US20050019104A1 - Soil stabilization and pile formation method - Google Patents
Soil stabilization and pile formation method Download PDFInfo
- Publication number
- US20050019104A1 US20050019104A1 US10/625,331 US62533103A US2005019104A1 US 20050019104 A1 US20050019104 A1 US 20050019104A1 US 62533103 A US62533103 A US 62533103A US 2005019104 A1 US2005019104 A1 US 2005019104A1
- Authority
- US
- United States
- Prior art keywords
- soil
- pile member
- pile
- tubular
- grout
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Abandoned
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/50—Piles comprising both precast concrete portions and concrete portions cast in situ
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/34—Concrete or concrete-like piles cast in position ; Apparatus for making same
- E02D5/38—Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
- E02D5/44—Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds with enlarged footing or enlargements at the bottom of the pile
Definitions
- the present invention relates generally to a method of securing a pile member in relatively unstable soil. More particularly, the present invention relates to a method of stabilizing a region of soil generally below a pile member to support the pile member thereon.
- the Bullivant patent U.S. Pat. No. 4,605,339, for example, describes a method for forming a cast pile in unstable soil.
- Bullivant teaches casting a pile which extends through a layer of unstable soil into a region of stable soil.
- the pile itself is cast of concrete.
- the Bullivant method is not, however, useful in a soil site that does not have an accessible layer of stable soil. If the Bullivant method were used in such a soil site, the void created by the mole would not remain open. Further, the unstable soil below the desired pile location would not be able to support an end-bearing pile.
- the method of the present invention secures a pile member in generally unstable soil. This method makes useable locations that would otherwise be too unstable to support a structure. In particular, this method allows building upon soil that, at surface level, is extremely unstable and that sits on top of a layer of semi-stable soil.
- a first tubular pile member is inserted generally vertically into the ground.
- the pile member is selected to be long enough to extend through the top extremely unstable soil layer and to terminate within the lower semi-stable soil layer.
- the pile member is a steel pipe.
- a second small diameter injection pipe is inserted within the pile member and is positioned to terminate below the lower end of the pile member. The termination depth of the small diameter injection pipe is determined by soil conditions.
- Grout is introduced through the injection pipe, under controlled pressure, as the injection pipe is withdrawn.
- the grout forms bulbs and lenses thereby compressing and stabilizing the material below the first tubular member providing support for the first tubular member.
- the pile member is lowered into the grouted material.
- a reinforcing bar can be inserted into the first tubular member and into the stabilizing material.
- the pile member When the grouted material cures, the pile member is securely embedded therein, and the grouted material below the pile member stabilizes the soil in the region below the pile member.
- a first tubular pile member is inserted generally vertically into the ground.
- the pile member is selected to be long enough to extend through the top extremely unstable soil layer and to terminate within the lower semi-stable soil layer.
- the pile member is a steel pipe.
- Grout is introduced through the pile member, under pressure. The grout fills a space generally below the end of the first tubular member, thereby compacting the soil below the pile member. The grout spreads radially to some degree, thereby filling a space below the pile member that has a diameter generally larger than the diameter of the pile member.
- the pile member is lowered into the grouted material. When the grouted material cures, the pile member is securely embedded therein, and the grouted material below the pile member stabilizes the soil in the region below the pile member.
- a pile member includes a pipe, with compaction grouted material solidified below the end of the pipe.
- the grouted material compacts and stabilizes the soil beneath the pipe.
- This pile member is an end-bearing pile member rather than a friction pile member.
- FIG. 1 is a side sectional view of a pile member positioned to terminate within a semi-stable soil layer beneath an extremely unstable soil layer, according to a step in the preferred method of the present invention
- FIG. 2 is a side sectional view of a pile member with a second tubular member positioned therein, according to a step in the preferred method of the present invention
- FIG. 3 is a side sectional view illustrating the introduction of grouting material through the second tubular member according to a step in the preferred method of the present invention
- FIG. 4 is a side sectional view illustrating the pile member being lowered into grout material, according to a step in the preferred method of the present invention
- FIG. 5 is a side sectional view illustrating the placement of a pile member according to an alternate embodiment of the method of the present invention
- FIG. 6 is a side sectional view illustrating the introduction of grout material according to the alternate embodiment of the method of the present invention.
