WO2016043641A1 - House foundation system and method of forming a house foundation and a method for forming a floor structure - Google Patents

House foundation system and method of forming a house foundation and a method for forming a floor structure Download PDF

Info

Publication number
WO2016043641A1
WO2016043641A1 PCT/SE2015/050716 SE2015050716W WO2016043641A1 WO 2016043641 A1 WO2016043641 A1 WO 2016043641A1 SE 2015050716 W SE2015050716 W SE 2015050716W WO 2016043641 A1 WO2016043641 A1 WO 2016043641A1
Authority
WO
WIPO (PCT)
Prior art keywords
foundation
frame
foundation frame
house
providing
Prior art date
Application number
PCT/SE2015/050716
Other languages
English (en)
French (fr)
Inventor
John HÖGLUND
Peter Lindqvist
Original Assignee
Get Ab
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Get Ab filed Critical Get Ab
Priority to ES15841882T priority Critical patent/ES2906575T3/es
Priority to PL15841882T priority patent/PL3194664T3/pl
Priority to HRP20220221TT priority patent/HRP20220221T1/hr
Priority to EP15841882.2A priority patent/EP3194664B1/en
Priority to LTEPPCT/SE2015/050716T priority patent/LT3194664T/lt
Priority to DK15841882.2T priority patent/DK3194664T3/da
Priority to SI201531788T priority patent/SI3194664T1/sl
Publication of WO2016043641A1 publication Critical patent/WO2016043641A1/en
Priority to CY20221100178T priority patent/CY1125407T1/el

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/48Special adaptations of floors for incorporating ducts, e.g. for heating or ventilating
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/01Flat foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/01Flat foundations
    • E02D27/013Shuttering specially adapted therefor
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/01Flat foundations
    • E02D27/016Flat foundations made mainly from prefabricated concrete elements

