WO2020062940A1 - Grouting consolidation method for full casing borehole guide prefabricated pile and prefabricated pile therefor - Google Patents
Grouting consolidation method for full casing borehole guide prefabricated pile and prefabricated pile therefor Download PDFInfo
- Publication number
- WO2020062940A1 WO2020062940A1 PCT/CN2019/091230 CN2019091230W WO2020062940A1 WO 2020062940 A1 WO2020062940 A1 WO 2020062940A1 CN 2019091230 W CN2019091230 W CN 2019091230W WO 2020062940 A1 WO2020062940 A1 WO 2020062940A1
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- borehole
- casing
- grouting
- pile
- bedrock
- Prior art date
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D15/00—Handling building or like materials for hydraulic engineering or foundations
- E02D15/02—Handling of bulk concrete specially for foundation or hydraulic engineering purposes
- E02D15/06—Placing concrete under water
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/62—Compacting the soil at the footing or in or along a casing by forcing cement or like material through tubes
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D11/00—Methods or apparatus specially adapted for both placing and removing sheet pile bulkheads, piles, or mould-pipes
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D15/00—Handling building or like materials for hydraulic engineering or foundations
- E02D15/02—Handling of bulk concrete specially for foundation or hydraulic engineering purposes
- E02D15/04—Placing concrete in mould-pipes, pile tubes, bore-holes or narrow shafts
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D15/00—Handling building or like materials for hydraulic engineering or foundations
- E02D15/08—Sinking workpieces into water or soil inasmuch as not provided for elsewhere
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/32—Foundations for special purposes
- E02D27/52—Submerged foundations, i.e. submerged in open water
- E02D27/525—Submerged foundations, i.e. submerged in open water using elements penetrating the underwater ground
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/34—Concrete or concrete-like piles cast in position ; Apparatus for making same
- E02D5/38—Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/34—Concrete or concrete-like piles cast in position ; Apparatus for making same
- E02D5/38—Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
- E02D5/385—Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds with removal of the outer mould-pipes
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D7/00—Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
- E02D7/26—Placing by using several means simultaneously
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D7/00—Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
- E02D7/28—Placing of hollow pipes or mould pipes by means arranged inside the piles or pipes
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2250/00—Production methods
- E02D2250/0023—Cast, i.e. in situ or in a mold or other formwork
Definitions
- the invention relates to the technical field of foundations, in particular to a grouting consolidation method for a full-sleeve drill-guided precast pile and its precast pile.
- the above-mentioned cofferdam island construction is also required to be removed, resulting in a huge amount of construction work using the above-mentioned cofferdam island construction method, which has the problems of long engineering cycle and high engineering cost.
- the hammered steel pipe pile is constructed by hammering and sinking into the foundation of the water area, when the hammered steel pipe pile encounters a hard bedrock, the end of the hammered steel pipe pile may be curled or even unable to hit.
- the present invention aims to provide a grouting consolidation method of a full casing drilled guide prefabricated pile and its prefabricated pile, in order to solve the prior art in the construction of a water-based foundation under various formation conditions, especially in marine engineering.
- the present application provides a grouting consolidation method for a full casing drilled guide prefabricated pile, which is used for foundation construction of a water area project, and includes the following steps:
- the prefabricated pile is implanted into the borehole, so that the prefabricated pile reaches the bottom of the hole of the borehole;
- Step S3 the step of implanting a precast pile into the borehole so that the precast pile reaches the bottom of the hole of the borehole includes the following steps: pre-injecting a slurry into the borehole; before the slurry solidifies , Implanting a prefabricated pile into the borehole to the bottom of the borehole.
- the prefabricated pile is prefabricated with a grouting channel for injecting slurry into the borehole
- Step S5 the pulling out the casing includes: during the pulling out of the casing, continuously grouting into the borehole through a grouting channel on the precast pile;
- injecting the slurry into the borehole includes: before the casing is pulled out, grouting into the borehole through a grouting channel on the precast pile.
- the grouting channel includes: a first grouting channel located on a bottom surface of the precast pile;
- Step S5 the pulling out the casing includes: continuously pulling into the borehole through the first grouting channel and / or the second grouting channel during the process of pulling out the casing.
- injecting the slurry into the borehole includes: before the casing is pulled out, grouting into the borehole through the first grouting channel.
- Step S1 driving the drilling rig carrying the casing to perform drilling construction to a preset hole depth, including the following steps: sinking the casing to the bedrock layer; passing the drill's drill bit through the casing The inner cavity of the casing sinks to the bedrock layer, and drills the bedrock layer to form the bedrock borehole in the bedrock layer;
- Step S2 the step of moving the drill bit of the rig out of the bedrock borehole, and the casing being accommodated in the bedrock borehole, comprises: sequentially drilling the drill bit from the bedrock and the Moving out of the casing, the lower end of the casing entering the opening edge of the borehole cavity of the bedrock,
- the borehole includes the bedrock borehole.
- the above loose layer is a loose layer such as sand
- step S1 driving the drilling rig carrying the casing to perform drilling construction, and drilling construction to a preset hole depth includes:
- Step S2 the step of removing the drill bit of the drilling rig from the borehole and accommodating the casing in the borehole includes: drilling the drill bit of the rig from the bedrock and the casing in order. Removed, the lower end of the casing enters the opening edge of the bedrock bore cavity;
- the drilling includes the loose layer drilling and the bedrock drilling.
- step S1 driving the drilling rig carrying the casing to perform drilling construction to a preset hole depth includes the steps of sinking the casing to the loose layer, and drilling the drill to the loose layer.
- the hole forms a loose layer drill hole, and drives the casing into the loose layer; removing the sediment in the casing.
- the upper end of the precast pile is located above the water surface of the water area, and / or the upper end of the precast pile is located below the water surface of the water area.
- the slurry includes cement slurry and / or mortar and / or chemical slurry.
- a prefabricated pile including
- the grouting channel is provided on the pile body, the liquid inlet end of the grouting channel extends out of the upper end surface of the pile body, the liquid outlet end of the grouting channel extends out of the lower end surface of the pile body and / Or the side of the pile.
- the pile body is a reinforced concrete prefabricated pile
- the grouting channel is a grouting pipe prefabricated on a reinforced cage of the pile body.