- FIG. 7 is a side sectional view illustrating the pile member being lowered into grout material, according to the alternate embodiment of the method of the present invention depicted in FIGS. 5 and 6 .
- the method of the present invention converts an unstable soil arrangement that cannot support a significant load, such as a house or other building, into a buildable site.
- a soil site is depicted in FIG. 1 .
- the site is characterized by a first upper layer of soil 10 that is extremely unstable, such as soil composed primarily of peat or soil that contains a relatively high volume of liquid.
- a second layer of soil 20 that is more stable than the upper layer 10 , but still too unstable to support a pile or foundation member for a building.
- This method can be used in soil sites where the first layer 10 is any depth. Typically, the depth of such a layer is between 10 and 100 feet, and most commonly between 20 and 40 feet.
- a tubular member 30 is introduced into the soil deeply enough that its terminating end 35 is within the second layer 20 , i.e. end 35 extends below the first soil layer 10 . Because the soil layer 10 is so soft or compliant, the tubular member 30 can be easily lowered through layer 10 into layer 20 without the use of drilling equipment or specialized moles or the like.
- tubular member 30 is a steel pipe having a diameter of between 4 to 6 inches, though those of skill in the art will recognize that tubular members of other materials and sizes will work according to the method described.
- the length of tubular member 30 is selected such that it extends from above the upper surface of layer 10 to below the first layer of extremely unstable soil 10 , such that tubular member 30 terminates within the second soil layer 20 .
- a second tubular member or injection pipe 40 having an outer diameter that is less than the inner diameter of first tubular member 30 , is inserted through said first tubular member, and lowered until its terminating end 45 is positioned within the second soil layer 20 , and preferably below the terminating end 35 of first tubular member 30 .
- terminating end 45 of second tubular member 40 is positioned between about 6 and 10 feet below the terminating end 35 of first tubular member 30 .
- grout material 50 such as cement-based grout
- second tubular member 40 is introduced through second tubular member 40 .
- the grout 50 is pumped under controlled pressure through tubular member 40 .
- the grout material 50 is deposited at the terminating end 45 of second tubular member 40 .
- Second tubular member 40 is then withdrawn, or moved upwardly.
- grout material is continually pumped therethrough under controlled pressure and is deposited at the terminating end 45 .
- a column 60 of grouted material 50 is formed.
- the column 60 includes bulb and lens formations.
- first tubular member or casing 30 is lowered into the grouted material 50 , as illustrated in FIG. 4 , in the direction indicated by arrow 75 into the grouted material 50 .
- the grouted material 50 cures, it provides a stabilized soil region to support the pile member 30 . Because of the characteristics of the second soil layer 20 , the grouted material remains relatively close to its deposit site and therefore forms a column 60 as the second tubular member 40 is withdrawn and grout material is simultaneously supplied.
- a first tubular pile member 130 is inserted through extremely unstable soil 110 such that the pile member's terminating end 135 is positioned within a second soil layer 120 .
- grout material 150 is introduced through pile member 130 .
- the grout material is deposited within the soil in the second soil layer 120 generally below the pile member 130 .
- pile member 130 is lowered, in the direction indicated by arrow 175 , into the grouted mass 180 .
- Use of the second tubular member or injection pipe 40 allows use of a shorter casing 30 . This is useful where there is low headroom or where the second soil layer 120 is too soft or unstable to provide any kind of end bearing for a cementatious bulb at the bottom of the pile, such as when the casing is installed though unstable material and terminates in a stable material.