Definitions

  • the present disclosure relates to a house foundation system, and to a method for forming a house foundation and a method for forming a floor structure.
  • Foundations for construction of buildings are traditionally formed by a concrete ground plate arranged on a layer of insulating material, such as cellular plastic, in an excavation.
  • the layer of cellular plastic may sometimes need to be as thick as 400 mm to provide necessary insulating properties.
  • the concrete ground plate, casted on site on the insulating material, may in such cases have difficulties to dry and cure. The drying can only be performed upwards due to the presence of cellular plastic below, and the drying and curing may take long time.
  • a prefabricated concrete ground plate would solve problems
  • a house foundation system comprising a foundation frame for arrangement on an excavation bottom.
  • the foundation frame comprises a plurality of height- adjustable support members which are adjustable for providing a leveled foundation frame on an uneven excavation bottom.
  • the frame may be prefabricated and arranged in an excavation and still provide a leveled foundation.
  • the need for an onsite casted concrete ground to get a leveled foundation is thereby avoided.
  • the time needed for providing a ready, dried house foundation may thereby be significantly shortened.
  • the support members may stand directly on the excavation bottom or on support plates arranged on the excavation bottom.
  • Each support member may be configured to provide a height-adjustability of a section of the frame which may be adjusted to provide a leveled upper surface of the frame.
  • the frame may in one embodiment comprise at least four support members, each arranged at a corner, or adjacent to a corner, of the frame.
  • the frame may further comprise additional support members on other sections of the frame to provide a more accurate height-adjustability to level the frame.
  • the foundation frame comprises at least four height-adjustable support members arranged in each corner of the foundation frame.
  • the foundation frame may be tilted and adjusted in several degrees of freedom.
  • the foundation may thus be adjusted length-wise as well as cross-wise relative to the frame.
  • each height-adjustable support member may comprise a threaded spindle or screw arranged in a
  • the spindle may be rotated to raise or lower the frame when standing on ground.
  • the holes may extend through the frame.
  • a threaded spindle arranged in such hole may then extend both below and above the frame when standing on ground.
  • the spindle may thereby be accessed from above for height-adjustment when the foundation frame is arranged in an excavation.
  • the hole may be made in the pre-casted frame.
  • the foundation frame may be made of light ballast concrete.
  • the ballast in the light ballast concrete may be foam glass, lightweight-expanded aggregate, pumice or the like, such as other ceramic material. Such light ballast concrete may provide insulating properties to the frame and the house foundation system.
  • the house foundation system may comprise an insulating and draining granulate material. Such material may be used for filling the frame when arranging the house foundation system in an
  • Such insulating and draining granulate material may be foam glass, lightweight-expanded aggregate, pumice or the like. Such materials may both provide an insulating function and a draining function to the house foundation. Such material may further be nonorganic, thereby providing a house foundation system free from organic material.
  • the foundation frame may be formed by frame modules connected by connection elements.
  • a frame in modules may be easier to arrange on an excavation bottom.
  • Connection elements may be arranged at the ends of the modules to interconnect modules.
  • the connection elements may be integrated with the location of the support members.
  • At least one of the frame modules comprises a plurality of support members, each support member associated with a corner of the frame module.
  • each frame module may be adjustable as required on an uneven excavation.
  • Each support member provides adjustability for each corner and results in movability in several degrees of freedom.
  • the house foundation system may further comprise at least one channel system for drying the foundation when arranged in an excavation.
  • the drying may be achieved by providing a controlled pressure flow of for instance air in the channel system, which may be achieved by using any or a mixture of the following: underpressure, overpressure, balanced pressure, varying pressure.
  • the channel system may comprise a channel formed in the granulate material, a perforated tube or hose arranged in the granulate material.
  • the channel system may be connected to a dehydrator arrangement configured to provide an underpressure in the channel system and thereby enable extraction of humidity in the foundation. Humidity in the foundation may thereby be drawn towards the channel system and extracted through the channel system.
  • a first section of the channel system be configured to provide a flow of dry air into the foundation, and a second section of the channel system may be configured to extract air from the foundation, thereby extracting humidity in the foundation.
  • the channel system may as well, or alternatively be arranged to provide dry air to the foundation in order to achieve a more quick and efficient drying procedure.
  • a method for forming a house foundation comprising the steps of arranging a foundation frame on an excavation bottom, filling the excavation with an insulating and draining granulate material, and providing a ground plate supported by said foundation frame.
  • Such method may provide a way of forming a house foundation which without organic material provides good insulation, draining and stability properties.
  • the foundation frame and/or the ground plate may be prefabricated, thereby facilitating and speeding up the foundation formation.
  • the granulate material may be foam glass, lightweight-expanded aggregate, pumice or the like. Such materials have good insulating and draining properties. The materials are further nonorganic, which is an advantage when it comes to preservation of the foundation over time.
  • the method further comprises a step of arranging a capillary barrier on the excavation bottom.
  • the capillary barrier may be arranged for preventing humidity from the ground to reach the granulate material on top of the capillary barrier.
  • the method may comprise a step of providing at least one channel system below the granulate material for drying the foundation using a controlled pressure flow of a gaseous medium.
  • Controlled pressure may be achieved by using any of the following: underpressure, overpressure, balanced pressure, varying pressure.
  • the gaseous medium may be air.