- a grouting consolidation method for a full-casing drill-guided prefabricated pile for foundation construction of a water area project comprising the following steps: S1, driving a drilling rig carrying a casing for drilling construction, drilling Construction to a preset hole depth; S2, the casing is accommodated in the borehole; S3, a precast pile is implanted into the borehole so that the precast pile reaches the bottom of the hole of the borehole; S4 , Injecting slurry into the borehole; S5, pulling out the sleeve so that the precast pile and the inner cavity of the borehole are fixed and cemented into an integrated structure.
- this application In order to adapt to the stratum of a variety of water engineering, especially the marine engineering environment that needs to be constructed on the seawater of rivers and lakes, this application first uses a casing to cooperate with drilling, then introduces the precast pile guide into the bottom of the hole, and finally injects slurry Realize the construction of water stratum in a fixed way.
- casing can be used to assist drilling to adapt to different underwater stratum structures.
- the introduction of prefabricated pile guides into the bottom of the hole can effectively ensure the foundation of water area engineering. Stable and reliable construction.
- the pile foundation construction work of rivers, lakes, seas and other water strata is realized in the above manner.
- step S3 the precast pile is implanted into the drilled hole so that the precast pile reaches the hole of the drilled hole
- the bottom includes the following steps: pre-injecting a slurry into the borehole; before the slurry is solidified, a precast pile is implanted into the borehole to reach the bottom of the borehole.
- the grouting consolidation method for a full-casing drill-guided prefabricated pile provided in the present invention, the prefabricated pile is prefabricated with a grouting channel for injecting slurry into the borehole, step S5, the extraction station
- the casing includes: during the process of extracting the casing, continuously grouting into the borehole through a grouting channel on the prefabricated pile; during the process of extracting the casing, through the above
- the grouting channel of the prefabricated pile can simply and conveniently make the slurry flow into the borehole to fill the gap generated during the pullout of the casing.
- step S4 injecting the slurry into the borehole includes: before the casing is pulled out, grouting into the borehole through a grouting channel on the precast pile. Before the casing is pulled out, the slurry is injected into the borehole through the grouting channel, or the slurry is directly poured into the borehole.
- the operation is simple and convenient, which can make the precast pile and the ground around the borehole 2 Tightly cemented together to form a precast pile foundation, thereby improving the connection strength of the precast pile with soil, sand and gravel in the marine engineering environment.
- the grouting channel comprises: a first grouting channel located on the bottom surface of the prefabricated pile; Set up grouting channels, so that the slurry can be injected into the boreholes from the bottom of the precast pile, so that the slurry can more evenly and fully fill the gap between the precast pile and the borehole, so that the precast pile and the ground around the borehole 2 are tightly cemented and fixed. Together form a precast pile foundation.
- step S1 said driving a drilling rig carrying a casing for drilling construction, drilling
- the hole construction to a preset hole depth includes the following steps: sinking the casing to the bedrock layer; sinking a drill bit of the rig to the bedrock layer through the casing cavity, and drilling the bedrock layer To form the bedrock borehole in the bedrock layer.
- Step S2 the step of moving the drill bit of the rig out of the bedrock borehole, and the casing being accommodated in the bedrock borehole, comprises: sequentially drilling the drill bit from the bedrock and the The casing is removed, the lower end of the casing enters the opening edge of the inner cavity of the bedrock borehole, and the borehole includes the bedrock borehole.
- the drill bit of the rig drills the bedrock layer through the casing, which can effectively solve the problem that the bedrock layer is difficult to construct during the construction of the water area with the bedrock layer at the bottom.
- the grouting consolidation method for a full-casing drill-guided prefabricated pile provided by the present invention, in a water area construction process with a loose layer and a bedrock layer in order from the bottom to the bottom, step S1, the drive carries a casing Drilling rig for drilling construction to a preset hole depth includes sinking the casing to the loose layer, and drilling the hole to the loose layer to drive the casing through the loose layer Layer to form a loose layer for drilling; removing earth, rock, and sediment in the casing; sinking a drill bit of the rig through the casing cavity to the bedrock layer, and drilling the bedrock layer to form the bedrock layer Rock formations form the bedrock borehole.
- Step S2 the step of removing the drill bit of the drilling rig from the borehole and accommodating the casing in the borehole includes: drilling the drill bit of the rig from the bedrock and the casing in order. When removed, the lower end of the casing enters the open edge of the inner cavity of the bedrock borehole; the borehole includes the loose layer borehole and the bedrock borehole.
- the loose layer is first drilled by the drill's drill bit, and then the sediment is discharged. Drilling the bedrock layer through a drill bit through the casing effectively solves the problem that the above waters are difficult to construct because of the loose layer and the bedrock layer.
- the bedrock boreholes are filled by injecting slurry into the bedrock boreholes in advance, and then the precast piles are settled into the bedrock boreholes.
- the grouting channels of the precast piles are continuously loosened.
- the layer grouting method further completes the work of filling and fixing the bedrock layer and the loose layer respectively.
- the bedrock drilling adopts the fixing method of pre-grouting and re-implanting the precast pile, which can effectively make the slurry have sufficient time to be cemented and fixed with the bedrock drilling, and the slurry can penetrate the bedrock layer more fully under the impact of the precast pile's falling impact; loose
- the layer is grouted into the loose layer during the casing lifting process, which can effectively fill the gap between the precast pile and the casing with slurry to complete the above grouting work, so that the slurry can fully precast the pile and loose.
- the formations around the boreholes are cemented together.
- FIG. 1 is a schematic diagram of installation steps of a full casing of a water area having a loose layer and a bedrock layer provided by the present invention
- FIG. 2 is a schematic diagram of steps for pre-grouting in a water area having a loose layer and a bedrock layer provided in the present invention toward the bedrock layer;
- FIG. 3 is a schematic diagram of steps for sinking a precast pile to the bottom of a pre-grouted borehole in a water area having a loose layer and a bedrock layer provided by the present invention
- FIG. 4 is a schematic diagram of a step of taking out a full casing in a water area having a loose layer and a bedrock layer provided by the present invention
- FIG. 5 is a schematic diagram of a connection structure between a precast pile and a bottom of a water area after completion of a grouting consolidation process of a full casing drilled guide prefabricated pile in a water area having a loose layer and a bedrock layer provided by the present invention
- FIG. 6 is a schematic structural diagram of the precast pile sinking to the bottom of a borehole provided by the present invention.
