WO2020062940A1 - Grouting consolidation method for full casing borehole guide prefabricated pile and prefabricated pile therefor - Google Patents

Grouting consolidation method for full casing borehole guide prefabricated pile and prefabricated pile therefor Download PDF

Info

Publication number
WO2020062940A1
WO2020062940A1 PCT/CN2019/091230 CN2019091230W WO2020062940A1 WO 2020062940 A1 WO2020062940 A1 WO 2020062940A1 CN 2019091230 W CN2019091230 W CN 2019091230W WO 2020062940 A1 WO2020062940 A1 WO 2020062940A1
Authority
WO
WIPO (PCT)
Prior art keywords
borehole
casing
grouting
pile
bedrock
Prior art date
Application number
PCT/CN2019/091230
Other languages
French (fr)
Chinese (zh)
Inventor
高永光
高云飞
Original Assignee
高永光
高云飞
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 高永光, 高云飞 filed Critical 高永光
Priority to KR1020217010783A priority Critical patent/KR20210058901A/en
Priority to US17/277,860 priority patent/US20210348355A1/en
Priority to EP19865349.5A priority patent/EP3839149A4/en
Priority to SG11202102769TA priority patent/SG11202102769TA/en
Priority to CN201980000859.3A priority patent/CN110896644B/en
Priority to JP2021515169A priority patent/JP2022502586A/en
Publication of WO2020062940A1 publication Critical patent/WO2020062940A1/en
Priority to CONC2021/0003362A priority patent/CO2021003362A2/en
Priority to PH12021550571A priority patent/PH12021550571A1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • E02D15/06Placing concrete under water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/62Compacting the soil at the footing or in or along a casing by forcing cement or like material through tubes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D11/00Methods or apparatus specially adapted for both placing and removing sheet pile bulkheads, piles, or mould-pipes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • E02D15/04Placing concrete in mould-pipes, pile tubes, bore-holes or narrow shafts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/08Sinking workpieces into water or soil inasmuch as not provided for elsewhere
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/52Submerged foundations, i.e. submerged in open water
    • E02D27/525Submerged foundations, i.e. submerged in open water using elements penetrating the underwater ground
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • E02D5/385Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds with removal of the outer mould-pipes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • E02D7/26Placing by using several means simultaneously
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • E02D7/28Placing of hollow pipes or mould pipes by means arranged inside the piles or pipes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork

Definitions

  • the invention relates to the technical field of foundations, in particular to a grouting consolidation method for a full-sleeve drill-guided precast pile and its precast pile.
  • the above-mentioned cofferdam island construction is also required to be removed, resulting in a huge amount of construction work using the above-mentioned cofferdam island construction method, which has the problems of long engineering cycle and high engineering cost.
  • the hammered steel pipe pile is constructed by hammering and sinking into the foundation of the water area, when the hammered steel pipe pile encounters a hard bedrock, the end of the hammered steel pipe pile may be curled or even unable to hit.
  • the present invention aims to provide a grouting consolidation method of a full casing drilled guide prefabricated pile and its prefabricated pile, in order to solve the prior art in the construction of a water-based foundation under various formation conditions, especially in marine engineering.
  • the present application provides a grouting consolidation method for a full casing drilled guide prefabricated pile, which is used for foundation construction of a water area project, and includes the following steps:
  • the prefabricated pile is implanted into the borehole, so that the prefabricated pile reaches the bottom of the hole of the borehole;
  • Step S3 the step of implanting a precast pile into the borehole so that the precast pile reaches the bottom of the hole of the borehole includes the following steps: pre-injecting a slurry into the borehole; before the slurry solidifies , Implanting a prefabricated pile into the borehole to the bottom of the borehole.
  • the prefabricated pile is prefabricated with a grouting channel for injecting slurry into the borehole
  • Step S5 the pulling out the casing includes: during the pulling out of the casing, continuously grouting into the borehole through a grouting channel on the precast pile;
  • injecting the slurry into the borehole includes: before the casing is pulled out, grouting into the borehole through a grouting channel on the precast pile.
  • the grouting channel includes: a first grouting channel located on a bottom surface of the precast pile;
  • Step S5 the pulling out the casing includes: continuously pulling into the borehole through the first grouting channel and / or the second grouting channel during the process of pulling out the casing.
  • injecting the slurry into the borehole includes: before the casing is pulled out, grouting into the borehole through the first grouting channel.
  • Step S1 driving the drilling rig carrying the casing to perform drilling construction to a preset hole depth, including the following steps: sinking the casing to the bedrock layer; passing the drill's drill bit through the casing The inner cavity of the casing sinks to the bedrock layer, and drills the bedrock layer to form the bedrock borehole in the bedrock layer;
  • Step S2 the step of moving the drill bit of the rig out of the bedrock borehole, and the casing being accommodated in the bedrock borehole, comprises: sequentially drilling the drill bit from the bedrock and the Moving out of the casing, the lower end of the casing entering the opening edge of the borehole cavity of the bedrock,
  • the borehole includes the bedrock borehole.
  • the above loose layer is a loose layer such as sand
  • step S1 driving the drilling rig carrying the casing to perform drilling construction, and drilling construction to a preset hole depth includes:
  • Step S2 the step of removing the drill bit of the drilling rig from the borehole and accommodating the casing in the borehole includes: drilling the drill bit of the rig from the bedrock and the casing in order. Removed, the lower end of the casing enters the opening edge of the bedrock bore cavity;
  • the drilling includes the loose layer drilling and the bedrock drilling.
  • step S1 driving the drilling rig carrying the casing to perform drilling construction to a preset hole depth includes the steps of sinking the casing to the loose layer, and drilling the drill to the loose layer.
  • the hole forms a loose layer drill hole, and drives the casing into the loose layer; removing the sediment in the casing.
  • the upper end of the precast pile is located above the water surface of the water area, and / or the upper end of the precast pile is located below the water surface of the water area.
  • the slurry includes cement slurry and / or mortar and / or chemical slurry.
  • a prefabricated pile including
  • the grouting channel is provided on the pile body, the liquid inlet end of the grouting channel extends out of the upper end surface of the pile body, the liquid outlet end of the grouting channel extends out of the lower end surface of the pile body and / Or the side of the pile.
  • the pile body is a reinforced concrete prefabricated pile
  • the grouting channel is a grouting pipe prefabricated on a reinforced cage of the pile body.
  • a grouting consolidation method for a full-casing drill-guided prefabricated pile for foundation construction of a water area project comprising the following steps: S1, driving a drilling rig carrying a casing for drilling construction, drilling Construction to a preset hole depth; S2, the casing is accommodated in the borehole; S3, a precast pile is implanted into the borehole so that the precast pile reaches the bottom of the hole of the borehole; S4 , Injecting slurry into the borehole; S5, pulling out the sleeve so that the precast pile and the inner cavity of the borehole are fixed and cemented into an integrated structure.
  • this application In order to adapt to the stratum of a variety of water engineering, especially the marine engineering environment that needs to be constructed on the seawater of rivers and lakes, this application first uses a casing to cooperate with drilling, then introduces the precast pile guide into the bottom of the hole, and finally injects slurry Realize the construction of water stratum in a fixed way.
  • casing can be used to assist drilling to adapt to different underwater stratum structures.
  • the introduction of prefabricated pile guides into the bottom of the hole can effectively ensure the foundation of water area engineering. Stable and reliable construction.
  • the pile foundation construction work of rivers, lakes, seas and other water strata is realized in the above manner.
  • step S3 the precast pile is implanted into the drilled hole so that the precast pile reaches the hole of the drilled hole
  • the bottom includes the following steps: pre-injecting a slurry into the borehole; before the slurry is solidified, a precast pile is implanted into the borehole to reach the bottom of the borehole.
  • the grouting consolidation method for a full-casing drill-guided prefabricated pile provided in the present invention, the prefabricated pile is prefabricated with a grouting channel for injecting slurry into the borehole, step S5, the extraction station
  • the casing includes: during the process of extracting the casing, continuously grouting into the borehole through a grouting channel on the prefabricated pile; during the process of extracting the casing, through the above
  • the grouting channel of the prefabricated pile can simply and conveniently make the slurry flow into the borehole to fill the gap generated during the pullout of the casing.
  • step S4 injecting the slurry into the borehole includes: before the casing is pulled out, grouting into the borehole through a grouting channel on the precast pile. Before the casing is pulled out, the slurry is injected into the borehole through the grouting channel, or the slurry is directly poured into the borehole.
  • the operation is simple and convenient, which can make the precast pile and the ground around the borehole 2 Tightly cemented together to form a precast pile foundation, thereby improving the connection strength of the precast pile with soil, sand and gravel in the marine engineering environment.
  • the grouting channel comprises: a first grouting channel located on the bottom surface of the prefabricated pile; Set up grouting channels, so that the slurry can be injected into the boreholes from the bottom of the precast pile, so that the slurry can more evenly and fully fill the gap between the precast pile and the borehole, so that the precast pile and the ground around the borehole 2 are tightly cemented and fixed. Together form a precast pile foundation.
  • step S1 said driving a drilling rig carrying a casing for drilling construction, drilling
  • the hole construction to a preset hole depth includes the following steps: sinking the casing to the bedrock layer; sinking a drill bit of the rig to the bedrock layer through the casing cavity, and drilling the bedrock layer To form the bedrock borehole in the bedrock layer.
  • Step S2 the step of moving the drill bit of the rig out of the bedrock borehole, and the casing being accommodated in the bedrock borehole, comprises: sequentially drilling the drill bit from the bedrock and the The casing is removed, the lower end of the casing enters the opening edge of the inner cavity of the bedrock borehole, and the borehole includes the bedrock borehole.
  • the drill bit of the rig drills the bedrock layer through the casing, which can effectively solve the problem that the bedrock layer is difficult to construct during the construction of the water area with the bedrock layer at the bottom.
  • the grouting consolidation method for a full-casing drill-guided prefabricated pile provided by the present invention, in a water area construction process with a loose layer and a bedrock layer in order from the bottom to the bottom, step S1, the drive carries a casing Drilling rig for drilling construction to a preset hole depth includes sinking the casing to the loose layer, and drilling the hole to the loose layer to drive the casing through the loose layer Layer to form a loose layer for drilling; removing earth, rock, and sediment in the casing; sinking a drill bit of the rig through the casing cavity to the bedrock layer, and drilling the bedrock layer to form the bedrock layer Rock formations form the bedrock borehole.
  • Step S2 the step of removing the drill bit of the drilling rig from the borehole and accommodating the casing in the borehole includes: drilling the drill bit of the rig from the bedrock and the casing in order. When removed, the lower end of the casing enters the open edge of the inner cavity of the bedrock borehole; the borehole includes the loose layer borehole and the bedrock borehole.
  • the loose layer is first drilled by the drill's drill bit, and then the sediment is discharged. Drilling the bedrock layer through a drill bit through the casing effectively solves the problem that the above waters are difficult to construct because of the loose layer and the bedrock layer.
  • the bedrock boreholes are filled by injecting slurry into the bedrock boreholes in advance, and then the precast piles are settled into the bedrock boreholes.
  • the grouting channels of the precast piles are continuously loosened.
  • the layer grouting method further completes the work of filling and fixing the bedrock layer and the loose layer respectively.
  • the bedrock drilling adopts the fixing method of pre-grouting and re-implanting the precast pile, which can effectively make the slurry have sufficient time to be cemented and fixed with the bedrock drilling, and the slurry can penetrate the bedrock layer more fully under the impact of the precast pile's falling impact; loose
  • the layer is grouted into the loose layer during the casing lifting process, which can effectively fill the gap between the precast pile and the casing with slurry to complete the above grouting work, so that the slurry can fully precast the pile and loose.
  • the formations around the boreholes are cemented together.
  • FIG. 1 is a schematic diagram of installation steps of a full casing of a water area having a loose layer and a bedrock layer provided by the present invention
  • FIG. 2 is a schematic diagram of steps for pre-grouting in a water area having a loose layer and a bedrock layer provided in the present invention toward the bedrock layer;
  • FIG. 3 is a schematic diagram of steps for sinking a precast pile to the bottom of a pre-grouted borehole in a water area having a loose layer and a bedrock layer provided by the present invention
  • FIG. 4 is a schematic diagram of a step of taking out a full casing in a water area having a loose layer and a bedrock layer provided by the present invention
  • FIG. 5 is a schematic diagram of a connection structure between a precast pile and a bottom of a water area after completion of a grouting consolidation process of a full casing drilled guide prefabricated pile in a water area having a loose layer and a bedrock layer provided by the present invention
  • FIG. 6 is a schematic structural diagram of the precast pile sinking to the bottom of a borehole provided by the present invention.
  • FIG. 7 is a schematic structural diagram of a connection structure between a precast pile and a foundation foundation environment when a full casing is taken out after a full casing drilling and grouting process provided by the present invention is completed.
  • This embodiment provides a grouting consolidation method for a full-casing drill-guided prefabricated pile.
  • the engineering implementation environment is shown in Figs. 1 to 7.
  • the bottom layer has a loose layer 8 and a bedrock layer 9 in this order from top to bottom.
  • the grouting consolidation method of a full-casing drill-guided precast pile includes the following steps:
  • step S1 the casing 1 is sunk to the loose layer 8 through the water surface 10, and a drilling rig drills the loose layer 8 to drive the casing 1 through the loose layer 8 to form a loose layer.
  • step S2 the drill bit of the rig is sequentially removed from the bedrock borehole 13 and the casing 1, and at this time, the lower end portion of the casing 1 enters the opening edge of the inner cavity of the bedrock borehole 13. So that the end of the casing 1 is sleeved with the opening edge of the bedrock borehole 13;
  • the grouting channel 5 includes: The first grouting channel 6 on the bottom surface of the prefabricated pile 4 is continuously grouting into the loose layer borehole 14 through the first grouting channel 6 during the process of pulling out the casing 1 so that the The prefabricated pile 4 is fixedly cemented with the hole wall and bottom of the bedrock borehole 13 and the hole wall of the loose layer borehole 14 to form an integrated structure;
  • the bedrock borehole 13 is filled by injecting cement slurry into the bedrock borehole 13 in advance, and then the precast pile 4 is settled into the bedrock borehole 13; then, through the process of lifting the casing 1, the precast pile 4 is passed through
  • the grouting channel 5 continuously grouts the loose layer 8 and then completes the work of filling and fixing the bedrock layer 9 and the loose layer 8 respectively.
  • the fixation of the bedrock borehole 13 by pre-grouting and re-implantation into the precast pile 4 can effectively allow the cement slurry to have sufficient time to be fixed with the bedrock borehole 13 and the cement slurry can be more adequate under the effect of the impact of the precast pile 4 falling.
  • the cement slurry can be injected into the bedrock borehole 13 and the loose layer borehole 14 from the bottom and side of the precast pile 4, respectively, to make the cement slurry more
  • the gap existing between the precast pile 4 and the bedrock borehole 13 and the gap between the precast pile 4 and the loose layer borehole 14 are evenly and sufficiently filled, so that the precast pile 4 and the ground around the borehole 2 are tightly cemented and fixed to Together form a precast pile foundation.
  • the application first uses the casing 1 to cooperate with the drilling, then guides the precast pile 4 into the drilling 2, and finally injects the slurry 3 to fix the water formation.
  • the pile foundation construction work of rivers, lakes, seas and other water strata is realized in the above manner. Because the process of building cofferdam islands and removing cofferdams is eliminated, and the above-mentioned casing 1 can also be used repeatedly, the large amount of engineering and long engineering cycle of the cast-in-place bored pile foundation can be solved under the premise of ensuring the construction strength And the problem of high engineering cost.
  • a certain volume of slurry 3 is poured into the steel sleeve 1 before the steel sleeve 1 is pulled out, and the slurry 3 can enter the soil or sand layer at the bottom of the steel sleeve 1 to make the bottom of the borehole 2
  • the ground is more tightly cemented with the bottom of the precast pile 4.
  • a solid fixed structure is formed at the bottom of the borehole 2 after the slurry is formed.
  • the slurry 3 will be tightly cemented with the ground around the borehole 2 so that the precast pile 4 and the ground around the sidewall of the drilled hole 2 will be tightly cemented together to form a precast pile foundation.
  • the connection strength of the precast pile 4 with soil, sand and gravel in the foundation foundation environment or the marine engineering environment is improved.
  • a prefabricated pile includes:
  • a pile body which is a reinforced concrete prefabricated pile
  • the grouting channel 5 is a grouting tube that is tied to the steel cage of the pile body.
  • the liquid inlet end 11 of the grouting channel 5 extends out of the upper end surface of the pile body.
  • the liquid end 12 extends from the lower end surface of the pile body and the side surface of the pile body.
  • the casing 1 is made of a metal material, and the bottom end of the casing 1 has a toothed structure for cutting the soil.
  • the application of the present invention does not specifically limit the position of the upper end of the precast pile 4.
  • the upper end of the precast pile 4 is located below the water surface of the water area.
  • the material composition of the slurry 3 is not specifically limited in the application of the present invention.
  • the slurry 3 may also be a mortar or a chemical slurry, and two or three of a cement slurry, a mortar, and a chemical slurry. mixture.
  • the application of the present invention does not specifically limit the connection manner between the grouting channel 5 and the reinforcing cage.
  • the grouting channel 5 is preset on the reinforcing cage.
  • the application of the present invention does not specifically limit the manner and number of the grouting channels on the precast pile 4.
  • the precast pile 4 only includes a plurality of first grouting channels 6 located on the bottom surface of the precast pile 4.
  • the precast pile 4 only includes a plurality of second grouting channels 7 located on the side of the precast pile 4.
  • the application of the present invention does not specifically limit the role of the second grouting channel 7.
  • the first grouting channel 6 and the The second grouting channel 7 continuously grouts into the loose layer borehole 14.
  • the engineering implementation environment is a grouting consolidation method for a prefabricated pile with a full-bore drilled guide during the construction of a water area with a bedrock layer 9 at the bottom, including the following steps:
  • Step S1 sinking the casing 1 to the bedrock layer; sinking a drill bit of the drill rig to the bedrock layer through the inner cavity of the casing 1, and drilling the bedrock layer to drill in the bedrock layer Forming said bedrock borehole 13;
  • Step S2 at this time, the lower end portion of the casing 1 enters the opening edge of the inner cavity of the bedrock borehole 13, so that the end of the casing 1 is sleeved with the opening edge of the bedrock borehole 13, and the The drill bit of the drilling rig is sequentially removed from the bedrock borehole 13 and the casing 1;
  • the drill bit of the rig drills the bedrock layer 9 through the casing 1, which can effectively solve the problem that the bedrock layer 9 is difficult to construct during the construction of the water area with the bedrock layer 9 at the bottom.
  • the falling impact of the precast pile 4 can effectively make more slurry 3 and the foundation
  • the rock formation 9 is sufficiently permeated and consolidated, so that the slurry 3 sufficiently fills the bottom and sides of the bedrock formation 9.
  • the engineering implementation environment is a grouting consolidation method for a prefabricated pile with a full-bore drilled guide during the construction of a water area with a loose layer 8 at the bottom, including the following steps:
  • step S1 the casing 1 is sunk to the loose layer 8, the drilling rig drills the loose layer 8 to form a loose layer drill hole 14, and drives the casing 1 into the loose layer 8; Removal of sediment in casing 1;
  • Step S2 the casing 1 is housed in the loose layer borehole 14;
  • Step S3 implanting the precast pile 4 into the loose layer drill hole 14 so that the precast pile 4 reaches the bottom of the hole of the loose layer drill hole 14;

