model are as shown in Figure 6.
The arrangement of tower crane should be according to construction site construction environment and the comprehensive determination of economic condition, under normal circumstances, assembled The arrangement principle of construction site tower crane should follow following basic principle: (1) meeting the needs for itself climbing and adhering to;(2) Lifting covering should be able to meet the lifting demand of most heavy prefabricated components and all kinds of construction materials, and should be ensured that tower crane and stack pre- The place of component processed is close to each other;(3) avoid the presence of lifting blind area;(4) comprehensively consider tower crane demolishing process, while should not influence The construction of proximity structure avoids each engineering construction installation progress from interacting.
This engineering tower crane plan view is as shown in Figure 7.By Fig. 7 it can be seen that every main building is configured with Liang Taita It hangs, podium is whole all in tower crane lifting range, can carry out podium construction while ensure that high building construction.According to this engineering Main building is divided into two flowing water sections by fabricated construction deployment, two tower cranes, i.e. a tower crane is responsible for left side flowing water section component and is hung Dress, the shuttering supporting that another tower crane is responsible for right side are set up to bind with laminated floor slab reinforcing bar and construct, and work holdup phenomenon is avoided.Together When, road arrangement is circumferential highway in field, and stockyard is arranged near main building, while in tower crane covering surface.It both avoids in this way The situation that a large amount of components block up when marching into the arena also avoids the case where appearance of separate unit tower crane can not unload.
The comparison of tower crane attachment anchoring and scheme are selected.The attached form of tower crane is as shown in Figure 8, comprising: tower crane attachment in Structural column, tower crane attachment are in Vierendeel girder side and tower crane attachment in frame back.
The comparison of tower crane attachment form is as follows: (1) the first tower crane attachment in structural column form is made in cast-in-place structural With a kind of attached form the most universal.(2) second of tower crane attachment are the optimization based on the first in Vierendeel girder side form, excellent Point has cantilevered structure in structural column, but this engineering main building outermost in avoiding drawknot, this attached form need to be in overhanging secondary beam Upper indwelling construction joint has certain influence to cantilevered structure, at the same the later period need to spend it is more manually and the time is to constructing herein Seam is repaired.(3) the third tower crane attachment is the optimization based on second in frame back, advantage in avoiding drawknot in Structural column, while the problem of avoid the indwelling construction joint at cantilevered structure.
The ratio choosing of tower crane attachment form and grouting form are close not in fabricated construction in the work of tower crane attachment formal character It can divide, i.e., live grouting form determines tower crane attachment anchor type.
Grouting is divided into following two kinds of forms in the selection work of grouting form: when layer grouting is in the milk with interlayer.When layer is in the milk It is in the milk immediately after the completion of prefabricated post lifts, the advantages of such mode is that structural column is connect with floor plates and more may be used It leans on, certain upper load can be carried.Disadvantage is that grouting construction is the key of progress monitoring during main structure construction Node exists simultaneously interchange operation, there is some potential safety problems.Interlayer grouting is i.e. to pre- before shuttering supporting framed bent is removed Cylinder processed carries out grouting construction, as shown in Figure 9.The advantages of such mode, is, although grouting construction is as progress key node But it can be interspersed in main structure construction, as two-level node even three-level node, not influence the whole duration, and there is no vertical Body crossed construction;The disadvantage is that, reinforcing bar and cushion block are only leaned in the connection of column and substructure before grouting construction, top is most of Load is supported by supporting row frame.The construction of final choice interlayer grouting.
The grouting form based on interlayer grouting is again to three kinds of attached forms of tower crane in the selection work of tower crane attachment form It carries out than choosing.The first attached form, when carrying out tower crane attachment, in-situ precast column is not in the milk, therefore, tower crane attachment In there are biggish security risks in the prefabricated post not being in the milk;Second of attached form, need to overhanging secondary beam on indwelling construction joint, There is certain influence to cantilevered structure, while the later period needs to spend and more manually repair with the time to construction joint herein;The Three kinds of attached forms, attachment stress are undertaken by entire Core Walls Structure floor system, and prefabricated post and framed bent are subjected only to minimum part power, The security risk for avoiding the first attached form has also evaded influence of second of attached form to cantilevered structure.Therefore, In conjunction with this project actual conditions, final choice tower crane attachment is in the construction of frame back.
Tower crane plays an important role during prefabricated concrete structure prefabricated part hanging, and prefabricated components are main Lifting, installation, correction rely on tower crane completion, therefore, the type selecting of tower crane, arrangement and adhere to the selection of anchor type and directly affect The construction deployment and construction speed of entire project.Operating radius, maximum prefabricated components lifting capacity, tower are combined during type selecting It hangs position and attached form etc. to comprehensively consider, matches grouting form and attached form, then match the grouting being in the milk using interlayer Form and tower crane attachment are in the attached form of frame back.Interlayer grouting is as progress key node but can be interspersed in main body knot In structure construction, the whole duration is not influenced, and there is no crossings on different level to construct, tower crane attachment is attached in the attached form of frame back Stress undertaken by entire Core Walls Structure floor system, prefabricated post and framed bent are subjected only to minimum part power.Overcome in the prior art The problems such as unbalanced between the inefficiency of simple-arranged tower crane, lifting operation region, have that tower crane is high-efficient, lifting operation area The high advantage of equilibrium degree between domain.
The above is only a preferred embodiment of the present invention, protection scope of the present invention is not limited merely to above-mentioned implementation Example, all technical solutions belonged under thinking of the present invention all belong to the scope of protection of the present invention.It should be pointed out that for the art Those of ordinary skill for, several improvements and modifications without departing from the principles of the present invention, these improvements and modifications It should be regarded as protection scope of the present invention.