- FIG. 7 is a schematic structural diagram of a connection structure between a precast pile and a foundation foundation environment when a full casing is taken out after a full casing drilling and grouting process provided by the present invention is completed.
- This embodiment provides a grouting consolidation method for a full-casing drill-guided prefabricated pile.
- the engineering implementation environment is shown in Figs. 1 to 7.
- the bottom layer has a loose layer 8 and a bedrock layer 9 in this order from top to bottom.
- the grouting consolidation method of a full-casing drill-guided precast pile includes the following steps:
- step S1 the casing 1 is sunk to the loose layer 8 through the water surface 10, and a drilling rig drills the loose layer 8 to drive the casing 1 through the loose layer 8 to form a loose layer.
- step S2 the drill bit of the rig is sequentially removed from the bedrock borehole 13 and the casing 1, and at this time, the lower end portion of the casing 1 enters the opening edge of the inner cavity of the bedrock borehole 13. So that the end of the casing 1 is sleeved with the opening edge of the bedrock borehole 13;
- the grouting channel 5 includes: The first grouting channel 6 on the bottom surface of the prefabricated pile 4 is continuously grouting into the loose layer borehole 14 through the first grouting channel 6 during the process of pulling out the casing 1 so that the The prefabricated pile 4 is fixedly cemented with the hole wall and bottom of the bedrock borehole 13 and the hole wall of the loose layer borehole 14 to form an integrated structure;
- the bedrock borehole 13 is filled by injecting cement slurry into the bedrock borehole 13 in advance, and then the precast pile 4 is settled into the bedrock borehole 13; then, through the process of lifting the casing 1, the precast pile 4 is passed through
- the grouting channel 5 continuously grouts the loose layer 8 and then completes the work of filling and fixing the bedrock layer 9 and the loose layer 8 respectively.
- the fixation of the bedrock borehole 13 by pre-grouting and re-implantation into the precast pile 4 can effectively allow the cement slurry to have sufficient time to be fixed with the bedrock borehole 13 and the cement slurry can be more adequate under the effect of the impact of the precast pile 4 falling.
- the cement slurry can be injected into the bedrock borehole 13 and the loose layer borehole 14 from the bottom and side of the precast pile 4, respectively, to make the cement slurry more
- the gap existing between the precast pile 4 and the bedrock borehole 13 and the gap between the precast pile 4 and the loose layer borehole 14 are evenly and sufficiently filled, so that the precast pile 4 and the ground around the borehole 2 are tightly cemented and fixed to Together form a precast pile foundation.
- the application first uses the casing 1 to cooperate with the drilling, then guides the precast pile 4 into the drilling 2, and finally injects the slurry 3 to fix the water formation.
- the pile foundation construction work of rivers, lakes, seas and other water strata is realized in the above manner. Because the process of building cofferdam islands and removing cofferdams is eliminated, and the above-mentioned casing 1 can also be used repeatedly, the large amount of engineering and long engineering cycle of the cast-in-place bored pile foundation can be solved under the premise of ensuring the construction strength And the problem of high engineering cost.
- a certain volume of slurry 3 is poured into the steel sleeve 1 before the steel sleeve 1 is pulled out, and the slurry 3 can enter the soil or sand layer at the bottom of the steel sleeve 1 to make the bottom of the borehole 2
- the ground is more tightly cemented with the bottom of the precast pile 4.
- a solid fixed structure is formed at the bottom of the borehole 2 after the slurry is formed.
- the slurry 3 will be tightly cemented with the ground around the borehole 2 so that the precast pile 4 and the ground around the sidewall of the drilled hole 2 will be tightly cemented together to form a precast pile foundation.
- the connection strength of the precast pile 4 with soil, sand and gravel in the foundation foundation environment or the marine engineering environment is improved.
- a prefabricated pile includes:
- a pile body which is a reinforced concrete prefabricated pile
- the grouting channel 5 is a grouting tube that is tied to the steel cage of the pile body.
- the liquid inlet end 11 of the grouting channel 5 extends out of the upper end surface of the pile body.
- the liquid end 12 extends from the lower end surface of the pile body and the side surface of the pile body.
- the casing 1 is made of a metal material, and the bottom end of the casing 1 has a toothed structure for cutting the soil.
- the application of the present invention does not specifically limit the position of the upper end of the precast pile 4.
- the upper end of the precast pile 4 is located below the water surface of the water area.
- the material composition of the slurry 3 is not specifically limited in the application of the present invention.
- the slurry 3 may also be a mortar or a chemical slurry, and two or three of a cement slurry, a mortar, and a chemical slurry. mixture.
- the application of the present invention does not specifically limit the connection manner between the grouting channel 5 and the reinforcing cage.
- the grouting channel 5 is preset on the reinforcing cage.
- the application of the present invention does not specifically limit the manner and number of the grouting channels on the precast pile 4.
- the precast pile 4 only includes a plurality of first grouting channels 6 located on the bottom surface of the precast pile 4.
- the precast pile 4 only includes a plurality of second grouting channels 7 located on the side of the precast pile 4.
- the application of the present invention does not specifically limit the role of the second grouting channel 7.
- the first grouting channel 6 and the The second grouting channel 7 continuously grouts into the loose layer borehole 14.
- the engineering implementation environment is a grouting consolidation method for a prefabricated pile with a full-bore drilled guide during the construction of a water area with a bedrock layer 9 at the bottom, including the following steps:
- Step S1 sinking the casing 1 to the bedrock layer; sinking a drill bit of the drill rig to the bedrock layer through the inner cavity of the casing 1, and drilling the bedrock layer to drill in the bedrock layer Forming said bedrock borehole 13;
- Step S2 at this time, the lower end portion of the casing 1 enters the opening edge of the inner cavity of the bedrock borehole 13, so that the end of the casing 1 is sleeved with the opening edge of the bedrock borehole 13, and the The drill bit of the drilling rig is sequentially removed from the bedrock borehole 13 and the casing 1;
- the drill bit of the rig drills the bedrock layer 9 through the casing 1, which can effectively solve the problem that the bedrock layer 9 is difficult to construct during the construction of the water area with the bedrock layer 9 at the bottom.