  • the channel system may be configured for connection to a dehydrator arrangement.
  • the channel system with the dehydrator may be arranged for extraction of humidity in the foundation using underpressure in the channel system.
  • the method for forming a house foundation may further comprise a step of extracting humidity from the house foundation by providing underpressure in said channel system.
  • varying pressure it is meant that the pressure may be varying during a period of time, such as pulsating in different positive pressure rates, or even varying between positive and negative pressure.
  • the ground plate may comprise light ballast concrete.
  • the ballast in the light ballast concrete ground plate may be foam glass, lightweight-extracted aggregate, pumice or the like.
  • a ground plate of such material may provide good both insulating and draining properties.
  • the ground plate may be made of foam concrete.
  • the method may further comprise a step of providing a support casting of the foundation and/or the ground plate.
  • the foundation frame may be fixed in place in the excavation.
  • the ground plate may then be fixed in position on the foundation frame by providing a support casting between the ground plate and the foundation frame.
  • the ground plate may thereby be fixed in position relative to the frame.
  • the support casting may be provided using light concrete, foam concrete or light ballast concrete using foam glass, lightweight-extracted aggregate or pumice as ballast.
  • the support casting may be provided such that it extends through couplings between frame modules.
  • the support casting may further extend towards the ends of support members by which the foundation frame stands on the excavation bottom.
  • support casting may be provided in a space between the granulate material within the foundation frame and the ground plate arranged on the foundation frame.
  • the foundation frame may comprise a plurality of height-adjustable support members, adjustable to provide a leveled foundation frame on an uneven excavation bottom.
  • the method may then further comprise a step of adjusting the support members to provide a leveled foundation frame arranged on the excavation bottom.
  • Such frame may provide arrangement in a leveled manner using the height-adjustable support members, thereby providing a facilitated house foundation forming method.
  • a method for forming a floor structure comprising the steps of providing a slab,
  • the slab may be arranged where the floor structure is to be built.
  • the slab may be a prefabricated concrete plate or a concrete plate cast on site.
  • the slab may be a steel slab, wooden slab, or any other suitable material.
  • the granulate material may be provided on top of the slab.
  • the channel system may comprise a channel formed in the granulate material, a perforated tube or hose arranged in the granulate material.
  • the dehydration may be done providing a controlled pressure flow in the channels such that moisture in the floor structure, and specifically in the granulate material may be extracted through the channels.
  • the channel system may be arranged in the lower region in the layer of granulate material, the moisture may be transported downwards, leaving the upper surface of the granulate material dry in order to allow floor installation more quickly without compromising the quality of the floor.
  • the floor structure according to the method may be suitable for any floor. It may be a floor structure intended to be used inside a building such as a ground foundation or a floor above ground. It may also be suitable for outdoor floors, such as ground terraces, roof terraces and balconies and the like.
  • the granulate material may be foam glass, lightweight-expanded aggregate, pumice or the like. Such materials may both provide an insulating function and a draining function to the floor structure. Such material may further be nonorganic, thereby providing a floor structure free from organic material.
  • the slab plate may be one of the following: a prefabricated concrete slab plate, a steel slab, a wooden slab.
  • a concrete plate may be of light ballast concrete or the like. Any of the mentioned may also be suitable in an outdoor floor structure.
  • the slab plate may be provided by casting a concrete slab.
  • controlled pressure may be achieved by using any of the following: underpressure, overpressure, balanced pressure, varying pressure.
  • controlled pressure it is meant that the pressure in the channel system may be controlled or manoeuvred by a user, for instance via a control device.
  • the drying and curing may be adapted to suit the specific material and environment.
  • the pressure may be controlled depended on the moisture level and the type of material. For instance, the dehydration may be achieved via a dehydrating suction arrangement causing underpressure in the channels such that the moisture may be transported downwards in the structure and extracted through the channels.
  • the provided suction may cause the moisture to transport downwards towards the channels and thereby allow the slab cure more quickly than a floor structure without any dehydrating function.
  • varying pressure it is meant that the pressure may be varying during a period of time, such as pulsating in different positive pressure rates, or even varying between positive and negative pressure. By doing this, the surface of the granulate material may dry more quickly so that floor installation may proceed faster.
  • the dehydrating system may be running during subsequent floor installation in order to ensure completely dry floor structure.
  • the channel system may be provided with an airing function for ventilating the floor structure.
  • the channel system may be connected to an arrangement providing dried air to the floor structure through the channel system. By doing this, the air may flow in the channels, causing the moisture in the floor structure to vent out more easily.
  • different channel systems may be arranged for different purposes in the floor structure. For instance, one channel system may be arranged to provide a dehydrating function while a second channel system may be arranged to provide dry air.
  • the different functions of the channel systems may thus interact in order to provide a more efficient drying of the floor structure. A quicker drying process may allow quicker floor installation.
  • the systems may be running simultaneously and also during subsequent floor installation in order to ensure a completely dry floor structure.
  • a concrete screed may be provided on top of said granulate material.
  • concrete screed it is meant a layer of concrete in order to protect the granulate material.
  • the concrete screed may in some embodiments be of other material than concrete for instance a cement material or another suitable material.