Abstract
A method of forming a grouted pile member in unstable soil involves introducing a pile member into the ground and passing it through a first extremely unstable layer of soil into a second layer of relatively unstable material. Grout is introduced through the pile member under pressure and forms a column generally below the pile member. The pile member is then lowered into the grouted material.
Description
- The present invention relates generally to a method of securing a pile member in relatively unstable soil. More particularly, the present invention relates to a method of stabilizing a region of soil generally below a pile member to support the pile member thereon.
- Methods are known for constructing piles in situ in somewhat unstable ground. The Bullivant patent, U.S. Pat. No. 4,605,339, for example, describes a method for forming a cast pile in unstable soil. Bullivant teaches casting a pile which extends through a layer of unstable soil into a region of stable soil. The pile itself is cast of concrete. The Bullivant method is not, however, useful in a soil site that does not have an accessible layer of stable soil. If the Bullivant method were used in such a soil site, the void created by the mole would not remain open. Further, the unstable soil below the desired pile location would not be able to support an end-bearing pile.
- The method of the present invention secures a pile member in generally unstable soil. This method makes useable locations that would otherwise be too unstable to support a structure. In particular, this method allows building upon soil that, at surface level, is extremely unstable and that sits on top of a layer of semi-stable soil.
- According to a preferred method, a first tubular pile member is inserted generally vertically into the ground. The pile member is selected to be long enough to extend through the top extremely unstable soil layer and to terminate within the lower semi-stable soil layer. In a preferred method, the pile member is a steel pipe. A second small diameter injection pipe is inserted within the pile member and is positioned to terminate below the lower end of the pile member. The termination depth of the small diameter injection pipe is determined by soil conditions.
- Grout is introduced through the injection pipe, under controlled pressure, as the injection pipe is withdrawn. The grout forms bulbs and lenses thereby compressing and stabilizing the material below the first tubular member providing support for the first tubular member. The pile member is lowered into the grouted material. If desired, a reinforcing bar can be inserted into the first tubular member and into the stabilizing material.
- When the grouted material cures, the pile member is securely embedded therein, and the grouted material below the pile member stabilizes the soil in the region below the pile member.
- In another embodiment, a first tubular pile member is inserted generally vertically into the ground. The pile member is selected to be long enough to extend through the top extremely unstable soil layer and to terminate within the lower semi-stable soil layer. In a preferred method, the pile member is a steel pipe. Grout is introduced through the pile member, under pressure. The grout fills a space generally below the end of the first tubular member, thereby compacting the soil below the pile member. The grout spreads radially to some degree, thereby filling a space below the pile member that has a diameter generally larger than the diameter of the pile member. The pile member is lowered into the grouted material. When the grouted material cures, the pile member is securely embedded therein, and the grouted material below the pile member stabilizes the soil in the region below the pile member.
- According to another aspect of this invention, a pile member includes a pipe, with compaction grouted material solidified below the end of the pipe. The grouted material compacts and stabilizes the soil beneath the pipe. This pile member is an end-bearing pile member rather than a friction pile member.