- the falling impact of the precast pile 4 can effectively make more slurry 3 and the foundation
- the rock formation 9 is sufficiently permeated and consolidated, so that the slurry 3 sufficiently fills the bottom and sides of the bedrock formation 9.
- the engineering implementation environment is a grouting consolidation method for a prefabricated pile with a full-bore drilled guide during the construction of a water area with a loose layer 8 at the bottom, including the following steps:
- step S1 the casing 1 is sunk to the loose layer 8, the drilling rig drills the loose layer 8 to form a loose layer drill hole 14, and drives the casing 1 into the loose layer 8; Removal of sediment in casing 1;
- Step S2 the casing 1 is housed in the loose layer borehole 14;
- Step S3 implanting the precast pile 4 into the loose layer drill hole 14 so that the precast pile 4 reaches the bottom of the hole of the loose layer drill hole 14;
Abstract
Description
Claims (12)
- 一种全套管钻孔导引预制桩的注浆固结方法,其特征在于,用于水域工程的地基基础施工,其包括以下步骤:A grouting consolidation method for a full-sleeve drill-guided prefabricated pile, which is characterized in that it is used for foundation construction of a water area project and includes the following steps:S1,驱动携带有套管(1)的钻机进行钻孔施工,钻孔施工至预设孔深,形成钻孔(2);S1. The drilling rig carrying the casing (1) is driven for drilling, and the drilling is performed to a preset hole depth to form a drilling (2);S2,所述套管(1)容置在所述钻孔(2)中;S2, the sleeve (1) is housed in the borehole (2);S3,将预制桩(4)植入所述钻孔(2),以使所述预制桩(4)到达所述钻孔(2)的孔底;S3. The precast pile (4) is implanted into the borehole (2), so that the precast pile (4) reaches the bottom of the hole of the borehole (2);S4,向所述钻孔(2)内注入浆液(3);S4. Inject slurry (3) into the borehole (2);S5,拔出所述套管(1),以使所述预制桩(4)和所述钻孔(2)的内腔固定胶结成一体结构。S5. Pull out the sleeve (1), so that the precast pile (4) and the inner cavity of the drilled hole (2) are fixed and cemented into an integrated structure.
- 根据权利要求1所述的全套管钻孔导引预制桩的注浆固结方法,其特征在于,步骤S3,所述将预制桩(4)植入所述钻孔(2),以使所述预制桩(4)到达所述钻孔(2)的孔底,包括以下步骤:向所述钻孔(2)内预先注入浆液(3);在所述浆液(3)凝固以前,将预制桩(4)植入所述钻孔(2)到达所述钻孔(2)的孔底。The method for grouting and consolidation of a prefabricated precast pile with full casing according to claim 1, characterized in that, in step S3, the precast pile (4) is implanted into the borehole (2) so that the The precast pile (4) reaching the bottom of the hole (2) includes the following steps: pre-injecting a slurry (3) into the hole (2); before the slurry (3) solidifies, prefabricating A post (4) is implanted into the borehole (2) to reach the bottom of the hole of the borehole (2).
- 根据权利要求1或2所述的全套管钻孔导引预制桩的注浆固结方法,其特征在于,The method for grouting and consolidation of a prefabricated drilled pile with full casing according to claim 1 or 2, wherein:所述预制桩(4)上预制有用于向所述钻孔(2)内注入浆液(3)的注浆通道(5),The precast pile (4) is prefabricated with a grouting channel (5) for injecting slurry (3) into the borehole (2),步骤S5,所述拔出所述套管(1),包括:在拔出所述套管(1)的过程中,通过所述预制桩(4)上的注浆通道(5)向所述钻孔(2)内持续注浆;Step S5. The pulling out the casing (1) includes: during the pulling out of the casing (1), through the grouting channel (5) on the precast pile (4) to the casing. Continuous grouting in the borehole (2);和/或,在步骤S4,所述向所述钻孔(2)内注入浆液(3),包括:在拔出所述套管(1)之前,通过所述预制桩(4)上的注浆通道(5)向所述钻孔(2)内注浆。And / or, in step S4, injecting the slurry (3) into the borehole (2) includes: before the casing (1) is pulled out, passing a note on the precast pile (4) The grouting channel (5) grouts into the borehole (2).
- 根据权利要求3所述的全套管钻孔导引预制桩的注浆固结方法,其特征在于,所述注浆通道(5)包括:位于所述预制桩(4)底面的第一注浆通道(6);The method for grouting and consolidation of a full casing drill-guided precast pile according to claim 3, wherein the grouting channel (5) comprises: a first grouting located on the bottom surface of the precast pile (4) Channel (6);步骤S5,所述拔出所述套管(1),包括:在拔出所述套管(1)的过程中,通过第一注浆通道(6)向所述钻孔(2)内持续注浆;Step S5. The pulling out the casing (1) includes: continuously pulling the casing (1) into the borehole (2) through the first grouting channel (6). Grouting和/或,在步骤S4,所述向所述钻孔(2)内注入浆液(3),包括:在拔出所述套管(1)之前,通过所述第一注浆通道(6)向所述钻孔(2)内注浆。And / or, in step S4, injecting the slurry (3) into the borehole (2) includes: before the casing (1) is pulled out, through the first grouting channel (6) Grouting into said borehole (2).
- 根据权利要求3或4所述的全套管钻孔导引预制桩的注浆固结方法,其特征在于,所述注浆通道(5)包括:位于所述预制桩(4)侧部向预制桩(4)和所述钻孔(2)之间注浆的第二注浆通道(7);The method for grouting and consolidation of a prefabricated full-hole casing-guided precast pile according to claim 3 or 4, characterized in that the grouting channel (5) comprises: prefabricating the side of the precast pile (4) A second grouting channel (7) for grouting between the pile (4) and the borehole (2);所述全套管钻孔导引预制桩的注浆固结方法还包括:步骤S6,通过第二注浆通道(7)向预制桩(4)和述钻孔(2)之间注浆。The method for grouting and consolidation of a prefabricated pile with a full casing drilling guide further includes: Step S6, grouting between the precast pile (4) and the borehole (2) through a second grouting channel (7).