Abstract

A grouting consolidation method for a full casing borehole guide prefabricated pile, comprising the following steps: S1, driving a drilling rig carrying a casing (1) to perform borehole construction, the borehole construction being performed to a preset hole depth to form a borehole (2); S2. the casing (1) being housed in the borehole (2); S3. implanting a prefabricated pile (4) into the borehole (2) so that the prefabricated pile (4) reaches a hole bottom of the borehole (2); S4. injecting a slurry (3) into the borehole (2); S5. pulling out the casing (1) so that the prefabricated pile (4) and an inner cavity of the borehole (2) are fixed and cemented into an integrated structure. Also provided is a prefabricated pile, comprising a pile body and a grouting channel (5) provided on the pile body, wherein a liquid inlet end (11) of the grouting channel (5) extends out from an upper end surface of the pile body and a liquid outlet end (12) of the grouting channel (5) extends out from a lower end surface of the pile body and/or a side surface of the pile body.

Description

全套管钻孔导引预制桩的注浆固结方法及其预制桩Grouting consolidation method for full casing drilled guide prefabricated pile and prefabricated pile 技术领域Technical field
本发明涉及地基基础技术领域,具体涉及一种全套管钻孔导引预制桩的注浆固结方法及其预制桩。The invention relates to the technical field of foundations, in particular to a grouting consolidation method for a full-sleeve drill-guided precast pile and its precast pile.
背景技术Background technique
目前在水域工程的地基基础工程领域,特别是在海洋工程技术领域,江河湖海中的桩基础多为钻孔灌注桩或者锤击钢管桩,其钻孔灌注桩施工方案和方法最常见的是围堰筑岛或者使用钢护筒辅助完成施工工作。围堰筑岛又称筑岛填心,为了解决海洋环境施工困难的问题,需要在围堰围成的区域内填土、砂及砂砾石,再进行钻孔灌注工序。并且,在钻孔灌注桩施工完成后还需要拆除上述围堰筑岛,导致采用上述围堰筑岛的方式施工工程量十分巨大,具有工程周期长以及工程造价高的问题。同样,因为锤击钢管桩采用锤击沉入水域地基基础的方式施工,导致锤击钢管桩在遇到质地坚硬的基岩时,锤击钢管桩的端部会出现卷边甚至无法打入基岩的施工问题,并且由于上述锤击钢管桩的钢管无法取出,不但容易发生腐蚀的问题,也造成上述施工方法的施工成本高、施工工程量大的问题。At present, in the field of foundation engineering of water area engineering, especially in the field of marine engineering technology, the pile foundations in rivers, lakes and seas are mostly bored cast-in-situ piles or hammered steel pipe piles. The most common construction methods and methods for bored-filled piles are Cofferdam construction of islands or the use of steel jackets to complete the construction work. Cofferdam island construction is also called island construction. In order to solve the problem of difficult construction in the marine environment, soil, sand and gravel need to be filled in the area surrounded by the cofferdam, and then the drilling and pouring process is performed. In addition, after the completion of the bored pile construction, the above-mentioned cofferdam island construction is also required to be removed, resulting in a huge amount of construction work using the above-mentioned cofferdam island construction method, which has the problems of long engineering cycle and high engineering cost. Similarly, because the hammered steel pipe pile is constructed by hammering and sinking into the foundation of the water area, when the hammered steel pipe pile encounters a hard bedrock, the end of the hammered steel pipe pile may be curled or even unable to hit. The problem of construction into the bedrock, and because the steel pipe with the hammered steel pipe pile cannot be taken out, not only the problem of corrosion is easy to occur, but also the problems of high construction cost and large amount of construction of the above construction method.
发明内容Summary of the Invention
因此,本发明旨在提供一种全套管钻孔导引预制桩的注浆固结方法及 其预制桩,以解决现有技术在各种地层条件下水上地基基础施工中,特别是在海洋工程地基基础施工中,钻孔灌注桩基础施工工程量大、工程周期长以及工程造价高的问题。本申请提供一种全套管钻孔导引预制桩的注浆固结方法,用于水域工程的地基基础施工,其包括以下步骤:Therefore, the present invention aims to provide a grouting consolidation method of a full casing drilled guide prefabricated pile and its prefabricated pile, in order to solve the prior art in the construction of a water-based foundation under various formation conditions, especially in marine engineering. In the foundation construction, the problems of large amount of bored cast-in-situ pile foundation construction, long engineering cycle and high engineering cost. The present application provides a grouting consolidation method for a full casing drilled guide prefabricated pile, which is used for foundation construction of a water area project, and includes the following steps:
S1,驱动携带有套管的钻机进行钻孔施工,钻孔施工至预设孔深;S1. Drive a drilling rig with a casing to perform drilling operations, and the drilling operations are performed to a preset hole depth;
S2,所述套管容置在所述钻孔中;S2, the casing is accommodated in the borehole;
S3,将预制桩植入所述钻孔,以使所述预制桩到达所述钻孔的孔底;S3. The prefabricated pile is implanted into the borehole, so that the prefabricated pile reaches the bottom of the hole of the borehole;
S4,向所述钻孔内注入浆液;S4. Injecting slurry into the borehole;
S5,拔出所述套管,以使所述预制桩和所述钻孔的内腔固定胶结成一体结构。S5. Pull out the sleeve, so that the precast pile and the inner cavity of the drilled hole are fixed and cemented into an integrated structure.
步骤S3,所述将预制桩植入所述钻孔,以使所述预制桩到达所述钻孔的孔底,包括以下步骤:向所述钻孔内预先注入浆液;在所述浆液凝固以前,将预制桩植入所述钻孔到达所述钻孔的孔底。Step S3, the step of implanting a precast pile into the borehole so that the precast pile reaches the bottom of the hole of the borehole includes the following steps: pre-injecting a slurry into the borehole; before the slurry solidifies , Implanting a prefabricated pile into the borehole to the bottom of the borehole.
所述预制桩上预制有用于向所述钻孔内注入浆液的注浆通道,The prefabricated pile is prefabricated with a grouting channel for injecting slurry into the borehole,
步骤S5,所述拔出所述套管,包括:在拔出所述套管的过程中,通过所述预制桩上的注浆通道向所述钻孔内持续注浆;Step S5, the pulling out the casing includes: during the pulling out of the casing, continuously grouting into the borehole through a grouting channel on the precast pile;
和/或,在步骤S4,所述向所述钻孔内注入浆液,包括:在拔出所述套管之前,通过所述预制桩上的注浆通道向所述钻孔内注浆。And / or, in step S4, injecting the slurry into the borehole includes: before the casing is pulled out, grouting into the borehole through a grouting channel on the precast pile.
所述注浆通道包括:位于所述预制桩底面的第一注浆通道;The grouting channel includes: a first grouting channel located on a bottom surface of the precast pile;
步骤S5,所述拔出所述套管,包括:在拔出所述套管的过程中,通过所述第一注浆通道和/或所述第二注浆通道向所述钻孔内持续注浆;Step S5, the pulling out the casing includes: continuously pulling into the borehole through the first grouting channel and / or the second grouting channel during the process of pulling out the casing. Grouting
和/或,在步骤S4,所述向所述钻孔内注入浆液,包括:在拔出所述套 管之前,通过所述第一注浆通道向所述钻孔内注浆。And / or, in step S4, injecting the slurry into the borehole includes: before the casing is pulled out, grouting into the borehole through the first grouting channel.
在底部具有基岩层的水域施工过程中,During the construction of waters with bedrock layers at the bottom,
步骤S1,所述驱动携带有套管的钻机进行钻孔施工,钻孔施工至预设孔深,包括以下步骤:将所述套管下沉至所述基岩层;将钻机其钻头通过所述套管内腔下沉至所述基岩层,对所述基岩层钻孔以在所述基岩层形成所述基岩钻孔;Step S1, driving the drilling rig carrying the casing to perform drilling construction to a preset hole depth, including the following steps: sinking the casing to the bedrock layer; passing the drill's drill bit through the casing The inner cavity of the casing sinks to the bedrock layer, and drills the bedrock layer to form the bedrock borehole in the bedrock layer;
步骤S2,所述将所述钻机的钻头移出所述基岩钻孔,所述套管容置在基岩钻孔中,包括:将所述钻机的钻头依次从所述基岩钻孔和所述套管中移出,所述套管的下端进入所述基岩钻孔内腔的开口边缘,Step S2, the step of moving the drill bit of the rig out of the bedrock borehole, and the casing being accommodated in the bedrock borehole, comprises: sequentially drilling the drill bit from the bedrock and the Moving out of the casing, the lower end of the casing entering the opening edge of the borehole cavity of the bedrock,
所述钻孔包括所述基岩钻孔。The borehole includes the bedrock borehole.
在底部从上至下依次具有松散层和基岩层的水域施工过程中,上述松散层为泥沙等松散地层;During the construction of a water area with a loose layer and a bedrock layer in order from the bottom to the bottom, the above loose layer is a loose layer such as sand;
步骤S1,所述驱动携带有套管的钻机进行钻孔施工,钻孔施工至预设孔深,包括:In step S1, driving the drilling rig carrying the casing to perform drilling construction, and drilling construction to a preset hole depth includes:
将所述套管下沉至所述松散层,钻机对所述松散层钻孔以带动所述套管穿过所述松散层,以形成松散层钻孔;Sinking the casing to the loose layer, and drilling a hole in the loose layer to drive the casing through the loose layer to form a loose layer borehole;
将所述套管内的泥沙移出;Removing sediment from the casing;
将钻机其钻头通过所述套管内腔下沉至所述基岩层,对所述基岩层钻孔以在所述基岩层形成所述基岩钻孔;Sinking a drill bit of the rig through the casing cavity to the bedrock layer, and drilling the bedrock layer to form the bedrock borehole in the bedrock layer;
步骤S2,所述将所述钻机的钻头移出所述钻孔,所述套管容置在钻孔中,包括:将所述钻机的钻头依次从所述基岩钻孔和所述套管中移出,所述套管的下端进入所述基岩钻孔内腔的开口边缘;Step S2, the step of removing the drill bit of the drilling rig from the borehole and accommodating the casing in the borehole includes: drilling the drill bit of the rig from the bedrock and the casing in order. Removed, the lower end of the casing enters the opening edge of the bedrock bore cavity;
所述钻孔包括所述松散层钻孔和所述基岩钻孔。The drilling includes the loose layer drilling and the bedrock drilling.
在底部具有松散层的水域施工过程中,During the construction of waters with loose layers at the bottom,
步骤S1,所述驱动携带有套管的钻机进行钻孔施工,钻孔施工至预设孔深,包括以下步骤:将所述套管下沉至所述松散层,钻机对所述松散层钻孔形成松散层钻孔,并带动所述套管进入所述松散层;将所述套管内的泥沙移出。In step S1, driving the drilling rig carrying the casing to perform drilling construction to a preset hole depth includes the steps of sinking the casing to the loose layer, and drilling the drill to the loose layer. The hole forms a loose layer drill hole, and drives the casing into the loose layer; removing the sediment in the casing.
所述预制桩的上端位于所述水域其水面以上,和/或所述预制桩的上端位于所述水域其水面以下。The upper end of the precast pile is located above the water surface of the water area, and / or the upper end of the precast pile is located below the water surface of the water area.
所述浆液包括水泥浆和/或砂浆和/或化学浆。The slurry includes cement slurry and / or mortar and / or chemical slurry.
一种预制桩,包括A prefabricated pile including
桩身;Pile body
注浆通道,设置在所述桩身上,所述注浆通道的进液端延伸出所述桩身的上端面,所述注浆通道的出液端延伸出所述桩身的下端面和/或所述桩身的侧面。The grouting channel is provided on the pile body, the liquid inlet end of the grouting channel extends out of the upper end surface of the pile body, the liquid outlet end of the grouting channel extends out of the lower end surface of the pile body and / Or the side of the pile.
所述桩身为钢筋混凝土预制桩,所述注浆通道为预制在所述桩身其钢筋笼上的注浆管。The pile body is a reinforced concrete prefabricated pile, and the grouting channel is a grouting pipe prefabricated on a reinforced cage of the pile body.
本发明的技术方案,具有如下优点:The technical solution of the present invention has the following advantages:
1.本发明提供的全套管钻孔导引预制桩的注浆固结方法,用于水域工程的地基基础施工,包括以下步骤:S1,驱动携带有套管的钻机进行钻孔施工,钻孔施工至预设孔深;S2,所述套管容置在所述钻孔中;S3,将预 制桩植入所述钻孔,以使所述预制桩到达所述钻孔的孔底;S4,向所述钻孔内注入浆液;S5,拔出所述套管,以使所述预制桩和所述钻孔的内腔固定胶结成一体结构。为了适应多种水上工程的地层,特别是需要在江河湖海水面上施工的海洋工程环境,本申请先通过套管配合钻孔,再将预制桩导引入钻孔的孔底,最后注入浆液固定的方式实现水域地层的施工。由于水域工程的地基基础对施工强度有较高要求,可以通过套管协助钻孔,以适应不同水下地层结构,将预制桩导引入钻孔的孔底可以有效地保证水域工程的地基基础施工的稳定可靠性。通过上述方式实现江河湖海等水域地层的桩基础施工工作。由于免去了围堰筑岛和拆除围堰的工序,且上述套管还可以反复利用,从而在保证施工强度的前提下,解决了水上钻孔灌注桩基础的工程量大、工程周期长以及以及工程造价高的问题。1. A grouting consolidation method for a full-casing drill-guided prefabricated pile for foundation construction of a water area project, comprising the following steps: S1, driving a drilling rig carrying a casing for drilling construction, drilling Construction to a preset hole depth; S2, the casing is accommodated in the borehole; S3, a precast pile is implanted into the borehole so that the precast pile reaches the bottom of the hole of the borehole; S4 , Injecting slurry into the borehole; S5, pulling out the sleeve so that the precast pile and the inner cavity of the borehole are fixed and cemented into an integrated structure. In order to adapt to the stratum of a variety of water engineering, especially the marine engineering environment that needs to be constructed on the seawater of rivers and lakes, this application first uses a casing to cooperate with drilling, then introduces the precast pile guide into the bottom of the hole, and finally injects slurry Realize the construction of water stratum in a fixed way. As the foundation of water area engineering has higher requirements for construction strength, casing can be used to assist drilling to adapt to different underwater stratum structures. The introduction of prefabricated pile guides into the bottom of the hole can effectively ensure the foundation of water area engineering. Stable and reliable construction. The pile foundation construction work of rivers, lakes, seas and other water strata is realized in the above manner. Because the process of building cofferdam islands and removing cofferdams is eliminated, and the above casing can also be reused, the large amount of engineering, long construction period and long construction period of the bored cast-in-place pile foundation can be solved under the premise of ensuring the construction intensity. And the problem of high engineering cost.
2.本发明提供的全套管钻孔导引预制桩的注浆固结方法,在步骤S3,所述将预制桩植入所述钻孔,以使所述预制桩到达所述钻孔的孔底,包括以下步骤:向所述钻孔内预先注入浆液;在所述浆液凝固以前,将预制桩植入所述钻孔到达所述钻孔的孔底。通过在钻孔内植入预制桩之前预先向钻孔内预先注入浆液,从而可以使预制桩和钻孔内的浆液充分胶结。而且,预制桩下降的冲击力还可以有效地使浆液进入钻孔底部,从而形成较大体积且坚实的钻孔2底部固定头。2. The grouting consolidation method for a full-casing drill-guided precast pile provided in the present invention, in step S3, the precast pile is implanted into the drilled hole so that the precast pile reaches the hole of the drilled hole The bottom includes the following steps: pre-injecting a slurry into the borehole; before the slurry is solidified, a precast pile is implanted into the borehole to reach the bottom of the borehole. By pre-injecting slurry into the borehole before implanting the precast pile in the borehole, the slurry in the precast pile and the borehole can be sufficiently cemented. Moreover, the falling impact force of the precast pile can also effectively make the slurry enter the bottom of the borehole, thereby forming a larger and solid bottom 2 fixed head.
3.本发明提供的全套管钻孔导引预制桩的注浆固结方法,所述预制桩上预制有用于向所述钻孔内注入浆液的注浆通道,步骤S5,所述拔出所述套管,包括:在拔出所述套管的过程中,通过所述预制桩上的注浆通道向所述钻孔内持续注浆;在拔出所述套管的过程中,通过上述预制桩的注浆 通道可以简单方便地使浆液流入钻孔,以填充套管拔出过程中产生的间隙。并且,通过上述方式不但可以使预制桩和钻孔周围的地层紧密胶结固定,以适用于各种地层,还可以使套管的拔出过程更加顺畅,降低操作难度,解决现有水上钻孔灌注桩基础的工程量大、工程周期长以及以及工程造价高的问题。在步骤S4中,所述向所述钻孔内注入浆液,包括:在拔出所述套管之前,通过所述预制桩上的注浆通道向所述钻孔内注浆。在拔出所述套管之前,通过注浆通道向钻孔内注入浆液,或者采用直接向钻孔内灌注浆液的方式注浆,其操作简单便利,可以使预制桩与钻孔2周围的地层紧密胶结固定在一起形成预制桩基础,进而提高了预制桩在海洋工程环境下预制桩和土壤、砂石的连接强度。3. The grouting consolidation method for a full-casing drill-guided prefabricated pile provided in the present invention, the prefabricated pile is prefabricated with a grouting channel for injecting slurry into the borehole, step S5, the extraction station The casing includes: during the process of extracting the casing, continuously grouting into the borehole through a grouting channel on the prefabricated pile; during the process of extracting the casing, through the above The grouting channel of the prefabricated pile can simply and conveniently make the slurry flow into the borehole to fill the gap generated during the pullout of the casing. In addition, through the above method, not only the precast pile and the ground surrounding the borehole can be tightly cemented and fixed to be applicable to various grounds, but also the casing can be pulled out more smoothly, the operation difficulty is reduced, and the existing waterbore drilling is solved. The problems of large amount of pile foundation, long engineering cycle and high engineering cost. In step S4, injecting the slurry into the borehole includes: before the casing is pulled out, grouting into the borehole through a grouting channel on the precast pile. Before the casing is pulled out, the slurry is injected into the borehole through the grouting channel, or the slurry is directly poured into the borehole. The operation is simple and convenient, which can make the precast pile and the ground around the borehole 2 Tightly cemented together to form a precast pile foundation, thereby improving the connection strength of the precast pile with soil, sand and gravel in the marine engineering environment.
4.本发明提供的全套管钻孔导引预制桩的注浆固结方法,所述注浆通道包括:位于所述预制桩底面的第一注浆通道;通过在预制桩的底面和侧面分别设置注浆通道,从而使浆液可以分别从预制桩的底面注入钻孔,使浆液更均匀充分地填充预制桩和钻孔之间存在的间隙,使预制桩与钻孔2周围的地层紧密胶结固定在一起形成预制桩基础。4. The grouting consolidation method for a full casing drilled guide prefabricated pile provided by the present invention, the grouting channel comprises: a first grouting channel located on the bottom surface of the prefabricated pile; Set up grouting channels, so that the slurry can be injected into the boreholes from the bottom of the precast pile, so that the slurry can more evenly and fully fill the gap between the precast pile and the borehole, so that the precast pile and the ground around the borehole 2 are tightly cemented and fixed. Together form a precast pile foundation.
5.本发明提供的全套管钻孔导引预制桩的注浆固结方法,在底部具有基岩层的水域施工过程中,步骤S1,所述驱动携带有套管的钻机进行钻孔施工,钻孔施工至预设孔深,包括以下步骤:将所述套管下沉至所述基岩层;将钻机其钻头通过所述套管内腔下沉至所述基岩层,对所述基岩层钻孔以在所述基岩层形成所述基岩钻孔。步骤S2,所述将所述钻机的钻头移出所述基岩钻孔,所述套管容置在基岩钻孔中,包括:将所述钻机的钻头依次从所述基岩钻孔和所述套管中移出,所述套管的下端进入所述基岩钻 孔内腔的开口边缘,所述钻孔包括所述基岩钻孔。钻机的钻头穿过套管对基岩层进行钻孔施工,可以有效地解决底部具有基岩层的水域施工过程中,基岩层难以施工的问题。而且,通过在基岩钻孔中预先注入浆液,再将预制桩沉降进入基岩钻孔的方式,通过预制桩的下降冲击作用,可以有效地使更多的浆液与基岩层充分渗透固结,从而使浆液充分填充基岩层的底部和侧部。5. The grouting consolidation method for a full-casing drilling guide prefabricated pile provided in the present invention, in a water area construction process with a bedrock layer at the bottom, step S1, said driving a drilling rig carrying a casing for drilling construction, drilling The hole construction to a preset hole depth includes the following steps: sinking the casing to the bedrock layer; sinking a drill bit of the rig to the bedrock layer through the casing cavity, and drilling the bedrock layer To form the bedrock borehole in the bedrock layer. Step S2, the step of moving the drill bit of the rig out of the bedrock borehole, and the casing being accommodated in the bedrock borehole, comprises: sequentially drilling the drill bit from the bedrock and the The casing is removed, the lower end of the casing enters the opening edge of the inner cavity of the bedrock borehole, and the borehole includes the bedrock borehole. The drill bit of the rig drills the bedrock layer through the casing, which can effectively solve the problem that the bedrock layer is difficult to construct during the construction of the water area with the bedrock layer at the bottom. In addition, by pre-injecting slurry into the bedrock borehole and then sinking the precast pile into the bedrock borehole, through the falling impact of the precast pile, more slurry can be effectively penetrated and consolidated with the bedrock layer. This allows the slurry to fully fill the bottom and sides of the bedrock formation.
6.本发明提供的全套管钻孔导引预制桩的注浆固结方法,在底部从上至下依次具有松散层和基岩层的水域施工过程中,步骤S1,所述驱动携带有套管的钻机进行钻孔施工,钻孔施工至预设孔深,包括:将所述套管下沉至所述松散层,钻机对所述松散层钻孔以带动所述套管穿过所述松散层,以形成松散层钻孔;将所述套管内的土石泥沙移出;将钻机其钻头通过所述套管内腔下沉至所述基岩层,对所述基岩层钻孔以在所述基岩层形成所述基岩钻孔。步骤S2,所述将所述钻机的钻头移出所述钻孔,所述套管容置在钻孔中,包括:将所述钻机的钻头依次从所述基岩钻孔和所述套管中移出,所述套管的下端进入所述基岩钻孔内腔的开口边缘;所述钻孔包括所述松散层钻孔和所述基岩钻孔。对应于底部从上至下依次具有松散层和基岩层的水域施工过程中,通过钻机的钻头先对松散层进行钻孔,再排出泥沙。再通过穿过套管的钻头对基岩层进行钻孔,有效地解决了因为具有松散层和基岩层导致上述水域施工困难的问题。而且,通过在基岩钻孔中预先注入浆液,再将预制桩沉降进入基岩钻孔的方式填充基岩钻孔;再通过提升套管的过程中,通过预制桩的注浆通道持续向松散层注浆的方式进而分别完成对基岩层和松散层填充固定的工作。基岩钻孔采用预先注浆再 植入预制桩的固定方式可以有效地使浆液有充分时间与基岩钻孔胶结固定,且在预制桩下降冲击力作用下浆液可以更充分渗入基岩层;松散层采用套管提升过程中,向松散层钻孔内注浆的方式,可以有效地通过浆液填充预制桩和套管之间的间隙,完成上述注浆工作,从而使浆液充分将预制桩和松散层钻孔周围的地层胶结固定在一起。6. The grouting consolidation method for a full-casing drill-guided prefabricated pile provided by the present invention, in a water area construction process with a loose layer and a bedrock layer in order from the bottom to the bottom, step S1, the drive carries a casing Drilling rig for drilling construction to a preset hole depth includes sinking the casing to the loose layer, and drilling the hole to the loose layer to drive the casing through the loose layer Layer to form a loose layer for drilling; removing earth, rock, and sediment in the casing; sinking a drill bit of the rig through the casing cavity to the bedrock layer, and drilling the bedrock layer to form the bedrock layer Rock formations form the bedrock borehole. Step S2, the step of removing the drill bit of the drilling rig from the borehole and accommodating the casing in the borehole includes: drilling the drill bit of the rig from the bedrock and the casing in order. When removed, the lower end of the casing enters the open edge of the inner cavity of the bedrock borehole; the borehole includes the loose layer borehole and the bedrock borehole. Corresponding to the construction of waters with loose layers and bedrock layers in order from bottom to top, the loose layer is first drilled by the drill's drill bit, and then the sediment is discharged. Drilling the bedrock layer through a drill bit through the casing effectively solves the problem that the above waters are difficult to construct because of the loose layer and the bedrock layer. In addition, the bedrock boreholes are filled by injecting slurry into the bedrock boreholes in advance, and then the precast piles are settled into the bedrock boreholes. During the process of lifting the casing, the grouting channels of the precast piles are continuously loosened. The layer grouting method further completes the work of filling and fixing the bedrock layer and the loose layer respectively. The bedrock drilling adopts the fixing method of pre-grouting and re-implanting the precast pile, which can effectively make the slurry have sufficient time to be cemented and fixed with the bedrock drilling, and the slurry can penetrate the bedrock layer more fully under the impact of the precast pile's falling impact; loose The layer is grouted into the loose layer during the casing lifting process, which can effectively fill the gap between the precast pile and the casing with slurry to complete the above grouting work, so that the slurry can fully precast the pile and loose. The formations around the boreholes are cemented together.