- An exemplary version of a method for securing a pile member in unstable soil is shown in the figures wherein like reference numerals refer to equivalent structure throughout, and wherein:
-
FIG. 1 is a side sectional view of a pile member positioned to terminate within a semi-stable soil layer beneath an extremely unstable soil layer, according to a step in the preferred method of the present invention; -
FIG. 2 is a side sectional view of a pile member with a second tubular member positioned therein, according to a step in the preferred method of the present invention; -
FIG. 3 is a side sectional view illustrating the introduction of grouting material through the second tubular member according to a step in the preferred method of the present invention; -
FIG. 4 is a side sectional view illustrating the pile member being lowered into grout material, according to a step in the preferred method of the present invention -
FIG. 5 is a side sectional view illustrating the placement of a pile member according to an alternate embodiment of the method of the present invention; -
FIG. 6 is a side sectional view illustrating the introduction of grout material according to the alternate embodiment of the method of the present invention; and -
FIG. 7 is a side sectional view illustrating the pile member being lowered into grout material, according to the alternate embodiment of the method of the present invention depicted inFIGS. 5 and 6 . - The method of the present invention converts an unstable soil arrangement that cannot support a significant load, such as a house or other building, into a buildable site. Such a soil site is depicted in
FIG. 1 . The site is characterized by a first upper layer ofsoil 10 that is extremely unstable, such as soil composed primarily of peat or soil that contains a relatively high volume of liquid. Below the extremely unstable soil is a second layer ofsoil 20 that is more stable than theupper layer 10, but still too unstable to support a pile or foundation member for a building. This method can be used in soil sites where thefirst layer 10 is any depth. Typically, the depth of such a layer is between 10 and 100 feet, and most commonly between 20 and 40 feet. - In a first preferred embodiment of the present invention, a
tubular member 30 is introduced into the soil deeply enough that its terminatingend 35 is within thesecond layer 20, i.e.end 35 extends below thefirst soil layer 10. Because thesoil layer 10 is so soft or compliant, thetubular member 30 can be easily lowered throughlayer 10 intolayer 20 without the use of drilling equipment or specialized moles or the like. In a preferred embodiment,tubular member 30 is a steel pipe having a diameter of between 4 to 6 inches, though those of skill in the art will recognize that tubular members of other materials and sizes will work according to the method described. The length oftubular member 30 is selected such that it extends from above the upper surface oflayer 10 to below the first layer of extremelyunstable soil 10, such thattubular member 30 terminates within thesecond soil layer 20. - After positioning the first
tubular member 30, a second tubular member or injection pipe 40, having an outer diameter that is less than the inner diameter of firsttubular member 30, is inserted through said first tubular member, and lowered until its terminating end 45 is positioned within thesecond soil layer 20, and preferably below the terminatingend 35 of firsttubular member 30. This is illustrated inFIG. 2 . In a preferred method, terminating end 45 of second tubular member 40 is positioned between about 6 and 10 feet below the terminatingend 35 of firsttubular member 30. - As shown in
FIG. 3 ,grout material 50, such as cement-based grout, is introduced through second tubular member 40. Preferably, thegrout 50 is pumped under controlled pressure through tubular member 40. Thegrout material 50 is deposited at the terminating end 45 of second tubular member 40. Second tubular member 40 is then withdrawn, or moved upwardly. As the tubular member 40 is raised, grout material is continually pumped therethrough under controlled pressure and is deposited at the terminating end 45. In this manner, a column 60 of groutedmaterial 50 is formed. The column 60 includes bulb and lens formations. - Finally, first tubular member or
casing 30 is lowered into the groutedmaterial 50, as illustrated inFIG. 4 , in the direction indicated byarrow 75 into the groutedmaterial 50. When the groutedmaterial 50 cures, it provides a stabilized soil region to support thepile member 30. Because of the characteristics of thesecond soil layer 20, the grouted material remains relatively close to its deposit site and therefore forms a column 60 as the second tubular member 40 is withdrawn and grout material is simultaneously supplied. - In an alternate embodiment of this method, illustrated in
FIG. 5 , a firsttubular pile member 130 is inserted through extremelyunstable soil 110 such that the pile member's terminatingend 135 is positioned within asecond soil layer 120. As illustrated inFIG. 6 ,grout material 150 is introduced throughpile member 130. The grout material is deposited within the soil in thesecond soil layer 120 generally below thepile member 130. Finally, as illustrated inFIG. 7 ,pile member 130 is lowered, in the direction indicated byarrow 175, into the groutedmass 180. - Use of the second tubular member or injection pipe 40 allows use of a
shorter casing 30. This is useful where there is low headroom or where thesecond soil layer 120 is too soft or unstable to provide any kind of end bearing for a cementatious bulb at the bottom of the pile, such as when the casing is installed though unstable material and terminates in a stable material. - Although an illustrative version of the method is shown, it should be clear that many modifications to the method may be made without departing from the scope of the invention.