- 根据权利要求1至5中任一项所述的全套管钻孔导引预制桩的注浆固结方法,其特征在于,在底部具有基岩层(9)的水域施工过程中,The grouting consolidation method for a full-casing drill-guided prefabricated pile according to any one of claims 1 to 5, characterized in that during the construction of a water area having a bedrock layer (9) at the bottom,步骤S1,所述驱动携带有套管(1)的钻机进行钻孔施工,钻孔施工至预设孔深,包括以下步骤:将所述套管(1)下沉至所述基岩层;将钻机其钻头通过所述套管(1)内腔下沉至所述基岩层,对所述基岩层钻孔以在所述基岩层形成基岩钻孔(13);Step S1, driving the drilling rig carrying the casing (1) to perform drilling construction to a predetermined hole depth, including the following steps: sinking the casing (1) to the bedrock layer; The drill rig sinks through the inner cavity of the casing (1) to the bedrock layer, and drills the bedrock layer to form a bedrock borehole (13) in the bedrock layer;步骤S2,所述将钻机的钻头移出所述基岩钻孔(13),所述套管(1)容置在基岩钻孔(13)中,包括:将所述钻机的钻头依次从所述基岩钻孔(13)和所述套管(1)中移出,所述套管(1)的下端进入所述基岩钻孔(13)内腔的开口边缘,In step S2, removing the drill bit from the bedrock borehole (13), and accommodating the casing (1) in the bedrock borehole (13) includes: sequentially moving the drill bit from the The bedrock borehole (13) and the casing (1) are removed, and the lower end of the casing (1) enters the opening edge of the inner cavity of the bedrock borehole (13),所述钻孔(2)包括所述基岩钻孔(13)。The borehole (2) includes the bedrock borehole (13).
- 根据权利要求1至5中任一项所述的全套管钻孔导引预制桩的注浆固结方法,其特征在于,在底部从上至下依次具有松散层(8)和基岩层(9)的水域施工过程中,The grouting consolidation method for a full-casing drill-guided prefabricated pile according to any one of claims 1 to 5, characterized in that it has a loose layer (8) and a bedrock layer (9) in order from the bottom to the bottom. ) During the construction of the waters,步骤S1,所述驱动携带有套管(1)的钻机进行钻孔施工,钻孔施工至预设孔深,包括:In step S1, driving the drilling rig carrying the casing (1) to perform drilling construction, and drilling construction to a preset hole depth includes:将所述套管(1)下沉至所述松散层(8),钻机对所述松散层(8)钻孔以带动所述套管(1)穿过所述松散层(8),以形成松散层钻孔(14);The casing (1) is sunk to the loose layer (8), and a drilling machine drills the loose layer (8) to drive the casing (1) through the loose layer (8) to Forming a loose layer borehole (14);将所述套管(1)内的泥沙移出;Removing the sediment in the casing (1);将钻机其钻头通过所述套管(1)内腔下沉至所述基岩层,对所述基岩层钻孔以在所述基岩层形成基岩钻孔(13);Sinking a drill bit of the rig through the inner cavity of the casing (1) to the bedrock layer, drilling the bedrock layer to form a bedrock borehole (13) in the bedrock layer;步骤S2,所述将钻机的钻头移出所述钻孔(2),所述套管(1)容置在钻孔(2)中,包括:将钻机的钻头依次从所述基岩钻孔(13)和所述套管(1)中移出,所述套管(1)的下端进入所述基岩钻孔(13)内腔的开口边缘;Step S2, the step of moving the drill bit out of the borehole (2), and the casing (1) accommodated in the borehole (2) includes: sequentially drilling the drill bit from the bedrock ( 13) and removed from the casing (1), the lower end of the casing (1) enters the opening edge of the inner cavity of the bedrock borehole (13);所述钻孔(2)包括所述松散层钻孔(14)和所述基岩钻孔(13)。The borehole (2) includes the loose layer borehole (14) and the bedrock borehole (13).
- 根据权利要求1至5中任一项所述的全套管钻孔导引预制桩的注浆固结方法,其特征在于,在底部具有松散层(8)的水域施工过程中,The grouting consolidation method for a full-casing drill-guided prefabricated pile according to any one of claims 1 to 5, characterized in that during the construction of a water area with a loose layer (8) at the bottom,步骤S1,所述驱动携带有套管(1)的钻机进行钻孔施工,钻孔施工至预设孔深,包括以下步骤:将所述套管(1)下沉至所述松散层(8),钻机对所述松散层(8)钻孔形成松散层钻孔(14),并带动所述套管(1)进入所述松散层(8);将所述套管(1)内的泥沙移出。In step S1, the driving of the drilling rig carrying the casing (1) to perform drilling construction to a preset hole depth includes the following steps: sinking the casing (1) to the loose layer (8) ), A rig drills the loose layer (8) to form a loose layer bore (14), and drives the casing (1) into the loose layer (8); The sediment was removed.
- 根据权利要求6至8中任一项所述的全套管钻孔导引预制桩的注浆固结方法,其特征在于,所述预制桩(4)的上端位于水域其水面以上,和/或所述预制桩(4)的上端位于水域其水面以下。The grouting consolidation method for a full-casing drill-guided prefabricated pile according to any one of claims 6 to 8, wherein the upper end of the prefabricated pile (4) is located above the water surface of the water area, and / or The upper end of the prefabricated pile (4) is located below the water surface of the water area.
- 根据权利要求1至9中任一项所述的全套管钻孔导引预制桩的注浆固结方法,其特征在于,所述浆液(3)包括水泥浆和/或砂浆和/或化学浆。The grouting consolidation method for a full-casing drill-guided precast pile according to any one of claims 1 to 9, wherein the slurry (3) comprises cement slurry and / or mortar and / or chemical slurry .
- 一种预制桩,其特征在于,包括A prefabricated pile, comprising桩身;Pile body注浆通道(5),设置在所述桩身上,所述注浆通道(5)的进液端(11)延伸出所述桩身的上端面,所述注浆通道(5)的出液端(12)延伸出所述桩身的下端面和/或所述桩身的侧面。The grouting channel (5) is arranged on the pile body, and the liquid inlet end (11) of the grouting channel (5) extends out of the upper end surface of the pile body, and the liquid out of the grouting channel (5) The end (12) extends from the lower end surface of the pile body and / or the side surface of the pile body.
