WO2018177306A1 - Paroi souterraine fabriquée et son procédé de construction - Google Patents
Paroi souterraine fabriquée et son procédé de construction Download PDFInfo
- Publication number
- WO2018177306A1 WO2018177306A1 PCT/CN2018/080790 CN2018080790W WO2018177306A1 WO 2018177306 A1 WO2018177306 A1 WO 2018177306A1 CN 2018080790 W CN2018080790 W CN 2018080790W WO 2018177306 A1 WO2018177306 A1 WO 2018177306A1
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- wall
- chain
- walls
- cutter
- adjacent
- Prior art date
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/20—Bulkheads or similar walls made of prefabricated parts and concrete, including reinforced concrete, in situ
Definitions
- the invention relates to a prefabricated underground wall and a construction method thereof, and belongs to the technical field of civil engineering foundation construction.
- the existing underground continuous wall technology uses a trenching machine on the ground to excavate a long and narrow deep trough under the condition of mud retaining wall, hoist the steel cage in the trough, and pour the underwater concrete into a unit trough section. This is done piece by piece.
- the main defects are as follows: 1) The underwater construction quality in the tank is difficult to control and detect, and the construction period is long; 2) The interface between the groove sections is difficult to construct and easy to seep; 3) The slotting machine is high and moves along the circumference. Applications are limited.
- the invention provides a prefabricated underground wall and a construction method thereof, the purpose of which is to overcome the defects existing in the prior art, and the main advantage thereof is that the assembly of the adjacent two walls 1 is embedded and welded by the concave and convex, and the connection is safe and reliable.
- the sealing is good; the wall 1 itself has a chain knife for excavating the bottom of the rock, the factory prefabricated wall, the block is divided or the whole is lowered after the site is spliced, the construction is simple, the construction period is short, and the cost is low.
- the underground wall 1 is assembled by the bottom wall 1-1 and a plurality of walls 1-2; the assembling and splicing portions of the adjacent two walls 1 are respectively provided with concave and convex sub-ports of steel structure, that is, convexity of one wall
- the platform is embedded in the groove of another wall, and is divided into two structures: A and B: A.
- the interface of the same wall has both a groove and a boss, and the other wall is reversed;
- B a wall is a groove, and the other wall It is a boss;
- the bottom and sides of the wall 1 are provided with a track 2
- the track 2 is provided with a chain knife 3
- the chain knife 3 is composed of a chain 3-1 and a cutter 3-2 mounted on the chain 3-1, the chain
- the upper plane of the lower wall 1 is lowered to the height set at the ground with the chain cutter, and then the upper part is assembled.
- Wall 1-2 the interface of the adjacent two walls is welded before entering the underground to make it integrated.
- the invention has the advantages that the assembly of the adjacent two walls 1 adopts the concave-convex embedded welding and splicing, and the connection is safe and reliable, and the wall 1 itself has a chain cutter for excavating the bottom rock of the wall, and the factory prefabricated wall 1 is divided into blocks or the whole is dropped after the site is spliced.
- the construction is simple, the construction period is short, and the cost is low.
- Figure 1 is a schematic view showing a structure in which the splicing joints of the adjacent two walls 1 are respectively provided with a concave and convex sub-port of a steel structure, that is, a boss of one wall is embedded in a groove of the other wall;
- Figure 2 is a view of the A-A of Figure 1, and is also a structural schematic diagram of the welding of the bottom wall 1-1 and the upper wall 1-2 rows.
- Figure 3 is a B-direction view of Figure 1, and is also a structural schematic diagram of the chain cutter driving device 5 composed of the driving power device 5-1, the spoil processing device 5-2 and the frame 5-3, and is also a chain knife 3 and a chain knife.
- Figure 4 is a C-C view of Figure 3, also a cross-sectional view of the middle portion of the wall 1;
- Figure 5 is an enlarged view of a portion I of Figure 2, which is also a schematic structural view of the rail 2 at the bottom of the bottom wall 1-1, and is also a mud nozzle 6-1 and a mud pipeline 6 of the mud pipeline device 6 on the bottom wall 1-1.
- Figure 6 is an enlarged view of a portion II of Figure 2, that is, one wall of the adjacent two walls 1 is a groove, and the other wall is a boss, and a plurality of holes are provided at the same position of the adjacent two walls, and the holes are formed at the time of splicing.