Claims (2)
1. A method of securing a pile member in soil that has an upper layer of very unstable material and a second lower layer of semi-stable material, comprising the steps of:
a) introducing a first tubular pile member having a terminating end into the soil, such that said terminating end is situated below the very unstable material;
b) pumping cement-based grout, under controlled pressure, through said tubular pile member and into the semi-stable material in said second layer, said grout forming a grout mass below the tubular member;
c) lowering said pile member into said grout mass.
2. A method of securing a pile member in soil having a first unstable upper layer and a second lower semi-stable layer, to support a pile member, comprising the steps of:
a) introducing a first tubular pile member such that said pile member extends through the first unstable upper layer of soil and said pile member terminates at an end positioned within said second lower semi-stable layer;
b) introducing a second tubular member inside of said first tubular pile member, and inserting it deeply enough that its terminating end is positioned below the terminating end of said first tubular member;
c) introducing cement-based grout under controlled pressure through said second tubular member;
d) withdrawing said second tubular member as grout is pumped therethrough, yielding a generally columnar grout formation that is generally in vertical alignment with and substantially below said first tubular member; and
e) lowering said pile member into said grouted material.
Priority Applications (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
US10/625,331 US20050019104A1 (en) | 2003-07-23 | 2003-07-23 | Soil stabilization and pile formation method |
US11/280,513 US20060115333A1 (en) | 2003-07-23 | 2005-11-16 | Soil stabilization and pile formation method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
US10/625,331 US20050019104A1 (en) | 2003-07-23 | 2003-07-23 | Soil stabilization and pile formation method |
Related Child Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
US11/280,513 Continuation-In-Part US20060115333A1 (en) | 2003-07-23 | 2005-11-16 | Soil stabilization and pile formation method |
Publications (1)
Publication Number | Publication Date |
---|---|
US20050019104A1 true US20050019104A1 (en) | 2005-01-27 |
Family
ID=34080187
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
US10/625,331 Abandoned US20050019104A1 (en) | 2003-07-23 | 2003-07-23 | Soil stabilization and pile formation method |
Country Status (1)
Country | Link |
---|---|
US (1) | US20050019104A1 (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2018193686A (en) * | 2017-05-12 | 2018-12-06 | 株式会社技研製作所 | Construction method of support pile |
CN110512596A (en) * | 2019-08-26 | 2019-11-29 | 中国十七冶集团有限公司 | A kind of construction method of elder generation's mud jacking filling pile |
JP2019206868A (en) * | 2018-05-30 | 2019-12-05 | 株式会社フジタ | Micro pile construction method and insertion member for filling grout material used in micro pile construction method |
US20210348355A1 (en) * | 2018-09-25 | 2021-11-11 | Yongguang GAO | Grouting consolidation method for full casing borehole guide prefabricated pile and prefabricated pile therefor |
US11453991B2 (en) * | 2020-07-22 | 2022-09-27 | Zhejiang University | High strength grouting method for single pile rock-socketed foundation of weakly weathered bed rock for offshore wind power |
Citations (19)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US1084063A (en) * | 1912-08-26 | 1914-01-13 | Edward Bignell | Means for forming underground footings for piles and caissons. |
US1599142A (en) * | 1924-11-14 | 1926-09-07 | Macarthur Concrete Pile & Foun | Method of forming piling |