- 根据权利要求11所述的预制桩,其特征在于,The precast pile according to claim 11, wherein:所述桩身为钢筋混凝土预制桩,所述注浆通道(5)为预制在所述桩身其钢筋笼上的注浆管。The pile body is a reinforced concrete prefabricated pile, and the grouting channel (5) is a grouting pipe prefabricated on the reinforced cage of the pile body.
Priority Applications (8)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020217010783A KR20210058901A (en) | 2018-09-25 | 2019-06-14 | Full casing drilling guide grouting and consolidation method of prefabricated pile and its prefabricated pile |
US17/277,860 US20210348355A1 (en) | 2018-09-25 | 2019-06-14 | Grouting consolidation method for full casing borehole guide prefabricated pile and prefabricated pile therefor |
EP19865349.5A EP3839149A4 (en) | 2018-09-25 | 2019-06-14 | Grouting consolidation method for full casing borehole guide prefabricated pile and prefabricated pile therefor |
SG11202102769TA SG11202102769TA (en) | 2018-09-25 | 2019-06-14 | Grouting consolidation method for full casing borehole guide prefabricated pile and prefabricated pile therefor |
CN201980000859.3A CN110896644B (en) | 2018-09-25 | 2019-06-14 | Grouting consolidation method for full-casing drilling guide precast pile |
JP2021515169A JP2022502586A (en) | 2018-09-25 | 2019-06-14 | Grouting consolidation method of ready-made piles guided by all-casing excavation, and the ready-made piles |
CONC2021/0003362A CO2021003362A2 (en) | 2018-09-25 | 2021-03-15 | Grout consolidation method for precast pile with full hole casing guide and precast pile for it |
PH12021550571A PH12021550571A1 (en) | 2018-09-25 | 2021-03-15 | Grouting consolidation method for full casing borehole guide prefabricated pile and prefabricated pile therefor |
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811091450.0A CN109295972A (en) | 2018-09-25 | 2018-09-25 | Full-sleeve engineering method prefabricated pile perfusion slurry and grouting behind shaft or drift lining concretion technology |
CN201811091450.0 | 2018-09-25 |
Publications (1)
Publication Number | Publication Date |
---|---|
WO2020062940A1 true WO2020062940A1 (en) | 2020-04-02 |
Family
ID=65163301
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
PCT/CN2019/091230 WO2020062940A1 (en) | 2018-09-25 | 2019-06-14 | Grouting consolidation method for full casing borehole guide prefabricated pile and prefabricated pile therefor |
Country Status (9)
Country | Link |
---|---|
US (1) | US20210348355A1 (en) |
EP (1) | EP3839149A4 (en) |
JP (1) | JP2022502586A (en) |
KR (1) | KR20210058901A (en) |
CN (1) | CN109295972A (en) |
CO (1) | CO2021003362A2 (en) |
PH (1) | PH12021550571A1 (en) |
SG (1) | SG11202102769TA (en) |
WO (1) | WO2020062940A1 (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111997620A (en) * | 2020-07-28 | 2020-11-27 | 中铁第四勘察设计院集团有限公司 | Grouting construction system and method for karst collapse area |
CN113250238A (en) * | 2021-05-19 | 2021-08-13 | 中交第三航务工程局有限公司 | Rock-socketed construction method of marine ultra-large-diameter single pile based on loosening ring theory |
CN114562328A (en) * | 2022-04-02 | 2022-05-31 | 中国矿业大学 | Method for controlling surface subsidence by grouting and filling unconsolidated layer of bedrock top boundary |
CN115075238A (en) * | 2022-06-13 | 2022-09-20 | 陕西正诚路桥工程研究院有限公司 | Reinforcing method in bored pile construction based on overwater operation platform |
CN115323999A (en) * | 2022-09-14 | 2022-11-11 | 赤峰中色白音诺尔矿业有限公司 | Segmented grouting construction device for culvert pipes of tailing pond and construction method thereof |
Families Citing this family (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110896644B (en) * | 2018-09-25 | 2021-04-09 | 高永光 | Grouting consolidation method for full-casing drilling guide precast pile |
CN109295972A (en) * | 2018-09-25 | 2019-02-01 | 高永光 | Full-sleeve engineering method prefabricated pile perfusion slurry and grouting behind shaft or drift lining concretion technology |
CN110565639B (en) * | 2019-09-11 | 2021-03-23 | 中船第九设计研究院工程有限公司 | Bored concrete pile hole forming and side wall grouting construction method for coral sand foundation |
CN113309089A (en) * | 2021-06-11 | 2021-08-27 | 河北省水利规划设计研究院有限公司 | Prefabricated hollow pile and construction method for taking soil and planting pile |
CN114753376A (en) * | 2022-03-28 | 2022-07-15 | 中电建十一局工程有限公司 | Method for excavating supporting slurry for deep foundation pit in gravel stratum |
CN115288212B (en) * | 2022-07-05 | 2023-05-16 | 湖北工业大学 | Optical fiber implantation device and implantation method for existing pile wall |
CN115233685B (en) * | 2022-08-01 | 2023-07-14 | 中交四航工程研究院有限公司 | Recyclable grouting device for maintaining horizontal rigidity of pile foundation and construction method thereof |
CN115478560A (en) * | 2022-09-28 | 2022-12-16 | 苏州枫石堂工程科技有限公司 | Wall cracking grouting reinforcement method |
KR102602249B1 (en) | 2023-02-14 | 2023-11-16 | 우창건설 주식회사 | Apparatus for guiding the casing and construction method using the same |
Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2000129669A (en) * | 1998-10-22 | 2000-05-09 | Asahi Chem Ind Co Ltd | Connecting method of prefabricated pile |
CN102002945A (en) * | 2010-03-25 | 2011-04-06 | 中国京冶工程技术有限公司 | Capsule type anti-corrosion device with pile shoe and anti-corrosion and construction method using device |
WO2011105703A2 (en) | 2010-02-26 | 2011-09-01 | Song Gi-Yong | Method for constructing a steel pipe/concrete composite pile in which the steel pipe is buried integrally with bedrock, and pile construction |
EP2527539A1 (en) | 2011-05-27 | 2012-11-28 | BAUER Maschinen GmbH | Submarine drilling assembly and method for inserting a foundation element into the soil of a body of water |