附图说明BRIEF DESCRIPTION OF THE DRAWINGS
为了更清楚地说明本发明具体实施方式或现有技术中的技术方案,下面将对具体实施方式或现有技术描述中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图是本发明的一些实施方式,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他的附图。In order to more clearly illustrate the specific embodiments of the present invention or the technical solutions in the prior art, the drawings needed to be used in the specific embodiments or the description of the prior art are briefly introduced below. Obviously, the appendixes in the following description The drawings are some embodiments of the present invention. For those of ordinary skill in the art, other drawings can be obtained according to these drawings without paying creative labor.
图1为本发明提供的具有松散层和基岩层的水域其全套管的安装步骤示意图;FIG. 1 is a schematic diagram of installation steps of a full casing of a water area having a loose layer and a bedrock layer provided by the present invention; FIG.
图2为本发明提供的具有松散层和基岩层的水域其朝向基岩层预先注浆的步骤示意图;FIG. 2 is a schematic diagram of steps for pre-grouting in a water area having a loose layer and a bedrock layer provided in the present invention toward the bedrock layer; FIG.
图3为本发明提供的具有松散层和基岩层的水域其将预制桩下沉至预先注浆的钻孔底部的步骤示意图;3 is a schematic diagram of steps for sinking a precast pile to the bottom of a pre-grouted borehole in a water area having a loose layer and a bedrock layer provided by the present invention;
图4为本发明提供的具有松散层和基岩层的水域其取出全套管的步骤示意图;4 is a schematic diagram of a step of taking out a full casing in a water area having a loose layer and a bedrock layer provided by the present invention;
图5为本发明提供的具有松散层和基岩层的水域其全套管钻孔导引预制桩的注浆固结工序完成后预制桩与水域底部的连接结构示意图;5 is a schematic diagram of a connection structure between a precast pile and a bottom of a water area after completion of a grouting consolidation process of a full casing drilled guide prefabricated pile in a water area having a loose layer and a bedrock layer provided by the present invention;
图6为本发明提供的预制桩下沉至钻孔底部的结构示意图;FIG. 6 is a schematic structural diagram of the precast pile sinking to the bottom of a borehole provided by the present invention; FIG.
图7为本发明提供的全套管钻孔注浆工序完成后取出全套管时预制桩与地基基础环境的连接结构示意图。FIG. 7 is a schematic structural diagram of a connection structure between a precast pile and a foundation foundation environment when a full casing is taken out after a full casing drilling and grouting process provided by the present invention is completed.
附图标记说明:Reference sign description:
1-套管;2-钻孔;3-浆液;4-预制桩;5-注浆通道;6-第一注浆通道;7-第二注浆通道;8-松散层;9-基岩层;10-水面;11-进液端;12-出液端;13-基岩钻孔;14-松散层钻孔。1-casing; 2-drilling; 3-grout; 4-precast pile; 5-grouting channel; 6-first grouting channel; 7-second grouting channel; 8- loose layer; 9- bedrock layer 10-water surface; 11-liquid inlet; 12-liquid outlet; 13-bedrock drilling; 14- loose layer drilling.
具体实施方式detailed description
下面将结合附图对本发明的技术方案进行清楚、完整地描述,显然,所描述的实施例是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。The technical solution of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are part of the present invention, but not all of them. Based on the embodiments of the present invention, all other embodiments obtained by a person of ordinary skill in the art without creative efforts shall fall within the protection scope of the present invention.
在本发明的描述中,需要说明的是,术语“中心”、“上”、“下”、“左”、“右”、“竖直”、“水平”、“内”、“外”等指示的方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述本发明和简化描述,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本发明的限制。此外,术语“第一”、“第二”、“第三”仅用于描述目的,而不能理解为指示或暗示相对重要性。In the description of the present invention, it should be noted that the terms "center", "up", "down", "left", "right", "vertical", "horizontal", "inside", "outside", etc. The indicated orientation or positional relationship is based on the orientation or positional relationship shown in the drawings, and is only for the convenience of describing the present invention and simplified description, and does not indicate or imply that the device or element referred to must have a specific orientation, a specific orientation Construction and operation should therefore not be construed as limiting the invention. In addition, the terms "first," "second," and "third" are used for descriptive purposes only, and should not be construed to indicate or imply relative importance.
在本发明的描述中,需要说明的是,除非另有明确的规定和限定,术 语“安装”、“相连”、“连接”应做广义理解,例如,可以是固定连接,也可以是可拆卸连接,或一体地连接;可以是机械连接,也可以是电连接;可以是直接相连,也可以通过中间媒介间接相连,可以是两个元件内部的连通。对于本领域的普通技术人员而言,可以具体情况理解上述术语在本发明中的具体含义。In the description of the present invention, it should be noted that the terms "installation", "connected", and "connected" should be understood in a broad sense unless otherwise specified and limited. For example, they may be fixed connections or removable. Connected or integrated; it can be mechanical or electrical; it can be directly connected, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two elements. For those of ordinary skill in the art, the specific meanings of the above terms in the present invention can be understood on a case-by-case basis.
此外,下面所描述的本发明不同实施方式中所涉及的技术特征只要彼此之间未构成冲突就可以相互结合。In addition, the technical features involved in the different embodiments of the present invention described below can be combined with each other as long as they do not conflict with each other.
实施例1Example 1
本实施例提供一种全套管钻孔导引预制桩的注浆固结方法,其工程实施环境如图1至图7所示,在底部从上至下依次具有松散层8和基岩层9的水域施工过程中,全套管钻孔导引预制桩的注浆固结方法,包括以下步骤:This embodiment provides a grouting consolidation method for a full-casing drill-guided prefabricated pile. The engineering implementation environment is shown in Figs. 1 to 7. The bottom layer has a loose layer 8 and a bedrock layer 9 in this order from top to bottom. During water construction, the grouting consolidation method of a full-casing drill-guided precast pile includes the following steps:
步骤S1,将所述套管1通过水面10进行下沉至所述松散层8,钻机对所述松散层8钻孔以带动所述套管1穿过所述松散层8,以形成松散层钻孔14;In step S1, the casing 1 is sunk to the loose layer 8 through the water surface 10, and a drilling rig drills the loose layer 8 to drive the casing 1 through the loose layer 8 to form a loose layer. Drilling 14
将所述套管1内的水以及泥沙移出;Removing water and sediment from the casing 1;
将钻机其钻头通过所述套管1内腔下沉至所述基岩层,对所述基岩层钻孔以在所述基岩层形成所述基岩钻孔13;Sinking a drill bit of the rig through the inner cavity of the casing 1 to the bedrock layer, and drilling the bedrock layer to form the bedrock borehole 13 in the bedrock layer;
步骤S2,将所述钻机的钻头依次从所述基岩钻孔13和所述套管1中移出,此时所述套管1的下端部分进入所述基岩钻孔13内腔的开口边缘,从而使套管1的端部与基岩钻孔13的开口边缘套接;In step S2, the drill bit of the rig is sequentially removed from the bedrock borehole 13 and the casing 1, and at this time, the lower end portion of the casing 1 enters the opening edge of the inner cavity of the bedrock borehole 13. So that the end of the casing 1 is sleeved with the opening edge of the bedrock borehole 13;
S3,向所述钻孔2内预先注入水泥浆;在所述水泥浆凝固以前,将预制桩4植入所述钻孔2,预制桩4到达所述基岩钻孔13的孔底;所述预制桩4的上端位于所述水域其水面以上,从而方便施工人员通过预制桩4上的注浆通道5其注浆孔注浆;S3, pre-injecting cement slurry into the borehole 2; before the cement slurry is solidified, a precast pile 4 is implanted into the borehole 2, and the precast pile 4 reaches the bottom of the hole 13 of the bedrock; The upper end of the prefabricated pile 4 is located above the water surface of the water area, thereby facilitating the construction personnel to grout through the grouting hole 5 on the prefabricated pile 4;
S4,提升套管1,在套管1上升过程中通过预制桩4上的注浆通道5持续向基岩钻孔13和松散层钻孔14注浆;所述注浆通道5包括:位于所述预制桩4底面的第一注浆通道6,在拔出所述套管1的过程中,通过所述第一注浆通道6向持续向松散层钻孔14内注浆,以使所述预制桩4分别与基岩钻孔13的孔壁和底部,以及松散层钻孔14的孔壁固定胶结成一体结构;S4, lifting the casing 1, during the ascent of the casing 1, through the grouting channel 5 on the prefabricated pile 4 to continuously grout the bedrock borehole 13 and the loose layer borehole 14; the grouting channel 5 includes: The first grouting channel 6 on the bottom surface of the prefabricated pile 4 is continuously grouting into the loose layer borehole 14 through the first grouting channel 6 during the process of pulling out the casing 1 so that the The prefabricated pile 4 is fixedly cemented with the hole wall and bottom of the bedrock borehole 13 and the hole wall of the loose layer borehole 14 to form an integrated structure;
S5,通过第二注浆通道7向预制桩4和地层之间注浆,以达到反复加固预制桩4的作用。对应于底部从上至下依次具有松散层8和基岩层9的水域施工过程中,通过钻机的钻头先对松散层8进行钻孔,再排出泥沙。再通过穿过套管1的钻头对基岩层9进行钻孔,有效地解决了因为具有松散层8和基岩层9导致上述水域施工困难的问题。而且,通过在基岩钻孔13中预先注入水泥浆,再将预制桩4沉降进入基岩钻孔13的方式填充基岩钻孔13;再通过提升套管1的过程中,通过预制桩4的注浆通道5持续向松散层8注浆的方式进而分别完成对基岩层9和松散层8填充固定的工作。基岩钻孔13采用预先注浆再植入预制桩4的固定方式可以有效地使水泥浆有充分时间与基岩钻孔13胶结固定,且在预制桩4下降冲击力作用下水泥浆可以更充分渗入基岩层9;松散层8采用套管1提升过程中,向松散层钻孔14内注浆的方式,可以有效地通过水泥浆填充预制桩4和套管1之间的间隙,完成上述注浆工作,从而使水泥浆充分将预制桩4和松散层钻孔14 周围的地层胶结固定在一起。并且,通过在预制桩4的底面和侧面分别设置的注浆通道,从而使水泥浆可以分别从预制桩4的底面和侧面分别注入基岩钻孔13和松散层钻孔14,使水泥浆更均匀充分地填充预制桩4和基岩钻孔13之间存在的间隙,以及预制桩4和松散层钻孔14之间存在的间隙,使预制桩4与钻孔2周围的地层紧密胶结固定在一起形成预制桩基础。而且,本申请先通过套管1配合钻孔,再将预制桩4导引入钻孔2中,最后注入浆液3固定的方式实现水域地层的施工。通过上述方式实现江河湖海等水域地层的桩基础施工工作。由于免去了围堰筑岛和拆除围堰的工序,且上述套管1还可以反复利用,从而在保证施工强度的前提下,解决了水上钻孔灌注桩基础的工程量大、工程周期长以及以及工程造价高的问题。另外,本申请通过在拔出所述钢套管1之前在钢套管1内灌注一定体积的浆液3,上述浆液3可以进入钢套管1底部的土壤或砂石层使钻孔2底部的地层与预制桩4底部更紧密的胶结在一起。从而在钻孔2底部形成凝浆后固体的固定结构。而且,在提升钢套管1时浆液3还会和钻孔2周围的地层紧密胶结固定在一起,进而使预制桩4与钻孔2侧壁周围的地层紧密胶结固定在一起形成预制桩基础,进而提高了预制桩4在地基基础环境或海洋工程环境下预制桩4和土壤、砂石的连接强度。