- a schematic structural view of the pin 7 is inserted therein, and is also a structural schematic view in which the connecting steel plate 8 is welded at the interface of the adjacent two walls 1 and the thickness after welding is not greater than the thickness of the underground wall 1;
- FIG. 8 is a schematic structural view of another space-curable chain cutter 3, and is also a schematic structural view of the chain 3-1 and the cutter 3-2;
- Figure 9 is a structural schematic view showing the assembly of the chain cutter 3 and the driving device 5 by assembling the bottom wall 1-1 and welding it into a whole;
- Figure 10 is the bottom of the wall 1-1 chain knife 3 excavated rock, the side of the chain knife 3 running from the bottom up to bring the excavated rock to the top, the wall 1-1 and the bottom of the chain knife 3 together to drop to the set position Schematic diagram of the structure;
- Figure 11 is a structural schematic view showing the removal of the driving device 5 after the upper chain cutter 3 is disconnected;
- Figure 12 is a view of the A-A of Figure 11, which is also a schematic structural view of the bottom wall 1-1, and is a structural schematic view of the bottom wall 1-1 on which the plane is lowered to a height position set from the ground;
- Figure 13 is a schematic view showing the structure after assembling the splicing upper wall 1-2, installing the chain cutter 3 and the driving device 5;
- Figure 14 is a view of the A-A of Figure 13, and is also a structural schematic view in which the pin 7 is inserted into the hole during splicing, and the interface is welded by the steel plate 8 to be integrated;
- Figure 15 is the bottom of the wall 1-1 chain knife 3 excavated rock, the side of the chain knife 3 running from the bottom up to bring the excavated geotechnical to the top, the welded wall 1 and the bottom of the chain knife 3 down to a schematic diagram of the structure of the set position;
- Figure 16 is a schematic structural view of the assembly and splicing construction of all the walls 1;
- Fig. 17 is a view taken along the line A in Fig. 16, and is a schematic view showing the structure in which the temporary tooling 4 is taken out after the wall 1 is constructed.
- 1 is the underground wall, which is assembled from the bottom wall 1-1 and several walls 1-2; 1-1 is the bottom wall of the underground wall 1; 1-2 is the wall above the bottom wall of the underground wall 1; It is a rail provided on the bottom and sides of the wall 1; 3 is a chain cutter for excavating rock and soil, consisting of a chain 3-1 and a cutter 3-2 mounted on the chain 3-1; 3-1 is a chain cutter 3 3-2 is a cutter constituting the chain cutter 3; 4 is a temporary tooling during construction; 5 is a chain cutter driving device, which is driven by the power unit 5-1, the spoil handling device 5-2, and the frame 5-3.
- composition Composition
- 5-1 is the driving power device
- 5-2 is the spoil handling device
- 5-3 is the frame
- 6 is the mud pipeline device
- 6-1 is the mud nozzle on the bottom of the wall 1
- 6-2 is the wall 1 internal mud pipeline
- 7 is the pin inserted in the hole when the wall 1 is spliced
- 8 is the steel plate welded when the wall 1 is spliced.
- the underground wall 1 is assembled from the bottom wall 1-1 and a plurality of walls 1-2; the assembly joints of the adjacent two walls 1 are respectively provided with concave and convex ports of steel structure, that is, the bosses of one wall are embedded in the concave of the other wall In the trough, there are two structures A and B: A. The interface of the same wall has both grooves and bosses, and the other wall is opposite; B, one wall is a groove, the other wall is a boss; wall 1 A rail 2 is arranged on the bottom and both sides, and a chain cutter 3 is arranged on the rail 2 during construction. The chain cutter 3 is composed of a chain 3-1 and a cutter 3-2 mounted on the chain 3-1.
- One wall of the adjacent two wall interfaces is a groove, and the other wall is a boss.
- a plurality of holes are arranged at the same position of the adjacent two walls, and a pin is inserted into the hole during the splicing.
- the interface between the adjacent two walls is welded with a connecting steel plate, and the thickness after welding is not greater than the thickness of the underground wall.
- the underground wall 1 is assembled from the bottom wall 1-1 and a plurality of walls 1-2; the assembling and splicing portions of the adjacent two walls 1 are respectively provided with concave and convex sub-ports of steel structure, that is, a wall
- the boss is embedded in the groove of the other wall, and is divided into two structures: A and B: A.
- the interface of the same wall has both a groove and a boss, and the other wall is reversed; B, a wall is a groove, and another One wall is a boss.
- the bottom of the wall 1 and the two sides are provided with a track 2, and the track 2 is provided with a chain cutter 3, the width of the chain cutter 3 is smaller than the width of the groove mouth at the interface, and the chain cutter 3 is connected by the chain 3-1 and the chain 3
- the tool 3-2 is composed of -1, and the driving power device 5-1 drives the chain cutter 3.