EP2650446A1 (en) | 2012-04-12 | 2013-10-16 | Herrenknecht AG | Method of creating a foundation for a offshore structure |
CN102691296B (en) * | 2012-05-22 | 2015-02-11 | 广州市建筑科学研究院有限公司 | Pipe pile foundation for static-pressure grouting on pile side and rotary jet grouting at pile bottom and construction method thereof |
EP2930275A1 (en) | 2014-04-08 | 2015-10-14 | Herrenknecht AG | System and method for producing a foundation for a building in water |
CN105442594A (en) * | 2015-12-04 | 2016-03-30 | 荣盛建设工程有限公司 | Hole reaming mud-jacking construction technology for prestress hollow square pile with built-in mud-jacking pipe |
CN107794925A (en) * | 2017-10-31 | 2018-03-13 | 浙江大学城市学院 | The grouting behind shaft or drift lining cast-in-situ concrete thin-wall and construction method of a kind of reserved grouting pipeline |
CN109295972A (en) * | 2018-09-25 | 2019-02-01 | 高永光 | Full-sleeve engineering method prefabricated pile perfusion slurry and grouting behind shaft or drift lining concretion technology |
Family Cites Families (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US1865652A (en) * | 1929-09-20 | 1932-07-05 | Raymond Concrete Pile Co | Method and apparatus for placing concrete in piles |
JPH05132930A (en) * | 1991-11-07 | 1993-05-28 | Jiototsupu:Kk | Developing method of foundation pile with drain layer |
NL9301176A (en) * | 1993-07-05 | 1995-02-01 | Verstraeten Beheersmij Bv | Method for forming a foundation pile in the ground using a prefabricated pile shaft. |
JPH1171758A (en) * | 1997-08-27 | 1999-03-16 | Nippon Steel Corp | Method for driving pile to rock mass |
JP2000257062A (en) * | 1999-03-05 | 2000-09-19 | Taisei Corp | Steel pipe pile pitching method |
JP2002155531A (en) * | 2000-11-21 | 2002-05-31 | Yoshitada Miyake | Pile burial method |
US20050019104A1 (en) * | 2003-07-23 | 2005-01-27 | Derald Christians | Soil stabilization and pile formation method |
JP4667479B2 (en) * | 2008-03-03 | 2011-04-13 | 中国電力株式会社 | Pile attachment / detachment structure and pile construction method |
JP6260931B2 (en) * | 2013-12-04 | 2018-01-17 | 株式会社大林組 | Steel pipe pile and its embedding method |
-
2018
- 2018-09-25 CN CN201811091450.0A patent/CN109295972A/en not_active Withdrawn
-
2019
- 2019-06-14 US US17/277,860 patent/US20210348355A1/en not_active Abandoned
- 2019-06-14 KR KR1020217010783A patent/KR20210058901A/en not_active Application Discontinuation
- 2019-06-14 SG SG11202102769TA patent/SG11202102769TA/en unknown
- 2019-06-14 JP JP2021515169A patent/JP2022502586A/en active Pending
- 2019-06-14 EP EP19865349.5A patent/EP3839149A4/en active Pending
- 2019-06-14 WO PCT/CN2019/091230 patent/WO2020062940A1/en active Application Filing
-
2021
- 2021-03-15 CO CONC2021/0003362A patent/CO2021003362A2/en unknown
- 2021-03-15 PH PH12021550571A patent/PH12021550571A1/en unknown
Patent Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2000129669A (en) * | 1998-10-22 | 2000-05-09 | Asahi Chem Ind Co Ltd | Connecting method of prefabricated pile |
WO2011105703A2 (en) | 2010-02-26 | 2011-09-01 | Song Gi-Yong | Method for constructing a steel pipe/concrete composite pile in which the steel pipe is buried integrally with bedrock, and pile construction |
CN102002945A (en) * | 2010-03-25 | 2011-04-06 | 中国京冶工程技术有限公司 | Capsule type anti-corrosion device with pile shoe and anti-corrosion and construction method using device |
EP2527539A1 (en) | 2011-05-27 | 2012-11-28 | BAUER Maschinen GmbH | Submarine drilling assembly and method for inserting a foundation element into the soil of a body of water |
EP2650446A1 (en) | 2012-04-12 | 2013-10-16 | Herrenknecht AG | Method of creating a foundation for a offshore structure |
CN102691296B (en) * | 2012-05-22 | 2015-02-11 | 广州市建筑科学研究院有限公司 | Pipe pile foundation for static-pressure grouting on pile side and rotary jet grouting at pile bottom and construction method thereof |
EP2930275A1 (en) | 2014-04-08 | 2015-10-14 | Herrenknecht AG | System and method for producing a foundation for a building in water |
CN105442594A (en) * | 2015-12-04 | 2016-03-30 | 荣盛建设工程有限公司 | Hole reaming mud-jacking construction technology for prestress hollow square pile with built-in mud-jacking pipe |
CN107794925A (en) * | 2017-10-31 | 2018-03-13 | 浙江大学城市学院 | The grouting behind shaft or drift lining cast-in-situ concrete thin-wall and construction method of a kind of reserved grouting pipeline |
CN109295972A (en) * | 2018-09-25 | 2019-02-01 | 高永光 | Full-sleeve engineering method prefabricated pile perfusion slurry and grouting behind shaft or drift lining concretion technology |
Non-Patent Citations (1)
Title |
---|
See also references of EP3839149A4 |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111997620A (en) * | 2020-07-28 | 2020-11-27 | 中铁第四勘察设计院集团有限公司 | Grouting construction system and method for karst collapse area |
CN113250238A (en) * | 2021-05-19 | 2021-08-13 | 中交第三航务工程局有限公司 | Rock-socketed construction method of marine ultra-large-diameter single pile based on loosening ring theory |
CN114562328A (en) * | 2022-04-02 | 2022-05-31 | 中国矿业大学 | Method for controlling surface subsidence by grouting and filling unconsolidated layer of bedrock top boundary |
CN114562328B (en) * | 2022-04-02 | 2022-12-02 | 中国矿业大学 | Method for controlling surface subsidence by grouting and filling unconsolidated layer of bedrock top boundary |
CN115075238A (en) * | 2022-06-13 | 2022-09-20 | 陕西正诚路桥工程研究院有限公司 | Reinforcing method in bored pile construction based on overwater operation platform |