US1658433A (en) * | 1923-12-21 | 1928-02-07 | Ellis Russell Scott | Concrete structure |
US2673453A (en) * | 1950-11-13 | 1954-03-30 | John B Templeton | Means and method for facilitating driving piles |
US2923133A (en) * | 1955-07-12 | 1960-02-02 | Muller Ludwig | Method for making pile structures with concrete casings |
US3084518A (en) * | 1958-07-18 | 1963-04-09 | Hochstrasser Robert | Tubular pile with driving cap |
US3512365A (en) * | 1968-01-19 | 1970-05-19 | Ludwig Muller | Method of forming a pile in situ |
US3559412A (en) * | 1968-07-15 | 1971-02-02 | Raymond Int Inc | Method of forming enlarged base encased concrete piles |
US3808823A (en) * | 1971-04-07 | 1974-05-07 | Bolt Associates Inc | Process and system for increasing load-bearing capacity of soil |
US3851485A (en) * | 1972-04-14 | 1974-12-03 | J Steding | Method and apparatus for installing concrete piles |
US3852971A (en) * | 1973-07-12 | 1974-12-10 | Raymond Int Inc | Pile structure |
US3925998A (en) * | 1974-07-22 | 1975-12-16 | Interpile Usa Inc | Method for forming cast-in-place caseless concrete piles |
US4012915A (en) * | 1975-07-18 | 1977-03-22 | Interpile Usa, Inc. | Driving tips for forming cast-in-place caseless concrete piles |
US4116012A (en) * | 1976-11-08 | 1978-09-26 | Nippon Concrete Industries Co., Ltd. | Method of obtaining sufficient supporting force for a concrete pile sunk into a hole |
US4293242A (en) * | 1977-04-29 | 1981-10-06 | Stanley Merjan | Piles |
US4397588A (en) * | 1981-01-23 | 1983-08-09 | Vibroflotation Foundation Company | Method of constructing a compacted granular or stone column in soil masses and apparatus therefor |
US4605339A (en) * | 1981-07-29 | 1986-08-12 | Roger Bullivant Of Texas, Inc. | Situ pile construction in ground liable to uplift |
US4618289A (en) * | 1984-05-22 | 1986-10-21 | Federer David L | Method of forming a cast-in-place support column |
US5980446A (en) * | 1997-08-12 | 1999-11-09 | Lockheed Martin Idaho Technologies Company | Methods and system for subsurface stabilization using jet grouting |
-
2003
- 2003-07-23 US US10/625,331 patent/US20050019104A1/en not_active Abandoned
Patent Citations (19)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US1084063A (en) * | 1912-08-26 | 1914-01-13 | Edward Bignell | Means for forming underground footings for piles and caissons. |
US1658433A (en) * | 1923-12-21 | 1928-02-07 | Ellis Russell Scott | Concrete structure |
US1599142A (en) * | 1924-11-14 | 1926-09-07 | Macarthur Concrete Pile & Foun | Method of forming piling |
US2673453A (en) * | 1950-11-13 | 1954-03-30 | John B Templeton | Means and method for facilitating driving piles |
US2923133A (en) * | 1955-07-12 | 1960-02-02 | Muller Ludwig | Method for making pile structures with concrete casings |
US3084518A (en) * | 1958-07-18 | 1963-04-09 | Hochstrasser Robert | Tubular pile with driving cap |
US3512365A (en) * | 1968-01-19 | 1970-05-19 | Ludwig Muller | Method of forming a pile in situ |
US3559412A (en) * | 1968-07-15 | 1971-02-02 | Raymond Int Inc | Method of forming enlarged base encased concrete piles |
US3808823A (en) * | 1971-04-07 | 1974-05-07 | Bolt Associates Inc | Process and system for increasing load-bearing capacity of soil |
US3851485A (en) * | 1972-04-14 | 1974-12-03 | J Steding | Method and apparatus for installing concrete piles |
US3852971A (en) * | 1973-07-12 | 1974-12-10 | Raymond Int Inc | Pile structure |
US3925998A (en) * | 1974-07-22 | 1975-12-16 | Interpile Usa Inc | Method for forming cast-in-place caseless concrete piles |
US4012915A (en) * | 1975-07-18 | 1977-03-22 | Interpile Usa, Inc. | Driving tips for forming cast-in-place caseless concrete piles |