  • the concrete screed may be arranged in order to protect the underlying granulate material.
  • a moisture barrier may be provided above the concrete screed. Subsequently, a superstructure may be provided above the moisture barrier.
  • the moisture barrier may be a waterproofing membrane or fiber or the like with the characteristics of preventing moisture from penetrating the underlying granulate material from above.
  • the floor structure may be suitable to be arranged outdoors, such as for terrace flooring or the like. When used outside, there may be needed a protective layer such as a moisture barrier to prevent moisture from the outdoor air or rain water from entering the structure.
  • a superstructure On top of the moisture barrier, a superstructure may be arranged.
  • the superstructure may be any material required, such as earth and grass, a wooden deck or the like. However, the step of providing a superstructure may be optional.
  • flooring may be provided on top of the concrete screed.
  • it may be suitable to arrange comfortable flooring which may be any floor required for the use of the room.
  • any steps according to the method may be performed in any suitable order. Since a floor may be built from the bottom and upwards, it may be suitable to perform steps accordingly. However, it is an alternative that one or more of the mentioned steps are performed in an order different from that chronological order mentioned to provide a prefabricated structure. The method may thus be unlimited to the order of steps.
  • Fig. 1 is a perspective view of a house foundation system according to an embodiment of the invention
  • Fig. 2 is a cross-sectional view of a house foundation system
  • Fig. 3 is a cross-sectional view of a house foundation system
  • Fig. 4 is a cross-sectional view of a house foundation system
  • Fig. 5 is a cross-sectional view of a house foundation system
  • Fig. 6 is a cross-sectional view of a house foundation system
  • Fig. 7 is a flow chart of a method according to an embodiment of the invention.
  • Fig. 8 is a cross sectional view of a floor structure according to an embodiment of the invention.
  • Fig. 9 is a cross sectional view of a floor structure according to an embodiment of the invention.
  • Figs. 1 -3 illustrate a house foundation system 1 comprising a
  • foundation frame 10 according to an embodiment of the invention.
  • the foundation frame 10 is arranged in an excavation 2 to form a house
  • the foundation frame 10 comprises a plurality of support members 12.
  • the support members 12 are formed by threaded spindles or screws 12 arranged in corresponding threaded holes 14 in the foundation frame 10. See fig. 2.
  • the support members 12 support the foundation frame 10 on the ground in the excavation 2.
  • the bottom surface of the excavation 2 is difficult or impossible to get completely plane.
  • Due to the threaded support members 12 in the threaded holes 14 are the support points of the foundation frame 10 adjustable in height.
  • the support members 10 are located at least at, or adjacent to, the corners of the foundation frame 10. In the illustrated embodiment are support members 12 further located at a midpoint of sides of the foundation frame 10.
  • support members 12 provide that different parts of the foundation frame 10 may be height-adjusted to provide a leveled upper side of the foundation frame 10.
  • a plurality of support members 12 are grouped together at location along the foundation frame 10. To provide stability of the foundation frame 10 and the support members 12 are all support members 12 placed on a support plate 18 on the excavation bottom.
  • the foundation frame 10 formed by a plurality of frame modules 10a-1 Of.
  • the frame modules 10a-1 Of are in the corners of the frame 10 connected by corner modules 1 1 .
  • At the ends of the frame modules 10a-f are coupling members 16 arranged.
  • Each coupling member 16 is configured for coupling to a corresponding coupling member 16 on another frame module.
  • the foundation frame 10 further comprises a shoulder 19 at an inner side of the frame 10.
  • the shoulder 19 is, as seen in fig. 2 and further in fig. 6, provided for support of a ground plate 40 of the house foundation system 1 .
  • the ground plate 40 may be arranged on the shoulder 19 of the foundation frame 10 and thereby be plane.
  • the ground plate 40 may thereby be prefabricated given the size of the foundation frame 10, and still provide a leveled surface of the house foundation system 1 .
  • the foundation frame 10 is preferably made of foam glass to provide a frame that has an insulating function.
  • Figs. 4-6 further illustrate the house foundation system 1 , and also the method of forming a house foundation system according to an embodiment of the invention.
  • the foundation frame 10 is arranged in an excavation 2, standing on the support members 12.
  • the support members 12 are further placed on support plates 18 on the ground in the excavation 2.
  • the granulate material 30 is in one embodiment made of foam glass. In another embodiment is the granulate material 30 lightweight- expanded aggregate, pumice or the like.
  • the granulate material 30 is packed in the excavation.
  • the granulate material 30 is provided, and packed, both inside the foundation frame 10 and outside the foundation frame 10, within the excavation 2. When packed in the excavation 2 will the granulate material 30 provide good insulation function as well as a draining function of the foundation.
  • the granulate material 30 is filled up to a level below the level of the shoulder 19 of the foundation frame 10. In one embodiment is the granulate material filled up to a level 30-80 mm below the shoulder 19 of the foundation frame 10, preferably about 50 mm below the shoulder 19.
  • On top of the packed granulate material 30 may a fiber cloth layer be arranged.
  • the ground plate 40 is arranged on the shoulder 19 of the foundation frame 10. A space 5 is thereby formed between the granulate material 30 and the ground plate 40.
  • the ground plate 40 is made of light ballast concrete comprising ballast in form of foam glass, lightweight- expanded aggregate, pumice or the like.
  • the ground plate 40 may in another embodiment be made of light concrete or foam concrete.
  • the ground plate 40 may further, instead of being prefabricated and put in place on the foundation frame 10, be casted directly in place on the foundation frame 10 and the granulate material 30.
  • the final step of forming the house foundation 1 is to provide a support casting for fixating the foundation frame 10 and the ground plate 40.
  • the support casting is performed to fix the ground plate 40 to the foundation frame 10.
  • the support casting is provided in a space 4 between the ground plate 40 and the foundation frame 10.
  • the support casting then extends downwards through the coupling between frame modules 10a-f.
  • the coupling members 16 are thereby fixed to the frame modules at each coupling.