Claims (7)

1. a kind of assembled general frame cast-in-place core wall structure lifting construction method, which comprises the steps of:
Step S1: the rough location of the most heavy prefabricated components weight of lifting, position and tower crane as needed determines the number of tower crane Amount and type;
Step S2: the final position of tower crane is determined according to architectural plan, building structure pattern and basement structure;
Step S3: joined according to the performance of the maximum weight comparison verification tower crane occurred in the maximum weight and construction of prefabricated components Number retains performance parameter the surplus of setting;
Step S4: arrangement tower crane, every main building configure two tower cranes, and the working range of tower crane is made to cover main building and podium;
Step S5: determining the attached form of tower crane, attached form include tower crane attachment in structural column, tower crane attachment in Vierendeel girder Side and tower crane attachment are in frame back.
2. assembled general frame cast-in-place core wall structure lifting construction method according to claim 1, feature exist In step S4 further include: main building is divided into two flowing water sections by two tower cranes, wherein a tower crane lifting components, another tower crane Lift template and laminated floor slab.
3. assembled general frame cast-in-place core wall structure lifting construction method according to claim 1, feature exist In step S5 further include:
Step S51: determine that grouting form, grouting form include when layer grouting and interlayer grouting;
Step S52: matching grouting form and attached form, then the grouting form being in the milk using interlayer and tower crane attachment are matched in frame It sets a roof beam in place the attached form on top.
4. assembled general frame cast-in-place core wall structure lifting construction method according to claim 1, feature exist In further including step S6: road is set as circumferential highway in the field by construction area, and the circumferential highway surrounds annex.
5. assembled general frame cast-in-place core wall structure lifting construction method according to claim 4, feature exist In the gradient of, the circumferential highway it is less than the road grade set, the turning radius of the circumferential highway, which is less than, to be set Road radius.
6. assembled general frame cast-in-place core wall structure lifting construction method according to claim 5, feature exist In being provided with stockyard by the circumferential highway, stockyard is arranged in around main building and is located in the working region of tower crane.
7. assembled general frame cast-in-place core wall structure lifting construction method according to claim 6, feature exist In the stockyard is located at by the tower crane, and close to the tower crane.
CN201811354101.3A 2018-11-14 2018-11-14 Hoisting construction method for cast-in-situ core tube structure of assembled integral frame Pending CN109534189A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811354101.3A CN109534189A (en) 2018-11-14 2018-11-14 Hoisting construction method for cast-in-situ core tube structure of assembled integral frame

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811354101.3A CN109534189A (en) 2018-11-14 2018-11-14 Hoisting construction method for cast-in-situ core tube structure of assembled integral frame

Publications (1)

Publication Number Publication Date
CN109534189A true CN109534189A (en) 2019-03-29

Family

ID=65847387

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811354101.3A Pending CN109534189A (en) 2018-11-14 2018-11-14 Hoisting construction method for cast-in-situ core tube structure of assembled integral frame

Country Status (1)