S5. Grouting between the precast pile 4 and the ground through the second grouting channel 7 to achieve the effect of repeatedly strengthening the precast pile 4. During the construction of the water area corresponding to the bottom with the loose layer 8 and the bedrock layer 9 in order from top to bottom, the loose layer 8 is first drilled by the drill bit of the rig, and then the sediment is discharged. Then drilling the bedrock layer 9 through the drill bit passing through the casing 1 effectively solves the problem that the above waters are difficult to construct because of having the loose layer 8 and the bedrock layer 9. Moreover, the bedrock borehole 13 is filled by injecting cement slurry into the bedrock borehole 13 in advance, and then the precast pile 4 is settled into the bedrock borehole 13; then, through the process of lifting the casing 1, the precast pile 4 is passed through The grouting channel 5 continuously grouts the loose layer 8 and then completes the work of filling and fixing the bedrock layer 9 and the loose layer 8 respectively. The fixation of the bedrock borehole 13 by pre-grouting and re-implantation into the precast pile 4 can effectively allow the cement slurry to have sufficient time to be fixed with the bedrock borehole 13 and the cement slurry can be more adequate under the effect of the impact of the precast pile 4 falling. Penetrating into bedrock layer 9; loose layer 8 is grouted into borehole 14 of loose layer during the casing 1 lifting process, and the gap between precast pile 4 and casing 1 can be effectively filled with cement slurry to complete the above injection. The slurry works so that the cement slurry fully cements the ground around the precast pile 4 and the loose layer borehole 14 together. In addition, through the grouting channels provided on the bottom and side of the precast pile 4, respectively, the cement slurry can be injected into the bedrock borehole 13 and the loose layer borehole 14 from the bottom and side of the precast pile 4, respectively, to make the cement slurry more The gap existing between the precast pile 4 and the bedrock borehole 13 and the gap between the precast pile 4 and the loose layer borehole 14 are evenly and sufficiently filled, so that the precast pile 4 and the ground around the borehole 2 are tightly cemented and fixed to Together form a precast pile foundation. In addition, the application first uses the casing 1 to cooperate with the drilling, then guides the precast pile 4 into the drilling 2, and finally injects the slurry 3 to fix the water formation. The pile foundation construction work of rivers, lakes, seas and other water strata is realized in the above manner. Because the process of building cofferdam islands and removing cofferdams is eliminated, and the above-mentioned casing 1 can also be used repeatedly, the large amount of engineering and long engineering cycle of the cast-in-place bored pile foundation can be solved under the premise of ensuring the construction strength And the problem of high engineering cost. In addition, in the present application, a certain volume of slurry 3 is poured into the steel sleeve 1 before the steel sleeve 1 is pulled out, and the slurry 3 can enter the soil or sand layer at the bottom of the steel sleeve 1 to make the bottom of the borehole 2 The ground is more tightly cemented with the bottom of the precast pile 4. Thus, a solid fixed structure is formed at the bottom of the borehole 2 after the slurry is formed. In addition, when the steel casing 1 is lifted, the slurry 3 will be tightly cemented with the ground around the borehole 2 so that the precast pile 4 and the ground around the sidewall of the drilled hole 2 will be tightly cemented together to form a precast pile foundation. Furthermore, the connection strength of the precast pile 4 with soil, sand and gravel in the foundation foundation environment or the marine engineering environment is improved.
在本实施中,一种预制桩,包括:In this implementation, a prefabricated pile includes:
桩身,所述桩身为钢筋混凝土预制桩;A pile body, which is a reinforced concrete prefabricated pile;
注浆通道5,为绑扎在所述桩身其钢筋笼上的注浆管,所述注浆通道5的进液端11延伸出所述桩身的上端面,所述注浆通道5的出液端12延伸出所述桩身的下端面和所述桩身的侧面。The grouting channel 5 is a grouting tube that is tied to the steel cage of the pile body. The liquid inlet end 11 of the grouting channel 5 extends out of the upper end surface of the pile body. The liquid end 12 extends from the lower end surface of the pile body and the side surface of the pile body.
在本实施中,套管1为金属材质,其底端具有用于将土壤剖开的齿状结构。In the present embodiment, the casing 1 is made of a metal material, and the bottom end of the casing 1 has a toothed structure for cutting the soil.
当然,本发明申请对预制桩4的上端的位置不做具体限制,在其它实施例中,所述预制桩4的上端位于所述水域其水面以下。Of course, the application of the present invention does not specifically limit the position of the upper end of the precast pile 4. In other embodiments, the upper end of the precast pile 4 is located below the water surface of the water area.
当然,本发明申请对浆液3的材料成分不做具体限制,在其它实施例中,所述浆液3还可以为砂浆或化学浆,以及水泥浆、砂浆和化学浆其三者其二或三者的混合物。Of course, the material composition of the slurry 3 is not specifically limited in the application of the present invention. In other embodiments, the slurry 3 may also be a mortar or a chemical slurry, and two or three of a cement slurry, a mortar, and a chemical slurry. mixture.
当然,本发明申请对注浆通道5与钢筋笼的连接方式不做具体限制,在其它实施例中,注浆通道5预置在钢筋笼上。Of course, the application of the present invention does not specifically limit the connection manner between the grouting channel 5 and the reinforcing cage. In other embodiments, the grouting channel 5 is preset on the reinforcing cage.
当然,本发明申请对预制桩4上的注浆通道设置方式以及数量不做具体限制,在其它实施例中,预制桩4只包括位于所述预制桩4底面的多条第一注浆通道6,或者预制桩4只包括位于所述预制桩4侧面的多条第二注浆通道7。Of course, the application of the present invention does not specifically limit the manner and number of the grouting channels on the precast pile 4. In other embodiments, the precast pile 4 only includes a plurality of first grouting channels 6 located on the bottom surface of the precast pile 4. Or, the precast pile 4 only includes a plurality of second grouting channels 7 located on the side of the precast pile 4.
当然,本发明申请对第二注浆通道7的作用不做具体限制,在其它实施例中,在拔出所述套管1的过程中,还可以同时通过所述第一注浆通道6和第二注浆通道7向持续向松散层钻孔14内注浆。Of course, the application of the present invention does not specifically limit the role of the second grouting channel 7. In other embodiments, during the process of pulling out the sleeve 1, the first grouting channel 6 and the The second grouting channel 7 continuously grouts into the loose layer borehole 14.
实施例2Example 2
本实施例与实施例1的区别在于,其工程实施环境为在底部具有基岩层9的水域施工过程中,全套管钻孔导引预制桩的注浆固结方法,包括以下步骤:The difference between this embodiment and Embodiment 1 is that the engineering implementation environment is a grouting consolidation method for a prefabricated pile with a full-bore drilled guide during the construction of a water area with a bedrock layer 9 at the bottom, including the following steps:
步骤S1,将所述套管1下沉至所述基岩层;将钻机其钻头通过所述套管1内腔下沉至所述基岩层,对所述基岩层钻孔以在所述基岩层形成所述基岩钻孔13;Step S1, sinking the casing 1 to the bedrock layer; sinking a drill bit of the drill rig to the bedrock layer through the inner cavity of the casing 1, and drilling the bedrock layer to drill in the bedrock layer Forming said bedrock borehole 13;
步骤S2,此时所述套管1的下端部分进入所述基岩钻孔13内腔的开口边缘,从而使套管1的端部与基岩钻孔13的开口边缘套接,将所述钻机的钻头依次从所述基岩钻孔13和所述套管1中移出;Step S2, at this time, the lower end portion of the casing 1 enters the opening edge of the inner cavity of the bedrock borehole 13, so that the end of the casing 1 is sleeved with the opening edge of the bedrock borehole 13, and the The drill bit of the drilling rig is sequentially removed from the bedrock borehole 13 and the casing 1;
S3,向所述钻孔2内预先注入浆液3;在所述浆液3凝固以前,将预制桩4植入所述基岩钻孔13,预制桩4到达所述基岩钻孔13的孔底;S3, injecting slurry 3 into the borehole 2 in advance; before the slurry 3 is solidified, a precast pile 4 is implanted into the bedrock borehole 13 and the precast pile 4 reaches the bottom of the bedrock borehole 13 ;
S4,拔出所述套管1,以使所述预制桩4和所述钻孔2的内腔固定胶结成一体结构。本实施例中,钻机的钻头穿过套管1对基岩层9进行钻孔施工,可以有效地解决底部具有基岩层9的水域施工过程中,基岩层9难以施工的问题。而且,通过在基岩钻孔13中预先注入浆液3,再将预制桩4沉降进入基岩钻孔13的方式,通过预制桩4的下降冲击作用,可以有效地使更多的浆液3与基岩层9充分渗透固结,从而使浆液3充分填充基岩层9的底部和侧部。S4. Pull out the sleeve 1 so that the internal cavity of the precast pile 4 and the borehole 2 is fixed and cemented into an integrated structure. In this embodiment, the drill bit of the rig drills the bedrock layer 9 through the casing 1, which can effectively solve the problem that the bedrock layer 9 is difficult to construct during the construction of the water area with the bedrock layer 9 at the bottom. Moreover, by injecting the slurry 3 into the bedrock borehole 13 in advance, and then sinking the precast pile 4 into the bedrock borehole 13, the falling impact of the precast pile 4 can effectively make more slurry 3 and the foundation The rock formation 9 is sufficiently permeated and consolidated, so that the slurry 3 sufficiently fills the bottom and sides of the bedrock formation 9.
实施例3Example 3
本实施例与实施例1的区别在于,其工程实施环境为在底部具有松散层8的水域施工过程中,全套管钻孔导引预制桩的注浆固结方法,包括以下步骤:The difference between this embodiment and Embodiment 1 is that the engineering implementation environment is a grouting consolidation method for a prefabricated pile with a full-bore drilled guide during the construction of a water area with a loose layer 8 at the bottom, including the following steps:
步骤S1,将所述套管1下沉至所述松散层8,钻机对所述松散层8钻孔形成松散层钻孔14,并带动所述套管1进入所述松散层8;将所述套管1 内的泥沙移出;In step S1, the casing 1 is sunk to the loose layer 8, the drilling rig drills the loose layer 8 to form a loose layer drill hole 14, and drives the casing 1 into the loose layer 8; Removal of sediment in casing 1;
步骤S2,所述套管1容置在所述松散层钻孔14中;Step S2, the casing 1 is housed in the loose layer borehole 14;
步骤S3,将预制桩4植入所述松散层钻孔14,以使所述预制桩4到达所述松散层钻孔14的孔底;Step S3, implanting the precast pile 4 into the loose layer drill hole 14 so that the precast pile 4 reaches the bottom of the hole of the loose layer drill hole 14;
S4,提升套管1,在套管1上升过程中通过预制桩4上的注浆通道5持续向松散层钻孔14内注浆;所述注浆通道5包括:位于所述预制桩4底面的第一注浆通道6,在拔出所述套管1的过程中,分别通过所述第一注浆通道6向持续向松散层钻孔14内注浆,以使所述预制桩4与松散层钻孔14的孔壁和底部固定胶结成一体结构。S4, lifting the casing 1, during the ascent of the casing 1, through the grouting channel 5 on the prefabricated pile 4 to continue grouting into the loose layer borehole 14; During the process of pulling out the casing 1, the first grouting channel 6 is continuously grouted into the loose hole 14 through the first grouting channel 6, so that the precast pile 4 and The hole wall of the loose layer drill hole 14 and the bottom are fixed and cemented into an integrated structure.
显然,上述实施例仅仅是为清楚地说明所作的举例,而并非对实施方式的限定。对于所属领域的普通技术人员来说,在上述说明的基础上还可以做出其它不同形式的变化或变动。这里无需也无法对所有的实施方式予以穷举。而由此所引伸出的显而易见的变化或变动仍处于本发明创造的保护范围之中。Obviously, the foregoing embodiment is merely an example for clear description, and is not a limitation on the implementation. For those of ordinary skill in the art, other different forms of changes or modifications can be made on the basis of the above description. There is no need and cannot be exhaustive for all implementations. However, the obvious changes or variations introduced thereby are still within the protection scope created by the present invention.