  • the support casting further fixates the foundation frame 10 towards the excavation bottom by filling a space 3 below the foundation frame 10 at which the support members 12 support the frame 10. Further, the support casting may fill the space 5 between the granulate material 30 and the ground plate 40, thereby further fixating the ground plate 40 to the foundation frame 10 and the granulate material 30.
  • the house foundation system 1 comprises a channel system 20 arranged at the bottom of the excavation 2.
  • the specific channel system 20 is connected to a dehydrator arrangement 22 in order to provide an underpressure in the channel system 20.
  • Dehydration may also be achieved by providing any controlled pressure flow of a gaseous medium, such as air, in the channel system 20 such that extraction of humidity from the foundation be performed, especially from the granulate material 30.
  • the controlled pressure may be achieved from any suitable flow, such as underpressure, overpressure, balanced pressure or varying pressure.
  • the method of forming a house foundation may comprise a step of providing a controlled pressure flow of for instance air or another gaseous medium in a channel system 20 in the foundation 1 to extract humidity therefrom.
  • the channel system 20 may alternatively be arranged to provide dry air to the foundation for an alternative drying procedure. Another option may be to provide two or more channel systems, wherein one may be connected to a dehydrator arrangement, and the second system provide dry air. The channel systems 20 may thus interact simultaneously for a more efficient drying procedure.
  • Fig. 7 illustrates a flow chart of a method of forming a house foundation according to an embodiment of the invention.
  • the method 100 comprises a step 1 10 of arranging a foundation frame 10 on the bottom of an excavation 2.
  • the foundation frame 10 comprises, in one embodiment, height-adjustable support members 12 that enable the foundation frame 10 to be height- adjusted to be leveled.
  • the method may then further comprise a step of adjusting the support members to provide a leveled foundation frame 10.
  • the method 100 further comprises a step 120 of filling the excavation 2 with an insulating and draining granulate material 30.
  • the granulate material 30 may for instance be foam glass.
  • the granulate material 30 is provided both inside and outside the foundation frame 10 in the excavation 2.
  • the step 120 may further comprise a step of packing the granulate material 30.
  • the method 100 comprises a step 130 of providing a ground plate 40 on the foundation frame 10.
  • the ground plate 40 can be prefabricated to shorten the time of the forming of the house foundation 1 .
  • the method comprises an optional step 140 of providing a support casting for fixating the ground plate 40 to the foundation frame 10.
  • the support casting further fixates the foundation frame 10 on the bottom of the excavation 2.
  • the described and illustrated embodiments comprise one foundation frame 10 in one piece or modules for receiving one ground plate 40 thereon.
  • the house foundation system may as well comprise further sections or modules of the foundation frame to form a plurality of frames arranged next to each other or interconnected by sharing frame modules.
  • Foundation frame configurations having various forms may thereby be formed, and thereby also being configured for receiving two or more ground plates thereon.
  • a foundation frame may comprise a rectangular shaped outer frame section being divided into two portions by an intermediate frame module.
  • the intermediate frame module may thereby be shared by the two portions.
  • the intermediate frame module may further be configured to support two ground plates, one for each portion of the foundation frame, by having two opposite shoulders.
  • Fig. 8 illustrates a cross sectional view of a floor structure 200 according to an embodiment of the invention.
  • the floor structure in Fig. 8 may be a general type of floor structure 200 typically used inside a building. This type of floor structure 200 may be suitable above ground level.
  • a slab 50 in the bottom of the floor structure 200 is provided first and may be made of a concrete material.
  • the slab may alternatively be made of other suitable material such as steel or wood. It may be a prefabricated plate.
  • a layer of insulating and draining granulate material 30 may be provided on top of the slab 50.
  • two channel systems 20 are arranged inside the layer of granulate material 30, two channel systems 20 are arranged. Preferably the channel systems 20 are arranged before the granulate material 30 is arranged.
  • Fig. 8 illustrates an embodiment using two channel systems 20, wherein a first channel system 21 is connected to a dehydrating arrangement causing suction and underpressure in the channel 21 .
  • a second channel system 22 is connected to an arrangement providing dry air to the floor structure.
  • the two channel systems cooperate to make the drying procedure more efficient and time reducing.
  • Arrows in channel 21 and channel 22 in Fig. 8 give guidance to the flow direction.
  • the granulate material may be cast on top of the slab.
  • a concrete screed 60 is provided on top of the granulate material 30, but it may alternatively be a prefabricated plate.
  • the concrete screed 60 may typically be arranged to protect the granulate material and to provide a suitable foundation for flooring.
  • the concrete screed 60 may thus be of other material suitable for that function.
  • the next step is to provide flooring 70 on top of the concrete screed 60.
  • the flooring may be any suitable flooring such as wooden boards.
  • Fig. 9 illustrates another embodiment of a floor structure 200 suitable for outdoor use.
  • a slab 50 is provided in the bottom of the floor structure 200.
  • the slab 50 may be of a suitable material such as concrete, steel or wood.
  • an insulating and draining material 30 is provided on top of the slab.
  • the insulating and draining material may be a granulate material.
  • two channel systems 20 are arranged such as illustrated in Fig. 8.
  • the channel systems 20 are arranged before the granulate material 30 is arranged.
  • a concrete screed 60 is arranged on top of the granulate material 30, a concrete screed 60 is arranged.
  • the concrete screed 60 may be provided in order to protect the granulate material.
  • the concrete screed 60 may be an onsite cast concrete plate.
  • a membrane layer such as a moisture barrier 80.
  • the moisture barrier 80 may be provided to protect the underlying layers from moisture penetrating the floor structure 200 from above.
  • a membrane layer such as a moisture barrier 80.
  • the superstructure 90 may be arranged.
  • the superstructure 90 may consist of earth and grass, or for instance a wooden deck.