CN115323999A (en) * | 2022-09-14 | 2022-11-11 | 赤峰中色白音诺尔矿业有限公司 | Segmented grouting construction device for culvert pipes of tailing pond and construction method thereof |
CN115323999B (en) * | 2022-09-14 | 2024-02-27 | 赤峰中色白音诺尔矿业有限公司 | Sectional grouting construction device for culvert pipes of tailing pond and construction method thereof |
Also Published As
Publication number | Publication date |
---|---|
US20210348355A1 (en) | 2021-11-11 |
SG11202102769TA (en) | 2021-04-29 |
JP2022502586A (en) | 2022-01-11 |
KR20210058901A (en) | 2021-05-24 |
EP3839149A1 (en) | 2021-06-23 |
CN109295972A (en) | 2019-02-01 |
CO2021003362A2 (en) | 2021-07-19 |
PH12021550571A1 (en) | 2021-10-25 |
EP3839149A4 (en) | 2022-04-20 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
WO2020062940A1 (en) | Grouting consolidation method for full casing borehole guide prefabricated pile and prefabricated pile therefor | |
CN103924987B (en) | A kind of SMW engineering method stake tunnel shielding portal seepage-proof structure and construction method thereof | |
CN108086328A (en) | A kind of dynamic sealing, assembled building enclosure and its construction method from recharge | |
CN105442605B (en) | Extract PHC and be reused in deep foundation pit supporting construction method | |
CN108166483A (en) | Bored pile construction method | |
CN101205721A (en) | Method for surrounding water by combination of steel cofferdam and heavy-pressure rotary-spraying pile in deep-water low-pile cap construction | |
CN108532586A (en) | A kind of construction method of garage parking diaphram wall | |
CN112281829A (en) | Composite pile foundation structure and construction method thereof | |
CN106948340A (en) | A kind of construction method of the Manual excavated pile structure of high polymer grouting protection | |
CN110295597A (en) | Close to buildings Soft Clay pattern foundation pit supporting structure steel sheet pile is pulled out and grouting strengthening method | |
CN112681295A (en) | Construction method of concrete-filled steel tube pile foundation and concrete-filled steel tube pile foundation | |
CN103953030A (en) | Threaded screwing inserting bar compaction filling pile | |
CN104404956A (en) | Construction method for pedestal piles | |
CN110896644B (en) | Grouting consolidation method for full-casing drilling guide precast pile | |
JP2003268767A (en) | Construction method for double tube digging small diameter pile using hole excavating rod | |
CN203796288U (en) | Water seepage prevention structure used for shield entrance door employing SMW piles | |
CN201459749U (en) | Stable structure for construction platform of deep water steel pipe pile | |
CN101603311B (en) | Jet grouting pile construction method adopting heavy hammer-tamping compaction soil preformed hole | |
CN208472716U (en) | Crack geology mortar leakage prevention drill-pouring pilework | |
JP2003147782A (en) | Foundation structure for constructing new building on existing basement and its construction method | |
CN105040705A (en) | Ground foundation treatment construction technology under multi-karst-cave geological conditions | |
CN115262614A (en) | Embedded rock-socketed pile foundation and construction method | |
CN106638646A (en) | Secondary bottom sealing structure of open caisson and construction method | |
CN105951743A (en) | Plum blossom-shaped profile steel cement stirring wall | |
JP3810882B2 (en) | Construction method of cast-in-place pile in confined groundwater zone |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
121 | Ep: the epo has been informed by wipo that ep was designated in this application |
Ref document number: 19865349 Country of ref document: EP Kind code of ref document: A1 |
|
DPE1 | Request for preliminary examination filed after expiration of 19th month from priority date (pct application filed from 20040101) | ||
ENP | Entry into the national phase |
Ref document number: 2021515169 Country of ref document: JP Kind code of ref document: A |
|
ENP | Entry into the national phase |
Ref document number: 2019865349 Country of ref document: EP Effective date: 20210315 |
|
REG | Reference to national code |
Ref country code: BR Ref legal event code: B01A Ref document number: 112021004781 Country of ref document: BR |
|
WWE | Wipo information: entry into national phase |
Ref document number: 2101001716 Country of ref document: TH |
|
NENP | Non-entry into the national phase |
Ref country code: DE |
|
ENP | Entry into the national phase |
Ref document number: 20217010783 Country of ref document: KR Kind code of ref document: A |
|
REG | Reference to national code |
Ref country code: BR Ref legal event code: B01E Ref document number: 112021004781 Country of ref document: BR Free format text: 1) ESCLARECER, EM ATE 60 (SESSENTA) DIAS, APRESENTANDO DOCUMENTACAO COMPROBATORIA, A INCLUSAO DO DEPOSITANTE BEIJING KERUIHENGJI CONSTRUCTION TECHNOLOGY DEVELOPMENT CO., LTD. CONSTANTE NA PETICAO INICIAL NO 870210023936 DE 13/03/2021 E NAO INCLUSO NA PUBLICACAO INTERNACIONAL WO/2020/062940 DE 02/04/2020. O DOCUMENTO DE CESSAO DA PRIORIDADE ENVIADO NA PETICAO NAO SERVE COMO DOCUMENTO PARA INCLUSAO DE DEPOSITANTE DO PCT.2) APRESENTAR, EM ATE 60 (SESSENTA) DIAS, DOCUMENTOS COMPROBATORIOS QUE EXPLIQUEM E REGULARIZEM A DIVERGENCIA NO NOME DOS INVENTORES E DEPOSITANTES CONSTANTES NA PUBLICACAO INTERNACIONAL WO/2020/062940 DE 02/04/2020 COMO YONGGUAN GAO E YUNFEI GAO CONSTANTE NO FORMULARIO DA PETI |
|
ENP | Entry into the national phase |
Ref document number: 112021004781 Country of ref document: BR Kind code of ref document: A2 Effective date: 20210313 |