Claims (12)

  1. 一种全套管钻孔导引预制桩的注浆固结方法,其特征在于,用于水域工程的地基基础施工,其包括以下步骤:A grouting consolidation method for a full-sleeve drill-guided prefabricated pile, which is characterized in that it is used for foundation construction of a water area project and includes the following steps:
    S1,驱动携带有套管(1)的钻机进行钻孔施工,钻孔施工至预设孔深,形成钻孔(2);S1. The drilling rig carrying the casing (1) is driven for drilling, and the drilling is performed to a preset hole depth to form a drilling (2);
    S2,所述套管(1)容置在所述钻孔(2)中;S2, the sleeve (1) is housed in the borehole (2);
    S3,将预制桩(4)植入所述钻孔(2),以使所述预制桩(4)到达所述钻孔(2)的孔底;S3. The precast pile (4) is implanted into the borehole (2), so that the precast pile (4) reaches the bottom of the hole of the borehole (2);
    S4,向所述钻孔(2)内注入浆液(3);S4. Inject slurry (3) into the borehole (2);
    S5,拔出所述套管(1),以使所述预制桩(4)和所述钻孔(2)的内腔固定胶结成一体结构。S5. Pull out the sleeve (1), so that the precast pile (4) and the inner cavity of the drilled hole (2) are fixed and cemented into an integrated structure.
  2. 根据权利要求1所述的全套管钻孔导引预制桩的注浆固结方法,其特征在于,步骤S3,所述将预制桩(4)植入所述钻孔(2),以使所述预制桩(4)到达所述钻孔(2)的孔底,包括以下步骤:向所述钻孔(2)内预先注入浆液(3);在所述浆液(3)凝固以前,将预制桩(4)植入所述钻孔(2)到达所述钻孔(2)的孔底。The method for grouting and consolidation of a prefabricated precast pile with full casing according to claim 1, characterized in that, in step S3, the precast pile (4) is implanted into the borehole (2) so that the The precast pile (4) reaching the bottom of the hole (2) includes the following steps: pre-injecting a slurry (3) into the hole (2); before the slurry (3) solidifies, prefabricating A post (4) is implanted into the borehole (2) to reach the bottom of the hole of the borehole (2).
  3. 根据权利要求1或2所述的全套管钻孔导引预制桩的注浆固结方法,其特征在于,The method for grouting and consolidation of a prefabricated drilled pile with full casing according to claim 1 or 2, wherein:
    所述预制桩(4)上预制有用于向所述钻孔(2)内注入浆液(3)的注浆通道(5),The precast pile (4) is prefabricated with a grouting channel (5) for injecting slurry (3) into the borehole (2),
    步骤S5,所述拔出所述套管(1),包括:在拔出所述套管(1)的过程中,通过所述预制桩(4)上的注浆通道(5)向所述钻孔(2)内持续注浆;Step S5. The pulling out the casing (1) includes: during the pulling out of the casing (1), through the grouting channel (5) on the precast pile (4) to the casing. Continuous grouting in the borehole (2);
    和/或,在步骤S4,所述向所述钻孔(2)内注入浆液(3),包括:在拔出所述套管(1)之前,通过所述预制桩(4)上的注浆通道(5)向所述钻孔(2)内注浆。And / or, in step S4, injecting the slurry (3) into the borehole (2) includes: before the casing (1) is pulled out, passing a note on the precast pile (4) The grouting channel (5) grouts into the borehole (2).
  4. 根据权利要求3所述的全套管钻孔导引预制桩的注浆固结方法,其特征在于,所述注浆通道(5)包括:位于所述预制桩(4)底面的第一注浆通道(6);The method for grouting and consolidation of a full casing drill-guided precast pile according to claim 3, wherein the grouting channel (5) comprises: a first grouting located on the bottom surface of the precast pile (4) Channel (6);
    步骤S5,所述拔出所述套管(1),包括:在拔出所述套管(1)的过程中,通过第一注浆通道(6)向所述钻孔(2)内持续注浆;Step S5. The pulling out the casing (1) includes: continuously pulling the casing (1) into the borehole (2) through the first grouting channel (6). Grouting
    和/或,在步骤S4,所述向所述钻孔(2)内注入浆液(3),包括:在拔出所述套管(1)之前,通过所述第一注浆通道(6)向所述钻孔(2)内注浆。And / or, in step S4, injecting the slurry (3) into the borehole (2) includes: before the casing (1) is pulled out, through the first grouting channel (6) Grouting into said borehole (2).
  5. 根据权利要求3或4所述的全套管钻孔导引预制桩的注浆固结方法,其特征在于,所述注浆通道(5)包括:位于所述预制桩(4)侧部向预制桩(4)和所述钻孔(2)之间注浆的第二注浆通道(7);The method for grouting and consolidation of a prefabricated full-hole casing-guided precast pile according to claim 3 or 4, characterized in that the grouting channel (5) comprises: prefabricating the side of the precast pile (4) A second grouting channel (7) for grouting between the pile (4) and the borehole (2);
    所述全套管钻孔导引预制桩的注浆固结方法还包括:步骤S6,通过第二注浆通道(7)向预制桩(4)和述钻孔(2)之间注浆。The method for grouting and consolidation of a prefabricated pile with a full casing drilling guide further includes: Step S6, grouting between the precast pile (4) and the borehole (2) through a second grouting channel (7).
  6. 根据权利要求1至5中任一项所述的全套管钻孔导引预制桩的注浆固结方法,其特征在于,在底部具有基岩层(9)的水域施工过程中,The grouting consolidation method for a full-casing drill-guided prefabricated pile according to any one of claims 1 to 5, characterized in that during the construction of a water area having a bedrock layer (9) at the bottom,
    步骤S1,所述驱动携带有套管(1)的钻机进行钻孔施工,钻孔施工至预设孔深,包括以下步骤:将所述套管(1)下沉至所述基岩层;将钻机其钻头通过所述套管(1)内腔下沉至所述基岩层,对所述基岩层钻孔以在所述基岩层形成基岩钻孔(13);Step S1, driving the drilling rig carrying the casing (1) to perform drilling construction to a predetermined hole depth, including the following steps: sinking the casing (1) to the bedrock layer; The drill rig sinks through the inner cavity of the casing (1) to the bedrock layer, and drills the bedrock layer to form a bedrock borehole (13) in the bedrock layer;
    步骤S2,所述将钻机的钻头移出所述基岩钻孔(13),所述套管(1)容置在基岩钻孔(13)中,包括:将所述钻机的钻头依次从所述基岩钻孔(13)和所述套管(1)中移出,所述套管(1)的下端进入所述基岩钻孔(13)内腔的开口边缘,In step S2, removing the drill bit from the bedrock borehole (13), and accommodating the casing (1) in the bedrock borehole (13) includes: sequentially moving the drill bit from the The bedrock borehole (13) and the casing (1) are removed, and the lower end of the casing (1) enters the opening edge of the inner cavity of the bedrock borehole (13),
    所述钻孔(2)包括所述基岩钻孔(13)。The borehole (2) includes the bedrock borehole (13).
  7. 根据权利要求1至5中任一项所述的全套管钻孔导引预制桩的注浆固结方法,其特征在于,在底部从上至下依次具有松散层(8)和基岩层(9)的水域施工过程中,The grouting consolidation method for a full-casing drill-guided prefabricated pile according to any one of claims 1 to 5, characterized in that it has a loose layer (8) and a bedrock layer (9) in order from the bottom to the bottom. ) During the construction of the waters,
    步骤S1,所述驱动携带有套管(1)的钻机进行钻孔施工,钻孔施工至预设孔深,包括:In step S1, driving the drilling rig carrying the casing (1) to perform drilling construction, and drilling construction to a preset hole depth includes:
    将所述套管(1)下沉至所述松散层(8),钻机对所述松散层(8)钻孔以带动所述套管(1)穿过所述松散层(8),以形成松散层钻孔(14);The casing (1) is sunk to the loose layer (8), and a drilling machine drills the loose layer (8) to drive the casing (1) through the loose layer (8) to Forming a loose layer borehole (14);
    将所述套管(1)内的泥沙移出;Removing the sediment in the casing (1);
    将钻机其钻头通过所述套管(1)内腔下沉至所述基岩层,对所述基岩层钻孔以在所述基岩层形成基岩钻孔(13);Sinking a drill bit of the rig through the inner cavity of the casing (1) to the bedrock layer, drilling the bedrock layer to form a bedrock borehole (13) in the bedrock layer;
    步骤S2,所述将钻机的钻头移出所述钻孔(2),所述套管(1)容置在钻孔(2)中,包括:将钻机的钻头依次从所述基岩钻孔(13)和所述套管(1)中移出,所述套管(1)的下端进入所述基岩钻孔(13)内腔的开口边缘;Step S2, the step of moving the drill bit out of the borehole (2), and the casing (1) accommodated in the borehole (2) includes: sequentially drilling the drill bit from the bedrock ( 13) and removed from the casing (1), the lower end of the casing (1) enters the opening edge of the inner cavity of the bedrock borehole (13);
    所述钻孔(2)包括所述松散层钻孔(14)和所述基岩钻孔(13)。The borehole (2) includes the loose layer borehole (14) and the bedrock borehole (13).
  8. 根据权利要求1至5中任一项所述的全套管钻孔导引预制桩的注浆固结方法,其特征在于,在底部具有松散层(8)的水域施工过程中,The grouting consolidation method for a full-casing drill-guided prefabricated pile according to any one of claims 1 to 5, characterized in that during the construction of a water area with a loose layer (8) at the bottom,
    步骤S1,所述驱动携带有套管(1)的钻机进行钻孔施工,钻孔施工至预设孔深,包括以下步骤:将所述套管(1)下沉至所述松散层(8),钻机对所述松散层(8)钻孔形成松散层钻孔(14),并带动所述套管(1)进入所述松散层(8);将所述套管(1)内的泥沙移出。In step S1, the driving of the drilling rig carrying the casing (1) to perform drilling construction to a preset hole depth includes the following steps: sinking the casing (1) to the loose layer (8) ), A rig drills the loose layer (8) to form a loose layer bore (14), and drives the casing (1) into the loose layer (8); The sediment was removed.
  9. 根据权利要求6至8中任一项所述的全套管钻孔导引预制桩的注浆固结方法,其特征在于,所述预制桩(4)的上端位于水域其水面以上,和/或所述预制桩(4)的上端位于水域其水面以下。The grouting consolidation method for a full-casing drill-guided prefabricated pile according to any one of claims 6 to 8, wherein the upper end of the prefabricated pile (4) is located above the water surface of the water area, and / or The upper end of the prefabricated pile (4) is located below the water surface of the water area.
  10. 根据权利要求1至9中任一项所述的全套管钻孔导引预制桩的注浆固结方法,其特征在于,所述浆液(3)包括水泥浆和/或砂浆和/或化学浆。The grouting consolidation method for a full-casing drill-guided precast pile according to any one of claims 1 to 9, wherein the slurry (3) comprises cement slurry and / or mortar and / or chemical slurry .
  11. 一种预制桩,其特征在于,包括A prefabricated pile, comprising
    桩身;Pile body
    注浆通道(5),设置在所述桩身上,所述注浆通道(5)的进液端(11)延伸出所述桩身的上端面,所述注浆通道(5)的出液端(12)延伸出所述桩身的下端面和/或所述桩身的侧面。The grouting channel (5) is arranged on the pile body, and the liquid inlet end (11) of the grouting channel (5) extends out of the upper end surface of the pile body, and the liquid out of the grouting channel (5) The end (12) extends from the lower end surface of the pile body and / or the side surface of the pile body.
  12. 根据权利要求11所述的预制桩,其特征在于,The precast pile according to claim 11, wherein:
    所述桩身为钢筋混凝土预制桩,所述注浆通道(5)为预制在所述桩身其钢筋笼上的注浆管。The pile body is a reinforced concrete prefabricated pile, and the grouting channel (5) is a grouting pipe prefabricated on the reinforced cage of the pile body.
PCT/CN2019/091230 2018-09-25 2019-06-14 Grouting consolidation method for full casing borehole guide prefabricated pile and prefabricated pile therefor WO2020062940A1 (en)