Landscapes

  • Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Paleontology (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Foundations (AREA)
  • Building Environments (AREA)
PCT/SE2015/050716 2014-09-15 2015-06-18 House foundation system and method of forming a house foundation and a method for forming a floor structure WO2016043641A1 (en)

Priority Applications (8)

Application Number Priority Date Filing Date Title
ES15841882T ES2906575T3 (es) 2014-09-15 2015-06-18 Procedimiento para formar una estructura de suelo y procedimiento para formar los cimientos de una casa
PL15841882T PL3194664T3 (pl) 2014-09-15 2015-06-18 Sposób formowania konstrukcji podłogowej i sposób formowania fundamentu domu
HRP20220221TT HRP20220221T1 (hr) 2014-09-15 2015-06-18 Postupak za formiranje podne konstrukcije i postupak za formiranje temelja kuće
EP15841882.2A EP3194664B1 (en) 2014-09-15 2015-06-18 Method for forming a floor structure and method for forming a house foundation
LTEPPCT/SE2015/050716T LT3194664T (lt) 2014-09-15 2015-06-18 Būdas grindų konstrukcijai formuoti ir būdas namo pamatams formuoti
DK15841882.2T DK3194664T3 (da) 2014-09-15 2015-06-18 Fremgangsmåde til at danne en gulvstruktur og fremgangsmåde til at danne et husfundament
SI201531788T SI3194664T1 (sl) 2014-09-15 2015-06-18 Postopek za tvorjenje talne strukture in postopek za tvorjenje temelja hiše
CY20221100178T CY1125407T1 (el) 2014-09-15 2022-03-01 Μεθοδος για τη διαμορφωση μιας δομης δαπεδου και μεθοδος για τη διαμορφωση των θεμελιων ενος οικηματος