- the rock belt is brought up to the upper side, and the device 5-2 separates the rock soil brought by the chain cutter 3 from the bottom of the wall 1 with the chain cutter 3, and the wall 1 and the bottom chain cutter 3 simultaneously run downward, and the upper plane of the lower wall 1-1 follows
- the upper wall 1-2 is assembled and the interface of the adjacent two walls is welded before entering the ground to make it integrated; a wall at the interface between the adjacent two walls
- the groove is the groove, the other wall is a boss, and a plurality of holes are arranged at the same position of the adjacent two walls, and the pin 7 is inserted into the hole during the splicing; the connecting steel plate 8 is welded at the interface of the adjacent two walls, and the welding is performed.
- the thickness afterwards is not greater than the thickness of the underground wall.
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Bulkheads Adapted To Foundation Construction (AREA)
Abstract
L'invention concerne une paroi souterraine fabriquée, constituée par l'épissage de multiples parois (1). La paroi (1) est formée par assemblage d'une paroi inférieure (1-1) et d'une paroi supérieure (1-2) ; un sous-orifice concave-convexe d'une structure en acier est disposé au niveau du joint d'épissage de deux parois adjacentes (1), c'est-à-dire qu'une saillie sur l'une des parois est incorporée dans un évidement sur l'autre des parois ; les surfaces inférieure et latérales des parois (1) sont pourvues de chenilles (2) ; un dispositif de coupe à chaîne (3) est monté sur la chenille (2) pendant la construction ; le dispositif de coupe à chaîne (3) est composé d'une chaîne (3-1) et d'un dispositif de coupe (3-2) monté sur la chaîne (3-1) ; pendant la construction, le dispositif de coupe à chaîne (3) excave simplement de la roche au fond de la paroi (1) ; la paroi (1) et le dispositif de coupe à chaîne inférieur (3) se déplacent vers le bas simultanément ; une fois qu'un plan supérieur d'une paroi inférieure (1) est abaissé avec le dispositif de coupe à chaîne jusqu'à une hauteur définie par rapport au sol, la paroi supérieure (1-2) est assemblée et épissée ; et le soudage est effectué au niveau du joint entre les parois supérieure et inférieure avant que les parois ne soient envoyées sous terre, ce qui permet d'intégrer les parois dans un ensemble. L'invention concerne également un procédé de construction de la paroi souterraine fabriquée.
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710195875.5 | 2017-03-29 | ||
CN201710195875.5A CN106836192A (zh) | 2017-03-29 | 2017-03-29 | 一种装配式地下墙及其施工法 |
Publications (1)
Publication Number | Publication Date |
---|---|
WO2018177306A1 true WO2018177306A1 (fr) | 2018-10-04 |
Family
ID=59141351
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
PCT/CN2018/080790 WO2018177306A1 (fr) | 2017-03-29 | 2018-03-28 | Paroi souterraine fabriquée et son procédé de construction |
Country Status (2)
Country | Link |
---|---|
CN (1) | CN106836192A (fr) |
WO (1) | WO2018177306A1 (fr) |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106836192A (zh) * | 2017-03-29 | 2017-06-13 | 王燏斌 | 一种装配式地下墙及其施工法 |
CN108035338A (zh) * | 2017-11-24 | 2018-05-15 | 上海市机械施工集团有限公司 | 预制地墙及其施工方法 |
CN114108797A (zh) * | 2021-10-21 | 2022-03-01 | 王树生 | 一种沉墙基础及其施工装置和施工法 |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5985021A (ja) * | 1982-11-05 | 1984-05-16 | Kajima Corp | 地下連続壁工法及びその工法に使用する装置 |
JPS62233328A (ja) * | 1986-04-01 | 1987-10-13 | Fusao Sakano | 爪付篦型バケットを備えた掘削装置本体を介して置き去り式に擁壁を設置する設置装置 |