Priority Applications (8)

Application Number Priority Date Filing Date Title
KR1020217010783A KR20210058901A (en) 2018-09-25 2019-06-14 Full casing drilling guide grouting and consolidation method of prefabricated pile and its prefabricated pile
US17/277,860 US20210348355A1 (en) 2018-09-25 2019-06-14 Grouting consolidation method for full casing borehole guide prefabricated pile and prefabricated pile therefor
EP19865349.5A EP3839149A4 (en) 2018-09-25 2019-06-14 Grouting consolidation method for full casing borehole guide prefabricated pile and prefabricated pile therefor
SG11202102769TA SG11202102769TA (en) 2018-09-25 2019-06-14 Grouting consolidation method for full casing borehole guide prefabricated pile and prefabricated pile therefor
CN201980000859.3A CN110896644B (en) 2018-09-25 2019-06-14 Grouting consolidation method for full-casing drilling guide precast pile
JP2021515169A JP2022502586A (en) 2018-09-25 2019-06-14 Grouting consolidation method of ready-made piles guided by all-casing excavation, and the ready-made piles
CONC2021/0003362A CO2021003362A2 (en) 2018-09-25 2021-03-15 Grout consolidation method for precast pile with full hole casing guide and precast pile for it
PH12021550571A PH12021550571A1 (en) 2018-09-25 2021-03-15 Grouting consolidation method for full casing borehole guide prefabricated pile and prefabricated pile therefor

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201811091450.0A CN109295972A (en) 2018-09-25 2018-09-25 Full-sleeve engineering method prefabricated pile perfusion slurry and grouting behind shaft or drift lining concretion technology
CN201811091450.0 2018-09-25

Publications (1)

Publication Number Publication Date
WO2020062940A1 true WO2020062940A1 (en) 2020-04-02

Family

ID=65163301

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2019/091230 WO2020062940A1 (en) 2018-09-25 2019-06-14 Grouting consolidation method for full casing borehole guide prefabricated pile and prefabricated pile therefor

Country Status (9)

Country Link
US (1) US20210348355A1 (en)
EP (1) EP3839149A4 (en)
JP (1) JP2022502586A (en)
KR (1) KR20210058901A (en)
CN (1) CN109295972A (en)
CO (1) CO2021003362A2 (en)
PH (1) PH12021550571A1 (en)
SG (1) SG11202102769TA (en)
WO (1) WO2020062940A1 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111997620A (en) * 2020-07-28 2020-11-27 中铁第四勘察设计院集团有限公司 Grouting construction system and method for karst collapse area
CN113250238A (en) * 2021-05-19 2021-08-13 中交第三航务工程局有限公司 Rock-socketed construction method of marine ultra-large-diameter single pile based on loosening ring theory
CN114562328A (en) * 2022-04-02 2022-05-31 中国矿业大学 Method for controlling surface subsidence by grouting and filling unconsolidated layer of bedrock top boundary
CN115075238A (en) * 2022-06-13 2022-09-20 陕西正诚路桥工程研究院有限公司 Reinforcing method in bored pile construction based on overwater operation platform
CN115323999A (en) * 2022-09-14 2022-11-11 赤峰中色白音诺尔矿业有限公司 Segmented grouting construction device for culvert pipes of tailing pond and construction method thereof