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
SE1451067-1 2014-09-15
SE1451067A SE1451067A1 (sv) 2014-09-15 2014-09-15 House foundation system and method of forming a house foundation

Publications (1)

Publication Number Publication Date
WO2016043641A1 true WO2016043641A1 (en) 2016-03-24

Family

ID=55662376

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/SE2015/050716 WO2016043641A1 (en) 2014-09-15 2015-06-18 House foundation system and method of forming a house foundation and a method for forming a floor structure

Country Status (12)

Country Link
EP (1) EP3194664B1 (hr)
CY (1) CY1125407T1 (hr)
DK (1) DK3194664T3 (hr)
ES (1) ES2906575T3 (hr)
HR (1) HRP20220221T1 (hr)
HU (1) HUE057789T2 (hr)
LT (1) LT3194664T (hr)
PL (1) PL3194664T3 (hr)
PT (1) PT3194664T (hr)
SE (1) SE1451067A1 (hr)
SI (1) SI3194664T1 (hr)
WO (1) WO2016043641A1 (hr)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SE1950930A1 (en) * 2019-08-14 2021-02-15 I & P I Norr Ab An adjustment system, and adjustable support, a method of orienting an element, and use of such system

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2454952A1 (de) 1973-11-22 1975-06-12 Euroc Administration Ab Verfahren zur herstellung eines bodenbelages oder eines bauelementes dafuer mit eingelegten heizkoerpern
SE442649B (sv) * 1984-06-06 1986-01-20 Johnny Johansson Prefabricerad tryckplatta
US4867377A (en) * 1983-12-28 1989-09-19 Ingestroem Curt Holger Method of controlling the conditions in a dwelling-house
DE19543507A1 (de) 1995-11-22 1997-05-28 Gerhard Fabritz Fußbodenheizung
WO2000020694A1 (en) * 1998-10-07 2000-04-13 Skanska Sverige Ab A method for production of a foundation plate for a building and a foundation plate manufactured according to the method
US6718711B1 (en) * 1999-01-26 2004-04-13 Alutiiq Manufacturing Contractors, Llc Prefabricated housing
EP1455022A2 (en) * 2003-03-04 2004-09-08 Roxbury Limited Forming building foundations
JP2005171637A (ja) * 2003-12-11 2005-06-30 Takayama Metal Industrial Co Ltd 型枠支持具及び基礎凹部の施工方法
GB2436686A (en) * 2006-03-30 2007-10-03 Roxbury Ltd Ventilated foundation
WO2013171605A1 (en) * 2012-05-14 2013-11-21 Nev-X Systems Limited Modular building system

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
NL8002702A (nl) * 1980-05-09 1981-12-01 Pelt & Hooykaas Elcemo Bv Werkwijze voor het aanbrengen van verwarmingsmediumtransportleidingen in een vloer of wand.
JPS5860725U (ja) * 1982-07-22 1983-04-23 株式会社ラザ− 冷暖房床構造
US5586416A (en) * 1995-03-22 1996-12-24 Hess, Iii; John Concrete form with integral drain
US20050274295A1 (en) * 2004-04-16 2005-12-15 University Of Iowa Research Foundation Multi-function construction material, system, and method for use around in-ground foundations
DE102011054069A1 (de) * 2011-09-29 2013-04-04 Entsorgungstechnik Kraus Martin E.K. Verfahren zur Herstellung großflächiger Bodenheizungen und durch dieses Verfahren hergestellte Bodenheizung