Country Link
CN (1) CN109534189A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110407104A (en) * 2019-07-26 2019-11-05 五冶集团上海有限公司 The accurate merogenesis hanging method of steel column based on BIM
WO2021000443A1 (en) * 2019-07-01 2021-01-07 济南轨道交通集团有限公司 Hosting method for heavy apparatus close to unsealed building
CN112561487A (en) * 2020-12-21 2021-03-26 广联达科技股份有限公司 Method, device and equipment for calculating construction progress and readable storage medium
CN113445741A (en) * 2021-07-08 2021-09-28 江苏沪宁钢机股份有限公司 Half-floor tower suspended ceiling construction method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104746884A (en) * 2015-04-10 2015-07-01 华东建筑设计研究院有限公司 Method for hoisting prefabricated parts of assembled building
CN206267309U (en) * 2016-12-15 2017-06-20 北京智慧云建科技有限公司 A kind of assembled steel concrete frame core wall structure system
CN106986275A (en) * 2017-03-13 2017-07-28 同济大学 A kind of assembled architecture plane layout of tower crane and selection method based on BIM
CN107165421A (en) * 2017-06-12 2017-09-15 江苏建科建设监理有限公司 A kind of construction method of concrete assembled building
CN107386660A (en) * 2017-08-02 2017-11-24 中国十七冶集团有限公司 Tower crane system in prefabricated concrete structure construction based on BIM technology
CN107476583A (en) * 2017-08-18 2017-12-15 国网上海市电力公司 A kind of concrete assembled building builds construction method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104746884A (en) * 2015-04-10 2015-07-01 华东建筑设计研究院有限公司 Method for hoisting prefabricated parts of assembled building
CN206267309U (en) * 2016-12-15 2017-06-20 北京智慧云建科技有限公司 A kind of assembled steel concrete frame core wall structure system
CN106986275A (en) * 2017-03-13 2017-07-28 同济大学 A kind of assembled architecture plane layout of tower crane and selection method based on BIM
CN107165421A (en) * 2017-06-12 2017-09-15 江苏建科建设监理有限公司 A kind of construction method of concrete assembled building
CN107386660A (en) * 2017-08-02 2017-11-24 中国十七冶集团有限公司 Tower crane system in prefabricated concrete structure construction based on BIM technology
CN107476583A (en) * 2017-08-18 2017-12-15 国网上海市电力公司 A kind of concrete assembled building builds construction method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
唐翔等: "塔式起重机在装配整体式框架-现浇核心筒结构施工中的应用", 《建筑施工》 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2021000443A1 (en) * 2019-07-01 2021-01-07 济南轨道交通集团有限公司 Hosting method for heavy apparatus close to unsealed building
CN110407104A (en) * 2019-07-26 2019-11-05 五冶集团上海有限公司 The accurate merogenesis hanging method of steel column based on BIM
CN112561487A (en) * 2020-12-21 2021-03-26 广联达科技股份有限公司 Method, device and equipment for calculating construction progress and readable storage medium
CN112561487B (en) * 2020-12-21 2024-01-23 广联达科技股份有限公司 Method, device and equipment for calculating construction progress and readable storage medium
CN113445741A (en) * 2021-07-08 2021-09-28 江苏沪宁钢机股份有限公司 Half-floor tower suspended ceiling construction method
CN113445741B (en) * 2021-07-08 2023-02-28 江苏沪宁钢机股份有限公司 Half-floor tower suspended ceiling construction method

Similar Documents

Publication Publication Date Title
CN109534189A (en) Hoisting construction method for cast-in-situ core tube structure of assembled integral frame
CN106894639B (en) The hanging reverse construction method of installation of steel construction under a kind of
CN112900692B (en) Large-span special-shaped steel structure building, supporting device thereof and construction method
CN102535845A (en) Construction method of bearing frame of corridor structure
CN103291076A (en) Multilayer steel truss fragmented reverse hoisting construction method in arc-shaped frame
CN114232805B (en) Construction method of ultrahigh-height large-span steel concrete beam hanging structure
CN102444203A (en) High-altitude long-span overhanging corridor type reinforced concrete structure and construction method
CN106760110B (en) Based on BIM profiled sheet-armored concrete hollow sandwich floor construction engineering method
CN107700648A (en) Prefabricated component and cast-in-place post assembled integral concrete frame structure construction
CN112502714B (en) Assembled shaft barrel structure and design and construction method
CN105421632A (en) Quick and saving floor system and construction method thereof
CN107269085A (en) A kind of construction method of large-diameter concrete silo top conical shell structure
CN107245953A (en) The bent device and crossed construction method of a kind of multilayer bridge structure
CN207277541U (en) Prefabricated component and cast-in-place column assembled integral concrete frame structure
CN104831928B (en) High-altitude long-span concrete conjoined structure shuttering supporting steel platform construction method
Abdelrazaq Design and construction planning of the Burj Khalifa, Dubai, UAE
CN116357143A (en) Tank room dome construction method based on BIM
CN106193621A (en) Fabricated construction superimposed sheet string hangs construction method
CN105386447A (en) Construction method for replacement support of post-cast strip in construction site
CN114892813A (en) Large-span building main body supporting steel structure and construction method
CN115324104A (en) Permanent and temporary combined assembly type station and construction method thereof
CN107165038A (en) The complete prefabricated substructure and construction method of a kind of bridge
KR20210141194A (en) Construction Method and Device of Wall and Floor Structure in Elevator's Machine Room in Apartment Building and Office Using Hanging Structural Method by Steel and Deck Plate in Top-down Structure
Abdelrazaq et al. Brief on the Construction Planning of the Burj Dubai Project, Dubai, UAE
CN115559351B (en) Reverse construction method for multi-layer basement of all-steel structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190329

RJ01 Rejection of invention patent application after publication