Families Citing this family (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110896644B (en) * 2018-09-25 2021-04-09 高永光 Grouting consolidation method for full-casing drilling guide precast pile
CN109295972A (en) * 2018-09-25 2019-02-01 高永光 Full-sleeve engineering method prefabricated pile perfusion slurry and grouting behind shaft or drift lining concretion technology
CN110565639B (en) * 2019-09-11 2021-03-23 中船第九设计研究院工程有限公司 Bored concrete pile hole forming and side wall grouting construction method for coral sand foundation
CN113309089A (en) * 2021-06-11 2021-08-27 河北省水利规划设计研究院有限公司 Prefabricated hollow pile and construction method for taking soil and planting pile
CN114753376A (en) * 2022-03-28 2022-07-15 中电建十一局工程有限公司 Method for excavating supporting slurry for deep foundation pit in gravel stratum
CN115288212B (en) * 2022-07-05 2023-05-16 湖北工业大学 Optical fiber implantation device and implantation method for existing pile wall
CN115233685B (en) * 2022-08-01 2023-07-14 中交四航工程研究院有限公司 Recyclable grouting device for maintaining horizontal rigidity of pile foundation and construction method thereof
CN115478560A (en) * 2022-09-28 2022-12-16 苏州枫石堂工程科技有限公司 Wall cracking grouting reinforcement method
KR102602249B1 (en) 2023-02-14 2023-11-16 우창건설 주식회사 Apparatus for guiding the casing and construction method using the same

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000129669A (en) * 1998-10-22 2000-05-09 Asahi Chem Ind Co Ltd Connecting method of prefabricated pile
CN102002945A (en) * 2010-03-25 2011-04-06 中国京冶工程技术有限公司 Capsule type anti-corrosion device with pile shoe and anti-corrosion and construction method using device
WO2011105703A2 (en) 2010-02-26 2011-09-01 Song Gi-Yong Method for constructing a steel pipe/concrete composite pile in which the steel pipe is buried integrally with bedrock, and pile construction
EP2527539A1 (en) 2011-05-27 2012-11-28 BAUER Maschinen GmbH Submarine drilling assembly and method for inserting a foundation element into the soil of a body of water
EP2650446A1 (en) 2012-04-12 2013-10-16 Herrenknecht AG Method of creating a foundation for a offshore structure
CN102691296B (en) * 2012-05-22 2015-02-11 广州市建筑科学研究院有限公司 Pipe pile foundation for static-pressure grouting on pile side and rotary jet grouting at pile bottom and construction method thereof
EP2930275A1 (en) 2014-04-08 2015-10-14 Herrenknecht AG System and method for producing a foundation for a building in water
CN105442594A (en) * 2015-12-04 2016-03-30 荣盛建设工程有限公司 Hole reaming mud-jacking construction technology for prestress hollow square pile with built-in mud-jacking pipe
CN107794925A (en) * 2017-10-31 2018-03-13 浙江大学城市学院 The grouting behind shaft or drift lining cast-in-situ concrete thin-wall and construction method of a kind of reserved grouting pipeline
CN109295972A (en) * 2018-09-25 2019-02-01 高永光 Full-sleeve engineering method prefabricated pile perfusion slurry and grouting behind shaft or drift lining concretion technology

Family Cites Families (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US1865652A (en) * 1929-09-20 1932-07-05 Raymond Concrete Pile Co Method and apparatus for placing concrete in piles
JPH05132930A (en) * 1991-11-07 1993-05-28 Jiototsupu:Kk Developing method of foundation pile with drain layer
NL9301176A (en) * 1993-07-05 1995-02-01 Verstraeten Beheersmij Bv Method for forming a foundation pile in the ground using a prefabricated pile shaft.
JPH1171758A (en) * 1997-08-27 1999-03-16 Nippon Steel Corp Method for driving pile to rock mass
JP2000257062A (en) * 1999-03-05 2000-09-19 Taisei Corp Steel pipe pile pitching method
JP2002155531A (en) * 2000-11-21 2002-05-31 Yoshitada Miyake Pile burial method
US20050019104A1 (en) * 2003-07-23 2005-01-27 Derald Christians Soil stabilization and pile formation method
JP4667479B2 (en) * 2008-03-03 2011-04-13 中国電力株式会社 Pile attachment / detachment structure and pile construction method
JP6260931B2 (en) * 2013-12-04 2018-01-17 株式会社大林組 Steel pipe pile and its embedding method

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000129669A (en) * 1998-10-22 2000-05-09 Asahi Chem Ind Co Ltd Connecting method of prefabricated pile
WO2011105703A2 (en) 2010-02-26 2011-09-01 Song Gi-Yong Method for constructing a steel pipe/concrete composite pile in which the steel pipe is buried integrally with bedrock, and pile construction
CN102002945A (en) * 2010-03-25 2011-04-06 中国京冶工程技术有限公司 Capsule type anti-corrosion device with pile shoe and anti-corrosion and construction method using device
EP2527539A1 (en) 2011-05-27 2012-11-28 BAUER Maschinen GmbH Submarine drilling assembly and method for inserting a foundation element into the soil of a body of water
EP2650446A1 (en) 2012-04-12 2013-10-16 Herrenknecht AG Method of creating a foundation for a offshore structure
CN102691296B (en) * 2012-05-22 2015-02-11 广州市建筑科学研究院有限公司 Pipe pile foundation for static-pressure grouting on pile side and rotary jet grouting at pile bottom and construction method thereof
EP2930275A1 (en) 2014-04-08 2015-10-14 Herrenknecht AG System and method for producing a foundation for a building in water
CN105442594A (en) * 2015-12-04 2016-03-30 荣盛建设工程有限公司 Hole reaming mud-jacking construction technology for prestress hollow square pile with built-in mud-jacking pipe
CN107794925A (en) * 2017-10-31 2018-03-13 浙江大学城市学院 The grouting behind shaft or drift lining cast-in-situ concrete thin-wall and construction method of a kind of reserved grouting pipeline
CN109295972A (en) * 2018-09-25 2019-02-01 高永光 Full-sleeve engineering method prefabricated pile perfusion slurry and grouting behind shaft or drift lining concretion technology

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
See also references of EP3839149A4

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111997620A (en) * 2020-07-28 2020-11-27 中铁第四勘察设计院集团有限公司 Grouting construction system and method for karst collapse area
CN113250238A (en) * 2021-05-19 2021-08-13 中交第三航务工程局有限公司 Rock-socketed construction method of marine ultra-large-diameter single pile based on loosening ring theory
CN114562328A (en) * 2022-04-02 2022-05-31 中国矿业大学 Method for controlling surface subsidence by grouting and filling unconsolidated layer of bedrock top boundary
CN114562328B (en) * 2022-04-02 2022-12-02 中国矿业大学 Method for controlling surface subsidence by grouting and filling unconsolidated layer of bedrock top boundary
CN115075238A (en) * 2022-06-13 2022-09-20 陕西正诚路桥工程研究院有限公司 Reinforcing method in bored pile construction based on overwater operation platform
CN115323999A (en) * 2022-09-14 2022-11-11 赤峰中色白音诺尔矿业有限公司 Segmented grouting construction device for culvert pipes of tailing pond and construction method thereof
CN115323999B (en) * 2022-09-14 2024-02-27 赤峰中色白音诺尔矿业有限公司 Sectional grouting construction device for culvert pipes of tailing pond and construction method thereof

Also Published As

Publication number Publication date
US20210348355A1 (en) 2021-11-11
SG11202102769TA (en) 2021-04-29
JP2022502586A (en) 2022-01-11
KR20210058901A (en) 2021-05-24
EP3839149A1 (en) 2021-06-23
CN109295972A (en) 2019-02-01
CO2021003362A2 (en) 2021-07-19
PH12021550571A1 (en) 2021-10-25
EP3839149A4 (en) 2022-04-20

Similar Documents

Publication Publication Date Title
WO2020062940A1 (en) Grouting consolidation method for full casing borehole guide prefabricated pile and prefabricated pile therefor
CN103924987B (en) A kind of SMW engineering method stake tunnel shielding portal seepage-proof structure and construction method thereof
CN108086328A (en) A kind of dynamic sealing, assembled building enclosure and its construction method from recharge
CN105442605B (en) Extract PHC and be reused in deep foundation pit supporting construction method
CN108166483A (en) Bored pile construction method
CN101205721A (en) Method for surrounding water by combination of steel cofferdam and heavy-pressure rotary-spraying pile in deep-water low-pile cap construction
CN108532586A (en) A kind of construction method of garage parking diaphram wall
CN112281829A (en) Composite pile foundation structure and construction method thereof
CN106948340A (en) A kind of construction method of the Manual excavated pile structure of high polymer grouting protection
CN110295597A (en) Close to buildings Soft Clay pattern foundation pit supporting structure steel sheet pile is pulled out and grouting strengthening method
CN112681295A (en) Construction method of concrete-filled steel tube pile foundation and concrete-filled steel tube pile foundation
CN103953030A (en) Threaded screwing inserting bar compaction filling pile
CN104404956A (en) Construction method for pedestal piles
CN110896644B (en) Grouting consolidation method for full-casing drilling guide precast pile
JP2003268767A (en) Construction method for double tube digging small diameter pile using hole excavating rod
CN203796288U (en) Water seepage prevention structure used for shield entrance door employing SMW piles
CN201459749U (en) Stable structure for construction platform of deep water steel pipe pile
CN101603311B (en) Jet grouting pile construction method adopting heavy hammer-tamping compaction soil preformed hole
CN208472716U (en) Crack geology mortar leakage prevention drill-pouring pilework
JP2003147782A (en) Foundation structure for constructing new building on existing basement and its construction method
CN105040705A (en) Ground foundation treatment construction technology under multi-karst-cave geological conditions
CN115262614A (en) Embedded rock-socketed pile foundation and construction method
CN106638646A (en) Secondary bottom sealing structure of open caisson and construction method
CN105951743A (en) Plum blossom-shaped profile steel cement stirring wall
JP3810882B2 (en) Construction method of cast-in-place pile in confined groundwater zone

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 19865349

Country of ref document: EP

Kind code of ref document: A1

DPE1 Request for preliminary examination filed after expiration of 19th month from priority date (pct application filed from 20040101)
ENP Entry into the national phase

Ref document number: 2021515169

Country of ref document: JP

Kind code of ref document: A

ENP Entry into the national phase

Ref document number: 2019865349

Country of ref document: EP

Effective date: 20210315

REG Reference to national code

Ref country code: BR

Ref legal event code: B01A

Ref document number: 112021004781

Country of ref document: BR

WWE Wipo information: entry into national phase

Ref document number: 2101001716

Country of ref document: TH

NENP Non-entry into the national phase

Ref country code: DE

ENP Entry into the national phase

Ref document number: 20217010783

Country of ref document: KR

Kind code of ref document: A

REG Reference to national code

Ref country code: BR

Ref legal event code: B01E

Ref document number: 112021004781

Country of ref document: BR

Free format text: 1) ESCLARECER, EM ATE 60 (SESSENTA) DIAS, APRESENTANDO DOCUMENTACAO COMPROBATORIA, A INCLUSAO DO DEPOSITANTE BEIJING KERUIHENGJI CONSTRUCTION TECHNOLOGY DEVELOPMENT CO., LTD. CONSTANTE NA PETICAO INICIAL NO 870210023936 DE 13/03/2021 E NAO INCLUSO NA PUBLICACAO INTERNACIONAL WO/2020/062940 DE 02/04/2020. O DOCUMENTO DE CESSAO DA PRIORIDADE ENVIADO NA PETICAO NAO SERVE COMO DOCUMENTO PARA INCLUSAO DE DEPOSITANTE DO PCT.2) APRESENTAR, EM ATE 60 (SESSENTA) DIAS, DOCUMENTOS COMPROBATORIOS QUE EXPLIQUEM E REGULARIZEM A DIVERGENCIA NO NOME DOS INVENTORES E DEPOSITANTES CONSTANTES NA PUBLICACAO INTERNACIONAL WO/2020/062940 DE 02/04/2020 COMO YONGGUAN GAO E YUNFEI GAO CONSTANTE NO FORMULARIO DA PETI

ENP Entry into the national phase

Ref document number: 112021004781

Country of ref document: BR

Kind code of ref document: A2

Effective date: 20210313