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2454952A1 (de) 1973-11-22 1975-06-12 Euroc Administration Ab Verfahren zur herstellung eines bodenbelages oder eines bauelementes dafuer mit eingelegten heizkoerpern
US4867377A (en) * 1983-12-28 1989-09-19 Ingestroem Curt Holger Method of controlling the conditions in a dwelling-house
SE442649B (sv) * 1984-06-06 1986-01-20 Johnny Johansson Prefabricerad tryckplatta
DE19543507A1 (de) 1995-11-22 1997-05-28 Gerhard Fabritz Fußbodenheizung
WO2000020694A1 (en) * 1998-10-07 2000-04-13 Skanska Sverige Ab A method for production of a foundation plate for a building and a foundation plate manufactured according to the method
US6718711B1 (en) * 1999-01-26 2004-04-13 Alutiiq Manufacturing Contractors, Llc Prefabricated housing
EP1455022A2 (en) * 2003-03-04 2004-09-08 Roxbury Limited Forming building foundations
JP2005171637A (ja) * 2003-12-11 2005-06-30 Takayama Metal Industrial Co Ltd 型枠支持具及び基礎凹部の施工方法
GB2436686A (en) * 2006-03-30 2007-10-03 Roxbury Ltd Ventilated foundation
WO2013171605A1 (en) * 2012-05-14 2013-11-21 Nev-X Systems Limited Modular building system

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
See also references of EP3194664A4

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SE1950930A1 (en) * 2019-08-14 2021-02-15 I & P I Norr Ab An adjustment system, and adjustable support, a method of orienting an element, and use of such system
SE544032C2 (en) * 2019-08-14 2021-11-09 I & P I Norr Ab An adjustment system, and adjustable support, a method of orienting an element, and use of such system

Also Published As

Publication number Publication date
PL3194664T3 (pl) 2022-04-11
SE1451067A1 (sv) 2016-03-16
PT3194664T (pt) 2022-02-23
ES2906575T3 (es) 2022-04-19
EP3194664A1 (en) 2017-07-26
EP3194664A4 (en) 2018-06-06
CY1125407T1 (el) 2024-02-16
EP3194664B1 (en) 2021-12-08
HUE057789T2 (hu) 2022-06-28
SI3194664T1 (sl) 2022-07-29
DK3194664T3 (da) 2022-02-21
LT3194664T (lt) 2022-03-10
HRP20220221T1 (hr) 2022-05-27

Similar Documents

Publication Publication Date Title
CN104499658B (zh) 主动呼吸式防潮排汽倒置屋面系统及其施工方法
KR20100021605A (ko) 지붕 외관용 복합 패널 및 그 제조 방법
US20190345713A1 (en) Ventilated and draining foam insulation panel for building construction
KR101536975B1 (ko) 바닥 구조물 내부 배수 배관 장치 및 그 시공 방법
US20140166129A1 (en) Drainage system for use in basements and a method for its installation and use
CN103866927A (zh) 呼吸式屋面保温结构及其施工方法
EP3194664B1 (en) Method for forming a floor structure and method for forming a house foundation
RU2630829C2 (ru) Способ теплоизоляции здания
US20220002988A1 (en) A Building and a Method of Constructing A Building
CN201883549U (zh) 一种提高建筑地面蓄能隔热的混凝土结构
CN203947725U (zh) 地板支架
KR101275273B1 (ko) 지하수 배수장치
US20160002908A1 (en) Building and method for constructing such a building
CN103866862A (zh) 无地基悬架式多功能可卸装组合木屋
CN201865303U (zh) 用于提高民用建筑首层温度的地面保温系统
DK155890B (da) Byggeelement
KR101330561B1 (ko) 층간 바닥구조의 습·음 배출수단 및 이를 이용한 층간 바닥구조
KR101057315B1 (ko) 목재 기둥의 고정 구조
Johansson et al. Performance of insulation materials for historic buildings: Case studies comparing a super insulation material and hemp-lime
KR102038505B1 (ko) 구조물용 받침대 및 그 시공 방법
SG195429A1 (en) Precast planter
CN203878745U (zh) 无地基悬架式多功能可卸装组合木屋
CN209353585U (zh) 一种屋面临时整体排水构造
KR102452215B1 (ko) 레벨 조정장치를 이용하여 조립식 욕실을 시공하는 방법
FI126183B (fi) Menetelmä rakennuksen valesokkelirakenteen korjaamiseksi

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 15841882

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

REEP Request for entry into the european phase

Ref document number: 2015841882

Country of ref document: EP

WWE Wipo information: entry into national phase

Ref document number: 2015841882