US4116012A (en) * | 1976-11-08 | 1978-09-26 | Nippon Concrete Industries Co., Ltd. | Method of obtaining sufficient supporting force for a concrete pile sunk into a hole |
US4293242A (en) * | 1977-04-29 | 1981-10-06 | Stanley Merjan | Piles |
US4397588A (en) * | 1981-01-23 | 1983-08-09 | Vibroflotation Foundation Company | Method of constructing a compacted granular or stone column in soil masses and apparatus therefor |
US4605339A (en) * | 1981-07-29 | 1986-08-12 | Roger Bullivant Of Texas, Inc. | Situ pile construction in ground liable to uplift |
US4618289A (en) * | 1984-05-22 | 1986-10-21 | Federer David L | Method of forming a cast-in-place support column |
US5980446A (en) * | 1997-08-12 | 1999-11-09 | Lockheed Martin Idaho Technologies Company | Methods and system for subsurface stabilization using jet grouting |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2018193686A (en) * | 2017-05-12 | 2018-12-06 | 株式会社技研製作所 | Construction method of support pile |
JP2019206868A (en) * | 2018-05-30 | 2019-12-05 | 株式会社フジタ | Micro pile construction method and insertion member for filling grout material used in micro pile construction method |
JP7032242B2 (en) | 2018-05-30 | 2022-03-08 | 株式会社フジタ | Inserting member for filling grout material used in micropile method and micropile method |
US20210348355A1 (en) * | 2018-09-25 | 2021-11-11 | Yongguang GAO | Grouting consolidation method for full casing borehole guide prefabricated pile and prefabricated pile therefor |
CN110512596A (en) * | 2019-08-26 | 2019-11-29 | 中国十七冶集团有限公司 | A kind of construction method of elder generation's mud jacking filling pile |
US11453991B2 (en) * | 2020-07-22 | 2022-09-27 | Zhejiang University | High strength grouting method for single pile rock-socketed foundation of weakly weathered bed rock for offshore wind power |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US7326004B2 (en) | Apparatus for providing a rammed aggregate pier | |
US8043028B2 (en) | Apparatus for providing a support column | |
US5123209A (en) | Earth engineering apparatus and method | |
CN109440762B (en) | Construction method of filling pile for drainage pump station | |
US9243379B2 (en) | Method of providing a support column | |
US4293242A (en) | Piles | |
US20020176749A1 (en) | Method and apparatus for lifting, leveling, amd underpinning a building foundation | |
US3992890A (en) | Method of forming foundations | |
US4906140A (en) | Method and apparatus for raising and supporting a foundation | |
US4787779A (en) | Method and apparatus for raising and supporting a foundation | |
US20050019104A1 (en) | Soil stabilization and pile formation method | |
JP3725403B2 (en) | Construction method of cast-in-place steel pipe concrete pile by all casing method. | |
KR20090120997A (en) | The method for constructing underwater structure | |
US6471446B2 (en) | Reduced skin friction bore casing | |
CN2892973Y (en) | Strong rammer replacement parapet structure | |
CN111042121A (en) | Construction method of bored backfill end pile foundation | |
JP2006070513A (en) | Height adjusting method of structure | |
US20060115333A1 (en) | Soil stabilization and pile formation method | |
JP2790038B2 (en) | Reinforcement method of existing pile foundation building | |
JP3760343B2 (en) | Drilling bottom stabilization method and construction method of underground building | |
GB2085950A (en) | Driven composite piles | |
JPH0464618A (en) | Pit excavation work method | |
JPS62268423A (en) | Construction work of underground pile used in common for earth anchor | |
JP6243648B2 (en) | Ground anchor construction method | |
JP4080421B2 (en) | How to adjust the height of the structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
STCB | Information on status: application discontinuation |
Free format text: ABANDONED -- FAILURE TO RESPOND TO AN OFFICE ACTION |