JPH04179726A (ja) * | 1990-11-13 | 1992-06-26 | Kazutoshi Isachi | 簡易地下連続壁工法における壁体用部材と該壁体用部材を使用した簡易地下連続壁工法 |
CN2260103Y (zh) * | 1996-08-05 | 1997-08-20 | 郭同元 | 桩 |
CN103334422A (zh) * | 2013-06-26 | 2013-10-02 | 中国建筑股份有限公司 | 一种可装配埋入式预制空心地下连续墙及其施工方法 |
CN105887806A (zh) * | 2016-06-13 | 2016-08-24 | 上海强劲地基工程股份有限公司 | 装配式地下连续墙及其施工方法 |
CN106836192A (zh) * | 2017-03-29 | 2017-06-13 | 王燏斌 | 一种装配式地下墙及其施工法 |
-
2017
- 2017-03-29 CN CN201710195875.5A patent/CN106836192A/zh active Pending
-
2018
- 2018-03-28 WO PCT/CN2018/080790 patent/WO2018177306A1/fr active Application Filing
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5985021A (ja) * | 1982-11-05 | 1984-05-16 | Kajima Corp | 地下連続壁工法及びその工法に使用する装置 |
JPS62233328A (ja) * | 1986-04-01 | 1987-10-13 | Fusao Sakano | 爪付篦型バケットを備えた掘削装置本体を介して置き去り式に擁壁を設置する設置装置 |
JPH04179726A (ja) * | 1990-11-13 | 1992-06-26 | Kazutoshi Isachi | 簡易地下連続壁工法における壁体用部材と該壁体用部材を使用した簡易地下連続壁工法 |
CN2260103Y (zh) * | 1996-08-05 | 1997-08-20 | 郭同元 | 桩 |
CN103334422A (zh) * | 2013-06-26 | 2013-10-02 | 中国建筑股份有限公司 | 一种可装配埋入式预制空心地下连续墙及其施工方法 |
CN105887806A (zh) * | 2016-06-13 | 2016-08-24 | 上海强劲地基工程股份有限公司 | 装配式地下连续墙及其施工方法 |
CN106836192A (zh) * | 2017-03-29 | 2017-06-13 | 王燏斌 | 一种装配式地下墙及其施工法 |
Also Published As
Publication number | Publication date |
---|---|
CN106836192A (zh) | 2017-06-13 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
WO2018177306A1 (fr) | Paroi souterraine fabriquée et son procédé de construction | |
US9371623B2 (en) | Diaphragm wall apparatus and methods | |
CN110043264B (zh) | 一种顶进预制矩形竖井结构型式的施工方法 | |
WO2018133740A1 (fr) | Bâtiment souterrain et son procédé de construction | |
WO2018133739A1 (fr) | Fondation ayant un dispositif de coupe à chaîne à la base pendant la construction et son procédé de construction | |
WO2018177307A1 (fr) | Bâtiment souterrain préfabriqué et son procédé de construction | |
JP6927165B2 (ja) | 接合構造物、杭式構造物ならびに杭式構造物の撤去方法 | |
WO2018133711A1 (fr) | Fondation de pilier et procédé de construction associé | |
WO2018133746A1 (fr) | Bâtiment souterrain formé de pieux et de murs, et son procédé de construction | |
JP2010222943A (ja) | 壁部材用接続金具及び地中連続壁構築方法 | |
WO2018177304A1 (fr) | Bâtiment souterrain préfabriqué et son procédé de construction | |
CN203270642U (zh) | 一种铣槽机掘削搅拌机构 | |
WO2018133742A1 (fr) | Appareil de coupe de rainure utilisé pour une construction de paroi souterraine et procédé de construction associé | |
CN203475439U (zh) | 基于预制地墙的基坑围护结构施工方法中的专用预制地墙 | |
JP4434022B2 (ja) | 鋼殻エレメントの継手構造及びそれを用いたトンネルの施工方法 | |
CN109914477B (zh) | 地下综合管廊预制拼装管道 | |
CN207727550U (zh) | 一种装配式地下墙 | |
WO2018177305A1 (fr) | Pieu rainuré pour bâtiment souterrain préfabriqué et son procédé de construction | |
WO2018166523A1 (fr) | Fondation en eau profonde, dispositif de construction, et procédé de construction associé | |
WO2018133748A1 (fr) | Navire de construction pour tunnel sous-marin et procédé de construction associé | |
WO2018177308A1 (fr) | Structure d'interface de construction souterraine fabriquée et son procédé de construction | |
CN108824523B (zh) | 一种链锯式切割箱 | |
CN103741724B (zh) | 一种预制预应力地下连续墙接头 | |
CN103243763B (zh) | 一种铣槽机纠偏机构 | |
CN204608826U (zh) | 全断面搅拌切削造墙机 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
121 | Ep: the epo has been informed by wipo that ep was designated in this application |
Ref document number: 18777826 Country of ref document: EP Kind code of ref document: A1 |
|
NENP | Non-entry into the national phase |
Ref country code: DE |
|
122 | Ep: pct application non-entry in european phase |
Ref document number: 18777826 Country of ref document: EP Kind code of ref document: A1 |